Letter Sequence RAI |
---|
|
|
MONTHYEARML20094N9281995-11-20020 November 1995 Forwards 91C2687.A46, USNRC USI A-46 Resolution Seismic Evaluation Rept Monticello Nuclear Generating Plant, in Response to Suppl 1 to GL 87-02 Project stage: Other ML20100J1101996-02-19019 February 1996 Supplemental Response to Suppl 1 to GL 87-02, Verification of Seismic Adequacy of Mechanical & Electrical Equipment in Operating Reactors,Unresolved Safety Issue USI A-46 Project stage: Supplement ML20134C3391997-01-29029 January 1997 Forwards RAI Re 951120 Summary Rept,In Response to USI A-46 Project stage: RAI ML20138G0431997-04-29029 April 1997 Forwards Response to 970129 RAI Re Resolution of Unresolved Safety Issue A-46.Samples of Anchorage Calculations Done W/Anchor Program,Also Encl Project stage: Other ML20138F6751997-04-29029 April 1997 Provides Update on Status of Response to GL 87-02,Suppl 1 Project stage: Other ML0312007011997-10-0808 October 1997 Withdrawn NRC Generic Letter 1991-018, Revision 1: Information to Licensees Regarding NRC Inspection Manual Section on Resolution of Degraded and Nonconforming Conditions Project stage: Request ML20217G7321997-10-0808 October 1997 Forwards RAI Re Licensee 970426 Submittal Re USI A-46 Seismic Evaluation Rept Project stage: RAI ML20199C8981997-11-12012 November 1997 Forwards Rev to Staff Request for Addl Info Related to Unresolved Safety Issues A-46 Seismic Evaluation Rept.Rev Adds Three Addl Questions & Extends Response Date to 980115 from 971219 Project stage: RAI ML20197H3531997-12-17017 December 1997 Informs of Plans to Respond to Majority of 971112 RAI Questions by 980115 Re USI A-46.Addl Time Is Requested to Respond to Questions 6,7 & 8.NSP Would Like to Withhold Response Until Industry Position Is Determined Project stage: Other ML20199G9801998-01-15015 January 1998 Provides Response to Question 6 in 971008 & 1112 RAIs on Resolution of USI A-46,seismic Evaluation Rept.Responses to Questions 7 & 8 Will Be Submitted by 980215 Project stage: Other ML20203C2431998-02-11011 February 1998 Provides Response to Questions 7 & 8 in 971008 & 1112 RAIs on Resolution of USI A-46,seismic Evaluation Rept Project stage: Other ML20197A9001998-02-27027 February 1998 Forwards RAI Re USI A-46, Seismic Evaluation Rept. Response Requested by 980508 Project stage: RAI ML20247M1721998-05-15015 May 1998 Provides Response to Request for Addl Info on Resolution of Unresolved Safety Issue A-46.Submittal Contains No New NRC Commitments & Does Not Modify Any Prior Commitments Project stage: Request 1997-12-17
[Table View] |
|
---|
Category:CORRESPONDENCE-LETTERS
MONTHYEARML20217M3801999-10-21021 October 1999 Forwards Insp Rept 50-263/99-06 on 990813-0923.Four Violations of NRC Requirements Identified & Being Treated as non-cited Violations Consistent with App C of Enforcement Policy ML20217G0711999-10-13013 October 1999 Forwards Insp Rept 50-263/99-12 on 990913-17.No Violations Noted ML20216J2491999-09-30030 September 1999 Ack Receipt of 980804,990626 & 0720 Ltrs in Response to GL 98-01,suppl 1, Year 2000 Readiness of Computer Sys at Npps. Staff Review Has Concluded That All Requested Info Has Been Provided ML20217B1421999-09-30030 September 1999 Informs That on 990902,NRC Staff Completed mid-cicle Plant Performance Review of Monticello Nuclear Generating Station. Staff Conducted Reviews for All Operating NPPs to Integrate Performance Information & to Plan for Insp Activities ML20212K9131999-09-30030 September 1999 Refers to 990920 Meeting Conducted at Monticello Nuclear Generating Station to Discuss Initiatives in Risk Area & to Establish Dialog Between SRAs & PRA ML20216J8091999-09-24024 September 1999 Informs That New Diaphragm Matl Has Corrected Sticking Problem Associated with Increased Control Rod Drive Scram Times.Augmented Testing of Valves at Monticello Has Been Discontinued ML20216G4341999-09-24024 September 1999 Forwards Exam Rept 50-263/99-301 on 990823-26.Violation Occurred & Being Treated as Ncv,Consistent with App C of Enforcement Policy.Test Was Administered to Two Applicants. Both Applicants Passed All Sections of Exam ML20212G7171999-09-24024 September 1999 Submits Semiannual Status Update on Project Plans for USAR Review Project & Conversion to Its.Conversion Package Submittal Continues to Be Targeted for Aug of 2000 ML20212G9801999-09-23023 September 1999 Refers to Resolution of Unresolved Items Identified Re Security Alarm Station Operations at Both Monitcello & Prairie Island ML20212F0901999-09-21021 September 1999 Confirms Discussion Between M Hammer & Rd Lanksbury to Have Routine Mgt Meeting on 991005 in Lisle,Il.Purpose of Meeting to Discuss Improvement Initiatives in Areas of Operations & Equipment Reliability ML20212A9761999-09-0909 September 1999 Submits 1999 Annual Rept of Any Changes or Errors Identified in ECCS Analytical Models or Applications ML20217A5751999-09-0909 September 1999 Forwards Individual Exam Results for Licensee Applicants Who Took Aug 1999 Initial License Exam.Without Encls ML20211Q6981999-09-0606 September 1999 Informs That NRC Tentatively Scheduled Initial Licensing Exam for Monticello Operator License Applicants During Wks of 010604 & 11.Validation of Exam Will Occur at Station During Wk of 010514 ML20211L1981999-09-0101 September 1999 Forwards Insp Rept 50-263/99-05 on 990702-0812.No Violations Noted ML20211K7971999-09-0101 September 1999 Informs That Util Reviewed Rvid as Requested in NRC .Recommended Corrections Are Listed ML20211K2591999-08-27027 August 1999 Forwards NSP Co Fitness for Duty Program Performance Data for Six Month Period Ending 990630 ML20211F9961999-08-26026 August 1999 Forwards Effluent & Waste Disposal Semi-Annual Rept for 990101-990630, Revised Effluent & Waste Disposal Semi-Annual Rept for 980701-981231 & Revs to ODCM for Monitcello Nuclear Generating Plant ML20211C9501999-08-23023 August 1999 Forwards Rev 17 to Monticello Nuclear Generating Plant USAR, Updating Info in USAR to Reflect Implementation of Increase in Licensed Core Thermal Power from 1,670 Mwt to 1,775 Mwt.Rept of Changes,Tests & Experiments Not Included ML20210U1831999-08-12012 August 1999 Revises 980202 Commitment Re GL 96-06, Assurance of Equipment Operability & Containment Integrity During Design- Basis Accident Conditions ML20210T9601999-08-12012 August 1999 Provides Rept on Status of Util RPV Feedwater Nozzle Insps Performed in Response to USI A-10 Re BWR Nozzle Cracking ML20210Q0341999-08-0404 August 1999 Forwards SE Granting Licensee 980724 Relief Request 10 Re Third 10-year Interval ISI Program Plan,Entitled, Limited Exam ML20210H0861999-07-28028 July 1999 Forwards Insp Rept 50-263/99-04 on 990521-0701.No Violations Noted.Licensee Conduct at Monticello Facility Characterized by safety-conscious Operations,Sound Engineering & Maint Practices & Appropriate Radiological Controls ML18107A7051999-07-20020 July 1999 Provides Suppl Info Which Supersedes Info in 990625 Ltr in Response to NRC RAI Re GL 98-01, Y2K Readiness of Computer Sys at Nuclear Power Plants. ML20212H3191999-07-16016 July 1999 Forwards Aug 1999 Monticello RO Exam Package,Including Revised Outlines.All Changes Are in Blue Font ML20209G5621999-07-14014 July 1999 Forwards Insp Rept 50-263/99-11 on 990621-24.No Violations Noted.Objective of Insp,To Determine Whether Monticello Nuclear Generating Station Emergency Plan Adequate & If Station Personnel Properly Implemented Emergency Plan ML20196J5351999-07-0202 July 1999 Discusses GL 92-01,Rev 1,Supp 1, Rv Integrity, Issued by NRC on 950515 & NSP Responses & 980917 for Monticello Npp.Informs That Staff Revised Info in Rvid & Released Info as Rvid Version 2 ML20196J9681999-07-0101 July 1999 Informs That in Sept 1998,Region III Received Rev 20 to Portions of Util Emergency Plan Under 10CFR50.54(q).Based on Determination That Changes Do Not Decrease Effectiveness of Licensee Emergency Plan,No NRC Approval Required ML20209B6151999-06-25025 June 1999 Responds to NRC Request for Info Re Y2K Readiness at Nuclear Power Plants.Gl 98-01 Requested Response on Status of Facility Y2K Readiness by 990701.Y2K Readiness Disclosure Attached ML20196H2291999-06-24024 June 1999 Responds to Administrative Ltr 99-02,dtd 990603,requesting Licensee to Provide Estimate of Licensing Action Submittals Anticipated.Four New Submittals Per Year Are Anticipated ML20207D5851999-05-25025 May 1999 Submits Info Re Partial Fulfillment of License Conditions Placed on Amend 101,which Approved Use of Ten Exceptions for 24 Months Subject to Listed App C Conditions.Util Will Submit Second Rept to Obtain Approval for Continued Use ML20206S0911999-05-17017 May 1999 Forwards Response to NRC 990324 RAI Re Proposed Amend to pressure-temp Limits & Surveillance Capsule Withdrawal Schedule, .Supporting Calculations Also Encl ML20206N5601999-05-13013 May 1999 Informs That NRC Office of Nuclear Reactor Regulation Reorganized Effective 990328.As Part of Reorganization,Div of Licensing Project Mgt Created.Cm Craig Will Be Section Chief for Monticello Npp.Organization Chart Encl ML20206G2181999-05-0505 May 1999 Discusses Completion of Licensing Action for GL 96-01, Testing of Safety-Related Logic Circuits, Dtd 960110,for Plant ML20206G4901999-05-0404 May 1999 Forwards Staff Review of Licensee 960508 Response to NRC Bulletin 96-002, Movement of Heavy Loads Over Sf,Over Fuel in Rc or Over Safety-Related Equipment, .Overall, Responses Acceptable.Tac M95610 Closed ML20206G7741999-05-0303 May 1999 Forwards Insp Rept 50-263/99-02 on 990223-0408.One Violation Occurred & Being Treated as non-cited Violation,Consistent with App C of Enforcement Policy ML20206D1651999-04-27027 April 1999 Forwards Radiation Environ Monitoring Program for MNGP for Jan-Dec 1998, Per Plant TS 6.7.C.1.Ltr Contains No New NRC Commitments or Modifies Any Prior Commitments ML20205N0821999-04-12012 April 1999 Forwards SE of NSP Response to NRC GL 95-07, Pressure Locking & Thermal Binding of Safety-Related Power-Operated Gate Valves. Licensee Adequately Addressed Actions Requested in GL ML20205N4811999-04-0909 April 1999 Forwards Licensing Requalification Insp Rept 50-263/99-10 on 990308-12.No Violations Noted.However,Inspectors Through Observation of Simulator Scenario Exams Noted Difficulties in Ability of SM to Simultaneously Implement Duties of SM ML20205N5301999-04-0909 April 1999 Discusses Arrangements Made on 990406 for Administration of Licensing Exams at Monticello Nuclear Generating Station During Wk of 990823.Requests That Exam Outlines Be Submitted by 990128 & Supporting Ref Matls by 990719 ML20196K7831999-03-31031 March 1999 Forwards Decommissioning Funding Status Rept for Monticello & Prairie Island Nuclear Generating Plants,Per Requirements of 10CFR50.75(f)(1) ML20205H5731999-03-29029 March 1999 Submits Required 1998 Actual & 1999 Projected Cash Flow Statements for Monticello Nuclear Generating Plant & PINGP, Units 1 & 2.Encl Contains Proprietary Info.Proprietary Info Withheld,Per 10CFR2.790(b)(1) ML20205C4851999-03-26026 March 1999 Informs That on 990203,NRC Staff Completed PPR of Nuclear Plant.Staff Conducts Reviews for All Operating NPPs to Develop an Integrated Understanding of Safety Performance ML20205C6561999-03-26026 March 1999 Submits Semiannual Update on Project Plans for USAR Review Project & Conversion to ITS ML20205A5881999-03-24024 March 1999 Forwards Request for Addl Info Re Submittal Requesting Rev of pressure-temperature Limits & Surveillance Capsule Withdrawal Schedule ML20204H4711999-03-18018 March 1999 Forwards SER Concluding That Util Established Acceptable Program to Verify Periodically design-basis Capability of safety-related MOVs at Monticello & Adequately Addressed Actions Requested in GL 96-05 ML20207H5161999-03-11011 March 1999 Forwards Insp Rept 50-263/99-01 on 990112-0222.No Violations Noted ML20207F4091999-02-28028 February 1999 Forwards Fitness for Duty Program Performance Data for Six Month Period from 980701-981231,IAW 10CFR26.71 ML20207F6741999-02-24024 February 1999 Forwards Summary of Nuclear Property Insurance Maintained at Monticello & Prairie Island Nuclear Generating Plants ML20207F6901999-02-23023 February 1999 Forwards Effluent & Waste Disposal Semi-Annual Rept for 980701-981231, Off-Site Radiation Dose Assessment for 980101-981231 & Revised Effluent & Waste Disposal Semi- Annual Rept for 980101-980630, for Monticello ML20203F2541999-02-10010 February 1999 Informs That Beginning 990216,DE Hills Will Be Chief of Operations Branch Which Includes Operator Licensing Function 1999-09-09
[Table view] Category:OUTGOING CORRESPONDENCE
MONTHYEARML20217M3801999-10-21021 October 1999 Forwards Insp Rept 50-263/99-06 on 990813-0923.Four Violations of NRC Requirements Identified & Being Treated as non-cited Violations Consistent with App C of Enforcement Policy ML20217G0711999-10-13013 October 1999 Forwards Insp Rept 50-263/99-12 on 990913-17.No Violations Noted ML20216J2491999-09-30030 September 1999 Ack Receipt of 980804,990626 & 0720 Ltrs in Response to GL 98-01,suppl 1, Year 2000 Readiness of Computer Sys at Npps. Staff Review Has Concluded That All Requested Info Has Been Provided ML20217B1421999-09-30030 September 1999 Informs That on 990902,NRC Staff Completed mid-cicle Plant Performance Review of Monticello Nuclear Generating Station. Staff Conducted Reviews for All Operating NPPs to Integrate Performance Information & to Plan for Insp Activities ML20212K9131999-09-30030 September 1999 Refers to 990920 Meeting Conducted at Monticello Nuclear Generating Station to Discuss Initiatives in Risk Area & to Establish Dialog Between SRAs & PRA ML20216G4341999-09-24024 September 1999 Forwards Exam Rept 50-263/99-301 on 990823-26.Violation Occurred & Being Treated as Ncv,Consistent with App C of Enforcement Policy.Test Was Administered to Two Applicants. Both Applicants Passed All Sections of Exam ML20212G9801999-09-23023 September 1999 Refers to Resolution of Unresolved Items Identified Re Security Alarm Station Operations at Both Monitcello & Prairie Island ML20212F0901999-09-21021 September 1999 Confirms Discussion Between M Hammer & Rd Lanksbury to Have Routine Mgt Meeting on 991005 in Lisle,Il.Purpose of Meeting to Discuss Improvement Initiatives in Areas of Operations & Equipment Reliability ML20217A5751999-09-0909 September 1999 Forwards Individual Exam Results for Licensee Applicants Who Took Aug 1999 Initial License Exam.Without Encls ML20211Q6981999-09-0606 September 1999 Informs That NRC Tentatively Scheduled Initial Licensing Exam for Monticello Operator License Applicants During Wks of 010604 & 11.Validation of Exam Will Occur at Station During Wk of 010514 ML20211L1981999-09-0101 September 1999 Forwards Insp Rept 50-263/99-05 on 990702-0812.No Violations Noted ML20210Q0341999-08-0404 August 1999 Forwards SE Granting Licensee 980724 Relief Request 10 Re Third 10-year Interval ISI Program Plan,Entitled, Limited Exam ML20210H0861999-07-28028 July 1999 Forwards Insp Rept 50-263/99-04 on 990521-0701.No Violations Noted.Licensee Conduct at Monticello Facility Characterized by safety-conscious Operations,Sound Engineering & Maint Practices & Appropriate Radiological Controls ML20209G5621999-07-14014 July 1999 Forwards Insp Rept 50-263/99-11 on 990621-24.No Violations Noted.Objective of Insp,To Determine Whether Monticello Nuclear Generating Station Emergency Plan Adequate & If Station Personnel Properly Implemented Emergency Plan ML20196J5351999-07-0202 July 1999 Discusses GL 92-01,Rev 1,Supp 1, Rv Integrity, Issued by NRC on 950515 & NSP Responses & 980917 for Monticello Npp.Informs That Staff Revised Info in Rvid & Released Info as Rvid Version 2 ML20196J9681999-07-0101 July 1999 Informs That in Sept 1998,Region III Received Rev 20 to Portions of Util Emergency Plan Under 10CFR50.54(q).Based on Determination That Changes Do Not Decrease Effectiveness of Licensee Emergency Plan,No NRC Approval Required ML20206N5601999-05-13013 May 1999 Informs That NRC Office of Nuclear Reactor Regulation Reorganized Effective 990328.As Part of Reorganization,Div of Licensing Project Mgt Created.Cm Craig Will Be Section Chief for Monticello Npp.Organization Chart Encl ML20206G2181999-05-0505 May 1999 Discusses Completion of Licensing Action for GL 96-01, Testing of Safety-Related Logic Circuits, Dtd 960110,for Plant ML20206G4901999-05-0404 May 1999 Forwards Staff Review of Licensee 960508 Response to NRC Bulletin 96-002, Movement of Heavy Loads Over Sf,Over Fuel in Rc or Over Safety-Related Equipment, .Overall, Responses Acceptable.Tac M95610 Closed ML20206G7741999-05-0303 May 1999 Forwards Insp Rept 50-263/99-02 on 990223-0408.One Violation Occurred & Being Treated as non-cited Violation,Consistent with App C of Enforcement Policy ML20205N0821999-04-12012 April 1999 Forwards SE of NSP Response to NRC GL 95-07, Pressure Locking & Thermal Binding of Safety-Related Power-Operated Gate Valves. Licensee Adequately Addressed Actions Requested in GL ML20205N4811999-04-0909 April 1999 Forwards Licensing Requalification Insp Rept 50-263/99-10 on 990308-12.No Violations Noted.However,Inspectors Through Observation of Simulator Scenario Exams Noted Difficulties in Ability of SM to Simultaneously Implement Duties of SM ML20205N5301999-04-0909 April 1999 Discusses Arrangements Made on 990406 for Administration of Licensing Exams at Monticello Nuclear Generating Station During Wk of 990823.Requests That Exam Outlines Be Submitted by 990128 & Supporting Ref Matls by 990719 ML20205C4851999-03-26026 March 1999 Informs That on 990203,NRC Staff Completed PPR of Nuclear Plant.Staff Conducts Reviews for All Operating NPPs to Develop an Integrated Understanding of Safety Performance ML20205A5881999-03-24024 March 1999 Forwards Request for Addl Info Re Submittal Requesting Rev of pressure-temperature Limits & Surveillance Capsule Withdrawal Schedule ML20204H4711999-03-18018 March 1999 Forwards SER Concluding That Util Established Acceptable Program to Verify Periodically design-basis Capability of safety-related MOVs at Monticello & Adequately Addressed Actions Requested in GL 96-05 ML20207H5161999-03-11011 March 1999 Forwards Insp Rept 50-263/99-01 on 990112-0222.No Violations Noted ML20203F2541999-02-10010 February 1999 Informs That Beginning 990216,DE Hills Will Be Chief of Operations Branch Which Includes Operator Licensing Function ML20202B7191999-01-26026 January 1999 Discusses 990125 Telcon with T Witschen & D Mcneil Re Arrangements for NRC to Inspect Licensed Operator Requalification Program at Monticello Nuclear Generating Station.Insp Planned for Week of 990308 ML20199H8321999-01-20020 January 1999 Forwards Insp Rept 50-263/98-18 on 981201-990111.No Violations Were Identified.Conduct of Activities at Monticello Facility Was Generally Characterized by safety- Conscious Operations & Sound Maint Practices ML20199G7721999-01-14014 January 1999 Forwards Request for Addl Info Re GL 88-20, Individual Plant Exam of External Events (IPEEE) for Severe Accident Vulnerabilities, Issued in June 1991 ML20206R8631999-01-12012 January 1999 Informs That Staff Has Prepared TS Interpretation of Requirements for Extending Surveillance Intervals at Plant,Per NRC Request ML20199E4791999-01-0606 January 1999 Forwards SER Accepting Licensee 951116,960214 & 0524 Responses to NRC Bulletin 95-002, Unexpected Clogging of Residual Heat Removal Pump Strainer While Operating in Suppression Pool Cooling Mode, for Monticello ML20206R8741999-01-0404 January 1999 Discusses Clarification of Understanding of Safety Evaluation Related to Deviation from Emergency Procedure Guidelines for Monticello.Staff Agrees with NSP Characterization & Resolution of Issues ML20198R2001998-12-30030 December 1998 Forwards Insp Rept 50-263/98-19 on 981214-18.No Violations Noted.Purpose of Insp Was to Review Plant Chemistry Program, PASS & REMP ML20198P0501998-12-28028 December 1998 Informs of Completion of Review of Relief Request 9 Re Third 10-year Interval ISI Program Plan,Entitled Use of High Alloy/High Nickel Calibr Block for Dissimilar Metal Welds. Supporting SE Encl ML20198G0761998-12-21021 December 1998 Acks Receipt of Notifying NRC That Commitment Noted in Is Complete Re Tornado Effects on Reactor Bldg Superstructure ML20198D0181998-12-15015 December 1998 Informs That as Part of PRA Implementation Plan,Commission Assigned Two SRAs to Each Regional Ofc.Sras Will Routinely Assess Licensee Event Repts,Plant Events,Insp Findings & EAs from Risk Perspective ML20198B7721998-12-14014 December 1998 Forwards Insp Rept 50-263/98-16 on 981014-1130 & Notice of Violation Re Fire Brigade Drill Participation ML20198D0641998-12-10010 December 1998 Forwards SE Accepting Licensee 971118 Request for Review & Approval of Deviation from BWROG Epg,Rev 4,NEDO-31331, March,1997.Deviation Will Permit Rev of Plant EOPs to Recognize 2/3 Core Height as Adequate for Core Cooling ML20196C2411998-11-24024 November 1998 Forwards Insp Rept 50-263/98-17 on 981026-30.No Violations Noted.Security Dept self-assessment Efforts Continue to Be Very Strong ML20196D5641998-11-20020 November 1998 Discusses 981104 Insp Resource Planning Meeting for Monticello & Advises of Planned Insp Effort for Next 6 Months at Plant.Info Provided to Min Resource Impacts on Staff & to Allow for Rescheduling Conflicts to Be Resolved ML20195J8811998-11-19019 November 1998 Informs That EOP Flow Charts C.5-1100 RPV Control, Rev 5 & C.5-1100... Rev 6 Marked Proprietary & Submitted as Attachments 3 & 4 to Util Will Be Withheld from Public Disclosure Per 10CFR2.790(b)(5) ML20196G6081998-11-19019 November 1998 Submits Correction to Which Advises Licensee That EOP Flow Charts, C.5-1100 RPV Control, Rev 5 & C.5-1100 RPV Control, Rev 6,marked Proprietary,Will Be Withheld from Public Disclosure.Ltr Reissued to Correct Date of Issuance ML20195E3321998-11-12012 November 1998 Forwards SE Concluding That Licensee Implementation Program to Resolve USI A-46 at Facility Has Adequately Addressed Purpose of 10CFR50.54(f) Request.Usi A-46 Program Was Established in Response to GL 87-02 ML20196D7291998-11-10010 November 1998 Forwards Insp Rept 50-263/98-15 on 980831-1014.No Violations Noted.Investigation Team Assembled by Station Mgt to Determine Root Cause of Offgas Sys Problem Was Thorough & Aggressive ML20154L2951998-10-0909 October 1998 Informs That Effective 981011,project Mgt Responsibility for Plant Will Be Transferred from Tj Kim to CF Lyon.Cf Lyon May Be Contacted at Listed Number ML20154F4971998-10-0606 October 1998 Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Rept 50-263/98-09 Issued on 980730 ML20154J2501998-10-0202 October 1998 Forwards Audit of Year 2000 Program at Monticello Nuclear Generating Plant on 980915-17 as Followup to NRC GL 98-01, Year 2000 Readiness of Computer Systems at Nuclear Power Plants, Issued on 980511 ML20153C4611998-09-21021 September 1998 Submits Comments on Draft Environ Impact Statement for Minnesota Lake Superior Coastal Program 1999-09-09
[Table view] |
Text
. . I Mr. Roger 0. Andsrson, Director "
Distribution '
Lice.nsing and Management Issues eDocketxFile RWessman Northern States Power Company PUBLIC GBagchi 414 Nicollet Mall PD3-1 Rdg. ACRS Minneapolis, MN 55401 JRoe JGrobe, RIII OGC BMcCabe EAdensam(EGA1) KManoly CWu i
SUBJECT:
MONTICELLO NUCLEAR GENERATING PLANT - REQUEST FOR ADDITIONAL INFORMATION ON THE RESOLUTION OF UNRESOLVED SAFETY ISSUE A-46 (TAC NO. M69460) i
Dear Mr. Anderson:
The staff has reviewed your Summary Report, dated November 20,1995, in response to the Unresolved Safety Issue A-46, and determined that additional !
information is necessary to complete its review. The enclosed request for additional information (RAI) provides details of the required material.
Please provide your response within 90 days of the date of this letter. If ;
you need additional time, or if you have any qu%tions, please contact me at (301) 415-1392.
Sincerely, Original signed by Tae Kim, Senior Project Manager Project Directorate III-1 Division of Reactor Projects III/IV Office of Nuclear Reactor Regulation Docket No: 50-263.
Enclosure:
As. stated cc w/ encl: See'next page DOCUMENT NAME: G:\WPDOCS\MONTICEL\ MON 69460.RAI To receive e copy of this document, indicate in the box: "C" = Copy without enclosures *E" = Copy with enclosures *N"
= No copy ,, i 0FFICE PD31:PM lE PD31:LA lE PD31:PD /'t '
l NAME TJKim -W//t. ' CJamerson Com+t JHannon
- DATE 1/zJ/97 V IMf/97 17)J4/97 I
0FFICIAL RECORD COPY g
- MC FR.E CENTER COPY 9701310381 970129 PDR ADOCK 05000263 P PDR I
- 44 p 4 UNITED STATES g j NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. maa =1
'+4 . . . . . ,d January 29, 1997 Mr. Roger 0. Anderson, Director Licensing and Management Issues Northern States Power Company 414 Nicollet Mall Minneapolis, MN 55401 l
SUBJECT:
MONTICELLO NUCLEAR GENERATING PLANT - REQUEST FOR ADDITIONAL INFORMATION ON THE RESOLUTION OF UNRESOLVED SAFETY ISSUE A-46 (TAC N0. M69460)
Dear Mr. Anderson:
The staff has reviewed your Summary Report, dated November 20,1995, in response to the Unresolved Safety Issue A-46, and determined that additional information is necessary to complete its review. The enclosed request for additional information (RAI) provides details of the required material.
Please provide your response within 90 days of the date of this letter. If you need additional time, or if you have any questions, please contact me at (301) 415-1392.
Sincerely, kg '
Tae Kim, Senior Project Manager i Project Directorate III-1 i Division of Reactor Projects III/IV .
Office of Nuclear Reactor Regulation i Docket No: 50-263 '
Enclosure:
As stated cc w/ enc 1: See next page
l l
Mr. Roger 0. Anderson, Director Monticello Nuclear Generating Plant Northern States Power Company i cc:
J. E. Silberg, Esquire Adonis A. Neblett Shaw, Pittman, Potts and Trowbridge Assistant Attorney General 2300 N Street, N. W. Office of the Attorney General Washington DC 20037 445 Minnesota Street Suite 900 U.S. Nuclear Regulatory Comission St. Paul, Minnesota 55101-2127 Resident Inspector's Offica 2807 W. County Road 75 Monticello, Minnesota 55362 Plant Manager Monticello Nuclear Generating Plant ATTN: Site Licensing Northern States Power Company 2807 West County Road 75 Monticello, Minnesota 55362-9637 Robert Nelson, President Minnesota Environmental Control Citizens Association (MECCA) 1051 South McKnight Road St. Paul, Minnesota 55119 Commissioner Minnesota Pollution Control Agency 520 Lafayette Road St. Paul, Minnesota 55119 Regional Administrator, Region III U.S. Nuclear Regulatory Commission 801 Warrenville Road Lisle, Illinois 60532-4351 Commissioner of Health Minnesota Department of Health 717 Delaware Street, S. E.
Minneapolis, Minnesota 55440 Darla Groshens, Auditor / Treasurer Wright County Government Center 10 NW Second Street Buffalo, Minnesota 55313 Kris Sanda, Commissioner Department of Public Service 121 Seventh Place East Suite 200 St. Paul, Minnesota 55101-2145 2muy ms
l
! REQUEST FOR ADDITIONAL INFORMATION l MONTICELLO NUCLEAR GENERATING PLANT.
- USI A-46 i
Reference:
Letter (and Attachments) from Northern States Power Company
! to USNRC, " Summary Report for Resolution of USI A-46,"
November 20, 1995.
- 1. With respect to Section 3.2, page 3-1, discuss the basis for defining l the seismic demand for equipment housed in buildings other than the l reactor and emergency filtration train (EFT) buildings as equivalent to
- the demand based on the response spectra generated for the reactor j building.
- 2. With respect to St.ction 3.2.1, page 3-2, explain in some detail as to how the original floor response spectrum (FRS) data were used to calculate response spectra for the additional oscillator damping.
- 3. Section 4, " Screening Verification and Walkdown," of GIP-2 under item
" Caveats" reads "In order to ...or the generic seismic testing GERS, the eauipment (underline added) should be similar (underline added) to the equipment in the earthquake experience equipment class or the generic seismic testing equipment class and..." However, Section 4.1.2, " Caveat Compliance" of the Monticello report (page 4-2) states that "the eauinment characteristics (underline added) are aenerally similar (underline added) to the earthquake experience equipment class."
Explain the basis for this apparent deviation from the specific caveat wording of GIP-2 and discuss in detail how the change in the specific wording of GIP-2 caveats impacted the final list of outliers. Also, provide a list of additional outliers which would have been identified if the wording in GIP-2 caveats was not changed.
- 4. Referring to Table 4-1, " Items Meeting Intent but Not Specific Wording of Caveats," each of the items listed in the table involve some degree of judgment or estimation by licensee personnel in concluding that the intent of applicable caveats was met. For each item listed in the '
table, provide a discussion of the bases for the judgment or estimation.
Also, provide the following additional information:
- a. For Control Cabinets C-19, C-289A, C-30, C-32 and C-33, provide a comparison to show that a through-bolt is equivalent to a cast in place bolt in meeting the intent of caveats.
- b. For Hydraulic Control Units CRD HCU E and W, provide the computation pertaining to the adequacy of fluid operated valves, the pneumatic controls (e.g., solenoid valves) and the overhead lines of the HCUs.
- c. For ECCS Area Drain Pumps, P-88A, B, C and D, discuss in detail how these vertical centrifugal drain pumps meet the intent of Class 6 caveats.
ENCLOSURE
l 6
l 2
- d. For relief valves RV-4236 and RV-4673 (each of which is mounted off j a 3/4" line), provide the calculation to show that the seismic
- stress is less than the allowable stress for the attached piping to ensure the seismic adequacy of the valve support.
! e. For Conduit in Area RB-A30 and Dampers Controllers TC-8089C and
{ TC-8089L in the diesel room, discuss in detail the tug test
! performed by the SRT, and provide the his for concluding the
- acceptability of the clamp supports and anchorage.
l 5. In reference to Section 4.1.3, the report states that anchorages were
- rigorously analyzed using hand calculation and ANCHOR software package.
i Provide samples of the anchorages engineering calculations. Also, j discuss a few cases of anchorage verification based on results of tug
- tests conducted and provide a description of the tests and the engineering justification for such an approach.
- 6. With respect to Section 4.3.2, " Comments About Anchorage," the last sentence of the second paragraph on page 4-7 reads: " Wall mounted equipment was not subject to a tightness check as allowed by the GIP because..." Identify the specific provision of the GIP-2 which allows such an exemption from performing the needed tightness check.
- 7. With respect to Section 4.3.2, third paragraph, discuss the extent of inspection implemented by a so-called " random ' spot' embedment check,"
and elaborate on the validity of the conclusion drawn from such a spot check with no identified installation problems.
- 8. Provide information regarding the seismic adequacy verification implemented under IE Bulletin 80-11 for a list of masonry block walls which were identified by the SRT to possess a II/I implication and a potential of collapsing on items listed in the SSEL.
- 9. Section 7.1.2 of GIP-2 specifies that a SQUG licensee perform a four-step engineering evaluation for verifying the seismic adequacy of tanks and heat exchangers according to guidelines provided in the section.
However, under Section 5.1 of the licensee's report, it is stated on page 5-1, that "the Seismic Capability Engineers performed the evaluation such that they meet the intent (underline added) of these guidelines..." Clarify whether the GIP-2 guidelines were always met, or identify any deviations from the guidelines where only the intent of the GIP-2 was satisfied.
- 10. With respect to the Diesel Oil Storage Tank (T-44) listed in Table 5-1, provide the rationale (supported by engineering analysis) for concluding that no large relative motion between the tank and the Pump iiouse will !
take place during the SSE.
- 11. With respect to Section 6.1, discuss in greater detail the basis for judging that conduit and cable tray supports in some inaccessible areas are acceptable and provide examples which led to such a conclusion.
4
! 3 f 12. Regarding Section 6.5, indicate why there were no rod hanger supports
! chosen for the Limited Analytical Review (LAR). Also, discuss the basis
! for selecting the cases shown on Table 6-2 and the rationale for judging that selection of 12 LAR cases is sufficiently adequate to represent the entire population of raceway and conduit supports.
l
! 13. Regarding Section 7, describe the approach which will be used to obtain the more realistic in-structure demand for the outlier pumps in the j intake structure.
- 14. In Table 8-1, only proposed outlier resolutions were included. Provide
! results of evaluations, tests, calculations and equipment modifications i and replacements used to resolve outliers, as required by Section 9 of j
the GIP-2. Also, provide the justification to ensure that the proposed
- schedule for resolving all the identified outliers or open items prior j to the end of 1998 refueling outage, does not lead to a potential safety significant scenario.
- 15. Referring to the Monticello Nuclear Generating Station A-46 Seismic
- Third Party Audit Report, the peer reviewers did not perform the walkdown of inaccessible areas due to radiological concerns including i the Primary Containment, the Reactor Water Cleanup Room and Main Steam j Tunnels. Discuss the general approach taken by the SRT in dealing with i items listed in the SSEL that are located in inaccessible areas, and the i rationale for concluding that the items are properly verified for their seismic adequacy.
- 16. Describe any corrective measures taken to address the peer reviewers comments as described in Appendix E of Attachment 1, for example, (1) Cabinet C-253A is about 1/4" away from cabinet Y-25 and may be an impact hazard, and (2) Cabinet C-27 contains a flexible RPIS Translation Electronics rack with circuit boards that could pop out under seismic ;
loads. The findings in these examples were not addressed in Table 7-1, Equipment Outliers.
- 17. Regarding Appendix C of Attachment 2, "USI A-46 Resolution, Relay l Evaluation Report, Monticello Nuclear Generating Plant," of the I submittal, provide a discussion and specific examples of relays whose malfunction (i.e. chatter) is acceptable. These relays were identified :
as " Chatter Acceptable (CA)" in the Appendix. !
- 18. Appendix C of Attachment 2, " Operator Actions," specifies !
relay / component combinations which are resolved by operator actions.
Clarify how these operator actions were verified and validated to ensure .
that under the postulated conditions of a design-basis earthquake they l could be adequately executed. What field and control room simulator scenarios were developed to verify and validate that these operator actions could be accomplished in the time frame required to facilitate safe shutdown? How were potentially harsh environmental conditions (e.g. blackout, high temperature and high pressure) factored into these analyses?
l 4
- 19. In addition to the outliers addressed in Tables 5-1 and 7-1 with respect to use of Clinch anchors, confim that RHR Heat Exchangers E-200A and E-2008 were evaluated and found structurally adequate in accordance with the rules and procedures given in Section 7 of the GIP.
- 20. Provide computations pertaining to the seismic adequacy of the Standby Diesel Generator Day Tanks (T-45A and T-458). Include the calculations of the seismic adequacy of their saddle supports and anchorages.
- 21. Referring to the in-structure response spectra provided in your 120-day-response to the NRC's request in Supplement No. I to Generic l Letter 87-02, dated May 22, 1992, provide the following information: '
- a. Identify structure (s) which have in-structure response spectra (5% critical damping) for elevations within 40-feet above the effective grade, which are higher in amplitude than 1.5 times the SQUG Bounding Spectrum.
- b. With respect to the comparison of equipment seismic capacity and seismic demand, indicate which method in Table 4-1 of GIP-2 was used to evaluate the seismic adequacy for equipment installed on the corresponding floors in the structure (s) identified in Item (a) above. If you have elected to use method A in Table 4-1 of the GIP-2, provide a technical justification for not using the in-structure response spectra provided in your 120-day-response. It appears that some A-46 licensees are making an incorrect comparison between their plant's safe shutdown earthquake (SSE) ground motion response spectrum and the SQUG Bounding Spectrum. The SSE ground motion response spectrum for most nuclear power plants is defined at the plant foundation level. The SQUG Bounding Spectrum is defined at the free field ground surface. For plants located at deep soil or rock sites, there may not be a significant difference between the ground motion amplitudes at the foundation level and those at the ground surface. However, for sites where a structure is founded on shallow soil, the amplification of the ground motion from the foundation level to the ground surface may be significant.
- c. For the structure (s) identified in Item (a) above, provide the in-structure response spectra designated according to the height above the effective grade. If the in-structure response spectra identified in the 120-day-response to Supplement No. I to Generic Letter 87-02 was not used, provide the response spectra that were actually used to verify the seismic adequacy of equipment within the structures identified in Item (a) above. Also, provide a comparison of these spectra to 1.5 times the Bounding Spectrum.