Forwards Safety Evaluation Accepting Licensee 850823 Response to Generic Ltr 83-28,Item 4.5.3, Reactor Trip Reliability - On-Line Functional Testing of Reactor Trip Sys
ML20245J432
Person / Time
Site: Three Mile Island Constellation icon.png
Issue date: 06/23/1989
From: Hernan R
Office of Nuclear Reactor Regulation
To: Hukill H
GENERAL PUBLIC UTILITIES CORP.
Shared Package
ML20245J437 List:
References
GL-83-28, TAC-54034, NUDOCS 8907030044
Download: ML20245J432 (2)


Text

'

'* June 23,'1989 DockStNo.l50-289 DISTR A h0N

" Docket n ew EJordan Mr. Henry. D. Hukill, Vice President- NRC &. Local PDRs BGrimes and Director - TMI-1 Plant File .ACRS(10).

s GPU Nuclear Corporation SVarga BMozafari .

P. O. Box'480 BBoger Middletown, Pennsylvania ~17057. SNorris RHernan

Dear Mr. Hukill:

OGC

SUBJECT:

SAFETY EVALUATION FOR GENERIC. LETTER 83-28, ITEM 4.5.3, REACTOR TRIP RELIABILITY - ON-LINE FUNCTIONAL TESTING OF THE REACTOR

TRIP SYSTEM (TAC NO. 54034)

Generic Letter 83-28, Item 4.5.3, required confirmation from all licensees and applicants that on-line functional testing of the reactor trip system, including independent testing of the diverse trip feature, was being performed.

By letter dated August.23, 1985 you submitted the response to Generic Letter

'83-28, Item 4.5.3. Therein you indicated your endorsement of.the B&W Owners Group's Report dated April-8,1985 as being applicable to Three Mile Island Unit-

1. The NRC ' staff, with the assistance of our contractor, E.G.&G. - Idaho, has -

reviewed your response and the B&W Owners Group's Report. We conclude that the existing intervals for on-line functional testing at Three Mile Island Unit 1 are consistent with achieving.high reactor trip system availability."

The enclosed safety evaluatic,n and contractor's. report (EGG-NTA 8341) provide the details and basis for our conclusion. Therefore, we. consider Generic Letter 83-28 Item 4.5.3 to be complete.

This completes all staff activities related to TAC No. 54034.

Sincerely, Ro'nald W. Hernan, Senior Project Manager Project Directorate I-4 Division of Reactor Projects I/II  ;

Office of Nuclear Reactor Regulation

]

Enclosures:

-As stated cc w/ enclosures:

See next page DFo/

[ TAC N0. 54034] I i N Nr l 6 4.3/89 6/2089 640/89 [

'6907030044 DR 890S23 p ADOCK 05000289 PDC

{

Mr.' Henry D. Hukill Three Mile Island Nuclear Station, GPU Nuclear Corporation Unit No. 1 cc:

G. Broughton Francis I. Young O&M Director, THI-1 SeniorResidentInspector(TMI-1)

GPU Nuclear Corporation U.S.N.R.C.

Post Office Box 480 Post Office Box 311 Middletown, Pennsylvania 17057 Middletown, Pennsylvania 17057 Richard J. McGoey I Manager, PWR Licensing Regional Administrator, Region I )

GPU Nuclear Corporation U.S. Nuclear Regulatory Commission i 100 Interpace Parkway 475 Allendale Road '

Parsippany, New Jersey 07054 King of Prussia, Pennsylvania 19406 C. W. Smyth Robert B. Borsum i TMI-1 Licensing Manager Babcock & Wilcox GPU Nuclear Corporation Nuclear Power Generation Division Post Office Box 480 Suite 525 Middletown, Pennsylvania 17057 1700 Rockville Pike Rockville, Maryland 20852 Ernest L. Blake, Jr., Esq. Governor's Office of State Planning Shaw, Pittman, Potts & Trowbridge and Development 2300 N Street, N.W. ATTN: Coordinator, Pennsylvania Washington, D.C.

~

20037 State Clearinghouse Post Office Box 1323 Harrisburg, Pennsylvania 17120 Sa'lly S. Klein, Chairman Thomas M. Gerusky, Director Dauphin County Commissioner Bureau of Radiation Protection Dauphin County Courthouse Pennsylvania Department of Front and Market Streets Environmental Resources Harrisburg, Pennsylvania 17120 Post Office Box 2063 Harrisburg, Pennsylvania 17120 Kenneth E. Witmer, Chairman Board of Supervisors of Londonderry Township 25 Roslyn Road Eilzabethtown, PA 17022 i

o____.___.__________.____ _ _ _ _ _ _ . _ -..