ML20128G504

From kanterella
Revision as of 09:50, 8 July 2020 by StriderTol (talk | contribs) (StriderTol Bot insert)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search
Advises That Based on Current Review Schedule,More than 60 Days Will Be Required to Review 850531 QA Program Description.Notification of Results Will Be Given
ML20128G504
Person / Time
Site: Kewaunee Dominion icon.png
Issue date: 07/03/1985
From: Spessard R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Hintz D
WISCONSIN PUBLIC SERVICE CORP.
References
NUDOCS 8507090212
Download: ML20128G504 (1)


Text

_

JUL 3 1985 Docket No. 50-305 Wisconsin Public Service Corporation ATTN: Mr. D. C. Hintz Manager Nuclear Power Post Office Box 19002 Green Bay, WI 54307-9002 Gentlemen:

Thank you for your Quality Assurance Program Description submittal of May 31, 1985, for Kewaunee Nuclear Power Plant. Based on our current review schedule, we anticipate that it will require more than 60 days from the date of your submittal to complete our review. You will be notified of the results.

Please contact Mr. Frank Hawkins of my staff (312-790-5555) with any questions you have regarding this matter.

Sincerely,

" Original Signed by R. L. Spessard" R. L. Spessard, Director Division of Reactor Safety cc: C. R. Steinhardt, Plant j Superintendent DMB/ Document Control Desk (RIDS)

Resident Inspector, RIII John J. Duffy, Chief Boiler Section Ness Flores, Chairperson Wisconsin Public Service Commission G. T. Ankrum, IE R II RIII R RII vandel/1c tawk ns c w eyes spessard 7/2/85 y g l090212 850703 p ADOCK 05000305 PDR

/6I