UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 475 ALLENDALE RD., SUITE 102 KING OF PRUSSIA, PA 19406-2713 December 21, 2022 Kelly Trice President - HDI Holtec Decommissioning International, LLC Krishna P. Singh Technology Campus 1 Holtec Boulevard Camden, NJ 08104

SUBJECT:

INDIAN POINT ENERGY CENTER, UNITS 1, 2, & 3 SECURITY INSPECTION PLAN

Dear Kelly Trice:

The enclosed inspection plan lists the security inspections scheduled through December 31, 2024. The inspection plan is provided to allow for the resolution of any scheduling conflicts and personnel availability issues well before our inspectors arrive on site.

In accordance with Title 10 of the Code of Federal Regulations 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRCs Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRCs Website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

If circumstances arise which cause us to change the inspection plan, we will contact you to discuss the change as soon as possible. Please contact me at (610) 337-5262 with any questions you may have regarding the inspection plan.

Sincerely, Digitally signed by Daniel Daniel L. L. Schroeder Date: 2022.12.21 Schroeder 15:17:37 -05'00' Daniel L. Schroeder, Chief Security, Emergency Preparedness and Incident Response Branch Division of Radiological Safety and Security Docket Nos.50-003, 50-247, and 50-286 License Nos. DPR-5, DPR-26, and DPR-64

Enclosure:

Indian Point Energy Center, Units 1, 2, & 3 Security Inspection Plan cc w/encl; D. Gagnon, Holtec Fleet Security Director J. Fleming, Vice President Regulatory Affairs A. Peterson, Senior Advisor, New York State Energy Research and Development Authority

ML22347A250 Non-Sensitive Publicly Available SUNSI Review Sensitive Non-Publicly Available OFFICE RI/DRSS RI/DRSS RI/ DRSS NAME TEck ADimitriadis DSchroeder DATE 12/15/2022 12/16/2022 12/21/2022 Site Inspection Activity Plan Indian Point 01/01/2023 - 12/31/2024 Unit Start End Activity CAC Title Staff Count AA, Access Control, Sec Trng, Sec Plan Review-IP 2 1,2,3 4/17/2023 4/21/2023 IP 81200.01 000024 Access Authorization for Decommissioning Nuclear Power Reactors 1,2,3 4/17/2023 4/21/2023 IP 81200.02 000025 Access Control for Decommissioning Nuclear Power Reactors 1,2,3 4/17/2023 4/21/2023 IP 81200.09 001786 Security Plan Changes for Decommissioning Power Reactors Access Control, Equipment, Sec Training, SPR - IP 2 1,2,3 2/26/2024 3/1/2024 IP 81200.02 000025 Access Control for Decommissioning Nuclear Power Reactors 1,2,3 2/26/2024 3/1/2024 IP 81200.04 000026 Equipment Performance, Testing, and Maintenance for Decommissioning Nuclear Power Reactors 1,2,3 2/26/2024 3/1/2024 IP 81200.07 000029 Security Training for Decommissioning Nuclear Power Reactors 1,2,3 2/26/2024 3/1/2024 IP 81200.09 001786 Security Plan Changes for Decommissioning Power Reactors Prepared on 11/22/2022 12:49:59 PM 1 of 1