Category:Inspection Plan
MONTHYEARML22347A2502022-12-21021 December 2022 Security Inspection Plan ML21208A2112021-07-27027 July 2021 Decommissioning Inspection Plan for Indian Point Generating Unit 3 - 2021 IR 05000286/20200062021-03-0303 March 2021 Annual Assessment Letter for Indian Point Energy Center, Unit 3 (Report 05000286/2020006) IR 05000286/20200052020-08-31031 August 2020 Updated Inspection Plan for Indian Point Energy Center, Unit 3 (Inspection Report 05000286/2020005) IR 05000247/20190062020-03-0303 March 2020 Annual Assessment Letter for Indian Point Energy Center, Units 2 and 3 (Report 05000247/2019006 and 05000286/2019006) IR 05000247/20190052019-08-28028 August 2019 Updated Inspection Plan (Inspection Report 05000247/2019005 and 05000286/2019005) IR 05000247/20180062019-03-0404 March 2019 Annual Assessment Letter for Indian Point Energy Center, Units 2 and 3 (Reports 05000247/2018006 and 05000286/2018006) IR 05000247/20180052018-08-28028 August 2018 Updated Inspection Plan (Inspection Report 05000247/2018005 and 05000286/2018005) ML18240A1612018-08-28028 August 2018 Updated Inspection Plan (Inspection Report 05000247/2018005 and 05000286/2018005) IR 05000247/20170062018-02-28028 February 2018 Annual Assessment Letter for Indian Point Energy Center, Units 2 and 3 (Report 05000247/2017006 and 05000286/2017006, Report 05000247/2017402 and 05000286/2017402, Report 05000247/2017501 and 05000286/2017501) IR 05000247/20170052017-08-28028 August 2017 Updated Inspection Plan for Indian Point Nuclear Generating, Units 2 and 3 (Report 05000247/2017005 and 05000286/2017005) IR 05000247/20160062017-03-0101 March 2017 Annual Assessment Letter for Indian Point Nuclear Generating, Units 2 and 3 (Report 05000247/2016006 and 05000286/2016006) IR 05000247/20160052016-08-31031 August 2016 Mid-Cycle Assessment Letter for Indian Point Nuclear Generating Units 2 and 3 (Report 05000247/2016005 and 05000286/2016005) IR 05000247/20150062016-03-0202 March 2016 2015 Annual Assessment Letter for Indian Point Nuclear Generating, Units 2 and 3 (Report 05000247/2015006 and 05000286/2015006) IR 05000247/20150052015-09-0101 September 2015 Mid-Cycle Assessment Letter for Indian Point Nuclear Generating Units 2 and 3 (Report 05000247/2015005 and 05000286/2015005) ML15061A4012015-03-0404 March 2015 2014 Annual Assessment Letter for Indian Point Nuclear Generating Units 2 and 3 (Report 05000247/2014001 and 05000286/2014001)(w/Inspection Plan) IR 05000247/20140062014-09-0202 September 2014 Mid-Cycle Assessment Letter and Inspection Plan 2014 (ROP-15) - Indian Point Nuclear Generating Units 2 and 3 (Report 05000247-14-006 and 05000286-14-006) IR 05000247/20130012014-03-0404 March 2014 2013 Annual Assessment Letter for Indian Point Nuclear Generating Units 2 and 3 (Report 05000247/2013001 and 05000286/2013001)(w/Inspection Plan) ML14027A4152014-01-16016 January 2014 Enclosure 2 to NL-14-010, Attachment 2, Final Response to U.S. NRC RAI 6-A Items 1 and 2 on the Rvi Program and Rvi Inspection Plan IR 05000247/20130062013-09-0303 September 2013 Mid-Cycle Performance Review and Inspection Plan 2013 (ROP-14) - Indian Point Nuclear Generating Units 2 and 3 (Report 05000247-13-006 and 05000286-13-006) IR 05000247/20120012013-03-0404 March 2013 Annual Assessment Letter for Indian Point Nuclear Generating Units 2 and 3 (Report 05000247-12-001 and 05000286-12-001) ML12297A0062012-10-22022 October 2012 Notification of Conduct of a Triennial Fire Protection Baseline Inspection ML12244A3542012-09-0404 September 2012 Mid-Cycle Performance Review and Inspection Plan - 2013 Indian Point Nuclear Generating Units 2 and 3 IR 05000247/20110012012-03-0505 March 2012 Annual Assessment Letter (Report 05000247/2011001 and 05000286/2011001) ML1124208362011-09-0101 September 2011 Mid-Cycle Performance Review and Inspection Plan 2011 - Indian Point Nuclear Generating Units 2 and 3 ML1106204642011-03-0404 March 2011 Annual Assessment Letter for Indian Point Nuclear Generating Units 2 and 3 (Reports 05000247/2010001 and 05000286/2010001) ML1024402362010-09-0101 September 2010 Mid-Cycle Performance Review and Inspection Plan 2010 - Indian Point Nuclear Generating Units 2 and 3 ML1006208632010-03-0303 March 2010 Annual Assessment Letter (Report 05000247-10-001 & 05000286-10-001) ML0924401932009-09-0101 September 2009 Mid-Cycle Performance Review and Inspection Plan - Indian Point Nuclear Generating Stations Units 2 and 3, Dated 09/01/09 IR 05000247/20090012009-03-0404 March 2009 IR 05000247-09-001 and 05000286-09-001, on 02/10/2009, Indian Point Nuclear Generating Units 1 & 2, Annual Assessment Letter, Dated March 4, 2009 ML0824703162008-09-0202 September 2008 Mid-Cycle Performance Review and Inspection Plan, Indian Point, Units 2 and 3 ML0904105262008-06-0202 June 2008 Inspection Plan - Indian Point 2; Station Blackout Diesel Generator Modification & 50.59; IR No. 50-247-08-012 IR 05000247/20080012008-03-0303 March 2008 Annual Assessment Letter EOC 2007 ROP8 - Indian Point Energy Center (05000247-08-001, 05000286-08-001) ML0734709592007-12-13013 December 2007 ROP8 - Indian Point 2 and 3 - Change to Inspection Plan, 12/13/07 ML0724309422007-08-31031 August 2007 Mid-Cycle Performance Review and Inspection Plan - Indian Point Nuclear Generating Units 2 and 3 ML0706106032007-03-0202 March 2007 Annual Assessment Letter EOC 2006 - Indian Point Station Units 2 & 3 (05-247/2007001 and 05-286/2007001) ML0708806212006-12-26026 December 2006 E-Mail from Mclaughlin to Alp@Nyserda.Org, NRC Reactor Inspection Schedule for 1Q07 ML0624306582006-08-31031 August 2006 Mid-cycle Performance Review and Inspection Plan - Indian Point Nuclear Generating Units 2 and 3 ML0613805862006-05-18018 May 2006 Inspection/Activity Plan, 05/01/2006 - 09/30/2007 ML0621406102006-05-18018 May 2006 Inspection / Activity Plan 05/01/2006 - 09/30/2007 ML0606201072006-03-0202 March 2006 2006-001 - Annual Assessment Letter - Indian Point Nuclear Generating Units 2 and 3 (Reports 05-247/2006001 & 05-286/2006001) ML0526400032005-09-20020 September 2005 Memo Special Inspection Charter - Indian Point, Unit No. 2 ML0524207132005-08-30030 August 2005 2005 Mid-Cycle Review and Inspection Plan - Indian Point 2 & 3 ML0506105932005-03-0202 March 2005 Annual Assessment Letter 2005001 - Indian Point 2 & 3 ML0424400842004-08-30030 August 2004 2004 Mid-Cycle Performance Review and Inspection Plan - Indian Point 2 and 3 ML0406305552004-03-0303 March 2004 2003-04 Annual Assessment Letter - Indian Point IR 05000286/20030012003-03-0303 March 2003 2003 Annual Assessment Letter - Indian Point Nuclear Generating Unit 2 (Report 50-286/2003001) ML0224100642002-08-28028 August 2002 2002 Mid-Cycle Performance Review and Inspection Plan - Indian Point Nuclear Generating Unit 2 ML0223803962002-08-26026 August 2002 2002 Indian Point 3 Mid-Cycle Performance Review and Inspection Plan IR 05000247/20020012002-03-0404 March 2002 2002 Annual Assessment Letter - Indian Point 2 (Report 50-247/02-01) 2022-12-21
[Table view] Category:Inspection Report
MONTHYEARIR 05000003/20240022024-08-0606 August 2024 NRC Inspection Report 05000003/2024002, 05000247/2024002, 05000286/2024002 IR 05000003/20240052024-05-21021 May 2024 And 3 - NRC Inspection Report Nos. 05000003/2024005, 05000247/2024005, 05000286/2024005, 07200051/2024001, and Notice of Violation IR 05000003/20240012024-03-20020 March 2024 NRC Inspection Report Nos. 05000003/2024001, 05000247/2024001, and 05000286/2024001 (Cover Letter Only) IR 05000003/20230042024-02-22022 February 2024 NRC Inspection Report Nos. 05000003/2023004, 05000247/2023004, 05000286/2023004, and 07200051/2023004 and Notice of Violation IR 05000003/20230032023-11-21021 November 2023 NRC Inspection Report Nos. 05000003/2023003, 05000247/2023003, 05000286/2023003, and 07200051/2023003 IR 05000003/20230022023-08-22022 August 2023 NRC Inspection Report 05000003/2023002, 05000247/2023002, 05000286/2023002, and 07200051/2023002 IR 05000003/20230012023-05-22022 May 2023 Unions 1, 2 and 3 - NRC Inspection Report Nos. 05000003/2023001, 05000247/2023001, 05000286/2023001, and 07200051/2023001 IR 05000003/20234012023-05-10010 May 2023 NRC Security Decommissioning Inspection Report Nos. 05000003/2023401, 05000247/2023401, and 05000286/2023401 IR 05000003/20220042023-03-13013 March 2023 NRC Inspection Report Nos. 05000003/2022004, 05000247/2022004, 05000286/2022004, and 07200051/2022002 IR 05000003/20220022022-11-17017 November 2022 NRC Inspection Report Nos. 05000003/2022002, 05000003/2022003, 05000247/2022002, 05000247/2022003, 05000286/2022002, 05000286/2022003, and 07200051/2022001 IR 05000003/20224022022-10-28028 October 2022 Reissued NRC Security Decommissioning Inspection Report Nos. 05000003/2022402, 05000247/2022402, and 05000286/2022402 (Letter Only) IR 05000003/20220012022-05-25025 May 2022 NRC Inspection Report Nos. 05000003/2022001, 05000247/2022001, and 05000286/2022001 IR 05000003/20224012022-05-25025 May 2022 NRC Security Decommissioning Inspection Report Nos. 05000003/2022401, 05000247/2022401, and 05000286/2022401 IR 05000003/20210042022-03-0404 March 2022 NRC Inspection Report Nos. 05000003/2021004, 05000247/2021004, 05000286/2021004, and 07200051/2021001 IR 05000003/20210032021-11-0909 November 2021 NRC Inspection Report Nos. 05000003/2021003, 05000247/2021003, and 05000286/2021003 IR 05000003/20210022021-08-0404 August 2021 NRC Inspection Report Nos. 05000003/2021002, 05000247/2021002, and 05000286/2021002 IR 05000286/20210022021-06-0707 June 2021 Integrated Inspection Report 05000286/2021002 IR 05000286/20214022021-05-0505 May 2021 Security Baseline Inspection Report 05000286/2021402 IR 05000003/20210012021-04-21021 April 2021 Entergy Nuclear Operations, Inc., Indian Point Nuclear Generating Station Units 1 and 2 - NRC Inspection Report No. 05000003/2021001 and 05000247/2020001 IR 05000286/20210012021-04-15015 April 2021 Integrated Inspection Report 05000286/2021001 IR 05000286/20200062021-03-0303 March 2021 Annual Assessment Letter for Indian Point Energy Center, Unit 3 (Report 05000286/2020006) IR 05000247/20200142021-02-0101 February 2021 Entergy Nuclear Operations, Inc., Indian Point Nuclear Generating Station Unit 2 NRC Inspection Report No. 05000247/2020014 IR 05000286/20200042021-01-28028 January 2021 Integrated Inspection Report 05000286/2020004 IR 05000003/20200012020-12-0808 December 2020 Entergy Nuclear Operations, Inc., Indian Point Nuclear Generating Station Units 1 and 2, NRC Inspection Report No. 05000003/2020001 and 05000247/2020013 IR 05000286/20200032020-10-28028 October 2020 Integrated Inspection Report 05000286/2020003 IR 05000286/20200102020-09-16016 September 2020 Evaluation of Changes, Tests and Experiments Baseline Inspection Report 05000286/2020010 IR 05000286/20200052020-08-31031 August 2020 Updated Inspection Plan for Indian Point Energy Center, Unit 3 (Inspection Report 05000286/2020005) IR 05000247/20200022020-08-10010 August 2020 Integrated Inspection Report 05000247/2020002 and 05000286/2020002 IR 05000286/20200122020-07-27027 July 2020 Design Basis Assurance Inspection (Programs) Inspection Report 05000286/2020012 IR 05000247/20020102020-05-12012 May 2020 Final ASP Analysis - Indian Point 2 (IR 050002472002010) IR 05000247/20200012020-04-29029 April 2020 Integrated Inspection Report 05000247/2020001 and 05000286/2020001 IR 05000247/20190062020-03-0303 March 2020 Annual Assessment Letter for Indian Point Energy Center, Units 2 and 3 (Report 05000247/2019006 and 05000286/2019006) IR 05000247/20190042020-02-10010 February 2020 Integrated Inspection Report 05000247/2019004 and 05000286/2019004 IR 05000003/20190012020-01-16016 January 2020 Entergy Nuclear Operations, Inc., Indian Point Nuclear Generating Station Unit 1 - NRC Inspection Report No. 05000003/2019001 IR 05000247/20190122020-01-0909 January 2020 Temporary Instruction 2515/194 Inspection Report 05000247/2019012 and 05000286/2019012 IR 05000247/20194112020-01-0909 January 2020 Material Control and Accounting Program Inspection Report 05000247/2019411 and 05000286/2019411 (Cover Letter Only) IR 05000247/20194032019-11-0505 November 2019 Cyber Security Inspection Report 05000247/2019403 and 05000286/2019403 (Cover Letter Only) IR 05000247/20190032019-11-0404 November 2019 Integrated Inspection Report 05000247/2019003 and 05000286/2019003 IR 05000247/20194102019-10-0202 October 2019 Security Inspection Report 05000247/2019410 and 05000286/2019410 (Cover Letter Only) IR 05000247/20190102019-09-26026 September 2019 Biennial Problem Identification and Resolution Inspection Report 05000247/2019010 and 05000286/2019010 IR 05000247/20190052019-08-28028 August 2019 Updated Inspection Plan (Inspection Report 05000247/2019005 and 05000286/2019005) IR 05000247/20190022019-08-13013 August 2019 Integrated Inspection Report 05000247/2019002 and 05000286/2019002 IR 05000247/20190112019-07-0909 July 2019 Design Basis Assurance Inspection (Programs) Inspection Report 05000247/2019011 and 05000286/2019011 IR 05000247/20190012019-05-13013 May 2019 Integrated Inspection Report 05000247/2019001 and 05000286/2019001 ML19130A0422019-05-0808 May 2019 Information Request for the Cyber-Security Inspection, Notification to Perform Inspection 05000247/2019403 and 05000286/2019403 IR 05000247/20193012019-04-18018 April 2019 Initial Operator Licensing Examination Report 05000247/2019301 IR 05000247/20180062019-03-0404 March 2019 Annual Assessment Letter for Indian Point Energy Center, Units 2 and 3 (Reports 05000247/2018006 and 05000286/2018006) IR 05000247/20180042019-02-0707 February 2019 Integrated Inspection Report 05000247/2018004 and 05000286/2018004 IR 05000247/20180102019-01-15015 January 2019 Design Bases Assurance Inspection (Teams) Report 05000247/2018010 and 05000286/2018010 IR 05000247/20180022019-01-0909 January 2019 Errata for Indian Point Nuclear Generating - Integrated Inspection Report 05000247/2018002 and 05000286/2018002 2024-08-06
[Table view] Category:Letter
MONTHYEARML24240A1692024-09-18018 September 2024 Cy 2023 Summary of Decommissioning Trust Fund Status IR 05000003/20240022024-08-0606 August 2024 NRC Inspection Report 05000003/2024002, 05000247/2024002, 05000286/2024002 PNP 2024-030, Update Report for Holtec Decommissioning International Fleet Decommissioning Quality Assurance Program Rev. 3 and Palisades Transitioning Quality Assurance Plan, Rev 02024-08-0202 August 2024 Update Report for Holtec Decommissioning International Fleet Decommissioning Quality Assurance Program Rev. 3 and Palisades Transitioning Quality Assurance Plan, Rev 0 ML24171A0122024-06-18018 June 2024 Reply to a Notice of Violation EA-24-037 ML24156A1162024-06-0404 June 2024 Correction - Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations ML24151A6482024-06-0303 June 2024 Changes in Reactor Decommissioning Branch Project Management Assignments for Some Decommissioning Facilities IR 05000003/20240052024-05-21021 May 2024 And 3 - NRC Inspection Report Nos. 05000003/2024005, 05000247/2024005, 05000286/2024005, 07200051/2024001, and Notice of Violation ML24128A0632024-05-0707 May 2024 Submittal of 2023 Annual Radiological Environmental Operating Report L-24-009, HDI Annual Occupational Radiation Exposure Data Reports - 20232024-04-29029 April 2024 HDI Annual Occupational Radiation Exposure Data Reports - 2023 ML24116A2412024-04-25025 April 2024 Annual Environmental Protection Plan Report ML24114A2282024-04-23023 April 2024 Annual Radioactive Effluent Release Report L-24-007, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations – Holtec Decommissioning International, LLC (HDI)2024-03-29029 March 2024 Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations – Holtec Decommissioning International, LLC (HDI) ML24080A1722024-03-20020 March 2024 Reply to a Notice of Violation EA-2024-010 IR 05000003/20240012024-03-20020 March 2024 NRC Inspection Report Nos. 05000003/2024001, 05000247/2024001, and 05000286/2024001 (Cover Letter Only) ML24045A0882024-02-22022 February 2024 Correction to the Technical Specifications to Reflect Appropriate Pages Removed and Retained by Previous License Amendments ML24053A0642024-02-22022 February 2024 2023 Annual Fitness for Duty Program Performance Data Report and Fatigue Management Program Data Report IR 05000003/20230042024-02-22022 February 2024 NRC Inspection Report Nos. 05000003/2023004, 05000247/2023004, 05000286/2023004, and 07200051/2023004 and Notice of Violation ML24011A1982024-01-12012 January 2024 ISFSI, Notice of Organization Change for Site Vice President ML23342A1082024-01-0909 January 2024 – Independent Spent Fuel Storage Installation Security Inspection Plan ML23353A1742023-12-19019 December 2023 ISFSI, Emergency Plan, Revision 23-04 L-23-019, Proof of Financial Protection 10 CFR 140.152023-12-18018 December 2023 Proof of Financial Protection 10 CFR 140.15 ML23326A1322023-12-0505 December 2023 Issuance of Amendment No. 67, 300 & 276 to Implement the Independent Spent Fuel Storage Installation Only Emergency Plan ML23339A0442023-12-0505 December 2023 Issuance of Amendment No. 68, 301 and 277 Regarding Changes to Implement the Independent Spent Fuel Storage Installation Physical Security Plan ML23338A2262023-12-0404 December 2023 Signed Amendment No. 27 to Indemnity Agreement No. B-19 ML23356A0212023-12-0101 December 2023 American Nuclear Insurers, Secondary Financial Protection (SFP) Program ML23242A2772023-11-30030 November 2023 NRC Letter Issuance - IP LAR for Units 2 and 3 Renewed Facility Licenses and PDTS to Reflect Permanent Removal of Spent Fuel from SFPs ML23338A0482023-11-30030 November 2023 ISFSI, Report of Changes to Physical Security, Training and Qualification, Safeguards Contingency Plan, and ISFSI Security Program, Revision 28 ML22339A1572023-11-27027 November 2023 Letter - Indian Point - Ea/Fonsi Request for Exemptions from Certain Emergency Planning Requirements for 10 CFR 50.47 and 10 CFR Part 50, Appendix E IR 05000003/20230032023-11-21021 November 2023 NRC Inspection Report Nos. 05000003/2023003, 05000247/2023003, 05000286/2023003, and 07200051/2023003 ML23100A1252023-11-17017 November 2023 Letter and Enclosure 1 - Issuance Indian Point Energy Center Units 1, 2, and 3 Exemption for Offsite Primary and Secondary Liability Insurance Indemnity Agreement ML23100A1172023-11-17017 November 2023 NRC Response - Indian Point Energy Center Generating Units 1, 2, and 3 Letter with Enclosures Regarding Changes to Remove the Cyber Security Plan License Condition ML23050A0032023-11-17017 November 2023 Letter - Issuance Indian Point Unit 2 License Amendment Request to Modify Tech Specs for Staffing Requirements Following Spent Fuel Transfer to Dry Storage ML23100A1432023-11-16016 November 2023 Letter - Issuance Indian Point Energy Center Generating Units 1, 2, and 3 Exemption Concerning Onsite Property Damage Insurance (Docket Nos. 50-003, 50-247, 50-286) L-23-012, Master Decommissioning Trust Agreement Changes for Indian Point Nuclear Generating Units 1, 2 and 3, Pilgrim Nuclear Power Station, Palisades Nuclear Plant and the Non-Qualified Trust for Big Rock Point2023-11-13013 November 2023 Master Decommissioning Trust Agreement Changes for Indian Point Nuclear Generating Units 1, 2 and 3, Pilgrim Nuclear Power Station, Palisades Nuclear Plant and the Non-Qualified Trust for Big Rock Point ML23064A0002023-11-13013 November 2023 NRC Issuance for Approval-Indian Point EC Units 1, 2 and 3 Emergency Plan and Emergency Action Level Scheme Amendments ML23306A0992023-11-0202 November 2023 And Indian Point Energy Center, Notification of Changes in Schedule in Accordance with 10 CFR 50.82(a)(7) ML23063A1432023-11-0101 November 2023 Letter - Issuance Holtec Request for Indian Point Energy Center Generating Units 1, 2, and 3 Exemptions from Certain Emergency Planning Requirements of 10 CFR 50.47 and Part 50 ML23292A0262023-10-19019 October 2023 LTR-23-0211-RI Thomas Congdon, Executive Deputy, Department of Public Service, Chair, Indian Point Decommissioning Oversight Board, Letter Independent Spent Fuel Storage Installation Inspection and Office of the Inspector General Report-RI ML23289A1582023-10-16016 October 2023 Decommissioning International - Registration of Spent Fuel Casks and Notification of Permanent Removal of All Indian Point Unit 3 Spent Fuel Assemblies from the Spent Fuel Pit ML23270A0082023-09-27027 September 2023 Registration of Spent Fuel Casks ML23237A5712023-09-22022 September 2023 09-22-2023 Letter to Dwaine Perry, Chief, Ramapo Munsee Nation, from Chair Hanson, Responds to Letter Regarding Opposition of the Release and Dumping of Radioactive Waste from Indian Point Nuclear Power Plant Into the Hudson River ML23242A2182023-09-12012 September 2023 IPEC – NRC Response to the Town of New Windsor, Ny Board Certified Motion Letter Regarding Treated Water Release from IP Site (Dockets 50-003, 50-247, 50-286) ML23250A0812023-09-0707 September 2023 Registration of Spent Fuel Casks ML23255A0142023-08-31031 August 2023 LTR-23-0211 Thomas Congdon, Executive Deputy, Department of Public Service, Chair, Indian Point Decommissioning Oversight Board, Letter Independent Spent Fuel Storage Installation Inspection and Office of the Inspector General Report IR 05000003/20230022023-08-22022 August 2023 NRC Inspection Report 05000003/2023002, 05000247/2023002, 05000286/2023002, and 07200051/2023002 ML23227A1852023-08-15015 August 2023 Request for a Revised Approval Date Regarding the Indian Point Energy Center Permanently Defueled Emergency Plan and Emergency Action Level Scheme ML23222A1442023-08-10010 August 2023 Registration of Spent Fuel Casks ML23208A1642023-07-26026 July 2023 Village of Croton-on-Hudson New York Letter Dated 7-26-23 Re Holtec Wastewater ML23200A0422023-07-19019 July 2023 Registration of Spent Fuel Casks ML23235A0602023-07-17017 July 2023 LTR-23-0194 Dwaine Perry, Chief, Ramapo Munsee Nation, Ltr Opposition of the Release and Dumping of Radioactive Waste from Indian Point Nuclear Power Plant Into the Hudson River 2024-09-18
[Table view] |
Text
March 3, 2020
SUBJECT:
ANNUAL ASSESSMENT LETTER FOR INDIAN POINT ENERGY CENTER, UNITS 2 AND 3 (REPORTS 05000247/2019006 AND 05000286/2019006)
Dear Mr. Vitale:
The U.S. Nuclear Regulatory Commission (NRC) has completed its end-of-cycle performance assessment of Indian Point Energy Center, Units 2 and 3, reviewing performance indicators (PIs), inspection results, and enforcement actions from January 1, 2019, through December 31, 2019. This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility. The NRC concluded that overall performance at your facility preserved public health and safety.
The NRC determined the performance at Indian Point Energy Center, Units 2 and 3 during the most recent quarter was within the Licensee Response Column (Column 1) of the NRCs Reactor Oversight Process (ROP) Action Matrix in Inspection Manual Chapter (IMC) 0305, Operating Reactor Assessment Program, because all inspection findings had very low safety significance (i.e., Green), and all PIs were within the expected range (i.e., Green). Therefore, the NRC plans to conduct ROP baseline inspections at Indian Point Energy Center, Units 2 and 3.
The enclosed inspection plan lists the inspections scheduled through December 31, 2021. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. In addition to the baseline inspections, the NRC will conduct Inspection Procedure 60855.1, Operation of an Independent Spent Fuel Storage Facility (ISFSI) at Operating Plants, and Inspection Procedure 92702, Follow-up on Traditional Enforcement Actions Including Violations, Deviations, Confirmatory Action Letters, Confirmatory Orders, and Alternative Dispute Resolution Confirmatory Orders.
Additionally, during this period the NRC will schedule an additional inspection per a revised version of Temporary Instruction (TI) 2515/194, Inspection of the Licensees Implementation of Industry Initiative Associated with the Open Phase Condition Design Vulnerability in Electrical Power Systems (NRC Bulletin 2012-01), for any sites who elect to implement the guidance of the Industry Initiative on Open Phase Condition, Revision 3 (ADAMS Accession No.
ML19163A176). Licensees will be individually notified when the NRC schedules these inspections. You should be aware that the agency is pursuing potential changes to the ROP, including changes to engineering inspections (SECY-18-0113, Recommendations for Modifying the Reactor Oversight Process Engineering Inspections) and other changes to the baseline inspection program described in SECY-19-0067, Recommendations for Enhancing the Reactor Oversight Process. Should these changes to the ROP be implemented, the engineering and other region-based inspections are subject to change in scope, as well as schedule.
Furthermore, all the inspections listed during the last twelve months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes.
Additionally, in a letter (ADAMS Accession No. ML17044A004) dated February 8, 2017, pursuant to Title 10 of the Code of Federal Regulations (10 CFR) 50.82(a)(1)(i), you notified the NRC of your intent to permanently cease power operations at Indian Point Energy Center, Units 2 and 3. Unit 2 will shut down by April 30, 2020, and Unit 3 will shut down by April 30, 2021. Therefore, the inspection schedule is tentative and may be revised. Once you formally notify the NRC in accordance with 10 CFR 50.82(a)(1)(ii) that either Unit 2 or Unit 3 is permanently shutdown and that all the nuclear fuel has been removed from the reactor vessel, then that unit will transition from NRC IMC 0305, Operating Reactor Assessment Program, and IMC 2515, Light-Water Reactor Inspection Program - Operations Phase, to IMC 2561, Decommissioning Power Reactor Inspection Program. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes.
Finally, the ROP and Inspection Program provides inherent flexibility to permit inspection sampling adjustments using IMC 2515, Appendix G, Baseline Inspection Guidance for Power Reactors Preparing for Transition to Decommissioning Phase. These adjustments are be made in order to better inform our assessment of performance during this unique period of operations prior to permanent plant shutdown. In addition, the NRC has implemented quarterly assessment reviews, consistent with the guidance contained in IMC 0305, Operating Reactor Assessment Program, in order to more closely monitor and review overall plant activities to assure that there are no issues emerging that might indicate a decline in focus on the safe operation of the facility. This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding.
Please contact me at 610-337-5262 with any questions you have regarding this letter.
Sincerely, X /RA/
Signed by: Daniel L. Schroeder Daniel L. Schroeder, Chief Reactor Projects Branch 2 Division of Reactor Projects Docket Nos. 50-247 and 50-286 License Nos. DPR-26 and DPR-64 Enclosure:
Inspection Plan cc w/ encl: Distribution via LISTSERV
ML20059M205 Non-Sensitive Publicly Available SUNSI Review Sensitive Non-Publicly Available OFFICE RI/DRP/SRI RI/DRP/SPE RI/DRP/BC NAME BHaagensen MDraxton DSchroeder DATE 2/26/2020 3/2/20 3/3/20
IP 22 Inspection Activity Plan Report Indian Point 01/01/2020 - 12/31/2021 Unit Start End Activity CAC Title Staff Count 71124.03 In-Plant Airborne Radioactivity Control and Mitigation & 71124.05 Radiation Monitoring Instrumentation 2 2, 3 03/02/2020 03/06/2020 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation 2, 3 03/02/2020 03/06/2020 IP 71124.05 000729 Radiation Monitoring Instrumentation 71124.01 Radiological Hazard Assessment and Exposure Controls 1 2, 3 05/11/2020 05/15/2020 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls Design Basis Assurance Inspection - Programs - Power Operated Valves - Indian Point Units and 3 3 2, 3 06/08/2020 06/12/2020 IP 71111.21N.02 001645 Design-Basis Capability of Power-Operated Valves Under 10 CFR 50.55a Requirements 2, 3 06/15/2020 06/19/2020 IP 71111.21N.02 001645 Design-Basis Capability of Power-Operated Valves Under 10 CFR 50.55a Requirements 2, 3 06/22/2020 06/26/2020 IP 71111.21N.02 001645 Design-Basis Capability of Power-Operated Valves Under 10 CFR 50.55a Requirements 71124.01 Radiological Hazard Assessment and Exposure Controls 1 2, 3 07/20/2020 07/24/2020 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls Access Control, Protective Strategy, TSR-IP 4 2, 3 10/19/2020 10/23/2020 IP 71130.02 000734 Access Control 2, 3 10/19/2020 10/23/2020 IP 71130.05 000737 Protective Strategy Evaluation 2, 3 10/19/2020 10/23/2020 IP 71130.09 001656 Security Plan Changes 2, 3 10/19/2020 10/23/2020 IP 71130.14 000743 Review of Power Reactor Target Sets 2, 3 10/19/2020 10/23/2020 IP 71151 001338 Performance Indicator Verification 71151 Performance Indicator Verification OR01 & PR01 1 2, 3 10/19/2020 10/23/2020 IP 71151 000746 Performance Indicator Verification 50.59 INSPECTION 3 2, 3 10/26/2020 10/30/2020 IP 71111.17T 000709 Evaluations of Changes, Tests, and Experiments EP EXERCISE INSPECTION - INDIAN POINT 5 2, 3 11/16/2020 11/20/2020 IP 71114.01 000716 Exercise Evaluation 2, 3 11/16/2020 11/20/2020 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes 2, 3 11/16/2020 11/20/2020 IP 71151 001397 Performance Indicator Verification BIENNIAL HEAT SINK 1 2, 3 01/31/2021 02/06/2021 IP 71111.21N 000714 Design Bases Assurance Inspection (Programs)
This report does not include INPO and OUTAGE activities. Page 1 of 2 This report shows only on-site and announced inspection procedures.
2/25/2020 12:37:08 PM Enclosure
IP 22 Inspection Activity Plan Report Indian Point 01/01/2020 - 12/31/2021 Unit Start End Activity CAC Title Staff Count 71124.04 Occupational Dose Assessment 1 2, 3 03/01/2021 03/05/2021 IP 71124.04 000728 Occupational Dose Assessment ISFSI Operational Inspection - IP 2 2, 3 03/29/2021 04/02/2021 IP 60855.1 000590 Operation of an Independent Spent Fuel Storage Installation at Operating Plants Radiological Hazard Assessment and Exposure Controls 71124.01 1 2, 3 05/10/2021 05/14/2021 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls EP Program Inspection - Indian Point (Decom) 1 2, 3 07/12/2021 07/16/2021 IP 71114.02 000717 Alert and Notification System Testing 2, 3 07/12/2021 07/16/2021 IP 71114.03 000718 Emergency Response Organization Staffing and Augmentation System 2, 3 07/12/2021 07/16/2021 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes 2, 3 07/12/2021 07/16/2021 IP 71114.05 000720 Maintenance of Emergency Preparedness 2, 3 07/12/2021 07/16/2021 IP 71114.06 000721 Drill Evaluation PI&R BIENNIAL - IP 4 2, 3 07/12/2021 07/16/2021 IP 71152B 000747 Problem Identification and Resolution 2, 3 07/26/2021 07/30/2021 IP 71152B 000747 Problem Identification and Resolution FORCE-ON-FORCE PLANNING AND EXERCISE WEEKS - IP 6 2, 3 09/13/2021 09/17/2021 IP 71130.03 000735 Contingency Response - Force-On-Force Testing 2, 3 10/04/2021 10/08/2021 IP 71130.03 000735 Contingency Response - Force-On-Force Testing 71124.08 Radwaste, 71124.02 ALARA, and 71151 Performance Indicator Verification 1 3 10/18/2021 10/22/2021 IP 71124.02 000726 Occupational ALARA Planning and Controls 3 10/18/2021 10/22/2021 IP 71124.08 000732 Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation 3 10/18/2021 10/22/2021 IP 71151 000746 Performance Indicator Verification Access Control, Equipment Testing and Maintenance 2 2, 3 11/01/2021 11/05/2021 IP 81200.02 000025 Access Control for Decommissioning Nuclear Power Reactors 2, 3 11/01/2021 11/05/2021 IP 81200.04 000026 Equipment Performance, Testing, and Maintenance for Decommissioning Nuclear Power Reactors This report does not include INPO and OUTAGE activities. Page 2 of 2 This report shows only on-site and announced inspection procedures.
2/25/2020 12:37:08 PM