ML20217M38021 October 1999Forwards Insp Rept 50-263/99-06 on 990813-0923.Four Violations of NRC Requirements Identified & Being Treated as non-cited Violations Consistent with App C of Enforcement PolicyPower change
ML20217G07113 October 1999Forwards Insp Rept 50-263/99-12 on 990913-17.No Violations Noted
ML20216J24930 September 1999Ack Receipt of 980804,990626 & 0720 Ltrs in Response to GL 98-01,suppl 1, Year 2000 Readiness of Computer Sys at Npps. Staff Review Has Concluded That All Requested Info Has Been Provided
ML20217B14230 September 1999Informs That on 990902,NRC Staff Completed mid-cicle Plant Performance Review of Monticello Nuclear Generating Station. Staff Conducted Reviews for All Operating NPPs to Integrate Performance Information & to Plan for Insp Activities
ML20212K91330 September 1999Refers to 990920 Meeting Conducted at Monticello Nuclear Generating Station to Discuss Initiatives in Risk Area & to Establish Dialog Between SRAs & PRAProbabilistic Risk Assessment
ML20216G43424 September 1999Forwards Exam Rept 50-263/99-301 on 990823-26.Violation Occurred & Being Treated as Ncv,Consistent with App C of Enforcement Policy.Test Was Administered to Two Applicants. Both Applicants Passed All Sections of Exam
ML20212G98023 September 1999Refers to Resolution of Unresolved Items Identified Re Security Alarm Station Operations at Both Monitcello & Prairie Island
ML20212F09021 September 1999Confirms Discussion Between M Hammer & Rd Lanksbury to Have Routine Mgt Meeting on 991005 in Lisle,Il.Purpose of Meeting to Discuss Improvement Initiatives in Areas of Operations & Equipment Reliability
ML20217A5759 September 1999Forwards Individual Exam Results for Licensee Applicants Who Took Aug 1999 Initial License Exam.Without Encls
ML20211Q6986 September 1999Informs That NRC Tentatively Scheduled Initial Licensing Exam for Monticello Operator License Applicants During Wks of 010604 & 11.Validation of Exam Will Occur at Station During Wk of 010514
ML20211L1981 September 1999Forwards Insp Rept 50-263/99-05 on 990702-0812.No Violations NotedPower change
ML20210Q0344 August 1999Forwards SE Granting Licensee 980724 Relief Request 10 Re Third 10-year Interval ISI Program Plan,Entitled, Limited Exam
ML20210H08628 July 1999Forwards Insp Rept 50-263/99-04 on 990521-0701.No Violations Noted.Licensee Conduct at Monticello Facility Characterized by safety-conscious Operations,Sound Engineering & Maint Practices & Appropriate Radiological Controls
ML20209G56214 July 1999Forwards Insp Rept 50-263/99-11 on 990621-24.No Violations Noted.Objective of Insp,To Determine Whether Monticello Nuclear Generating Station Emergency Plan Adequate & If Station Personnel Properly Implemented Emergency Plan
ML20196J5352 July 1999Discusses GL 92-01,Rev 1,Supp 1, Rv Integrity, Issued by NRC on 950515 & NSP Responses & 980917 for Monticello Npp.Informs That Staff Revised Info in Rvid & Released Info as Rvid Version 2
ML20196J9681 July 1999Informs That in Sept 1998,Region III Received Rev 20 to Portions of Util Emergency Plan Under 10CFR50.54(q).Based on Determination That Changes Do Not Decrease Effectiveness of Licensee Emergency Plan,No NRC Approval Required
ML20206N56013 May 1999Informs That NRC Office of Nuclear Reactor Regulation Reorganized Effective 990328.As Part of Reorganization,Div of Licensing Project Mgt Created.Cm Craig Will Be Section Chief for Monticello Npp.Organization Chart EnclEnforcement Discretion
ML20206G2185 May 1999Discusses Completion of Licensing Action for GL 96-01, Testing of Safety-Related Logic Circuits, Dtd 960110,for Plant
ML20206G4904 May 1999Forwards Staff Review of Licensee 960508 Response to NRC Bulletin 96-002, Movement of Heavy Loads Over Sf,Over Fuel in Rc or Over Safety-Related Equipment, .Overall, Responses Acceptable.Tac M95610 ClosedSafe Shutdown
Control of Heavy Loads
ML20206G7743 May 1999Forwards Insp Rept 50-263/99-02 on 990223-0408.One Violation Occurred & Being Treated as non-cited Violation,Consistent with App C of Enforcement PolicyPower change
ML20205N08212 April 1999Forwards SE of NSP Response to NRC GL 95-07, Pressure Locking & Thermal Binding of Safety-Related Power-Operated Gate Valves. Licensee Adequately Addressed Actions Requested in GL
ML20205N4819 April 1999Forwards Licensing Requalification Insp Rept 50-263/99-10 on 990308-12.No Violations Noted.However,Inspectors Through Observation of Simulator Scenario Exams Noted Difficulties in Ability of SM to Simultaneously Implement Duties of SM
ML20205N5309 April 1999Discusses Arrangements Made on 990406 for Administration of Licensing Exams at Monticello Nuclear Generating Station During Wk of 990823.Requests That Exam Outlines Be Submitted by 990128 & Supporting Ref Matls by 990719
ML20205C48526 March 1999Informs That on 990203,NRC Staff Completed PPR of Nuclear Plant.Staff Conducts Reviews for All Operating NPPs to Develop an Integrated Understanding of Safety PerformanceEnforcement Discretion
Probabilistic Risk Assessment
Systematic Assessment of Licensee Performance
Scaffolding
ML20205A58824 March 1999Forwards Request for Addl Info Re Submittal Requesting Rev of pressure-temperature Limits & Surveillance Capsule Withdrawal Schedule
ML20204H47118 March 1999Forwards SER Concluding That Util Established Acceptable Program to Verify Periodically design-basis Capability of safety-related MOVs at Monticello & Adequately Addressed Actions Requested in GL 96-05
ML20207H51611 March 1999Forwards Insp Rept 50-263/99-01 on 990112-0222.No Violations Noted
ML20203F25410 February 1999Informs That Beginning 990216,DE Hills Will Be Chief of Operations Branch Which Includes Operator Licensing Function
ML20202B71926 January 1999Discusses 990125 Telcon with T Witschen & D Mcneil Re Arrangements for NRC to Inspect Licensed Operator Requalification Program at Monticello Nuclear Generating Station.Insp Planned for Week of 990308
ML20199H83220 January 1999Forwards Insp Rept 50-263/98-18 on 981201-990111.No Violations Were Identified.Conduct of Activities at Monticello Facility Was Generally Characterized by safety- Conscious Operations & Sound Maint Practices
ML20199G77214 January 1999Forwards Request for Addl Info Re GL 88-20, Individual Plant Exam of External Events (IPEEE) for Severe Accident Vulnerabilities, Issued in June 1991Hot Short
High winds
Probabilistic Risk Assessment
Earthquake
Fuel cladding
ML20206R86312 January 1999Informs That Staff Has Prepared TS Interpretation of Requirements for Extending Surveillance Intervals at Plant,Per NRC RequestBackfit
ML20199E4796 January 1999Forwards SER Accepting Licensee 951116,960214 & 0524 Responses to NRC Bulletin 95-002, Unexpected Clogging of Residual Heat Removal Pump Strainer While Operating in Suppression Pool Cooling Mode, for MonticelloForeign Material Exclusion
ML20206R8744 January 1999Discusses Clarification of Understanding of Safety Evaluation Related to Deviation from Emergency Procedure Guidelines for Monticello.Staff Agrees with NSP Characterization & Resolution of Issues
ML20198R20030 December 1998Forwards Insp Rept 50-263/98-19 on 981214-18.No Violations Noted.Purpose of Insp Was to Review Plant Chemistry Program, PASS & REMP
ML20198P05028 December 1998Informs of Completion of Review of Relief Request 9 Re Third 10-year Interval ISI Program Plan,Entitled Use of High Alloy/High Nickel Calibr Block for Dissimilar Metal Welds. Supporting SE EnclDissimilar Metal Weld
ML20198G07621 December 1998Acks Receipt of Notifying NRC That Commitment Noted in Is Complete Re Tornado Effects on Reactor Bldg SuperstructureIncorporated by reference
ML20198D01815 December 1998Informs That as Part of PRA Implementation Plan,Commission Assigned Two SRAs to Each Regional Ofc.Sras Will Routinely Assess Licensee Event Repts,Plant Events,Insp Findings & EAs from Risk PerspectiveProbabilistic Risk Assessment
ML20198B77214 December 1998Forwards Insp Rept 50-263/98-16 on 981014-1130 & Notice of Violation Re Fire Brigade Drill Participation
ML20198D06410 December 1998Forwards SE Accepting Licensee 971118 Request for Review & Approval of Deviation from BWROG Epg,Rev 4,NEDO-31331, March,1997.Deviation Will Permit Rev of Plant EOPs to Recognize 2/3 Core Height as Adequate for Core Cooling
ML20196C24124 November 1998Forwards Insp Rept 50-263/98-17 on 981026-30.No Violations Noted.Security Dept self-assessment Efforts Continue to Be Very Strong
ML20196D56420 November 1998Discusses 981104 Insp Resource Planning Meeting for Monticello & Advises of Planned Insp Effort for Next 6 Months at Plant.Info Provided to Min Resource Impacts on Staff & to Allow for Rescheduling Conflicts to Be ResolvedProbabilistic Risk Assessment
Nondestructive Examination
Temporary Modification
Foreign Material Exclusion
Scaffolding
ML20195J88119 November 1998Informs That EOP Flow Charts C.5-1100 RPV Control, Rev 5 & C.5-1100... Rev 6 Marked Proprietary & Submitted as Attachments 3 & 4 to Util Will Be Withheld from Public Disclosure Per 10CFR2.790(b)(5)
ML20196G60819 November 1998Submits Correction to Which Advises Licensee That EOP Flow Charts, C.5-1100 RPV Control, Rev 5 & C.5-1100 RPV Control, Rev 6,marked Proprietary,Will Be Withheld from Public Disclosure.Ltr Reissued to Correct Date of Issuance
ML20195E33212 November 1998Forwards SE Concluding That Licensee Implementation Program to Resolve USI A-46 at Facility Has Adequately Addressed Purpose of 10CFR50.54(f) Request.Usi A-46 Program Was Established in Response to GL 87-02
ML20196D72910 November 1998Forwards Insp Rept 50-263/98-15 on 980831-1014.No Violations Noted.Investigation Team Assembled by Station Mgt to Determine Root Cause of Offgas Sys Problem Was Thorough & Aggressive
ML20154L2959 October 1998Informs That Effective 981011,project Mgt Responsibility for Plant Will Be Transferred from Tj Kim to CF Lyon.Cf Lyon May Be Contacted at Listed Number
ML20154F4976 October 1998Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Rept 50-263/98-09 Issued on 980730Temporary Modification
ML20154J2502 October 1998Forwards Audit of Year 2000 Program at Monticello Nuclear Generating Plant on 980915-17 as Followup to NRC GL 98-01, Year 2000 Readiness of Computer Systems at Nuclear Power Plants, Issued on 980511
ML20153C46121 September 1998Submits Comments on Draft Environ Impact Statement for Minnesota Lake Superior Coastal Program