Forwards Essex Corp Human Factors Design Engineering Evaluation of Control Room Per NUREG-0660,Task I.D.1.Review Conducted from 800617-1001,using Criteria from NUREG-1580, Human Engineering Guide to Control Room Evaluation
ML20062K802
Person / Time
Site: Grand Gulf Entergy icon.png
Issue date: 12/29/1980
From: Dale L
MISSISSIPPI POWER & LIGHT CO.
To: Harold Denton
Office of Nuclear Reactor Regulation
Shared Package
ML20062K805 List:
References
RTR-NUREG-0660, RTR-NUREG-1580, RTR-NUREG-660, TASK-1.D.1, TASK-TM AECM-80-316, NUDOCS 8101060435
Download: ML20062K802 (2)


Text

  • f 1 o /

his DOCUMENT CONTAINS F00RQUAUTYPAGES MISSISSIPPI POW $R & LIGHT COMPANY Helping Build Mississippi

" " " " " = "

P. O, B O X 164 0, J A C K S O N, MISSISSIPPI 39205 December 29, 1980 NUct EAR PRoOUCTioN DEPARTMENT U.S. Nuclear Regulatory Commission Office of Nuclear Reactor Regulation Washington, D.C. 20555 Attention: Mr. Harold R. Denton, Director

Dear Sir:

SUBJECT:

Grand Gulf Nuclear Station Unit 1 Docket No. 50-416 File 0260/0277/0755/L-860.0

, Control Room Design Review Report 2

AECM-80/316 NUREG-0660, Task I.D.1 requires us: to perform a comprehensive review of our control room using NRC human factors design guidelines and evaluation criteria; to modify to correct significant deficiencies; to 7 issue a report describing methods of review, results of review, including bases of findings made, and implementation schedules.

Accordingly, Mississippi Power & Light Company (MP&L), as agent for Middle South Energy, Inc. contracted with the Essex Corporation to perform an independent third party review of the Grand Gulf Nuclear Station Unit I control room. This evaluation was conducted during the period from June 17, 1980 to October 1, 1980 and employed state-of-the-art human engineering evaluation techniques especially tailored for a control room design review using criteria from

.WREG-1580, " Human Engineering Guide to Control Room Evaluation."

The results of that design review have been compiled into the report which is attached for your review. The report prioritizes discrepancies, recommends corrective actions, and presents an implementation schedule.

We would request that we be advised as soon as possible of any comments or recommendations you may have in regard to this report and its conclusions.

Yours truly, G ,/ 9 /

gm4 f'L.F. Dale geo/

3 Nuclear Project Manager CLT/JDR:Im Attachment  !!

cc: (See Next Page) 8101060 Member Middle Souen ceitities System

O MISSISSIPPI POWEft & LIGHT COMPANY U.S. Nuclear Regulatory Commission AECM-80/316 Office of Nuclear Reactor Regulation Page 2 cc: Mr. N. L. Stampley (w/o)

Mr. G. B. Taylor (w/o)

Mr. R. B. McGehee (w/o)

Mr. T. B. Conner (w/o)

Mr. Victor Stello, Jr. , Director (w/a)

Division of Inspection & Enforcement U.S. Nuclear Regulatory Connaission Washington, D.C. 20555 t

l l

l l