2014 Annual Assessment Letter for Indian Point Nuclear Generating Units 2 and 3 (Report 05000247/2014001 and 05000286/2014001)(w/Inspection Plan)
ML15061A401
Person / Time
Site: Indian Point  Entergy icon.png
Issue date: 03/04/2015
From: Burritt A L
Reactor Projects Branch 2
To: Coyle L
Entergy Nuclear Operations
Burritt A L
References
FOIA/PA-2016-0148 IR 2014001
Download: ML15061A401 (5)


See also: IR 05000247/2014001

Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 2100 RENAISSANCE BLVD., SUITE 100 KING OF PRUSSIA, PA 19406-2713 March 4, 2015

Mr. Larry Coyle

Site Vice President Entergy Nuclear Operations, Inc. Indian Point Energy Center

450 Broadway, GSB

P.O. Box 249

Buchanan, NY 10511-0249

SUBJECT: ANNUAL ASSESSMENT LETTER FOR INDIAN POINT NUCLEAR GENERATING UNITS 2 AND 3 (REPORT 05000247/2014001 AND

05000286/2014001)

Dear Mr. Coyle: On February 11, 2015, the U. S. Nuclear Regulatory Commission (NRC) completed its end-of-

cycle performance review of Indian Point Nuclear Generating (Indian Point) Units 2 and 3. The

NRC reviewed the most recent quarterly performance indicators (PIs) in addition to inspection

results and enforcement actions from January 1, 2014 through December 31, 2014. This letter informs you of the NRC's assessment of your facility during this period and its plans for future inspections at your facility.

The NRC determined that overall, Indian Point Units 2 and 3 operated in a manner that preserved public health and safety and met all cornerstone objectives. The NRC determined

the performance at Indian Point Units 2 and 3 during the most recent quarter was within the Licensee Response Column of the NRC's Reactor Oversight Process (ROP) Action Matrix because all inspection findings had very low (i.e., Green) safety significance, and all PIs

indicated that your performance was within the nominal, expected range (i.e., Green).

Therefore, the NRC plans to conduct ROP baseline inspections at your facility. The enclosed inspection plan lists the inspections scheduled through June 30, 2016. Routine inspections performed by resident inspectors are not included in the inspection plan. The

inspections listed during the last nine months of the inspection plan are tentative and may be

revised at the mid-cycle performance review. In addition to baseline inspections, the NRC will perform inspection procedure (IP) 60855, "Operation of an Independent Spent Fuel Storage

Installation at Operating Plants," IP 92702, "Follow-up on Corrective Actions for Violations," and Temporary Instruction 2516-001, "Review of License Renewal Activities." The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel

availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not

include security-related inspections, which will be sent via separate, non-publicly available correspondence.

L. Coyle 2

In accordance with Title 10 of the Code of Federal Regulations, Part 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records component of NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). Please contact me at (610)337-5069 with any questions you have regarding this letter.

Sincerely,

/RA/ Arthur L. Burritt, Chief

Reactor Projects Branch 2

Division of Reactor Projects Docket Nos. 50-247 and 50-286

License Nos. DPR-26 and DPR-64

Enclosure: Indian Point 2 & 3 Inspection/Activity Plan

cc w/encl: Distribution via ListServ

ML15061A401 SUNSI Review Non-Sensitive Sensitive Publicly Available Non-Publicly Available OFFICE RI/DRP RI/DRP NAME TSetzer/TCS ABurritt/ALB DATE 02/23/15 03/02/15

Page 1 of 203/02/201515:16:39Report 22UnitNumberPlanned DatesStart EndInspection ActivityTitleNo. of Staffon SiteIndian PointInspection / Activity Plan01/01/2015-06/30/20165/11EXAM-U3 INITIAL OL EXAM5 3 FY15-IP3 INITIAL OPERATOR LICENSING EXAMU0190804/13/201504/17/2015 3 FY15-IP3 INITIAL OPERATOR LICENSING EXAMU0190805/11/201505/15/201571124-RETS1 2,3 IPRadiation Monitoring Instrumentation71124.0502/09/201502/13/2015 2,3 IPRadioactive Gaseous and Liquid Effluent Treatment71124.0602/09/201502/13/201571124-HP1 3 IPRadiological Hazard Assessment and Exposure Controls71124.0103/02/201503/06/2015 3 IPOccupational ALARA Planning and Controls71124.0203/02/201503/06/20157111108P-U3 INSERVICE INSPECTION1 3 IPInservice Inspection Activities - PWR7111108P03/09/201503/20/201571152-GROUNDWATER MONITORING5 2 IPProblem Identification and Resolution7115205/04/201505/07/201571124-HP1 2,3 IPRadiological Hazard Assessment and Exposure Controls71124.0105/07/201505/13/2015 2,3 IPOccupational ALARA Planning and Controls71124.0205/07/201505/13/20157111107T-TRIENNIAL HEAT SINK1 2,3 IPHeat Sink Performance7111107T07/06/201507/10/2015CDBI-COMPONENT DESIGN BASIS INSPECTION8 2,3 IPComponent Design Bases Inspection711112107/20/201507/24/2015 2,3 IPComponent Design Bases Inspection711112108/03/201508/07/2015 2,3 IPComponent Design Bases Inspection711112108/17/201508/21/20157111111B-IP3 REQUAL INSP W/ P/F RESULTS2 3 IPLicensed Operator Requalification Program7111111B09/21/201509/25/201571124-HP1 2,3 IPOccupational Dose Assessment71124.0408/10/201508/14/2015 2,3 IPRadiation Monitoring Instrumentation71124.0508/10/201508/14/2015 2,3 IPPerformance Indicator Verification7115108/10/201508/14/2015EP-EP PROGRAM INSPECTION1 2,3 IPAlert and Notification System Testing711140208/17/201508/21/2015 2,3 IPEmergency Preparedness Organization Staffing and Augmentation System711140308/17/201508/21/2015 2,3 IPCorrection of Emergency Preparedness Weaknesses and Deficiencies711140508/17/201508/21/2015This report does not include INPO and OUTAGE activities. This report shows only on-site and announced inspection procedures.

Page 2 of 203/02/201515:16:39Report 22UnitNumberPlanned DatesStart EndInspection ActivityTitleNo. of Staffon SiteIndian PointInspection / Activity Plan01/01/2015-06/30/2016ISFSI-ISFSI LOADING INSPECTION2 2,3 IPOperation Of An ISFSI6085508/17/201508/21/2015 2 IPOperation of an Independent Spent Fuel Storage Installation at Operating Plants60855.108/17/201508/21/20152516-001-TI 2516-001 U3 LR COMMITMENTS INSPECTION1 3 IPReview of License Renewal Activities2516/00111/16/201511/20/201571124.08-RADWASTE1 2,3 IPRadioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation71124.0811/16/201511/20/201571152B-PI&R - BIENNIAL4 2,3 IPProblem Identification and Resolution71152B11/30/201512/04/2015 2,3 IPProblem Identification and Resolution71152B12/14/201512/18/201571124-HP1 2 IPRadiological Hazard Assessment and Exposure Controls71124.0103/07/201603/11/2016 2 IPOccupational ALARA Planning and Controls71124.0203/07/201603/11/2016ISI-U2 INSERVICE INSPECTION1 2 IPInservice Inspection Activities - PWR7111108P03/14/201603/25/2016EP-EP EXERCISE EVALUATION4 2,3 IPExercise Evaluation711140106/27/201607/01/2016TRI FI-TRIENNIAL FIRE PROTECTION4 2,3 IPFire Protection [Triennial]7111105T05/23/201605/27/2016 2,3 IPFire Protection [Triennial]7111105T06/06/201606/10/201671124.07-REMP1 2,3 IPRadiological Environmental Monitoring Program71124.0706/20/201606/24/2016This report does not include INPO and OUTAGE activities. This report shows only on-site and announced inspection procedures.