Forwards Request for Addl Info Re Licensee 981125 Amend Application Re TS Change Request 277 for OTSG Inservice Insp During 13R for Three Mile Island,Unit 1
ML20203F491
Person / Time
Site: Three Mile Island Constellation icon.png
Issue date: 02/05/1999
From: Colburn T
NRC (Affiliation Not Assigned)
To: Langenbach J
GENERAL PUBLIC UTILITIES CORP.
References
TAC-MA4234, NUDOCS 9902180156
Download: ML20203F491 (4)


Text

,

February 5, 1999 Mr. James W. Langenbach, Vice President ,

and Director- TMI  !

GPU Nuclear, Inc.-

P.O. Box 480 Middletown, PA 17057

SUBJECT:

REQUEST FOR ADDITIONAL INFORMATION REGARDING GPU NUCLEAR,  ;

INC., TSCR NO. 277, ONCE THROUGH STEAM GENERATOR (OiSG) J CYCLE 13 (13R) INSERVICE INSPECTIONS FOR THE THREE MILE ISLAND NUCLEAR STATION, UNIT 1 (TMI-1)(TAC NO. MA4234)

Dear Mr. Langenbach:

The staff has reviewed your November 25,1998, license amendment application i regarding Technical Specification Change Request (TSCR) No. 277, for OTSG inservice inspection during 13R for TMI-1. The staff has determined that it will need the additional information identified in the enclosure to complete its review. The need for this information was discussed with Mr. Robert Knight of your staff on February 2,1999. In order fur the NRC staff to complete its review of your application by April 15,1999, per your staff's request, please respond to this request for additional information within 3 weeks of receipt in order for l l

the staff to remain on schedule with its review.

Sincerely,

/s/

Timothy G. Colbum, Senior Project Manager Project Directorate 1-2 Division of Reactor Projects - 1/11 lj Office of Nuclear Reactor Regulation

/I Docket No. 50439 I

Enclosure:

Request for AdditionalInformation cc S./ encl. See next page hj 4 DISTRIBUTIO% JZwolinski ff f' Docket File ESullivan PRush CBeardsley PUBLIC - RBlough, RI OGC TCyrk PDI-2 Reading WDean ACRS TC@ bum OFFICE PDI-$h'/ / PDI-2/LA EM F3/FKO , PDid[D! l NAME TChi TClark ' a WD /

DATE 7// h/99 d /(/99 Q/S99 Ilh /99 , !

I OFFICIAL RECORD COPY DOCUMENT NAME: TMl4234.RAI k 9902180156 990205 PDR ADOCK 05000289 G PDR ,

g rung g #*, UNITED STATES

,5 j_ NUCLEAR REGULATORY COMMISSION i 2 WASHINGTON, D.C. 2006tHD001

% ,o February 5, 1999 Mr. James W. Langenbach, Vice President and Director- TMI GPU Nuclear, Inc.  !

P.O. Box 480 Middletown, PA 17057 i

SUBJECT:

REQUEST FOR ADDITIONAL INFORMATION REGARDING GPU NUCLEAR, j INC., TSCR NO. 277, ONCE THROUGH STEAM GENERATOR (OTSG) l CYCLE 13 (13R) INSERVICE INSPECTIONS FOR THE THREE MILE ISLAND NUCLEAR STATION, UNIT 1 (TMI-1)(TAC NO. MA4234)

Dear Mr. Langenbach:

The staff has reviewed your November 25,1998, license amendment application regarding Technical Specification Change Request (TSCR) No. 277, for OTSG inservice inspection di ,ing 13R for TMI-1. The staff has determined that it will need the additional information identified in the enclosure to complete its review. The need for this information was discussed with Mr. Robert Knight of your staff on February 2,1999. In order for the NRC l

staff to complete its review of your application b'y April 15,1999, per your staff's request, please respond to this request for additional information within 3 weeks of receipt in order for the staff to remain on schedule with its review.

Sincerely, Timothy G. Colbum, S ior Project Manager Project Directorate 1-2 Division of Reactor Projects - t/ll i

Office of Nuclear Reactor Regulation Docket No. 50-289

Enclosure:

Request for Additionalinformation cc w/ encl: See next page g__

J.Langenbach' ,

Three Mile Island Nudear Station, Unit No.1 I

cc:

Michael Ross Director, O&M, TMl Robert B. Borsum GPU Nuclear, Inc. B&W Nuclear Technologies P.O. Box 480 . Suite 525 Middletown, PA 17057 1700 Rockville Pike Rockville, MD 20852 John C. Fomicola Dire:: tor, Planning and William Domsife, Acting Director.

Regulatory Affairs Bureau of Radiation Protection GPU Nuclear, Inc. Pennsylvania Department of

' 100 Interpace Parkway Environmental Resources Parsippany, NJ 07054 P.O. Box 2063 Harrisburg, PA 17120 Jack S. Wetmore Manager, TMI Regulatory Affairs Dr. Judith Johnsrud GPU Nuclear, Inc. National Energy Committee P.O. Box 480 Sierra Club Middletown, PA 17057 433 Oriando Avenue State College, PA 16803 Emest L. Blake, Jr., Esquire Shaw, Pittman, Potts & Trowbridge Peter W. Eselgroth, Region 1 2300 N Street, NW. U.S. Nuclear Regulator / Commission Washington, DC 20037 475 Allendale Road King of Prussia, PA 19406 Chairman Board of County Commissioners of Dauphin County Dauphin County Courthouse Harrisburg, PA 17120 Chairman Board of Supervisors of LondonderryTownship R.D. #1, Geyers Church Road Middletown, PA 17057 Wayne L. Schmidt Senior Resident inspector (TMI-1)

U.S. Nuclear Regulatory Commission -

P.O. Box 219 Middletown, PA 17057 Regional Administrator Region i U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 x ._ -

l

. \

l

~

REQUEST FOR ADDITIONAL INFORMATION THREE MILE ISLAND, UNIT 1 TECHNICAL SPECIFICATION CHANGE REQUEST NO. 277 i

CYCLE 13 STEAM GENERATOR ID IGA INSPECTION ACCEPTANCE CRITERIA )

4 By letter dated November 25,1998, GPU Nuclear, Inc., submitted a request to change the

[ - Technical Specification surveillance requirements for Steam Generator inservice inspections j for Three Mile Island, Unit 1 (TMI-1) cycle 13 refueling outage (13R) examinations which would be applicable for one cycle of operation only. Specifically, the change requested 14 wasociated

! with inspection acceptance criteria for inside diameter intergranular attack (ID IGA) of the

steam generator tubes. The staff had previously issued a request for additional information on i January 20,1999, for this request; however, due to the expedited schedule you requested for i: . this review (April 15,1999), the staff had not completed it full review of your application by the

! January 20,1999, date. Subsequently, the staff has determined additional information is necessary to complate the review. The required information is listed below, i The technical specification change request proposed a change to technical

specification (TS) Section 4.19.5(b) regarding " Reports" of steam generator inspection results to allow 12 months for reporting the complete steam generator inspection results rather than 90 days, as is currently in the TS. The basis for this change was that 12 months is consistent with NRC Draft Regulatory Guide (DG) 1074, " Steam Generator Tube Integrity," dated March 1998.

The 12-month reporting requirement in DG 1074 is one part of an entire program. It is not appropriate to select one part of a program as an independent element. The assumption of zero growth rate for these inner diameter flaws is a significant aspect of the technical basis supporting this amendment request. Therefore, there is a heightened sensitivity as to the results of the steam generatorinspections. The staff believes a reporting period of 90 days is appropriate. Please provide additional basis for extending the reporting period beyond 90 days or withdraw the portion of your request re'ating to a 12-month reporting requirement.

ENCLOSURE i