Forwards Rev 1 to Detailed Control Room Design Review Summary Rept, Per Suppl 1 to NUREG-0737.Rept Documents Apr & June 1984 Environ Surveys Addressing Concerns Identified in Util 840321 & NRC 840605 Ltrs
ML20093A387
Person / Time
Site: Wolf Creek, Callaway, 05000000
Issue date: 06/29/1984
From: Petrick N
STANDARDIZED NUCLEAR UNIT POWER PLANT SYSTEM
To: Harold Denton
Office of Nuclear Reactor Regulation
Shared Package
ML20093A388 List:
References
RTR-NUREG-0737, RTR-NUREG-737 SLNRC-84-99, NUDOCS 8407100429
Download: ML20093A387 (2)


Text

r -- p.

s o

  • SNUPPS Standardiaod Nuclear Unit Power Mant System 5 Choke Cherry Road Nicholas A. Petrick Rockville, Maryland 20050 Exocutive Director June 29, 1984 SLNRC 84-99 FILE: 0671.1 SUBJ: Revision 1 to DCRDR Summary Report for SN'JPPS Mr. Harold R. Denton, Director, Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, D.C. 20555 Docket Nos. STN 50-482 and STN 50-483

References:

1. SLNRC 84-0019, 02/02/84: DCRDR Summary Report for SNUPPS
2. SLNRC 84-0048, 03/21/84: NRC Audit of SNUPPS CRDR, Week of 02/27/84
3. NRC (Youngblood) letter to UE (Schnell) and KGE (Koester) dated 06/05/84: Results of Preimplementation Audit
4. NRC (Youngblood) letter to UE (Schnell) dated 06/11/84:

Callaway ASP

Dear Mr. Denton:

Reference 1 transmitted the Detailed Control Room Design Review (DCRDR)

Summary Report for the SNUPPS units. Reference 2 documented results of the site audits of DCRDR progress, for which the Summary Report was used as a basis. The NRC provided their documentation of results of the site audits of the Callaway and Wolf Creek control rooms by issuing reference 3, which also contains new concerns in the form of comments on the Summary Report.

Transmitted herewith is Revision 1 to the Summary Report, generated to document the two Environmental Surveys, held in April and June 1984, to address commitments and concerns identified in references 2 and 3, and to revise various responses and implementation schedules, which were unavail-able at the time of the reference I submittal. The majority of the new concerns identified by reference 3 are addressed in this revision; a summary of these items and their location within the attached revision is provided in Appendix K along with concerns and commitments resulting from the site audits. The remaining concerns from reference 3 will be addressed as discussed btiow. Union Electric will provide, under separate cover, a response to the NRC regarding the reference 4 findings.

SNUPPS will submit a supplemental report on the revised Task Analysis by July 01, 1985. Several utilities have been requested to address this concern. This schedule will allow time for development of a generic response to the task analysis upgrade which the NRC has required. This 8407100429 840629 R PDR ADOCK 05000402 F PDR g gD >y L

r a

?

SLNRC 84-99

'Page Two

~

schedule will also support completion of the related E0P upgrade program by September 1985. This letter and schedule commitment above completes response to Callaway license condition C(9)(a).

Very truly yours, Rh(\C Nichclas A. Petrick

'DJK/dck/12a12 Attachnent cc: G. L. Koester, KGE w/o D. T. McPhee, KCPL D. F. Schnell, UE "

J. H. Neisler, USNRC/ Cal

8. H. Little, USNRC/ Cal "

H. Bundy, USNRC/WC W. L. Forney USNRC/ Reg. III E. H. Johnson, USNRC/ Reg. IV

.