Advises That Tech Spec Changes Contained in Amends 4 & 6 to License NPF-29 Will Be Effective Before Startup After First Refueling Outage,Per 850918 & 1021 Requests
ML20138K200
Person / Time
Site: Grand Gulf Entergy icon.png
Issue date: 12/06/1985
From: Dale L
MISSISSIPPI POWER & LIGHT CO.
To: Harold Denton
Office of Nuclear Reactor Regulation
References
AECM-85-0396, AECM-85-396, TAC-59184, TAC-59185, TAC-59186, TAC-59187, TAC-59360, TAC-59361, TAC-59362, TAC-59363, TAC-59364, TAC-59365, NUDOCS 8512180311
Download: ML20138K200 (2)


Text

r- j MISSISSIPPI POWER & LIGHT COMPANY

] Helping Build Mississippi Ein Mi&liddB P. O. B O X 164 0, J A C K S O N, MIS SIS SIP PI 39215-1640 December 6, 1985 NUCLE AR LICENSING & SAFETY DEPARTMENT U. S. Nuclear Regulatory Commission Office of Nuclear Reactor Regulation Washington, D. C. 20555 Attention: Mr. Harold R. Denton, Director

Dear Mr. Denton:

SUBJECT:

Grand Gulf Nuclear Station Unit 1 Docket No. 50-416 License No. NPF-29 File: 0260/0840/L-860.0 Technical Specification Amendment Effective Dates AECM-85/0396

Reference:

1) Letter from Elinor G. Adensam to Mr. J. B. Richard dated September 18, 1985
2) Letter from Elinor G. Adensam to Mr. J. B. Richard dated Octrher 21, 1985 Mississippi Power & Light (MP&L) was requested by the referenced letters to notify the Nuclear Regulatory Commission (NRC) of the effective date of certain technical specification changes. MP&L was also requested to notify the NRC of equipment installation delays beyond the Fall Outage scheduled for October and November of 1985 associated with the reference technical speci-fication changes.

Amendment 4 to Facility Operating License NPF-29, provided changes to the Containment and Drywell Isolation Valves table 3.6.4-1 and the Primary Containment Penetration Conductor Overcurrent Protection Devices table 3.8.4.1-1 and have an effective date of November 7, 1985. Changes to the Fire Detection Instrumentation table 3.3.7.9-1.c.16 have been administratively implemented but cannot be made effective in the technical specifications until work has been completed to make effective changes to 3.3.7.9-1.d.1.

Both of these changes affect page 3/4 3-87 of the technical specifications, and will be made effective before startup after the first refueling outage.

Amendment 6 to Facility Operating License NPF-29, provided changes to unit organization, control rod scram accumulators, and fire detection instrumentation and were made effective immediately upon receipt. Changes to the primary containment penetration conductor overcurrent protection devices, table 3.8.4.1-1, and electrical power systems, 4.8.1.1.2.d.8.a and 4.8.1.1.2.d.16 will be made effective before startup after the first refueling k out>8e- e3121eO211eS12g;1, ,

PDR ADOCK 0500 g) 1 L

P J16AECM85120301 - 1 Member Middle South Utilities System

r b

AECM-85/0396 Page 2 MP&L.will notify the NRC within 30 days of the effective date of the delayed technical specification changes.

MP&L believes this method of providing effective dates for operating license amendments associated with design changes has greatly increased our

.iflexibility to plan, schedule and implement work during planned outages.

If_you have any questions, please contact this office.

. Yours truly,

~

L. F. Dale Director JMG/SHH: bas

\

cc: Mr. O. D. Kingsley, Jr.

.Mr. T. H. Cloninger Mr. R. B. McGehee Mr. N. S. Reynolds Mr. H. L. Thomas Mr. R. C. Butcher Mr. James M. Taylor, Director Office of Inspection & Enforcement U. S. Nuclear Regulatory Commission Washington, D. C. 20555 Dr. J. Nelson Grace, Regional Administrator U.'S. Nuclear Regulatory Commission Region II

-101 Marietta St., N. W., Suite 2900 Atlanta, Georgia 30323 I

J16AECM85120301 - 2