|
---|
Category:CORRESPONDENCE-LETTERS
MONTHYEARML20217P3791999-10-21021 October 1999 Forwards NRC Form 396 & NRC Form 398 for Renewal of Licenses SOP-20607-1 & SOP-20610-1.Without Encls ML20217N2521999-10-20020 October 1999 Provides Supplemental Info Re 990405 Containment Insp Program Requests for Relief RR-L-1 & RR-L-2,in Response to 991013 Telcon with NRC ML20217K7541999-10-15015 October 1999 Forwards Rev 1 to Unit 1,Cycle 9 & Unit 2 Cycle 7 Colrs,Iaw Requirements of TS 5.6.5.Figure 5, Axial Flux Difference Limits as Function of Percent of Rated Thermal Power for RAOC, Was Revised for Both Units ML20217G6751999-10-13013 October 1999 Requests Withholding of Proprietary Info Contained in Application for Amend to OLs to Implement Relaxations Allowed by WCAP-14333-P-A,rev 1 ML20217G1071999-10-0707 October 1999 Informs That on 990930,NRC Staff Completed mid-cycle PPR of Vogtle & Did Not Identify Any Areas in Which Performance Warranted More than Core Insp Program.Nrc Plans to Conduct Core Insps at Facility Over Next Six Months ML20216J9041999-10-0101 October 1999 Forwards Response to RAI Re GL 96-05, Periodic Verification of Design-Basis Capability of Safety-Related Motor-Operated Valves ML20216J9161999-10-0101 October 1999 Forwards Response to NRC 990723 RAI Re GL 95-07, Pressure Locking & Thermal Binding of SR Power-Operated Gate Valves ML20217B0141999-10-0101 October 1999 Forwards Insp Repts 50-424/99-06 & 50-425/99-06 on 990725- 0904 at Vogtle Units 1 & 2 Reactor Facilities.Determined That One Violation Occurred & Being Treated as non-cited Violation ML20212E8751999-09-20020 September 1999 Forwards Response to NRC GL 99-02, Lab Testing of Nuclear Grade Activated Charcoal. Description of Methods Used to Comply with Std Along with Most Recent Test Results Encl ML20212E7481999-09-20020 September 1999 Requests Approval Per 10CFR50.55a to Use Alternative Method for Determining Qualified Life of Certain BOP Diaphragm Valves than That Specified in Code Case N-31.Proposed Alternative,Encl ML20212C2191999-09-16016 September 1999 Forwards NRC Form 536, Operator Licensing Exam Data, Which Is Current Need for NRC Operator Licensing Exams for Years 2000 Through 2003 of Plant Vogtle,Per Administrative Ltr 99-03 ML20211Q4801999-09-0101 September 1999 Informs That on 990812-13,Region II Hosted Training Managers Conference on Recent Changes to Operator Licensing Program. List of Attendees,Copy of Slide Presentations & List of Questions Received from Participants Encl ML20211J5291999-08-30030 August 1999 Forwards Snoc Copyright Notice Dtd 990825,re Production of Engineering Drawings Ref in VEGP UFSAR ML20211J5251999-08-30030 August 1999 Forwards Response to NRC 990727 RAI Re GL 96-06, Assurance of Equipment Operability & Containment Integrity During Design Basis Accident Conditions ML20211J7381999-08-27027 August 1999 Informs That Licensee Vessel Data Is Different than NRC Database Based on Listed Info,Per 990722 Request to Review Rvid ML20211E9251999-08-23023 August 1999 Forwards fitness-for-duty Performance Data for Jan-June 1999,as Required by 10CFR26.71(d).Data Reflected in Rept Covers Employees at Vogtle Electric Generating Plant ML20210V0881999-08-16016 August 1999 Forwards Insp Repts 50-424/99-05 & 50-425/99-05 on 990620- 0724.No Violations Noted.Vogtle Facility Generally Characterized by safety-conscious Operations,Sound Engineering & Maintenance Practices ML20210Q4611999-08-0505 August 1999 Informs That NRC Plans to Administer Generic Fundamentals Exam Section of Written Operator Licensing Exam on 991006 for Vogtle.Requests Info Re Individuals Who Will Take Exam. Sample Registration Ltr Encl ML20210L2181999-08-0202 August 1999 Forwards NRC Form 396 & Form 398 for Renewal of Listed Licenses,Iaw 10CFR55.57.Without Encl ML20210N1191999-08-0202 August 1999 Discusses 990727 Telcon Between Rs Baldwin & R Brown Re Administration of Licensing Exam at Facility During Wk of 991213 ML20210G3351999-07-27027 July 1999 Forwards Second Request for Addl Info Re GL 96-06, Assurance of Equipment Operability & Containment Integrity During Design Basis Accident Conditions ML20210E0121999-07-23023 July 1999 Forwards Second Request for Addl Info Re GL 95-07, Pressure Locking & Thermal Binding of Safety-Related Power-Operated Gate Valves ML20210D9341999-07-22022 July 1999 Discusses Closure of TACs MA0581 & MA0582,response to Requests for Info in GL 92-01,rev 1,suppl 1, Reactor Vessel Structural Integrity ML20210C8011999-07-21021 July 1999 Provides Response to NRC AL 99-02,which Requests That Addressees Submit Info Pertaining to Estimates of Number of Licensing Actions That Will Be Submitted for NRC Review for Upcoming Fy 2000 & 2001 ML20210E0431999-07-15015 July 1999 Forwards Insp Repts 50-424/99-04 & 50-425/99-04 on 990502- 0619.Two Violations of NRC Requirements Identified & Being Treated as non-cited Violations Consistent with App C of Enforcement Policy ML20209H3881999-07-14014 July 1999 Forwards Revs 1 & 2 to ISI Program Second 10-Year Interval Vogtle Electric Generating Plant Unit 1 & 2 ML20209C4041999-07-0101 July 1999 Forwards Rev 29 to VEGP Units 1 & 2 Emergency Plan.Rev 29 Incorporates Design Change Associated with Consolidation of Er Facilities Computer & Protues Computer.Justifications for Changes & Insertion Instructions Are Encl ML20196H8081999-06-28028 June 1999 Discusses 990528 Meeting Re Results of Periodic PPR for Period of Feb 1997 to Jan 1999.List of Attendees Encl ML20212J2521999-06-21021 June 1999 Responds to NRC RAI Re Yr 2000 Readiness at Nuclear Power Plants.Gl 98-01 Requested Response on Status of Facility Y2K Readiness by 990701 ML20196F9171999-06-21021 June 1999 Forwards Owner Rept for ISI for Vogtle Electric Generating Plant,Unit 1 Eighth Maint/Refueling Outage. Separate Submittal Will Not Be Made to NRC on SG Tubes Inspected During Subj Outage ML20195F8031999-06-11011 June 1999 Forwards Changes to VEGP Unit 1 Emergency Response Data Sys (ERDS) Data Point Library.Changes Were Completed on 990308 While Unit 1 Was SD for Refueling Outage ML20207E7421999-06-0303 June 1999 Refers to from NRC Which Issued Personnel Assignment Ltr to Inform of Lm Padovan Assignment as Project Manager for Farley Npp.Reissues Ltr with Effective Date Corrected to 990525 ML20207F6201999-06-0202 June 1999 Sixth Partial Response to FOIA Request for Documents.Records in App J Encl & Will Be Available in Pdr.App K Records Withheld in Part (Ref FOIA Exemptions 7) & App L Records Completely Withheld (Ref FOIA Exemption 7) ML20207D9861999-05-28028 May 1999 Informs That,Effective 990325,LM Padovan Was Assigned as Project Manager for Plant,Units 1 & 2 ML20207D2701999-05-19019 May 1999 Forwards Insp Repts 50-424/99-03 & 50-425/99-03 on 990321- 0501.One Violation of NRC Requirements Identified & Being Treated as non-cited Violation Consistent with App C of Enforcement Policy ML20206M5141999-05-11011 May 1999 Informs That NRC Ofc of Nuclear Regulation Reorganized Effective 990328.As Part of Reorganization,Div of Licensing Project Mgt Created.Rl Emch Section Chief for Vogtle. Reorganization Chart Encl ML20206U4061999-05-11011 May 1999 Confirms Telcon with J Bailey Re Mgt Meeting Scheduled for 990528 to Discuss Results of Periodic Plant Performance Review for Plan Nuclear Facility Fo Period of Feb 1997 - Jan 1999 05000424/LER-1998-006, Forwards LER 98-006-03 Re Motor Control Ctr Breaker Buckets Not Being Seismically Qualified.Rev Is Submitted to Document Results of Seismic Testing That Demonstrated That No Condition Outside Design Basis of TS Requirements Exi1999-05-10010 May 1999 Forwards LER 98-006-03 Re Motor Control Ctr Breaker Buckets Not Being Seismically Qualified.Rev Is Submitted to Document Results of Seismic Testing That Demonstrated That No Condition Outside Design Basis of TS Requirements Existed ML20206D6411999-04-29029 April 1999 Forwards Vogtle Electric Generating Plant Radiological Environ Operating Rept for 1998 & Vogtle Electric Generating Plant Units 1 & 2 1998 Annual Rept Annual Radioactive Effluent Release Rept ML20206D5881999-04-29029 April 1999 Forwards Rept Which Summarizes Effects of Changes & Errors in ECCS Evaluation Models on PCT for 1998,per Requirements of 10CFR50.46(a)(3)(ii).Rept Results Will Be Incorporated Into Next FSAR Update ML20206D6951999-04-28028 April 1999 Provides Update of Plans for VEGP MOV Periodic Verification Program Re GL 96-05, Periodic Verification of Design-Basis Capability of Safety-Related Movs ML20206C2241999-04-21021 April 1999 Forwards Revised Monthly Operating Repts for Mar 1999 for Vogtle Electric Generating Plant,Units 1 & 2.Page E2-2 Was Iandvertently Omitted from Previously Submitted Rept on 990413 ML20206A6371999-04-21021 April 1999 Forwards SE Authorizing Licensee Re Rev 9 to First 10-yr ISI Interval Program Plan & Associated Requests for Relief (RR) 65 from ASME Boiler & Pressure Vessel Code ML20205Q3351999-04-15015 April 1999 Forwards Insp Repts 50-424/99-02 & 50-425/99-02 on 990214-0320.Three Violations Identified & Being Treated as Non-Cited Violations ML20205T2351999-04-0909 April 1999 Informs That on 990317,B Brown & Ho Christensen Confirmed Initial Operator Licensing Exam Scheduled for Y2K.Initial Exam Date Scheduled for Wk of 991213 for Approx 10 Candidates ML20205K7501999-04-0505 April 1999 Informs That Effective 990329,NRC Project Mgt Responsibility for Plant Has Been Transferred from Dh Jaffe to R Assa ML20209A3741999-04-0505 April 1999 Submits Several Requests for Relief for Plant from Code Requirements Pursuant to 10CFR50.55a(a)(3) & (g)(5)(iii).NRC Is Respectfully Requested to Approve Requests Prior to Jan 1,2000 ML20205H3481999-03-31031 March 1999 Forwards Georgia Power Co,Oglethorpe Power Corp,Municipal Electric Authority of Ga & City of Dalton,Ga Status of Decommissioning Funding for Each Reactor or Part of Reactor Owned for OLs NPF-68 & NPF-81 ML20205F9091999-03-29029 March 1999 Submits Rept of Number of SG Tubes Plugged During Plant Eighth Maintenance/Refueling Outage (1R8).Inservice Insps Were Completed on SGs 1 & 4 on 990315.No Tubes Were Plugged ML20205G0761999-03-26026 March 1999 Provides Results of Individual Monitoring for 1998.Encl Media Contains All Info Required by Form NRC 5.Without Encl 1999-09-20
[Table view] Category:INCOMING CORRESPONDENCE
MONTHYEARML20217P3791999-10-21021 October 1999 Forwards NRC Form 396 & NRC Form 398 for Renewal of Licenses SOP-20607-1 & SOP-20610-1.Without Encls ML20217N2521999-10-20020 October 1999 Provides Supplemental Info Re 990405 Containment Insp Program Requests for Relief RR-L-1 & RR-L-2,in Response to 991013 Telcon with NRC ML20217K7541999-10-15015 October 1999 Forwards Rev 1 to Unit 1,Cycle 9 & Unit 2 Cycle 7 Colrs,Iaw Requirements of TS 5.6.5.Figure 5, Axial Flux Difference Limits as Function of Percent of Rated Thermal Power for RAOC, Was Revised for Both Units ML20217G6751999-10-13013 October 1999 Requests Withholding of Proprietary Info Contained in Application for Amend to OLs to Implement Relaxations Allowed by WCAP-14333-P-A,rev 1 ML20216J9161999-10-0101 October 1999 Forwards Response to NRC 990723 RAI Re GL 95-07, Pressure Locking & Thermal Binding of SR Power-Operated Gate Valves ML20216J9041999-10-0101 October 1999 Forwards Response to RAI Re GL 96-05, Periodic Verification of Design-Basis Capability of Safety-Related Motor-Operated Valves ML20212E7481999-09-20020 September 1999 Requests Approval Per 10CFR50.55a to Use Alternative Method for Determining Qualified Life of Certain BOP Diaphragm Valves than That Specified in Code Case N-31.Proposed Alternative,Encl ML20212E8751999-09-20020 September 1999 Forwards Response to NRC GL 99-02, Lab Testing of Nuclear Grade Activated Charcoal. Description of Methods Used to Comply with Std Along with Most Recent Test Results Encl ML20212C2191999-09-16016 September 1999 Forwards NRC Form 536, Operator Licensing Exam Data, Which Is Current Need for NRC Operator Licensing Exams for Years 2000 Through 2003 of Plant Vogtle,Per Administrative Ltr 99-03 ML20211J5291999-08-30030 August 1999 Forwards Snoc Copyright Notice Dtd 990825,re Production of Engineering Drawings Ref in VEGP UFSAR ML20211J5251999-08-30030 August 1999 Forwards Response to NRC 990727 RAI Re GL 96-06, Assurance of Equipment Operability & Containment Integrity During Design Basis Accident Conditions ML20211J7381999-08-27027 August 1999 Informs That Licensee Vessel Data Is Different than NRC Database Based on Listed Info,Per 990722 Request to Review Rvid ML20211E9251999-08-23023 August 1999 Forwards fitness-for-duty Performance Data for Jan-June 1999,as Required by 10CFR26.71(d).Data Reflected in Rept Covers Employees at Vogtle Electric Generating Plant ML20210L2181999-08-0202 August 1999 Forwards NRC Form 396 & Form 398 for Renewal of Listed Licenses,Iaw 10CFR55.57.Without Encl ML20210C8011999-07-21021 July 1999 Provides Response to NRC AL 99-02,which Requests That Addressees Submit Info Pertaining to Estimates of Number of Licensing Actions That Will Be Submitted for NRC Review for Upcoming Fy 2000 & 2001 ML20209H3881999-07-14014 July 1999 Forwards Revs 1 & 2 to ISI Program Second 10-Year Interval Vogtle Electric Generating Plant Unit 1 & 2 ML20209C4041999-07-0101 July 1999 Forwards Rev 29 to VEGP Units 1 & 2 Emergency Plan.Rev 29 Incorporates Design Change Associated with Consolidation of Er Facilities Computer & Protues Computer.Justifications for Changes & Insertion Instructions Are Encl ML20196F9171999-06-21021 June 1999 Forwards Owner Rept for ISI for Vogtle Electric Generating Plant,Unit 1 Eighth Maint/Refueling Outage. Separate Submittal Will Not Be Made to NRC on SG Tubes Inspected During Subj Outage ML20212J2521999-06-21021 June 1999 Responds to NRC RAI Re Yr 2000 Readiness at Nuclear Power Plants.Gl 98-01 Requested Response on Status of Facility Y2K Readiness by 990701 ML20195F8031999-06-11011 June 1999 Forwards Changes to VEGP Unit 1 Emergency Response Data Sys (ERDS) Data Point Library.Changes Were Completed on 990308 While Unit 1 Was SD for Refueling Outage 05000424/LER-1998-006, Forwards LER 98-006-03 Re Motor Control Ctr Breaker Buckets Not Being Seismically Qualified.Rev Is Submitted to Document Results of Seismic Testing That Demonstrated That No Condition Outside Design Basis of TS Requirements Exi1999-05-10010 May 1999 Forwards LER 98-006-03 Re Motor Control Ctr Breaker Buckets Not Being Seismically Qualified.Rev Is Submitted to Document Results of Seismic Testing That Demonstrated That No Condition Outside Design Basis of TS Requirements Existed ML20206D5881999-04-29029 April 1999 Forwards Rept Which Summarizes Effects of Changes & Errors in ECCS Evaluation Models on PCT for 1998,per Requirements of 10CFR50.46(a)(3)(ii).Rept Results Will Be Incorporated Into Next FSAR Update ML20206D6411999-04-29029 April 1999 Forwards Vogtle Electric Generating Plant Radiological Environ Operating Rept for 1998 & Vogtle Electric Generating Plant Units 1 & 2 1998 Annual Rept Annual Radioactive Effluent Release Rept ML20206D6951999-04-28028 April 1999 Provides Update of Plans for VEGP MOV Periodic Verification Program Re GL 96-05, Periodic Verification of Design-Basis Capability of Safety-Related Movs ML20206C2241999-04-21021 April 1999 Forwards Revised Monthly Operating Repts for Mar 1999 for Vogtle Electric Generating Plant,Units 1 & 2.Page E2-2 Was Iandvertently Omitted from Previously Submitted Rept on 990413 ML20209A3741999-04-0505 April 1999 Submits Several Requests for Relief for Plant from Code Requirements Pursuant to 10CFR50.55a(a)(3) & (g)(5)(iii).NRC Is Respectfully Requested to Approve Requests Prior to Jan 1,2000 ML20205H3481999-03-31031 March 1999 Forwards Georgia Power Co,Oglethorpe Power Corp,Municipal Electric Authority of Ga & City of Dalton,Ga Status of Decommissioning Funding for Each Reactor or Part of Reactor Owned for OLs NPF-68 & NPF-81 ML20205F9091999-03-29029 March 1999 Submits Rept of Number of SG Tubes Plugged During Plant Eighth Maintenance/Refueling Outage (1R8).Inservice Insps Were Completed on SGs 1 & 4 on 990315.No Tubes Were Plugged ML20205G0761999-03-26026 March 1999 Provides Results of Individual Monitoring for 1998.Encl Media Contains All Info Required by Form NRC 5.Without Encl ML20205H4051999-03-25025 March 1999 Forwards Info on Status of Decommissioning Funding for Each Reactor or Part of Reactor Owned for OLs NPF-68 & NPF-81,as Requested IAW 10CFR50.75(f)(1) ML20205H3891999-03-25025 March 1999 Forwards Info on Status of Decommissioning Funding for Each Reactor or Part of Reactor Owned for OLs NPF-68 & NPF-81,as Requested IAW 10CFR50.75(f)(1).Page 2 in Third Amend Power Sales Contract of Incoming Submittal Not Included ML20205A9441999-03-25025 March 1999 Forwards VEGP Unit 1 Cycle 9 Colr,Per TS 5.6.5.d ML20205H3811999-03-24024 March 1999 Forwards Info on Status of Decommissioning Funding for Each Reactor or Part of Reactor Owned for OLs NPF-68 & NPF-81,as Requested IAW 10CFR50.75(f)(1) ML20205H3621999-03-22022 March 1999 Forwards Info on Status of Decommissioning Funding for Each Reactor or Part of Reactor Owned for OLs NPF-68 & NPF-81, as Requested IAW 10CFR50.75(f)(1) ML20204G4361999-03-18018 March 1999 Forwards Summary Rept of Present Level & Source of on-site Property Damage Insurance Coverage for Vegp,Iaw Requirements of 10CFR50.54(w)(3) ML20204C0591999-03-17017 March 1999 Forwards Rev 0 to WCAP-15160, Evaluation of Pressurized Thermal Shock for Vegp,Unit 2 & Rev 0 to WCAP-15159, Analysis of Capsule X from Vegp,Unit 2 Reactor Vessel Radiation Surveillance Program ML20207K9551999-03-11011 March 1999 Forwards Response to Rai,Pertaining to Positive Alcohol Test of Licensed Operator.Encl Info Provided for NRC Use in Evaluation of Fitness for Duty Occurrence.Encl Withheld,Per 10CFR2.790(a)(6) ML20207L9721999-03-10010 March 1999 Forwards Rev 15 to EPIP 91104-C of Manual Set 6 of Vogtle Epips.Without Encl ML20207B0191999-02-25025 February 1999 Forwards Fitness for Duty Performance Data for six-month Reporting Period 980701-1231,IAW 10CFR26.71(d) 05000424/LER-1998-009, Forwards LER 98-009-00 Re Event in Which Improper Testing Method Resulted in Inadequate Surveillances on 9812291999-01-27027 January 1999 Forwards LER 98-009-00 Re Event in Which Improper Testing Method Resulted in Inadequate Surveillances on 981229 ML20199F7701999-01-13013 January 1999 Submits Revised Response to RAI Re Licensee 980713 Proposed Amend to Ts,Eliminating Periodic Response Time Testing Requirements on Selected Sensors & Protection Channels. Corrected Copy of Table,Encl ML20199F7981999-01-13013 January 1999 Forwards Corrected Pages to VEGP-2 ISI Summary Rept for Spring 1998 Maint/Refueling Outage. Change Bar in Margin of Affected Pages Denotes Changes to Rept ML20199G1381999-01-13013 January 1999 Forwards Copy of Permit Renewal Application Package for NPDES Permit Number GA0026786,per Section 3.2 of VP Environ Protection Plan 05000424/LER-1998-007, Forwards LER 98-007-00,re Inadequate Surveillances Due to Improperly Performed Response Time Testing,On 981215,IAW 10CFR50.731999-01-13013 January 1999 Forwards LER 98-007-00,re Inadequate Surveillances Due to Improperly Performed Response Time Testing,On 981215,IAW 10CFR50.73 ML20198F6131998-12-18018 December 1998 Forwards Revised Certification of Medical Exam Form for License SOP-21147.Licensee Being Treated for Hypertension. Util Requests That Individual License Be Amended to Reflect Change in Status ML20198L6631998-12-18018 December 1998 Forwards Amend 37 to Physical Security & Contingency Plan. Encl 1 Provides Description & Justification for Changes & Encl 2 Contains Actual Amend 37 Pages.Amend Withheld,Per 10CFR73.21 ML20198D9291998-12-16016 December 1998 Forwards Requested Info Re Request to Revise TSs Elimination of Periodic Pressure Sensor Response Time Tests & Elimination of Periodic Protection Channel Response Time Tests ML20198D9991998-12-16016 December 1998 Forwards Responses to 980916 RAI Re Response to GL 97-01, Degradation of Control Rod Drive Mechanism Nozzle & Other Vessel Closure Head Penetrations ML20198D8171998-12-14014 December 1998 Forwards NRC Form 396 & Form 398 for Renewal of License OP-20993.Without Encls ML20206N3051998-12-0808 December 1998 Submits RAI Re Replacement of Nuclear Instrument Sys Source & Intermediate Range Channels & post-accident Neutron Flux Monitoring Sys 1999-09-20
[Table view] Category:LEGAL/LAW FIRM TO NRC
MONTHYEARML20044A7461990-06-25025 June 1990 Forwards Endorsement 35 to Nelia Policy NF-302 & Endorsement 29 to Maelu Policy MF-129 ML20064B4911990-05-31031 May 1990 Forwards 900507 Court Order Instructing Parties to Provide Info to Wage & Hour Administrator Re M Hobby Claims Against Util Under ERA ML20006A6241990-01-16016 January 1990 Forwards Draft Qualified Master Trust Agreement for Decommissioning of Nuclear Plants,For Review.Licensee Will Make Contributions to Qualified & Nonqualified Trust as Appropriate ML20244D9001989-04-0606 April 1989 Forwards Endorsements 94 & 18 to Maelu Policies MF-78 & MF-129,respectively & Endorsements 112 & 24 to Nelia Policies NF-215 & NF-302,respectively ML20244D9131989-04-0505 April 1989 Forwards Endorsements 1 to Nelia Certificate N-117 & Maelu Certificate M-117 ML20247A3021989-03-21021 March 1989 Discusses 890302 Notice of Finding of No Significant Antitrust Changes Re OL for Unit.Oglethorpe Power Corp 890317 Comments Do Not Affect NRC Ability to Recommend & Commission Ability to Issue Full Power License on 890330 ML20247H3981989-03-21021 March 1989 Forwards 890228,0308 & 15 Ltrs on No Significant Change Finding Re Antitrust OL Review ML20245H7831989-02-28028 February 1989 Discusses Transaction Between Oglethorpe Power Corp & Seminole Power Cooperative,Per Antitrust Review.Antitrust Review Reflects Assertions That Are Factually Incorrect & Should Reflect Addl Facts Available ML20151Z5491988-08-23023 August 1988 Forwards Supplemental Reg Guide 9.3 Info in Response to Mathews to Wg Hairston ML20150E4781988-07-0505 July 1988 Forwards Endorsement 14 to Maelu Policy MF-129 & Endorsement 20 to Nelia Policy NF-302 ML20148H0821988-01-12012 January 1988 Forwards Endorsements 105 & 16 to Nelia Policies NF-215 & NF-302 & Endorsements 87 & 10 to Maelu Policies MF-78 & MF-129 ML20206R9481987-04-10010 April 1987 Forwards Endorsements 15 & 9 to Nelia Policy NF-302 & Maelu Policy MF-129,respectively ML20204F4841987-02-26026 February 1987 Forwards Endorsement 8 to Maelu Policy MF-129 & Endorsements 10,11,12,13 to Nelia Policy NF-302 ML20207T6041987-02-26026 February 1987 Forwards Dept of Labor 870218 Final Decision Dismissing Case 86-ERA-9 Re JW Durham Vs Util & Butler Svc Group,Per Cw Whitney Request.W/Certificate of Svc ML20210S5371987-02-0202 February 1987 Forwards Endorsement 1 to Nelia Policy N-111 & Maelu Policy M-111 ML20211J8201986-10-14014 October 1986 Forwards Endorsement 8 to Nelia Policy NF-302 ML20214Q1441986-09-18018 September 1986 Discusses ASLB 860827 Partial Initial Decision Re Several Contentions,Incuding Contention 10.1 Addressing dose-rate Effects & Applicant Submittal of Addl Info on Subj.Addl Info Should Not Change ASLB Conclusions.Svc List Encl ML20206S2701986-09-17017 September 1986 Notifies of Address Change Effective on 860927.Requests Address on Encl List of Dockets Be Changed ML20214L6021986-09-0505 September 1986 Forwards Kp Twine Supplemental Affidavit on Contention EP-5 Re Rev to Savannah River Plant Plan,Incorporating Info on Reception Ctrs.Inclusion of Reception Ctr Info in Emergency Plans Resolve ASLB Concern ML20212Q8141986-09-0303 September 1986 Forwards Applicant 860821 & 0902 Ltrs to NRC Re Board Notification 86-018,for Info.W/Svc List.Related Correspondence ML20212N0631986-08-26026 August 1986 Discusses Plant Conformance to NUREG-0654,App 3 Re Emergency Broadcast Sys,Per Board 860812 Order.Related Correspondence ML20212H4171986-08-11011 August 1986 Forwards 860430 Scheduling Svcs Agreement Between Georgia Power Co & Oglethorpe Power Corp.Partially Deleted Interconnection Agreement Between Alabama Electric Cooperative,Inc & Ogelthorpe Power Corp Also Encl ML20204K0691986-08-0404 August 1986 Informs That Listed Info on Burke County Reception Ctr Capacity Will Be Added to Emergency Plan,Per Board 860717 Memorandum & Order.Info Should Enable NRC & FEMA to Complete Verification of Plan.W/Svc List ML20202G1691986-07-10010 July 1986 Forwards Correspondence Re Application for 10CFR70 License for Possession & Storage of Unirradiated Reactor Fuel & Associated Snm.W/Svc List.Related Correspondence ML20206P7131986-06-30030 June 1986 Forwards Revised Pages to Offsite Plans Re Emergency Public Info Program for Transients (EP-2/EP-2 (H)),Per Board 860505 Memorandum & Order.W/Svc List.Related Correspondence ML20206J7821986-06-23023 June 1986 Forwards Updated Page Changes for Burke County & State of Ga Emergency Plans for Facility Plume Pathway Emergency Planning Zone.Encl Plan Changes Composite of Feb & Apr 1986 Changes.Svc List Encl.Related Correspondence ML20206D8211986-06-16016 June 1986 Responds to Re 860310 Motion for Summary Disposition of Contention EP-5.Applicants Did Not Address Savannah River Plant Plan Because Reception Ctrs Not Related to Issue Raised.Kp Twine Affidavit Encl.W/Svc List ML20206D7041986-06-16016 June 1986 Forwards Revised Burke County Plan Pages Re EP-4 & EP-1/EP-1(a)/EP-2(b).In Accordance w/860513 Ltr to Board, Revised Plan Pages Re EP-2/EP-2(h) on Public Info for Transients Will Be Provided on or Before 860701.W/svc List ML20209E7401986-06-12012 June 1986 Forwards Certified Declarations Page for Endorsements 1 Through 6 to Nelia Policy NF-302,dtd 860605 ML20155K0021986-05-20020 May 1986 Requests That Specific Revised Sections of Burke County Emergency Plan Which Accurately Identify Backup Means of Notification & Line of Succession of Emp Be Provided to NRC & FEMA by 860701.Svc List Encl ML20197G7181986-05-13013 May 1986 Discusses Steps Taken to Comply W/Aslb 860429 & 0505 Orders Re Offsite Emergency Planning.Changes Will Be Reflected in Full Plan Revs Scheduled for Fall 1986 ML20203D6621986-04-17017 April 1986 Informs of Review of Staff Response to Applicant Motion for Summary Disposition of Joint Intervenors Contention EP-2/EP-2(h) & Affidavit of Cl Stovall.State & Local Emergency Plans Will Be Revised.Related Correspondence ML20203A0071986-04-14014 April 1986 Forwards Proposed Findings of Fact & Conclusions of Law on Technical & Environ Contentions.Certificate of Svc & Svc List Encl ML20138C1491986-03-28028 March 1986 Forwards Revised Emergency Public Info/Education Matls for State of Ga Portion of Plume Exposure Pathway Emergency Planning Zone.Info Revised to Include Use of Fixed Sirens. Svc List Encl.Related Correspondence ML20137Z5791986-03-11011 March 1986 Requests That Gf Trowbridge Be Replaced as Addressee for NRC Correspondence in Accordance W/Listed Client Facility & Designated Addressee ML20203C2321986-03-0505 March 1986 Appeals Lack of Response to FOIA Request for Documents Re NRC Investigation Into Complaints of Register,L Price & JB Register Concerning Illegal & Improper Procedures & Practices at Facility ML20154B8611986-02-28028 February 1986 Forwards Draft Bechtel Rept, Groundwater Numerical Modeling, Dtd Feb 1986.Svc List Encl.Related Correspondence ML20154C4641986-02-27027 February 1986 Forwards Page 13 of Asco Catalog NP-1,omitted from Exhibit F to Applicants 860224 Testimony of Gt Baenteli,G Bockhold, Sj Cereghino,Wv Cesarski & Hj Quasny on Contention 10.5 Re Solenoid Valves.Related Correspondence ML20205J7171986-02-24024 February 1986 Forwards Applicant Testimony on Contentions 7 & 10.1 Re Groundwater,Per ASLB 860114 & 23 Scheduling Order & Suppl,Respectively.Testimony of Contention 10.5 Filed Under Separate Cover.W/Certificate of Svc.Related Correspondence ML20205K3911986-02-24024 February 1986 Forwards Updated Reg Guide 9.3 Info for Antitrust Review of Facility,Per Jl Funches 861218 Request ML20153E0761986-02-18018 February 1986 Identifies Witnesses Scheduled to Testify on Applicant Behalf Re Contentions 7,10.1 & 10.5 Per ASLB 860114 & 23 Scheduling Order & Supplemental Scheduling Order, Respectively.Svc List Encl.Related Correspondence ML20147C4651986-02-14014 February 1986 FOIA Request for All Documents Re Mcnally,B Weatherford, J Register,St Register & L Price ML20151W8721986-02-10010 February 1986 Forwards Vogtle Energy Generating Plant Groundwater Monitoring Program Jul-Dec 1985 & Results of Hydrogeologic Testing Power Block Area Vogtle Electric Generating Plant.... W/Svc List.Related Correspondence ML20151U7241986-02-0505 February 1986 Forwards site-specific Emergency Response Plans,In Response to 850812 & 1001 Memorandum & Orders Re Ruling on Proposed Contentions on Emergency Planning & Ruling on 850905 Reconsideration Motion.Svc List Encl.Related Correspondence ML20199E3961986-01-15015 January 1986 FOIA Request for Documents Re Allegations,Findings & Orders That Pullman Power Products Employees Intimidated & Harassed QC Inspectors at Nuclear Facilities ML20138P6151985-12-17017 December 1985 Advises That Applicants in Accord w/851212 Ltr Stating Proceeding Expected to Commence in Mar 1986.Emergency Planning Issues Remaining After Summary Disposition Will Be Ready for Mar Hearing.Related Correspondence ML20133K9991985-10-18018 October 1985 Forwards Emergency Planning Zone Map.W/O Map.Svc List Encl. Related Correspondence ML20133F1131985-10-0404 October 1985 Forwards Emergency Public Info/Educ Matls for Plume Exposure Pathway Emergency Planning Zone.Challenges to Adequacy of Matls Should Be Submitted by Joint Intervenors within 30 Days.Svc List Encl.Related Correspondence ML20210K5041985-10-0303 October 1985 Forwards for Review,Petition & Supporting Brief Re Dept of Labor Case 85-ERA-27 (Mcnally,Et Al Vs Georgia Power Co), Per C Whitney Request.W/O Encl ML20210K5111985-10-0303 October 1985 Forwards for Review,Petition & Supporting Brief Re Dept of Labor Case 85-ERA-27 (Mcnally,Et Al Vs Georgia Power Co), Per C Whitney Request.W/O Encl 1990-06-25
[Table view] |
Text
- .
JOHN R. MYER ir is MEALD S U I LDI N G TH O M AS A. BOWMAN sv rens m s .. N.w.
ATL.ANTA. GEC RGIA 3C3C 3 4o4,sazasa4 arronNns AT L&W August 2, 1979 Mr. Harold R. Denton Director, Of fice of Nuclear Reactor Regulation United States Nuclear Regulatory Commission Phillips Building Room T 202A Washington, D. C. 20555 Re: Docket Nos. 50-424 & 50-425
Dear Mr. Denton:
In connection with the current Georgia Power Company (GPC) application for a rate increase, additional information centinues to become available that is rele vant to the Nuclear Regulatory Commission (NRC) consideration of whether to re-voke the construction permit for Vogtle 1 and 2. GPC has provided a more recent projection of the capacity of the GPC system. The projection indicates somewhat greater capacity than the GPC December, 19 78 submission to the NRC. A copy of this projection is attached as Exhibit "1."
I have enclosed a copy of the recent testimony of Dr. Keewhan Choi as Exhibit "2." Dr. Choi was hired by the Georgia Public Service Commission to evaluate the method of the GPC to fore-case peak demand. Historically, Dr. Choi's forecast of future energy needs has been c loser to the mark than the Company's.
Dr. Choi estimates the growth of the annual peak demand for the next fourteen years to be approximately 3.7%. In contrast, the projection submitted to the NRC shows an average annual growth of 4.6%. By the mid-1980's, the difference in the GPC forecast and Dr. Choi's forecast is greater than the entire capacity of the two Vogtle plan'-3. For example, t- ~'C forecast of peak demand for 19 84 exceeds Dr. Choi's fore ast by 2208 MW, and the increase widens thereafter. More significantly, by Dr. Choi's fo re cas t , the Company will have a 1989 peak demand of 14,208 MN.
If the Company continues its constructicn program as planned in Exhibit "1" attached hereto , bat does not construct Vogtle 1& 2, i t w ill h ave re se rve s o f 18 ,62 7 "N o r more th an 30% reserve capacity without Vogtle. If GPC does not sell a share of Sche rer plants this reserve capacity will be even greater. Th)s 522 3n5 c'
@Qg' a 7 9080 . ,
7D o n
e .
Mr. Haroid R. Denton Page Two August 2, 1979 calculation does not include a'lowance for conservation or alternative energy systems as oatlined in the GAFE Petition of May 1, 1979.
The Company appare: ;1y recogni.zes this over-abundaI ce of generating capacity which will result from construe: tion of Vogtle. Recently disclosed letters indicate that in May, 1978, GPC sought to further reduce its share of Vogtle through sales to companies ir North Carolina, South Carolina, Kentucky and Florida. Obvi asly, GPC does not believe it need; the full output of "egtle for its customers. Copies of these letters are also attached hereto as Exhibit "3." Moreover, R. W.
Scherer, Pre sident o f the Comp any , recently testified that in 1976, Georgia Power sought to sell 90' of the output of the Vugtle plants. A transcript of this part of Mr. Scherer's testimony is not yet available.
I urge the NRC to reconsider its Apt .1 13, 1979 analysis of the GPC need for power based on the - re recent data supplied by GANE. The NRC staf f should recompute its April 13 analysis in light of Dr. Choi's forecast of peak demand and the more recent projections of capacity of the system. I believe that the conclusien of such a study will demonstrate that both Vogtle 1 or 2 are unnecessary to supply the GPC service area with adequate electricity.
Very truly yours ,
Gary Flack, Attorney for GANE GF/1 Encls.
522 306
N. 00lfi h NWCI b JULY i4 lvid GEORLIA P0wtH COMPAtay PAGE - 1 T U G.P C_3 0 ,
_ _ _ . . _ _ - _ . _ _ _ . . - N T_ _ D A fl_ CA$Cy_Y H .; HW_ l_ O A D HW $ 5'Eilil n'~1Sih d_ _
f@.0gCTED
~ ~ ~
~
_ _ _ _ INJTI Q Lt4EliI G0t4 _ Q N [777 Q{T 6,'i
~~ ~" ~ ~ ' ~ ~ ~
m Ar.k l y 2 s to FC 5/f8 870d SAVANNAH A D JU $1 Ht t4 T 6/[8 -2).0 - _.
5 t +> A tiYDHU ADJU5{MLNT _ _ . _ _ . 6/78 -23 7 _ ._
5t PA PHtttHLt4CE_ADJUSTHENT 6/18 23,7
-T_-[~C_
~ -- ~
10fAL _b/3J/iH_ _ _, 134h.f l{}2t l.0 _ 3214'.5 31748 1 ___
~ ~
~~~ t t A G Op i 10t4 m A r4 5 L I Y 'l"0 N 6- ) 0'278 7/78 44.4 __ _ . _
' ~ Ht A G OP i10tJ = At4SL t V 1 Ote 6-30-78 - T/78 -44.4 '
~-tt A l t h / (67 f40CLEAH - - ---~M 1/19 761.0 ~
~ 6/F9
~- L AV Ar.N All' ADJusIMtte r 49.0
. IVA IfJlt hCH ANGt A DJUS T ML'f4 T' .g 6/19~ l'.' 0
_ M L L6 PU9 CHASE ADJUSIMEt4T h 6/F9 -75.0
-26.4 SLPA HYl>HO ADJtsS tHir4I ~~
6/19 StPA Pht F t Htf4CL ADJUSIMENT ' ' ~ ~ ~ ~ 6/79 26.9
~' - - -
~ ~
TOiAL- ~ ~6/30/79 11167.S 11~0 2 3. 0 3144.5 28.53 Pt AK itiG 50 Mw COHH I Ud ti "' ~ ' ~ ~ 5/80 $0.0 wAtLAct DAM l-6 HYDHO 7 *5/80 325.0 iVA INil HCH Af 4GL ADJUSTMEt4T ' ~. 6/80 -43.0 StPA PHEttktNCL ADJUSIMEtif e. a 6/80 30.8 SEPA HYDHO A D JU S I M E to i 6/80 -30.8 y"w;a
- ~~ ~
i)695.0
~ ~
._ _IOIAI__._ M}9#90 ~ - ] _ ~~ ~ ~ ' - ~~l M99.5 2804.5 ~ 23.98
~ - ~~~ ~
IVA ItJItHCHAN6L ADJu$iHENT~ ~ ~~ ~ ~6/81 -43.0 6/ til
~ ~ ~~
~~~StPA tisDHO Al) Jus t et tei -35.5 St P A PHEfthtNCt ~AOJUSTHEhT 6'/81 ~3 5 . 5 101AL 6/.30/01 14456.5 1228270' ~2174.5 17.~ 71-~ ~ ~ ~
SCutHtH I 800 FC 2/02 808.0
~~ ~ Ann.Hlotti IL< HLTIHL ~ " - - - ~ ~ ~ - ~ ~ - ~ ~ ~ ~ - ~ - 6/82 - -76.0 IVA It4ILHCH5NGt ' ADJu$THf t T 6/82 -1.0 SEPA iM OH O Al> JUS T Ht NI
.. _ SEPA PHtFLkttCt A DJUS I M E idI, Q 6/02 -41.4 m 6/82 41.4
. . , , ____ C.__ ~
,g 15185.5 12817.0 2368.5 18.48 --~7
- ..u .m _ e -. -.- m me .=_.e..- -*
_ . _ _ _ --.____.___e__._ _ _____ _ _ _ _ _ _ . _ _ _ _ _ .______-w ,
. . _ Ex/g 6 f f _ -. ___
m __
,, .,, .ies.we..e e ow n s- **
.em.e
.ufj',!;il'OWCf RS
__ . JuLLC ? i91H GE0Hb}A POWER _ COMPANY PAGE *- 2
._SYST{M.E WANS80t! PLAT { ___
78GPCJO ~
197u - 1990 _
~
5_ - --- _ Uhl[ _._ 0 d E. CAPAyl{ tid Hy LOAD _ H[NESEHVE % AfSEHVE__ _
PH0JLCHD
~~
~ TGIAL' '6/30/02
~
1518'5 3 128I7.0 2368h 18 18..
~ r4055t LL 'O Alf SE P A~t t Y D H O ___ _ _ _ . _6/d3 150 i) _I
~
g --_. . I O I A L 6/10/81 15135.5 13335.0 2000.5 15.00 (O C'et HL H 2 t10 0 FC 2/84 808.0 e - H O . n Y HautJ111td 4-3 PoHP . . _ _ .STOH 4 / ti 4 675.0 W AN A'lotti 3L, kiilHE 6/04 -09.0 f i 'itit l L I L 2 A t. I I HL" 6/64 -46.0 Ib
, TOTAL 6/10/84 16683.6 14058.0 2625.6 18.68 V06 I t. F i 1150' t4tlCLt AR-~ ~ ~ ~ ~ ' ~ ~ ~ ~ lI/84 1150.0 ,
j ~/ 8 5
[~.NsSEtt'OAM'5LPA~NS 15 -~O SChlHLR 3 703 FCS ___ __ __ _ __ _ _ , 2 / 8 5, _76310 __ _________
p" t""
to At--6/30/as 1 ___ _ _ 7 _____ _.
19 66.6 p 7 7?_. 6 398 q __27;co .
~ ~ - ti Akil t T IS f f hHV NYOHO- ' ^ - ~ ~ ~ ' ADDITION 4/06 100.0 A18 i rno's l'9tiIHL -50.d
~
6/86
~' - - - ~ ~
T O T I. t_ , .of30/86 ~ ~ ~ ~ _
18u16.6~- - 15427(6 3389-6 2?.97- - ~ ~
~ S C HF s.t .2 6 7 6.1 t C 5 2/87 f f> 3. 0 Alt irasari 2 HtIIHL 6/87 -58.0 0
~
['_TVA ~ I N TLHUtt AN6( 'kojuS THE NT _ 6/87_. __
~~ ~~ ~ ' ~ ~ ~ ~ ~ ~ ~
TOTAL 6.' _4 0 / u_7 - ~19540 '6 B056.0 3484'.6 21.70
~ ~ ~ ~ ~ VOSTLE 2 115 0 NtsCL L.iR'- ~' 't)/87. __)l 5M C' _. ___].
~~~E - To r Ai:- 0 3 6 ?8 0 _ __ __. _ _ _ _20E90.6 166pl.0__ _ 4W3h6 2H26 60AT H0CK__HYOHO ADDITION 4/89 67.0
_ _ _ __ _A H K w n _! titt i . S A_ L 5. h.H L T. I. H. E_ _ -_ - .
,.~ 6/u9 -30.0
'19.~69 - --
~" ~ -
TOTAL 6/30/09 IV 2072726 17 317.~0 3410.6
, ATK!N50N SAlbd'HEitoE.'~ Z _~-~ ~~T_{_-~L 1 6/90-~~~ -68.6 _ _ _ _ _. . ]- T
- - - - - -10 r K gngMg_
. _n 266sL 6 ia6g970 2L3 g6 _ rgs9___
- *=.- - m._eem e .
,. , . - - e #. - . , - - .-e- .---e- -@-.- . _-e
.-, - - - - - - . . * - . . , - - - . m.m
_ee --N -
o._. - - w~ ._+.--me-- -e- -me.+w -w -*-ww_w
- i, .e
- i
- EVA/6// 4 i,
. l
. ~
}
I BEFORE THE GECRGIA FUBLIC SERVICE CO:SIISSIO!i KEE'.,"dA!! CHOI Docket !!c. 312C-U Georgia Power Compray Application To Increase service Rates _
~~
v DIRECT TESTI:101'Y and SUPPORTI!;G EXHIBIT b/2 FOR THE CECRGIA PU3LIC SERVICE CC:CISSIO:1
's.
.--~ . - - . .
DIRECT TESTIMO.7 OF KEEWHAN CHOI Q. Please state your name, address, and occupation. ,
A. My name is Keewi.an Choi and my address is 1122 Springdale Road N.E.,
Atlanta, CA 30306. I am a Professor of Mathematics at the Georgia State bniversity, currently on leave of absence.
Q. Please describe your educational background.
A. I received my Bachelor's degree (1953) in Mathematics from the Case Western Reserve University and both my M.A. (1960) and Ph.D. (1963) in Statistics from the Harvard University.
Q. Please describe your professional experience .
A. I taught Statistics at the Coraell Universiev (1962-1966), and at the University of Missouri (1966-1963). Since ?972, I have been teaching Statistics at the Georgia State University. I was a Research Associate in Statistics at the Atocic Bomb Casualty Commission (o'f the U. S. Acade=y of Sciences and the Japanese Depart =ent of Public Health) from 1968 to 1972. In additica to my full-ti=e teaching activities , I have served as a consultant on Statistical Methods to the Health Systems Reccarch Group at Georgia Institute of Technology, National Cancer Insri-tute and Of fice of the Secretary, Department of Health, Education, and Welfare.
Q. Have you testified in previous rate proceedings?} }io A. Yes. I testified be:are che Georgia Public Service Cct,ission in 1977 (Dackee Nc. 2002-U), under a contrac t with the Ccorgia Public
Serv ice Ccmmis sion. My testimony covered the following three areas:
- 1. Evaluation of the Georgia Power Ccmpany's Allocated Cost of Service Study.
2 Evaluation of the Company's forecasting method for the integrated system peak demand.
- 3. Evaluation of the Cocpany's revenue projection by customer class for 1977 and 1978.
Q. Picase describe the purpose of your testimony.
A. My testimony das prepared under a contract with the Georgia Public Service Co= mis sion. My testimon) covers the following area:
- 1. Evaluation of the Georgia Power Company's forecasting =ethod for the integrated system peak demand.
Q. Picase give your evaluation of the Company's forecasting method
\
for the integrated s, stem peak demand.
A. The Company's forecasts of the annual system peak demand for years
~
1978-1992 are not re1{able for the following 5easons:
- 1. Very small amount o' data (only 14 past peak demands to forecast 16 future manual peak de= ands) were used for
~ '~ ~
forecasting.
- 2. The Company's so-callid '"we ather-normalization" process is.,
}
logically inconsist5nt.
- 3. The Cocpany's econometric model for forecasting the peak demand is very unstable because of the collinearity.
Q. Please explain'the three reasons which made the Company's forecasting
" ~
~
method unreliable.
~
_3 A. 1. Small amount of data.
- The Company'used only 14 pa s t (annual) peak demands to for eca s t 16 future (annual) peak demands. The decreasing certainty of the exogenous variables in the econometric codel with the increasing length of the forecasting horizon and the small a=ount of historical data compounds the fotecasting error of.the Co=pany's method. -
There is a distinct 12-month cycle of monthly peak demands, which should be utilized to obtain more accurate forecasts.
- 2. "'n'es ther-nor=aliza t ion" pro c e s s .
The Company's so-called " weather-norcalization" proces; to modify actual (past) peak de=cnd ia logically inconsistent. A detailed discussion of the logical inconsistency was given in N. my direct testimony before the Public Service Cocaission in 1977 (Docket No. 3002-U).1 t
- 3. The collinearity problem for the Co=pany's econometric codel.
The cost serious defect in the Ccapany's method of forecasting the peak de=and is in its use of two econo.uic indicators, gross state product and total personal income (which was lagged one year), to forecast the peak demand. Thos two ind ica tor s are almost perfectly correlated. The correlation coef ficient between the two indicators (which was co=puted from the 1950 to 1978 data) is .996. It is a nell-known (se istical) fact that a cultiple regression equation (which is the Company's econcmetric model) based er highly correlated 1
See Appendix 1 for a copy of the discussica.
522 ?I2
- independent variables (two economic indicators) is very unstable.
Such a problem is called "collinearity" proLica. (See, for instance, Data Analysis and Regression by F. Mosteller and J. W. Tukey (1977)
Addison Wesley).
The Cenpany's peak demand forecast will change by a large amount when either one (or both) of the econcaic indicators is changed slightly. In other words, small changes in gross state prcduct or total personal income (which are forecasts the=selves) vill cause a large change in the forecasted peak de=and.
The consequences of collinearity of two economic i'dicators is so severe that a si=pler cethod of forecasting the peak demand using only the gross state produce alone is core accurate than the Company's method of forecasting the peak demand using the two economic indicators A
and "wcather-nor=alized" peak demand data and adjusting the forecasts for the effec.ts of air conditioner ownership, electric transportation Y
and natural gas.
In the following table, the actual peak de= ands for 1977 and 1978 are compared with the Cc=pany's forecasts (=ade in 1977) and the forecasts frce the simpler econometric model which uses only aros3 , , ,
Jdu jl) state product as an economic indicator.
Actual Company The simpler Year p e a k (.'nJ ) Forecast forecast 1977 9,631 10,093 (over 4.8%) 9,297 (under 3.5*:)
1973 10,113 11,429 (o- a 13. 0~:) 10,373 (over 2.17)
The simpler codel is of the same form as the Company's econemetric model, with one economic ind ic a to r . The data used for the simpler
model were the annual peak demands for the years 1950-1976.
The value of R is .985 for the si=ple =cdel.
Q. Has the Georgia Power Ccapany used the similar econometric model for the peak demand forecast in 1974?
A. Yes, the Company used tb. similar model in 1974 to forecast annual peak demands for the years 1975 to 1983.
Q. Please ccapare the Ccapany's forecasted peak demands with the actual peak demand for the years 1975 to 1978.
A. The following table presents the actual peaks, the Company's 1974 forecasts (using the 1960-1974 data) and the Company's 1977 fore-asrs (using the 1963-1974 data).
Actual 74 Company 77 Coapany Year y ak (MW) forecast foreca s t 1965 8,795 9,888 (over 12.4%)
N*
1976 9,150 10,878 (over 18.9~)
1977- 9,631 11,'967 (over 24.2%) 10,093 (over 4.8~)
1978 10,113 13,165 (over 30.2~) 11,429 (over 13%)
Q. In your testimony in 1977, you evaluated the Company's forecasting method and also presented your own peak 'emand forecast using the Box-Jenkin's method. How did your forecasts cocpare with the Company's forecasts?
A. My forecast for the 1977 peak demand was under 2.6%, while the Company's furecast was over 4.8".. For 1978 my forecast was under 2.4%, while the Ccapany's forecast was over 13.0%.
Q. What is your recommendation for forecasting the peak demand through 1992?
A. I recommend that the Ccapany cake the forecasts by several dif ferent methods of forecasting, including econometcic method and Box-Jenkin's nethod, and the X-ll program by the U. S. Census Bureau.
522 314
. Q. I! ave you made forecasts using the Sox-Tankin's =cthod?
A. 't e s , I have. The following table gives the forecasts made by the Box-Jenkin's method (using conthly peak demand data for the period of January 1960 to December 19'/8) with one regular diffe.ence, one seasonal difference of order 12 and threc coving averages of order 1,10 and 12 each. ,
1979 Company Forecast Q F.7 ) My Forecast
-(
g Year 1979 11,023 "i,885 Q' S$0 1980 11,695 10,250 1981 12,282 10,629 1982 12,817 11,022 1983 13,335 11,429 1984 14,058 11,850 s
1985 14,77' 12,289 1986 15,427 y 12,743
^
1987 16,056 13,213 1988 16,651 13,702 1989 17,317 14,208 1990 18,029 14,733 1991 18,779 15,277 1992 19,546 15,841 Based on your peak demand forecasts, w.ia t is y our foret.a s t o f the ra te o f Q.
increase for the annual peak demand for the next 14 years?
5"?)
\1
5 A. 3.7 p:r cent.
Q. 'sha t is the consequence o f the Company's over-forecas ts o f the peak de .a:.6 in 1974 and 1977?
t i
A. Since the Company based its 10 year generating plant construction ,
program on the long term forecarts of the peak demand, the over-forecasts of the peak demand have resulted in the present (February 1, 1979) construction program with the capa_ city =uch bigger than the Company's forecasted needs through 10 9.
\.
. y
Appendix I The following statements on the "seather normalized" load were included in my direct testimony before the Public Service Commission in 1977 (Docket No. 3002-U):
l' There is a logical inconsistency in using so-called " weather-normalized" loads in the econotetric model to forecast annual peak loads.
(i) For each year between 1960 and'1975, the so-called " weather-normalized" i load was obtained by adding the " residual" to a load which was obtained fro =
a regression equation of the 'aily peak lead by substituting the nine year (1967-1975) average values of the four temperatures and Julian dates of the peak de=and days. Adding the " residual" to the fitted values frcs regression equ: tions invalidater the entire. theoretical basis for regression analysis. Using such " weather-normalized" loads as annual peak loads in the econometric model is devoid of any theoretical or ;
empirical justification. In the set- of regression equations, daily peak ,
i demand is assu=ed .to be a fu. ction o f f our te=peratures and Julian date. '
On the other hand, in the econocetric model, annual de=and is assumed to '
be a function of the Georgia State Froduct (GSP) and the Total Personal Incoce of the previous year (TPY). Absent in Exhibit 56 is any discussion o f the co=patability of the so-called " weather-normalized" loads (which vere obtained from the first set of regression equations) with r.he defini-tion of ar nual peak load in the econc=etric codel.
(ii) Every one of the actual (annual) peak de= ands from 1960 to 1975 was modified to a so-called " weather-normalized" load. See Attachment 3 in Exhibit 56. This " weather ncrmalization" process i= plies that the weather conditions (temperatures / of the peak demand days hav2 been C ) ?-
J c/. < .
always abnormal _ so that the peak demand for each year has to be
=odified to obtain the " weather-nor=alized" peak demand which would have been the peak demand if the weather conditions had been normal.
In such a case, how does one estimate what would be a peak demand under nor=al weather conditions?
522 318
I-
. . n .<.,
, . c; . . c. ...t
[Xh/b/ h
!i. G. ."hI f - .f r.
rn ..m - ., N ac,,,
se,a uc:mrf May 9, 1978 ,, ,
, Mr . harry W. Wright
. Executive Vice Presid2nt &
, General Manager i
Seminole Electric Cooperative 2410 East Busch Boulevard - Suite 129 -
Tampa, Florida 33612
Dear Mr. Wright:
Georgia Power Company has under construction two 1150 did PUR nuclear generating units at Plant Vogtle in Burke County, Georgia, near Augusta. These units are currently scheduled to begin ccamercial operation in the mid-1980's. Undivided ownership interests in ' e plant are presently held as follows:
t Georgia Power Ccmpany 50.7%
Oglethorpe Electric Membership Corporation 30.0%
Municipal Electric Authority of Georgia 17.7%
City.of Dalton 1.6%
t Under the ter=s of the contracts covering this joint ownership, Georgia P w".r has the unfettered right to sell up to an addi-tional 30*'. interest in Plant Vogtle if the sale is consu==ated befora January 27, 1979; thereafter it may sell any portion of its 50.7% interest subject to a right of first refusal of the other participants. It may also make uait power sales frca the units.
The latest ecenc=etric informaticn available to Georgia Pcwer indicates that the electrical load growth of its service territory may 'ce less thar. previcusly anticipated. In the resulting restudy of our generation expansion program for the 1980 decade, we may find it prudent to sell an additional cwnership share in or unit power frca Plant Vogtle.
At sccetime in the past, your organica'tice indicated an interest in Plant Vogtle, either orally c. in writing.
Please advise if your organization still has an interest in this subj ect and whether you wish to be contacted further about it.
Sinc erel:/ ,
lf y//a m
I
/
3 H. G. 3aker, Jr EG3Jr/cpw rs ", ) ; )Q L- J .
..:. ,et .
., :. i . . ,
. - 1, *, : m . la ; , i,,si H. G. Ca':: r, Jr.
Cowar V.cc rt y..ct:m
%cr ces f May 9, 1978 r. . . w?, ,.:, :ve .:, r ,
Mr. W. M. Irving, Managing Director
,7'Jacksonville Electric Authority
. O. Box 53015 0' Jacksonville, Florida 32202
Dear Mr. Irving:
Georgia Power Ccarany has under construction two 1150 MW PWR nuclear generating units at Plant Vogtle in Burke Ccunty, Georgia, near Aurjusta. There units are currently scheduled to begin commercial operation in the mid-1980's. Undivided ownership interests in the plant are presently held as follows.
Georgia Power Company 50.7%
Oglethorpe Electric Membership Corporation . 30.0%
Municipal Electric Authority of Georgia 17.7%
City of Dalton 1.6%
Under the ter=s of the contracts covering this joint ownership, Georgia Power has the unfettered right to sell up to an addi-tiona] 30% interest in Plant Vogtle if the sale is consummated before January 27, 1979; thereafter it may sell any portion of its 50.7% interest subj ecc to a right of first refusal of the other parsicipants. It may also make unit power sales from the unit.s.
The latest econometric information available to Georgia Power indicates that the electrical load growth of its service territory may be less than previously anticipated. In the resulting restudy of our generation expansion program for the .
1930 decade, we may find it prudent to sell an additicaal cwnership share in or unit pcwer from Plant Vogtle.
At scoetime in the past, your organitation indicated an interest in Plant Vogtle, either orally cr in writing.
Please advise if your organization still has an interest in this subj ect and whether you wish to be contacted further about it.
Sincerely, f
(
%/hh H. G. Baker, Jr.
[- 6 -)
HG Jr/co.w 5/< -
7?0 s -
.i,.
li -it.i+. .. -
. .u ru us a m-
\ , ; .g fN 't * !;I A '
i14'
!!. G. G A cr.Jr.
F.anct ve iw .:.o ac cr cciacq May 9, 1973 ,,,,,m..,,,,,.,,..,.,.,,,
, Mr. E. A. Adocat
.' Executive Vice President
,.y Florida Power & Light Cocpany P. O. Box 013100 Miami, Florida 33101 -
Dear >b. Adocat:
Georgia Power Cc=pany has under construction two 1150 MW PWR nuclear generating units at Plant Vogtle in Burke County, Georgia, near Augusta. These units are currently scheduled to begin co==ercial operation in the mid-1930's. Undivided ownership interests in the plant are presently held as follows.
Georgia Pm. - company '
50.7%
Oglethorpe atric Me=bership Corporation 30.0%
Municipal Electric Authority of Georgia 17.7%
City of Dalton 1.6%
Under the terms of the contracts covering thi: joint ownership, Georgia Power has the unfettered right to sel; up to an addi-tional 30% interest in Plant Vogtle if the sal = is consurmated before January 27, 1979; thereafter it may sell any portion of its 50.7% interest subject to a right of first refusal of the other participants. It may also make unit power sales from the units.
The latest econometric information available to Georgia Power indicates that the electrical load growth of its service territory may be less than previously anticipated. In the r sulting restudy of our generation expansion program for the 1930 decade, s' may find it prudent to sell an additional ownership share in or unit pcwer from Plant Vogtle.
At sacetime in the past, your organization indicated an interest in Plant Vogtle, either orally or in writing.
Please advise if your organitation still has an interest in this subject and whether you wish to be contacted further about it.
(
"-?1 o
dancerety, 524
/ /
/us < '
GT ~ /
E. G. Baker, Jr.
HG3Jr/cpw
r, . n ,.i;,
., ,, n te .
M. G. C M.:r Jr.
Sco.cr '/::a Pmm:m -
eme ecm,c:y ,ay 9, ,19 /., 8 d
;r. , . .m . , :r n ..m f, .
Mr. Alton g kall
. : Executive Vice President &
y General Manager e North Carolina Electric Membership Corporation P. O. Box 27306 Raleigh, North Carolina 27611
Dear Mr. Wall:
Georgia Power Co=cany has under construction two 1150 FD7 PWR nuclear generating units at Plant Vogtle in Burke County, Georgia, near Augusta. These units are currently scheduled to begin com=ercial operation in the mid-1980's. Undivided ewnership interest, in the plant are presently held as follows:
Georgia Power Company 50.7%
Oglethorpe Electric Membership Corporation 30.0%
Municipal Electric Authcrity of Georgia 17.7%
City of Dalton 1.6%
Under the terms of the contracts covering this joint ownership, Georgia Power has the unfettered right to sell up to an addi-tional 30% interest in Plant Vogtle if the sale is consu= mated before January 27, 1979; thereafter it may sell any portion of its 50.7'/ intereat subject to a right of first refusal of the other participants. It may also make. unit power sales from the units.
The latest econocetric information available to Georgia Power indicates that the electrical load growth of its service territory may be less than previously anticipated. In the resulting restudy of our generation expansion program for the 1960 decade, we =ay find _: prudent to sell an additional ownership share in or unit power from Plant Vogtle.
At sometime in the past, your organization indicated an interest in Plant Vogtle, either orally or in writing.
Please advise if your organization still has an interest in this subj ect and whethe. you wish to be contacted turther
, about it.
Sincerely,
,) , hq i ,/
L -"
, l u, - . m, E. G. Ba.;er , Jr .
HG3Jr/ cow -
i
i.. ' . . . i '. s
. . u, e r oi; , .u*
,..e.,,
c s i,.a
!!. G. C e l= r, 'r.
Pice..en:
,,C.r.ic e ', c :
- .u r cc.,<ce, May 9, 1978 ,,,,..,,,.,y,,. ,..,,,,
Mr. Marshall R. Dorsey J General Manager 1 Big River 5 Electric Corporation C' P. O. Box 24 Henderson, Kentucky 42420 .
Dear Mr. Dorsey:
Gevrgia Power Company has under construction two 1150 FJ P'4R nuclear generating units at Plant Vogtle in Burke County, Georgia, near Augusta. These units are currently scheduled to begin co==ercial operatica in the mid-1980's. Undivided ownership interests in the plant are presently held as follows:
Georgia Power Company , 50.7%
Oglethorpe Electric Membership Corporation 30.0%
Municipal Electric Authority of Georgia 17.7%
City of Dalton 1.6%
Under the terms of the contracts covering this joint ownership, Georgia Power r:as the unfettered right to sell up to an addi-tional 30% interest in Plant Vogtle if the sale is consu==ated before January 27, 1979; thereafter it may sell any portion of its 50.7% interest subj ect to a right of first refusal of the other participants. It may also make unit power sales frc=
the units.
The latest econometric infor aticn available to Georgia Power indicates that the electrical load growth of its service territory may be less than previcusly anticipated. In the resulting restudy of our generation expansion program for the .
1980 decade, we may find it prudent to sell an additional ownership share in or unit power from Plant Vogtle.
At sometime in the past, your organization indicated an interest in Plant Vogele, either orally or in writing.
Please advise if your organization still has an interest in this subject and whether you wish to be contacted further about it.
Sincerely, -,2 L 323'
. Wh '
H. G. Baker, Jr.
HG2Jr/cpw
I '. ' a .
. . i,...._ . ..
- c. c.e :r.ar.
.%.mr vin Pre . 'ud P:..a oc:.my May 9, 1973 cr . . . . ., , , , z . . . . :, c . ,-:1
. 1: r
. Mr. M. C. Johnson, Vice President Soutn Carolina Electric & Gas Carpany
,.)
P. O. Box 764 Columbia, South Carolina 29218
Dear Mr. Johnson:
Cecrgia Pcwer Company has under construction two 1150 MW PWR nuclear generating units at Plant Vogtle in Burke County, Georgia, near Augusta. These units are currently scheduled to begin cc mercial operation in the mid-1980's. Undivided ownership interests in the plant are presently held as follows.
Georgia Power Company 50.7%
Oglethorpe Electric Membership Corporction 30.0%
Municipal Electric Authority of Georgia 17.7%
City of Dalton 1.6%
Under the terms of the contracts covering this joint ownership, Georgia Power has the unfettered right to sell up to an addi-tional 30% interest in Plant Vogtle if the sale is consummated before .Tanuary 27, 1979; thereafter it may sell any portion of its 50./% interest ubject to a right of first refusal of the other participants. It may also make unit power sales frca the units.
The latest econometric infor=ation available to Georgia Power indicates that the electrical load growth of its service territory may be less than previously anticipated. In the resulting restudy of our generaticn expansion program for the ,
1980 decade, we may find it prudent to sell an additional ownership share in or unit power frca Plant Vogtle.
At scmetime in the past, your organication indicated an interest in Plant Vogtle, either orally or in writing.
Please advise if your organication still has an interest in this subject and whether you wish to be contacted further about it.
Sincerely 572 324
\/ .
hk H. G. 3aker, Jr.
HGE r/cpw}}