{{#Wiki_filter:June 28, 2021 Mr. David P. Rhoades Senior Vice President Exelon Generation Company, LLC President and Chief Nuclear Officer (CNO)
Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555
 
==SUBJECT:==
CLINTON POWER STATION, UNIT NO. 1 - ISSUANCE OF AMENDMENT NO. 238 RE: TECHNICAL SPECIFICATIONS TASK FORCE TRAVELER TSTF-505, REVISION 2, PROVIDE RISK-INFORMED EXTENDED COMPLETION TIMES - RITSTF INITIATIVE 4B (EPID L-2020-LLA-0097)
 
==Dear Mr. Rhoades:==
 
The U.S. Nuclear Regulatory Commission has issued the enclosed Amendment No. 238 to Facility Operating License No. NPF-62 for the Clinton Power Station, Unit No. 1. The amendment is in response to your application dated April 30, 2020 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML20121A178) as supplemented by letters dated November 24, 2020 (ADAMS Accession No. ML20329A433) and March 23, 2021 (ADAMS Accession No. ML21082A268).
The amendment modifies technical specifications to permit the use of risk-informed completion times in accordance with Technical Specifications Task Force (TSTF) Traveler TSTF-505, Revision 2, "Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b,"
(ADAMS Accession No. ML18183A493).
A copy of the Safety Evaluation is also enclosed. A Notice of Issuance will be included in the Commissions next monthly Federal Register notice.
Sincerely,
                                            /RA/
Joel S. Wiebe, Senior Project Manager Plant Licensing Branch III Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-461
 
==Enclosures:==
: 1. Amendment No. 238 to NPF-62
: 2. Safety Evaluation cc: Listserv
 
EXELON GENERATION COMPANY, LLC DOCKET NO. 50-461 CLINTON POWER STATION, UNIT NO. 1 AMENDMENT TO FACILITY OPERATING LICENSE Amendment No. 238 License No. NPF-62
: 1. The U.S. Nuclear Regulatory Commission (the Commission) has found that:
A. The application for amendment by Exelon Generation Company, LLC (the licensee), dated April 30, 2020, as supplemented by letters dated November 24, 2020 and March 23, 2021, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act), and the Commissions rules and regulations set forth in 10 CFR Chapter I; B. The facility will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission; C. There is reasonable assurance: (i) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commissions regulations; D. The issuance of this amendment will not be inimical to the common defense and security or to the health and safety of the public; and E. The issuance of this amendment is in accordance with 10 CFR Part 51 of the Commissions regulations and all applicable requirements have been satisfied.
Enclosure 1
: 2. Accordingly, the license is amended by changes to the Technical Specifications as indicated in the attachment to this license amendment, and paragraph 2.C.(2) of Facility Operating License No. NPF-62 is hereby amended to read as follows:
(2)    Technical Specifications and Environmental Protection Plan The Technical Specifications contained in Appendix A and the Environmental Protection Plan contained in Appendix B, as revised through Amendment No. 238, are hereby incorporated in the license. Exelon Generation Company shall operate the facility in accordance with the Technical Specifications and the Environmental Protection Plan.
: 3. This license amendment is effective as of its date of issuance and shall be implemented within 180 days of the date of issuance.
FOR THE NUCLEAR REGULATORY COMMISSION Digitally signed by Nancy L.            Nancy L. Salgado Date: 2021.06.28 Salgado            14:54:11 -04'00' Nancy L. Salgado, Chief Plant Licensing Branch III Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation
 
==Attachment:==
 
Changes to the Facility Operating License and Technical Specifications Date of Issuance: June 28, 2021
 
ATTACHMENT TO LICENSE AMENDMENT NO. 238 FACILITY OPERATING LICENSE NO. NPF-62 CLINTON POWER STATION, UNIT NO. 1 DOCKET NO. 50-461 Replace the following pages of the Facility Operating License No. NPF-62 and the Appendix A, Technical Specifications, with the attached revised pages. The revised pages are identified by amendment number and contain marginal lines indicating the areas of change.
REMOVE                                INSERT Page 3                                Page 3 Technical Specifications REMOVE                                INSERT 1.0-24                                1.0-24 1.0-25                                1.0-25 1.0-26                                1.0-26 1.0-27                                1.0-27 1.0-28                                1.0-28 1.0-29                                1.0-29
                      --                                    1.0-30 3.1-20                                3.1-20 3.3-1                                  3.3-1 3.3-2                                  3.3-2 3.3-25                                3.3-25 3.3-26                                3.3-26 3.3-32                                3.3-32 3.3-33                                3.3-33 3.3-34                                3.3-34 3.3-35                                3.3-35 3.3-36                                3.3-36 3.3-37                                3.3-37
                      --                                    3.3-37a
                      --                                    3.3-37b 3.3-45                                3.3-45 3.3-46                                3.3-46 3.3-49                                3.3-49 3.3-50                                3.3-50 3.3-51                                3.3-51 3.3-52                                3.3-52 3.3-53                                3.3-53 3.3-54                                3.3-54 3.3-65                                3.3-65 3.3-66                                3.3-66
 
REMOVE (continued) INSERT (continued) 3.3-69            3.3-69 3.3-70            3.3-70 3.3-74            3.3-74 3.3-78            3.3-78 3.3-79            3.3-79 3.3-80            3.3-80 3.3-81            3.3-81 3.3-82            3.3-82
--                3.3-83 3.5-1              3.5-1 3.5-2              3.5-2 3.5-3              3.5-3 3.5-4              3.5-4 3.5-5              3.5-5 3.5-6              3.5-6 3.5-7              3.5-7 3.5-8              3.5-8 3.5-9              3.5-9 3.5-10            3.5-10 3.5-11            3.5-11 3.5-12            3.5-12
--                3.5-13
--                3.5-14 3.6-6              3.6-6 3.6-10            3.6-10 3.6-11            3.6-11 3.6-13            3.6-13 3.6-14            3.6-14 3.6-22            3.6-22 3.6-24            3.6-24 3.6-32            3.6-32 3.6-34            3.6-34 3.6-59            3.6-59 3.6-62            3.6-62 3.7-1              3.7-1 3.7-13            3.7-13 3.7-14            3.7-14 3.8-1              3.8-1 3.8-2              3.8-2 3.8-3              3.8-3 3.8-4              3.8-4 3.8-5              3.8-5 3.8-6              3.8-6 3.8-6a            --
3.8-6b            --
3.8-7              3.8-7 3.8-24            3.8-24 3.8-24a            3.8-24a 3.8-34            3.8-34 3.8-35            3.8-35
 
REMOVE (continued) INSERT (continued) 3.8-39            3.8-39 3.8-40            3.8-40 3.8-41            3.8-41 5.0-16c            5.0-16c 5.0-17            5.0-17 5.0-18            5.0-18 5.0-19            5.0-19
 
(4)      Exelon Generation Company, pursuant to the Act and to 10 CFR Parts 30, 40, and 70, to receive, possess, and use at any time any byproduct, source and special nuclear material as sealed neutron sources for reactor startup, sealed sources for reactor instrumentation and radiation monitoring equipment calibration, and as fission detectors in amounts as required; (5)      Exelon Generation Company, pursuant to the Act and 10 CFR Parts 30, 40, and 70, to receive, possess, and use in amounts as required any byproduct, source or special nuclear material without restriction to chemical or physical form, for sample analysis or instrument calibration or associated with radioactive apparatus or components; (6)      Exelon Generation Company, pursuant to the Act and 10 CFR Parts 30, 40, and 70, to possess, but not separate, such byproduct and special nuclear materials as may be produced by the operation of the facility.
Mechanical disassembly of the GE14i isotope test assemblies containing Cobalt-60 is not considered separation; and (7)    Exelon Generation Company, pursuant to the Act and 10 CFR Parts 30, to intentionally produce, possess, receive, transfer, and use Cobalt-60.
C. This license shall be deemed to contain and is subject to the conditions specified in the Commissions regulations set forth in 10 CFR Chapter I and is subject to all applicable provisions of the Act and to the rules, regulations and orders of the Commission now or hereafter in effect; and is subject to the additional conditions specified or incorporated below:
(1)      Maximum Power Level Exelon Generation Company is authorized to operate the facility at reactor core power levels not in excess of 3473 megawatts thermal (100 percent rated power) in accordance with the conditions specified herein.
(2)      Technical Specifications and Environmental Protection Plan The Technical Specifications contained in Appendix A and the Environmental Protection Plan contained in Appendix B, as revised through Amendment No. 238, are hereby incorporated into this license.
Exelon Generation Company shall operate the facility in accordance with the Technical Specifications and the Environmental Protection Plan.
Amendment No. 238
 
Completion Times 1.3 1.3  Completion Times EXAMPLES          EXAMPLE 1.3-7  (continued)
Condition B is entered, but continues from the time Condition A was initially entered. If Required Action A.1 is met after Condition B is entered, Condition B is exited and operation may continue in accordance with Condition A, provided the Completion Time for Required Action A.2 has not expired.
EXAMPLE 1.3-8 ACTIONS CONDITION          REQUIRED ACTION    COMPLETION TIME A. One            A.1 Restore subsystem  7 days subsystem          to OPERABLE inoperable.        status.          OR In accordance with the Risk Informed Completion Time Program B. Required        B.1 Be in MODE 3.      6 hours Action and associated    AND Completion Time not      B.2 Be in MODE 5.      36 hours met.
When a subsystem is declared inoperable, Condition A is entered. The 7 day Completion Time may be applied as discussed in Example 1.3-2. However, the licensee may elect to apply the Risk Informed Completion Time Program which permits calculation of a Risk Informed Completion Time (RICT) that may be used to complete the Required Action beyond the 7 day Completion Time. The RICT cannot exceed 30 days. After the 7 day Completion Time has expired, the subsystem must be restored to OPERABLE status within the RICT or Condition B must also be entered.
(continued)
CLINTON                              1.0-24              Amendment No. 238
 
Completion Times 1.3 1.3  Completion Times EXAMPLES          EXAMPLE 1.3-8  (continued)
The Risk Informed Completion Time Program requires recalculation of the RICT to reflect changing plant conditions. For planned changes, the revised RICT must be determined prior to implementation of the change in configuration. For emergent conditions, the revised RICT must be determined within the time limits of the Required Action Completion Time (i.e., not the RICT) or 12 hours after the plant configuration change, whichever is less.
If the 7 day Completion Time clock of Condition A has expired and subsequent changes in plant condition result in exiting the applicability of the Risk Informed Completion Time Program without restoring the inoperable subsystem to OPERABLE status, Condition B is also entered and the Completion Time clocks for Required Actions B.1 and B.2 start.
If the RICT expires or is recalculated to be less than the elapsed time since the Condition was entered and the inoperable subsystem has not been restored to OPERABLE status, Condition B is also entered and the Completion Time clocks for Required Actions B.1 and B.2 start. If the inoperable subsystems are restored to OPERABLE status after Condition B is entered, Condition A is exited, and therefore, the Required Actions of Condition B may be terminated.
IMMEDIATE        When "Immediately" is used as a Completion Time, the COMPLETION TIME  Required Action should be pursued without delay and in a controlled manner.
CLINTON                              1.0-25                Amendment No. 238
 
Frequency 1.4 1.0  USE AND APPLICATION 1.4  Frequency PURPOSE          The purpose of this section is to define the proper use and application of Frequency requirements.
DESCRIPTION      Each Surveillance Requirement (SR) has a specified Frequency in which the Surveillance must be met in order to meet the associated Limiting Condition for Operation (LCO). An understanding of the correct application of the specified Frequency is necessary for compliance with the SR.
The "specified Frequency" is referred to throughout this section and each of the Specifications of Section 3.0, Surveillance Requirement (SR) Applicability. The "specified Frequency" consists of the requirements of the Frequency column of each SR, as well as certain Notes in the Surveillance column that modify performance requirements.
Sometimes special situations dictate when the requirements of a Surveillance are to be met. They are "otherwise stated" conditions allowed by SR 3.0.1. They may be stated as clarifying Notes in the Surveillance, as part of the Surveillance, or both. Example 1.4-4 discusses these special situations.
Situations where a Surveillance could be required (i.e., its Frequency could expire), but where it is not possible or not desired that it be performed until sometime after the associated LCO is within its Applicability, represent potential SR 3.0.4 conflicts. To avoid these conflicts, the SR (i.e., the Surveillance or the Frequency) is stated such that it is only "required" when it can be and should be performed. With an SR satisfied, SR 3.0.4 imposes no restriction.
The use of "met" or "performed" in these instances conveys specified meanings. A Surveillance is "met" only when the acceptance criteria are satisfied. Known failure of the requirements of a Surveillance, even without a Surveillance specifically being "performed," constitutes a Surveillance not "met." "Performance" refers only to the requirement to specifically determine the ability to meet the acceptance (continued)
CLINTON                            1.0-26              Amendment No. 238
 
Frequency 1.4 1.4  Frequency DESCRIPTION    criteria. SR 3.0.4 restrictions would not apply if both the (continued)  following conditions are satisfied:
: a. The Surveillance is not required to be performed; and
: b. The Surveillance is not required to be met or, even if required to be met, is not known to be failed.
EXAMPLES      The following examples illustrate the various ways that Frequencies are specified. In these examples, the Applicability of the LCO (LCO not shown) is MODES 1, 2, and 3. The examples do not reflect the potential application of LCO 3.0.4.b.
EXAMPLE 1.4-1 SURVEILLANCE REQUIREMENTS SURVEILLANCE                    FREQUENCY Perform CHANNEL CHECK.                    12 hours Example 1.4-1 contains the type of SR most often encountered in the Technical Specifications (TS). The Frequency specifies an interval (12 hours) during which the associated Surveillance must be performed at least one time.
Performance of the Surveillance initiates the subsequent interval. Although the Frequency is stated as 12 hours, an extension of the time interval to 1.25 times the interval specified in the Frequency is allowed by SR 3.0.2 for operational flexibility. The measurement of this interval continues at all times, even when the SR is not required to be met per SR 3.0.1 (such as when the equipment is inoperable, a variable is outside specified limits, or the unit is outside the Applicability of the LCO). If the interval specified by SR 3.0.2 is exceeded while the unit is in a MODE or other specified condition in the Applicability of the LCO, and the performance of the Surveillance is not otherwise modified (refer to Examples 1.4-3 and 1.4-4), then SR 3.0.3 becomes applicable.
(continued)
CLINTON                          1.0-27            Amendment No. 238
 
Frequency 1.4 1.4  Frequency EXAMPLES      EXAMPLE 1.4-1  (continued)
If the interval as specified by SR 3.0.2 is exceeded while the unit is not in a MODE or other specified condition in the Applicability of the LCO for which performance of the SR is required, the Surveillance must be performed within the Frequency requirements of SR 3.0.2 prior to entry into the MODE or other specified condition. Failure to do so would result in a violation of SR 3.0.4.
EXAMPLE 1.4-2 SURVEILLANCE REQUIREMENTS SURVEILLANCE                    FREQUENCY Verify flow is within limits.            Once within 12 hours after 25% RTP AND 24 hours thereafter Example 1.4-2 has two Frequencies. The first is a one time performance Frequency, and the second is of the type shown in Example 1.4-1. The logical connector "AND" indicates that both Frequency requirements must be met. Each time reactor power is increased from a power level < 25% RTP to 25% RTP, the Surveillance must be performed within 12 hours.
The use of "once" indicates a single performance will satisfy the specified Frequency (assuming no other Frequencies are connected by "AND"). This type of Frequency does not qualify for the extension allowed by SR 3.0.2.
(continued)
CLINTON                          1.0-28                Amendment No. 238
 
Frequency 1.4 1.4  Frequency EXAMPLES      EXAMPLE 1.4-2  (continued)
              "Thereafter" indicates future performances must be established per SR 3.0.2, but only after a specified condition is first met (i.e., the "once" performance in this example). If reactor power decreases to < 25% RTP, the measurement of both intervals stops. New intervals start upon reactor power reaching 25% RTP.
EXAMPLE 1.4-3 SURVEILLANCE REQUIREMENTS SURVEILLANCE                    FREQUENCY
                ------------------NOTE------------------
Not required to be performed until 12 hours after  25% RTP.
Perform channel adjustment.              7 days The interval continues whether or not the unit operation is
              < 25% RTP between performances.
As the Note modifies the required performance of the Surveillance, it is construed to be part of the "specified Frequency." Should the 7 day interval be exceeded while operation is < 25% RTP, this Note allows 12 hours after power reaches  25% RTP to perform the Surveillance. The Surveillance is still considered to be within the "specified Frequency." Therefore, if the Surveillance were not performed within the 7 day interval (plus the extension allowed by SR 3.0.2), but operation was < 25% RTP, it would not constitute a failure of the SR or failure to meet the LCO. Also, no violation of SR 3.0.4 occurs when changing MODES, even with the 7 day Frequency not met, provided operation does not exceed 12 hours (plus the extension allowed by SR 3.0.2) with power  25% RTP.
(continued)
CLINTON                          1.0-29              Amendment No. 238
 
Frequency 1.4 1.4  Frequency EXAMPLES      EXAMPLE 1.4-3  (continued)
Once the unit reaches 25% RTP, 12 hours would be allowed for completing the Surveillance. If the Surveillance were not performed within this 12 hour interval (plus the extension allowed by SR 3.0.2), there would then be a failure to perform a Surveillance within the specified Frequency, and the provisions of SR 3.0.3 would apply.
EXAMPLE 1.4-4 SURVEILLANCE REQUIREMENTS SURVEILLANCE                    FREQUENCY
                ------------------NOTE-----------------
Only required to be met in MODE 1.
Verify leakage rates are within limits. 24 hours Example 1.4-4 specifies that the requirements of this Surveillance do not have to be met until the unit is in MODE 1. The interval measurement for the Frequency of this Surveillance continues at all times, as described in Example 1.4-1. However, the Note constitutes an "otherwise stated" exception to the Applicability of this Surveillance.
Therefore, if the Surveillance were not performed within the 24 hour (plus the extension allowed by SR 3.0.2) interval, but the unit was not in MODE 1, there would be no failure of the SR nor failure to meet the LCO. Therefore, no violation of SR 3.0.4 occurs when changing MODES, even with the 24 hour Frequency exceeded, provided the MODE change was not made into MODE 1. Prior to entering MODE 1 (assuming again that the 24 hour Frequency were not met), SR 3.0.4 would require satisfying the SR.
CLINTON                          1.0-30            Amendment No. 238
 
SLC System 3.1.7 3.1  REACTIVITY CONTROL SYSTEMS 3.1.7  Standby Liquid Control (SLC) System LCO  3.1.7      Two SLC subsystems shall be OPERABLE.
APPLICABILITY:    MODES 1, 2, and 3.
ACTIONS CONDITION                    REQUIRED ACTION        COMPLETION TIME A. One SLC subsystem        A.1    Restore SLC subsystem    7 days inoperable.                      to OPERABLE status.
OR In accordance with the Risk Informed Completion Time Program B. Two SLC subsystems        B.1    Restore one SLC          8 hours inoperable.                      subsystem to OPERABLE status.
C. Required Action and      C.1    Be in MODE 3.            12 hours associated Completion Time not met.            AND C.2  Be in MODE 4.            36 hours SURVEILLANCE REQUIREMENTS SURVEILLANCE                          FREQUENCY SR  3.1.7.1        Verify available volume of sodium            In accordance pentaborate solution is within the limits    with the of Figure 3.1.7-1.                          Surveillance Frequency Control Program (continued)
CLINTON                                3.1-20              Amendment No. 238
 
RPS Instrumentation 3.3.1.1 3.3  INSTRUMENTATION 3.3.1.1  Reactor Protection System (RPS) Instrumentation LCO  3.3.1.1    The RPS instrumentation for each Function in Table 3.3.1.1-1 shall be OPERABLE.
APPLICABILITY:  According to Table 3.3.1.1-1.
ACTIONS
------------------------------------NOTES-------------------------------------
: 1. Separate Condition entry is allowed for each Function.
: 2. When Functions 2.b and 2.c channels are inoperable due to the calculated power exceeding the APRM output by more than 2% RTP while operating at 21.6% RTP, entry into associated Conditions and Required Actions may be delayed for up to 2 hours.
CONDITION                  REQUIRED ACTION        COMPLETION TIME A. One or more Functions  A.1  Place one channel in    48 hours with one channel              affected Function in inoperable.                  trip.                  OR In accordance with the Risk Informed Completion Time Program B. One or more Functions  B.1  Place one channel in    6 hours with two channels            affected Function in inoperable.                  trip.                  OR In accordance with the Risk Informed Completion Time Program C. One or more Functions  C.1  Restore two channels    1 hour with three or more            in affected Function channels inoperable.          to OPERABLE status.
(continued)
CLINTON                              3.3-1                Amendment No. 238
 
RPS Instrumentation 3.3.1.1 ACTIONS  (continued)
CONDITION              REQUIRED ACTION        COMPLETION TIME D. Required Action and  D.1 Enter the Condition    Immediately associated              referenced in Completion Time of      Table 3.3.1.1-1 for Condition A, B, or C    the channel.
not met.
E. As required by      E.1 Reduce THERMAL POWER  8 hours Required Action D.1      to < 33.3% RTP.
and referenced in Table 3.3.1.1-1.
F. As required by      F.1 Reduce THERMAL POWER  8 hours Required Action D.1      to < 21.6% RTP.
and referenced in Table 3.3.1.1-1.
G. As required by      G.1 Be in MODE 2.          8 hours Required Action D.1 and referenced in Table 3.3.1.1-1.
H. As required by      H.1 Be in MODE 3.          12 hours Required Action D.1 and referenced in Table 3.3.1.1-1.
I. As required by      I.1 Initiate action to    Immediately Required Action D.1      fully insert all and referenced in        insertable control Table 3.3.1.1-1.        rods in core cells containing one or more fuel assemblies.
CLINTON                          3.3-2                  Amendment No. 238
 
EOC-RPT Instrumentation 3.3.4.1 3.3  INSTRUMENTATION 3.3.4.1  End of Cycle Recirculation Pump Trip (EOC-RPT) Instrumentation LCO  3.3.4.1    Four channels for each EOC-RPT instrumentation Function listed below shall be OPERABLE:
: a. Turbine Stop Valve (TSV) Closure; and
: b. Turbine Control Valve (TCV) Fast Closure, Trip Oil Pressure-Low.
APPLICABILITY:    THERMAL POWER  33.3% RTP with any recirculation pump in fast speed.
ACTIONS
------------------------------------NOTE -------------------------------------
Separate Condition entry is allowed for each Function.
CONDITION                  REQUIRED ACTION          COMPLETION TIME A. One or more Functions  A.1  Restore channel to        48 hours with one required            OPERABLE status.
channel inoperable.                                    OR In accordance with the Risk Informed Completion Time Program OR A.2  --------NOTE---------
Not applicable if inoperable channel is the result of an inoperable breaker.
Place one channel in      48 hours affected Function in trip.                    OR In accordance with the Risk Informed Completion Time Program (continued)
CLINTON                              3.3-25                  Amendment No. 238
 
EOC-RPT Instrumentation 3.3.4.1 ACTIONS  (continued)
CONDITION                  REQUIRED ACTION          COMPLETION TIME B. One or more Functions    B.1    Place one channel in    6 hours with two channels                affected Function in inoperable.                      trip.                    OR In accordance with the Risk Informed Completion Time Program C. One or more Functions    C.1    Restore two channels    2 hours with three or more              in affected Function channels inoperable.            to OPERABLE status.
D. Required Action and      D.1    Remove the associated    8 hours associated Completion            recirculation pump Time not met.                    fast speed breaker from service.
OR D.2    Reduce THERMAL POWER    8 hours to < 33.3% RTP.
SURVEILLANCE REQUIREMENTS
------------------------------------NOTE -------------------------------------
When a channel is placed in an inoperable status solely for performance of required Surveillances, entry into associated Conditions and Required Actions may be delayed for up to 6 hours, provided the associated Function maintains EOC-RPT trip capability.
SURVEILLANCE                              FREQUENCY SR  3.3.4.1.1      Perform CHANNEL FUNCTIONAL TEST.            In accordance with the Surveillance Frequency Control Program (continued)
CLINTON                              3.3-26                  Amendment No. 238
 
ECCS Instrumentation 3.3.5.1 ACTIONS  (continued)
CONDITION              REQUIRED ACTION          COMPLETION TIME B. As required by      B.1 --------NOTE---------
Required Action A.1    Only applicable for and referenced in      Functions 1.a, 1.b, Table 3.3.5.1-1.        2.a, and 2.b.
Declare supported        1 hour from feature(s) inoperable    discovery of when its redundant        loss of feature ECCS initiation  initiation capability is            capability for inoperable.              feature(s) in both divisions AND B.2 --------NOTE---------
Only applicable for Functions 3.a and 3.b.
Declare High Pressure    1 hour from Core Spray (HPCS)        discovery of System inoperable.        loss of HPCS initiation capability AND B.3 Place channel in trip. 24 hours OR
                                                        ------NOTE-----
Not applicable when trip capability is not maintained.
In accordance with the Risk Informed Completion Time Program (continued)
CLINTON                        3.3-32                  Amendment No. 238
 
ECCS Instrumentation 3.3.5.1 ACTIONS  (continued)
CONDITION              REQUIRED ACTION        COMPLETION TIME C. As required by      C.1 ---------NOTE--------
Required Action A.1    Only applicable for and referenced in      Functions 1.c, 1.d, Table 3.3.5.1-1.        2.c, and 2.d.
Declare supported        1 hour from feature(s) inoperable    discovery of when its redundant      loss of feature ECCS            initiation initiation capability    capability for is inoperable.          feature(s) in both divisions AND C.2 Restore channel to      24 hours OPERABLE status.
OR
                                                        ------NOTE-----
Not applicable when trip capability is not maintained.
In accordance with the Risk Informed Completion Time Program (continued)
CLINTON                          3.3-33                  Amendment No. 238
 
ECCS Instrumentation 3.3.5.1 ACTIONS  (continued)
CONDITION                REQUIRED ACTION        COMPLETION TIME D. As required by      D.1  --------NOTE--------
Required Action A.1      Only applicable if and referenced in        HPCS pump suction is Table 3.3.5.1-1.          not aligned to the suppression pool.
Declare HPCS System    1 hour from inoperable.            discovery of loss of HPCS initiation capability AND D.2.1 Place channel in        24 hour trip.
OR
                                                        ------NOTE-----
Not applicable when trip capability is not maintained.
In accordance with the Risk Informed Completion Time Program OR D.2.2 Align the HPCS pump    24 hours suction to the suppression pool.
(continued)
CLINTON                          3.3-34                Amendment No. 238
 
ECCS Instrumentation 3.3.5.1 ACTIONS  (continued)
CONDITION              REQUIRED ACTION        COMPLETION TIME E. As required by      E.1 --------NOTE---------
Required Action A.1    Only applicable for and referenced in      Functions 1.e, 1.f, Table 3.3.5.1-1.        and 2.e.
Declare supported        1 hour from feature(s) inoperable    discovery of when its redundant      loss of feature ECCS            initiation initiation capability    capability for is inoperable.          feature(s) in both divisions AND E.2 Restore channel to      7 days OPERABLE status.
OR
                                                        ------NOTE-----
Not applicable when trip capability is not maintained.
In accordance with the Risk Informed Completion Time Program (continued)
CLINTON                        3.3-35                  Amendment No. 238
 
ECCS Instrumentation 3.3.5.1 ACTIONS  (continued)
CONDITION              REQUIRED ACTION      COMPLETION TIME F. As required by      F.1 Declare Automatic      1 hour from Required Action A.1    Depressurization      discovery of and referenced in      System (ADS) valves    loss of ADS Table 3.3.5.1-1.        inoperable.            initiation capability in both trip systems AND F.2 Place channel in      96 hours or in trip.                  accordance with the Risk Informed Completion Time Program from discovery of inoperable channel concurrent with HPCS or reactor core isolation cooling (RCIC) inoperable AND
                                                      ------NOTE-----
The Risk Informed Completion Time Program is not applicable when trip capability is not maintained.
8 days or in accordance with the Risk Informed Completion Time Program (continued)
CLINTON                        3.3-36                Amendment No. 238
 
ECCS Instrumentation 3.3.5.1 ACTIONS  (continued)
CONDITION              REQUIRED ACTION        COMPLETION TIME G. As required by      G.1 --------NOTES--------
Required Action A.1    Only applicable for and referenced in      Functions 4.c, 4.e, Table 3.3.5.1-1.        4.f, 4.g, 5.c, 5.e, and 5.f.
Declare ADS valves      1 hour from inoperable.              discovery of loss of ADS initiation capability in both trip systems AND G.2 Restore channel to      96 hours or in OPERABLE status.        accordance with the Risk Informed Completion Time Program from discovery of inoperable channel concurrent with HPCS or RCIC inoperable AND
                                                        ------NOTE-----
The Risk Informed Completion Time Program is not applicable when trip capability is not maintained.
8 days or in accordance with the Risk Informed Completion Time Program (continued)
CLINTON                        3.3-37                  Amendment No. 238
 
ECCS Instrumentation 3.3.5.1 ACTIONS  (continued)
CONDITION            REQUIRED ACTION        COMPLETION TIME H. Required Action and  H.1 Declare associated      Immediately associated Completion    supported feature(s)
Time of Condition B,      inoperable.
C, D, E, F, or G not met.
CLINTON                        3.3-37a                Amendment No. 238
 
ECCS Instrumentation 3.3.5.1 This page intentionally left blank.
CLINTON              3.3-37b                  Amendment No. 238
 
RCIC System Instrumentation 3.3.5.3 3.3  INSTRUMENTATION 3.3.5.3  Reactor Core Isolation Cooling (RCIC) System Instrumentation LCO  3.3.5.3    The RCIC System instrumentation for each Function in Table 3.3.5.3-1 shall be OPERABLE.
APPLICABILITY:  MODE 1, MODES 2 and 3 with reactor steam dome pressure > 150 psig.
ACTIONS
------------------------------------NOTE--------------------------------------
Separate Condition entry is allowed for each channel.
CONDITION                  REQUIRED ACTION          COMPLETION TIME A. One or more channels  A.1  Enter the Condition      Immediately inoperable.                referenced in Table 3.3.5.3-1 for the channel.
B. As required by        B.1  Declare RCIC System      1 hour from Required Action A.1        inoperable.              discovery of and referenced in                                    loss of RCIC Table 3.3.5.3-1.                                      initiation capability AND B.2  Place channel in          24 hours trip.
OR
                                                            ------NOTE-----
Not applicable when trip capability is not maintained.
In accordance with the Risk Informed Completion Time Program (continued)
CLINTON                            3.3-45                  Amendment No. 238
 
RCIC System Instrumentation 3.3.5.3 ACTIONS  (continued)
CONDITION                  REQUIRED ACTION          COMPLETION TIME C. As required by      C.1    Restore channel to        24 hours Required Action A.1        OPERABLE status.
and referenced in Table 3.3.5.3-1.
D. As required by      D.1    ---------NOTE----------
Required Action A.1        Only applicable if and referenced in          RCIC pump suction is Table 3.3.5.3-1.            not aligned to the suppression pool.
Declare RCIC System      1 hour from inoperable.              discovery of loss of RCIC initiation capability AND D.2.1 Place channel in          24 hours trip.
OR
                                                            ------NOTE-----
Not applicable when trip capability is not maintained.
In accordance with the Risk Informed Completion Time Program OR D.2.2 Align RCIC pump            24 hours suction to the suppression pool.
E. Required Action and  E.1    Declare RCIC System      Immediately associated                  inoperable.
Completion Time of Condition B, C, or D not met.
CLINTON                            3.3-46                  Amendment No. 238
 
Primary Containment and Drywell Isolation Instrumentation 3.3.6.1 3.3  INSTRUMENTATION 3.3.6.1  Primary Containment and Drywell Isolation Instrumentation LCO  3.3.6.1      The primary containment and drywell isolation instrumentation for each Function in Table 3.3.6.1-1 shall be OPERABLE.
APPLICABILITY:    According to Table 3.3.6.1-1.
ACTIONS
-------------------------------------NOTE-------------------------------------
Separate Condition entry is allowed for each channel.
CONDITION                  REQUIRED ACTION          COMPLETION TIME
-----------NOTE----------    A.1    Place one channel in    48 hours Only applicable to Main              affected Function in Steam Line (MSL) isolation          trip.                  OR Functions.
-------------------------                                    In accordance with the Risk A. One or more Functions                                    Informed with one channel                                        Completion Time inoperable.                                              Program
-----------NOTE----------    B.1    Place one channel in    6 hours Only applicable to MSL              affected Function in isolation Functions.                trip.                  OR In accordance B. One or more Functions                                  with the Risk with two channels                                      Informed inoperable.                                            Completion Time Program
-----------NOTE----------    C.1    Restore two channels    1 hour Only applicable to MSL              in affected Function isolation Functions.                to OPERABLE status.
C. One or more Functions with three or more channels inoperable.
(continued)
CLINTON                              3.3-49                  Amendment No. 238
 
Primary Containment and Drywell Isolation Instrumentation 3.3.6.1 ACTIONS  (continued)
CONDITION                    REQUIRED ACTION        COMPLETION TIME
------------NOTE----------  D.1      Place channel in trip. 24 hours Not applicable to MSL isolation Functions.                                        OR
                                                              ------NOTE-----
D. One or more required                                    Not applicable channels inoperable.                                    when trip capability is not maintained.
In accordance with the Risk Informed Completion Time Program
------------NOTE---------    E.1      Restore isolation      1 hour Not applicable to MSL                capability.
isolation Functions.
E. One or more automatic Functions with isolation capability not maintained.
F. Required Action and      F.1      Enter the Condition    Immediately associated Completion            referenced in Time of Condition A,              Table 3.3.6.1-1 for B, C, D, or E not                the channel.
met.
G. As required by          G.1      Isolate associated    12 hours Required Action F.1              MSL.
and referenced in Table 3.3.6.1-1.        OR G.2.1    Be in MODE 3.          12 hours AND G.2.2    Be in MODE 4.          36 hours (continued)
CLINTON                              3.3-50                  Amendment No. 238
 
Primary Containment and Drywell Isolation Instrumentation 3.3.6.1 ACTIONS  (continued)
CONDITION                  REQUIRED ACTION        COMPLETION TIME H. As required by          H.1  Be in MODE 2.            6 hours Required Action F.1 and referenced in Table 3.3.6.1-1.
I. As required by          I.1  Isolate the affected      1 hour Required Action F.1          penetration flow and referenced in            path(s).
Table 3.3.6.1-1.
J. As required by          J.1      Isolate the affected  24 hours Required Action F.1              penetration flow and referenced in                path(s).
Table 3.3.6.1-1.
K. As required by          K.1      Be in MODE 3.          12 hours Required Action F.1 and referenced in      AND Table 3.3.6.1-1.
K.2      Be in MODE 4.          36 hours OR Required Action and associated Completion Time of Condition I or J not met.
L. As required by          L.1      Declare associated    1 hour Required Action F.1              standby liquid and referenced in                control subsystem Table 3.3.6.1-1.                inoperable.
OR L.2      Isolate the Reactor    1 hour Water Cleanup System.
M. As required by          M.1      Initiate action to    Immediately Required Action F.1              restore channel to and referenced in                OPERABLE status.
Table 3.3.6.1-1.
OR (continued)
CLINTON                              3.3-51                  Amendment No. 238
 
Primary Containment and Drywell Isolation Instrumentation 3.3.6.1 ACTIONS CONDITION                  REQUIRED ACTION        COMPLETION TIME M.    (continued)          M.2      Initiate action to    Immediately isolate the Residual Heat Removal (RHR)
Shutdown Cooling System suction from the reactor vessel.
OR M.3.1    Initiate action to    Immediately restore secondary containment to OPERABLE status.
AND M.3.2    Initiate action to    Immediately restore one standby gas treatment (SGT) subsystem to OPERABLE status.
AND M.3.3    Initiate action to    Immediately restore isolation capability in each required secondary containment and secondary containment bypass penetration flow path not isolated.
AND M.3.4    ---------NOTE-------
Entry and exit is permissible under administrative control.
Initiate action to    Immediately close one door in the upper containment personnel air lock.
(continued)
CLINTON                              3.3-52                  Amendment No. 238
 
Primary Containment and Drywell Isolation Instrumentation 3.3.6.1 ACTIONS  (continued)
CONDITION                  REQUIRED ACTION          COMPLETION TIME N. As required by          N.1    Isolate the affected    Immediately Required Action F.1              penetration flow and referenced in                path(s).
Table 3.3.6.1-1.
OR N.2    Suspend movement of    Immediately recently irradiated fuel assemblies in the primary and secondary containment.
SURVEILLANCE REQUIREMENTS
------------------------------------NOTES------------------------------------
: 1. Refer to Table 3.3.6.1-1 to determine which SRs apply for each Primary Containment and Drywell Isolation Function.
: 2. When a channel is placed in an inoperable status solely for performance of required Surveillances, entry into associated Conditions and Required Actions may be delayed for up to 6 hours, provided the associated Function maintains isolation capability.
SURVEILLANCE                            FREQUENCY SR  3.3.6.1.1      Perform CHANNEL CHECK.                    In accordance with the Surveillance Frequency Control Program SR  3.3.6.1.2      Perform CHANNEL FUNCTIONAL TEST.          In accordance with the Surveillance Frequency Control Program (continued)
CLINTON                              3.3-53                  Amendment No. 238
 
Primary Containment and Drywell Isolation Instrumentation 3.3.6.1 SURVEILLANCE REQUIREMENTS  (continued)
SURVEILLANCE                            FREQUENCY SR  3.3.6.1.3    Calibrate the analog trip module.          In accordance with the Surveillance Frequency Control Program SR  3.3.6.1.4    Perform CHANNEL CALIBRATION.              In accordance with the Surveillance Frequency Control Program SR  3.3.6.1.5    Perform CHANNEL CALIBRATION.              In accordance with the Surveillance Frequency Control Program SR  3.3.6.1.6    Perform LOGIC SYSTEM FUNCTIONAL TEST.      In accordance with the Surveillance Frequency Control Program SR  3.3.6.1.7    ---------------NOTE---------------------
Channel sensors are excluded.
Verify the ISOLATION SYSTEM RESPONSE      In accordance TIME for the main steam isolation valves  with the is within limits.                          Surveillance Frequency Control Program SR  3.3.6.1.8    Perform CHANNEL CALIBRATION.              In accordance with the Surveillance Frequency Control Program CLINTON                              3.3-54                  Amendment No. 238
 
RHR Containment Spray System Instrumentation 3.3.6.3 3.3  INSTRUMENTATION 3.3.6.3  Residual Heat Removal (RHR) Containment Spray System Instrumentation LCO  3.3.6.3    The RHR Containment Spray System instrumentation for each Function in Table 3.3.6.3-1 shall be OPERABLE.
APPLICABILITY:  MODES 1, 2, and 3.
ACTIONS
-------------------------------------NOTE-------------------------------------
Separate Condition entry is allowed for each channel.
CONDITION                  REQUIRED ACTION        COMPLETION TIME A. One or more channels    A.1  Enter the Condition      Immediately inoperable.                  referenced in Table 3.3.6.3-1 for the channel.
B. As required by          B.1  Declare associated        1 hour from Required Action A.1          RHR containment spray    discovery of and referenced in            subsystem inoperable. loss of RHR Table 3.3.6.3-1.                                        containment spray initiation capability in both trip systems AND B.2  Place channel in          24 hours trip.
OR
                                                            ------NOTE-----
Not applicable when trip capability is not maintained.
In accordance with the Risk Informed Completion Time Program (continued)
CLINTON                              3.3-65                  Amendment No. 238
 
RHR Containment Spray System Instrumentation 3.3.6.3 ACTIONS  (continued)
CONDITION                REQUIRED ACTION        COMPLETION TIME C. As required by        C.1  --------NOTE---------
Required Action A.1        Only applicable for and referenced in          Functions 4 and 5.
Table 3.3.6.3-1.          ---------------------
Declare associated      1 hour from RHR containment spray    discovery of subsystem inoperable. loss of RHR containment spray initiation capability in both trip systems AND 24 hours C.2  Restore channel to OPERABLE status.          OR
                                                          ------NOTE-----
Not applicable when trip capability is not maintained.
In accordance with the Risk Informed Completion Time Program D. Required Action and  D.1  Declare associated      Immediately associated Completion      RHR containment Time of Condition B        spray subsystem or C not met.              inoperable.
CLINTON                          3.3-66                  Amendment No. 238
 
SPMU System Instrumentation 3.3.6.4 3.3  INSTRUMENTATION 3.3.6.4  Suppression Pool Makeup (SPMU) System Instrumentation LCO  3.3.6.4    The SPMU System instrumentation for each Function in Table 3.3.6.4-1 shall be OPERABLE.
APPLICABILITY:  MODES 1, 2, and 3.
ACTIONS
-------------------------------------NOTE-------------------------------------
Separate Condition entry is allowed for each channel.
CONDITION                  REQUIRED ACTION          COMPLETION TIME A. One or more channels    A.1  Enter the Condition        Immediately inoperable.                  referenced in Table 3.3.6.4-1 for the channel.
B. As required by          B.1    Declare associated        1 hour from Required Action A.1            SPMU subsystem            discovery of and referenced in              inoperable.              loss of SPMU Table 3.3.6.4-1.                                        initiation capability in both trip systems AND B.2    Place channel in          24 hours trip.
OR
                                                              ------NOTE-----
Not applicable when trip capability is not maintained.
In accordance with the Risk Informed Completion Time Program (continued)
CLINTON                              3.3-69                  Amendment No. 238
 
SPMU System Instrumentation 3.3.6.4 ACTIONS  (continued)
CONDITION              REQUIRED ACTION          COMPLETION TIME C. As required by        C.1 --------NOTE---------
Required Action A.1      Only applicable for and referenced in        Function 4.
Table 3.3.6.4-1.          ---------------------
Declare associated        1 hour from SPMU subsystem            discovery of inoperable.              loss of SPMU initiation capability in both trip systems AND C.2 Restore channel to        24 hours OPERABLE status.
OR
                                                        ------NOTE-----
Not applicable when trip capability is not maintained.
In accordance with the Risk Informed Completion Time Program D. Required Action and  D.1 Declare associated        Immediately associated Completion    SPMU subsystem Time of Condition B      inoperable.
or C not met.
CLINTON                        3.3-70                  Amendment No. 238
 
Relief and LLS Instrumentation 3.3.6.5 3.3  INSTRUMENTATION 3.3.6.5  Relief and Low-Low Set (LLS) Instrumentation LCO  3.3.6.5    Two relief and LLS instrumentation trip systems shall be OPERABLE.
APPLICABILITY:  MODES 1, 2, and 3.
ACTIONS CONDITION                  REQUIRED ACTION          COMPLETION TIME A. One trip system        A.1  Restore trip system        7 days inoperable.                  to OPERABLE status.
OR In accordance with the Risk Informed Completion Time Program OR A.2  Declare associated        7 days relief and LLS valve(s) inoperable.
B. Required Action and    B.1  Be in MODE 3.              12 hours associated Completion Time of Condition A    AND not met.
B.2  Be in MODE 4.              36 hours OR Two trip systems inoperable.
CLINTON                              3.3-74                  Amendment No. 238
 
LOP Instrumentation 3.3.8.1 3.3  INSTRUMENTATION 3.3.8.1  Loss of Power (LOP) Instrumentation LCO  3.3.8.1    The LOP instrumentation for each Function in Table 3.3.8.1-1 shall be OPERABLE.
APPLICABILITY:    MODES 1, 2, and 3, When the associated diesel generator (DG) is required to be OPERABLE by LCO 3.8.2, "AC Sources-Shutdown."
ACTIONS
-------------------------------------NOTE-------------------------------------
Separate Condition entry is allowed for each channel.
CONDITION                  REQUIRED ACTION        COMPLETION TIME A. One or more channels    A.1    Place channel in trip. 1 hour inoperable.
OR
                                                            ------NOTE-----
Not applicable when trip capability is not maintained.
In accordance with the Risk Informed Completion Time Program AND (continued)
CLINTON                              3.3-78                  Amendment No. 238
 
LOP Instrumentation 3.3.8.1 ACTIONS CONDITION              REQUIRED ACTION          COMPLETION TIME A.  (continued)          A.2 ---------NOTE----------
Only applicable for Functions 1.c, 1.d, 1.e, 2.c, 2.d, and 2.e Restore channel to        7 days OPERABLE status.
OR
                                                        ------NOTE-----
Not applicable when trip capability is not maintained.
In accordance with the Risk Informed Completion Time Program B. Required Action and  B.1 Declare associated DG    Immediately associated Completion    inoperable.
Time not met.
CLINTON                        3.3-79                  Amendment No. 238
 
LOP Instrumentation 3.3.8.1 SURVEILLANCE REQUIREMENTS
-------------------------------------NOTES------------------------------------
: 1. Refer to Table 3.3.8.1-1 to determine which SRs apply for each LOP Function.
: 2. When a channel is placed in an inoperable status solely for performance of required Surveillances, entry into associated Conditions and Required Actions may be delayed for up to 2 hours provided the associated Function maintains DG initiation capability.
SURVEILLANCE                            FREQUENCY SR  3.3.8.1.1    Deleted SR  3.3.8.1.2    Perform CHANNEL FUNCTIONAL TEST.          In accordance with the Surveillance Frequency Control Program SR  3.3.8.1.3    Perform CHANNEL CALIBRATION.              In accordance with the Surveillance Frequency Control Program SR  3.3.8.1.4    Perform LOGIC SYSTEM FUNCTIONAL TEST.      In accordance with the Surveillance Frequency Control Program CLINTON                            3.3-80                  Amendment No. 238
 
LOP Instrumentation 3.3.8.1 Table 3.3.8.1-1 (page 1 of 1)
Loss of Power Instrumentation REQUIRED CHANNELS PER        SURVEILLANCE                ALLOWABLE FUNCTION          DIVISION      REQUIREMENTS                  VALUE
: 1. Divisions 1 and 2 - 4.16 kV Emergency Bus Undervoltage
: a. Loss of Voltage - 4.16 kV    6        SR  3.3.8.1.3      2345 V and  3395 V basis                                  SR  3.3.8.1.4
: b. Loss of Voltage - Time        6        SR  3.3.8.1.3      5.0 seconds Delay                                  SR  3.3.8.1.4
: c. Degraded Voltage              2        SR  3.3.8.1.2      4102.2 V and  4109.3 V Reset - 4.16 kV basis                  SR  3.3.8.1.3 SR  3.3.8.1.4
: d. Degraded Voltage              2        SR  3.3.8.1.2      4051 V Drop-out - 4.16 kV basis              SR  3.3.8.1.3 SR  3.3.8.1.4
: e. Degraded Voltage-Time        1        SR  3.3.8.1.2      14 seconds and  16 seconds Delay                                  SR  3.3.8.1.3 SR  3.3.8.1.4
: 2. Division 3 - 4.16 kV Emergency Bus Undervoltage
: a. Loss of Voltage - 4.16 kV    4        SR  3.3.8.1.3      2345 V and  2730 V basis                                  SR  3.3.8.1.4
: b. Loss of Voltage - Time        1        SR  3.3.8.1.3      3.0 seconds Delay                                  SR  3.3.8.1.4
: c. Degraded Voltage              2        SR  3.3.8.1.2      4102.2 V and  4109.3 V Reset - 4.16 kV basis                  SR  3.3.8.1.3 SR  3.3.8.1.4
: d. Degraded Voltage              2        SR  3.3.8.1.2      4051 V Drop-out - 4.16 kV basis              SR  3.3.8.1.3 SR  3.3.8.1.4
: e. Degraded Voltage - Time      1        SR  3.3.8.1.2      13.2 seconds and  16.8 Delay                                  SR  3.3.8.1.3    seconds SR  3.3.8.1.4 CLINTON                                  3.3-81                        Amendment No. 238
 
RPS Electric Power Monitoring 3.3.8.2 3.3  INSTRUMENTATION 3.3.8.2  Reactor Protection System (RPS) Electric Power Monitoring LCO  3.3.8.2    One RPS electric power monitoring assembly shall be OPERABLE for each inservice RPS special solenoid power supply or alternate power supply.
APPLICABILITY:    MODES 1, 2, and 3, MODES 4 and 5 with any control rod withdrawn from a core cell containing one or more fuel assemblies.
ACTIONS CONDITION                  REQUIRED ACTION          COMPLETION TIME A. One or both inservice  A.1    Remove associated        1 hour power supplies with            inservice power the electric power            supply(s) from monitoring assembly            service.
inoperable.
B. Required Action and    -------------NOTE------------
associated Completion  LCO 3.0.4a is not Time of Condition A    applicable when entering not met in MODE 1, 2,  MODE 3 or 3.                  -----------------------------
B.1    Be in MODE 3.            12 hours C. Required Action and      C.1    Initiate action to        Immediately associated Completion          fully insert all Time of Condition A            insertable control rods not met in MODE 4 or 5          in core cells with any control rod            containing one or more withdrawn from a core          fuel assemblies.
cell containing one or more fuel assemblies.
Amendment No. 238 CLINTON                              3.3-82
 
RPS Electric Power Monitoring 3.3.8.2 SURVEILLANCE REQUIREMENTS SURVEILLANCE                            FREQUENCY SR  3.3.8.2.1    -----------------NOTE-------------------
Only required to be performed prior to entering MODE 2 or 3 from MODE 4, when in MODE 4 for  24 hours.
Perform CHANNEL FUNCTIONAL TEST.          In accordance with the Surveillance Frequency Control Program SR  3.3.8.2.2    Perform CHANNEL CALIBRATION. The          In accordance Allowable Values shall be:                with the Surveillance
: a. Overvoltage                            Frequency Control Program Bus A  127.3 V Bus B  126.7 V
: b. Undervoltage Bus A  115.0 V Bus B  114.7 V
: c. Underfrequency (with time delay  4.0 seconds)
Bus A  57 Hz Bus B  57 Hz SR  3.3.8.2.3    Perform a system functional test.          In accordance with the Surveillance Frequency Control Program CLINTON                              3.3-83                  Amendment No. 238
 
ECCS  Operating 3.5.1 3.5  EMERGENCY CORE COOLING SYSTEMS (ECCS), REACTOR PRESSURE VESSEL (RPV)
WATER INVENTORY CONTROL, AND REACTOR CORE ISOLATION COOLING (RCIC)
SYSTEM 3.5.1  ECCS  Operating LCO  3.5.1        Each ECCS injection/spray subsystem and the Automatic Depressurization System (ADS) function of seven safety/
relief valves shall be OPERABLE.
                  ----------------------------NOTE----------------------------
One low pressure coolant injection (LPCI) subsystem may be inoperable during alignment and operation for decay heat removal with reactor steam dome pressure less than the residual heat removal cut in permissive pressure.
APPLICABILITY:    MODE 1, MODES 2 and 3, except ADS valves are not required to be OPERABLE with reactor steam dome pressure  150 psig.
ACTIONS
-------------------------------------NOTE-------------------------------------
LCO 3.0.4.b is not applicable to High Pressure Core Spray (HPCS).
CONDITION                  REQUIRED ACTION          COMPLETION TIME A. One low pressure ECCS    A.1      Restore low pressure  7 days injection/spray                    ECCS injection/spray subsystem inoperable.              subsystem to OPERABLE  OR status.
In accordance with the Risk Informed Completion Time Program (continued)
CLINTON                                3.5-1                  Amendment No. 238
 
ECCS  Operating 3.5.1 ACTIONS  (continued)
CONDITION                REQUIRED ACTION        COMPLETION TIME B. HPCS System            B.1      Verify by            1 hour inoperable.                    administrative means RCIC System is OPERABLE when RCIC is required to be OPERABLE.
AND B.2      Restore HPCS System  14 days to OPERABLE status.
OR In accordance with the Risk Informed Completion Time Program C. Two ECCS injection    C.1      Restore one ECCS      72 hours subsystems inoperable.          injection/spray subsystem to OPERABLE OR OR                              status.
In accordance One ECCS injection and                                with the Risk one ECCS spray                                        Informed subsystem inoperable.                                Completion Time Program D. Required Action and    -------------NOTE------------
associated Completion  LCO 3.0.4.a is not Time of Condition A,  applicable when entering B, or C not met.      MODE 3.
D.1      Be in MODE 3.        12 hours E. One ADS valve          E.1      Restore ADS valve to  14 days inoperable.                    OPERABLE status.
OR In accordance with the Risk Informed Completion Time Program (continued)
CLINTON                            3.5-2                  Amendment No. 238
 
ECCS  Operating 3.5.1 ACTIONS  (continued)
CONDITION                REQUIRED ACTION        COMPLETION TIME F. One ADS valve          F.1      Restore ADS valve to  72 hours inoperable.                    OPERABLE status.
OR AND In accordance One low pressure ECCS                                with the Risk injection/spray                                      Informed subsystem inoperable.                                Completion Time Program OR F.2      Restore low pressure  72 hours ECCS injection/spray subsystem to OPERABLE OR status.
In accordance with the Risk Informed Completion Time Program G. Two or more ADS valves -------------NOTE------------
inoperable.            LCO 3.0.4.a is not applicable when entering OR                    MODE 3.
Required Action and associated Completion  G.1      Be in MODE 3.        12 hours Time of Condition E or F not met.
(continued)
CLINTON                            3.5-3                  Amendment No. 238
 
ECCS  Operating 3.5.1 ACTIONS  (continued)
CONDITION            REQUIRED ACTION    COMPLETION TIME H. HPCS and Low Pressure  H.1  Enter LCO 3.0.3. Immediately Core Spray (LPCS)
Systems inoperable.
OR Three or more ECCS injection/spray subsystems inoperable.
OR HPCS System and one or more ADS valves inoperable.
OR Two or more ECCS injection/spray subsystems and one or more ADS valves inoperable.
CLINTON                        3.5-4            Amendment No. 238
 
ECCS  Operating 3.5.1 SURVEILLANCE REQUIREMENTS SURVEILLANCE                            FREQUENCY SR  3.5.1.1    Verify, for each ECCS injection/spray        In accordance subsystem, locations susceptible to gas      with the accumulation are sufficiently filled with    Surveillance water.                                      Frequency Control Program SR  3.5.1.2    --------------------NOTE-------------------
Not required to be met for system vent flow paths opened under administrative control.
Verify each ECCS injection/spray subsystem  In accordance manual, power operated, and automatic valve  with the in the flow path, that is not locked,        Surveillance sealed, or otherwise secured in position,    Frequency is in the correct position.                  Control Program SR  3.5.1.3    Verify ADS accumulator supply pressure is    In accordance 140 psig.                                  with the Surveillance Frequency Control Program SR  3.5.1.4    Verify each ECCS pump develops the          In accordance specified flow rate with the specified pump  with the differential pressure.                      INSERVICE TESTING PROGRAM PUMP DIFFERENTIAL SYSTEM      FLOW RATE        PRESSURE LPCS        5010 gpm      290 psid LPCI        5050 gpm      113 psid HPCS        5010 gpm      363 psid (continued)
CLINTON                              3.5-5                  Amendment No. 238
 
ECCS  Operating 3.5.1 SURVEILLANCE REQUIREMENTS  (continued)
SURVEILLANCE                            FREQUENCY SR  3.5.1.5    -------------------NOTE--------------------
Vessel injection/spray may be excluded.
Verify each ECCS injection/spray subsystem  In accordance actuates on an actual or simulated          with the automatic initiation signal.                Surveillance Frequency Control Program SR  3.5.1.6    -------------------NOTE--------------------
Valve actuation may be excluded.
Verify the ADS actuates on an actual or      In accordance simulated automatic initiation signal.      with the Surveillance Frequency Control Program SR  3.5.1.7    -------------------NOTE--------------------
Not required to be performed until 12 hours after reactor steam pressure and flow are adequate to perform the test.
Verify each ADS valve actuator strokes when  In accordance manually actuated.                          with the Surveillance Frequency Control Program SR  3.5.1.8    -------------------NOTE--------------------
ECCS actuation instrumentation is excluded.
Verify the ECCS RESPONSE TIME for each ECCS  In accordance injection/spray subsystem is within limits. with the Surveillance Frequency Control Program CLINTON                              3.5-6                  Amendment No. 238
 
RPV Water Inventory Control 3.5.2 3.5  EMERGENCY CORE COOLING SYSTEMS (ECCS), REACTOR PRESSURE VESSEL (RPV)
WATER INVENTORY CONTROL, AND REACTOR CORE ISOLATION COOLING (RCIC)
SYSTEM 3.5.2  RPV Water Inventory Control LCO  3.5.2      DRAIN TIME of RPV water inventory to the top of active fuel (TAF) shall be  36 hours.
AND One ECCS injection/spray subsystem shall be OPERABLE.
                  ----------------------------NOTE----------------------------
One low pressure coolant injection (LPCI) subsystem may be inoperable during alignment and operation for decay heat removal with reactor steam dome pressure less than the residual heat removal cut in permissive pressure.
APPLICABILITY:    MODES 4 and 5.
ACTIONS CONDITION                  REQUIRED ACTION          COMPLETION TIME A. Required ECCS            A.1      Restore required ECCS  4 hours injection/spray                  injection/spray subsystem inoperable.            subsystem to OPERABLE status.
B. Required Action and      B.1      Initiate action to      Immediately associated Completion            establish a method of Time of Condition A              water injection not met.                          capable of operating without offsite electrical power.
(continued)
CLINTON                              3.5-7 Amendment No. 238
 
RPV Water Inventory Control 3.5.2 ACTIONS  (continued)
CONDITION            REQUIRED ACTION          COMPLETION TIME C. DRAIN TIME < 36 hours C.1 Verify secondary          4 hours and  8 hours.            containment boundary is capable of being established in less than the DRAIN TIME.
AND C.2 Verify each secondary    4 hours containment penetration flow path is capable of being isolated in less than the DRAIN TIME.
AND C.3 Verify one standby gas    4 hours treatment (SGT) subsystem is capable of being placed in operation in less than the DRAIN TIME.
(continued)
CLINTON                        3.5-8                    Amendment No. 238
 
RPV Water Inventory Control 3.5.2 ACTIONS  (continued)
CONDITION            REQUIRED ACTION          COMPLETION TIME D. DRAIN TIME < 8 hours. D.1  ------- NOTE --------
Required ECCS injection/spray subsystem or additional method of water injection shall be capable of operating without offsite electrical power.
Initiate action to      Immediately establish an additional method of water injection with water sources capable of maintaining RPV water level > TAF for 36 hours.
AND D.2  Initiate action to      Immediately establish secondary containment boundary.
AND D.3  Initiate action to      Immediately isolate each secondary containment penetration flow path or verify it can be automatically or manually isolated from the control room.
AND D.4  Initiate action to      Immediately verify one SGT subsystem is capable of being placed in operation.
(continued)
CLINTON                        3.5-9                    Amendment No. 238
 
RPV Water Inventory Control 3.5.2 ACTIONS  (continued)
CONDITION                  REQUIRED ACTION          COMPLETION TIME E. Required Action and      E.1      Initiate action to      Immediately associated Completion            restore DRAIN TIME to Time of Condition C                36 hours.
or D not met.
OR DRAIN TIME < 1 hour.
SURVEILLANCE REQUIREMENTS SURVEILLANCE                              FREQUENCY SR  3.5.2.1    Verify DRAIN TIME  36 hours.                  In accordance with the Surveillance Frequency Control Program SR  3.5.2.2    Verify, for a required low pressure ECCS        In accordance injection/spray subsystem, the suppression      with the pool water level is  12 ft 8 inches.          Surveillance Frequency Control Program SR  3.5.2.3    Verify, for a required High Pressure Core      In accordance Spray (HPCS) System, the:                      with the Surveillance
: a. Suppression pool water level is            Frequency 12 ft 8 inches; or                      Control Program
: b. RCIC storage tank available water volume is  125,000 gal.
SR  3.5.2.4    Verify, for the required ECCS                  In accordance injection/spray subsystem, locations            with the susceptible to gas accumulation are            Surveillance sufficiently filled with water.                Frequency Control Program (continued)
CLINTON                              3.5-10                    Amendment No. 238
 
RPV Water Inventory Control 3.5.2 SURVEILLANCE REQUIREMENTS  (continued)
SURVEILLANCE                            FREQUENCY SR  3.5.2.5    --------------------NOTES------------------
: 1. Operation may be through the test return line.
: 2. Credit may be taken for normal system operation to satisfy this SR.
Operate the required ECCS injection/spray      In accordance subsystem for  10 minutes.                    with the Surveillance Frequency Control Program SR  3.5.2.6    Verify each valve credited for                In accordance automatically isolating a penetration flow    with the path actuates to the isolation position on    Surveillance an actual or simulated isolation signal.      Frequency Control Program SR  3.5.2.7    -------------------NOTE--------------------
Vessel injection/spray may be excluded.
Verify the required ECCS injection/spray      In accordance subsystem can be manually operated.            with the Surveillance Frequency Control Program CLINTON                              3.5-11                  Amendment No. 238
 
RCIC System 3.5.3 3.5  EMERGENCY CORE COOLING SYSTEMS (ECCS), REACTOR PRESSURE VESSEL (RPV)
WATER INVENTORY CONTROL, AND REACTOR CORE ISOLATION COOLING (RCIC)
SYSTEM 3.5.3  RCIC System LCO  3.5.3      The RCIC System shall be OPERABLE.
APPLICABILITY:    MODE 1, MODES 2 and 3 with reactor steam dome pressure > 150 psig.
ACTIONS
-------------------------------------NOTE-------------------------------------
LCO 3.0.4.b is not applicable to RCIC.
CONDITION                  REQUIRED ACTION          COMPLETION TIME A. RCIC System              A.1      Verify by              1 hour inoperable.                      administrative means High Pressure Core Spray System is OPERABLE.              123 AND A.2      Restore RCIC System    14 days to OPERABLE status.
OR In accordance with the Risk Informed Completion Time Program B. Required Action and      B.1      Be in MODE 3.          12 hours associated Completion Time not met.            AND B.2      Reduce reactor steam  36 hours dome pressure to 150 psig.
CLINTON                              3.5-12                  Amendment No. 238
 
RCIC System 3.5.3 SURVEILLANCE REQUIREMENTS SURVEILLANCE                            FREQUENCY SR  3.5.3.1    Verify the RCIC System locations            In accordance susceptible to gas accumulation are          with the sufficiently filled with water.              Surveillance Frequency Control Program SR  3.5.3.2    -------------------NOTE--------------------
Not required to be met for system vent flow paths opened under administrative control.
Verify each RCIC System manual, power        In accordance operated, and automatic valve in the flow    with the path, that is not locked, sealed, or        Surveillance otherwise secured in position, is in the    Frequency correct position.                            Control Program SR  3.5.3.3    -------------------NOTE--------------------
Not required to be performed until 12 hours after reactor steam pressure and flow are adequate to perform the test.
Verify, with RCIC steam supply pressure      In accordance 1045 psig and  920 psig, the RCIC pump    with the can develop a flow rate  600 gpm against a  Surveillance system head corresponding to reactor        Frequency pressure.                                    Control Program SR  3.5.3.4    -------------------NOTE--------------------
Not required to be performed until 12 hours after reactor steam pressure and flow are adequate to perform the test.
Verify, with RCIC steam supply pressure      In accordance 150 psig and  135 psig, the RCIC pump    with the can develop a flow rate  600 gpm against a  Surveillance system head corresponding to reactor        Frequency pressure.                                    Control Program (continued)
CLINTON                            3.5-13                  Amendment No. 238
 
RCIC System 3.5.3 SURVEILLANCE REQUIREMENTS  (continued)
SURVEILLANCE                          FREQUENCY SR  3.5.3.5    -------------------NOTE--------------------
Vessel injection may be excluded.
Verify the RCIC System actuates on an        In accordance actual or simulated automatic initiation    with the signal.                                      Surveillance Frequency Control Program CLINTON                              3.5-14                Amendment No. 238
 
Primary Containment Air Locks 3.6.1.2 ACTIONS  (continued)
CONDITION            REQUIRED ACTION          COMPLETION TIME C. One or more required    C.1 Initiate action to        Immediately primary containment        evaluate primary air locks inoperable      containment overall for reasons other than    leakage rate per Condition A or B.          LCO 3.6.1.1, using current air lock test results.
AND C.2 Verify a door is          1 hour closed in the affected air lock.
AND C.3 Restore air lock to      24 hours OPERABLE status.
OR
                                                          -----NOTE------
Not applicable if leakage exceeds limits or if loss of function.
In accordance with the Risk Informed Completion Time Program D. Required Action and  D.1 Be in MODE 3.            12 hours associated Completion Time of Condition A,  AND B, or C not met in MODE 1, 2, or 3.      D.2 Be in MODE 4.            36 hours (continued)
CLINTON                          3.6-6                    Amendment No. 238
 
PCIVs 3.6.1.3 ACTIONS  (continued)
CONDITION              REQUIRED ACTION      COMPLETION TIME A. One or more            A.1 Isolate the affected  4 hours or in penetration flow paths    penetration flow path accordance with with one PCIV              by use of at least    the Risk inoperable, except due    one closed and de-    Informed to leakage not within      activated automatic  Completion Time limit.                    valve, closed manual  Program except valve, blind flange,  for main steam or check valve with  line and excess flow through the      flow check valve secured.        valves (EFCVs)
AND 8 hours or in accordance with the Risk Informed Completion Time Program for main steam line AND 12 hours or in accordance with the Risk Informed Completion Time Program for EFCVs AND (continued)
CLINTON                          3.6-10              Amendment No. 238
 
PCIVs 3.6.1.3 ACTIONS CONDITION      REQUIRED ACTION      COMPLETION TIME A.    (continued)  A.2 --------NOTE---------
Isolation devices in high radiation areas may be verified by use of administrative means.
Verify the affected  Once per penetration flow path 31 days is isolated.          following isolation for isolation devices outside primary containment, drywell, and steam tunnel AND Prior to entering MODE 2 or 3 from MODE 4, if not performed within the previous 92 days, for isolation devices inside primary containment, drywell, or steam tunnel (continued)
CLINTON                  3.6-11              Amendment No. 238
 
PCIVs 3.6.1.3 ACTIONS  (continued)
CONDITION              REQUIRED ACTION      COMPLETION TIME D. One or more            D.1 Isolate the affected  24 hours penetration flow paths    penetration flow with one or more          path by use of at    OR primary containment        least one closed and purge valves not          de-activated          In accordance within purge valve        automatic valve,      with the Risk leakage limits.            closed manual valve,  Informed or blind flange.      Completion Time Program AND D.2 ---------NOTE--------
Isolation devices in high radiation areas may be verified by use of administrative means.
Verify the affected  Once per 31 penetration flow path days following is isolated.          isolation for isolation devices outside primary containment AND Prior to entering MODE 2 or 3 from MODE 4 if not performed within the previous 92 days for isolation devices inside primary containment AND (continued)
CLINTON                          3.6-13              Amendment No. 238
 
PCIVs 3.6.1.3 ACTIONS CONDITION              REQUIRED ACTION      COMPLETION TIME D.  (continued)          D.3 Perform SR 3.6.1.3.5  Once per 92 for the resilient    days following seal purge valves    isolation closed to comply with Required Action D.1.
E. Required Action and  E.1 Be in MODE 3.        12 hours associated Completion Time of Condition A,  AND B, C, or D not met in MODE 1, 2, or 3.      E.2 Be in MODE 4.        36 hours F. Required Action and  F.1 --------NOTE---------
associated Completion    LCO 3.0.3 is not Time of Condition A,      applicable.
B, C, or D not met        ---------------------
for PCIV(s) required to be OPERABLE during    Suspend movement of  Immediately movement of recently      recently irradiated irradiated fuel          fuel assemblies in assemblies in the        primary and secondary primary or secondary      containment.
containment.
CLINTON                        3.6-14              Amendment No. 238
 
LLS Valves 3.6.1.6 3.6  CONTAINMENT SYSTEMS 3.6.1.6  Low-Low Set (LLS) Valves LCO  3.6.1.6      The LLS function of five safety/relief valves shall be OPERABLE.
APPLICABILITY:    MODES 1, 2, and 3.
ACTIONS CONDITION                    REQUIRED ACTION        COMPLETION TIME A. One LLS valve            A.1  Restore LLS valve to    14 days inoperable.                    OPERABLE status.
OR In accordance with the Risk Informed Completion Time Program B. Required Action and      ------------NOTE------------
associated Completion    LCO 3.0.4.a is not Time of Condition A      applicable when entering not met.                MODE 3.
B.1  Be in MODE 3.            12 hours C. Two or more LLS valves  C.1  Be in MODE 3.            12 hours inoperable.
AND C.2  Be in MODE 4.            36 hours CLINTON                              3.6-22                  Amendment No. 238
 
RHR Containment Spray System 3.6.1.7 3.6  CONTAINMENT SYSTEMS 3.6.1.7  Residual Heat Removal (RHR) Containment Spray System LCO  3.6.1.7      Two RHR containment spray subsystems shall be OPERABLE.
                  ----------------------------NOTE----------------------------
One RHR containment spray subsystem may be inoperable during alignment and operation for decay heat removal with reactor steam dome pressure less than the residual heat removal cut in permissive pressure.
APPLICABILITY:    MODES 1, 2, and 3.
ACTIONS CONDITION                  REQUIRED ACTION          COMPLETION TIME A. One RHR containment    A.1  Restore RHR                7 days spray subsystem              containment spray inoperable.                  subsystem to OPERABLE      OR status.
In accordance with the Risk Informed Completion Time Program B. Two RHR containment    B.1  Restore one RHR            8 hours spray subsystems            containment spray inoperable.                  subsystem to OPERABLE status.
C. Required Action and    ------------NOTE------------
associated Completion  LCO 3.0.4.a is not Time not met.          applicable when entering MODE 3.
C.1  Be in MODE 3.              12 hours CLINTON                              3.6-24                  Amendment No. 238
 
RHR Suppression Pool Cooling 3.6.2.3 3.6  CONTAINMENT SYSTEMS 3.6.2.3  Residual Heat Removal (RHR) Suppression Pool Cooling LCO  3.6.2.3    Two RHR suppression pool cooling subsystems shall be OPERABLE.
                  ----------------------------NOTE----------------------------
One RHR suppression pool cooling subsystem may be inoperable during alignment and operation for decay heat removal with reactor steam dome pressure less than the residual heat removal cut in permissive pressure.
APPLICABILITY:    MODES 1, 2, and 3.
ACTIONS CONDITION                  REQUIRED ACTION          COMPLETION TIME A. One RHR suppression      A.1    Restore RHR              7 days pool cooling subsystem          suppression pool inoperable.                      cooling subsystem to    OR OPERABLE status.
In accordance with the Risk Informed Completion Time Program B. Required Action and      ------------NOTE------------
associated Completion    LCO 3.0.4.a is not Time of Condition A      applicable when entering not met.                MODE 3.
B.1    Be in MODE 3.            12 hours C. Two RHR suppression      C.1    Be in MODE 3.            12 hours pool cooling subsystems inoperable. AND C.2    Be in MODE 4.            36 hours CLINTON                              3.6-32                    Amendment No. 238
 
SPMU System 3.6.2.4 3.6  CONTAINMENT SYSTEMS 3.6.2.4  Suppression Pool Makeup (SPMU) System LCO  3.6.2.4    Two SPMU subsystems shall be OPERABLE.
APPLICABILITY:    MODES 1, 2, and 3.
ACTIONS CONDITION                  REQUIRED ACTION            COMPLETION TIME A. Combined upper            A.1    Restore upper            4 hours containment pool and            containment pool and suppression pool water          suppression pool water levels not within                levels to within limit.
limit.
B. Upper containment pool    B.1    Restore upper            24 hours water temperature not            containment pool water within limit.                    temperature to within limit.
C. One SPMU subsystem        C.1    Restore SPMU subsystem    7 days inoperable for reasons          to OPERABLE status.
other than Condition A                                    OR or B.
In accordance with the Risk Informed Completion Time Program D. Required Action and      D.1    Be in MODE 3.            12 hours associated Completion Time not met.            AND D.2    Be in MODE 4.            36 hours CLINTON                              3.6-34                  Amendment No. 238
 
Drywell Air Lock 3.6.5.2 ACTIONS  (continued)
CONDITION            REQUIRED ACTION      COMPLETION TIME C. Drywell air lock        C.1  Verify a door is    1 hour inoperable for reasons      closed.
other than Condition A or B.                  AND C.2  Restore air lock to 24 hours OPERABLE status.
OR
                                                    -----NOTE------
Not applicable if leakage exceeds limits or if loss of function.
In accordance with the Risk Informed Completion Time Program D. Required Action and    D.1  Be in MODE 3.      12 hours associated Completion Time not met.          AND D.2  Be in MODE 4.      36 hours CLINTON                        3.6-59              Amendment No. 238
 
Drywell Isolation Valves 3.6.5.3 ACTIONS  (continued)
CONDITION            REQUIRED ACTION          COMPLETION TIME A. One or more            A.1  Isolate the affected    8 hours penetration flow paths      penetration flow path with one required          by use of at least      OR drywell isolation          one closed and de-valve inoperable.          activated automatic    In accordance valve, closed manual    with the Risk valve, blind flange,    Informed or check valve with    Completion Time flow through the        Program valve secured.
AND A.2  --------NOTE---------
Isolation devices in high radiation areas may be verified by use of administrative means.
Verify the affected    Prior to penetration flow path  entering MODE 2 is isolated.            or 3 from MODE 4, if not performed within the previous 92 days (continued)
CLINTON                        3.6-62                  Amendment No. 238
 
Division 1 and 2 SX Subsystems and UHS 3.7.1 3.7  PLANT SYSTEMS 3.7.1  Division 1 and 2 Shutdown Service Water (SX) Subsystems and Ultimate Heat Sink (UHS)
LCO  3.7.1      Division 1 and 2 SX subsystems and the UHS shall be OPERABLE.
APPLICABILITY:    MODES 1, 2, and 3.
ACTIONS CONDITION                  REQUIRED ACTION          COMPLETION TIME A. UHS water volume not    A.1    Restore UHS water        90 days within limit                    volume to within limit.
-----------NOTE-----------  ------------NOTES------------
Not applicable during    1. Enter applicable replacement of                Conditions and Required Division 2 SX pump            Actions of LCO 3.8.1, during the Division 2        "AC Sources -Operating,"
SX system outage              for diesel generator made window from October 26        inoperable by SX.
through November 8, 2015.                    2. Enter applicable
--------------------------        Conditions and Required Actions of LCO 3.4.9, B. Division 1 or 2 SX            "Residual Heat Removal subsystem inoperable.        (RHR) Shutdown Cooling System - Hot Shutdown,"
for RHR shutdown cooling subsystem made inoperable by SX.
B.1    Restore SX subsystem    72 hours to OPERABLE status.
OR In accordance with the Risk Informed Completion Time Program (continued)
CLINTON                              3.7-1                    Amendment No. 238
 
Main Turbine Bypass 3.7.6 3.7  PLANT SYSTEMS 3.7.6  Main Turbine Bypass System LCO  3.7.6      The Main Turbine Bypass System shall be OPERABLE.
OR The following limits are made applicable:
: a. Reactor THERMAL POWER limit for an inoperable Main Turbine Bypass System as specified in the COLR; and
: b. LCS 3.2.2, "MINIMUM CRITICAL POWER RATIO (MCPR)," limit for an inoperable Main Turbine Bypass System as specified in the COLR; and
: c. LCO 3.2.3, "LINEAR HEAT GENERATION RATE (LHGR)," limit for an inoperable Main Turbine Bypass System as specified in the COLR.
APPLICABILITY:    THERMAL POWER  21.6% RTP.
ACTIONS CONDITION                  REQUIRED ACTION          COMPLETION TIME A. Requirements of the      A.1      Satisfy the            2 hours LCO not met.                      requirements of the LCO.                  OR In accordance with the Risk Informed Completion Time Program B. Required Action and      B.1      Reduce THERMAL POWER  4 hours associated Completion            to < 21.6% RTP.
Time not met.
CLINTON                              3.7-13                  Amendment No. 238
 
Main Turbine Bypass System 3.7.6 SURVEILLANCE REQUIREMENTS SURVEILLANCE                            FREQUENCY SR  3.7.6.1    Verify one complete cycle of each main        In accordance turbine bypass valve.                        with the Surveillance Frequency Control Program SR  3.7.6.2    Perform a system functional test.            In accordance with the Surveillance Frequency Control Program SR  3.7.6.3    Verify the TURBINE BYPASS SYSTEM RESPONSE    In accordance TIME is within limits.                        with the Surveillance Frequency Control Program CLINTON                            3.7-14                  Amendment No. 238
 
AC Sources  Operating 3.8.1 3.8  ELECTRICAL POWER SYSTEMS 3.8.1  AC Sources  Operating LCO  3.8.1      The following AC electrical power sources shall be OPERABLE:
: a. Two qualified circuits between the offsite transmission network and the onsite Class 1E AC Electric Power Distribution System; and
: b. Three diesel generators (DGs).
APPLICABILITY:    MODES 1, 2, and 3.
                  ----------------------------NOTE----------------------------
Division 3 AC electrical power sources are not required to be OPERABLE when High Pressure Core Spray System is inoperable.
ACTIONS
-------------------------------------NOTE-------------------------------------
LCO 3.0.4.b is not applicable to DGs.
CONDITION                  REQUIRED ACTION          COMPLETION TIME A. One offsite circuit      A.1      Perform SR 3.8.1.1      1 hour inoperable.                        for OPERABLE offsite circuit.                AND Once per 8 hours thereafter AND A.2      Restore offsite        72 hours circuit to OPERABLE status.                OR In accordance with the Risk Informed Completion Time Program (continued)
CLINTON                                3.8-1                    Amendment No. 238
 
AC Sources  Operating 3.8.1 ACTIONS  (continued)
CONDITION          REQUIRED ACTION          COMPLETION TIME B. One required DG  B.1    Perform SR 3.8.1.1      1 hour inoperable.              for OPERABLE offsite circuit(s).            AND Once per 8 hours thereafter AND B.2    Declare required        4 hours from feature(s), supported  discovery of by the inoperable DG,  Condition B inoperable when the    concurrent with redundant required      inoperability of feature(s) are          redundant inoperable.            required feature(s)
AND B.3.1  Determine OPERABLE      24 hours DG(s) are not inoperable due to common cause failure.
OR B.3.2  Perform SR 3.8.1.2      24 hours for OPERABLE DG(s).
AND (continued)
CLINTON                      3.8-2                    Amendment No. 238
 
AC Sources  Operating 3.8.1 ACTIONS CONDITION          REQUIRED ACTION          COMPLETION TIME B.  (continued)          B.4  Restore required DG    72 hours or in to OPERABLE status. accordance with the Risk Informed Completion Time Program from discovery of an inoperable Division 3 DG AND 14 days or in accordance with the Risk Informed Completion Time Program C. Two offsite circuits C.1  Declare required        12 hours from inoperable.              feature(s) inoperable  discovery of when the redundant      Condition C required feature(s)    concurrent with are inoperable.        inoperability of redundant required feature(s)
AND C.2  Restore one offsite    24 hours circuit to OPERABLE status.                OR In accordance with the Risk Informed Completion Time Program (continued)
CLINTON                      3.8-3                    Amendment No. 238
 
AC Sources  Operating 3.8.1 ACTIONS  (continued)
CONDITION                REQUIRED ACTION          COMPLETION TIME D. One offsite circuit    D.1    Restore offsite        12 hours inoperable.                    circuit to OPERABLE status.                OR AND In accordance One required DG                                        with the Risk inoperable.                                            Informed Completion Time Program OR D.2    Restore required DG    12 hours to OPERABLE status.
OR In accordance with the Risk Informed Completion Time Program E. Two required DGs      E.1    Restore one required    2 hours inoperable.                    DG to OPERABLE status.                OR 24 hours if Division 3 DG is inoperable F. Required Action and    -------------NOTE------------
Associated Completion  LCO 3.0.4.a is not applicable Time of Condition A,  when entering MODE 3.
B, C, D, or E not met. -----------------------------
F.1    Be in MODE 3.          12 hours G. Three or more required G.1    Enter LCO 3.0.3.        Immediately AC sources inoperable.
CLINTON                            3.8-4                    Amendment No. 238
 
AC Sources  Operating 3.8.1 SURVEILLANCE REQUIREMENTS SURVEILLANCE                            FREQUENCY SR  3.8.1.1    Verify correct breaker alignment and        In accordance indicated power availability for each        with the offsite circuit.                            Surveillance Frequency Control Program SR  3.8.1.2    -------------------NOTES-------------------
: 1. Performance of SR 3.8.1.7 satisfies this SR.
: 2. All DG starts may be preceded by an engine prelube period and followed by a warmup period prior to loading.
: 3. A modified DG start involving idling and gradual acceleration to synchronous speed may be used for this SR as recommended by the manufacturer.
When modified start procedures are not used, the time, voltage, and frequency tolerances of SR 3.8.1.7 must be met.
Verify each DG starts from standby          In accordance conditions and achieves steady state        with the voltage  4084 V and  4300 V and frequency  Surveillance 58.8 Hz and  61.2 Hz.                    Frequency Control Program SR  3.8.1.3    -------------------NOTES-------------------
: 1. DG loadings may include gradual loading as recommended by the manufacturer.
: 2. Momentary transients outside the load range do not invalidate this test.
: 3. This Surveillance shall be conducted on only one DG at a time.
: 4. This SR shall be preceded by, and immediately follow, without shutdown, a successful performance of SR 3.8.1.2 or SR 3.8.1.7.
Verify each DG operates for  60 minutes at  In accordance a load  3482 kW for DG 1A,  3488 kW for    with the Surveillance DG 1B, and  1980 kW for DG 1C.              Frequency Control Program (continued)
CLINTON                              3.8-5                  Amendment No. 238
 
AC Sources  Operating 3.8.1 SURVEILLANCE REQUIREMENTS  (continued)
SURVEILLANCE                            FREQUENCY SR  3.8.1.4    Verify each day tank contains  385 gal of  In accordance fuel oil for DG 1A and DG 1B and  240 gal  with the for DG 1C.                                  Surveillance Frequency Control Program SR  3.8.1.5    Check for and remove accumulated water from  In accordance each day tank.                              with the Surveillance Frequency Control Program SR  3.8.1.6    Verify the fuel oil transfer system          In accordance operates to automatically transfer fuel oil  with the from the storage tank to the day tank.      Surveillance Frequency Control Program SR  3.8.1.7    -------------------NOTE-------------------
All DG starts may be preceded by an engine prelube period.
Verify each DG starts from standby          In accordance condition and achieves:                      with the Surveillance
: a. In  12 seconds, voltage  4084 V and  Frequency frequency  58.8 Hz; and                Control Program
: b. Steady state voltage  4084 V and 4300 V and frequency  58.8 Hz and 61.2 Hz.
(continued)
CLINTON                              3.8-6                  Amendment No. 238
 
AC Sources  Operating 3.8.1 SURVEILLANCE REQUIREMENTS  (continued)
SURVEILLANCE                            FREQUENCY SR  3.8.1.8    ------------------NOTE--------------------
This Surveillance shall not be performed in MODE 1 or 2 (not applicable to Division 3 AC sources). However, credit may be taken for unplanned events that satisfy this SR.
Verify automatic and manual transfer of      In accordance unit power supply from the normal offsite    with the circuit to the alternate offsite circuit. Surveillance Frequency Control Program SR  3.8.1.9    -------------------NOTE--------------------
: 1. Credit may be taken for unplanned events that satisfy this SR.
: 2. If performed with DG synchronized with offsite power, it shall be performed at a power factor < 0.9.
Verify each DG rejects a load greater than  In accordance or equal to its associated single largest    with the post accident load and following load        Surveillance rejection, the engine speed is maintained    Frequency less than nominal plus 75% of the            Control Program difference between nominal speed and the overspeed trip setpoint or 15% above nominal, whichever is lower.
SR  3.8.1.10  -------------------NOTE--------------------
Credit may be taken for unplanned events that satisfy this SR.
Verify each DG operating at a power factor  In accordance 0.9 does not trip and voltage is          with the maintained  5000 V for DG 1A and DG 1B and  Surveillance Frequency 5824 V for DG 1C during and following a    Control Program load rejection of a load  3482 kW for DG 1A,  3488 kW for DG 1B, and  1980 kW for DG 1C.
(continued)
CLINTON                              3.8-7                  Amendment No. 238
 
DC Sources-Operating 3.8.4 3.8  ELECTRICAL POWER SYSTEMS 3.8.4  DC Sources  Operating LCO  3.8.4      The Division 1, Division 2, Division 3, and Division 4 DC electrical power subsystems shall be OPERABLE.
APPLICABILITY:    MODES 1, 2, and 3.
ACTIONS CONDITION                  REQUIRED ACTION          COMPLETION TIME A. One battery charger on    A.1    Restore battery        2 hours Division 1 or 2                  terminal voltage to inoperable.                      greater than or equal to the minimum established float voltage.
AND A.2    Verify battery float    Once per 12 hours current < 2 amps.
AND A.3    Restore battery        7 days charger to OPERABLE status.                OR In accordance with the Risk Informed Completion Time Program B. One battery on            B.1    Restore battery to      2 hours Division 1 or 2                  OPERABLE status.
inoperable.                                              OR In accordance with the Risk Informed Completion Time Program (continued)
CLINTON                              3.8-24                    Amendment No. 238
 
DC Sources-Operating 3.8.4 ACTIONS  (continued)
CONDITION                REQUIRED ACTION          COMPLETION TIME C. Division 1 or 2 DC    C.1      Restore Division 1      2 hours electrical power                and 2 DC electrical subsystem inoperable            power subsystems to    OR for reasons other than          OPERABLE status.
Condition A or B.                                      In accordance with the Risk Informed Completion Time Program D. Required Action and    -------------NOTE------------
associated Completion  LCO 3.0.4.a is not Time for Condition A,  applicable when entering B, or C not met.      MODE 3.
D.1      Be in MODE 3.          12 hours E. Division 3 or 4 DC    E.1      Declare High Pressure  Immediately electrical power                Core Spray System subsystem inoperable.          inoperable.
F. Required Action and    F.1      Be in MODE 3.          12 hours associated Completion Time for Condition E  AND not met.
F.2      Be in MODE 4.          36 hours CLINTON                          3.8-24a                    Amendment No. 238
 
Inverters-Operating 3.8.7 3.8  ELECTRICAL POWER SYSTEMS 3.8.7  Inverters  Operating LCO  3.8.7      The Division 1, 2, 3, and 4 inverters, and A and B RPS solenoid bus inverters shall be OPERABLE.
APPLICABILITY:    MODES 1, 2, and 3.
ACTIONS
-------------------------------------NOTE-------------------------------------
Enter applicable Conditions and Required Actions of LCO 3.8.9, "Distribution Systems  Operating," with any uninterruptible AC bus de-energized.
CONDITION                  REQUIRED ACTION          COMPLETION TIME A. Division 1 or 2          A.1    Restore Division 1      7 days inverter inoperable.              and 2 inverters to OPERABLE status.        OR In accordance with the Risk Informed Completion Time Program B. Required Action and      -------------NOTE------------
associated Completion    LCO 3.0.4.a is not Applicable Time of Condition A      when entering MODE 3.
not met.                  -----------------------------
B.1      Be in MODE 3.          12 hours C. One or more Division 3    C.1    Declare High Pressure  Immediately or 4 inverters                    Core Spray System inoperable.                      inoperable.
(continued)
CLINTON                              3.8-34                  Amendment No. 238
 
Inverters-Operating 3.8.7 ACTIONS  (continued)
CONDITION                  REQUIRED ACTION          COMPLETION TIME D. One RPS solenoid bus    D.1.1    Transfer RPS bus to    1 hour inverter inoperable.              alternate power source.
AND D.1.2    Verify RPS bus supply  Once per 8 hours frequency  57 Hz.      thereafter OR 1 hour D.2      De-energize RPS bus.
E. Both RPS solenoid bus    E.1      De-energize one RPS    1 hour inverters inoperable.            solenoid bus.
F. Required Action and      F.1      Be in MODE 3.          12 hours associated Completion Time for Condition C,    AND D, or E not met.
F.2      Be in MODE 4.          36 hours SURVEILLANCE REQUIREMENTS SURVEILLANCE                              FREQUENCY SR  3.8.7.1    Verify correct inverter voltage, frequency,    In accordance and alignment to required uninterruptible      with the AC buses and RPS solenoid buses.                Surveillance Frequency Control Program CLINTON                              3.8-35                    Amendment No. 238
 
Distribution Systems-Operating 3.8.9 3.8  ELECTRICAL POWER SYSTEMS 3.8.9  Distribution Systems  Operating LCO  3.8.9      Division 1, 2, and 3 AC, Division 1, 2, 3, and 4 DC, and Division 1, 2, 3, and 4 uninterruptible AC bus electrical power distribution subsystems shall be OPERABLE.
APPLICABILITY:    MODES 1, 2, and 3.
                  ----------------------------NOTE----------------------------
Division 3 and 4 electrical power distribution subsystems are not required to be OPERABLE when High Pressure Core Spray System is inoperable.
ACTIONS CONDITION                  REQUIRED ACTION          COMPLETION TIME A. One or more Division 1    A.1      Restore Division 1      8 hours or 2 AC electrical                and 2 AC electrical power distribution                power distribution      OR subsystems inoperable.            subsystems to OPERABLE status.        -----NOTE------
Not applicable if loss of function.
In accordance with the Risk Informed Completion Time Program (continued)
CLINTON                              3.8-39                    Amendment No. 238
 
Distribution Systems-Operating 3.8.9 ACTIONS  (continued)
CONDITION                REQUIRED ACTION          COMPLETION TIME B. One or more Division 1 B.1      Restore Division 1      8 hours or 2 uninterruptible            and 2 uninterruptible AC bus distribution            AC bus distribution    OR subsystems inoperable.          subsystems to OPERABLE status.        -----NOTE------
Not applicable if loss of function.
In accordance with the Risk Informed Completion Time Program C. One or more Division 1 C.1      Restore Division 1      2 hours or 2 DC electrical              and 2 DC electrical power distribution              power distribution      OR subsystems inoperable.          subsystems to OPERABLE status.        -----NOTE------
Not applicable if loss of function.
In accordance with the Risk Informed Completion Time Program D. Required Action and    -------------NOTE------------
associated Completion  LCO 3.0.4.a is not applicable Time of Condition A,  when entering MODE 3.
B, or C not met.      -----------------------------
D.1      Be in MODE 3.          12 hours E. One or more Division 3 E.1      Declare High Pressure  Immediately or 4 AC, DC, or                Core Spray System uninterruptible AC bus          inoperable.
electrical power distribution subsystems inoperable.
(continued)
CLINTON                            3.8-40                    Amendment No. 238
 
Distribution Systems-Operating 3.8.9 ACTIONS  (continued)
CONDITION                  REQUIRED ACTION          COMPLETION TIME F. Two or more divisions  F.1      Enter LCO 3.0.3.        Immediately with inoperable distribution subsystems that result in a loss of function.
SURVEILLANCE REQUIREMENTS SURVEILLANCE                              FREQUENCY SR  3.8.9.1    Verify correct breaker alignments and          In accordance voltage to required AC, DC, and                with the uninterruptible AC bus electrical power        Surveillance distribution subsystems.                      Frequency Control Program CLINTON                            3.8-41                    Amendment No. 238
 
Programs and Manuals 5.5 5.5  Programs and Manuals  (continued) 5.5.15      Control Room Envelope Habitability Program  (continued)
: d. Measurement, at designated locations, of the CRE pressure relative to all external areas adjacent to the CRE boundary during the pressurization mode of operation by one subsystem of the Control Room Ventilation System, operating at the flow rate required by the VFTP, at a Frequency of 24 months on a STAGGERED TEST BASIS. The results shall be trended and used as a part of the 24 month assessment of the CRE boundary.
: e. The quantitative limits on unfiltered air inleakage into the CRE. These limits shall be stated in a manner to allow direct comparison to the unfiltered air inleakage measured by the testing described in paragraph c. The unfiltered air inleakage limit for radiological challenges is the inleakage flow rate assumed in the licensing basis analyses of DBA consequences. Unfiltered air inleakage limits for hazardous chemicals must ensure that exposure of CRE occupants to these hazards will be within the assumptions in the licensing basis.
: f. The provisions of SR 3.0.2 are applicable to the Frequencies for assessing CRE habitability, determining CRE unfiltered inleakage, and measuring CRE pressure and assessing the CRE boundary as required by paragraph c and d, respectively.
5.5.16      Surveillance Frequency Control Program This program provides controls for Surveillance Frequencies. The program shall ensure that Surveillance Requirements specified in the Technical Specifications are performed at intervals sufficient to assure the associated Limiting Conditions for Operation are met.
: a. The Surveillance Frequency Control Program shall contain a list of Frequencies of those Surveillance Requirements for which the Frequency is controlled by the program.
: b. Changes to the Frequencies listed in the Surveillance Frequency Control Program shall be made in accordance with NEI 04-10, Risk-Informed Method for control of Surveillance Frequencies, Revision 1.
: c. The provisions of Surveillance Requirements 3.0.2 and 3.0.3 are applicable to the Frequencies established in the Surveillance Frequency Control Program.
(continued)
CLINTON                            5.0-16c                  Amendment No. 238
 
Programs and Manuals 5.5 5.5  Programs and Manuals  (continued) 5.5.17      Risk Informed Completion Time Program This program provides controls to calculate a Risk Informed Completion Time (RICT) and must be implemented in accordance with NEI 06-09-A, Revision 0, "Risk-Managed Technical Specifications (RMTS) Guidelines." The program shall include the following:
: a. The RICT may not exceed 30 days;
: b. A RICT may only be utilized in MODE 1 and 2;
: c. When a RICT is being used, any change to the plant configuration, as defined in NEI 06-09-A, Appendix A, must be considered for the effect on the RICT.
: 1. For planned changes, the revised RICT must be determined prior to implementation of the change in configuration.
: 2. For emergent conditions, the revised RICT must be determined within the time limits of the Required Action Completion Time (i.e., not the RICT) or 12 hours after the plant configuration change, whichever is less.
: 3. Revising the RICT is not required if the plant configuration change would lower plant risk and would result in a longer RICT.
: d. For emergent conditions, if the extent of condition evaluation for inoperable structures, systems, or components (SSCs) is not complete prior to exceeding the Completion Time, the RICT shall account for the increased possibility of common cause failure (CCF) by either:
: 1. Numerically accounting for the increased possibility of CCF in the RICT calculation; or
: 2. Risk Management Actions (RMAs) not already credited in the RICT calculation shall be implemented that support redundant or diverse SSCs that perform the function(s) of the inoperable SSCs, and, if practicable, reduce the frequency of initiating events that challenge the function(s) performed by the inoperable SSCs.
: e. The risk assessment approaches and methods shall be acceptable to the NRC. The plant PRA shall be based on the as-built, as-operated, and maintained plant; and reflect the operating experience at the plant, as specified in Regulatory Guide 1.200, Revision 2. Methods to assess the risk from extending the Completion Times must be PRA methods used to support this license amendment, or other methods approved by the NRC for generic use; and any change in the PRA methods to assess risk that are outside these approval boundaries require prior NRC approval.
CLINTON                            5.0-17                    Amendment No. 238
 
Reporting Requirements 5.6 5.0  ADMINISTRATIVE CONTROLS 5.6  Reporting Requirements The following reports shall be submitted in accordance with 10 CFR 50.4.
5.6.1        Deleted 5.6.2        Annual Radiological Environmental Operating Report The Annual Radiological Environmental Operating Report covering the operation of the unit during the previous calendar year shall be submitted by May 1 of each year. The report shall include summaries, interpretations, and analyses of trends of the results of the Radiological Environmental Monitoring Program for the reporting period. The material provided shall be consistent with the objectives outlined in the Offsite Dose Calculation Manual (ODCM), and in 10 CFR 50, Appendix I, Sections IV.B.2, IV.B.3, and IV.C.
The Annual Radiological Environmental Operating Report shall include the results of analyses of all radiological environmental samples and of all environmental radiation measurements taken during the period pursuant to the locations specified in the table and figures in the ODCM, as well as summarized and tabulated results of these analyses and measurements in the format of the table in the Radiological Assessment Branch Technical Position, Revision 1, November 1979. In the event that some individual results are not available for inclusion with the report, the report shall be submitted noting and explaining the reasons for the missing results. The missing data shall be submitted in a supplementary report as soon as possible.
5.6.3        Radioactive Effluent Release Report The Radioactive Effluent Release Report covering the operation of the unit during the previous calendar year shall be submitted by May 1 of each year. The report shall include a summary of the quantities of radioactive liquid and gaseous effluents and solid waste released from the unit. The material provided shall be consistent with the objectives outlined in the ODCM and process control program and in conformance with 10 CFR 50.36a and 10 CFR 50, Appendix I, Section IV.B.1.
5.6.4        Deleted (continued)
CLINTON                              5.0-18                  Amendment No. 238
 
Reporting Requirements 5.6 5.6  Reporting Requirements    (continued) 5.6.5        CORE OPERATING LIMITS REPORT (COLR)
: a. Core operating limits shall be established prior to each reload cycle, or prior to any remaining portion of a reload cycle, and shall be documented in the COLR for the following:
: 1. LCO 3.2.1, Average Planar Linear Heat Generation Rate (APLHGR),
: 2. LCO 3.2.2, Minimum Critical Power Ratio (MCPR) and MCPR99.9%,
: 3. LCO 3.2.3, Linear Heat Generation Rate (LHGR),
: 4. LCO 3.3.1.1, RPS Instrumentation (SR 3.3.1.1.14),
: 5. LCO 3.3.1.3, Oscillation Power Range Monitor (OPRM)
Instrumentation, and
: 6. LCO 3.7.6, Main Turbine Bypass System, (cycle dependent thermal power limits for an inoperable Main Turbine Bypass System).
: b. The analytical methods used to determine the core operating limits shall be those previously reviewed and approved by the NRC in (1)  General Electric Standard Application for Reactor Fuel (GESTAR), NEDE-24011-P-A, or (2)  NEDO-32465, "BWR Owners' Group Reactor Stability Detect and Suppress Solutions Licensing Basis Methodology and Reload Applications."
: c. The core operating limits shall be determined such that all applicable limits (e.g., fuel thermal mechanical limits, core thermal hydraulic limits, Emergency Core Cooling Systems (ECCS) limits, nuclear limits such as SDM, transient analysis limits, and accident analysis limits) of the safety analysis are met.
: d. The COLR, including any midcycle revisions or supplements, shall be provided upon issuance for each reload cycle to the NRC.
CLINTON                                5.0-19                  Amendment No. 238
 
SAFETY EVALUATION BY THE OFFICE OF NUCLEAR REACTOR REGULATION RELATED TO AMENDMENT NO. 238 TO FACILITY OPERATING LICENSE NO. NPF-62 EXELON GENERATION COMPANY, LLC CLINTON POWER STATION, UNIT NO. 1 DOCKET NO. 50-461
 
==1.0      INTRODUCTION==
 
By application dated April 30, 2020 (Reference 1), as supplemented by letters dated November 24, 2020 (Reference 2), and March 23, 2021 (Reference 3), Exelon Generation Company, LLC (Exelon, the licensee) submitted a license amendment request (LAR) for Clinton Power Station, Unit 1 (CPS).
The amendment would revise technical specification (TS) requirements to permit the use of risk-informed completion times (RICTs) for actions to be taken when limiting conditions for operation (LCOs) are not met. The proposed changes are based on Technical Specifications Task Force (TSTF) Traveler TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b, dated July 2, 2018 (Reference 4). The U.S. Nuclear Regulatory Commission (NRC or Commission) issued a final model safety evaluation (SE) approving TSTF-505, Revision 2, on November 21, 2018 (Reference 5).
The supplemental letters dated November 24, 2020, and March 23, 2021, provided additional information that clarified the application, did not expand the scope of the application as originally noticed, and did not change the NRC staffs original proposed no significant hazards consideration determination as published in the Federal Register (FR) on June 16, 2020 (85 FR 36435).
 
==2.0      REGULATORY EVALUATION==
 
2.1      Description of Risk-Informed Completion Time Program The TS LCOs are the lowest functional capability or performance levels of equipment required for safe operation of the facility. When an LCO is not met, the licensee must shut down the reactor or follow any remedial or required action (e.g., testing, maintenance, or repair activity) permitted by the TSs until the condition can be met. The remedial actions (i.e., ACTIONS) associated with an LCO contain Conditions that typically describe the ways in which the
 
requirements of the LCO can fail to be met. Specified with each stated Condition are Required Action(s) and Completion Times (CTs). The CTs are referred to as the front stops in the context of this SE. For certain Conditions, the TS require exiting the Mode of Applicability of an LCO (i.e., shut down the reactor).
Topical Report (TR) Nuclear Energy Institute (NEI) 06-09-A, Risk-Informed Technical Specifications Initiative 4b: Risk-Managed Technical Specifications (RMTS), October 2012, Revision 0 (Reference 6) provides a methodology for extending existing CTs and, thereby, delay exiting the operational mode of applicability or taking Required Actions if risk is assessed and managed within the limits and programmatic requirements established by a RICT program.
2.2    Description of TS Changes The licensees {{letter dated|date=April 30, 2020|text=letter dated April 30, 2020}}, submittal, requested approval to add a RICT program to the Administrative Controls section of the TS, and modify selected CTs to permit extending the CTs, provided risk is assessed and managed as described in NEI 06-09-A. The licensees application for the changes proposed to use NEI 06-09-A and included documentation regarding the technical adequacy of the probabilistic risk assessment (PRA) models for the RICT program, consistent with the guidance of Regulatory Guide (RG) 1.200, Revision 2, An Approach for Determining the Technical Adequacy of Probabilistic Risk Assessment Results for Risk-Informed Activities, March 2009 (Reference 7).
2.2.1  TS 1.0 Use and Application Example 1.3-8, would be added to TS 1.3, CTs, and reads as follows:
EXAMPLE 1.3-8 ACTIONS CONDITION        REQUIRED ACTION          COMPLETION TIME A. One          A.1 Restore subsystem 7 days subsystem        to OPERABLE inoperable.      status.              OR In accordance with the Risk Informed Completion Time Program B. Required    B.1 Be in MODE 3.        6 hours Action and associated    AND Completion Time not    B.2 Be in MODE 5.        36 hours met.
When a subsystem is declared inoperable, Condition A is entered.
The 7-day Completion Time may be applied as discussed in Example 1.3-2. However, the licensee may elect to apply the Risk Informed Completion Time Program, which permits calculation of
 
a Risk Informed Completion Time (RICT), that may be used to complete the Required Action beyond the 7-day Completion Time.
The RICT cannot exceed 30 days. After the 7-day Completion Time has expired, the subsystem must be restored to OPERABLE status within the RICT or Condition B must also be entered.
The Risk Informed Completion Time Program requires recalculation of the RICT to reflect changing plant conditions. For planned changes, the revised RICT must be determined prior to implementation of the change in configuration. For emergent conditions, the revised RICT must be determined within the time limits of the Required Action Completion Time (i.e., not the RICT) or 12 hours after the plant configuration change, whichever is less.
If the 7-day Completion Time clock of Condition A has expired and subsequent changes in plant condition result in exiting the applicability of the Risk Informed Completion Time Program without restoring the inoperable subsystem to OPERABLE status, Condition B, is also entered and the Completion Time clocks for Required Actions B.1 and B.2 start.
If the RICT expires or is recalculated to be less than the elapsed time since the Condition was entered, and the inoperable subsystem has not been restored to OPERABLE status, Condition B is also entered and the Completion Time clocks for Required Actions B.1 and B.2 start. If the inoperable subsystems are restored to OPERABLE status after Condition B is entered, Condition A is exited and, therefore, the required actions of Condition B may be terminated.
2.2.2  TS 5.5.17 RICT program TS 5.5.17, which describes the RICT program, would be added to the TS and reads as follows:
Risk-Informed Completion Time Program This program provides controls to calculate a Risk Informed Completion Time (RICT) and must be implemented in accordance with NEI 06-09-A, Revision 0, Risk-Managed Technical Specifications (RMTS) Guidelines. The program shall include the following:
: a.      The RICT may not exceed 30 days;
: b.      A RICT may only be utilized in MODE 1 and 2;
: c. When a RICT is being used, any change to the plant configuration, as defined in NEI 06-09-A, Appendix A, must be considered for the effect on the RICT.
: 1.      For planned changes, the revised RICT must be determined prior to implementation of the change in configuration.
: 2.      For emergent conditions, the revised RICT must be determined within the time limits of the Required Action Completion Time (i.e., not the RICT) or 12 hours after the plant configuration change, whichever is less.
: 3.      Revising the RICT is not required if the plant configuration change would lower plant risk and would result in a longer RICT.
: d. For emergent conditions, if the extent of condition evaluation for inoperable structures, systems, or components (SSCs) is not complete prior to exceeding the Completion Time, the RICT shall account for the increased possibility of common cause failure (CCF) by either:
: 1.      Numerically accounting for the increased possibility of CCF in the RICT calculation; or
: 2.      Risk Management Actions (RMAs) not already credited in the RICT calculation shall be implemented that support redundant or diverse SSCs that perform the function(s) of the inoperable SSCs, and, if practicable, reduce the frequency of initiating events that challenge the function(s) performed by the inoperable SSCs.
: e. The risk assessment approaches and methods shall be acceptable to the NRC. The plant PRA shall be based on the as-built, as-operated, and maintained plant; and reflect the operating experience at the plant, as specified in Regulatory Guide 1.200, Revision 2. Methods to assess the risk from extending the Completion Times must be PRA methods used to support this license amendment, or other methods approved by the NRC for generic use; and any change in the PRA methods to assess risk that are outside these approval boundaries require prior NRC approval.
 
2.2.3  Application of the RICT Program to Existing LCOs and Conditions The typical CT is modified by the application of the RICT program as shown in the following example. The changed portion is indicated in italics.
ACTIONS CONDITION              REQUIRED ACTION            COMPLETION TIME A. One subsystem            A.1 Restore subsystem 7 days inoperable.                  to OPERABLE status.              OR In accordance with the Risk Informed Completion Time Program Where necessary, conforming changes are made to CTs to make them accurate following use of a RICT. For example, most TSs have requirements to close/isolate containment isolation devices if one or more containment penetrations have inoperable devices. This is followed by a requirement to periodically verify the penetration is isolated. By adding the flexibility to use a RICT to determine a time to isolate the penetration, the periodic verifications must then be based on the time following isolation.
Individual LCO Required Actions and CTs modified by the proposed change are identified below. The changed portion is indicated in italics.
LCO 3.1.7      Two SLC [standby liquid control] subsystems shall be OPERABLE.
CONDITION              REQUIRED ACTION            COMPLETION TIME A. One SLC subsystem        A.1 Restore SLC          7 days inoperable.                  subsystem to OPERABLE status. OR In accordance with the Risk Informed Completion Time Program
 
LCO 3.3.1.1  The RPS [reactor protection system] instrumentation for each Function in Table 3.3.1.1-1 shall be OPERABLE.
CONDITION              REQUIRED ACTION                  COMPLETION TIME A. One or more              A.1 Place one channel          48 hours Functions with one            in affected channel inoperable.          Function in trip.        OR In accordance with the Risk Informed Completion Time Program B. One or more                B.1 Place one channel          6 hours Functions with two            in affected channels inoperable.          Function in trip.        OR In accordance with the Risk Informed Completion Time Program LCO 3.3.4.1  Four channels for each EOC-RPT [end of cycle - recirculation pump trip]
instrumentation Function listed below shall be OPERABLE:
: a. Turbine Stop Valve (TSV) Closure; and
: b. Turbine Control Valve (TCV) Fast Closure, Trip Oil Pressure-Low.
CONDITION              REQUIRED ACTION                  COMPLETION TIME A. One or more              A.1 Restore channel to 48 hours Functions with one            OPERABLE status.
channel inoperable.                                    OR OR In accordance with the A.2 --------NOTE--------- Risk Informed Not applicable if          Completion Time inoperable channel Program is the result of an inoperable breaker.
Place one channel 48 hours in affected Function in trip.        OR In accordance with the Risk Informed Completion Time Program
 
B. One or more                      B.1 Place one channel    6 hours Functions with two                in affected channels inoperable.              Function in trip. OR In accordance with the Risk Informed Completion Time Program LCO 3.3.6.1    The primary containment and drywell isolation instrumentation for each Function in Table 3.3.6.1-1 shall be OPERABLE.
CONDITION                  REQUIRED ACTION            COMPLETION TIME
      -----------NOTE---------------- A.1 Place one channel        48 hours Only applicable to Main                  in affected function Steam Line (MSL)                        in trip.            OR isolation Functions.
      ------------------------------------                          In accordance with the A. One or more                                                Risk Informed Functions with one                                      Completion Time channel inoperable.                                    Program
      -----------NOTE---------------- B.1 Place one channel        6 hours Only applicable to MSL                  in affected function isolation Functions.                    in trip.            OR B. One or more                                                In accordance with the Functions with two                                      Risk Informed channels inoperable.                                    Completion Time Program LCO 3.3.6.5    Two relief and LLS [low-low set] instrumentation trip systems shall be OPERABLE.
CONDITION                  REQUIRED ACTION            COMPLETION TIME A. One trip system                A.1 Restore trip system 7 days inoperable.                        to OPERABLE status.              OR In accordance with the Risk Informed Completion Time Program
 
LCO 3.5.1    Each ECCS [emergency core cooling system] injection/spray subsystem and the Automatic Depressurization System (ADS) function of seven safety/relief valves shall be OPERABLE.
            ----------------------------NOTE---------------------------------------------
One low pressure coolant injection (LPCI) subsystem may be inoperable during alignment and operation for decay heat removal with reactor steam dome pressure less than the residual heat removal cut in permissive pressure.
CONDITION                    REQUIRED ACTION                    COMPLETION TIME A. One low pressure                A.1 Restore low                  7 days ECCS injection/spray                pressure ECCS subsystem inoperable.                injection/spray            OR subsystem to OPERABLE status. In accordance with the Risk Informed Completion Time Program B. HPCS [high pressure            B.2 Restore HPCS                  14 days core spray] System                  System to inoperable.                          OPERABLE status. OR In accordance with the Risk Informed Completion Time Program C. Two ECCS injection              C.1 Restore one ECCS 72 hours subsystems                          injection/spray inoperable.                          subsystem to                OR OPERABLE status.
OR                                                              In accordance with the Risk Informed One ECCS injection                                              Completion Time and one ECCS spray                                              Program subsystem inoperable.
E. One ADS valve                  E.1 Restore ADS valve 14 days inoperable.                          to OPERABLE status.                    OR In accordance with the Risk Informed Completion Time Program
 
F. One ADS valve          F.1 Restore ADS valve 72 hours inoperable.                to OPERABLE status.              OR AND In accordance with the One low pressure                                Risk Informed ECCS injection/spray OR                          Completion Time subsystem inoperable.                            Program F.2 Restore low          72 hours pressure ECCS injection/spray      OR subsystem to OPERABLE status. In accordance with the Risk Informed Completion Time Program LCO 3.5.3    The RCIC [reactor core isolation cooling] System shall be OPERABLE.
CONDITION            REQUIRED ACTION            COMPLETION TIME A. RCIC System            A.2 Restore RCIC          14 days inoperable.                System to OPERABLE status. OR In accordance with the Risk Informed Completion Time Program LCO 3.6.1.3  Each PCIV [primary containment isolation valve] shall be OPERABLE.
CONDITION            REQUIRED ACTION            COMPLETION TIME A. One or more            A.1 Isolate the affected  4 hours or in accordance penetration flow paths      penetration flow    with the Risk Informed with one PCIV              path by use of at    Completion Time inoperable, except          least one closed    Program except for main due to leakage not          and de-activated    steam line and excess within limit.              automatic valve,    flow check valves closed manual        (EFCVs) valve, blind flange, or check valve with  AND flow through the valve secured.      8 hours or in accordance with the Risk Informed Completion Time Program for main steam line
 
AND 12 hours or in accordance with the Risk Informed Completion Time Program for EFCVs AND (continued)
A. (continued)            A.2 --------NOTE---------
Isolation devices in high radiation areas may be verified by use of administrative means.
Verify the affected        Once per 31 days penetration flow          following isolation for path is isolated.          isolation devices outside primary containment, drywell, and steam tunnel AND Prior to entering MODE 2 or 3 from MODE 4, if not performed within the previous 92 days, for isolation devices inside primary containment, drywell, or steam tunnel D. One or more            D.1 Isolate the affected      24 hours penetration flow paths    penetration flow with one or more          path by use of at          OR primary containment        least one closed purge valves not          and de-activated          In accordance with the within purge valve        automatic valve,          Risk Informed leakage limits.            closed manual              Completion Time valve, or blind            Program flange.
AND D.2 --------NOTE---------
Isolation devices in high radiation areas may be
 
verified by use of administrative means.
Verify the affected        Once per 31 days penetration flow          following isolation for path is isolated.          isolation devices outside primary containment AND Prior to entering MODE 2 or 3 from MODE 4 if not performed within the previous 92 days for isolation devices inside primary containment AND D.3 Perform SR                Once per 92 days
[surveillance              following isolation requirement]
3.6.1.3.5 for the resilient seal purge valves closed to comply with Required Action D.1.
 
LCO 3.6.1.7  Two RHR [residual heat removal] containment spray subsystems shall be OPERABLE.
              ----------------------------NOTE----------------------------------------------------
One RHR containment spray subsystem may be inoperable during alignment and operation for decay heat removal with reactor steam dome pressure less than the residual heat removal cut in permissive pressure.
CONDITION                    REQUIRED ACTION                    COMPLETION TIME A. One RHR                        A.1 Restore RHR                  7 days containment spray                    containment spray subsystem inoperable.                subsystem to                OR OPERABLE status.
In accordance with the Risk Informed Completion Time Program LCO 3.6.2.3  Two RHR suppression pool cooling subsystems shall be OPERABLE.
              ----------------------------NOTE-------------------------------------------------------------
One RHR suppression pool cooling subsystem may be inoperable during alignment and operation for decay heat removal with reactor steam dome pressure less than the residual heat removal cut in permissive pressure.
CONDITION                    REQUIRED ACTION                    COMPLETION TIME A. One RHR                        A.1 Restore RHR                  7 days suppression pool                    suppression pool cooling subsystem                    cooling subsystem          OR inoperable.                          to OPERABLE status.                    In accordance with the Risk Informed Completion Time Program
 
LCO 3.6.2.4  Two SPMU [suppression pool makeup] subsystems shall be OPERABLE.
CONDITION                    REQUIRED ACTION                    COMPLETION TIME C. One SPMU                      C.1 Restore SPMU                  7 days subsystem inoperable                subsystem to for reasons other than              OPERABLE status. OR Condition A or B.
In accordance with the Risk Informed Completion Time Program LCO 3.6.5.3  One drywell isolation valve in each drywell penetration flow path shall be OPERABLE, except for the drywell vent and purge penetrations in which two drywell isolation valves shall be OPERABLE.
              --------------------------NOTE-------------------------------------------------------
This LCO does not apply to OPERABILITY of drywell post-LOCA
[loss-of-coolant accident] vacuum relief system valves.
CONDITION                    REQUIRED ACTION                    COMPLETION TIME A. One or more                    A.1 Isolate the affected          8 hours penetration flow paths              penetration flow with one required                    path by use of at          OR drywell isolation valve              least one closed inoperable.                          and deactivated            In accordance with the automatic valve,            Risk Informed closed manual              Completion Time valve, blind flange,        Program or check valve with flow through the valve secured.
 
LCO 3.7.1      Division 1 and 2 SX [shutdown service water] Subsystems and UHS [ultimate heat sink] shall be OPERABLE.
CONDITION              REQUIRED ACTION                COMPLETION TIME
      -----------NOTE-----------      ------------NOTES---------
Not applicable during          1. Enter applicable replacement of Division 2            Conditions and SX pump during the                    Required Actions Division 2 SX system                  of LCO 3.8.1, "AC outage window from                    [alternating current]
October 26 through                    Sources -
November 8, 2015.                    Operating," for
      --------------------------            diesel generator B. Division 1 or 2 SX                made inoperable subsystem inoperable.          by SX.
: 2. Enter applicable Conditions and Required Actions of LCO 3.4.9, "Residual Heat Removal (RHR)
Shutdown Cooling System - Hot Shutdown," for RHR shutdown cooling subsystem made inoperable by SX.
B.1 Restore SX                72 hours subsystem to OPERABLE status. OR In accordance with the Risk Informed Completion Time Program LCO 3.7.6      The Main Turbine Bypass System shall be OPERABLE.
OR The following limits are made applicable:
: a. Reactor THERMAL POWER limit for an inoperable Main Turbine Bypass System as specified in the COLR [core operating limits report]; and
: b. LCS 3.2.2, "MINIMUM CRITICAL POWER RATIO (MCPR)," limit for an inoperable Main Turbine Bypass System as specified in the COLR; and
: c. LCO 3.2.3, "LINEAR HEAT GENERATION RATE (LHGR)," limit for an inoperable Main Turbine Bypass System as specified in the COLR.
CONDITION              REQUIRED ACTION            COMPLETION TIME A. Requirements of the      A.1 Satisfy the            2 hours LCO not met.                  requirements of the LCO.                  OR In accordance with the Risk Informed Completion Time Program LCO 3.8.1  The following AC electrical power sources shall be OPERABLE:
: a. Two qualified circuits between the offsite transmission network and the onsite Class 1E AC Electric Power Distribution System; and
: b. Three diesel generators (DGs).
CONDITION              REQUIRED ACTION            COMPLETION TIME A. One offsite circuit      A.2 Restore offsite        72 hours inoperable.                  circuit to OPERABLE status. OR In accordance with the Risk Informed Completion Time Program B. One required DG          B.4 Restore required      72 hours or in inoperable.                  DG to OPERABLE        accordance with the Risk status.              Informed Completion Time Program from discovery of an inoperable Division 3 DG AND 14 days or in accordance with the Risk Informed Completion Time Program
 
C. Two offsite circuits    C.2 Restore one offsite 24 hours inoperable.                  circuit to OPERABLE status. OR In accordance with the Risk Informed Completion Time Program D. One offsite circuit    D.1 Restore offsite        12 hours inoperable.                    circuit to OPERABLE            OR AND                            status.
In accordance with the One required DG                                    Risk Informed inoperable.              OR                        Completion Time Program D.2 Restore required      12 hours DG to OPERABLE status.              OR In accordance with the Risk Informed Completion Time Program LCO 3.8.4  The Division 1, Division 2, Division 3, and Division 4 DC [direct current] electrical power subsystems shall be OPERABLE.
CONDITION              REQUIRED ACTION              COMPLETION TIME A. One battery charger      A.3 Restore battery        7 days on Division 1 or 2            charger to inoperable.                  OPERABLE status. OR In accordance with the Risk Informed Completion Time Program B. One battery on          B.1 Restore battery to 2 hours Division 1 or 2              OPERABLE status.
inoperable.                                        OR In accordance with the Risk Informed Completion Time Program
 
C. Division 1 or 2 DC      C.1 Restore Division 1 2 hours electrical power            and 2 DC electrical subsystem inoperable        power subsystem      OR for reasons other than      to OPERABLE Condition A or B.            status.              In accordance with the Risk Informed Completion Time Program LCO 3.8.7      The Division 1, 2, 3, and 4 inverters, and A and B RPS solenoid bus inverters shall be OPERABLE.
CONDITION              REQUIRED ACTION            COMPLETION TIME A. Division 1 or 2 inverter A.1 Restore Division 1 7 days inoperable.                  and 2 inverters to OPERABLE status. OR In accordance with the Risk Informed Completion Time Program 2.2.4  Variations from TSTF-505, Revision 2 2.2.4.1  Application of the RICT Program to Modified Conditions, Required Actions, and Completion Times These are Conditions included in TSTF-505, Revision 2, which are applicable when one or more subsystems/channels are inoperable and there is no TS loss of function. The CT of these specific ACTIONS are modified to accommodate a RICT. Example:
CONDITION                  REQUIRED ACTION              COMPLETION TIME A. One or more                  A.1 Restore [channel/        [24 hours]
[channel/subsystem/            subsystem/train] to train] inoperable.              OPERABLE status.
 
The revised ACTIONS requirement states:
ACTIONS CONDITION                REQUIRED ACTION                COMPLETION TIME A. One or more              A.1 Restore [channel/        [24 hours]
[channel/subsystem/          subsystem/train] to train] inoperable.            OPERABLE status.        OR
                                                                    ------------NOTE------------
Not applicable when
[all/two/four/both] required
[channel/subsystem/train]
are inoperable.
In accordance with the Risk Informed Completion Time Program The following Conditions are modified to permit the application of a RICT. The changed portion is indicated in italics.
LCO 3.3.5.1      The ECCS instrumentation for each Function in Table 3.3.5.1-1 shall be OPERABLE.
CONDITION          REQUIRED ACTION            COMPLETION TIME B. As required by        B.3 Place channel in      24 hours Required Action A.1        trip.
and referenced in                                OR Table 3.3.5.1-1.
                                                              --------NOTE-----------------
Not applicable when trip capability is not maintained.
In accordance with the Risk Informed Completion Time Program C. As required by          C.2 Restore channel to 24 hours Required Action A.1        OPERABLE status.
and referenced in                                OR Table 3.3.5.1-1.
                                                              --------NOTE-----------------
Not applicable when trip capability is not maintained.
In accordance with
 
the Risk Informed Completion Time Program D. As required by      D.2.1 Place channel in 24 hour Required Action A.1    trip.
and referenced in                          OR Table 3.3.5.1-1.
                                              --------NOTE-----------------
Not applicable when trip capability is not maintained.
In accordance with the Risk Informed Completion Time Program E. As required by      E.2 Restore channel to 7 days Required Action A.1    OPERABLE status.
and referenced in                          OR Table 3.3.5.1-1.
                                              --------NOTE-----------------
Not applicable when trip capability is not maintained.
In accordance with the Risk Informed Completion Time Program
 
F. As required by      F.2 Place channel in  96 hours or in Required Action A.1    trip.              accordance with the Risk and referenced in                          Informed Completion Table 3.3.5.1-1.                          Time Program from discovery of inoperable channel concurrent with HPCS or reactor core isolation cooling (RCIC) inoperable AND
                                              --------------NOTE-----------
The Risk Informed Completion Time Program is not applicable when trip capability is not maintained.
8 days or in accordance with the Risk Informed Completion Time Program G. As required by      G.2 Restore channel to 96 hours or in Required Action A.1    OPERABLE status. accordance with the Risk and referenced in                          Informed Completion Table 3.3.5.1-1.                          Time Program from discovery of inoperable channel concurrent with HPCS or reactor core isolation cooling (RCIC)
Inoperable AND
                                              --------------NOTE-----------
The Risk Informed Completion Time Program is not applicable when trip capability is not maintained.
8 days or in accordance with the Risk Informed Completion Time Program
 
LCO 3.3.5.3    The RCIC System instrumentation for each Function in Table 3.3.5.3-1 shall be OPERABLE.
CONDITION                  REQUIRED ACTION          COMPLETION TIME B. As required by                B.2 Place channel in  24 hours Required Action A.1                trip.
and referenced in                                    OR Table 3.3.5.3-1.
                                                                  --------NOTE-----------------
Not applicable when trip capability is not maintained.
In accordance with the Risk Informed Completion Time Program D. As required by                D.2.1 Place channel in 24 hours Required Action A.1                trip.
and referenced in                                    OR Table 3.3.5.3-1.
                                                                  --------NOTE-----------------
Not applicable when trip capability is not maintained.
In accordance with the Risk Informed Completion Time Program LCO 3.3.6.1    The primary containment and drywell isolation instrumentation for each Function in Table 3.3.6.1-1 shall be OPERABLE.
CONDITION                  REQUIRED ACTION          COMPLETION TIME
      -----------NOTE---------------- D.1 Place channel in        24 hours Not applicable to MSL                    trip.
isolation Functions.                                        OR D. One or more required                                    --------NOTE-----------------
channels inoperable.                                  Not applicable when trip capability is not maintained.
In accordance with the Risk Informed Completion Time Program
 
LCO 3.3.6.3  The RHR Containment Spray System instrumentation for each Function in Table 3.3.6.3-1 shall be OPERABLE.
CONDITION              REQUIRED ACTION          COMPLETION TIME B. As required by          B.2 Place channel in  24 hours Required Action A.1          trip.
and referenced in                              OR Table 3.3.6.3-1.
                                                            --------NOTE-----------------
Not applicable when trip capability is not maintained.
In accordance with the Risk Informed Completion Time Program C. As required by          C.2 Restore channel to 24 hours Required Action A.1          OPERABLE status.
and referenced in                              OR Table 3.3.6.3-1.
                                                            --------NOTE-----------------
Not applicable when trip capability is not maintained.
In accordance with the Risk Informed Completion Time Program
 
LCO 3.3.8.1    The LOP [loss of power] instrumentation for each Function in Table 3.3.8.1-1 shall be OPERABLE.
CONDITION            REQUIRED ACTION                  COMPLETION TIME A. One or more channels A.1 Place channel in              1 hour inoperable.                  trip.
OR
                                                                    --------NOTE-----------------
AND                              Not applicable when trip capability is not maintained.
A.2                              ---------------------------------
                                  ---------NOTE-------------- In accordance with Only applicable for              the Risk Informed Functions 1.c, 1.d, 1.e, Completion Time 2.c, 2.d, and 2.e                Program Restore channel to              7 days OPERABLE status.
OR
                                                                    --------NOTE-----------------
Not applicable when trip capability is not maintained.
In accordance with the Risk Informed Completion Time Program LCO 3.6.1.2    Each primary containment air lock shall be OPERABLE.
CONDITION            REQUIRED ACTION                  COMPLETION TIME C. One or more required C.3 Restore air lock to 24 hours primary containment          OPERABLE status.
air locks inoperable                                    OR for reasons other than Condition A or B.                                      --------NOTE-----------------
Not applicable if leakage exceeds limits or if loss of function.
In accordance with the Risk Informed Completion Time Program
 
LCO 3.6.5.2    The drywell air lock shall be OPERABLE.
CONDITION              REQUIRED ACTION          COMPLETION TIME C. Drywell air lock        C.2 Restore air lock to 24 hours inoperable for reasons        OPERABLE status.
other than Condition A                            OR or B.
                                                              --------NOTE-----------------
Not applicable if leakage exceeds limits or if loss of function.
In accordance with the Risk Informed Completion Time Program 2.2.4.2  Application of the RICT to Additional ACTIONS Requirements The following CPS TS Conditions proposed for the RICT program are not listed in TSTF 505, Revision 2.
LCO 3.3.6.4    The SPMU system instrumentation for each Function in Table 3.3.6.4-1 shall be OPERABLE.
CONDITION              REQUIRED ACTION          COMPLETION TIME B. As required by          B.2 Place channel in    24 hours Required Action A.1            trip.
and referenced in                                OR Table 3.3.6.4-1.
                                                              --------NOTE-----------------
Not applicable when trip capability is not maintained.
In accordance with the Risk Informed Completion Time Program
 
C. As required by          C.2 Restore channel to 24 hours Required Action A.1          OPERABLE status.
and referenced in                                  OR Table 3.3.6.4-1.
                                                                --------NOTE-----------------
Not applicable when trip capability is not maintained.
In accordance with the Risk Informed Completion Time Program LCO 3.6.1.6  The LLS function of five safety/relief valves shall be OPERABLE.
CONDITION              REQUIRED ACTION              COMPLETION TIME A. One LLS valve            A.1 Restore LLS valve 14 days inoperable.                  to OPERABLE status.                OR In accordance with the Risk Informed Completion Time Program LCO 3.8.9    Division 1, 2, and 3 AC, Division 1, 2, 3, and 4, DC, and Division 1, 2, 3, and 4, uninterruptible AC bus electrical power distribution subsystems shall be OPERABLE.
CONDITION              REQUIRED ACTION              COMPLETION TIME A. One or more              A.1 Restore Division 1 8 hours Division 1 or 2 AC          and 2 AC electrical electrical power            power distribution    OR distribution                subsystems to subsystems                  OPERABLE status. --------NOTE-----------------
inoperable.                                        Not applicable if loss of function.
In accordance with the Risk Informed Completion Time Program
 
B. One or more              B.1 Restore Division 1      8 hours Division 1 or 2              and 2 uninterruptible AC bus        uninterruptible AC    OR distribution                  bus distribution subsystems                    subsystems to          --------NOTE-----------------
inoperable.                  OPERABLE status.      Not applicable if loss of function.
In accordance with the Risk Informed Completion Time Program C. One or more            C.1 Restore Division 1 2 hours Division 1 or 2 DC            and 2 DC electrical electrical power              power distribution    OR distribution                  subsystems to subsystems                    OPERABLE status. --------NOTE-----------------
inoperable.                                          Not applicable if loss of function.
In accordance with the Risk Informed Completion Time Program 2.3      Regulatory Review 2.3.1    Applicable Regulations Under Section 50.90, Application for amendment of license, construction permit, or early site permit, of Title 10 of the Code of Federal Regulations (10 CFR), whenever a holder of a license wishes to amend the license, including TSs in the license, an application for amendment must be filed, fully describing the changes desired.
The regulation at 10 CFR 50.36(c)(2) requires that TSs contain LCOs, which are the lowest functional capability or performance levels of equipment required for safe operation of the facility. When an LCO of a nuclear reactor is not met, the licensee shall shut down the reactor or follow any remedial action permitted by the TSs until the LCO can be met. Typically, the TSs require restoration of equipment in a timeframe commensurate with its safety significance, along with other engineering considerations. The regulation at 10 CFR 50.36(b) requires that TSs be derived from the analyses and evaluation included in the safety analysis report, and amendments thereto.
In determining whether the proposed TS remedial actions should be granted, the Commission will apply the reasonable assurance standards of 10 CFR 50.40(a) and 50.57(a)(3). The regulation at 10 CFR 50.40(a) states that in determining whether to grant the licensing request, the Commission will be guided by, among other things, consideration about whether the processes to be performed, the operating procedures, the facility and equipment, the use of the facility, and other technical specifications, or the proposals, in regard to any of the foregoing collectively provide reasonable assurance that the applicant will comply with the regulations in
 
this chapter, including the regulations in 10 CFR Part 20 of this chapter, and that the health and safety of the public will not be endangered.
The regulation at 10 CFR 50.36(c)(5) states that administrative controls are the provisions relating to organization and management, procedures, recordkeeping, review and audit, and reporting necessary to assure operation of the facility in a safe manner.
The regulation at 10 CFR 50.55a(h), Protection and safety systems, requires that for nuclear power plants with construction permits issued after January 1, 1971, but before May 13, 1999, protection systems must meet the requirements in IEEE Std 279-1968, Proposed IEEE Criteria for Nuclear Power Plant Protection Systems, or the requirements in IEEE Std 279-1971 1, Criteria for Protection Systems for Nuclear Power Generating Stations, or the requirements in IEEE Std 603-19911, Criteria for Safety Systems for Nuclear Power Generating Stations, and the correction sheet dated January 30, 1995. The CPS construction permit was issued on February 24, 1976. The CPS USAR, Chapters 6 and 7 (Reference 12), describes conformance to IEEE Std 279 by system.
2.3.2  Regulatory Guidance The NRC staff considered the following regulatory guidance during its review of the proposed changes:
* RG 1.200, Revision 2, An Approach for Determining the Technical Adequacy of Probabilistic Risk Assessment Results for Risk-Informed Activities.
* RG 1.174, Revision 3, An Approach for Using Probabilistic Risk Assessment in Risk-Informed Decisions on Plant-Specific Changes to the Licensing Basis, January 2018 (Reference 8).
* RG 1.177, Revision 1, An Approach for Plant-Specific, Risk-Informed Decisionmaking:
Technical Specifications, May 2011 (Reference 9).
* NUREG-1855, Revision 1, Guidance on the Treatment of Uncertainties Associated with PRAs in Risk-Informed Decisionmaking, March 2017 (Reference 10).
* NUREG-0800, Standard Review Plan [SRP] for the Review of Safety Analysis Reports for Nuclear Power Plants: LWR Edition, Chapter 19, Section 19.2, Review of Risk Information Used to Support Permanent Plant-Specific Changes to the Licensing Basis:
General Guidance, June 2007 (Reference 11).
* NEI 06 09 A, Risk Informed Technical Specifications Initiative 4b: Risk Managed Technical Specifications (RMTS), October 2012, Revision 0.
1 Available from Electric Power Research Institute, 3420 Hillview Avenue, Palo Alto, California 94304.
 
==3.0      TECHNICAL EVALUATION==
 
3.1      Method of Staff Review The NRC staff reviewed the licensees PRA peer review history and results, alternative methods and proposed approaches to determine if they are acceptable for use in the proposed RICT extensions. The NRC staff also reviewed the licensees proposed RICT program to determine if it provides the necessary administrative controls to permit completion time extensions for consistency with NEI 06-09-A.
An acceptable approach for making risk-informed decisions about proposed TS changes, including both permanent and temporary changes, is to show that the proposed licensing basis (LB) changes meet the five key principles stated in Section C of RG 1.174, Revision 3, and the three-tiered approach outlined in Section C of RG 1.177. These key principles and tiers are:
Principle 1:  The proposed LB change meets the current regulations unless it is explicitly related to a requested exemption.
Principle 2:  The proposed LB change is consistent with the defense in depth (DID) philosophy.
Principle 3:  The proposed LB change maintains sufficient safety margins.
Principle 4:  When the proposed LB change results in an increase in risk, the increase should be small and consistent with the intent of the Commissions policy statement (60 FR 42622, dated August 16,1995) on safety goals for the operations of nuclear power plants.
* Tier 1: PRA Capability and Insights
* Tier 2: Avoidance of Risk-Significant Plant Configurations
* Tier 3: Risk-Informed Configuration Risk Management Principle 5:  The impact of the proposed LB change should be monitored by using performance measures strategies.
Each of these key risk-informed principles and tiers are addressed in NEI 06-09-A. NEI 06-09-A provides a methodology for extending existing CTs, and thereby, delay exiting the operational mode of applicability or taking Required Actions if risk is assessed and managed within the limits and programmatic requirements established by a RICT program. The NRC staffs evaluation of the licensees proposed use of RICT program against the key safety principles is discussed below.
3.2      Review of Key Principles Revision 1 of RG 1.177 and RG 1.174, Revision 3, identify five key safety principles to be applied to risk-informed changes to the TSs. Each of these principles are addressed in NEI 06-09-A. The NRC staffs evaluation of the licensees proposed use of RICTs against these key safety principles is discussed below.
 
3.2.1    Key Principle 1: Evaluation of Compliance with Current Regulations Paragraph 50.36(c)(2) of 10 CFR require that LCOs are the lowest functional capability or performance levels of equipment required for safe operation of the facility. When an LCO of a nuclear reactor is not met, the licensee shall shut down the reactor or follow any remedial action permitted by the TSs until the condition can be met.
The CTs in the current TSs were established using experiential data, risk insights, and engineering judgement. The RICT program provides the necessary administrative controls to permit extension of CTs and, thereby, delay reactor shut down or Required Actions, if risk is assessed and managed appropriately within specified limits and programmatic requirements.
The addition of the option to determine the CT in accordance with the RICT program would allow an evaluation to determine a configuration-specific CT. The evaluation would be done in accordance with the methodology prescribed in NEI 06-09, and TS 5.5.17. The RICT is limited to a maximum of 30 days (i.e., back stop).
With the incorporation of the RICT program, the required performance levels of equipment specified in LCOs are not changed. Only the required CT for the Required Actions are modified by the RICT program such that 10 CFR 50.36(c)(2) will remain met. Based on the discussion provided above, the NRC staff finds that the proposed changes meet the first key safety principle of RG 1.174, Revision 3, and RG 1.177, Revision 1.
3.2.2    Key Principle 2: Evaluation of Defense in Depth (DID)
DID is an approach to designing and operating nuclear facilities that prevents and mitigates accidents that release radiation or hazardous materials. The key is creating multiple independent and redundant layers of defense to compensate for potential human and mechanical failures so that no single layer, no matter how robust, is exclusively relied upon.
DID includes the use of access controls, physical barriers, redundant and diverse key safety functions, and emergency response measures.
In RG 1.174, Revision 3, the NRC identified the following considerations used for evaluating how the LB change is maintained for the DID philosophy:
* Preserve a reasonable balance among the layers of defense.
* Preserve adequate capability of design features without an overreliance on programmatic activities as compensatory measures.
* Preserve system redundancy, independence, and diversity commensurate with the expected frequency and consequences of challenges to the system, including consideration of uncertainty.
* Preserve adequate defense against potential CCFs.
* Maintain multiple fission product barriers.
* Preserve sufficient defense against human errors.
* Continue to meet the intent of the plants design criteria.
The proposed change represents a robust technical approach that preserves a reasonable balance among redundant and diverse key safety function that provide avoidance of core damage, avoidance of containment failure, and consequence mitigation. The three-tiered approach to risk-informed TS CT changes provides additional assurance that defense-in-depth will not be significantly impacted by such changes to the licensing basis. The licensee is
 
proposing no changes to the design of the plant or any operating parameter, no new operating configurations, and no new changes to the design basis in the proposed changes to the TS.
Since no changes to the design of the plant or any operating parameter, no new operating configuration, and no new changes to the design basis are proposed, the NRC staff finds that the 10 CFR 50.55a(h) requirements continue to be met.
The effect of the proposed changes when implemented will allow CTs to vary based on the risk significance of the given plant configuration (i.e., the equipment out-of-service at any given time) provided that the system(s) retain(s) the capability to perform the applicable safety function(s) without any further failures (e.g., one train of a two train system is inoperable). A configuration-specific RICT may not be used if the system has lost the capability to perform its safety function(s). These restrictions on inoperability of all required trains of a system ensure that consistency with the DID philosophy is maintained by following existing guidance when the capability to perform TS safety function(s) is lost.
The proposed RICT program uses plant-specific operating experience for component reliability and availability data. Thus, the allowances permitted by the RICT program are directly reflective of actual component performance in conjunction with component risk significance.
The RICT will be applied to extend CTs on key electrical power distribution systems. Failures in electrical power distribution systems can simultaneously affect multiple safety functions; therefore, potential degradation to DID during the extended CTs is discussed further below.
Use of Compensatory Measures to Retain DID In NEI 06-09, addresses potential compensatory actions and RMA measures by stating, in generic terms, that compensatory measures may include but are not limited to the following:
* Reduce the duration of risk-sensitive activities.
* Remove risk-sensitive activities from the planned work scope.
* Reschedule work activities to avoid high risk-sensitive equipment outages or maintenance states that result in high-risk plant configurations.
* Accelerate the restoration of out-of-service equipment.
* Determine and establish the safest plant configuration.
NEI 06-09, requires that compensatory measures be initiated when the PRA calculated RMA time (RMAT) is exceeded, or for preplanned maintenance for which the RMAT is expected to be exceeded, RMAs shall be implemented at the earliest appropriate time. Therefore, quantitative risk analysis, the qualitative considerations, and the prohibition on loss of all trains of a required system assure a reasonable balance of DID is maintained to ensure protection of public health and safety.
3.2.2.1    Evaluation of Electrical Power Systems According to Revision 21 of the Updated Safety Analysis Report (USAR) (Reference 12), the plant is designed such that the safety functions are maintained assuming a single failure within the electrical power system. By incorporating an electrical power supply perspective, this concept is further reflected in a number of principal design criteria. Single-failure requirements
 
are typically suspended for the time that a plant is not meeting an LCO (i.e., in an ACTION statement). This section considers the plant configurations from a DID perspective.
The licensee has requested to use the RICT program to extend the existing CT for the following TS 3.8, Electrical Power Systems, condition(s). The NRC staffs evaluation of the proposed changes considered a number of potential plant conditions allowed by the proposed RICTs.
The NRC staff also considered the available redundant or diverse means to respond to various plant conditions. In these evaluations, the NRC staff examined the safety significance of different plant conditions resulting in both shorter and longer CTs. The plant conditions evaluated are discussed in more detail below.
The NRC staff reviewed information pertaining to the proposed electrical power systems TS conditions in the application, the USAR, and applicable TS LCO and TS Bases to verify that the capability of the affected electrical power systems to perform their safety functions (assuming no additional failures) is maintained. To achieve that objective, the staff verified whether each proposed TS conditions design success criteria reflect the redundant or absolute minimum electrical power source/subsystem required to be operable by the LCOs to support the safety functions necessary to mitigate postulated design-basis accidents (DBAs), safely shut down the reactor, and maintain the reactor in a safe shutdown condition. The NRC staff further reviewed the remaining credited power source/equipment to verify whether the proposed condition satisfies its design success criteria. In conjunction with reviewing the remaining credited power source/equipment, the NRC staff considered supplemental electrical power sources/equipment (not necessarily required by the LCOs and either safety or nonsafety-related) that is available at CPS and capable of performing the same safety function that would be performed by the inoperable electrical power source/equipment. In addition, the NRC staff reviewed the proposed RMA examples for reasonable assurance that these RMAs are appropriate to monitor and control risk for applicable TS conditions.
3.2.2.1.1 Loss of Power (LOP) Instrumentation (TS 3.3.8.1)
Description of the LOP Instrumentation Revision 21 of the CPS USAR, Chapter 8, Electric Power, and TS Bases Section B.3.3.8.1, Loss of Power (LOP) Instrumentation, indicate that the LOP instrumentation monitors the 4.16 kV (kilovolt) emergency buses. Offsite power is the preferred source of power for the 4.16 kV emergency buses. If the voltage monitors determine that insufficient power is available, the buses are disconnected from the offsite power sources and connected to the onsite DG power sources. Each 4.16 kV emergency bus has its own independent LOP instrumentation and associated trip logic. The voltage for the Division 1, 2, and 3, buses is monitored at two levels, which can be considered as two different undervoltage functions: loss of voltage and degraded voltage.
The OPERABILITY of the LOP instrumentation is dependent upon the OPERABILITY of the individual instrumentation channel relating to the loss of voltage and degraded voltage functions. Each Function must have a required number of OPERABLE channels for each 4.16 kV emergency bus with the setpoints within the allowable values specified in the TS. A channel is considered inoperable if its actual trip setpoint is not within its required allowable value.
 
Description of Loss of Voltage Functions (TS Table 3.3.8.1-1; Functions 1.a, 1.b, 2.a, 2.b)
Loss of voltage on a 4.16 kV emergency bus indicates that offsite power (provided by either of two offsite circuits) may be completely lost to the respective emergency bus and is unable to supply sufficient power for proper operation of the applicable equipment. Therefore, the power supply to the bus is transferred from offsite power to DG power when the associated bus voltage drops below the loss of voltage function allowable value. This ensures that adequate power will be available to the required equipment.
The loss of voltage function is also provided a time delay. The time delay allowable value is long enough to provide time for the offsite power supply to recover to normal voltages, but short enough to ensure that power is available to the required equipment.
According to TS Table 3.3.8.1-1, there are six channels of 4.16 kV emergency bus loss of voltage function instrumentation for each Division 1 and 2, and four channels for Division 3, which are required to be OPERABLE. Each channel of Division 1 and Division 2 consists of an inverse time delay relay providing a voltage function and a time delay function. Division 3 has four loss of voltage relays/channels and a single time delay relay.
Description of Degraded Voltage Functions (TS Table 3.3.8.1 Functions 1c, 1.d, 1.e, 2.c, 2.d, and 2.e)
A reduced voltage condition on a 4.16 kV emergency bus indicates that while offsite power may not be completely lost to the respective emergency bus, power may be insufficient for starting large motors without risking damage to the motors that could disable the ECCS function.
Therefore, power supply to the bus is transferred from offsite power to onsite DG power when the voltage on the bus drops below the degraded voltage function allowable value. This ensures that adequate power will be available to the required equipment.
The purpose of this instrumentation is to ensure that sufficient power will be available to support the ECCS function during a LOCA. During a LOCA, the ECCS and other safety systems will be initiated at the start of the event. This large loading of the safety buses results in a voltage transient of sufficient magnitude to start the degraded voltage timers. If the degraded voltage relays do not reset, which requires the voltage to be restored to a level above the relay reset setpoint, the bus undervoltage time delay relays will trip, resulting in bus transfer to the DGs.
According to TS Table 3.3.8.1-1, each division has two channels of degraded voltage relays and a single channel of time delay relay, which are required to be OPERABLE.
TS 3.3.8.1 - Changes Relating to LOP Instrumentation Refer to Section 2.2 of this SE for a detailed view of the TS changes.
Evaluation of TS Changes Relating to LOP Instrumentation According to TS 3.3.8.1, Action A.1, the current TS requires placement of any channel relating to loss of voltage or degraded voltage functions in the trip position within one hour. The licensee has proposed to extend the completion time as per the RICT program. According to Action A.2, the current TS requires restoration of any channel relating to the degraded voltage function within 7 days. The licensee has proposed to extend the completion time as per the RICT program. However, the extension in completion time will not be applicable if the trip
 
capability is not maintained. If any of the actions and associated completion times are not met, the associated bus DG is required to be declared inoperable immediately.
In its {{letter dated|date=November 24, 2020|text=letter dated November 24, 2020}}, the licensee explained the loss of functions, as follows if any inoperable channel relating to loss of voltage or degraded voltage function is placed in the trip position:
The Division 1 and 2 emergency bus Loss of Voltage Function is monitored by two undervoltage relays on the emergency bus and two undervoltage relays on each of the two offsite power sources. This results in a total of six relay/channels for the Loss of Voltage Function for each Division. Each of these relays is an inverse time delay relay. The outputs of these relays are arranged in a two-out-of-two taken three times logic configuration to start the respective Divisional Diesel Generator. Any relay/channel failing will result in the respective Diesel Generator not starting.
The Division 3 emergency bus Loss of Voltage Function is monitored by four undervoltage relays whose outputs are arranged in a one-out-of-two taken twice logic configuration. The output of this logic inputs to a time delay relay. A failure of a channel associated with Function 2.a [Degraded Voltage Function for Division 3] will not result in a loss of the function. However, a failure of Function 2.b [Degraded Time Function for Division 3] will result in the Division 3 Diesel Generator not starting.
Each Division 1, Division 2, and Division 3 emergency bus Degraded Voltage Function is monitored by two undervoltage relays for each emergency bus whose outputs are arranged in a two-out-of-two logic configuration. The output of this logic inputs to a time delay relay on each emergency bus. Any relay/channel failing will result in the respective Diesel Generator not starting.
The NRC staff finds that based on logic explained by the licensee in its above response, in most cases of one or more channel failures, the Loss of Power Instrumentation will continue to serve its design function (i.e., detect loss of voltage or degraded voltage).
The TS change also has a Note stating that the RICT is not applicable when the trip capability is not maintained (i.e., unable to meet its design function).
In its {{letter dated|date=November 24, 2020|text=letter dated November 24, 2020}}, the licensee also explained that in the RICT PRA modelling, the "Inoperability of One or more channels" is modeled as a failure of the autostart mode of the associated DG. The manual start mode of the associated DG is still considered available in the RICT model. The NRC staff finds this aspect of the RICT modelling reasonable and, therefore, acceptable.
The above extension in CT will only be applicable when One or more channels [are]
inoperable and will not result in a loss of the design function (i.e., unable to detect loss of voltage or degraded voltage). For instrumentation that has the potential for a configuration in which trip capability is not maintained, a Note was added to the Completion Time which prohibits applying a RICT when trip capability is not maintained. The associated DG, if declared inoperable, can be started manually, thus, providing a partial safety function for certain design events which do not require immediate/auto starting of DG.
 
The NRC staff finds that because of redundancies in the availability of the offsite and onsite power sources the LOP design has sufficient redundancy, diversity, and DID to protect against common cause failures and potential single failure when using the RICT Program. Therefore, the staff finds the above TS changes are acceptable.
3.2.2.1.2 AC Sources - Operating (TS 3.8.1)
Description of the AC Sources CPS USAR Section 8, and TS Bases B.3.8.1, describe the Unit Class 1E AC Electrical Power Distribution System AC Sources as consisting of the offsite power sources and the onsite standby power sources (DGs 1A, 1B, and 1C). As required by 10 CFR Part 50, Appendix A, General Design Criteria 17, the design of the AC electrical power system provides independence and redundancy to ensure an available source of power to the engineered safety feature (ESF) systems.
The Class 1E AC distribution system supplies electrical power to three divisional load groups, with each division powered by an independent Class 1E 4.16 kV ESF bus. Each ESF bus has two separate and independent offsite sources of power. Each ESF bus has a dedicated onsite DG. The ESF systems of any two of the three divisions provide for the minimum safety functions necessary to shut down the unit and maintain it in a safe shutdown condition.
Offsite power is supplied to the switchyard from the transmission network. From the switchyard, one 345 kV circuit provides AC power to each 4.16 kV ESF bus. An electrically and physically independent 138 kV power source provides a second completely independent circuit to each 4.16 kV ESF bus. The offsite AC electrical power sources are designed and located so as to minimize to the extent practical the likelihood of their simultaneous failure under operating and postulated accident and environmental conditions.
The onsite standby power source for each 4.16 kV ESF bus is a dedicated DG. A DG starts automatically on a LOCA signal (i.e., low reactor water level signal or high drywell pressure signal) or on an ESF bus degraded voltage or undervoltage signal. In the event of a loss of offsite power (LOOP), the ESF electrical loads are automatically connected to the DGs in sufficient time to provide for safe reactor shut down and to mitigate the consequences of a design basis accident such as a LOCA.
TS 3.8.1 - Changes Relating to AC Power - Operating Refer to Section 2.2 of this SE for a detailed view of the TS changes.
Evaluation of TS Changes Relating to AC Sources - Operating For each change identified below, the NRC staff reviewed the information pertaining to the proposed TS change in the LAR, the USAR, and applicable TS LCO and TS Bases to verify that the capability of the affected electrical power systems to perform their safety functions (assuming no additional failures) is maintained. To achieve that objective, the NRC staff verified that the proposed TS conditions design success criteria (as provided in Enclosure 1 of the LAR) reflect the redundant or absolute minimum electrical power source/subsystem required to be operable to support the safety functions necessary to mitigate postulated DBAs, safely shut down the reactor, and maintain the reactor in a safe shutdown condition. In addition, the staff
 
reviewed the proposed RMA examples for reasonable assurance that these RMAs are appropriate to monitor and control risk for the condition applicable to the proposed TS change.
TS 3.8.1, Condition A One offsite circuit inoperable, Action A.2 The licensee has proposed to apply the RICT program to TS 3.8.1, Condition A, One offsite circuit inoperable, Action A.2 to extend the CT from the current value of 72 hours to 30 days maximum per the RICT program if risk remains within the guidance of NEI 06-09-A. In the LAR, 2, Risk Management Action (RMA) Examples, the licensee provided examples of multiple RMAs that may be considered during a RICT program entry to reduce the risk impact and ensure adequate DID. In particular, Enclosure 12 of the LAR listed the example RMAs which are likely to be implemented during TS action 3.8.1.A, One offsite circuit inoperable.
TS 3.8.1, Condition B One required DG inoperable, Action B.4 The licensee has proposed to apply the RICT program to TS 3.8.1, Condition B, One required DG inoperable, Action B.4 to extend the CT from the current value of 72 hours to 30 days maximum per the RICT program for the Division 3 DG; and to extend the CT from the current value of 14 days to 30 days maximum per the RICT program for the Division 1 or 2 DG, if the risk remains within limits of the NEI 06-09-A guidance. In the LAR, Enclosure 12, Risk Management Action (RMA) Examples, the licensee provided examples of multiple RMAs that may be considered during a RICT program entry to reduce the risk impact and ensure adequate DID. In particular, Enclosure 12 of the LAR listed the example RMAs which are likely to be implemented during TS action 3.8.1.B, One required DG inoperable.
TS 3.8.1, Condition C Two offsite circuits inoperable, Action C.2 The licensee has proposed to apply the RICT program to TS 3.8.1, Condition C, Two offsite circuits inoperable, Action C.2 to extend the CT from the current value of 24 hours to 30 days maximum per the RICT program, if risk remains within the limits of the NEI 06-09-A guidance.
In the LAR, Enclosure 12, Risk Management Action (RMA) Examples, the licensee provided examples of RMAs that may be considered during a RICT program entry to reduce the risk impact and ensure adequate DID.
In its supplement dated November 24, 2020, the licensee provided the example RMAs which are likely to be implemented during RICT of TS 3.8.1, Condition C, Two offsite circuits inoperable.
TS 3.8.1, Condition D One required offsite circuit inoperable AND One required DG inoperable, Action D.1 or Action D.2 The licensee has proposed to apply the RICT program to TS 3.8.1, Condition D, One required offsite circuit inoperable AND One required DG inoperable, Action D.1 or Action D.2 to extend the CT from the current value of 12 hours to 30 days maximum per the RICT program, if the risk remains within the limits of the NEI 06-09-A guidance. In the LAR, Enclosure 12, Risk Management Action (RMA) Examples, the licensee provided examples of RMAs that may be considered during a RICT program entry to reduce the risk impact and ensure adequate DID. In particular, Enclosure 12 of the LAR listed the example RMAs which are likely to be implemented during TS action 3.8.1, Condition D, One required offsite circuit inoperable AND One required DG inoperable.
 
3.2.2.1.3 DC Sources - Operating (TS 3.8.4)
Description of the DC Sources CPS USAR Section 8, and TS Bases B.3.8.4 describe that each Division 1, 2, 3, and 4, battery has adequate storage capacity to meet the load duty cycle(s) discussed in the USAR, Section 8.3.2. Each DC battery subsystem is located in an area separated physically and electrically from the other subsystems to ensure that a single failure in one subsystem does not cause a failure in a redundant subsystem. There is no sharing between redundant Class 1E subsystems such as batteries, battery chargers, or distribution panels.
The batteries for a DC electrical power subsystem are sized to produce the required capacity at 80 percent of nameplate rating. The minimum design voltage limit is 105 volt (V). The battery cells are flooded lead acid construction with a nominal specific gravity of 1.215. This specific gravity corresponds to an open circuit battery voltage of approximately 120 V for a 58-cell battery (i.e., cell voltage of 2.065 volts per cell). The nominal float voltage of 2.22 Vpc corresponds to a total float voltage output of 128.8 V for a 58-cell battery. Each battery charger of Division 1, 2, 3, and 4, DC electrical power subsystems has ample power output capacity for the steady state operation of connected loads required during normal operation, while at the same time maintaining its battery bank fully charged. Each battery charger has sufficient excess capacity to restore the battery bank from the design minimum charge to its fully charged state within 12 hours while supplying normal steady-state loads.
TS 3.8.4 - Changes Relating to DC Power - Operating See Section 2.2 of this SE for a detailed view of TS changes.
Evaluation of TS Changes Relating to DC Sources - Operating For each change identified below, the NRC staff reviewed the information pertaining to the proposed TS change in the LAR, the USAR, and applicable TS LCO and TS Bases to verify that the capability of the affected electrical power systems to perform their safety functions (assuming no additional failures) is maintained. To achieve that objective, the NRC staff verified that the proposed TS conditions design success criteria (as provided in Enclosure 1 of the LAR) reflect the redundant or absolute minimum electrical power source/subsystem required to be operable to support the safety functions necessary to mitigate postulated DBAs, safely shut down the reactor, and maintain the reactor in a safe shutdown condition. In addition, the staff reviewed the proposed RMA examples for reasonable assurance that these RMAs are appropriate to monitor and control risk for the condition applicable to the proposed TS change.
TS 3.8.4, Condition A One battery charger on Division 1 or 2 inoperable, Action A.3 The licensee has proposed to apply the RICT program to TS 3.8.4, Condition A, One battery charger on Division 1 or 2 inoperable, Action A.3 to extend the CT from the current value of 7 days to 30 days maximum per the RICT program, if the risk remains within the guidance of NEI 06-09-A. In the LAR, Enclosure 12, Risk Management Action (RMA) Examples, the licensee provided examples of RMAs that may be considered during a RICT program entry to reduce the risk impact and ensure adequate DID. In particular, Enclosure 12 of the LAR listed the example RMAs which are likely to be implemented during TS action 3.8.4.A, One battery charger on Division 1 or 2 inoperable.
 
Considering that the CT extension will be implemented if the risk values are in accordance with the NEI 06-09-A guidance, and that additional RMAs will be implemented, the NRC staff finds that the plant will have adequate DID. Therefore, the NRC staff finds the application of the RICT program to TS 3.8.4, Condition A, One battery charger on Division 1 or 2 inoperable, Action A.3, acceptable.
TS 3.8.4, Condition B One battery on Division 1 or 2 inoperable, Action B.1 The licensee has proposed to apply the RICT program to TS 3.8.4, Condition B, One battery on Division 1 or 2 inoperable, Action B.1 to extend the CT from the current value of 2 hours to 30 days maximum per the RICT program, if risk remains within the guidance of NEI 06-09-A. In the LAR, Enclosure 12, Risk Management Action (RMA) Examples, the licensee provided examples of RMAs that are likely to implemented during a RICT program entry to reduce the risk impact and ensure adequate DID.
In the supplement dated November 24, 2020, the licensee provided the example RMAs which are likely to be implemented during RICT of TS 3.8.4, Condition B, One battery on Division 1 or 2 inoperable.
(c)      TS 3.8.4, Condition C Division 1 or 2 DC electrical power subsystem inoperable for reasons other than Condition A or B, Action C.1 The licensee has proposed to apply the RICT program to TS 3.8.4, Condition C, Division 1 or 2 DC electrical power subsystem inoperable for reasons other than Condition A or B, Action C.1 to extend the CT from the current value of 2 hours to 30 days maximum per the RICT program, if risk remains within the guidance of NEI 06-09-A. In the LAR, Enclosure 12, Risk Management Action (RMA) Examples, the licensee provided examples of RMAs that are likely to be implemented during a RICT program entry to reduce the risk impact and ensure adequate DID.
In the supplement dated November 24, 2020, , the licensee provided the example RMAs which will be implemented during RICT of TS 3.8.4, Condition C, Division 1 or 2 DC electrical power subsystem inoperable for reasons other than Condition A or B.
3.2.2.1.4 Inverters - Operating (TS 3.8.7)
Description of the Inverters CPS USAR, Section 8, and TS Bases B.3.8.7, describe that the inverters are the preferred source of power for the uninterruptible AC buses and the RPS solenoid buses because of the stability and reliability they achieve. There is one inverter per uninterruptible AC bus (comprising a total of four divisional inverters) and one inverter per RPS solenoid bus (comprising a total of two RPS solenoid bus inverters). The function of the inverter is to provide AC electrical power to these buses. The inverters are powered from both AC and DC sources.
The DC source provides an uninterruptible power source for the instrumentation and controls (I&C) for the RPS, the ECCS initiation, miscellaneous isolations, and the RPS and main steam isolation valve (MSIV) solenoids.
The divisional inverters contain a solid-state transfer switch to automatically transfer to an alternate source if the inverter detects abnormal conditions, such as an internal inverter component failure or for handling fault clearing or inrush current demands. The transfer of the
 
divisional inverters to their alternate source will occur if the alternate source is either energized or deenergized.
TS 3.8.7 - Changes Relating to Inverters - Operating See Section 2.2 of this SE for a detailed view of TS changes.
Staff Evaluations of TS Changes Relating to Inverters - Operating For each change identified below, the NRC staff reviewed the information pertaining to the proposed TS change in the LAR, the USAR, and applicable TS LCO and TS Bases to verify that the capability of the affected electrical power systems to perform their safety functions (assuming no additional failures) is maintained. To achieve that objective, the NRC staff verified that the proposed TS conditions design success criteria (as provided in Enclosure 1 of the LAR) reflect the redundant or absolute minimum electrical power source/subsystem required to be operable to support the safety functions necessary to mitigate postulated DBAs, safely shut down the reactor, and maintain the reactor in a safe shutdown condition. In addition, the staff reviewed the proposed RMA examples for reasonable assurance that these RMAs are appropriate to monitor and control risk for the condition applicable to the proposed TS change.
TS 3.8.7, Condition A Division 1 or 2 inverter inoperable, Action A.1 The licensee has proposed to apply the RICT program to TS 3.8.7, Division 1 or 2 inverter inoperable, Action A.1 to extend the CT from the current value of 7 days to 30 days maximum per the RICT program, if risk remains within the guidance of NEI 06-09-A. In the LAR, 2, Risk Management Action (RMA) Examples, the licensee provided examples of RMAs that are likely to be implemented during a RICT program entry to reduce the risk impact and ensure adequate DID.
In its {{letter dated|date=November 24, 2020|text=letter dated November 24, 2020}}, the licensee provided the example RMAs which are likely to be implemented during RICT of TS 3.8.7, Condition A Division 1 or 2 inverter inoperable.
3.2.2.1.5 Distribution Systems - Operating (TS 3.8.9)
Description of the Distribution Systems CPS TS Bases B.3.8.9 describes that the onsite Class 1E AC and DC electrical power distribution systems are divided into three independent AC, four independent DC, and four divisional uninterruptible AC bus electrical power distribution subsystems.
The primary AC distribution system consists of each 4.16 kV ESF bus that has at least one separate and independent offsite source of power, as well as a dedicated onsite DG source.
Each 4.16 kV ESF bus is normally connected to a preferred source. If all offsite sources are unavailable, the onsite emergency DGs supply power to the 4.16 kV ESF buses. The DC distribution system provides control power for the 4.16 kV breakers which is supplied from the Class 1E batteries.
The secondary plant AC distribution system includes 480 V ESF load centers and associated loads, motor control centers, and transformers. The 120 V uninterruptible AC buses are arranged in four divisions and are normally powered from an inverter supplied with DC power.
The alternate power supply for the uninterruptible AC buses is a Class 1E constant voltage
 
source transformer powered from the same division as the associated inverter. There are four independent 125 vpc (volt per cell) electrical power distribution subsystems.
TS 3.8.9 - Changes Relating to Distribution Systems - Operating See Section 2.2 of this SE for a detailed view of TS changes.
Evaluation of TS Changes Relating to Inverters - Operating For each change identified below, the NRC staff reviewed the information pertaining to the proposed TS change in the LAR, the USAR, and applicable TS LCO and TS Bases to verify that the capability of the affected electrical power systems to perform their safety functions (assuming no additional failures) is maintained. To achieve that objective, the NRC staff verified that the proposed TS conditions design success criteria (as provided in Enclosure 1 of the LAR) reflect the redundant or absolute minimum electrical power source/subsystem required to be operable to support the safety functions necessary to mitigate postulated DBAs, safely shut down the reactor, and maintain the reactor in a safe shutdown condition. In addition, the staff reviewed the proposed RMA examples for reasonable assurance that these RMAs are appropriate to monitor and control risk for the condition applicable to the proposed TS change.
TS 3.8.9, Condition A One or more Division 1 or 2 AC electrical power distribution subsystems inoperable, Action A.1 The licensee has proposed to apply the RICT program to TS 3.8.9, Condition A, One or more Division 1 or 2 AC electrical power distribution subsystems inoperable, Action A.1 to extend the CT from the current value of 8 hours to 30 days maximum per the RICT program, provided no loss of function occurs and if risk remains within the guidance of NEI 06-09-A. In the LAR, 2, Risk Management Action (RMA) Examples, the licensee provided examples of RMAs that are likely to be implemented during a RICT program entry to reduce the risk impact and ensure adequate DID.
In its {{letter dated|date=November 24, 2020|text=letter dated November 24, 2020}}, the licensee provided the example RMAs which will be implemented during RICT of TS 3.8.9, Condition A, One or more Division 1 or 2 AC electrical power distribution subsystems inoperable.
TS 3.8.9, Condition B One or more Division 1 or 2 uninterruptible AC bus distribution subsystems inoperable, Action B.1 The licensee has proposed to apply the RICT program to TS 3.8.9, Condition B, One or more Division 1 or 2 uninterruptible AC bus distribution subsystems inoperable, Action B.1, to extend the CT from the current value of 8 hours to 30 days maximum per the RICT program, provided no loss of function occurs and if risk remains within the guidance of NEI 06-09-A. In the LAR, 2, Risk Management Action (RMA) Examples, the licensee provided examples of RMAs that are likely to be considered during a RICT program entry to reduce the risk impact and ensure adequate DID.
In its {{letter dated|date=November 24, 2020|text=letter dated November 24, 2020}}, the licensee provided the example RMAs which are likely to be implemented during RICT of TS 3.8.9, Condition B, One or more Division 1 or 2 uninterruptible AC bus distribution subsystems inoperable.
 
TS 3.8.9, Condition C One or more Division 1 or 2 DC electrical distribution subsystems inoperable, Action C.1 The licensee has proposed to apply the RICT program to TS 3.8.9, Condition C, One or more Division 1 or 2 DC electrical distribution subsystems inoperable, Action C.1, to extend the CT from the current value of 2 hours to 30 days maximum per the RICT program, provided no loss of function occurs and if risk remains within the guidance of NEI 06-09-A. In the LAR, 2, Risk Management Action (RMA) Examples, the licensee provided examples of RMAs that are likely to be considered during a RICT program entry to reduce the risk impact and ensure adequate DID.
In the supplement dated November 24, 2020, the licensee provided the example RMAs which are likely to be implemented during RICT of TS 3.8.9, Condition C, One or more Division 1 or 2 DC electrical distribution subsystems inoperable.
3.2.2.1.6        Electrical Power Systems Evaluation Conclusion The NRC staff finds that while the redundancy is not maintained (e.g., one train of a two-train system is inoperable), the CT extensions in accordance with the RICT program are acceptable because: (1) the capability of the systems to perform their safety functions (assuming no additional failures) is maintained thereby maintaining DID, and (2) the licensees demonstration of identifying and implementing compensatory measures or RMAs, in accordance with the RICT program, are appropriate to monitor and control risk.
3.2.2.2    Evaluation of Instrumentation and Control (I&C) Systems The licensee has requested to use the RICT program to extend the existing CT for the following TS conditions. The NRC staffs evaluation of the proposed changes considered a number of potential plant conditions allowed by the new TSs and considered what redundant or diverse means were available to assist the licensee in responding to various plant conditions. The plant conditions evaluated are discussed in more detail below. See Section 2.2 for a detailed view of TS changes.
LCO 3.3.1.1      Reactor Protection System (RPS) Instrumentation LCO 3.3.4.1      End of Cycle Recirculation Pump Trip (EOC-RPT) Instrumentation LCO 3.3.5.1      Emergency Core Cooling System (ECCS) Instrumentation LCO 3.3.5.3      Reactor Core Isolation Cooling (RCIC) System Instrumentation LCO 3.3.6.1      Primary Containment and Drywell Isolation Instrumentation LCO 3.3.6.3      Residual Heat Removal (RHR) Containment Spray System Instrumentation LCO 3.3.6.4      Suppression Pool Makeup (SPMU) System Instrumentation LCO 3.3.6.5      Relief and Low-Low Set (LLS) Instrumentation LCO 3.3.8.1      Loss of Power (LOP) Instrumentation  of the LAR provided information supporting the evaluation of the redundancy and diversity of instrumentation included in the TS changes proposed. The information provided in  of the LAR was evaluated as described in the subsections below.
 
The NRC staff followed the guidance formulated in RG 1.174 and elaborated upon in RG 1.177, to assess the proposed changes consistency with DID criteria. The applicable DID criteria to the affected CPS I&C systems are:
* Over-reliance on programmatic activities as compensatory measures associated with the change in the LB is avoided.
* System redundancy, independence, and diversity are maintained commensurate with the expected frequency and consequences of challenges to the system (e.g., there are no risk outliers).
* Defenses against potential CCF are maintained and the potential for the introduction of new common cause failure mechanisms is assessed.
* The intent of the plants design criteria is maintained.
The licensee confirmed, and NRC staff verified that, in accordance with the CPS USAR in all applicable operating modes, the affected protective feature would perform its intended function by ensuring the ability to detect and mitigate the associated event or accident when the CT of a channel is extended. The RICT program is not being applied to shutdown modes. Therefore, the NRC staff concludes that the intent of the plants design criteria for the I&C functions identified in the amendment are maintained.
The NRC staff finds that while in an LCO condition, the redundancy of the function will be temporarily relaxed, and consequently the system reliability will be degraded accordingly. The NRC staff examined the design information from the CPS USAR and the risk-informed LCO conditions for the affected I&C functions. Based on this information, the NRC staff confirmed that under any given DBA evaluated in the CPS USAR, the affected I&C protective features maintains adequate DID by either necessary redundancy (e.g., at least one redundant channel) and/or necessary diversity (e.g., at least one alternative safety feature).
The licensee stated in the LAR that the proposed changes do not alter CPS I&C system designs. Consequently, the NRC staff concludes that the proposed changes do not alter the ways in which the CPS I&C systems fail, and do not introduce new CCF modes, and that system independence is maintained. The NRC staff finds that some proposed changes reduce the level of redundancy of the affected I&C systems, and this reduction may reduce the level of defense against some CCFs; however, the NRC staff finds, as described below, that such reduction in redundancy and defense against common cause failures are acceptable due to existing diverse means available to maintain adequate DID against a potential single failure during the RICT for the CPS I&C systems.
The following sections summarize the NRC staffs findings with respect to the DID principle for the functions identified in the LAR by identifying associated diverse means that maintain adequate DID against potential single failure during an RICT for the CPS I&C systems.
3.2.2.2.1 LCO 3.3.1.1 Reactor Program System (RPS) Instrumentation The LAR states that the RPS is a fail-safe system design (de-energizes to trip) and is comprised of four independent trip logic divisions as described in USAR, Section 7.2. In addition to RPS de-energizing the scram pilot valves and energizing the backup scram valves, CPS has redundant and diverse methods of shutting down the reactor in the unlikely event that the RPS does not SCRAM the reactor (anticipated transient without scram (ATWS), alternate rod
 
insertion (ARI), recirculation pump trip (RPT) breakers, and the standby liquid control system (SLCS)).
The logic trip arrangement, redundancy, and diverse inputs causing a trip of the RPS are discussed and shown in USAR Section 7.2 and Figures 7.2-2 thru 7.2-4, CPS TS LCO 3.3.3.1, Table 3.3.1.1-1 and Bases B3.3.1.1 and reflected in Attachment 5 of the LAR.
The NRC staff finds that the RPS design has sufficient redundancy, diversity, and DID to protect against common cause failures and potential failure during the RICT for the CPS I&C systems and does not rely on manual actions as the only diverse means; therefore, there is no over-reliance on programmatic activities as compensatory measures.
3.2.2.2.2 LCO 3.3.4.1 End of Cycle-Recirculation Pump Trip (EOC-RPT) Instrumentation The LAR states that the EOC-RPT instrumentation initiates a recirculation pump trip (RPT) to reduce the peak reactor pressure and power resulting from turbine trip or generator load rejection transients to provide additional margin to core thermal MCPR Safety Limits.
The logic trip arrangement, redundancy, and diverse inputs causing a trip of the EOC-RPT are discussed and shown in USAR Section 7.6.1.8, CPS TS LCO 3.3.4.1 and Bases B3.3.4.1 and reflected in Attachment 5 of the LAR.
The NRC staff finds that the EOC-RPS design has sufficient redundancy, diversity, and DID to protect against common cause failures and potential single failure during the RICT for the CPS I&C systems and does not rely on manual actions as the only diverse means; therefore, there is no over-reliance on programmatic activities as compensatory measures.
3.2.2.2.3 LCO 3.3.5.1 ECCS Instrumentation The LAR states that the purpose of the ECCS instrumentation is to initiate appropriate responses from the systems to ensure that fuel is adequately cooled in the event of a design basis accident or transient. The ECCS instrumentation actuates low-pressure core spray (LPCS), LPCI, high-pressure core spray (HPCS), ADS, and the DGs.
For instrumentation that has the potential for a configuration in which trip capability is not maintained, a Note was added to the CT which prohibits applying a RICT when trip capability is not maintained.
The logic trip arrangement, redundancy, and diverse inputs causing a trip of the ECCS are discussed and shown in USAR Sections 5.2.2, 6.3, and 7.3, CPS TS LCO 3.3.5.1, Table 3.3.5.1-1, and reflected in Attachment 5 of the LAR.
The NRC staff finds that the ECCS design has sufficient redundancy, diversity, and DID to protect against CCFs and potential single failure during the RICT for the CPS I&C systems and does not rely on manual actions as the only diverse means; therefore, there is no over-reliance on programmatic activities as compensatory measures .
3.2.2.2.4 LCO 3.3.5.3 Reactor Core Isolation Cooling (RCIC) System The LAR states that the RCIC system instrumentation is to initiate actions to ensure adequate core cooling when the reactor vessel is isolated from its primary heat sink (the main condenser)
 
and normal coolant makeup flow from the reactor feedwater system is unavailable, such that initiation of the low pressure ECCS pumps does not occur.
For instrumentation that has the potential for a configuration in which trip capability is not maintained, a Note was added to the CT which prohibits applying a RICT when trip capability is not maintained. The logic trip arrangement, redundancy, and diverse inputs causing a trip of the RCIC system are discussed and shown in USAR Section 7.4.1.1.3.2, CPS TS LCO 3.3.5.3, Table 3.3.5.3-1 and reflected in Attachment 5 of the LAR.
The NRC staff finds that the RCIC system design has sufficient redundancy, diversity, and DID to protect against common cause failures and potential single failure during the RICT for the CPS I&C systems and does not rely on manual actions as the only diverse means; therefore, there is no over-reliance on programmatic activities as compensatory measures.
3.2.2.2.5 LCO 3.3.6.1 Primary Containment and Drywell Isolation Instrumentation The LAR states that the primary containment and drywell isolation instrumentation automatically initiates closure of appropriate primary containment isolation valves (PCIVs) and drywell isolation valves. The function of the PCIVs, in combination with other accident mitigation systems, is to limit fission product release during and following postulated DBAs. Functional diversity is provided by monitoring a wide range of independent parameters.
For instrumentation that has the potential for a configuration in which trip capability is not maintained, a Note was added to the CT which prohibits applying a RICT when trip capability is not maintained.
The logic trip arrangement, redundancy, and diverse inputs causing a trip of the primary containment and drywell isolation instrumentation are discussed and shown in USAR Section 7.3.1.1.2, CPS TS LCO 3.3.6.1, Table 3.3.6.1-1, and reflected in Attachment 5 of the LAR.
The NRC staff finds that the primary containment and drywell isolation instrumentation design has sufficient redundancy, diversity, and DID to protect against common cause failures and potential single failure during the RICT for the CPS I&C systems and does not rely on manual actions as the only diverse means; therefore, there is no over-reliance on programmatic activities as compensatory measures.
3.2.2.2.6 LCO 3.3.6.3 Residual Heat Removal (RHR) Containment Spray System (CSS)
Instrumentation The LAR states that the RHR CSS is an operating mode of the RHR system that is initiated to condense steam in the containment atmosphere. This ensures that containment pressure is maintained within its limits following a LOCA.
For instrumentation that has the potential for a configuration in which trip capability is not maintained, a Note was added to the CT which prohibits applying a RICT when trip capability is not maintained.
The logic trip arrangement, redundancy, and diverse, inputs causing a trip of the RHR CSS are discussed and shown in USAR Section 7.3.1.1.4, CPS TS LCO 3.3.6.3, Table 3.3.6.3-1, and reflected in Attachment 5 of the LAR.
 
The NRC staff finds that the RHR CSS design has sufficient redundancy, diversity, and DID to protect against common cause failures and potential single failure during the RICT for the CPS I&C systems and does not rely on manual actions as the only diverse means; therefore, there is no over-reliance on programmatic activities as compensatory measures .
3.2.2.2.7 LCO 3.3.6.4 Suppression Pool Makeup (SPMU) System Instrumentation The LAR states that the SPMU system provides water from the upper containment pool to the suppression pool, by gravity flow, after a LOCA to ensure that primary containment temperature and pressure design limits are met.
For instrumentation that has the potential for a configuration in which trip capability is not maintained, a Note was added to the CT which prohibits applying a RICT when trip capability is not maintained.
The logic trip arrangement, redundancy, and diverse, inputs causing a trip of the SPMU system, are discussed and shown in USAR Section 7.3.1.1.10, CPS TS LCO 3.3.6.4, Table 3.3.6.4-1, and reflected in Attachment 5 of the LAR.
The NRC staff finds that the SPMU design has sufficient redundancy, diversity, and DID to protect against CCFs and potential single failure during the RICT for the CPS I&C systems and does not rely on manual actions as the only diverse means; therefore, there is no over-reliance on programmatic activities as compensatory measures.
3.2.2.2.8 LCO 3.3.6.5 Relief and Low Low Set (LLS) Instrumentation The LAR states that the safety relief valves (SRVs) prevent overpressurization of the nuclear steam system. Instrumentation is provided to support two modes (in addition to the ADS mode of operation for selected valves) of SRV operation.
The logic trip arrangement, redundancy, and diverse, inputs causing a trip of the LLS instrumentation are discussed and shown in USAR Section 7.3.1.1.1.4, 7.3.1.1.1.4.2, CPS TS LCO 3.3.6.5 and are reflected in Attachment 5 of the LAR.
The NRC staff finds that the LLC design has sufficient redundancy, diversity, and DID to protect against common cause failures and potential single failure during the RICT for the CPS I&C systems and does not rely on manual actions as the only diverse means; therefore, there is no over-reliance on programmatic activities as compensatory measures.
3.2.2.2.9 LCO 3.3.8.1 Loss of Power (LOP) Instrumentation The electrical aspects of the loss of power instrumentation is described in Section 3.2.2.1.1, Loss of Power (LOP) Instrumentation (TS 3.3.8.1), above. The defense-in-depth aspects of concern to instrumentation and controls were evaluated but this section does not repeat the detailed description of electrical and loss of power instrumentation descriptions above.
For instrumentation that has the potential for a configuration in which trip capability is not maintained, a Note was added to the CT which prohibits applying a RICT when trip capability is not maintained.
 
The logic trip arrangement, redundancy, and diverse, inputs causing a trip of the LOP instrumentation are discussed and shown in USAR Section 8.3.1.1.2, CPS LCO 3.3.8-1, TS Table 3.3.8.1-1, and reflected in attachment 5 of the LAR.
The NRC staff finds that the LOP design has sufficient redundancy, diversity, and DID to protect against common cause failures and potential single failure during the RICT for the CPS I&C systems and does not rely on manual actions as the only diverse means; therefore, there is no over-reliance of programmatic activities as compensatory measures .
3.2.2.2.10 Instrumentation and Control (I&C) Evaluation Conclusion Since the licensee did not propose any changes to the design basis, the independency and the fail-safe principle remain unchanged. The licensee stated in the LAR that the proposed changes did not include any TS loss of function conditions. However, it is recognized that while in an ACTION statement, redundancy of the given protective feature will be temporarily reduced, and, accordingly, the system reliability will be reduced. In the LAR, the licensee stated in the description of proposed changes to the I&C systems that at least one redundant or diverse means (e.g., other automatic features or manual action) to accomplish the safety functions (e.g., reactor trip, safety injection, or containment isolation) remain available during the use of the RICT. The NRC staff reviewed the licensees proposed TS changes to assess the availability of the redundant or diverse means to accomplish the safety function(s). The NRC staff finds that the availability of the redundant or diverse protective features provide sufficient DID to accomplish the safety functions, allowing for the extension of CTs in accordance with the RICT program. The NRC staff finds that the licensees proposed RICT program for the identified I&C systems is in compliance with 10 CFR 50.36(b).
The NRC staff reviewed the licensees proposed TS changes and supporting documentation.
The staff finds that while the I&C redundancy is reduced, the CT extensions implemented in accordance with the RICT program are acceptable because: (1) the capability of the I&C systems to perform their safety functions is maintained, (2) redundant or diverse means to accomplish the safety functions exist, and (3) the licensee will identify and implement risk management actions to monitor and control risk in accordance with the RICT program.
3.2.2.3 Evaluation of Balance of Plant Components The regulation in 10 CFR 50.36(c)(2) requires that TSs contain LCOs, which are the lowest functional capability or performance levels of equipment required for safe operation of the facility. When an LCO is not met, the licensee shall shut down the reactor or follow any remedial action permitted by the TSs. In Attachment 2, the licensee proposed a Note, Not applicable if loss of function, for TS LCO conditions to prohibit entering a RICT during a loss of function condition. However, the proposed change to TS LCO 3.7.6 (main turbine bypass system), Condition A, (requirements of LCO not met) appears to include a TS loss of function and has no such Note. Enclosure 1 to the LAR, Table E1-1, indicates that the design basis success criteria for TS 3.7.6.A requires all six turbine bypass valves to be operable, indicating loss of function with a failure of a single valve. Therefore, the NRC staff asked the licensee to justify that the proposed RICT for TS 3.7.6.A did not include a loss of function.
In its response, dated November 24, 2020, the licensee stated that the purpose of LCO 3.7.6 is to limit peak pressure in the main steam lines and maintain reactor pressure within acceptable limits during events that cause rapid pressurization, which is accomplished by either: (1) the main turbine bypass system, or (2) by limiting reactor power and implementing designated
 
thermal limits in accordance with the cycle-dependent COLR and modifications to the MCPR limits and LHGR limits. The cycle-specific analyses as documented in the COLR evaluate different combinations of turbine bypass valves (TBVs) that are out-of-service (OOS). The COLR for the current operating cycle supports full power operation with one TBV OOS, but also considers different conditions including all TBVs OOS. As a result, the LCO function of limiting peak pressure in the main steam lines and maintaining reactor pressure within acceptable limits continues to be met under the conditions analyzed in the cycle-specific analyses, which includes all TPVs OOS. Based on the number of TBVs out of service, the correct COLR thermal limit set is selected. By using the correct thermal limit, the analyzed design function of the TBVs will be met and no loss of function results.
The NRC staff finds that the licensees response clarifies that if a turbine bypass valve fails, LCO 3.7.6 function is maintained by limiting reactor power and implementing designated thermal limits in accordance with the cycle-dependent COLR and modifications to the MCPR limits and LHGR limits. Therefore, the staff finds that the licensees response demonstrates that no loss of function exists.
3.2.2.4 Key Principle 2: Conclusions The LAR proposes to modify the TS requirements to permit extending selected CTs using the RICT program in accordance with NEI 06-09-A. The NRC staff finds that extending the selected CTs with the RICT program following loss of redundancy, but maintaining the capability of the system to perform its safety function, is an acceptable reduction in DID provided that the licensee identifies and implements RMAs in accordance with the RICT program during the extended CT.
Quantitative risk analysis, qualitative considerations including compensatory measures, and retaining the current CT for loss of all trains of a required system, assure that DID is maintained to assure adequate protection of public health and safety. The NRC staff finds that the proposed changes are consistent with the DID philosophy because:
* System redundancy (with the exceptions discussed above), independence, and diversity commensurate with the expected frequency and consequences of challenges to the system is preserved.
* Adequate capability of design features without an overreliance on programmatic activities as compensatory measures is preserved.
* The intent of the plants design criteria continues to be met.
Therefore, the NRC staff finds that the proposed change to modify the TS requirements to permit extending selected CTs using the RICT program in accordance with NEI 06-09-A meets the second key safety principle of RG 1.177 and is, therefore, acceptable. Additionally, the NRC staff concludes that the change is consistent with the DID philosophy as described in RG 1.174.
 
3.2.3    Key Principle 3: Evaluation of Safety Margins Section 2.2.2 of RG 1.177, Revision 1, states, in part, that sufficient safety margins are maintained when:
* Codes and standards  or alternatives approved for use by the NRC are met.
* Safety analysis acceptance criteria in the final safety analysis report (FSAR) are met or proposed revisions provide sufficient margin to account for analysis and data uncertainties.
The licensee is not proposing in this application to change any quality standard, material, or operating specification. Acceptance criteria for operability of equipment are not changed and use of the RICT only when the system(s) retain(s) the capability to perform the applicable safety function(s) ensure that the current safety margins are retained. Safety margins are also maintained if PRA functionality is determined for the inoperable train which would result in an increased CT. Credit for PRA functionality, as described in NEI 06-09-A, is limited to the inoperable train, loop, or component. The reduced but available functionality may support a further increase in the CT consistent with available safety margin. The specified safety function is still being met by the operable train and therefore requires no evaluation of PRA functionality to meet the design basis success criteria.
3.2.3.1 Key Principle 3: Conclusions The NRC staff finds that the design-basis analyses for CPS remain applicable. Although the licensee will be able to have design-basis equipment out-of-service longer than the current TS allow and the likelihood of successful fulfillment of the function will be decreased when redundant train(s) are not available, the capability to fulfill the function will be retained when the available equipment functions as designed. Any increase in unavailability because less equipment is available for a longer time is included in the RICT evaluation and is expected to be insignificant given the relatively short duration of the extended CT. Therefore, sufficient safety margins are maintained with the implementation of the RICT program. The NRC staff concludes that the proposed changes meet the third key safety principle of RG 1.177 and are acceptable.
3.2.4    Key Principle 4: Change in Risk Consistent with the Safety Goal Policy Statement TS Section 5.5.17 Risk Informed Completion Time Program, states that the RICT must be implemented in accordance with NEI 06-09, Revision 0,Risk-Managed Technical Specification (RMTS) Guidelines.
NEI 06-09 provides a methodology for a licensee to evaluate and manage the risk impact of extensions to TS CTs. Permanent changes to the fixed TS CTs are typically evaluated by using the three-tiered approach described in Chapter 16.1 of the SRP, RG 1.177, and RG 1.174, Revision 1. This approach addresses the calculated change in risk as measured by the change in delta core damage frequency (CDF) and delta large early release frequency (LERF), as well as the incremental conditional core damage probability and incremental conditional large early release probability; the use of compensatory measures to reduce risk; and, the implementation of a configuration risk management program (CRMP) to identify risk-significant plant configurations.
 
The NRC staff evaluated the licensees processes and methodologies for determining that the change in risk from implementation of RICTs will be small and consistent with the intent of the Commissions Safety Goal Policy Statement, as discussed below. The NRC staff evaluated the licensees proposed changes against the three-tiered approach in RG 1.177, Revision 1, for the licensees evaluation of the risk associated with a proposed TS CT change. The results of the staffs review are discussed below.
3.2.4.1 Tier 1: PRA Capability and Insights The first tier evaluates the impact of the proposed changes on plant operational risk. The Tier 1 review involves two aspects: (1) the technical acceptability of the PRA models and their application to the proposed changes, and (2) a review of the PRA results and insights described in the licensees application.
3.2.4.1.1    PRA Technical Acceptability Scope of PRA RG 1.174 states that the scope, level of detail, and technical adequacy of the PRA are to be commensurate with the application for which it is intended and the role the PRA results play in the integrated decision process. The NRCs SE for NEI 06-09 states that the PRA models should conform to the guidance in RG 1.200, Revision 1, An Approach for Determining the Technical Adequacy of Probabilistic Risk Assessment Results for Risk-Informed Activities, January 2017 (Reference 13). The current version is RG 1.200, Revision 2, which clarifies the current applicable American Society of Mechanical Engineers/American Nuclear Society (ASME/ANS) PRA Standard is ASME/ANS RA-Sa-2009, Addenda to ASME RA-S-2008, Standard for Probabilistic Risk Assessment for Nuclear Power Plant Applications (Reference 14). For external hazards for which a PRA is not available, the guidance in NEI 06-09-A allows for the use of bounding analysis of the risk contribution of the hazard for incorporation into the RICT calculation or justification for why the hazard is not significant to the RICT calculation.
According to the LAR, the proposed RICT program is only applicable to operational conditions (or Modes) 1 and 2, therefore, risk evaluations for Modes 3, 4, and 5, are not relevant to the proposed change.
The NRC staff evaluated the PRA acceptability information provided by the licensee in  of its submittal, including industry peer review results and the licensees self-assessment of the PRA models for internal events, including internal flooding, and fire, against the guidance in RG 1.200, Revision 2. The licensee screened out all external hazard events, except for seismic, as described in Section 3.2.4.1.2 of this SE, as insignificant contributors to RICT calculations. The CPS PRA model with modifications is used as the CRMP model as described in Section 3.2.4.1.2 of this SE. In addition, the licensee provided a bounding estimate of the seismic CDF and LERF and included those CDF and LERF values in the change-in-risk used to calculate RICTs consistent with the guidance in NEI 06-09-A 3.2.4.1.2 Evaluation of PRA Acceptability for Internal Events and Internal Fires Internal Events PRA (IEPRA) (Includes Internal Flooding)
The CPS PRA is comprised of a full-power, Level 1, IEPRA which evaluates the CDF and LERF risk metrics. The licensee discussed in Enclosure 2 of the LAR that the IEPRA (includes
 
internal floods) model had been assessed against RG 1.200, Revision 2. The NRC staff evaluated the scope of the PRA including: (1) peer-review history and results, (2) the Appendix X, independent assessment process, (3) credit for FLEX in the PRA, and (4) assessment of key assumptions and key sources of uncertainty. The NRC staff also performed a review of the remaining open facts and observations (F&Os) for the IEPRA, along with the dispositions provided in Enclosure 2 of the LAR and its supplements.
For both the CPS 10 CFR 50.69 (Reference 16) and the CPS TSTF-505 risk-informed applications, the PRA models were reviewed against the current PRA Standard across all technical elements at Capability Category (CC) II. Therefore, the staffs review of the IEPRA (includes internal floods) model for PRA acceptability was performed concurrently with the CPS 10 CFR 50.69 application. A detailed staff evaluation of the IEPRA peer review history is provided in the NRC staffs safety evaluation dated May 19, 2021 (Reference 17). The NRC staffs evaluation of the key assumptions and key sources of uncertainty specific to the TSTF-505 application are provided below.
Based on its review, and applicable precedent provided in the issuance of the SE for CPSs adoption of 10 CFR 50.69, the NRC staff finds that the IEPRA has been peer reviewed consistent with RG 1.200, Revision 2; F&Os were closed consistent with Appendix X guidance of NEI 07-12, Revision 0, Fire Probabilistic Risk Assessment (FPRA) Peer Review Process Guidelines, Draft Version H, November 2008 (Reference 18), as accepted, with conditions by the NRC staff; and any remaining open F&Os have been appropriately assessed for impact on the RICT program. Therefore, the NRC staff concludes that the internal events PRA, including internal flooding, is acceptable for use in the RICT program.
Internal Fire Events PRA The NRC staff review of the CPS fire PRA was based on the results of a full-scope peer review of the fire PRA and two F&Os closure reviews described in LAR Enclosure 2. The full-scope peer review of the fire PRA was performed in April 2018 using the NEI 07-12 process and the guidance in the ASME/ANS RA-Sa-2009 PRA Standard and RG 1.200, Revision 2.
The licensee stated that the 2018 fire PRA peer review F&Os were addressed in subsequent fire PRA updates and the resolutions to the F&Os were reviewed by independent review teams in two separate F&O Closures (December 2018 and November 2019) that included fire PRA F&Os. The second CPS fire PRA F&O closure review performed in November 2019 resulted in closing all finding level F&Os.
Extensive and detailed reviews of fire PRAs undertaken in support of LARs to transition to National Fire Protection Association-805 determined that implementation of some of the complex fire PRA methods often used non-conservative and over-simplified assumptions to apply the method to specific plant configurations. Accordingly, the NRC staff requested the following fire PRA information that did not appear to be addressed by other docketed information.
On October 27, 2020 (Reference 19), the NRC staff requested information about the use of reduced transient fire heat release rates (HRRs) below those prescribed in NUREG/CR-6850, EPRI/NRC Fire PRA Methodology for Nuclear Power Facilities, September 2005 (Reference 20), and NUREG/CR-6850, Supplement 1, Fire Probabilistic Risk Assessment Methods Enhancement, September 2010 (Reference 21), and justification if reduced HRRs were used.
 
Key factors for justifying reduced HRRs below those prescribed in NUREG/CR-6850 are discussed in guidance provided in the {{letter dated|date=June 21, 2012|text=June 21, 2012, letter}} from Joseph Giitter, NRC, to Biff Bradley, NEI (Reference 22).
In its {{letter dated|date=November 24, 2020|text=letter dated November 24, 2020}}, the licensee explained that for the cable spreading rooms (CSRs), three potential transient fire sizes were assessed (i.e., 60 kW (kilowatt), 145 kW, and 317 kW). The licensee stated that the cited results of fire tests reported in NUREG/CR-6850 for 60 kW, 145 kW, and 317 kW, fires were considered representative for spaces in the CSRs. The licensee explained that detailed fire modeling was performed for each of the three fire sizes and that the results of the fire modeling were averaged, and the average probability of fire damage was used in the fire PRA (i.e., product of the Severity Factor and Non-Suppression Probability).
The licensee justified the use of a reduced HRR by addressing factors described in the NRC {{letter dated|date=June 21, 2012|text=letter dated June 21, 2012}}.
The licensee cited its transient combustible material control procedure and explained that Transient Combustible Permits (TCPs) are required and reviewed by the Fire Marshall and procedures provide specific guidance for storage and transporting combustible materials in Transient Combustible Free Zones. The licensee stated that per procedure, combustible materials are limited in Transient Combustible Free Zones to materials required to support work activity and are immediately removed from the area following completion of the task. The licensee presented a list of the TCPs from the last 4 years for the CSRs showing that the increase in combustible loading in British Thermal Units (BTUs) compared to the BTUs for cable loading for each TCP is only about 1% or lower. The licensee also showed that over this same time period (i.e., since 2016), there have been no compliance issues or violations associated with the use of transient combustibles in the CSRs.
Based on its review, the NRC staff finds the licensees use of reduced HRRs in the CSRs to be acceptable and consistent with NRC guidance because: (1) the reduced HRRs used are based on the results of fire tests reported in NUREG/CR-6850 that represent fires that could happen in the CSRs, (2) transient combustible controls are implemented for the areas where reduced HRRs are credited (i.e., CSRs) and are implemented through a TCP which requires materials to be removed immediately following completion of the task, (3) the historical increase in combustible loading in the CSRs when a TCP is used is very low, and (4) there have been no compliance issues or violations associated with the use of transient combustibles in the CSRs.
On October 27, 2020, the NRC staff requested information about the treatment of sensitive electronics and whether the treatment was consistent with the guidance in Frequently Asked Questions (FAQ) 13-0004, Clarifications on Treatment of Sensitive Electronics, dated December 3, 2013 (Reference 23), including the caveats about configurations that can invalidate the approach (i.e., sensitive electronics mounted on the surface of cabinets and the presence of louver or vents).
In its {{letter dated|date=November 24, 2020|text=letter dated November 24, 2020}}, the licensee explained that its treatment of sensitive electronics is consistent with the guidance in FAQ 13-0004 in which the damage threshold for thermoset cable is used for sensitive electronics within an electrical cabinet. However, the response also explains that the caveats cited in FAQ 13-0004 about configurations that invalidate the approach were not explicitly addressed. The licensee stated that consideration of such configurations should have negligible impact on fire risk due to the functions associated with sensitive electronics (e.g., a single logic channel).
 
The licensee also stated that a gap in the analysis could exist where the exposed sensitive electronics are beyond the zone of influence (ZOI) of the ignition source determined by thermoset failure criteria allowed by FAQ 13-0004 but within a ZOI defined by the nominal damage criteria for sensitive electronics (i.e., criteria from NUREG/CR-6850). The licensee suggested that its treatment of the potential for fire to grow beyond the analyzed ZOI offset the this identified gap. As further justification of its treatment, the licensee provided an evaluation of a sampling of seven sensitive electronics cabinet configurations and determined that the sensitive electronics: (1) have no impact on a PRA credited function, (2) are not damaged in fire, or (3) failure is already accounted for in the fire PRA scenarios.
On February 26, 2021 (Reference 24), the NRC staff stated its view that the limited sampling was insufficient to determine the impact of the modeling assumption on the RICT calculations and with this observation and others discussed above, and the staff therefore requested justification that the licensees treatment of sensitive electronics will have negligible impact on the RICT calculations.
In its March 23, 2021, response, the licensee described its evaluation of a sampling of cabinet configurations. The licensee explained that a plant walkdown was conducted by the Site Risk Management Engineer and a Senior Reactor Operator to identify sensitive electronics in risk significant areas of the CPS. For each of these areas, the licensee explained that either sensitive electronics were not associated with fire PRA credited equipment or failures of the sensitive electronics are already accounted for by the failures of other targets in the target set (e.g., fire-induced failure of different components that support the same function). The licensee also stated that these insights are representative of sensitive electronics in other areas of the plant not explicitly evaluated as part of the walkdown and that this supports the conclusion that cabinet configurations that invalidate the use of FAQ 13-004 would have negligible impact on fire risk.
Based on its review of the information provided by the licensee, the NRC staff concludes that the licensees approach of using the thermal damage threshold from FAQ 13-0004 for sensitive electronics without explicit consideration of the caveats about cabinet configuration that invalidate the approach is acceptable for the application. It is found acceptable because the licensee showed that sensitive electronics existing in the plant either are not associated with fire PRA credited equipment or their failures are already accounted for by the failures of other targets in the target set in propagating and non-propagating fire scenarios.
On October 27, 2020, the NRC staff requested information about whether minimum joint human error probabilities (HEP) values less than 1E-05 were assumed in the fire PRA. NUREG-1921, EPRI/NRC-RES Fire Human Reliability Analysis Guidelines- Final Report, July 2012 (Reference 25), discusses the need to consider a minimum value for the joint probability of HFEs. NUREG-1921 refers to Table 2-1 of NUREG-1792, Good Practices for Implementing Human Reliability Analysis (HRA), April 2005 (Reference 26), which recommends that joint HEP values should not be below 1E-5. Table 4-4 of Electrical Power Research Institute (EPRI) 1021081, "Establishing Minimum Acceptable Values for Probabilities of Human Failure Events," 2 provides a lower limiting value of 1E-6 for sequences with a very low level of dependence. Therefore, the guidance in NUREG-1921 allows for assigning joint HEPs that are less than 1E-5, but only through assigning proper levels of dependency. The NRC staff also requested the results of a sensitivity study if a minimum joint HEP less than 1E-05 is used in the fire PRA.
2 Available from Electric Power Research Institute, 3420 Hillview Avenue, Palo Alto, California 94304.
 
In its response dated November 24, 2020, the licensee explained that for fire PRA dependency analysis a minimum joint HEP of 1E-06 was used unless the timeframe for completing one or more actions in the combination was longer than 15 hours. In these cases, a lower minimum joint HEP of 5E-07 was used.
The licensee also explained that a sensitivity study was performed in which a minimum joint HEP of 1E-05 was applied in the sensitivity case and calculated the RICTs for a sample of eight LCOs selected because they represent plant configurations for which the RICTs are most likely to change in the sensitivity case. The results of the sensitivity study show that the calculated RICTs essentially did not change as the decreases in all calculated RICTs are less than 1 percent. The NRC staff finds the licensees application of minimum joint HEP values acceptable because the licensee shows it meets the intent of the above guidance to establish an appropriate minimum joint HEP value, with allowance for further decrease consistent with the level of dependency of HEPs in the combination; and even though the minimum joint HEP value for the fire PRA is set at 1E-06 opposed to 1E-05, the licensees sensitivity study demonstrated that setting the minimum joint HEP for the fire PRA to 1E-05 rather than 1E-6 has a minimal impact on the RICT application.
On October 27, 2020, NRC staff requested information about how well sealed cabinets were treated in the fire PRA. Information was requested about how fire propagation outside of well-sealed motor control centers (MCC) cabinets greater than 440 V was evaluated and whether it was consistent with the NRC guidance in fire PRA FAQ 14-0009, Treatment of Well-Sealed MCC Electrical Panels Greater than 440V, dated April 29, 2015 (Reference 27). Information was also requested about whether well-sealed cabinets less than 440 V are included in the Bin 15 count of ignition sources consistent with guidance in NUREG/CR-6850.
In its November 24, 2020, response, the licensee explained that all MCCs are assumed not to be well-sealed and, therefore, all fires originating from MCC cabinets are assumed to damage external targets. Accordingly, the refinements using the guidance in FAQ 14-0009 were not applied. The licensee also explained all other cabinets are also assumed not to be well-sealed, and therefore, cabinets less than 440 V are included in the Bin 15 count and fires postulated for those cabinets are evaluated for the potential to damage external targets. The NRC staff finds the licensees treatment of well-sealed cabinets consistent with the above guidance.
Based on its review, the NRC staff finds that the licensees fire PRA has been adequately peer reviewed against the current versions of the PRA standard and RG 1.200, that the licensee has adequately closed the F&Os, and the licensee has performed the fire PRA using the most current NRC approved guidance. Therefore, the NRC staff concludes that the fire PRA is technically acceptable to support the RICT program.
3.2.4.1.3 Evaluation of External Hazards The NRC staffs SE for NEI 06-09 states that sources of risk besides internal events and internal fires (i.e., seismic and other external events) must be quantitatively assessed if they contribute significantly to configuration-specific risk. The SE further states that bounding analyses or other conservative quantitative evaluations are permitted where realistic PRA models are unavailable.
In addition, the SE concludes that if sources of risk can be shown to be insignificant contributors to configuration risk, then they may be excluded from the RMTS.
As discussed in Section 3.2.4 of this SE, the PRA models used for the RICT program include contributions from internal events, including internal flooding, and fire events. In addition, the
 
licensee provided a conservative estimate of the seismic CDF (SCDF) and seismic LERF (SLERF) and will include those CDF and LERF values into the change-in-risk used to calculate RICTs consistent with the guidance in NEI 06-09-A. The licensee addressed the risk from seismic events and other external hazards in the context of this application in Enclosure 4 to the LAR.
In the LAR Enclosure 4, Section 2, the licensee stated that for the overall process, consistent with NUREG-1855, Revision 1, external hazards may be addressed by: (1) screening the hazard on low frequency of occurrence, (2) bounding the potential impact and including it in the decisionmaking, and (3) developing a PRA model to be used in the RMAT/RICT calculation.
The licensee stated that as part of this process the following two aspects of the external hazard contribution to risk should be considered.
* The first is the contribution from the occurrence of beyond design basis conditions, e.g.,
winds greater than design, seismic events greater than design-basis earthquake, etc.
These beyond design basis conditions challenge the capability of the SSCs to maintain functionality and support safe shutdown of the plant.
* The second aspect addressed are the challenges caused by external conditions that are within the design basis, but still require some plant response to assure safe shutdown, e.g., high winds or seismic events causing loss of offsite power, etc. While the plant design basis assures that the safety-related equipment necessary to respond to these challenges are protected, the occurrence of these conditions nevertheless causes a demand on these systems that presents a risk.
The NRC staff reviewed Enclosure 4 to the LAR dated April 30, 2020, and supplemental information dated November 24, 2020, to determine the acceptability of the consideration of risk from seismic events and other external hazards for this application.
Seismic Hazard Contribution to the RICT In LAR Enclosure 4, the licensee provided a conservative estimate for the risk from seismic events for use in determining the configuration risk for the RICTs identified in the LAR. The licensee explained in the LAR Enclosure 4, Section 3.0, that RICT calculations will include a risk contribution from seismic events using a seismic penalty approach. A seismic penalty, commonly used in RICT calculations and for estimation of SCDF, is performed using a mathematical convolution of the seismic hazard and plant level seismic capacity curves. For SLERF, the penalty is obtained by multiplying the calculated SCDF by an average seismic conditional large early release probability (CLERP). The licensees approach for including the seismic risk contribution in the RICT calculation is to add a constant SCDF and SLERF to each RICT calculation. Section 3.3.5 of NEI 06-09 states that for stations without external events PRAs, the station should apply one of three acceptable methods to determine external event risk. The second method, used for CPS, is to perform a reasonable bounding analysis which must be case-specific, technically verifiable, and must be shown to be conservative from the perspective of RICT determination. For application to CPS RICT calculations, the licensee proposed to add a SCDF contribution of 6.4E-06 per year and a SLERF contribution of 1.6E-06 per year to the configuration-specific delta risk contribution from internal events (including internal flooding) and internal fire events.
The licensees proposed SCDF estimate is based on using the plant-specific seismic hazard curves developed in response to the Near-Term Task Force Recommendation 2.1 dated March
 
31, 2014 (Reference 28), and supplemented on August 21, 2014 (Reference 29), and a plant-level high confidence of low probability of failure (HCLPF) capacity of 0.30g (gravity) referenced to peak ground acceleration (PGA). HCLPF is the capacity representing 95 percent confidence that the conditional probability of failure of an SSC is 5 percent or less. The uncertainty parameter for seismic capacity was represented by a combined beta factor of 0.4. The HCLPF parameters used for the CPS SCDF estimate are those cited for the CPS in Table B-2 and C-2 of Results of Safety/Risk Assessment of Generic Issue 199, Implications of Updated Probabilistic Seismic Hazard Estimates in Central and Eastern United States on Existing Plants, dated September 2, 2010 (Reference 30). Approximate SCDF estimates were developed in Reference 30 using a method which includes integrating the mean seismic hazard curve and the mean plant-level fragility curve for each NPP. This method, developed by Kennedy (1997), is discussed in Section 10.8.9 of AMSE/ANS RA-Sa-2009 and has previously been used by the staff in the resolution of GI-194, Implications of Updated Probabilistic Seismic Hazard Estimates, and during reviews of various risk-informed license amendments. The 0.30g PGA value is consistent with the CPS individual plant examination of external events (IPEEEs) review level earthquake. The licensees estimation of the SCDF is performed by convolving the PGA based seismic hazard curve for the CPS site using the geometric mean of the 19 seismic hazard intervals (from 0.0005g to 10g) with the CPS PGA based HCLPF as shown in LAR Enclosure 4, Table E4-2. The NRC staff review finds that the method used to estimate the SCDF is acceptable because it is consistent with the approach used in Reference 30.
As described by the licensee in LAR Enclosure 4, Section 3, the proposed SLERF penalty of 1.6E-06 per year was determined by estimating the average seismic conditional large early release probability (CLERP) at 0.25 and multiplying it by the estimated SCDF of 6.4E-06 per year. The licensee explained that an estimate of the average seismic CLERP was determined using: (1) the average contribution of different accident types to SLERF using fragility information from completed seismic PRAs and generic guidance, and (2) the CLERP for the current CPS internal events PRA model of record for each accident type. The average percent contribution of different accident types to seismic LERF was then multiplied by the internal events PRA CLERP to produce a seismic CLERP for the designated accident types which were in turn used to calculate a sequence-weighted average seismic CLERP. The LAR indicates that the seismic PRA does not produce different accident scenarios from the internal events PRA but rather a different distribution of accident scenario types for seismic events. The LAR further explains that containment isolation failures were evaluated to ensure that random or seismically induced failures leading directly to LERF are insignificant risk contributors. The LAR presents a graphical approach for determining the average contribution of different accident types to SLERF based on fragility information from several cited sources. The graphic resembles an event tree in which the top events and end states are used to define the accident types of interest and the branch point probabilities are used to calculate the percent contribution of each accident type to the total SCDF. The branch point probabilities are determined by the seismic failure of components relevant to the branch points based on review of industry fragility information.
In its supplement dated November 24, 2020, the licensee provided an additional description of how the branch point probabilities in LAR Enclosure 4, Figure E4-1, were determined. The licensee explained that nodal probabilities for the seismic capacities assigned to each node (i.e.,
branch point) of the graphic are calculated using a typical double lognormal fragility probability model. The types of SSCs typical to a given node are discussed in the LAR (e.g., containment structure, RPV supports, DG or control building failures, off-site power, and containment isolation valves). The licensee explained that the seismic capacity was selected from the lower
 
end of the ranges for over 150 representative capacities compiled from a review of industry studies that include the EPRI 3002000709 report, Seismic Probabilistic Risk Assessment Implementation Guide, December 2013 (Reference 31), Lawrence Livermore National Laboratory report UCID-20571, "Compilation of Fragility Information from Available Probabilistic Risk Assessments," 3 and several plant-specific seismic PRAs performed in response to the NRC staffs 10 CFR 50.54(f) request for information dated March 12, 2012 (ADAMS Accession No. ML12053A340), with regard to Near Term Task Force Recommendation 2.1. The licensee explained that the SCDF fraction for each scenario type was determined by convolving the PGA based seismic hazard curve for the CPS site using the geometric mean of 10 seismic hazard intervals from 0.05g to 3g (which is a more coarse convolution than the convolution used to calculate the total seismic CDF but detailed enough for this use). Based on this convolution, the nominal fraction of seismic CDF for each scenario type was calculated to determine the seismic CLERP as discussed above.
In its supplement dated November 24, 2020, the licensee provided justification that the SLERF penalty for CPS is conservative. The licensee stated that its approach to estimate the SLERF is based on the combination of: (1) an estimated SCDF which is not necessarily conservative, (2) an average seismic CLERP which is estimated conservatively, and (3) use of a SLERF penalty in the RICT calculations which is conservative because the entire CDF and LERF is applied in every RICT calculation. The licensee discussed several conservatisms made in estimating the average seismic CLERP such as: (1) the seismic-induced loss of offsite power is assumed to occur at a probability of 1.0 for the entire seismic hazard curve, and (2) the low end of the capacity distributions compiled from generic sources was used to determine the node probabilities to estimate the nominal fraction of SCDF for each scenario type. The licensee also presented the results of a sensitivity study on the impact of the seismic penalty factor on the calculated RICTs by increasing the seismic penalty in the sensitivity case by a factor of two.
The results show that the seismic penalty factor has a very small impact on the RICT calculated for risk significant configurations (i.e., short RICTs).
The NRC staff finds the licensees development of its seismic CLERP acceptable because it used several conservative assumptions as discussed above and was derived using a combination of industry seismic PRA results and plant-specific information. Additionally, a seismic CLERP of 0.25 is within the range of seismic CLERP values observed by the staff for plants with current seismic PRAs. The NRC staff finds the licensees estimate of and use of its SLERF penalty acceptable for this application because: (1) reasonable or somewhat conservative assumptions are used in its estimation and application of this penalty in the RICT program and (2) the seismic penalty has a minor impact on the calculated RICTs.
The NRC staff finds that for RICTs associated with SSCs credited in the design basis to mitigate seismic events, the licensee's proposed methodology captures the risk associated with seismically induced failures of redundant SSCs because such SSCs are assumed to be fully correlated. By assuming full correlation, the seismic risk for those RICTs will not increase if one of the redundant SSCs is unavailable because simultaneous failure of all redundant trains would be assumed in a seismic PRA. During RICTs for SSCs not credited in the design-basis seismic event, but which could be used when credited SSCs fail, the proposed methodology for considering seismic risk contributions may be non-conservative because the seismically-induced failure of such SSCs during the RICT may not be included in the risk increase.
However, the occurrence and degree of non-conservatism depends on the plant high confidence in low probability of failure (HCLPF) value used for the RICT calculations, as 3 Available at https://www.osti.gov/servlets/purl/5455630.
 
compared to the HCLPF values for such SSCs. The degree of non-conservatism will be low or nonexistent if the plant HCLPF value is lower than most or all SSCs impacted by a seismic event. During RICTs for SSCs that are not used to mitigate a seismic event, the proposed methodology for considering seismic risk contributions is conservative because the seismically induced failure of such SSCs would not result in a risk increase associated with the plant configuration during the RICT, but the seismic penalty is still included in the calculation.
The licensee also calculated the total (i.e., across the entire hazard curve) seismically induced LOOP frequency of 1.7E-03 per year for CPS, which is about 6 percent of the total unrecovered LOOP frequency addressed in the IEPRA for the CPS. Additionally, the license calculated that the below design basis seismic-induced LOOP frequency is about 4 percent of the total unrecovered LOOP frequency already addressed in the internal events PRA for the CPS. The NRC staff evaluated the analysis and finds that the analysis adequately addresses the impact of seismically induced LOOP and finds it has an insignificant impact on the RICT program calculations.
In summary, the NRC staff finds the licensees proposal to use the SCDF contributions of 6.4E-06 per year, and a SLERF contribution of 1.6E-06 per year acceptable for the licensees RICT program for CPS because: (1) the licensee used the most current site-specific seismic hazard information, (2) the licensee used an acceptably low plant HCLPF value of 0.3g consistent with the information for the CPS in the GI-199 evaluation, (3) reasonable industry seismic PRA results and plant-specific information informed the calculation of the seismic CLERP, and (4) adding the seismic risk contribution to RICT calculations, which assumes the fully correlated failures, is conservative for SSCs credited in seismic events, while any potential non-conservative results for SSCs that are not credited in seismic events is small or nonexistent, as discussed above.
Extreme Winds and Tornado Hazards LAR Enclosure 4, Section 4, discusses the licensees evaluation of the risk from the extreme winds and tornadoes hazards. Evaluation of the extreme winds and tornado hazard has been updated since the licensees IPEEE. The basis for the insignificant impact of extreme winds and tornados (including tornado-generated missiles) for this application relies on the design of SSCs and tornado missile analysis. Table E4-7 of the same enclosure presents the licensees screening criteria used to disposition the risk for the extreme wind and tornado hazards. Table E4-7 indicates that criterion PS2 (Design-basis hazard cannot cause a core damage accident) and PS4 (Bounding mean CDF is < 1E- 6/y (year)) were used to screen the extreme wind and tornado hazard.
In the LAR, the licensee stated that wind damage is bounded by tornadoes and that the tornado wind speed that would be exceeded at a frequency of 1E-07 per year is less than the CPS design wind speed value according to NUREG/CR-4461, Revision 2, Tornado Climatology of the Contiguous United States, February 2007 (Reference 32), using the enhanced Fujita Scale.
The licensee stated that subsequent to its IPEEE screening evaluation of extreme winds it has performed a number of tornado missile protection (TMP) evaluations of CPS. The licensee stated that in 2007 an updated CPS TORMIS-based tornado missile risk analysis was performed. The 2007 TORMIS quantification results exceeded the 1E-06 per year CDF acceptance criterion. However, the evaluation identified the five largest contributors to tornado missile CDF, which, if removed, would reduce the tornado-missile CDF to 6.5E-07 per year.
The licensee stated that subsequent to the study, three of the associated targets were modified by installing missile shielding and two of the associated targets were re-assessed and it was
 
shown that the existing concrete enclosure and backfill provide adequate protection. Another tornado missile evaluation was performed in 2015-2016 in response to Regulatory Issue Summary 2015-06, Tornado Missile Protection, dated June 20, 2015 (Reference 33), and NRC Enforcement Guidance Memorandum 15-002, Enforcement Discretion for Tornado-Generated Missile Protection Noncompliance, dated June 10, 2015 (Reference 34). The licensee stated that the 2015-2016 tornado-missile evaluation did not alter the results of the conservatively performed 2007 tornado-missile evaluation study.
The licensee additionally stated that the high winds and tornado screening was performed considering SSCs out of service for maintenance and that there was no significant high winds risk impact from allowed maintenance configurations.
Based on the above, the NRC staff finds that the extreme winds and tornado hazard has an insignificant contribution to configuration risk and can be excluded from the calculation of the proposed RICTs.
External Flooding In the LAR Enclosure 4, Section 5, the licensee provided an evaluation of the risk from the external flooding hazard. The evaluation of external flooding hazards has been significantly updated since the licensees IPEEE. The licensees conclusion that the impact of external flooding on this application is insignificant is based on the results documented in the licensees flood hazard reevaluation report (FHRR) for CPS dated March 12, 2014 (Reference 35). Table E4-7 of the LAR Enclosure 4 presents the licensees screening criteria used to disposition the risk for the external flooding hazard. Table E4-7 also indicates that criterion C1 (event damage potential is less than events for which plant is designed) was used to screen the external flood hazard. The NRC staff evaluation issued November 18, 2015 (Reference 36),
concludes that the reevaluted flood hazard mechanisms at Clinton are bounded by the current design-basis.
In LAR Enclosure 4, Section 5, the licensee stated that the results of the FHRR show that flooding from all mechanisms except local intense precipitation (LIP) are bounded by the current LB and the plant response is considered adequate. In its CPS Mitigating Strategies Assessment dated March 24, 2016 (Reference 37), the licensee identified that the model used to develop the LIP flood-causing mechanism was found to incorrectly simulate rain-on-buildings.
The licensees revised calculation identifies the radwaste building as subject to 1.2 inches of standing water. The licensees {{letter dated|date=March 24, 2016|text=March 24, 2016, letter}} concluded that no safe shutdown SSCs are located in the radwaste building. Therefore, the water leakage into the radwaste building would not impact CPS safety functions. The licensee additionally stated that there are no configuration specific considerations related to the hazard screening discussed above.
Based on the above, the NRC staff finds that the external flooding hazard has an insignificant contribution to configuration risk and can be excluded from the calculation of the proposed RICTs.
Other External Hazards The licensee provided its assessment of the external hazard risk for the RICT program in LAR , Information Supporting Justification of Excluding Sources of Risk Not Addressed by the PRA Models. In Enclosure 4, the licensee stated that this assessment is based on an update of the CPS IPEEE external hazard screening evaluation. The licensee listed the
 
hazards assessed in LAR Enclosure 4, Table E4-7. The NRC staff notes that this list is essentially the same list of hazards as presented in Table 4-1 of NUREG-1855, Revision 1. The NRC staff finds that the list of external hazards considered by the licensee is consistent with the hazards listed in Appendix 6-A of the ASME/ANS RA-Sa-2009 PRA Standard, which is endorsed in RG 1.200, Revision 2. NRC staff also notes that the Initial Preliminary Screening criteria and Progressive Screening criteria used and presented in LAR Table E4-8 are the same criteria presented in Supporting Requirements EXT-B1 and EXT-C1 of the ASME/ANS PRA Standard for screening external hazards, as endorsed by RG 1.200, Revision 2.
In LAR Table E4-7 and the supplement to the LAR dated November 24, 2020, the licensee provided a screening disposition for each non-seismic external hazard as well as other hazards and concluded that no unique PRA model for these hazards is required in order to assess configuration risk for the RICT program.
The licensee explained for the snow hazard that the CPS USAR addresses design snow and ice loads using the latest hazard information. The licensee also identified that snow or ice loading is screened using criteria in LAR Enclosure 4, Table E4-8; criterion C1 (event damage potential is less than events for which the plant is designed), and because it is a slow developing event, criterion C5 (event develops slowly, allowing adequate time to eliminate or mitigate the threat). The licensee explained that RMAs such as those described in the stations adverse weather procedures will ensure that the assumptions that resulted in screening the hazard will continue to be valid during the proposed RICTs. The licensee explained for the sand or dust storm hazard that CPS is not located in an area that is impacted by sand or dust storms.
The licensee also identified that in addition to criterion C1 that criterion C3 also applies to this hazard (event cannot occur close enough to the plant to affect it). The licensee explained for the ice cover hazard that the CPS USAR stipulates that the submerged location of the ultimate heat sink (UHS) pond suction prevents ice formation or ice jams from affecting the performance of the UHS. The licensee also explained that scheduled periodic reviews, as discussed in NEI 00-04, will be conducted to evaluate new insights from available information. If it is determined that there are changes that can impact categorization, the risk information and the categorization process will be updated. NRC staff finds that the bases for screening the snow, sand or dust storm, and ice cover hazards are acceptable because they consider the as-built, as-operated plant, use current hazard information, and will be updated if changes that can impact categorization are identified from periodic reviews.
The NRC staffs review of the information in the submittal as supplemented finds that the contributions from the other external hazards have an insignificant contribution to configuration risk and can be excluded from the calculation of the proposed RICTs because they either do not challenge the plant or they are bounded by the external hazards analyzed for the plant.
External Hazards Conclusion The NRC staff concludes that the licensee's approach for considering the impact of seismic events, non-seismic external hazards and other hazards for the CPS in the RICT calculations is acceptable because the licensee included a technically acceptable quantitative assessment of the seismic risk for the CPS and configuration specific tornado missile risk for the CPS consistent with the guidance in the NEI 06-09 and demonstrated the insignificant contribution to configuration risk from other external hazards on the proposed RICTs.
 
3.2.4.1.4 PRA Results and Insights The proposed change implements a process to determine TS RICTs rather than specific changes to individual TS CTs. NEI 06-09-A indicates that periodic assessment should be performed of the risk incurred due to operation beyond the front stop CTs resulting from implementation of the RICT program and comparison to the guidance of RG 1.174, Revision 3, for small increases in risk.
NEI 06-09-A further stipulates that configuration risk should be assessed to determine the RICT and establishes the criteria for incremental core damage probability (ICDP) and incremental large early release frequency (ILERP) on which to base the RICT. An ICDP of 1E-5 and an ILERP of 1E-6 are used as the risk measures for calculating individual RICTs. These limits are consistent with NUMARC 93-01, Revision 4F Industry Guideline for Monitoring the Effectiveness of Maintenance at Nuclear Power Plants, dated April 27, 2018 (Reference 38).
NEI 06-09-A as modified by the limitations and conditions in the associated SE requires that the cumulative impact of implementation of an RMTS be periodically assessed and shown to result in: (1) a total risk impact below 1E-5/reactor-year for changes to CDF, (2) a total risk impact below 1E-6/year for changes to LERF, and (3) the total CDF and total LERF must be reasonably shown to be less than 1E-4/reactor-year and 1E-5/reactor-year, respectively. The licensee indicated in Enclosure 5 of the submittal that the estimated total CDF and LERF meet the 1E-4/reactor-year CDF and 1E-5/reactor-year LERF criteria of RG 1.174 consistent with the guidance in NEI 06-09-A and that these guidelines will be satisfied for implementation of a RICT.
On October 27, 2020, the NRC staff requested a summary of how the SOKC investigation was performed in the baseline PRAs supporting the TSTF-505 application and how it will be addressed in risk metrics used in the RICT application. In its response dated November 24, 2020, the licensee showed that the combined impact on internal and fire events is a 1.5 percent increase in CDF and 0.6 percent increase in LERF and that there is adequate margin between the total mean CDF and LERF values (i.e., 8.86E-05 and 7.11E-06, respectively) and RG 1.174 guidelines to accommodate further increase before the total threshold vales are reached.
These updated values demonstrate that the estimated total CDF and LERF meet the 1E-4/reactor-year CDF and 1E-5/reactor-year LERF criteria of RG 1.174, consistent with the guidance in NEI 06-09-A.
The licensee has incorporated NEI 06-09-A in the RICT program of TS 5.5.17 and, therefore, it can calculate the RICT appropriately to assess and ensure that any risk increases are small and in accordance with RG 1.174, Revision 3, and the intent of RG 1.177, Revision 1. Also, the estimate of the current total CDF and LERF meets the intent of the RG 1.174, Revision 3, acceptance guidelines. Therefore, the NRC staff finds that the licensees RICT program is consistent with NEI 06-09-A guidance and is acceptable.
3.2.4.1.5 Key Assumptions and Uncertainty Analyses Using PRAs to evaluate TS changes requires consideration of the assumptions made within the PRA that can have a significant influence on the ultimate acceptability of the proposed changes.
The licensee considered PRA modeling uncertainties and their potential impact on the RICT program and identified, as necessary, applicable RMAs to limit the impact of these uncertainties. In Enclosure 9 of the LAR, the licensee discussed key assumptions and key sources of uncertainty along with providing the dispositions for impact on the risk-informed
 
application or applicable sensitivities. The licensees evaluation the CPS PRA model to identify the key assumptions and key sources of uncertainty for this application consistent with RG 1.200 definitions, using sensitivity and importance analyses to place bounds on uncertain processes, to identify alternate modeling strategies, and to provide information to users of the PRA.
In regard to the fire PRA, the licensee stated in LAR Enclosure 9, Section 4, that it used guidance from NUREG-1855, Revision 1, and guidance for fire PRA development including NUREG/CR-6850, EPRI/NRC-RES Fire PRA Methodology for Nuclear Power Facilities, to address the fire PRA uncertainty analysis. The licensee explained that plant-specific assumptions and sources of modeling uncertainty identified from the fire PRA were considered, as well generic industry sources of uncertainty from EPRI TR 1026511. The licensee explained that the fire PRA uncertainties were organized by the fire PRA topics presented in NUREG/CR-6850.
The licensee explained that it has used consensus modeling approaches from NUREG/CR-6850 and guidance from NUREG-7150 4 and fire PRA FAQs. In LAR Enclosure 9, Table E9-3, the licensee dispositioned the fire PRA modeling uncertainties stating in each case that they do not present a significant impact on the RICT calculations and no RMAs (or additional RMAs) were required to address the uncertainty.
The NRC staff reviewed the licensees dispositions for the RICT application provided in LAR , Tables E9-1, E9-2, and E9-3, to understand key assumptions and sources of modeling uncertainty and noted sources of uncertainty that did not appear to fully dispositioned and appeared to have the potential to impact the RICT calculations. In the LAR, the licensee stated that certain components were conservatively assumed to be failed because of the lack of cable data in certain locations, and because of this it performed two sensitivity studies to determine the impact. These components were referred to as unknown location (UNL) components. The licensee stated that based on the sensitivity results, it concluded that its approach does not introduce any epistemic uncertainties that would impact the RICT calculations. However, the licensee did not provide the results of the uncertainty analysis in the LAR. On October 27, 2020,, the NRC staff requested identification of the systems or components that were assumed to fail because of the lack of cable routing and requested the licensee to provide justification that this treatment has an inconsequential impact on the RICT program.
In its response dated November 24, 2020, the licensee identified the UNL components and stated that [m]ost of the UNL components are associated with systems that are not within the scope of the TSTF-505 RICT program and do not serve support function for the TSTF-505 RICT LCOs. The licensee also explained that it performed a sensitivity study of the impact of this treatment on calculated RICTs for a sampling of TS LCOs selected for this study because their estimated RICTs are less than 30 days. In the sensitivity case, the RICT calculation was based on fire PRA modeling in which all UNL failures were removed. The NRC staff notes that this removal of the UNL component failures has the effect of eliminating the possible impact of the conservatism associated with modeling the UNL components. Therefore, the NRC staff concludes that the UNL components will not pose a significant impact to the RICT program.
On October 27, 2020, the NRC staff requested that the licensee justify that the uncertainty associated with post-fire HRA modelling has an inconsequential impact on calculated RICTs for 4 Available at https://www.nrc.gov/reading-rm/doc-collections/nuregs/contract/cr7150/
 
components supporting TS LCO conditions in the RICT program. In its {{letter dated|date=November 24, 2020|text=November 24, 2020, letter}}, the licensee responded that it evaluated FPRA HRA uncertainty as a part of its parametric uncertainty evaluation. Furthermore, the licensee presented the results of a sensitivity study for a set of TS LCOs to determine the impact of using point-values rather than parametric mean values on the calculated RICT values based on CDF. Based on the above, the NRC staff finds the licensees treatment of post-fire HRA modeling is consistent with guidance in NUREG-1855, Revision 1 and is therefore acceptable.
Based on the above, the NRC staff concludes the licensee performed an adequate assessment to identify the potential key sources of uncertainty, and key assumptions consistent with the guidance in NUREG-1855 and associated EPRI TR-1016737 and EPRI TR-1026511.
Therefore, the NRC staff finds that the licensee has satisfied the guidance in RG 1.177, Revision 1 (Sections 2.3.4 and 2.3.5), and RG 1.174, Revision 3 (Section 2.2.2), and that the identification of assumptions and treatment of model uncertainties for risk evaluation of extended CTs is appropriate for this application and consistent with the guidance identified in NEI 06-09-A.
PRA Scope and Acceptability Conclusions Based upon its review, the NRC staff finds that the licensee (1) has reviewed the PRA using endorsed guidance and adequately resolved all identified issues, (2) has established a periodic update and review process to update the PRA and associated CRMP model to incorporate changes made to the plant and PRA methods and data consistent with the RICT program, and (3) will calculate RICTs using NRC-accepted PRA methods. Therefore, the NRC staff concludes that the licensee has and will maintain a PRA that is technically adequate to support implementation of the RICT program.
Based on the above, the NRC staff finds that the licensee has satisfied the intent of RG 1.177, Revision 1, and RG 1.174, Revision 3, and that the scope of the PRA model and the use of a bounding analysis for seismic events is appropriate for this application.
3.2.4.1.6 Application of PRA Models in the RICT Program Table E1-1 in Enclosure 1 to the LAR, as supplemented by the licensee in its letters dated November 24, 2020, and March 23, 2021: (1) identifies each TS LCO condition in scope of the RICT program and, the SSCs covered by the LCO, as applicable, (2) indicates whether the SSC is modeled in the PRA, and (3) for the cases in which the SSCs are not explicitly modeled, explains how the PRA uses surrogate events that bound the function(s) of the TS LCO SCC(s).
The NRC staff noted for some LCOs identified in Table E1-1 of Enclosure 1 to the LAR, the licensee explained that the associated SSCs are not modeled in the PRAs but will be considered using a surrogate event. For certain LCOs, it was not clear to NRC staff whether the surrogate PRA modeling will be adequate to support the RICT calculations. The LAR, in Table E1-1 indicates that the relief function is not modeled and, therefore, surrogate modeling will be used. On October 27, 2020, the NRC staff requested clarification of the surrogate modeling that will be used to model TS LCO 3.3.6.5, Relief and Low-Low Set (LLS) Instrumentation, Condition A (one trip system inoperable). Specifically, NRC staff requested: (1) confirmation of which SSCs for this LCO are not explicitly modeled in the PRAs, (2) explanation of the surrogate modeling that will be used for the SSCs, and (3) justification that the surrogate modelling appropriately represents the failure of the design function associated with TS LCO Condition A. In its response dated November 24, 2020, the licensee clarified that the relief (or
 
overpressure) function of the SRVs is modeled in the PRAs, but that the pressure instrumentation providing the signal for the SRVs to open on high reactor pressure is not modeled. Therefore, both the relief and low-low set instrumentation (which open SRVs at lower pressure) is not included in the PRA models. The licensee explained that the two LLS SRVs (one on Division 1 and the other on Division 2) will be used as a conservative surrogate for the relief and LLS instrumentation. The NRC finds that the licensees surrogate modeling of the relief and LLS instrumentation serves as an appropriate substitute and appropriately represents the failure of the design function associated with TS LCO 3.3.6.5 Condition A.
Risk Assessment Approaches and Methods Changes to the PRA are expected to occur over time to reflect changes in PRA methods and changes to the as-built, as-operated, and maintained plant to reflect the operating experience at the plant as specified in RG 1.200, Revision 2. Changes in PRA methods are addressed by constraint e. of TS Administrative Section 5.5.17:
The risk assessment approaches and methods shall be acceptable to the NRC.
The plant PRA shall be based on the as-built, as-operated, and maintained plant; and reflect the operating experience at the plant, as specified in Regulatory Guide 1.200, Revision 2. Methods to assess the risk from extending the Completion Times must be PRA methods used to support this license amendment, or other methods approved by the NRC for generic use; and any change in the PRA methods to assess risk that are outside these approval boundaries require prior NRC approval.
The NRC staff finds that this constraint is acceptable because it adequately implements the RICT program using models, methods, and approaches consistent with applicable guidance that are acceptable to the NRC.
Credit for FLEX The NRC staffs memorandum dated May 30, 2017, Assessment of the Nuclear Energy Institute 16-06, Crediting Mitigating Strategies in Risk-Informed Decision Making, Guidance for Risk-Informed Changes to Plants Licensing Basis (Reference 39), provides the NRC staffs assessment of challenges to incorporating FLEX equipment and strategies into a PRA model in support of risk-informed decisionmaking in accordance with the guidance of RG 1.200, Revision 2. The review of the FLEX strategies and modeling for the PRA was performed as a combined effort with the CPS LAR for adoption of 10 CFR 50.69, which the NRC staff approved previously. The basis for acceptability is documented in the SE for 10 CFR 50.69 and the conclusions apply to this SE as well.
3.2.4.2    Tier 2: Avoidance of Risk-Significant Plant Configurations As prescribed in RG 1.177, Revision 1, the second tier provides that a licensee should provide reasonable assurance that risk-significant plant equipment outage configurations will not occur when specific plant equipment is taken out-of-service in accordance with the proposed TS change.
NEI 06-09-A does not permit voluntary entry into high-risk configurations, which would exceed instantaneous CDF and LERF limits of 1E-3/year and 1E-4/year, respectively. The guidance in NEI 06-09-A specifies that if the instantaneous CDF and LERF limits are exceeded for emergent
 
conditions, then implementation of RMAs is required. It further requires implementation of RMAs when the actual or anticipated risk accumulation during a RICT will exceed one-tenth of the ICDP or ILERP limit (the RMAT). Such RMAs may include rescheduling planned activities to lower risk periods or implementing risk-reduction measures. The limits established for entry into a RICT and for RMA implementation are consistent with the guidance of NUMARC 93-01, Revision 4F, endorsed by RG 1.160, Revision 4 5, as applicable to plant maintenance activities.
The RICT program requirements and criteria are consistent with the principle of Tier 2 to avoid risk-significant configurations.
Consistent with NEI 06-09-A, Enclosure 12 of the LAR identifies three kinds of RMAs:
* actions to provide increased risk awareness and control,
* actions to reduce the duration of maintenance activities, and
* actions to minimize the magnitude of the risk increase).
The LAR also explains that RMAs will be implemented, in accordance with current plant procedures, no later than the time at which the ICDP or ILERP is reached and under emergent conditions when the instantaneous CDF and LERF thresholds are exceeded.
Based on the licensees incorporation of NEI 06-09-A in the TS as discussed in LAR  and use of RMAs as discussed in LAR Enclosure 12, Risk Management Actions and the licensee supplements, and because the proposed changes are consistent with the guidance of RG 1.174, Revision 3, and RG 1.177, Revision 1, the NRC staff finds that the licensees Tier 2 program is acceptable and supports the proposed implementation of the RICT program.
3.2.4.3    Tier 3: Risk-Informed Configuration Risk Management The third tier provides that a licensee should develop a program that ensures that the risk impact of out-of-service equipment is appropriately evaluated prior to performing any maintenance activity.
NEI 06-09-A specifies that the RMTS risk assessment process should be integrated into station-wide work control processes and defines the necessary attributes of the RMTS program structure. In the conduct of RMTS, procedural guidance is required for conducting and using the results of the risk assessment. In Enclosure 8 of the LAR, Attributes of the Real-Time Risk Model, the licensee confirms that future changes made to the baseline PRA model, changes made to the baseline PRA model for translation to the online model, and changes made to the online model configuration files are controlled and documented by plant procedures.
Based on the licensees incorporation of NEI 06-09-A, in the TS, as discussed in LAR  and the use of RMAs as discussed in LAR Enclosure 12, Risk Management Actions, as supplemented, and because the proposed changes are consistent with the Tier 3 guidance of RG 1.177, Revision 1, the NRC staff finds that the proposed changes are acceptable.
5 Available at https://www.nrc.gov/docs/ML1822/ML18220B281.pdf
 
3.2.4.4    Key Principle 4: Conclusions Based upon its review, the NRC staff concludes that the licensee has demonstrated the technical acceptability and scope of its PRA models that can support implementation of the RICT program for determining CTs. The licensee has properly considered key assumptions and sources of uncertainty. The licensees risk metrics are consistent with the approved methodology of NEI 06-09-A and the acceptance guidance in RG 1.177 and RG 1.174. The RICT program is controlled administratively through plant procedures and training. The RICT program follows the NRC-approved methodology in NEI 06-09-A. The NRC staff concludes that the RICT program satisfies the fourth key safety principle of RG 1.177 and is, therefore, acceptable.
3.2.5    Key Principle 5: Performance Measurement Strategies - Implementation and Monitoring Program RG 1.177, Revision 1, and RG 1.174, Revision 3, establish the need for an implementation and monitoring program to ensure that extensions to TS CTs do not degrade operational safety over time and that no adverse degradation occurs due to unanticipated degradation or common cause mechanisms. An implementation and monitoring program is intended to ensure that the impact of the proposed TS change continues to reflect the reliability and availability of SSCs impacted by the change. Revision 3 of RG 1.174 states that monitoring performed in conformance with the Maintenance Rule, 10 CFR 50.65, can be used when the monitoring performed is sufficient for the SSCs affected by the risk-informed application. According to LAR 1, the SSCs in the scope of the RICT program are also in the scope of the Maintenance Rule. In its {{letter dated|date=November 24, 2020|text=letter dated November 24, 2020}}, the licensee described the approach and methods used for SSC performance monitoring as described in Regulatory Position C.3.2 referenced in RG 1.177 for meeting the fifth key safety principle. Furthermore, in Enclosure 11 of the LAR, the licensee confirmed that the cumulative risk is calculated at least every refueling cycle, but the recalculation period does not exceed 24 months, which is consistent with NEI 06-09-A. This evaluation assures that RMTS program implementation meets RG 1.174 guidance for small risk increases.
The NRC staff concludes that the RICT program satisfies the fifth key safety principle of RG 1.177, Revision 1, and RG 1.174 b, by, in part, monitoring the average annual cumulative risk increase as described in NEI 06-09 and using this average annual increase to ensure the program as implemented meets RG 1.174 guidance for small risk increases therefore, is acceptable. Additionally, the NRC staff concludes that the RICT program satisfies the fifth key safety principle of RG 1.177, Revision 1, and RG 1.174, because, in part, all the affected SSCs are within the Maintenance Rule program which can be used to monitor changes to the reliability and availability of these SSCs.
3.3      Variations from TSTF-505 The NRC staff evaluated the proposed use of RICTs in the variations stated above in Section 2.2.4 of this SE in conjunction with evaluating the proposed use of RICTs in each of the individual LCO, Required Actions, and CTs stated above in Section 2.2.3. The NRC staffs evaluation of the licensees proposed use of RICTs in the variations against the key safety principles is discussed above in Sections 3.2.1 through 3.2.5. Based on the above Sections 3.2.1 through 3.2.5, the NRC staff finds that each of the five key principles in RG 1.177, Revision 1, and RG 1.174, Revision 3, have been met. Evaluation of the acceptability of the specific proposed use of RICTs is included below.
 
3.3.1    Application of the RICT Program to Modified Conditions, Required Actions, and CTs Section 2.2.4.1 of this SE discusses changes proposed in the LAR that modify CTs to permit the application of a RICT.
* LCO 3.6.1.2, states, Each primary containment air lock shall be OPERABLE.
Condition 3.6.1.C, One or more containment air locks inoperable for reasons other than Condition A or B.
* LCO 3.6.5.2, states, The drywell air lock shall be OPERABLE. Condition 3.6.5.2.C, Drywell air lock inoperable for reasons other than Condition A or B.
* Modified CTs in LCOs 3.3.5.1, 3.3.5.3, 3.3.6.1, 3.3.6.3, and 3.3.8.1 are evaluated in Section 3.1.2.3, Evaluation of Instrumentation and Control Systems.
For Condition 3.6.1.2.C, the potential for containment leakage beyond allowable limits must be assessed to ensure no loss of containment function is associated with the air lock inoperability.
The licensees proposed change to the associated Action C.3 permits consideration of the RICT for restoration of the affected airlock to operable status only when (C.1) action to evaluate overall containment leakage rate per LCO 3.6.1.1 has been immediately initiated using current airlock test results and (C.2) one air lock door is closed. These conditions provide reasonable assurance that any loss of function condition would be detected and preclude usage of the RICT. The licensee proposed the following TS Conditions to add the RICT program modified by a note that states, Not applicable if leakage exceeds limits or if loss of function. This approach retains the existing requirements and limits the use of a RICT to conditions in which the function can still be performed. The licensee must justify that the required function can still be performed absent an additional failure when a RICT is applied. Therefore, the proposed change to Action 3.6.1.2.C.3 is acceptable.
For Condition 3.6.5.2.C, the potential for containment leakage beyond allowable limits must be assessed to ensure no loss of containment function is associated with the drywell air lock inoperability. The licensees proposed change to the associated Action C.2 permits consideration of the RICT for restoration of the affected air lock to operable status only when (C.1) a door has been verified closed. These conditions provide reasonable assurance that any loss of function condition would be detected and preclude usage of the RICT. The licensee proposed the following TS Conditions to add the RICT program modified by a note that states, Not applicable if leakage exceeds limits or if loss of function. This approach retains the existing requirements and limits the use of a RICT to conditions in which the function can still be performed. The licensee must justify that the required function can still be performed absent an additional failure when a RICT is applied. Therefore, the proposed change to Action 3.6.5.2.C.2 is acceptable.
3.3.2    Application of the RICT to Additional ACTIONS Requirements Section 2.2.4.2 of this SE discusses changes proposed in the LAR that are not Actions listed in TSTF-505. Additional Actions proposed in LCO 3.3.6.4 are evaluated in Section 3.1.2.3.
Additional Actions proposed in LCO 3.8.9 are evaluated in Section 3.1.2.2, Evaluation of Electrical Power Systems.
Condition 3.6.1.6.A applies when one LLS valve is inoperable. Table E1-1 states the design success criterion of Condition 3.6.1.6.A is four of five LLS valves are operable to fulfill the safety
 
function. In Attachment 4 of the LAR, the licensee identified and provided additional justification for which the LAR proposed applying the RICT program, that varies from TSTF-505, Revision 2:
Industry guidance developed by the TSTF indicates that this action was excluded because the traveler will not modify Required Actions for systems that do not affect CDF or LERF or for which a RICT cannot be quantitatively determined.
However, CPS proposes to apply a RICT to this action because the function is modeled in the PRA and can be directly included in the RTR tool for the RICT program. As stated in the CPS TS Bases for Required Action A.1, with one LLS valve inoperable, the remaining operable LLS valves are adequate to perform the designed function.
Considering Action 3.6.1.6.A.1 and the associated design success criterion, the NRC staff finds that there is reasonable assurance that the existing requirement allows the use of a RICT for the condition in which the function can still be performed. Based on the above, the NRC staff determines that the proposed change to Action 3.6.1.6.A.1 is acceptable.
3.4    TS Administrative Controls Section The NRC staff reviewed the licensees proposed addition of a new program, the RICT program, to the Administrative Controls section of the TS. The NRC staff evaluated the elements of the new program to ensure alignment with the requirements in 10 CFR 50.36(c)(5) and to ensure the programmatic controls are consistent with the RICT program described in NEI 06-09-A.
TS 5.5.17 requires that the RICT program be implemented in accordance with NEI 06-09-A.
This is acceptable because NEI 06-09-A establishes an appropriate framework for an acceptable RICT program.
The TS states that a RICT may not exceed 30 days. The NRC staff determined that 30-day limit is appropriate because it allows sufficient time to restore SSCs to operable status while avoiding excessive out-of-service times for TS SSCs.
The TS states that the RICT may only be used in Modes 1 and 2. This provision ensures that the RICT is only used for determination of CDF and LERF for modes of operation modeled in the PRA.
The TS requires that while in a RICT, any change in plant configuration as defined in NEI 06 A must be considered for the effect on the RICT. The TS also specifies time limits for determining the effect on the RICT. These time limitations are consistent with those specified in NEI 06-09-A.
The TS contains requirements for the treatment of CCFs for emergent conditions in which the common cause evaluation is not complete. The requirements are to either: (1) numerically account for the increased probability of CCF or (2) to implement RMAs that support redundant or diverse SSCs that perform the functions of the inoperable SSCs and, if practicable, reduce the frequency of initiating events that challenge the function(s) performed by the inoperable SSCs. Key Principle 2 of risk-informed decisionmaking is intended to assure that the change is consistent with DID philosophy. The seven considerations supporting the evaluation of the impact of the change on DID are discussed in RG 1.174, including one to preserve adequate defense against potential CCF. The NRC staff finds that numerically accounting for an
 
increased probability of failure will shorten the estimated RICT based on the particular SSCs involved, thereby limiting the time when a CCF could affect risk. Alternatively, implementing actions that can increase the availability of other mitigating SSCs or decrease the frequency of demand on the affected SSCs will decrease the likelihood that a CCF could affect risk. The NRC staff concludes that both the quantitative and the qualitative actions minimize the impact of CCF and, therefore, support meeting Key Principle 2 as described in RG 1.174. These methods either limit the exposure time, help ensure the availability of alternate SSCs, or decrease the probability of plant conditions requiring the safety function to be performed. The NRC staff finds that these methods contribute to maintaining DID because the methods limit the exposure time or ensure the availability of alternate SSCs.
The TS contains a provision that risk assessment approaches and methods used shall be acceptable to the NRC. The plant PRA shall be based on the as-built, as-operated, and maintained plant; and reflect the operating experience at the plant, as specified in RG 1.200, Revision 2. Methods to assess the risk from extending the CTs must be PRA methods used to support this LAR, or other methods approved by the NRC for generic use. As stated in the NRC staffs SE for NEI 06-09-A:
NEI 06-09, Revision 0, requires an evaluation of the PRA model used to support the RMTS against the requirements of RG 1.200, Revision 1, and ASME RA-S-2002, Standard for Probabilistic Risk Assessment for Nuclear Power Plant Applications, for CC II. This assures that the PRA model is technically adequate for use in the assessment of configuration risk. This capability category of PRA is sufficient to support the evaluation of risk associated with OOS SSCs and establishing risk-informed CTs.
TS 5.5.17 was updated to reflect the current revision of RG 1.200 which incorporates ASME RA-S-2002 by reference.
The NRC staffs SE for NEI 06-09-A also states:
As part of its review and approval of a licensees application requesting to implement the RMTS, the NRC staff intends to impose a license condition that will explicitly address the scope of the PRA and non-PRA methods approved by the NRC staff for use in the plant-specific RMTS program. If a licensee wishes to change its methods, and the change is outside the bounds of the license condition, the licensee will need NRC approval, via a license amendment, of the implementation of the new method in its RMTS program. The focus of the NRC staffs review and approval will be on the technical adequacy of the methodology and analyses relied upon for the RMTS application.
The limitation and condition are being relocated from a license condition to the Administrative Controls section of the TS. Proposed TS 5.5.17 restates this limitation and condition from the NRC staffs SE in language that is appropriate for the Administrative Controls section of the CPS TS. This constraint appropriately requires the licensee to utilize the risk assessment approaches and methods previously approved by the NRC and/or incorporated in the RICT program, and requires prior NRC approval for any change in PRA methods to assess risk that are outside those approval boundaries. The NRC staff finds that this requirement is appropriately reflected in the Administrative Controls section of the CPS TS.
The regulations in 10 CFR 50.36(c)(5) require the TS to contain administrative controls providing provisions relating to organization and management, procedures, recordkeeping,
 
review and audit, and reporting necessary to assure operation of the facility in a safe manner.
The NRC staff has determined that Administrative Controls section of the TS will assure operation of the facility in a safe manner when the facility uses the RICT program. Therefore, the NRC staff has determined that the requirements of 10 CFR 50.36(c)(5) are satisfied.
4.0      ADDITIONAL CHANGES TO THE OPERATING LICENSE The licensee did not propose an additional change to the operating license or commit to implementation items in its TSTF-505 LAR.
5.0     
 
==SUMMARY==
 
The NRC staff finds that the licensees proposed implementation of the RICT program for the identified scope of Required Actions is consistent with the guidance of NEI 06-09-A. The licensees methodology for assessing the risk impact of extended CTs, including the individual CT extension impacts in terms of ICDP and ILERP, and the overall program impact in terms of CDF and LERF, is accomplished using PRA models of sufficient scope and technical adequacy based on consistency with the guidance of RG 1.200, Revision 2. For external hazards, which do not have PRA models, the licensee will use bounding analyses in accordance with NEI 06-09-A guidance and TS Administrative Control. The RICT calculation uses the PRA model as translated into the real-time risk model, and the licensee has an acceptable process in place to ensure the quality of the translation. In addition, the NRC staff finds that the proposed implementation of the RICT Program addresses the RG 1.177 defense-in-depth philosophy and safety margins to ensure that they are adequately maintained and includes adequate administrative controls as well as performance monitoring programs.
Paragraph 50.36(a)(1) of 10 CFR states, in part: [a] summary statement of the bases or reasons for such specifications other than those covering administrative controls shall also be included in the application but shall not become part of the technical specifications.
Accordingly, along with the proposed TS changes, the licensee also submitted TS Bases changes that correspond to the proposed TS changes, to provide the reasons for those TSs.
 
==6.0      STATE CONSULTATION==
 
In accordance with the Commissions regulations, the Illinois State official was notified of the proposed issuance of the amendments on May 12, 2021. The State official had no comments.
 
==7.0      ENVIRONMENTAL CONSIDERATION==
 
The amendments change requirements with respect to installation or use of a facilitys components located within the restricted area as defined in 10 CFR Part 20. The NRC staff has determined that the amendments involve no significant increase in the amounts, and no significant change in the types, of any effluents that may be released offsite, and that there is no significant increase in individual or cumulative occupational radiation exposure. The Commission has previously issued a proposed finding that the amendments involve no significant hazards consideration (85 FR 36435, June 16, 2020), and there has been no public comment on such finding. Accordingly, the amendments meet the eligibility criteria for categorical exclusion set forth in 10 CFR 51.22(c)(9). Pursuant to 10 CFR 51.22(b) no environmental impact statement or environmental assessment need be prepared in connection with the issuance of the amendments.
 
==8.0    CONCLUSION==
 
The Commission has concluded, based on the considerations discussed above, that: (1) there is reasonable assurance that the health and safety of the public will not be endangered by operation in the proposed manner, (2) there is reasonable assurance that such activities will be conducted in compliance with the Commissions regulations, and (3) the issuance of the amendment(s) will not be inimical to the common defense and security or to the health and safety of the public.
 
==9.0    REFERENCES==
 
1 Simpson, P.R., Exelon Generation Company, LLC letter to U.S. Nuclear Regulatory Commission, "Application to Revise Clinton Power Station Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b," dated April 30, 2020 (ADAMS Accession No. ML20121A178).
2 Simpson, P.R., Exelon Generation Company, LLC, letter to U.S. Nuclear Regulatory Commission, "Response to Request for Additional Information Regarding License Amendment Requests to Adopt TSTF-505, Revision 2, and 10 CFR 50.69," dated November 24, 2020 (ADAMS Accession No. ML20329A433).
3 Simpson, P.R., Exelon Generation Company, LLC, letter to U.S. Nuclear Regualtory Commission, "Response to Request for Additional Information Regarding License Amendment Request to Adopt TSTF-505, Revision 2," dated March 23, 2021 (ADAMS Accession No. ML21082A268).
4 Technical Specifications Task Force letter to U.S. Nuclear Regulatory Commission, "TSTF-505, Revision 2, TSTF Comments on Draft Safety Evaluation for Traveler TSTF-505, Provide Risk-Informed Extended Completion Times and Submittal of TSTF-505, Revision 2," dated July 2, 2018 (ADAMS Package Accession No. ML18183A493).
5 Golder, J.M., U.S. Nuclear Regulatory Commission, letter to Biff Bradley, Nuclear Energy Institute, "Final Safety Evaluation For Nuclear Energy Institute (NEI) Topical Report (TR)
NEI 06-09, Risk-Informed Technical Specifications Initiative 4b, Risk-Managed Technical Specifications (RMTS) Guidelines," dated May 17, 2007 (ADAMS Accession No. ML071200238).
6 Nuclear Energy Institute, "Risk-Informed Technical Specifications Initiative 4b: Risk-Managed Technical Specifications (RMTS)," NEI 06-09, Revision 0-A, October 2012 (ADAMS Accession No. ML122860402).
7 U.S. Nuclear Regulatory Commission, "An Approach for Determining the Technical Adequacy of Probabilistic Risk Assessment for Risk-Informed Activities," Regulatory Guide 1.200, Revision 2, March 2009 (ADAMS Accession No. ML090410014).
8 U.S. Nuclear Regulatory Commission, "An Approach for Using Probabilistic Risk Assessment in Risk-Informed Decisions on Plant-Specific Changes to the Licensing Basis,"
Regulatory Guide 1.174, Revision 3, January 2018 (ADAMS Accession No. ML17317A256).
9 U.S. Nuclear Regulatory Commission, "An Approach for Plant-Specific, Risk-Informed Decisionmaking: Technical Specifications," Regulatory Guide 1.177, Revision 1, May 2011 (ADAMS Accession No. ML100910008).
10 U.S. Nuclear Regulatory Commission, "Guidance on the Treatment of Uncertainties Associated with PRAs in Risk-Informed Decisionmaking," NUREG-1855, Revision 1, March 2017 (ADAMS Accession No. ML17062A466).
 
11 U.S. Nuclear Regulatory Commission, "Review of Risk Information Used to Support Permanent Plant-Specific Changes to the Licensing Basis: General Guidance," NUREG-0800, Chapter 19, Section 19.2, June 2007 (ADAMS Accession No. ML071700658).
12 Gullott, D.M., Exelon Generation Company, LLC, letter to U.S. Nuclear Regulatory Commission, "Clinton Power Station, Updated Safety Analysis Report, Revision 21," dated March 31, 2020 (ADAMS Accession No. ML20217L480).
13 U.S. Nulear Regulatory Commission, "An Approach for Determining the Technical Adequacy of Probabilistic Risk Assessment Results for Risk-Informed Activities," Regulatory Guide 1.200, Revision 1, January 2017 (ADAMS Accession No. ML070240001).
14 American Society of Mechanical Engineers/American Nuclear Society, "Standard for Level 1/Large Early Release Frequency Probabilistic Risk Assessment for Nuclear Power Plant Applications, Addendum A to RA-S-2008," PRA Standard ASME/ANS RA-Sa-2009, June 2005.
15 U.S. Nuclear Regulatory Commission, "U.S. Nuclear Regulatory Commission Acceptance on Nuclear Energy Institute Appendix X Guidance 05-04, 07-12, and 12-13, Close-Out of Facts and Observations (F&Os)," dated May 3, 2017 (ADAMS Accession No. ML17079A427).
16 Simpson, P.R., Exelon Generation Company, LLC, letter to U.S. Nuclear Regulatory Commission, "Application to Adopt 10 CFR 50.69, Risk-informed Categorization and Treatment of Structures, Systems, and Components for Nuclear Power Reactors," dated April 30, 2020 (ADAMS Accession No. ML20121A241).
17 Wiebe, J. S., U.S. Nuclear Regulatory Commission, letter to David P. Rhoades, Exelon Generation Company, LLC, "Clinton Power Station, Unit No. 1 - Issuance of Amendment No. 237 Regarding Adoption of 10 CFR 50.69, Risk Informed Categorization and Treatment of Structures, Systems and Components of Nuclear Power Reactors (EPID L 2019 LLA 0098)," dated May 19, 2021 (ADAMS Accession No. ML21090A193).
18 Nuclear Energy Institute, "Fire Probabilistic Risk Assessment (FPRA) Peer Review Process Guidelines, Draft Version H," NEI 07-12, Revision 0, November 2008 (ADAMS Package Accession No. ML17086A431).
19 Wiebe, J.S., U.S. Nuclear Regulatory Commission, e-mail to Ken Nicely, Exelon Generation Company, LLC, "Clinton Nuclear Power Station - Request for Additional Information," dated October 27, 2020 (ADAMS Accession No. ML20307A659).
20 U.S. Nuclear Regulatory Commission, "EPRI/NRC Fire PRA Methodology for Nuclear Power Facilities," NUREG/CR-6850, September 2005 (ADAMS Accession No. ML052580075).
21 U.S. Nuclear Regulatory Commmission, "Fire Probabilistic Risk Assessment Methods Enhancement," NUREG/CR-6850, Supplement 1, September 2010 (ADAMS Accession No. ML203090242).
22 Giitter, J., U.S. Nuclear Regulatory Commission, letter to Biff Bradley, Nuclear Energy Institute, "Recent Fire PRA Methods Review Panel Decisions and EPRI 1022993, Evaluation of Peak Heat Release Rates in Eloectrical Cabinet Fires," dated June 21, 2012 (ADAMS Accession No. ML12171A583).
23 U.S. Nuclear Regulatory Commission, "Close-out of Fire PRA Frequently Asked Question 13-0004 on Clarification Regarding Treatment of Sensitive Electronics," FAQ 13-0004 ,
dated December 3, 2013 (ADAMS Accession No. ML13322A085).
 
24 Wiebe, J. S., U.S. Nuclear Regulatory Commission, e-mail to Ken Nicely, Exelon Generation Company, LLC, "Clarification of Second Round RAI - Clinton TSTF-505 License Amendment Request," dated February 26, 2021 (ADAMS Accession No. ML21057A101).
25 U.S. Nuclear Regulatory Commission, "EPRI/NRC-RES Fire Human Reliability Analysis Guidelines Final Report," NUREG-1921, July 2012 (ADAMS Accession No. ML12216A104).
26 U.S. Nuclear Regulatory Commission, "Good Practices for Implementing Human Reliability Analysis (HRA)," NUREG-1792, April 2005 (ADAMS Accession No. ML051160213).
27 U.S. Nuclear Regulatory Commisison, "Close-out of Fire PRA Frequently Asked Question 14-0009 on Treatment of Well-Sealed MCC Electrical Panels Greater Than 440V," FAQ 14-0009, dated April 29, 2015 (ADAMS Accession No. ML15114A441).
28 Kaegi, G.T., Exelon Generation Company, LLC, U.S. Nuclear Regulatory Commission, "Clinton Power Station Unit 1, Seismic Hazard and Screening Report (CEUS Sites),
  'Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the NTTF Review of the Fukushima DAi-ichi Accident'," dated March 31, 2014 (ADAMS Accession No. ML14091A011).
29 Barstow, J., Exelon Generation Company, LLC, letter to U.S. Nuclear Regulatory Commission, "Supplemental Information Regarding Seismic Hazard and Screening Report (Central and Eastern United States (CEUS) Sites - Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1," dated August 21, 2014 (ADAMS Accession No. ML14234A124).
30 U.S. Nuclear Regulatory Commission, "Results of Safety/Risk Assessment of Generic Issue 199, 'Implications of Updated Probabilistic Seismic Hazard Estimates in Central and Eastern United States on Existing Plants'," dated September 2, 2010 (ADAMS Package Accession No. ML100270582).
31 Electric Power Research Institute, "Seismic Probabilistic Rick Assessment Implementation Guide," EPRI 3002000709, December 2013.
32 U.S. Nuclear Regulatory Commission, "Tornado Climatology of the Contiguous United States," NUREG/CR-4461, Revision 2, February 2007 (ADAMS Accession No. ML070810400).
33 U.S. Nuclear Regulatory Commission, "Tornado Missile Protection," NRC Regulatory Issue Summary (RIS) 2015-06, dated June 10, 2015 (ADAMS Accession No. ML15020A419).
34 U.S. Nuclear Regulatory Commmission, "Enforcement Discretion for Tornado-Generated Missile Protection Noncompliance," NRC Enforcement Guidance Memorandum (EGM) 15-002, June 10, 2015 (ADAMS Accession No. ML15111A269).
35 Exelon Generation Company, LLC, "Clinton Power Station Flood Hazard Reevaluation Report, Enclosure 1," dated March 12, 2014 (ADAMS Accession No. ML14079A420).
36 Govan, T., U.S. Nuclear Regulatory Commission, letter to Bryan Hanson, Exelon Generation Company, LLC, "Clinton Power Station, Unit No. 1 - Correction to Staff Assessment of Response to Request for Information Pursuant to 10 CFR 50.54(f) - Flood-Causing Mechanisms Reevalution (TAC NO. MF3654)," dated November 18, 2015 (ADAMS Accession No. ML15321A034).
37 Kaegi, G. T., Exelon Generation Company, LLC, letter to U.S. Nuclear Regulatory Commission, "Mitigating Strategies Flood Hazard Assessment (MSFHA) Submittal," dated March 24, 2016 (ML16084A859).
38 Vaughan, S., Nuclear Energy Institute, letter to U.S. Nuclear Regulatory Commission, "Submittal of NUMARC 93-01, Rev 4f, 'Industry Guideline for Monitoring the Effectiveness
 
of Maintenance at Nuclear Power Plants' for NRC Endorsement," dated April 27, 2018 (ADAMS Accession No. ML18120A069).
39 Reisi-Fard, M., memorandum to Joseph Giitter, U.S. Nuclear Regulatory Commission, "Assessment of The Nuclear Energy Institute 16-06, Crediting Mitigating Strategies in Risk-Informed Decision Making, Guidance for Risk-Informed Changes to Plants Licensing Basis," dated May 30, 2017 (ADAMS Accession No. ML17031A269).
Principal Contributors: H. Wagage J. Ashcraft K. West J. Evans V. Goel R. Vettori K. Tetter Date of issuance: June 28, 2021
 
ML21132A288 OFFICE  NRR/DORL/LPL3/PM  NRR/DORL/LPL3/LA    NRR/DSS/STSB/BC(A) NRR/DSS/SCPB/BC NAME    JWiebe            SRohrer            NJordan            BWittick DATE    05/04/2021        05/20/2021          06/01/2021        06/01/2021 OFFICE  NRR/DEX/EICB/BC    NRR/DEX/EEEB/BC    NRR/DEX/EMIB/BC    NRR/DRA/APLA/BC NAME    MWaters            BTitus              ABuford            RPascarelli DATE    06/28/2021        01/21/2021          04/19/2021        04/28/2021 OFFICE  NRR/DRA/APLB/BC    NRR/DRA/APLC/BC    OGC                NRR/DORL/LPL3/BC NAME    SRosenberg        SVasavada          STurk NLO          NSalgado DATE    04/28/2021        04/28/2021          06/23/2021        06/28/2021 OFFICE  NRR/DORL/LPL3/PM NAME    JWiebe DATE    06/28/2021}}

Revision as of 07:35, 9 September 2021

Issuance of Amendment No. 238, Adoption of Technical Specifications Task Force Traveler TSTF-505, Revision 2, Provide Risk Informed Extended Completion Times - RITSTF Initiative 4B
ML21132A288
Person / Time
Site: Clinton Constellation icon.png
Issue date: 06/28/2021
From: Joel Wiebe
Plant Licensing Branch III
To: Rhoades D
Exelon Generation Co
Wiebe J
References
EPID L-2020-LLA-0097
Download: ML21132A288 (165)


Text

June 28, 2021 Mr. David P. Rhoades Senior Vice President Exelon Generation Company, LLC President and Chief Nuclear Officer (CNO)

Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555

SUBJECT:

CLINTON POWER STATION, UNIT NO. 1 - ISSUANCE OF AMENDMENT NO. 238 RE: TECHNICAL SPECIFICATIONS TASK FORCE TRAVELER TSTF-505, REVISION 2, PROVIDE RISK-INFORMED EXTENDED COMPLETION TIMES - RITSTF INITIATIVE 4B (EPID L-2020-LLA-0097)

Dear Mr. Rhoades:

The U.S. Nuclear Regulatory Commission has issued the enclosed Amendment No. 238 to Facility Operating License No. NPF-62 for the Clinton Power Station, Unit No. 1. The amendment is in response to your application dated April 30, 2020 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML20121A178) as supplemented by letters dated November 24, 2020 (ADAMS Accession No. ML20329A433) and March 23, 2021 (ADAMS Accession No. ML21082A268).

The amendment modifies technical specifications to permit the use of risk-informed completion times in accordance with Technical Specifications Task Force (TSTF) Traveler TSTF-505, Revision 2, "Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b,"

(ADAMS Accession No. ML18183A493).

A copy of the Safety Evaluation is also enclosed. A Notice of Issuance will be included in the Commissions next monthly Federal Register notice.

Sincerely,

/RA/

Joel S. Wiebe, Senior Project Manager Plant Licensing Branch III Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-461

Enclosures:

1. Amendment No. 238 to NPF-62
2. Safety Evaluation cc: Listserv

EXELON GENERATION COMPANY, LLC DOCKET NO. 50-461 CLINTON POWER STATION, UNIT NO. 1 AMENDMENT TO FACILITY OPERATING LICENSE Amendment No. 238 License No. NPF-62

1. The U.S. Nuclear Regulatory Commission (the Commission) has found that:

A. The application for amendment by Exelon Generation Company, LLC (the licensee), dated April 30, 2020, as supplemented by letters dated November 24, 2020 and March 23, 2021, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act), and the Commissions rules and regulations set forth in 10 CFR Chapter I; B. The facility will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission; C. There is reasonable assurance: (i) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commissions regulations; D. The issuance of this amendment will not be inimical to the common defense and security or to the health and safety of the public; and E. The issuance of this amendment is in accordance with 10 CFR Part 51 of the Commissions regulations and all applicable requirements have been satisfied.

Enclosure 1

2. Accordingly, the license is amended by changes to the Technical Specifications as indicated in the attachment to this license amendment, and paragraph 2.C.(2) of Facility Operating License No. NPF-62 is hereby amended to read as follows:

(2) Technical Specifications and Environmental Protection Plan The Technical Specifications contained in Appendix A and the Environmental Protection Plan contained in Appendix B, as revised through Amendment No. 238, are hereby incorporated in the license. Exelon Generation Company shall operate the facility in accordance with the Technical Specifications and the Environmental Protection Plan.

3. This license amendment is effective as of its date of issuance and shall be implemented within 180 days of the date of issuance.

FOR THE NUCLEAR REGULATORY COMMISSION Digitally signed by Nancy L. Nancy L. Salgado Date: 2021.06.28 Salgado 14:54:11 -04'00' Nancy L. Salgado, Chief Plant Licensing Branch III Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation

Attachment:

Changes to the Facility Operating License and Technical Specifications Date of Issuance: June 28, 2021

ATTACHMENT TO LICENSE AMENDMENT NO. 238 FACILITY OPERATING LICENSE NO. NPF-62 CLINTON POWER STATION, UNIT NO. 1 DOCKET NO. 50-461 Replace the following pages of the Facility Operating License No. NPF-62 and the Appendix A, Technical Specifications, with the attached revised pages. The revised pages are identified by amendment number and contain marginal lines indicating the areas of change.

REMOVE INSERT Page 3 Page 3 Technical Specifications REMOVE INSERT 1.0-24 1.0-24 1.0-25 1.0-25 1.0-26 1.0-26 1.0-27 1.0-27 1.0-28 1.0-28 1.0-29 1.0-29

-- 1.0-30 3.1-20 3.1-20 3.3-1 3.3-1 3.3-2 3.3-2 3.3-25 3.3-25 3.3-26 3.3-26 3.3-32 3.3-32 3.3-33 3.3-33 3.3-34 3.3-34 3.3-35 3.3-35 3.3-36 3.3-36 3.3-37 3.3-37

-- 3.3-37a

-- 3.3-37b 3.3-45 3.3-45 3.3-46 3.3-46 3.3-49 3.3-49 3.3-50 3.3-50 3.3-51 3.3-51 3.3-52 3.3-52 3.3-53 3.3-53 3.3-54 3.3-54 3.3-65 3.3-65 3.3-66 3.3-66

REMOVE (continued) INSERT (continued) 3.3-69 3.3-69 3.3-70 3.3-70 3.3-74 3.3-74 3.3-78 3.3-78 3.3-79 3.3-79 3.3-80 3.3-80 3.3-81 3.3-81 3.3-82 3.3-82

-- 3.3-83 3.5-1 3.5-1 3.5-2 3.5-2 3.5-3 3.5-3 3.5-4 3.5-4 3.5-5 3.5-5 3.5-6 3.5-6 3.5-7 3.5-7 3.5-8 3.5-8 3.5-9 3.5-9 3.5-10 3.5-10 3.5-11 3.5-11 3.5-12 3.5-12

-- 3.5-13

-- 3.5-14 3.6-6 3.6-6 3.6-10 3.6-10 3.6-11 3.6-11 3.6-13 3.6-13 3.6-14 3.6-14 3.6-22 3.6-22 3.6-24 3.6-24 3.6-32 3.6-32 3.6-34 3.6-34 3.6-59 3.6-59 3.6-62 3.6-62 3.7-1 3.7-1 3.7-13 3.7-13 3.7-14 3.7-14 3.8-1 3.8-1 3.8-2 3.8-2 3.8-3 3.8-3 3.8-4 3.8-4 3.8-5 3.8-5 3.8-6 3.8-6 3.8-6a --

3.8-6b --

3.8-7 3.8-7 3.8-24 3.8-24 3.8-24a 3.8-24a 3.8-34 3.8-34 3.8-35 3.8-35

REMOVE (continued) INSERT (continued) 3.8-39 3.8-39 3.8-40 3.8-40 3.8-41 3.8-41 5.0-16c 5.0-16c 5.0-17 5.0-17 5.0-18 5.0-18 5.0-19 5.0-19

(4) Exelon Generation Company, pursuant to the Act and to 10 CFR Parts 30, 40, and 70, to receive, possess, and use at any time any byproduct, source and special nuclear material as sealed neutron sources for reactor startup, sealed sources for reactor instrumentation and radiation monitoring equipment calibration, and as fission detectors in amounts as required; (5) Exelon Generation Company, pursuant to the Act and 10 CFR Parts 30, 40, and 70, to receive, possess, and use in amounts as required any byproduct, source or special nuclear material without restriction to chemical or physical form, for sample analysis or instrument calibration or associated with radioactive apparatus or components; (6) Exelon Generation Company, pursuant to the Act and 10 CFR Parts 30, 40, and 70, to possess, but not separate, such byproduct and special nuclear materials as may be produced by the operation of the facility.

Mechanical disassembly of the GE14i isotope test assemblies containing Cobalt-60 is not considered separation; and (7) Exelon Generation Company, pursuant to the Act and 10 CFR Parts 30, to intentionally produce, possess, receive, transfer, and use Cobalt-60.

C. This license shall be deemed to contain and is subject to the conditions specified in the Commissions regulations set forth in 10 CFR Chapter I and is subject to all applicable provisions of the Act and to the rules, regulations and orders of the Commission now or hereafter in effect; and is subject to the additional conditions specified or incorporated below:

(1) Maximum Power Level Exelon Generation Company is authorized to operate the facility at reactor core power levels not in excess of 3473 megawatts thermal (100 percent rated power) in accordance with the conditions specified herein.

(2) Technical Specifications and Environmental Protection Plan The Technical Specifications contained in Appendix A and the Environmental Protection Plan contained in Appendix B, as revised through Amendment No. 238, are hereby incorporated into this license.

Exelon Generation Company shall operate the facility in accordance with the Technical Specifications and the Environmental Protection Plan.

Amendment No. 238

Completion Times 1.3 1.3 Completion Times EXAMPLES EXAMPLE 1.3-7 (continued)

Condition B is entered, but continues from the time Condition A was initially entered. If Required Action A.1 is met after Condition B is entered, Condition B is exited and operation may continue in accordance with Condition A, provided the Completion Time for Required Action A.2 has not expired.

EXAMPLE 1.3-8 ACTIONS CONDITION REQUIRED ACTION COMPLETION TIME A. One A.1 Restore subsystem 7 days subsystem to OPERABLE inoperable. status. OR In accordance with the Risk Informed Completion Time Program B. Required B.1 Be in MODE 3. 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> Action and associated AND Completion Time not B.2 Be in MODE 5. 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br /> met.

When a subsystem is declared inoperable, Condition A is entered. The 7 day Completion Time may be applied as discussed in Example 1.3-2. However, the licensee may elect to apply the Risk Informed Completion Time Program which permits calculation of a Risk Informed Completion Time (RICT) that may be used to complete the Required Action beyond the 7 day Completion Time. The RICT cannot exceed 30 days. After the 7 day Completion Time has expired, the subsystem must be restored to OPERABLE status within the RICT or Condition B must also be entered.

(continued)

CLINTON 1.0-24 Amendment No. 238

Completion Times 1.3 1.3 Completion Times EXAMPLES EXAMPLE 1.3-8 (continued)

The Risk Informed Completion Time Program requires recalculation of the RICT to reflect changing plant conditions. For planned changes, the revised RICT must be determined prior to implementation of the change in configuration. For emergent conditions, the revised RICT must be determined within the time limits of the Required Action Completion Time (i.e., not the RICT) or 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> after the plant configuration change, whichever is less.

If the 7 day Completion Time clock of Condition A has expired and subsequent changes in plant condition result in exiting the applicability of the Risk Informed Completion Time Program without restoring the inoperable subsystem to OPERABLE status, Condition B is also entered and the Completion Time clocks for Required Actions B.1 and B.2 start.

If the RICT expires or is recalculated to be less than the elapsed time since the Condition was entered and the inoperable subsystem has not been restored to OPERABLE status, Condition B is also entered and the Completion Time clocks for Required Actions B.1 and B.2 start. If the inoperable subsystems are restored to OPERABLE status after Condition B is entered, Condition A is exited, and therefore, the Required Actions of Condition B may be terminated.

IMMEDIATE When "Immediately" is used as a Completion Time, the COMPLETION TIME Required Action should be pursued without delay and in a controlled manner.

CLINTON 1.0-25 Amendment No. 238

Frequency 1.4 1.0 USE AND APPLICATION 1.4 Frequency PURPOSE The purpose of this section is to define the proper use and application of Frequency requirements.

DESCRIPTION Each Surveillance Requirement (SR) has a specified Frequency in which the Surveillance must be met in order to meet the associated Limiting Condition for Operation (LCO). An understanding of the correct application of the specified Frequency is necessary for compliance with the SR.

The "specified Frequency" is referred to throughout this section and each of the Specifications of Section 3.0, Surveillance Requirement (SR) Applicability. The "specified Frequency" consists of the requirements of the Frequency column of each SR, as well as certain Notes in the Surveillance column that modify performance requirements.

Sometimes special situations dictate when the requirements of a Surveillance are to be met. They are "otherwise stated" conditions allowed by SR 3.0.1. They may be stated as clarifying Notes in the Surveillance, as part of the Surveillance, or both. Example 1.4-4 discusses these special situations.

Situations where a Surveillance could be required (i.e., its Frequency could expire), but where it is not possible or not desired that it be performed until sometime after the associated LCO is within its Applicability, represent potential SR 3.0.4 conflicts. To avoid these conflicts, the SR (i.e., the Surveillance or the Frequency) is stated such that it is only "required" when it can be and should be performed. With an SR satisfied, SR 3.0.4 imposes no restriction.

The use of "met" or "performed" in these instances conveys specified meanings. A Surveillance is "met" only when the acceptance criteria are satisfied. Known failure of the requirements of a Surveillance, even without a Surveillance specifically being "performed," constitutes a Surveillance not "met." "Performance" refers only to the requirement to specifically determine the ability to meet the acceptance (continued)

CLINTON 1.0-26 Amendment No. 238

Frequency 1.4 1.4 Frequency DESCRIPTION criteria. SR 3.0.4 restrictions would not apply if both the (continued) following conditions are satisfied:

a. The Surveillance is not required to be performed; and
b. The Surveillance is not required to be met or, even if required to be met, is not known to be failed.

EXAMPLES The following examples illustrate the various ways that Frequencies are specified. In these examples, the Applicability of the LCO (LCO not shown) is MODES 1, 2, and 3. The examples do not reflect the potential application of LCO 3.0.4.b.

EXAMPLE 1.4-1 SURVEILLANCE REQUIREMENTS SURVEILLANCE FREQUENCY Perform CHANNEL CHECK. 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> Example 1.4-1 contains the type of SR most often encountered in the Technical Specifications (TS). The Frequency specifies an interval (12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />) during which the associated Surveillance must be performed at least one time.

Performance of the Surveillance initiates the subsequent interval. Although the Frequency is stated as 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />, an extension of the time interval to 1.25 times the interval specified in the Frequency is allowed by SR 3.0.2 for operational flexibility. The measurement of this interval continues at all times, even when the SR is not required to be met per SR 3.0.1 (such as when the equipment is inoperable, a variable is outside specified limits, or the unit is outside the Applicability of the LCO). If the interval specified by SR 3.0.2 is exceeded while the unit is in a MODE or other specified condition in the Applicability of the LCO, and the performance of the Surveillance is not otherwise modified (refer to Examples 1.4-3 and 1.4-4), then SR 3.0.3 becomes applicable.

(continued)

CLINTON 1.0-27 Amendment No. 238

Frequency 1.4 1.4 Frequency EXAMPLES EXAMPLE 1.4-1 (continued)

If the interval as specified by SR 3.0.2 is exceeded while the unit is not in a MODE or other specified condition in the Applicability of the LCO for which performance of the SR is required, the Surveillance must be performed within the Frequency requirements of SR 3.0.2 prior to entry into the MODE or other specified condition. Failure to do so would result in a violation of SR 3.0.4.

EXAMPLE 1.4-2 SURVEILLANCE REQUIREMENTS SURVEILLANCE FREQUENCY Verify flow is within limits. Once within 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> after 25% RTP AND 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> thereafter Example 1.4-2 has two Frequencies. The first is a one time performance Frequency, and the second is of the type shown in Example 1.4-1. The logical connector "AND" indicates that both Frequency requirements must be met. Each time reactor power is increased from a power level < 25% RTP to 25% RTP, the Surveillance must be performed within 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />.

The use of "once" indicates a single performance will satisfy the specified Frequency (assuming no other Frequencies are connected by "AND"). This type of Frequency does not qualify for the extension allowed by SR 3.0.2.

(continued)

CLINTON 1.0-28 Amendment No. 238

Frequency 1.4 1.4 Frequency EXAMPLES EXAMPLE 1.4-2 (continued)

"Thereafter" indicates future performances must be established per SR 3.0.2, but only after a specified condition is first met (i.e., the "once" performance in this example). If reactor power decreases to < 25% RTP, the measurement of both intervals stops. New intervals start upon reactor power reaching 25% RTP.

EXAMPLE 1.4-3 SURVEILLANCE REQUIREMENTS SURVEILLANCE FREQUENCY


NOTE------------------

Not required to be performed until 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> after 25% RTP.

Perform channel adjustment. 7 days The interval continues whether or not the unit operation is

< 25% RTP between performances.

As the Note modifies the required performance of the Surveillance, it is construed to be part of the "specified Frequency." Should the 7 day interval be exceeded while operation is < 25% RTP, this Note allows 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> after power reaches 25% RTP to perform the Surveillance. The Surveillance is still considered to be within the "specified Frequency." Therefore, if the Surveillance were not performed within the 7 day interval (plus the extension allowed by SR 3.0.2), but operation was < 25% RTP, it would not constitute a failure of the SR or failure to meet the LCO. Also, no violation of SR 3.0.4 occurs when changing MODES, even with the 7 day Frequency not met, provided operation does not exceed 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> (plus the extension allowed by SR 3.0.2) with power 25% RTP.

(continued)

CLINTON 1.0-29 Amendment No. 238

Frequency 1.4 1.4 Frequency EXAMPLES EXAMPLE 1.4-3 (continued)

Once the unit reaches 25% RTP, 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> would be allowed for completing the Surveillance. If the Surveillance were not performed within this 12 hour1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> interval (plus the extension allowed by SR 3.0.2), there would then be a failure to perform a Surveillance within the specified Frequency, and the provisions of SR 3.0.3 would apply.

EXAMPLE 1.4-4 SURVEILLANCE REQUIREMENTS SURVEILLANCE FREQUENCY


NOTE-----------------

Only required to be met in MODE 1.

Verify leakage rates are within limits. 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> Example 1.4-4 specifies that the requirements of this Surveillance do not have to be met until the unit is in MODE 1. The interval measurement for the Frequency of this Surveillance continues at all times, as described in Example 1.4-1. However, the Note constitutes an "otherwise stated" exception to the Applicability of this Surveillance.

Therefore, if the Surveillance were not performed within the 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> (plus the extension allowed by SR 3.0.2) interval, but the unit was not in MODE 1, there would be no failure of the SR nor failure to meet the LCO. Therefore, no violation of SR 3.0.4 occurs when changing MODES, even with the 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> Frequency exceeded, provided the MODE change was not made into MODE 1. Prior to entering MODE 1 (assuming again that the 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> Frequency were not met), SR 3.0.4 would require satisfying the SR.

CLINTON 1.0-30 Amendment No. 238

SLC System 3.1.7 3.1 REACTIVITY CONTROL SYSTEMS 3.1.7 Standby Liquid Control (SLC) System LCO 3.1.7 Two SLC subsystems shall be OPERABLE.

APPLICABILITY: MODES 1, 2, and 3.

ACTIONS CONDITION REQUIRED ACTION COMPLETION TIME A. One SLC subsystem A.1 Restore SLC subsystem 7 days inoperable. to OPERABLE status.

OR In accordance with the Risk Informed Completion Time Program B. Two SLC subsystems B.1 Restore one SLC 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> inoperable. subsystem to OPERABLE status.

C. Required Action and C.1 Be in MODE 3. 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> associated Completion Time not met. AND C.2 Be in MODE 4. 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br /> SURVEILLANCE REQUIREMENTS SURVEILLANCE FREQUENCY SR 3.1.7.1 Verify available volume of sodium In accordance pentaborate solution is within the limits with the of Figure 3.1.7-1. Surveillance Frequency Control Program (continued)

CLINTON 3.1-20 Amendment No. 238

RPS Instrumentation 3.3.1.1 3.3 INSTRUMENTATION 3.3.1.1 Reactor Protection System (RPS) Instrumentation LCO 3.3.1.1 The RPS instrumentation for each Function in Table 3.3.1.1-1 shall be OPERABLE.

APPLICABILITY: According to Table 3.3.1.1-1.

ACTIONS


NOTES-------------------------------------

1. Separate Condition entry is allowed for each Function.
2. When Functions 2.b and 2.c channels are inoperable due to the calculated power exceeding the APRM output by more than 2% RTP while operating at 21.6% RTP, entry into associated Conditions and Required Actions may be delayed for up to 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br />.

CONDITION REQUIRED ACTION COMPLETION TIME A. One or more Functions A.1 Place one channel in 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br /> with one channel affected Function in inoperable. trip. OR In accordance with the Risk Informed Completion Time Program B. One or more Functions B.1 Place one channel in 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> with two channels affected Function in inoperable. trip. OR In accordance with the Risk Informed Completion Time Program C. One or more Functions C.1 Restore two channels 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> with three or more in affected Function channels inoperable. to OPERABLE status.

(continued)

CLINTON 3.3-1 Amendment No. 238

RPS Instrumentation 3.3.1.1 ACTIONS (continued)

CONDITION REQUIRED ACTION COMPLETION TIME D. Required Action and D.1 Enter the Condition Immediately associated referenced in Completion Time of Table 3.3.1.1-1 for Condition A, B, or C the channel.

not met.

E. As required by E.1 Reduce THERMAL POWER 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> Required Action D.1 to < 33.3% RTP.

and referenced in Table 3.3.1.1-1.

F. As required by F.1 Reduce THERMAL POWER 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> Required Action D.1 to < 21.6% RTP.

and referenced in Table 3.3.1.1-1.

G. As required by G.1 Be in MODE 2. 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> Required Action D.1 and referenced in Table 3.3.1.1-1.

H. As required by H.1 Be in MODE 3. 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> Required Action D.1 and referenced in Table 3.3.1.1-1.

I. As required by I.1 Initiate action to Immediately Required Action D.1 fully insert all and referenced in insertable control Table 3.3.1.1-1. rods in core cells containing one or more fuel assemblies.

CLINTON 3.3-2 Amendment No. 238

EOC-RPT Instrumentation 3.3.4.1 3.3 INSTRUMENTATION 3.3.4.1 End of Cycle Recirculation Pump Trip (EOC-RPT) Instrumentation LCO 3.3.4.1 Four channels for each EOC-RPT instrumentation Function listed below shall be OPERABLE:

a. Turbine Stop Valve (TSV) Closure; and
b. Turbine Control Valve (TCV) Fast Closure, Trip Oil Pressure-Low.

APPLICABILITY: THERMAL POWER 33.3% RTP with any recirculation pump in fast speed.

ACTIONS


NOTE -------------------------------------

Separate Condition entry is allowed for each Function.

CONDITION REQUIRED ACTION COMPLETION TIME A. One or more Functions A.1 Restore channel to 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br /> with one required OPERABLE status.

channel inoperable. OR In accordance with the Risk Informed Completion Time Program OR A.2 --------NOTE---------

Not applicable if inoperable channel is the result of an inoperable breaker.

Place one channel in 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br /> affected Function in trip. OR In accordance with the Risk Informed Completion Time Program (continued)

CLINTON 3.3-25 Amendment No. 238

EOC-RPT Instrumentation 3.3.4.1 ACTIONS (continued)

CONDITION REQUIRED ACTION COMPLETION TIME B. One or more Functions B.1 Place one channel in 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> with two channels affected Function in inoperable. trip. OR In accordance with the Risk Informed Completion Time Program C. One or more Functions C.1 Restore two channels 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> with three or more in affected Function channels inoperable. to OPERABLE status.

D. Required Action and D.1 Remove the associated 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> associated Completion recirculation pump Time not met. fast speed breaker from service.

OR D.2 Reduce THERMAL POWER 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> to < 33.3% RTP.

SURVEILLANCE REQUIREMENTS


NOTE -------------------------------------

When a channel is placed in an inoperable status solely for performance of required Surveillances, entry into associated Conditions and Required Actions may be delayed for up to 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />, provided the associated Function maintains EOC-RPT trip capability.

SURVEILLANCE FREQUENCY SR 3.3.4.1.1 Perform CHANNEL FUNCTIONAL TEST. In accordance with the Surveillance Frequency Control Program (continued)

CLINTON 3.3-26 Amendment No. 238

ECCS Instrumentation 3.3.5.1 ACTIONS (continued)

CONDITION REQUIRED ACTION COMPLETION TIME B. As required by B.1 --------NOTE---------

Required Action A.1 Only applicable for and referenced in Functions 1.a, 1.b, Table 3.3.5.1-1. 2.a, and 2.b.

Declare supported 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> from feature(s) inoperable discovery of when its redundant loss of feature ECCS initiation initiation capability is capability for inoperable. feature(s) in both divisions AND B.2 --------NOTE---------

Only applicable for Functions 3.a and 3.b.

Declare High Pressure 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> from Core Spray (HPCS) discovery of System inoperable. loss of HPCS initiation capability AND B.3 Place channel in trip. 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> OR


NOTE-----

Not applicable when trip capability is not maintained.

In accordance with the Risk Informed Completion Time Program (continued)

CLINTON 3.3-32 Amendment No. 238

ECCS Instrumentation 3.3.5.1 ACTIONS (continued)

CONDITION REQUIRED ACTION COMPLETION TIME C. As required by C.1 ---------NOTE--------

Required Action A.1 Only applicable for and referenced in Functions 1.c, 1.d, Table 3.3.5.1-1. 2.c, and 2.d.

Declare supported 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> from feature(s) inoperable discovery of when its redundant loss of feature ECCS initiation initiation capability capability for is inoperable. feature(s) in both divisions AND C.2 Restore channel to 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> OPERABLE status.

OR


NOTE-----

Not applicable when trip capability is not maintained.

In accordance with the Risk Informed Completion Time Program (continued)

CLINTON 3.3-33 Amendment No. 238

ECCS Instrumentation 3.3.5.1 ACTIONS (continued)

CONDITION REQUIRED ACTION COMPLETION TIME D. As required by D.1 --------NOTE--------

Required Action A.1 Only applicable if and referenced in HPCS pump suction is Table 3.3.5.1-1. not aligned to the suppression pool.

Declare HPCS System 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> from inoperable. discovery of loss of HPCS initiation capability AND D.2.1 Place channel in 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> trip.

OR


NOTE-----

Not applicable when trip capability is not maintained.

In accordance with the Risk Informed Completion Time Program OR D.2.2 Align the HPCS pump 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> suction to the suppression pool.

(continued)

CLINTON 3.3-34 Amendment No. 238

ECCS Instrumentation 3.3.5.1 ACTIONS (continued)

CONDITION REQUIRED ACTION COMPLETION TIME E. As required by E.1 --------NOTE---------

Required Action A.1 Only applicable for and referenced in Functions 1.e, 1.f, Table 3.3.5.1-1. and 2.e.

Declare supported 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> from feature(s) inoperable discovery of when its redundant loss of feature ECCS initiation initiation capability capability for is inoperable. feature(s) in both divisions AND E.2 Restore channel to 7 days OPERABLE status.

OR


NOTE-----

Not applicable when trip capability is not maintained.

In accordance with the Risk Informed Completion Time Program (continued)

CLINTON 3.3-35 Amendment No. 238

ECCS Instrumentation 3.3.5.1 ACTIONS (continued)

CONDITION REQUIRED ACTION COMPLETION TIME F. As required by F.1 Declare Automatic 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> from Required Action A.1 Depressurization discovery of and referenced in System (ADS) valves loss of ADS Table 3.3.5.1-1. inoperable. initiation capability in both trip systems AND F.2 Place channel in 96 hours0.00111 days <br />0.0267 hours <br />1.587302e-4 weeks <br />3.6528e-5 months <br /> or in trip. accordance with the Risk Informed Completion Time Program from discovery of inoperable channel concurrent with HPCS or reactor core isolation cooling (RCIC) inoperable AND


NOTE-----

The Risk Informed Completion Time Program is not applicable when trip capability is not maintained.

8 days or in accordance with the Risk Informed Completion Time Program (continued)

CLINTON 3.3-36 Amendment No. 238

ECCS Instrumentation 3.3.5.1 ACTIONS (continued)

CONDITION REQUIRED ACTION COMPLETION TIME G. As required by G.1 --------NOTES--------

Required Action A.1 Only applicable for and referenced in Functions 4.c, 4.e, Table 3.3.5.1-1. 4.f, 4.g, 5.c, 5.e, and 5.f.

Declare ADS valves 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> from inoperable. discovery of loss of ADS initiation capability in both trip systems AND G.2 Restore channel to 96 hours0.00111 days <br />0.0267 hours <br />1.587302e-4 weeks <br />3.6528e-5 months <br /> or in OPERABLE status. accordance with the Risk Informed Completion Time Program from discovery of inoperable channel concurrent with HPCS or RCIC inoperable AND


NOTE-----

The Risk Informed Completion Time Program is not applicable when trip capability is not maintained.

8 days or in accordance with the Risk Informed Completion Time Program (continued)

CLINTON 3.3-37 Amendment No. 238

ECCS Instrumentation 3.3.5.1 ACTIONS (continued)

CONDITION REQUIRED ACTION COMPLETION TIME H. Required Action and H.1 Declare associated Immediately associated Completion supported feature(s)

Time of Condition B, inoperable.

C, D, E, F, or G not met.

CLINTON 3.3-37a Amendment No. 238

ECCS Instrumentation 3.3.5.1 This page intentionally left blank.

CLINTON 3.3-37b Amendment No. 238

RCIC System Instrumentation 3.3.5.3 3.3 INSTRUMENTATION 3.3.5.3 Reactor Core Isolation Cooling (RCIC) System Instrumentation LCO 3.3.5.3 The RCIC System instrumentation for each Function in Table 3.3.5.3-1 shall be OPERABLE.

APPLICABILITY: MODE 1, MODES 2 and 3 with reactor steam dome pressure > 150 psig.

ACTIONS


NOTE--------------------------------------

Separate Condition entry is allowed for each channel.

CONDITION REQUIRED ACTION COMPLETION TIME A. One or more channels A.1 Enter the Condition Immediately inoperable. referenced in Table 3.3.5.3-1 for the channel.

B. As required by B.1 Declare RCIC System 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> from Required Action A.1 inoperable. discovery of and referenced in loss of RCIC Table 3.3.5.3-1. initiation capability AND B.2 Place channel in 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> trip.

OR


NOTE-----

Not applicable when trip capability is not maintained.

In accordance with the Risk Informed Completion Time Program (continued)

CLINTON 3.3-45 Amendment No. 238

RCIC System Instrumentation 3.3.5.3 ACTIONS (continued)

CONDITION REQUIRED ACTION COMPLETION TIME C. As required by C.1 Restore channel to 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> Required Action A.1 OPERABLE status.

and referenced in Table 3.3.5.3-1.

D. As required by D.1 ---------NOTE----------

Required Action A.1 Only applicable if and referenced in RCIC pump suction is Table 3.3.5.3-1. not aligned to the suppression pool.

Declare RCIC System 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> from inoperable. discovery of loss of RCIC initiation capability AND D.2.1 Place channel in 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> trip.

OR


NOTE-----

Not applicable when trip capability is not maintained.

In accordance with the Risk Informed Completion Time Program OR D.2.2 Align RCIC pump 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> suction to the suppression pool.

E. Required Action and E.1 Declare RCIC System Immediately associated inoperable.

Completion Time of Condition B, C, or D not met.

CLINTON 3.3-46 Amendment No. 238

Primary Containment and Drywell Isolation Instrumentation 3.3.6.1 3.3 INSTRUMENTATION 3.3.6.1 Primary Containment and Drywell Isolation Instrumentation LCO 3.3.6.1 The primary containment and drywell isolation instrumentation for each Function in Table 3.3.6.1-1 shall be OPERABLE.

APPLICABILITY: According to Table 3.3.6.1-1.

ACTIONS


NOTE-------------------------------------

Separate Condition entry is allowed for each channel.

CONDITION REQUIRED ACTION COMPLETION TIME


NOTE---------- A.1 Place one channel in 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br /> Only applicable to Main affected Function in Steam Line (MSL) isolation trip. OR Functions.


In accordance with the Risk A. One or more Functions Informed with one channel Completion Time inoperable. Program


NOTE---------- B.1 Place one channel in 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> Only applicable to MSL affected Function in isolation Functions. trip. OR In accordance B. One or more Functions with the Risk with two channels Informed inoperable. Completion Time Program


NOTE---------- C.1 Restore two channels 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> Only applicable to MSL in affected Function isolation Functions. to OPERABLE status.

C. One or more Functions with three or more channels inoperable.

(continued)

CLINTON 3.3-49 Amendment No. 238

Primary Containment and Drywell Isolation Instrumentation 3.3.6.1 ACTIONS (continued)

CONDITION REQUIRED ACTION COMPLETION TIME


NOTE---------- D.1 Place channel in trip. 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> Not applicable to MSL isolation Functions. OR


NOTE-----

D. One or more required Not applicable channels inoperable. when trip capability is not maintained.

In accordance with the Risk Informed Completion Time Program


NOTE--------- E.1 Restore isolation 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> Not applicable to MSL capability.

isolation Functions.

E. One or more automatic Functions with isolation capability not maintained.

F. Required Action and F.1 Enter the Condition Immediately associated Completion referenced in Time of Condition A, Table 3.3.6.1-1 for B, C, D, or E not the channel.

met.

G. As required by G.1 Isolate associated 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> Required Action F.1 MSL.

and referenced in Table 3.3.6.1-1. OR G.2.1 Be in MODE 3. 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> AND G.2.2 Be in MODE 4. 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br /> (continued)

CLINTON 3.3-50 Amendment No. 238

Primary Containment and Drywell Isolation Instrumentation 3.3.6.1 ACTIONS (continued)

CONDITION REQUIRED ACTION COMPLETION TIME H. As required by H.1 Be in MODE 2. 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> Required Action F.1 and referenced in Table 3.3.6.1-1.

I. As required by I.1 Isolate the affected 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> Required Action F.1 penetration flow and referenced in path(s).

Table 3.3.6.1-1.

J. As required by J.1 Isolate the affected 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> Required Action F.1 penetration flow and referenced in path(s).

Table 3.3.6.1-1.

K. As required by K.1 Be in MODE 3. 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> Required Action F.1 and referenced in AND Table 3.3.6.1-1.

K.2 Be in MODE 4. 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br /> OR Required Action and associated Completion Time of Condition I or J not met.

L. As required by L.1 Declare associated 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> Required Action F.1 standby liquid and referenced in control subsystem Table 3.3.6.1-1. inoperable.

OR L.2 Isolate the Reactor 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> Water Cleanup System.

M. As required by M.1 Initiate action to Immediately Required Action F.1 restore channel to and referenced in OPERABLE status.

Table 3.3.6.1-1.

OR (continued)

CLINTON 3.3-51 Amendment No. 238

Primary Containment and Drywell Isolation Instrumentation 3.3.6.1 ACTIONS CONDITION REQUIRED ACTION COMPLETION TIME M. (continued) M.2 Initiate action to Immediately isolate the Residual Heat Removal (RHR)

Shutdown Cooling System suction from the reactor vessel.

OR M.3.1 Initiate action to Immediately restore secondary containment to OPERABLE status.

AND M.3.2 Initiate action to Immediately restore one standby gas treatment (SGT) subsystem to OPERABLE status.

AND M.3.3 Initiate action to Immediately restore isolation capability in each required secondary containment and secondary containment bypass penetration flow path not isolated.

AND M.3.4 ---------NOTE-------

Entry and exit is permissible under administrative control.

Initiate action to Immediately close one door in the upper containment personnel air lock.

(continued)

CLINTON 3.3-52 Amendment No. 238

Primary Containment and Drywell Isolation Instrumentation 3.3.6.1 ACTIONS (continued)

CONDITION REQUIRED ACTION COMPLETION TIME N. As required by N.1 Isolate the affected Immediately Required Action F.1 penetration flow and referenced in path(s).

Table 3.3.6.1-1.

OR N.2 Suspend movement of Immediately recently irradiated fuel assemblies in the primary and secondary containment.

SURVEILLANCE REQUIREMENTS


NOTES------------------------------------

1. Refer to Table 3.3.6.1-1 to determine which SRs apply for each Primary Containment and Drywell Isolation Function.
2. When a channel is placed in an inoperable status solely for performance of required Surveillances, entry into associated Conditions and Required Actions may be delayed for up to 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />, provided the associated Function maintains isolation capability.

SURVEILLANCE FREQUENCY SR 3.3.6.1.1 Perform CHANNEL CHECK. In accordance with the Surveillance Frequency Control Program SR 3.3.6.1.2 Perform CHANNEL FUNCTIONAL TEST. In accordance with the Surveillance Frequency Control Program (continued)

CLINTON 3.3-53 Amendment No. 238

Primary Containment and Drywell Isolation Instrumentation 3.3.6.1 SURVEILLANCE REQUIREMENTS (continued)

SURVEILLANCE FREQUENCY SR 3.3.6.1.3 Calibrate the analog trip module. In accordance with the Surveillance Frequency Control Program SR 3.3.6.1.4 Perform CHANNEL CALIBRATION. In accordance with the Surveillance Frequency Control Program SR 3.3.6.1.5 Perform CHANNEL CALIBRATION. In accordance with the Surveillance Frequency Control Program SR 3.3.6.1.6 Perform LOGIC SYSTEM FUNCTIONAL TEST. In accordance with the Surveillance Frequency Control Program SR 3.3.6.1.7 ---------------NOTE---------------------

Channel sensors are excluded.

Verify the ISOLATION SYSTEM RESPONSE In accordance TIME for the main steam isolation valves with the is within limits. Surveillance Frequency Control Program SR 3.3.6.1.8 Perform CHANNEL CALIBRATION. In accordance with the Surveillance Frequency Control Program CLINTON 3.3-54 Amendment No. 238

RHR Containment Spray System Instrumentation 3.3.6.3 3.3 INSTRUMENTATION 3.3.6.3 Residual Heat Removal (RHR) Containment Spray System Instrumentation LCO 3.3.6.3 The RHR Containment Spray System instrumentation for each Function in Table 3.3.6.3-1 shall be OPERABLE.

APPLICABILITY: MODES 1, 2, and 3.

ACTIONS


NOTE-------------------------------------

Separate Condition entry is allowed for each channel.

CONDITION REQUIRED ACTION COMPLETION TIME A. One or more channels A.1 Enter the Condition Immediately inoperable. referenced in Table 3.3.6.3-1 for the channel.

B. As required by B.1 Declare associated 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> from Required Action A.1 RHR containment spray discovery of and referenced in subsystem inoperable. loss of RHR Table 3.3.6.3-1. containment spray initiation capability in both trip systems AND B.2 Place channel in 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> trip.

OR


NOTE-----

Not applicable when trip capability is not maintained.

In accordance with the Risk Informed Completion Time Program (continued)

CLINTON 3.3-65 Amendment No. 238

RHR Containment Spray System Instrumentation 3.3.6.3 ACTIONS (continued)

CONDITION REQUIRED ACTION COMPLETION TIME C. As required by C.1 --------NOTE---------

Required Action A.1 Only applicable for and referenced in Functions 4 and 5.

Table 3.3.6.3-1. ---------------------

Declare associated 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> from RHR containment spray discovery of subsystem inoperable. loss of RHR containment spray initiation capability in both trip systems AND 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> C.2 Restore channel to OPERABLE status. OR


NOTE-----

Not applicable when trip capability is not maintained.

In accordance with the Risk Informed Completion Time Program D. Required Action and D.1 Declare associated Immediately associated Completion RHR containment Time of Condition B spray subsystem or C not met. inoperable.

CLINTON 3.3-66 Amendment No. 238

SPMU System Instrumentation 3.3.6.4 3.3 INSTRUMENTATION 3.3.6.4 Suppression Pool Makeup (SPMU) System Instrumentation LCO 3.3.6.4 The SPMU System instrumentation for each Function in Table 3.3.6.4-1 shall be OPERABLE.

APPLICABILITY: MODES 1, 2, and 3.

ACTIONS


NOTE-------------------------------------

Separate Condition entry is allowed for each channel.

CONDITION REQUIRED ACTION COMPLETION TIME A. One or more channels A.1 Enter the Condition Immediately inoperable. referenced in Table 3.3.6.4-1 for the channel.

B. As required by B.1 Declare associated 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> from Required Action A.1 SPMU subsystem discovery of and referenced in inoperable. loss of SPMU Table 3.3.6.4-1. initiation capability in both trip systems AND B.2 Place channel in 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> trip.

OR


NOTE-----

Not applicable when trip capability is not maintained.

In accordance with the Risk Informed Completion Time Program (continued)

CLINTON 3.3-69 Amendment No. 238

SPMU System Instrumentation 3.3.6.4 ACTIONS (continued)

CONDITION REQUIRED ACTION COMPLETION TIME C. As required by C.1 --------NOTE---------

Required Action A.1 Only applicable for and referenced in Function 4.

Table 3.3.6.4-1. ---------------------

Declare associated 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> from SPMU subsystem discovery of inoperable. loss of SPMU initiation capability in both trip systems AND C.2 Restore channel to 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> OPERABLE status.

OR


NOTE-----

Not applicable when trip capability is not maintained.

In accordance with the Risk Informed Completion Time Program D. Required Action and D.1 Declare associated Immediately associated Completion SPMU subsystem Time of Condition B inoperable.

or C not met.

CLINTON 3.3-70 Amendment No. 238

Relief and LLS Instrumentation 3.3.6.5 3.3 INSTRUMENTATION 3.3.6.5 Relief and Low-Low Set (LLS) Instrumentation LCO 3.3.6.5 Two relief and LLS instrumentation trip systems shall be OPERABLE.

APPLICABILITY: MODES 1, 2, and 3.

ACTIONS CONDITION REQUIRED ACTION COMPLETION TIME A. One trip system A.1 Restore trip system 7 days inoperable. to OPERABLE status.

OR In accordance with the Risk Informed Completion Time Program OR A.2 Declare associated 7 days relief and LLS valve(s) inoperable.

B. Required Action and B.1 Be in MODE 3. 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> associated Completion Time of Condition A AND not met.

B.2 Be in MODE 4. 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br /> OR Two trip systems inoperable.

CLINTON 3.3-74 Amendment No. 238

LOP Instrumentation 3.3.8.1 3.3 INSTRUMENTATION 3.3.8.1 Loss of Power (LOP) Instrumentation LCO 3.3.8.1 The LOP instrumentation for each Function in Table 3.3.8.1-1 shall be OPERABLE.

APPLICABILITY: MODES 1, 2, and 3, When the associated diesel generator (DG) is required to be OPERABLE by LCO 3.8.2, "AC Sources-Shutdown."

ACTIONS


NOTE-------------------------------------

Separate Condition entry is allowed for each channel.

CONDITION REQUIRED ACTION COMPLETION TIME A. One or more channels A.1 Place channel in trip. 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> inoperable.

OR


NOTE-----

Not applicable when trip capability is not maintained.

In accordance with the Risk Informed Completion Time Program AND (continued)

CLINTON 3.3-78 Amendment No. 238

LOP Instrumentation 3.3.8.1 ACTIONS CONDITION REQUIRED ACTION COMPLETION TIME A. (continued) A.2 ---------NOTE----------

Only applicable for Functions 1.c, 1.d, 1.e, 2.c, 2.d, and 2.e Restore channel to 7 days OPERABLE status.

OR


NOTE-----

Not applicable when trip capability is not maintained.

In accordance with the Risk Informed Completion Time Program B. Required Action and B.1 Declare associated DG Immediately associated Completion inoperable.

Time not met.

CLINTON 3.3-79 Amendment No. 238

LOP Instrumentation 3.3.8.1 SURVEILLANCE REQUIREMENTS


NOTES------------------------------------

1. Refer to Table 3.3.8.1-1 to determine which SRs apply for each LOP Function.
2. When a channel is placed in an inoperable status solely for performance of required Surveillances, entry into associated Conditions and Required Actions may be delayed for up to 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> provided the associated Function maintains DG initiation capability.

SURVEILLANCE FREQUENCY SR 3.3.8.1.1 Deleted SR 3.3.8.1.2 Perform CHANNEL FUNCTIONAL TEST. In accordance with the Surveillance Frequency Control Program SR 3.3.8.1.3 Perform CHANNEL CALIBRATION. In accordance with the Surveillance Frequency Control Program SR 3.3.8.1.4 Perform LOGIC SYSTEM FUNCTIONAL TEST. In accordance with the Surveillance Frequency Control Program CLINTON 3.3-80 Amendment No. 238

LOP Instrumentation 3.3.8.1 Table 3.3.8.1-1 (page 1 of 1)

Loss of Power Instrumentation REQUIRED CHANNELS PER SURVEILLANCE ALLOWABLE FUNCTION DIVISION REQUIREMENTS VALUE

1. Divisions 1 and 2 - 4.16 kV Emergency Bus Undervoltage
a. Loss of Voltage - 4.16 kV 6 SR 3.3.8.1.3 2345 V and 3395 V basis SR 3.3.8.1.4
b. Loss of Voltage - Time 6 SR 3.3.8.1.3 5.0 seconds Delay SR 3.3.8.1.4
c. Degraded Voltage 2 SR 3.3.8.1.2 4102.2 V and 4109.3 V Reset - 4.16 kV basis SR 3.3.8.1.3 SR 3.3.8.1.4
d. Degraded Voltage 2 SR 3.3.8.1.2 4051 V Drop-out - 4.16 kV basis SR 3.3.8.1.3 SR 3.3.8.1.4
e. Degraded Voltage-Time 1 SR 3.3.8.1.2 14 seconds and 16 seconds Delay SR 3.3.8.1.3 SR 3.3.8.1.4
2. Division 3 - 4.16 kV Emergency Bus Undervoltage
a. Loss of Voltage - 4.16 kV 4 SR 3.3.8.1.3 2345 V and 2730 V basis SR 3.3.8.1.4
b. Loss of Voltage - Time 1 SR 3.3.8.1.3 3.0 seconds Delay SR 3.3.8.1.4
c. Degraded Voltage 2 SR 3.3.8.1.2 4102.2 V and 4109.3 V Reset - 4.16 kV basis SR 3.3.8.1.3 SR 3.3.8.1.4
d. Degraded Voltage 2 SR 3.3.8.1.2 4051 V Drop-out - 4.16 kV basis SR 3.3.8.1.3 SR 3.3.8.1.4
e. Degraded Voltage - Time 1 SR 3.3.8.1.2 13.2 seconds and 16.8 Delay SR 3.3.8.1.3 seconds SR 3.3.8.1.4 CLINTON 3.3-81 Amendment No. 238

RPS Electric Power Monitoring 3.3.8.2 3.3 INSTRUMENTATION 3.3.8.2 Reactor Protection System (RPS) Electric Power Monitoring LCO 3.3.8.2 One RPS electric power monitoring assembly shall be OPERABLE for each inservice RPS special solenoid power supply or alternate power supply.

APPLICABILITY: MODES 1, 2, and 3, MODES 4 and 5 with any control rod withdrawn from a core cell containing one or more fuel assemblies.

ACTIONS CONDITION REQUIRED ACTION COMPLETION TIME A. One or both inservice A.1 Remove associated 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> power supplies with inservice power the electric power supply(s) from monitoring assembly service.

inoperable.

B. Required Action and -------------NOTE------------

associated Completion LCO 3.0.4a is not Time of Condition A applicable when entering not met in MODE 1, 2, MODE 3 or 3. -----------------------------

B.1 Be in MODE 3. 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> C. Required Action and C.1 Initiate action to Immediately associated Completion fully insert all Time of Condition A insertable control rods not met in MODE 4 or 5 in core cells with any control rod containing one or more withdrawn from a core fuel assemblies.

cell containing one or more fuel assemblies.

Amendment No. 238 CLINTON 3.3-82

RPS Electric Power Monitoring 3.3.8.2 SURVEILLANCE REQUIREMENTS SURVEILLANCE FREQUENCY SR 3.3.8.2.1 -----------------NOTE-------------------

Only required to be performed prior to entering MODE 2 or 3 from MODE 4, when in MODE 4 for 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.

Perform CHANNEL FUNCTIONAL TEST. In accordance with the Surveillance Frequency Control Program SR 3.3.8.2.2 Perform CHANNEL CALIBRATION. The In accordance Allowable Values shall be: with the Surveillance

a. Overvoltage Frequency Control Program Bus A 127.3 V Bus B 126.7 V
b. Undervoltage Bus A 115.0 V Bus B 114.7 V
c. Underfrequency (with time delay 4.0 seconds)

Bus A 57 Hz Bus B 57 Hz SR 3.3.8.2.3 Perform a system functional test. In accordance with the Surveillance Frequency Control Program CLINTON 3.3-83 Amendment No. 238

ECCS Operating 3.5.1 3.5 EMERGENCY CORE COOLING SYSTEMS (ECCS), REACTOR PRESSURE VESSEL (RPV)

WATER INVENTORY CONTROL, AND REACTOR CORE ISOLATION COOLING (RCIC)

SYSTEM 3.5.1 ECCS Operating LCO 3.5.1 Each ECCS injection/spray subsystem and the Automatic Depressurization System (ADS) function of seven safety/

relief valves shall be OPERABLE.


NOTE----------------------------

One low pressure coolant injection (LPCI) subsystem may be inoperable during alignment and operation for decay heat removal with reactor steam dome pressure less than the residual heat removal cut in permissive pressure.

APPLICABILITY: MODE 1, MODES 2 and 3, except ADS valves are not required to be OPERABLE with reactor steam dome pressure 150 psig.

ACTIONS


NOTE-------------------------------------

LCO 3.0.4.b is not applicable to High Pressure Core Spray (HPCS).

CONDITION REQUIRED ACTION COMPLETION TIME A. One low pressure ECCS A.1 Restore low pressure 7 days injection/spray ECCS injection/spray subsystem inoperable. subsystem to OPERABLE OR status.

In accordance with the Risk Informed Completion Time Program (continued)

CLINTON 3.5-1 Amendment No. 238

ECCS Operating 3.5.1 ACTIONS (continued)

CONDITION REQUIRED ACTION COMPLETION TIME B. HPCS System B.1 Verify by 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> inoperable. administrative means RCIC System is OPERABLE when RCIC is required to be OPERABLE.

AND B.2 Restore HPCS System 14 days to OPERABLE status.

OR In accordance with the Risk Informed Completion Time Program C. Two ECCS injection C.1 Restore one ECCS 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> subsystems inoperable. injection/spray subsystem to OPERABLE OR OR status.

In accordance One ECCS injection and with the Risk one ECCS spray Informed subsystem inoperable. Completion Time Program D. Required Action and -------------NOTE------------

associated Completion LCO 3.0.4.a is not Time of Condition A, applicable when entering B, or C not met. MODE 3.

D.1 Be in MODE 3. 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> E. One ADS valve E.1 Restore ADS valve to 14 days inoperable. OPERABLE status.

OR In accordance with the Risk Informed Completion Time Program (continued)

CLINTON 3.5-2 Amendment No. 238

ECCS Operating 3.5.1 ACTIONS (continued)

CONDITION REQUIRED ACTION COMPLETION TIME F. One ADS valve F.1 Restore ADS valve to 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> inoperable. OPERABLE status.

OR AND In accordance One low pressure ECCS with the Risk injection/spray Informed subsystem inoperable. Completion Time Program OR F.2 Restore low pressure 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> ECCS injection/spray subsystem to OPERABLE OR status.

In accordance with the Risk Informed Completion Time Program G. Two or more ADS valves -------------NOTE------------

inoperable. LCO 3.0.4.a is not applicable when entering OR MODE 3.

Required Action and associated Completion G.1 Be in MODE 3. 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> Time of Condition E or F not met.

(continued)

CLINTON 3.5-3 Amendment No. 238

ECCS Operating 3.5.1 ACTIONS (continued)

CONDITION REQUIRED ACTION COMPLETION TIME H. HPCS and Low Pressure H.1 Enter LCO 3.0.3. Immediately Core Spray (LPCS)

Systems inoperable.

OR Three or more ECCS injection/spray subsystems inoperable.

OR HPCS System and one or more ADS valves inoperable.

OR Two or more ECCS injection/spray subsystems and one or more ADS valves inoperable.

CLINTON 3.5-4 Amendment No. 238

ECCS Operating 3.5.1 SURVEILLANCE REQUIREMENTS SURVEILLANCE FREQUENCY SR 3.5.1.1 Verify, for each ECCS injection/spray In accordance subsystem, locations susceptible to gas with the accumulation are sufficiently filled with Surveillance water. Frequency Control Program SR 3.5.1.2 --------------------NOTE-------------------

Not required to be met for system vent flow paths opened under administrative control.

Verify each ECCS injection/spray subsystem In accordance manual, power operated, and automatic valve with the in the flow path, that is not locked, Surveillance sealed, or otherwise secured in position, Frequency is in the correct position. Control Program SR 3.5.1.3 Verify ADS accumulator supply pressure is In accordance 140 psig. with the Surveillance Frequency Control Program SR 3.5.1.4 Verify each ECCS pump develops the In accordance specified flow rate with the specified pump with the differential pressure. INSERVICE TESTING PROGRAM PUMP DIFFERENTIAL SYSTEM FLOW RATE PRESSURE LPCS 5010 gpm 290 psid LPCI 5050 gpm 113 psid HPCS 5010 gpm 363 psid (continued)

CLINTON 3.5-5 Amendment No. 238

ECCS Operating 3.5.1 SURVEILLANCE REQUIREMENTS (continued)

SURVEILLANCE FREQUENCY SR 3.5.1.5 -------------------NOTE--------------------

Vessel injection/spray may be excluded.

Verify each ECCS injection/spray subsystem In accordance actuates on an actual or simulated with the automatic initiation signal. Surveillance Frequency Control Program SR 3.5.1.6 -------------------NOTE--------------------

Valve actuation may be excluded.

Verify the ADS actuates on an actual or In accordance simulated automatic initiation signal. with the Surveillance Frequency Control Program SR 3.5.1.7 -------------------NOTE--------------------

Not required to be performed until 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> after reactor steam pressure and flow are adequate to perform the test.

Verify each ADS valve actuator strokes when In accordance manually actuated. with the Surveillance Frequency Control Program SR 3.5.1.8 -------------------NOTE--------------------

ECCS actuation instrumentation is excluded.

Verify the ECCS RESPONSE TIME for each ECCS In accordance injection/spray subsystem is within limits. with the Surveillance Frequency Control Program CLINTON 3.5-6 Amendment No. 238

RPV Water Inventory Control 3.5.2 3.5 EMERGENCY CORE COOLING SYSTEMS (ECCS), REACTOR PRESSURE VESSEL (RPV)

WATER INVENTORY CONTROL, AND REACTOR CORE ISOLATION COOLING (RCIC)

SYSTEM 3.5.2 RPV Water Inventory Control LCO 3.5.2 DRAIN TIME of RPV water inventory to the top of active fuel (TAF) shall be 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />.

AND One ECCS injection/spray subsystem shall be OPERABLE.


NOTE----------------------------

One low pressure coolant injection (LPCI) subsystem may be inoperable during alignment and operation for decay heat removal with reactor steam dome pressure less than the residual heat removal cut in permissive pressure.

APPLICABILITY: MODES 4 and 5.

ACTIONS CONDITION REQUIRED ACTION COMPLETION TIME A. Required ECCS A.1 Restore required ECCS 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> injection/spray injection/spray subsystem inoperable. subsystem to OPERABLE status.

B. Required Action and B.1 Initiate action to Immediately associated Completion establish a method of Time of Condition A water injection not met. capable of operating without offsite electrical power.

(continued)

CLINTON 3.5-7 Amendment No. 238

RPV Water Inventory Control 3.5.2 ACTIONS (continued)

CONDITION REQUIRED ACTION COMPLETION TIME C. DRAIN TIME < 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br /> C.1 Verify secondary 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> and 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />. containment boundary is capable of being established in less than the DRAIN TIME.

AND C.2 Verify each secondary 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> containment penetration flow path is capable of being isolated in less than the DRAIN TIME.

AND C.3 Verify one standby gas 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> treatment (SGT) subsystem is capable of being placed in operation in less than the DRAIN TIME.

(continued)

CLINTON 3.5-8 Amendment No. 238

RPV Water Inventory Control 3.5.2 ACTIONS (continued)

CONDITION REQUIRED ACTION COMPLETION TIME D. DRAIN TIME < 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />. D.1 ------- NOTE --------

Required ECCS injection/spray subsystem or additional method of water injection shall be capable of operating without offsite electrical power.

Initiate action to Immediately establish an additional method of water injection with water sources capable of maintaining RPV water level > TAF for 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />.

AND D.2 Initiate action to Immediately establish secondary containment boundary.

AND D.3 Initiate action to Immediately isolate each secondary containment penetration flow path or verify it can be automatically or manually isolated from the control room.

AND D.4 Initiate action to Immediately verify one SGT subsystem is capable of being placed in operation.

(continued)

CLINTON 3.5-9 Amendment No. 238

RPV Water Inventory Control 3.5.2 ACTIONS (continued)

CONDITION REQUIRED ACTION COMPLETION TIME E. Required Action and E.1 Initiate action to Immediately associated Completion restore DRAIN TIME to Time of Condition C 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />.

or D not met.

OR DRAIN TIME < 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />.

SURVEILLANCE REQUIREMENTS SURVEILLANCE FREQUENCY SR 3.5.2.1 Verify DRAIN TIME 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />. In accordance with the Surveillance Frequency Control Program SR 3.5.2.2 Verify, for a required low pressure ECCS In accordance injection/spray subsystem, the suppression with the pool water level is 12 ft 8 inches. Surveillance Frequency Control Program SR 3.5.2.3 Verify, for a required High Pressure Core In accordance Spray (HPCS) System, the: with the Surveillance

a. Suppression pool water level is Frequency 12 ft 8 inches; or Control Program
b. RCIC storage tank available water volume is 125,000 gal.

SR 3.5.2.4 Verify, for the required ECCS In accordance injection/spray subsystem, locations with the susceptible to gas accumulation are Surveillance sufficiently filled with water. Frequency Control Program (continued)

CLINTON 3.5-10 Amendment No. 238

RPV Water Inventory Control 3.5.2 SURVEILLANCE REQUIREMENTS (continued)

SURVEILLANCE FREQUENCY SR 3.5.2.5 --------------------NOTES------------------

1. Operation may be through the test return line.
2. Credit may be taken for normal system operation to satisfy this SR.

Operate the required ECCS injection/spray In accordance subsystem for 10 minutes. with the Surveillance Frequency Control Program SR 3.5.2.6 Verify each valve credited for In accordance automatically isolating a penetration flow with the path actuates to the isolation position on Surveillance an actual or simulated isolation signal. Frequency Control Program SR 3.5.2.7 -------------------NOTE--------------------

Vessel injection/spray may be excluded.

Verify the required ECCS injection/spray In accordance subsystem can be manually operated. with the Surveillance Frequency Control Program CLINTON 3.5-11 Amendment No. 238

RCIC System 3.5.3 3.5 EMERGENCY CORE COOLING SYSTEMS (ECCS), REACTOR PRESSURE VESSEL (RPV)

WATER INVENTORY CONTROL, AND REACTOR CORE ISOLATION COOLING (RCIC)

SYSTEM 3.5.3 RCIC System LCO 3.5.3 The RCIC System shall be OPERABLE.

APPLICABILITY: MODE 1, MODES 2 and 3 with reactor steam dome pressure > 150 psig.

ACTIONS


NOTE-------------------------------------

LCO 3.0.4.b is not applicable to RCIC.

CONDITION REQUIRED ACTION COMPLETION TIME A. RCIC System A.1 Verify by 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> inoperable. administrative means High Pressure Core Spray System is OPERABLE. 123 AND A.2 Restore RCIC System 14 days to OPERABLE status.

OR In accordance with the Risk Informed Completion Time Program B. Required Action and B.1 Be in MODE 3. 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> associated Completion Time not met. AND B.2 Reduce reactor steam 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br /> dome pressure to 150 psig.

CLINTON 3.5-12 Amendment No. 238

RCIC System 3.5.3 SURVEILLANCE REQUIREMENTS SURVEILLANCE FREQUENCY SR 3.5.3.1 Verify the RCIC System locations In accordance susceptible to gas accumulation are with the sufficiently filled with water. Surveillance Frequency Control Program SR 3.5.3.2 -------------------NOTE--------------------

Not required to be met for system vent flow paths opened under administrative control.

Verify each RCIC System manual, power In accordance operated, and automatic valve in the flow with the path, that is not locked, sealed, or Surveillance otherwise secured in position, is in the Frequency correct position. Control Program SR 3.5.3.3 -------------------NOTE--------------------

Not required to be performed until 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> after reactor steam pressure and flow are adequate to perform the test.

Verify, with RCIC steam supply pressure In accordance 1045 psig and 920 psig, the RCIC pump with the can develop a flow rate 600 gpm against a Surveillance system head corresponding to reactor Frequency pressure. Control Program SR 3.5.3.4 -------------------NOTE--------------------

Not required to be performed until 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> after reactor steam pressure and flow are adequate to perform the test.

Verify, with RCIC steam supply pressure In accordance 150 psig and 135 psig, the RCIC pump with the can develop a flow rate 600 gpm against a Surveillance system head corresponding to reactor Frequency pressure. Control Program (continued)

CLINTON 3.5-13 Amendment No. 238

RCIC System 3.5.3 SURVEILLANCE REQUIREMENTS (continued)

SURVEILLANCE FREQUENCY SR 3.5.3.5 -------------------NOTE--------------------

Vessel injection may be excluded.

Verify the RCIC System actuates on an In accordance actual or simulated automatic initiation with the signal. Surveillance Frequency Control Program CLINTON 3.5-14 Amendment No. 238

Primary Containment Air Locks 3.6.1.2 ACTIONS (continued)

CONDITION REQUIRED ACTION COMPLETION TIME C. One or more required C.1 Initiate action to Immediately primary containment evaluate primary air locks inoperable containment overall for reasons other than leakage rate per Condition A or B. LCO 3.6.1.1, using current air lock test results.

AND C.2 Verify a door is 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> closed in the affected air lock.

AND C.3 Restore air lock to 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> OPERABLE status.

OR


NOTE------

Not applicable if leakage exceeds limits or if loss of function.

In accordance with the Risk Informed Completion Time Program D. Required Action and D.1 Be in MODE 3. 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> associated Completion Time of Condition A, AND B, or C not met in MODE 1, 2, or 3. D.2 Be in MODE 4. 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br /> (continued)

CLINTON 3.6-6 Amendment No. 238

PCIVs 3.6.1.3 ACTIONS (continued)

CONDITION REQUIRED ACTION COMPLETION TIME A. One or more A.1 Isolate the affected 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> or in penetration flow paths penetration flow path accordance with with one PCIV by use of at least the Risk inoperable, except due one closed and de- Informed to leakage not within activated automatic Completion Time limit. valve, closed manual Program except valve, blind flange, for main steam or check valve with line and excess flow through the flow check valve secured. valves (EFCVs)

AND 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> or in accordance with the Risk Informed Completion Time Program for main steam line AND 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> or in accordance with the Risk Informed Completion Time Program for EFCVs AND (continued)

CLINTON 3.6-10 Amendment No. 238

PCIVs 3.6.1.3 ACTIONS CONDITION REQUIRED ACTION COMPLETION TIME A. (continued) A.2 --------NOTE---------

Isolation devices in high radiation areas may be verified by use of administrative means.

Verify the affected Once per penetration flow path 31 days is isolated. following isolation for isolation devices outside primary containment, drywell, and steam tunnel AND Prior to entering MODE 2 or 3 from MODE 4, if not performed within the previous 92 days, for isolation devices inside primary containment, drywell, or steam tunnel (continued)

CLINTON 3.6-11 Amendment No. 238

PCIVs 3.6.1.3 ACTIONS (continued)

CONDITION REQUIRED ACTION COMPLETION TIME D. One or more D.1 Isolate the affected 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> penetration flow paths penetration flow with one or more path by use of at OR primary containment least one closed and purge valves not de-activated In accordance within purge valve automatic valve, with the Risk leakage limits. closed manual valve, Informed or blind flange. Completion Time Program AND D.2 ---------NOTE--------

Isolation devices in high radiation areas may be verified by use of administrative means.

Verify the affected Once per 31 penetration flow path days following is isolated. isolation for isolation devices outside primary containment AND Prior to entering MODE 2 or 3 from MODE 4 if not performed within the previous 92 days for isolation devices inside primary containment AND (continued)

CLINTON 3.6-13 Amendment No. 238

PCIVs 3.6.1.3 ACTIONS CONDITION REQUIRED ACTION COMPLETION TIME D. (continued) D.3 Perform SR 3.6.1.3.5 Once per 92 for the resilient days following seal purge valves isolation closed to comply with Required Action D.1.

E. Required Action and E.1 Be in MODE 3. 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> associated Completion Time of Condition A, AND B, C, or D not met in MODE 1, 2, or 3. E.2 Be in MODE 4. 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br /> F. Required Action and F.1 --------NOTE---------

associated Completion LCO 3.0.3 is not Time of Condition A, applicable.

B, C, or D not met ---------------------

for PCIV(s) required to be OPERABLE during Suspend movement of Immediately movement of recently recently irradiated irradiated fuel fuel assemblies in assemblies in the primary and secondary primary or secondary containment.

containment.

CLINTON 3.6-14 Amendment No. 238

LLS Valves 3.6.1.6 3.6 CONTAINMENT SYSTEMS 3.6.1.6 Low-Low Set (LLS) Valves LCO 3.6.1.6 The LLS function of five safety/relief valves shall be OPERABLE.

APPLICABILITY: MODES 1, 2, and 3.

ACTIONS CONDITION REQUIRED ACTION COMPLETION TIME A. One LLS valve A.1 Restore LLS valve to 14 days inoperable. OPERABLE status.

OR In accordance with the Risk Informed Completion Time Program B. Required Action and ------------NOTE------------

associated Completion LCO 3.0.4.a is not Time of Condition A applicable when entering not met. MODE 3.

B.1 Be in MODE 3. 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> C. Two or more LLS valves C.1 Be in MODE 3. 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> inoperable.

AND C.2 Be in MODE 4. 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br /> CLINTON 3.6-22 Amendment No. 238

RHR Containment Spray System 3.6.1.7 3.6 CONTAINMENT SYSTEMS 3.6.1.7 Residual Heat Removal (RHR) Containment Spray System LCO 3.6.1.7 Two RHR containment spray subsystems shall be OPERABLE.


NOTE----------------------------

One RHR containment spray subsystem may be inoperable during alignment and operation for decay heat removal with reactor steam dome pressure less than the residual heat removal cut in permissive pressure.

APPLICABILITY: MODES 1, 2, and 3.

ACTIONS CONDITION REQUIRED ACTION COMPLETION TIME A. One RHR containment A.1 Restore RHR 7 days spray subsystem containment spray inoperable. subsystem to OPERABLE OR status.

In accordance with the Risk Informed Completion Time Program B. Two RHR containment B.1 Restore one RHR 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> spray subsystems containment spray inoperable. subsystem to OPERABLE status.

C. Required Action and ------------NOTE------------

associated Completion LCO 3.0.4.a is not Time not met. applicable when entering MODE 3.

C.1 Be in MODE 3. 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> CLINTON 3.6-24 Amendment No. 238

RHR Suppression Pool Cooling 3.6.2.3 3.6 CONTAINMENT SYSTEMS 3.6.2.3 Residual Heat Removal (RHR) Suppression Pool Cooling LCO 3.6.2.3 Two RHR suppression pool cooling subsystems shall be OPERABLE.


NOTE----------------------------

One RHR suppression pool cooling subsystem may be inoperable during alignment and operation for decay heat removal with reactor steam dome pressure less than the residual heat removal cut in permissive pressure.

APPLICABILITY: MODES 1, 2, and 3.

ACTIONS CONDITION REQUIRED ACTION COMPLETION TIME A. One RHR suppression A.1 Restore RHR 7 days pool cooling subsystem suppression pool inoperable. cooling subsystem to OR OPERABLE status.

In accordance with the Risk Informed Completion Time Program B. Required Action and ------------NOTE------------

associated Completion LCO 3.0.4.a is not Time of Condition A applicable when entering not met. MODE 3.

B.1 Be in MODE 3. 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> C. Two RHR suppression C.1 Be in MODE 3. 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> pool cooling subsystems inoperable. AND C.2 Be in MODE 4. 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br /> CLINTON 3.6-32 Amendment No. 238

SPMU System 3.6.2.4 3.6 CONTAINMENT SYSTEMS 3.6.2.4 Suppression Pool Makeup (SPMU) System LCO 3.6.2.4 Two SPMU subsystems shall be OPERABLE.

APPLICABILITY: MODES 1, 2, and 3.

ACTIONS CONDITION REQUIRED ACTION COMPLETION TIME A. Combined upper A.1 Restore upper 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> containment pool and containment pool and suppression pool water suppression pool water levels not within levels to within limit.

limit.

B. Upper containment pool B.1 Restore upper 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> water temperature not containment pool water within limit. temperature to within limit.

C. One SPMU subsystem C.1 Restore SPMU subsystem 7 days inoperable for reasons to OPERABLE status.

other than Condition A OR or B.

In accordance with the Risk Informed Completion Time Program D. Required Action and D.1 Be in MODE 3. 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> associated Completion Time not met. AND D.2 Be in MODE 4. 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br /> CLINTON 3.6-34 Amendment No. 238

Drywell Air Lock 3.6.5.2 ACTIONS (continued)

CONDITION REQUIRED ACTION COMPLETION TIME C. Drywell air lock C.1 Verify a door is 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> inoperable for reasons closed.

other than Condition A or B. AND C.2 Restore air lock to 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> OPERABLE status.

OR


NOTE------

Not applicable if leakage exceeds limits or if loss of function.

In accordance with the Risk Informed Completion Time Program D. Required Action and D.1 Be in MODE 3. 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> associated Completion Time not met. AND D.2 Be in MODE 4. 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br /> CLINTON 3.6-59 Amendment No. 238

Drywell Isolation Valves 3.6.5.3 ACTIONS (continued)

CONDITION REQUIRED ACTION COMPLETION TIME A. One or more A.1 Isolate the affected 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> penetration flow paths penetration flow path with one required by use of at least OR drywell isolation one closed and de-valve inoperable. activated automatic In accordance valve, closed manual with the Risk valve, blind flange, Informed or check valve with Completion Time flow through the Program valve secured.

AND A.2 --------NOTE---------

Isolation devices in high radiation areas may be verified by use of administrative means.

Verify the affected Prior to penetration flow path entering MODE 2 is isolated. or 3 from MODE 4, if not performed within the previous 92 days (continued)

CLINTON 3.6-62 Amendment No. 238

Division 1 and 2 SX Subsystems and UHS 3.7.1 3.7 PLANT SYSTEMS 3.7.1 Division 1 and 2 Shutdown Service Water (SX) Subsystems and Ultimate Heat Sink (UHS)

LCO 3.7.1 Division 1 and 2 SX subsystems and the UHS shall be OPERABLE.

APPLICABILITY: MODES 1, 2, and 3.

ACTIONS CONDITION REQUIRED ACTION COMPLETION TIME A. UHS water volume not A.1 Restore UHS water 90 days within limit volume to within limit.


NOTE----------- ------------NOTES------------

Not applicable during 1. Enter applicable replacement of Conditions and Required Division 2 SX pump Actions of LCO 3.8.1, during the Division 2 "AC Sources -Operating,"

SX system outage for diesel generator made window from October 26 inoperable by SX.

through November 8, 2015. 2. Enter applicable


Conditions and Required Actions of LCO 3.4.9, B. Division 1 or 2 SX "Residual Heat Removal subsystem inoperable. (RHR) Shutdown Cooling System - Hot Shutdown,"

for RHR shutdown cooling subsystem made inoperable by SX.

B.1 Restore SX subsystem 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> to OPERABLE status.

OR In accordance with the Risk Informed Completion Time Program (continued)

CLINTON 3.7-1 Amendment No. 238

Main Turbine Bypass 3.7.6 3.7 PLANT SYSTEMS 3.7.6 Main Turbine Bypass System LCO 3.7.6 The Main Turbine Bypass System shall be OPERABLE.

OR The following limits are made applicable:

a. Reactor THERMAL POWER limit for an inoperable Main Turbine Bypass System as specified in the COLR; and
b. LCS 3.2.2, "MINIMUM CRITICAL POWER RATIO (MCPR)," limit for an inoperable Main Turbine Bypass System as specified in the COLR; and
c. LCO 3.2.3, "LINEAR HEAT GENERATION RATE (LHGR)," limit for an inoperable Main Turbine Bypass System as specified in the COLR.

APPLICABILITY: THERMAL POWER 21.6% RTP.

ACTIONS CONDITION REQUIRED ACTION COMPLETION TIME A. Requirements of the A.1 Satisfy the 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> LCO not met. requirements of the LCO. OR In accordance with the Risk Informed Completion Time Program B. Required Action and B.1 Reduce THERMAL POWER 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> associated Completion to < 21.6% RTP.

Time not met.

CLINTON 3.7-13 Amendment No. 238

Main Turbine Bypass System 3.7.6 SURVEILLANCE REQUIREMENTS SURVEILLANCE FREQUENCY SR 3.7.6.1 Verify one complete cycle of each main In accordance turbine bypass valve. with the Surveillance Frequency Control Program SR 3.7.6.2 Perform a system functional test. In accordance with the Surveillance Frequency Control Program SR 3.7.6.3 Verify the TURBINE BYPASS SYSTEM RESPONSE In accordance TIME is within limits. with the Surveillance Frequency Control Program CLINTON 3.7-14 Amendment No. 238

AC Sources Operating 3.8.1 3.8 ELECTRICAL POWER SYSTEMS 3.8.1 AC Sources Operating LCO 3.8.1 The following AC electrical power sources shall be OPERABLE:

a. Two qualified circuits between the offsite transmission network and the onsite Class 1E AC Electric Power Distribution System; and
b. Three diesel generators (DGs).

APPLICABILITY: MODES 1, 2, and 3.


NOTE----------------------------

Division 3 AC electrical power sources are not required to be OPERABLE when High Pressure Core Spray System is inoperable.

ACTIONS


NOTE-------------------------------------

LCO 3.0.4.b is not applicable to DGs.

CONDITION REQUIRED ACTION COMPLETION TIME A. One offsite circuit A.1 Perform SR 3.8.1.1 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> inoperable. for OPERABLE offsite circuit. AND Once per 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> thereafter AND A.2 Restore offsite 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> circuit to OPERABLE status. OR In accordance with the Risk Informed Completion Time Program (continued)

CLINTON 3.8-1 Amendment No. 238

AC Sources Operating 3.8.1 ACTIONS (continued)

CONDITION REQUIRED ACTION COMPLETION TIME B. One required DG B.1 Perform SR 3.8.1.1 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> inoperable. for OPERABLE offsite circuit(s). AND Once per 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> thereafter AND B.2 Declare required 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> from feature(s), supported discovery of by the inoperable DG, Condition B inoperable when the concurrent with redundant required inoperability of feature(s) are redundant inoperable. required feature(s)

AND B.3.1 Determine OPERABLE 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> DG(s) are not inoperable due to common cause failure.

OR B.3.2 Perform SR 3.8.1.2 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> for OPERABLE DG(s).

AND (continued)

CLINTON 3.8-2 Amendment No. 238

AC Sources Operating 3.8.1 ACTIONS CONDITION REQUIRED ACTION COMPLETION TIME B. (continued) B.4 Restore required DG 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> or in to OPERABLE status. accordance with the Risk Informed Completion Time Program from discovery of an inoperable Division 3 DG AND 14 days or in accordance with the Risk Informed Completion Time Program C. Two offsite circuits C.1 Declare required 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> from inoperable. feature(s) inoperable discovery of when the redundant Condition C required feature(s) concurrent with are inoperable. inoperability of redundant required feature(s)

AND C.2 Restore one offsite 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> circuit to OPERABLE status. OR In accordance with the Risk Informed Completion Time Program (continued)

CLINTON 3.8-3 Amendment No. 238

AC Sources Operating 3.8.1 ACTIONS (continued)

CONDITION REQUIRED ACTION COMPLETION TIME D. One offsite circuit D.1 Restore offsite 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> inoperable. circuit to OPERABLE status. OR AND In accordance One required DG with the Risk inoperable. Informed Completion Time Program OR D.2 Restore required DG 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> to OPERABLE status.

OR In accordance with the Risk Informed Completion Time Program E. Two required DGs E.1 Restore one required 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> inoperable. DG to OPERABLE status. OR 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> if Division 3 DG is inoperable F. Required Action and -------------NOTE------------

Associated Completion LCO 3.0.4.a is not applicable Time of Condition A, when entering MODE 3.

B, C, D, or E not met. -----------------------------

F.1 Be in MODE 3. 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> G. Three or more required G.1 Enter LCO 3.0.3. Immediately AC sources inoperable.

CLINTON 3.8-4 Amendment No. 238

AC Sources Operating 3.8.1 SURVEILLANCE REQUIREMENTS SURVEILLANCE FREQUENCY SR 3.8.1.1 Verify correct breaker alignment and In accordance indicated power availability for each with the offsite circuit. Surveillance Frequency Control Program SR 3.8.1.2 -------------------NOTES-------------------

1. Performance of SR 3.8.1.7 satisfies this SR.
2. All DG starts may be preceded by an engine prelube period and followed by a warmup period prior to loading.
3. A modified DG start involving idling and gradual acceleration to synchronous speed may be used for this SR as recommended by the manufacturer.

When modified start procedures are not used, the time, voltage, and frequency tolerances of SR 3.8.1.7 must be met.

Verify each DG starts from standby In accordance conditions and achieves steady state with the voltage 4084 V and 4300 V and frequency Surveillance 58.8 Hz and 61.2 Hz. Frequency Control Program SR 3.8.1.3 -------------------NOTES-------------------

1. DG loadings may include gradual loading as recommended by the manufacturer.
2. Momentary transients outside the load range do not invalidate this test.
3. This Surveillance shall be conducted on only one DG at a time.
4. This SR shall be preceded by, and immediately follow, without shutdown, a successful performance of SR 3.8.1.2 or SR 3.8.1.7.

Verify each DG operates for 60 minutes at In accordance a load 3482 kW for DG 1A, 3488 kW for with the Surveillance DG 1B, and 1980 kW for DG 1C. Frequency Control Program (continued)

CLINTON 3.8-5 Amendment No. 238

AC Sources Operating 3.8.1 SURVEILLANCE REQUIREMENTS (continued)

SURVEILLANCE FREQUENCY SR 3.8.1.4 Verify each day tank contains 385 gal of In accordance fuel oil for DG 1A and DG 1B and 240 gal with the for DG 1C. Surveillance Frequency Control Program SR 3.8.1.5 Check for and remove accumulated water from In accordance each day tank. with the Surveillance Frequency Control Program SR 3.8.1.6 Verify the fuel oil transfer system In accordance operates to automatically transfer fuel oil with the from the storage tank to the day tank. Surveillance Frequency Control Program SR 3.8.1.7 -------------------NOTE-------------------

All DG starts may be preceded by an engine prelube period.

Verify each DG starts from standby In accordance condition and achieves: with the Surveillance

a. In 12 seconds, voltage 4084 V and Frequency frequency 58.8 Hz; and Control Program
b. Steady state voltage 4084 V and 4300 V and frequency 58.8 Hz and 61.2 Hz.

(continued)

CLINTON 3.8-6 Amendment No. 238

AC Sources Operating 3.8.1 SURVEILLANCE REQUIREMENTS (continued)

SURVEILLANCE FREQUENCY SR 3.8.1.8 ------------------NOTE--------------------

This Surveillance shall not be performed in MODE 1 or 2 (not applicable to Division 3 AC sources). However, credit may be taken for unplanned events that satisfy this SR.

Verify automatic and manual transfer of In accordance unit power supply from the normal offsite with the circuit to the alternate offsite circuit. Surveillance Frequency Control Program SR 3.8.1.9 -------------------NOTE--------------------

1. Credit may be taken for unplanned events that satisfy this SR.
2. If performed with DG synchronized with offsite power, it shall be performed at a power factor < 0.9.

Verify each DG rejects a load greater than In accordance or equal to its associated single largest with the post accident load and following load Surveillance rejection, the engine speed is maintained Frequency less than nominal plus 75% of the Control Program difference between nominal speed and the overspeed trip setpoint or 15% above nominal, whichever is lower.

SR 3.8.1.10 -------------------NOTE--------------------

Credit may be taken for unplanned events that satisfy this SR.

Verify each DG operating at a power factor In accordance 0.9 does not trip and voltage is with the maintained 5000 V for DG 1A and DG 1B and Surveillance Frequency 5824 V for DG 1C during and following a Control Program load rejection of a load 3482 kW for DG 1A, 3488 kW for DG 1B, and 1980 kW for DG 1C.

(continued)

CLINTON 3.8-7 Amendment No. 238

DC Sources-Operating 3.8.4 3.8 ELECTRICAL POWER SYSTEMS 3.8.4 DC Sources Operating LCO 3.8.4 The Division 1, Division 2, Division 3, and Division 4 DC electrical power subsystems shall be OPERABLE.

APPLICABILITY: MODES 1, 2, and 3.

ACTIONS CONDITION REQUIRED ACTION COMPLETION TIME A. One battery charger on A.1 Restore battery 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> Division 1 or 2 terminal voltage to inoperable. greater than or equal to the minimum established float voltage.

AND A.2 Verify battery float Once per 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> current < 2 amps.

AND A.3 Restore battery 7 days charger to OPERABLE status. OR In accordance with the Risk Informed Completion Time Program B. One battery on B.1 Restore battery to 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> Division 1 or 2 OPERABLE status.

inoperable. OR In accordance with the Risk Informed Completion Time Program (continued)

CLINTON 3.8-24 Amendment No. 238

DC Sources-Operating 3.8.4 ACTIONS (continued)

CONDITION REQUIRED ACTION COMPLETION TIME C. Division 1 or 2 DC C.1 Restore Division 1 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> electrical power and 2 DC electrical subsystem inoperable power subsystems to OR for reasons other than OPERABLE status.

Condition A or B. In accordance with the Risk Informed Completion Time Program D. Required Action and -------------NOTE------------

associated Completion LCO 3.0.4.a is not Time for Condition A, applicable when entering B, or C not met. MODE 3.

D.1 Be in MODE 3. 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> E. Division 3 or 4 DC E.1 Declare High Pressure Immediately electrical power Core Spray System subsystem inoperable. inoperable.

F. Required Action and F.1 Be in MODE 3. 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> associated Completion Time for Condition E AND not met.

F.2 Be in MODE 4. 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br /> CLINTON 3.8-24a Amendment No. 238

Inverters-Operating 3.8.7 3.8 ELECTRICAL POWER SYSTEMS 3.8.7 Inverters Operating LCO 3.8.7 The Division 1, 2, 3, and 4 inverters, and A and B RPS solenoid bus inverters shall be OPERABLE.

APPLICABILITY: MODES 1, 2, and 3.

ACTIONS


NOTE-------------------------------------

Enter applicable Conditions and Required Actions of LCO 3.8.9, "Distribution Systems Operating," with any uninterruptible AC bus de-energized.

CONDITION REQUIRED ACTION COMPLETION TIME A. Division 1 or 2 A.1 Restore Division 1 7 days inverter inoperable. and 2 inverters to OPERABLE status. OR In accordance with the Risk Informed Completion Time Program B. Required Action and -------------NOTE------------

associated Completion LCO 3.0.4.a is not Applicable Time of Condition A when entering MODE 3.

not met. -----------------------------

B.1 Be in MODE 3. 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> C. One or more Division 3 C.1 Declare High Pressure Immediately or 4 inverters Core Spray System inoperable. inoperable.

(continued)

CLINTON 3.8-34 Amendment No. 238

Inverters-Operating 3.8.7 ACTIONS (continued)

CONDITION REQUIRED ACTION COMPLETION TIME D. One RPS solenoid bus D.1.1 Transfer RPS bus to 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> inverter inoperable. alternate power source.

AND D.1.2 Verify RPS bus supply Once per 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> frequency 57 Hz. thereafter OR 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> D.2 De-energize RPS bus.

E. Both RPS solenoid bus E.1 De-energize one RPS 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> inverters inoperable. solenoid bus.

F. Required Action and F.1 Be in MODE 3. 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> associated Completion Time for Condition C, AND D, or E not met.

F.2 Be in MODE 4. 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br /> SURVEILLANCE REQUIREMENTS SURVEILLANCE FREQUENCY SR 3.8.7.1 Verify correct inverter voltage, frequency, In accordance and alignment to required uninterruptible with the AC buses and RPS solenoid buses. Surveillance Frequency Control Program CLINTON 3.8-35 Amendment No. 238

Distribution Systems-Operating 3.8.9 3.8 ELECTRICAL POWER SYSTEMS 3.8.9 Distribution Systems Operating LCO 3.8.9 Division 1, 2, and 3 AC, Division 1, 2, 3, and 4 DC, and Division 1, 2, 3, and 4 uninterruptible AC bus electrical power distribution subsystems shall be OPERABLE.

APPLICABILITY: MODES 1, 2, and 3.


NOTE----------------------------

Division 3 and 4 electrical power distribution subsystems are not required to be OPERABLE when High Pressure Core Spray System is inoperable.

ACTIONS CONDITION REQUIRED ACTION COMPLETION TIME A. One or more Division 1 A.1 Restore Division 1 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> or 2 AC electrical and 2 AC electrical power distribution power distribution OR subsystems inoperable. subsystems to OPERABLE status. -----NOTE------

Not applicable if loss of function.

In accordance with the Risk Informed Completion Time Program (continued)

CLINTON 3.8-39 Amendment No. 238

Distribution Systems-Operating 3.8.9 ACTIONS (continued)

CONDITION REQUIRED ACTION COMPLETION TIME B. One or more Division 1 B.1 Restore Division 1 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> or 2 uninterruptible and 2 uninterruptible AC bus distribution AC bus distribution OR subsystems inoperable. subsystems to OPERABLE status. -----NOTE------

Not applicable if loss of function.

In accordance with the Risk Informed Completion Time Program C. One or more Division 1 C.1 Restore Division 1 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> or 2 DC electrical and 2 DC electrical power distribution power distribution OR subsystems inoperable. subsystems to OPERABLE status. -----NOTE------

Not applicable if loss of function.

In accordance with the Risk Informed Completion Time Program D. Required Action and -------------NOTE------------

associated Completion LCO 3.0.4.a is not applicable Time of Condition A, when entering MODE 3.

B, or C not met. -----------------------------

D.1 Be in MODE 3. 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> E. One or more Division 3 E.1 Declare High Pressure Immediately or 4 AC, DC, or Core Spray System uninterruptible AC bus inoperable.

electrical power distribution subsystems inoperable.

(continued)

CLINTON 3.8-40 Amendment No. 238

Distribution Systems-Operating 3.8.9 ACTIONS (continued)

CONDITION REQUIRED ACTION COMPLETION TIME F. Two or more divisions F.1 Enter LCO 3.0.3. Immediately with inoperable distribution subsystems that result in a loss of function.

SURVEILLANCE REQUIREMENTS SURVEILLANCE FREQUENCY SR 3.8.9.1 Verify correct breaker alignments and In accordance voltage to required AC, DC, and with the uninterruptible AC bus electrical power Surveillance distribution subsystems. Frequency Control Program CLINTON 3.8-41 Amendment No. 238

Programs and Manuals 5.5 5.5 Programs and Manuals (continued) 5.5.15 Control Room Envelope Habitability Program (continued)

d. Measurement, at designated locations, of the CRE pressure relative to all external areas adjacent to the CRE boundary during the pressurization mode of operation by one subsystem of the Control Room Ventilation System, operating at the flow rate required by the VFTP, at a Frequency of 24 months on a STAGGERED TEST BASIS. The results shall be trended and used as a part of the 24 month assessment of the CRE boundary.
e. The quantitative limits on unfiltered air inleakage into the CRE. These limits shall be stated in a manner to allow direct comparison to the unfiltered air inleakage measured by the testing described in paragraph c. The unfiltered air inleakage limit for radiological challenges is the inleakage flow rate assumed in the licensing basis analyses of DBA consequences. Unfiltered air inleakage limits for hazardous chemicals must ensure that exposure of CRE occupants to these hazards will be within the assumptions in the licensing basis.
f. The provisions of SR 3.0.2 are applicable to the Frequencies for assessing CRE habitability, determining CRE unfiltered inleakage, and measuring CRE pressure and assessing the CRE boundary as required by paragraph c and d, respectively.

5.5.16 Surveillance Frequency Control Program This program provides controls for Surveillance Frequencies. The program shall ensure that Surveillance Requirements specified in the Technical Specifications are performed at intervals sufficient to assure the associated Limiting Conditions for Operation are met.

a. The Surveillance Frequency Control Program shall contain a list of Frequencies of those Surveillance Requirements for which the Frequency is controlled by the program.
b. Changes to the Frequencies listed in the Surveillance Frequency Control Program shall be made in accordance with NEI 04-10, Risk-Informed Method for control of Surveillance Frequencies, Revision 1.
c. The provisions of Surveillance Requirements 3.0.2 and 3.0.3 are applicable to the Frequencies established in the Surveillance Frequency Control Program.

(continued)

CLINTON 5.0-16c Amendment No. 238

Programs and Manuals 5.5 5.5 Programs and Manuals (continued) 5.5.17 Risk Informed Completion Time Program This program provides controls to calculate a Risk Informed Completion Time (RICT) and must be implemented in accordance with NEI 06-09-A, Revision 0, "Risk-Managed Technical Specifications (RMTS) Guidelines." The program shall include the following:

a. The RICT may not exceed 30 days;
b. A RICT may only be utilized in MODE 1 and 2;
c. When a RICT is being used, any change to the plant configuration, as defined in NEI 06-09-A, Appendix A, must be considered for the effect on the RICT.
1. For planned changes, the revised RICT must be determined prior to implementation of the change in configuration.
2. For emergent conditions, the revised RICT must be determined within the time limits of the Required Action Completion Time (i.e., not the RICT) or 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> after the plant configuration change, whichever is less.
3. Revising the RICT is not required if the plant configuration change would lower plant risk and would result in a longer RICT.
d. For emergent conditions, if the extent of condition evaluation for inoperable structures, systems, or components (SSCs) is not complete prior to exceeding the Completion Time, the RICT shall account for the increased possibility of common cause failure (CCF) by either:
1. Numerically accounting for the increased possibility of CCF in the RICT calculation; or
2. Risk Management Actions (RMAs) not already credited in the RICT calculation shall be implemented that support redundant or diverse SSCs that perform the function(s) of the inoperable SSCs, and, if practicable, reduce the frequency of initiating events that challenge the function(s) performed by the inoperable SSCs.
e. The risk assessment approaches and methods shall be acceptable to the NRC. The plant PRA shall be based on the as-built, as-operated, and maintained plant; and reflect the operating experience at the plant, as specified in Regulatory Guide 1.200, Revision 2. Methods to assess the risk from extending the Completion Times must be PRA methods used to support this license amendment, or other methods approved by the NRC for generic use; and any change in the PRA methods to assess risk that are outside these approval boundaries require prior NRC approval.

CLINTON 5.0-17 Amendment No. 238

Reporting Requirements 5.6 5.0 ADMINISTRATIVE CONTROLS 5.6 Reporting Requirements The following reports shall be submitted in accordance with 10 CFR 50.4.

5.6.1 Deleted 5.6.2 Annual Radiological Environmental Operating Report The Annual Radiological Environmental Operating Report covering the operation of the unit during the previous calendar year shall be submitted by May 1 of each year. The report shall include summaries, interpretations, and analyses of trends of the results of the Radiological Environmental Monitoring Program for the reporting period. The material provided shall be consistent with the objectives outlined in the Offsite Dose Calculation Manual (ODCM), and in 10 CFR 50, Appendix I, Sections IV.B.2, IV.B.3, and IV.C.

The Annual Radiological Environmental Operating Report shall include the results of analyses of all radiological environmental samples and of all environmental radiation measurements taken during the period pursuant to the locations specified in the table and figures in the ODCM, as well as summarized and tabulated results of these analyses and measurements in the format of the table in the Radiological Assessment Branch Technical Position, Revision 1, November 1979. In the event that some individual results are not available for inclusion with the report, the report shall be submitted noting and explaining the reasons for the missing results. The missing data shall be submitted in a supplementary report as soon as possible.

5.6.3 Radioactive Effluent Release Report The Radioactive Effluent Release Report covering the operation of the unit during the previous calendar year shall be submitted by May 1 of each year. The report shall include a summary of the quantities of radioactive liquid and gaseous effluents and solid waste released from the unit. The material provided shall be consistent with the objectives outlined in the ODCM and process control program and in conformance with 10 CFR 50.36a and 10 CFR 50, Appendix I, Section IV.B.1.

5.6.4 Deleted (continued)

CLINTON 5.0-18 Amendment No. 238

Reporting Requirements 5.6 5.6 Reporting Requirements (continued) 5.6.5 CORE OPERATING LIMITS REPORT (COLR)

a. Core operating limits shall be established prior to each reload cycle, or prior to any remaining portion of a reload cycle, and shall be documented in the COLR for the following:
1. LCO 3.2.1, Average Planar Linear Heat Generation Rate (APLHGR),
2. LCO 3.2.2, Minimum Critical Power Ratio (MCPR) and MCPR99.9%,
3. LCO 3.2.3, Linear Heat Generation Rate (LHGR),
4. LCO 3.3.1.1, RPS Instrumentation (SR 3.3.1.1.14),
5. LCO 3.3.1.3, Oscillation Power Range Monitor (OPRM)

Instrumentation, and

6. LCO 3.7.6, Main Turbine Bypass System, (cycle dependent thermal power limits for an inoperable Main Turbine Bypass System).
b. The analytical methods used to determine the core operating limits shall be those previously reviewed and approved by the NRC in (1) General Electric Standard Application for Reactor Fuel (GESTAR), NEDE-24011-P-A, or (2) NEDO-32465, "BWR Owners' Group Reactor Stability Detect and Suppress Solutions Licensing Basis Methodology and Reload Applications."
c. The core operating limits shall be determined such that all applicable limits (e.g., fuel thermal mechanical limits, core thermal hydraulic limits, Emergency Core Cooling Systems (ECCS) limits, nuclear limits such as SDM, transient analysis limits, and accident analysis limits) of the safety analysis are met.
d. The COLR, including any midcycle revisions or supplements, shall be provided upon issuance for each reload cycle to the NRC.

CLINTON 5.0-19 Amendment No. 238

SAFETY EVALUATION BY THE OFFICE OF NUCLEAR REACTOR REGULATION RELATED TO AMENDMENT NO. 238 TO FACILITY OPERATING LICENSE NO. NPF-62 EXELON GENERATION COMPANY, LLC CLINTON POWER STATION, UNIT NO. 1 DOCKET NO. 50-461

1.0 INTRODUCTION

By application dated April 30, 2020 (Reference 1), as supplemented by letters dated November 24, 2020 (Reference 2), and March 23, 2021 (Reference 3), Exelon Generation Company, LLC (Exelon, the licensee) submitted a license amendment request (LAR) for Clinton Power Station, Unit 1 (CPS).

The amendment would revise technical specification (TS) requirements to permit the use of risk-informed completion times (RICTs) for actions to be taken when limiting conditions for operation (LCOs) are not met. The proposed changes are based on Technical Specifications Task Force (TSTF) Traveler TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b, dated July 2, 2018 (Reference 4). The U.S. Nuclear Regulatory Commission (NRC or Commission) issued a final model safety evaluation (SE) approving TSTF-505, Revision 2, on November 21, 2018 (Reference 5).

The supplemental letters dated November 24, 2020, and March 23, 2021, provided additional information that clarified the application, did not expand the scope of the application as originally noticed, and did not change the NRC staffs original proposed no significant hazards consideration determination as published in the Federal Register (FR) on June 16, 2020 (85 FR 36435).

2.0 REGULATORY EVALUATION

2.1 Description of Risk-Informed Completion Time Program The TS LCOs are the lowest functional capability or performance levels of equipment required for safe operation of the facility. When an LCO is not met, the licensee must shut down the reactor or follow any remedial or required action (e.g., testing, maintenance, or repair activity) permitted by the TSs until the condition can be met. The remedial actions (i.e., ACTIONS) associated with an LCO contain Conditions that typically describe the ways in which the

requirements of the LCO can fail to be met. Specified with each stated Condition are Required Action(s) and Completion Times (CTs). The CTs are referred to as the front stops in the context of this SE. For certain Conditions, the TS require exiting the Mode of Applicability of an LCO (i.e., shut down the reactor).

Topical Report (TR) Nuclear Energy Institute (NEI) 06-09-A, Risk-Informed Technical Specifications Initiative 4b: Risk-Managed Technical Specifications (RMTS), October 2012, Revision 0 (Reference 6) provides a methodology for extending existing CTs and, thereby, delay exiting the operational mode of applicability or taking Required Actions if risk is assessed and managed within the limits and programmatic requirements established by a RICT program.

2.2 Description of TS Changes The licensees letter dated April 30, 2020, submittal, requested approval to add a RICT program to the Administrative Controls section of the TS, and modify selected CTs to permit extending the CTs, provided risk is assessed and managed as described in NEI 06-09-A. The licensees application for the changes proposed to use NEI 06-09-A and included documentation regarding the technical adequacy of the probabilistic risk assessment (PRA) models for the RICT program, consistent with the guidance of Regulatory Guide (RG) 1.200, Revision 2, An Approach for Determining the Technical Adequacy of Probabilistic Risk Assessment Results for Risk-Informed Activities, March 2009 (Reference 7).

2.2.1 TS 1.0 Use and Application Example 1.3-8, would be added to TS 1.3, CTs, and reads as follows:

EXAMPLE 1.3-8 ACTIONS CONDITION REQUIRED ACTION COMPLETION TIME A. One A.1 Restore subsystem 7 days subsystem to OPERABLE inoperable. status. OR In accordance with the Risk Informed Completion Time Program B. Required B.1 Be in MODE 3. 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> Action and associated AND Completion Time not B.2 Be in MODE 5. 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br /> met.

When a subsystem is declared inoperable, Condition A is entered.

The 7-day Completion Time may be applied as discussed in Example 1.3-2. However, the licensee may elect to apply the Risk Informed Completion Time Program, which permits calculation of

a Risk Informed Completion Time (RICT), that may be used to complete the Required Action beyond the 7-day Completion Time.

The RICT cannot exceed 30 days. After the 7-day Completion Time has expired, the subsystem must be restored to OPERABLE status within the RICT or Condition B must also be entered.

The Risk Informed Completion Time Program requires recalculation of the RICT to reflect changing plant conditions. For planned changes, the revised RICT must be determined prior to implementation of the change in configuration. For emergent conditions, the revised RICT must be determined within the time limits of the Required Action Completion Time (i.e., not the RICT) or 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> after the plant configuration change, whichever is less.

If the 7-day Completion Time clock of Condition A has expired and subsequent changes in plant condition result in exiting the applicability of the Risk Informed Completion Time Program without restoring the inoperable subsystem to OPERABLE status, Condition B, is also entered and the Completion Time clocks for Required Actions B.1 and B.2 start.

If the RICT expires or is recalculated to be less than the elapsed time since the Condition was entered, and the inoperable subsystem has not been restored to OPERABLE status, Condition B is also entered and the Completion Time clocks for Required Actions B.1 and B.2 start. If the inoperable subsystems are restored to OPERABLE status after Condition B is entered, Condition A is exited and, therefore, the required actions of Condition B may be terminated.

2.2.2 TS 5.5.17 RICT program TS 5.5.17, which describes the RICT program, would be added to the TS and reads as follows:

Risk-Informed Completion Time Program This program provides controls to calculate a Risk Informed Completion Time (RICT) and must be implemented in accordance with NEI 06-09-A, Revision 0, Risk-Managed Technical Specifications (RMTS) Guidelines. The program shall include the following:

a. The RICT may not exceed 30 days;
b. A RICT may only be utilized in MODE 1 and 2;
c. When a RICT is being used, any change to the plant configuration, as defined in NEI 06-09-A, Appendix A, must be considered for the effect on the RICT.
1. For planned changes, the revised RICT must be determined prior to implementation of the change in configuration.
2. For emergent conditions, the revised RICT must be determined within the time limits of the Required Action Completion Time (i.e., not the RICT) or 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> after the plant configuration change, whichever is less.
3. Revising the RICT is not required if the plant configuration change would lower plant risk and would result in a longer RICT.
d. For emergent conditions, if the extent of condition evaluation for inoperable structures, systems, or components (SSCs) is not complete prior to exceeding the Completion Time, the RICT shall account for the increased possibility of common cause failure (CCF) by either:
1. Numerically accounting for the increased possibility of CCF in the RICT calculation; or
2. Risk Management Actions (RMAs) not already credited in the RICT calculation shall be implemented that support redundant or diverse SSCs that perform the function(s) of the inoperable SSCs, and, if practicable, reduce the frequency of initiating events that challenge the function(s) performed by the inoperable SSCs.
e. The risk assessment approaches and methods shall be acceptable to the NRC. The plant PRA shall be based on the as-built, as-operated, and maintained plant; and reflect the operating experience at the plant, as specified in Regulatory Guide 1.200, Revision 2. Methods to assess the risk from extending the Completion Times must be PRA methods used to support this license amendment, or other methods approved by the NRC for generic use; and any change in the PRA methods to assess risk that are outside these approval boundaries require prior NRC approval.

2.2.3 Application of the RICT Program to Existing LCOs and Conditions The typical CT is modified by the application of the RICT program as shown in the following example. The changed portion is indicated in italics.

ACTIONS CONDITION REQUIRED ACTION COMPLETION TIME A. One subsystem A.1 Restore subsystem 7 days inoperable. to OPERABLE status. OR In accordance with the Risk Informed Completion Time Program Where necessary, conforming changes are made to CTs to make them accurate following use of a RICT. For example, most TSs have requirements to close/isolate containment isolation devices if one or more containment penetrations have inoperable devices. This is followed by a requirement to periodically verify the penetration is isolated. By adding the flexibility to use a RICT to determine a time to isolate the penetration, the periodic verifications must then be based on the time following isolation.

Individual LCO Required Actions and CTs modified by the proposed change are identified below. The changed portion is indicated in italics.

LCO 3.1.7 Two SLC [standby liquid control] subsystems shall be OPERABLE.

CONDITION REQUIRED ACTION COMPLETION TIME A. One SLC subsystem A.1 Restore SLC 7 days inoperable. subsystem to OPERABLE status. OR In accordance with the Risk Informed Completion Time Program

LCO 3.3.1.1 The RPS [reactor protection system] instrumentation for each Function in Table 3.3.1.1-1 shall be OPERABLE.

CONDITION REQUIRED ACTION COMPLETION TIME A. One or more A.1 Place one channel 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br /> Functions with one in affected channel inoperable. Function in trip. OR In accordance with the Risk Informed Completion Time Program B. One or more B.1 Place one channel 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> Functions with two in affected channels inoperable. Function in trip. OR In accordance with the Risk Informed Completion Time Program LCO 3.3.4.1 Four channels for each EOC-RPT [end of cycle - recirculation pump trip]

instrumentation Function listed below shall be OPERABLE:

a. Turbine Stop Valve (TSV) Closure; and
b. Turbine Control Valve (TCV) Fast Closure, Trip Oil Pressure-Low.

CONDITION REQUIRED ACTION COMPLETION TIME A. One or more A.1 Restore channel to 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br /> Functions with one OPERABLE status.

channel inoperable. OR OR In accordance with the A.2 --------NOTE--------- Risk Informed Not applicable if Completion Time inoperable channel Program is the result of an inoperable breaker.

Place one channel 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br /> in affected Function in trip. OR In accordance with the Risk Informed Completion Time Program

B. One or more B.1 Place one channel 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> Functions with two in affected channels inoperable. Function in trip. OR In accordance with the Risk Informed Completion Time Program LCO 3.3.6.1 The primary containment and drywell isolation instrumentation for each Function in Table 3.3.6.1-1 shall be OPERABLE.

CONDITION REQUIRED ACTION COMPLETION TIME


NOTE---------------- A.1 Place one channel 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br /> Only applicable to Main in affected function Steam Line (MSL) in trip. OR isolation Functions.


In accordance with the A. One or more Risk Informed Functions with one Completion Time channel inoperable. Program


NOTE---------------- B.1 Place one channel 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> Only applicable to MSL in affected function isolation Functions. in trip. OR B. One or more In accordance with the Functions with two Risk Informed channels inoperable. Completion Time Program LCO 3.3.6.5 Two relief and LLS [low-low set] instrumentation trip systems shall be OPERABLE.

CONDITION REQUIRED ACTION COMPLETION TIME A. One trip system A.1 Restore trip system 7 days inoperable. to OPERABLE status. OR In accordance with the Risk Informed Completion Time Program

LCO 3.5.1 Each ECCS [emergency core cooling system] injection/spray subsystem and the Automatic Depressurization System (ADS) function of seven safety/relief valves shall be OPERABLE.


NOTE---------------------------------------------

One low pressure coolant injection (LPCI) subsystem may be inoperable during alignment and operation for decay heat removal with reactor steam dome pressure less than the residual heat removal cut in permissive pressure.

CONDITION REQUIRED ACTION COMPLETION TIME A. One low pressure A.1 Restore low 7 days ECCS injection/spray pressure ECCS subsystem inoperable. injection/spray OR subsystem to OPERABLE status. In accordance with the Risk Informed Completion Time Program B. HPCS [high pressure B.2 Restore HPCS 14 days core spray] System System to inoperable. OPERABLE status. OR In accordance with the Risk Informed Completion Time Program C. Two ECCS injection C.1 Restore one ECCS 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> subsystems injection/spray inoperable. subsystem to OR OPERABLE status.

OR In accordance with the Risk Informed One ECCS injection Completion Time and one ECCS spray Program subsystem inoperable.

E. One ADS valve E.1 Restore ADS valve 14 days inoperable. to OPERABLE status. OR In accordance with the Risk Informed Completion Time Program

F. One ADS valve F.1 Restore ADS valve 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> inoperable. to OPERABLE status. OR AND In accordance with the One low pressure Risk Informed ECCS injection/spray OR Completion Time subsystem inoperable. Program F.2 Restore low 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> pressure ECCS injection/spray OR subsystem to OPERABLE status. In accordance with the Risk Informed Completion Time Program LCO 3.5.3 The RCIC [reactor core isolation cooling] System shall be OPERABLE.

CONDITION REQUIRED ACTION COMPLETION TIME A. RCIC System A.2 Restore RCIC 14 days inoperable. System to OPERABLE status. OR In accordance with the Risk Informed Completion Time Program LCO 3.6.1.3 Each PCIV [primary containment isolation valve] shall be OPERABLE.

CONDITION REQUIRED ACTION COMPLETION TIME A. One or more A.1 Isolate the affected 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> or in accordance penetration flow paths penetration flow with the Risk Informed with one PCIV path by use of at Completion Time inoperable, except least one closed Program except for main due to leakage not and de-activated steam line and excess within limit. automatic valve, flow check valves closed manual (EFCVs) valve, blind flange, or check valve with AND flow through the valve secured. 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> or in accordance with the Risk Informed Completion Time Program for main steam line

AND 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> or in accordance with the Risk Informed Completion Time Program for EFCVs AND (continued)

A. (continued) A.2 --------NOTE---------

Isolation devices in high radiation areas may be verified by use of administrative means.

Verify the affected Once per 31 days penetration flow following isolation for path is isolated. isolation devices outside primary containment, drywell, and steam tunnel AND Prior to entering MODE 2 or 3 from MODE 4, if not performed within the previous 92 days, for isolation devices inside primary containment, drywell, or steam tunnel D. One or more D.1 Isolate the affected 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> penetration flow paths penetration flow with one or more path by use of at OR primary containment least one closed purge valves not and de-activated In accordance with the within purge valve automatic valve, Risk Informed leakage limits. closed manual Completion Time valve, or blind Program flange.

AND D.2 --------NOTE---------

Isolation devices in high radiation areas may be

verified by use of administrative means.

Verify the affected Once per 31 days penetration flow following isolation for path is isolated. isolation devices outside primary containment AND Prior to entering MODE 2 or 3 from MODE 4 if not performed within the previous 92 days for isolation devices inside primary containment AND D.3 Perform SR Once per 92 days

[surveillance following isolation requirement]

3.6.1.3.5 for the resilient seal purge valves closed to comply with Required Action D.1.

LCO 3.6.1.7 Two RHR [residual heat removal] containment spray subsystems shall be OPERABLE.


NOTE----------------------------------------------------

One RHR containment spray subsystem may be inoperable during alignment and operation for decay heat removal with reactor steam dome pressure less than the residual heat removal cut in permissive pressure.

CONDITION REQUIRED ACTION COMPLETION TIME A. One RHR A.1 Restore RHR 7 days containment spray containment spray subsystem inoperable. subsystem to OR OPERABLE status.

In accordance with the Risk Informed Completion Time Program LCO 3.6.2.3 Two RHR suppression pool cooling subsystems shall be OPERABLE.


NOTE-------------------------------------------------------------

One RHR suppression pool cooling subsystem may be inoperable during alignment and operation for decay heat removal with reactor steam dome pressure less than the residual heat removal cut in permissive pressure.

CONDITION REQUIRED ACTION COMPLETION TIME A. One RHR A.1 Restore RHR 7 days suppression pool suppression pool cooling subsystem cooling subsystem OR inoperable. to OPERABLE status. In accordance with the Risk Informed Completion Time Program

LCO 3.6.2.4 Two SPMU [suppression pool makeup] subsystems shall be OPERABLE.

CONDITION REQUIRED ACTION COMPLETION TIME C. One SPMU C.1 Restore SPMU 7 days subsystem inoperable subsystem to for reasons other than OPERABLE status. OR Condition A or B.

In accordance with the Risk Informed Completion Time Program LCO 3.6.5.3 One drywell isolation valve in each drywell penetration flow path shall be OPERABLE, except for the drywell vent and purge penetrations in which two drywell isolation valves shall be OPERABLE.


NOTE-------------------------------------------------------

This LCO does not apply to OPERABILITY of drywell post-LOCA

[loss-of-coolant accident] vacuum relief system valves.

CONDITION REQUIRED ACTION COMPLETION TIME A. One or more A.1 Isolate the affected 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> penetration flow paths penetration flow with one required path by use of at OR drywell isolation valve least one closed inoperable. and deactivated In accordance with the automatic valve, Risk Informed closed manual Completion Time valve, blind flange, Program or check valve with flow through the valve secured.

LCO 3.7.1 Division 1 and 2 SX [shutdown service water] Subsystems and UHS [ultimate heat sink] shall be OPERABLE.

CONDITION REQUIRED ACTION COMPLETION TIME


NOTE----------- ------------NOTES---------

Not applicable during 1. Enter applicable replacement of Division 2 Conditions and SX pump during the Required Actions Division 2 SX system of LCO 3.8.1, "AC outage window from [alternating current]

October 26 through Sources -

November 8, 2015. Operating," for


diesel generator B. Division 1 or 2 SX made inoperable subsystem inoperable. by SX.

2. Enter applicable Conditions and Required Actions of LCO 3.4.9, "Residual Heat Removal (RHR)

Shutdown Cooling System - Hot Shutdown," for RHR shutdown cooling subsystem made inoperable by SX.

B.1 Restore SX 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> subsystem to OPERABLE status. OR In accordance with the Risk Informed Completion Time Program LCO 3.7.6 The Main Turbine Bypass System shall be OPERABLE.

OR The following limits are made applicable:

a. Reactor THERMAL POWER limit for an inoperable Main Turbine Bypass System as specified in the COLR [core operating limits report]; and
b. LCS 3.2.2, "MINIMUM CRITICAL POWER RATIO (MCPR)," limit for an inoperable Main Turbine Bypass System as specified in the COLR; and
c. LCO 3.2.3, "LINEAR HEAT GENERATION RATE (LHGR)," limit for an inoperable Main Turbine Bypass System as specified in the COLR.

CONDITION REQUIRED ACTION COMPLETION TIME A. Requirements of the A.1 Satisfy the 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> LCO not met. requirements of the LCO. OR In accordance with the Risk Informed Completion Time Program LCO 3.8.1 The following AC electrical power sources shall be OPERABLE:

a. Two qualified circuits between the offsite transmission network and the onsite Class 1E AC Electric Power Distribution System; and
b. Three diesel generators (DGs).

CONDITION REQUIRED ACTION COMPLETION TIME A. One offsite circuit A.2 Restore offsite 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> inoperable. circuit to OPERABLE status. OR In accordance with the Risk Informed Completion Time Program B. One required DG B.4 Restore required 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> or in inoperable. DG to OPERABLE accordance with the Risk status. Informed Completion Time Program from discovery of an inoperable Division 3 DG AND 14 days or in accordance with the Risk Informed Completion Time Program

C. Two offsite circuits C.2 Restore one offsite 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> inoperable. circuit to OPERABLE status. OR In accordance with the Risk Informed Completion Time Program D. One offsite circuit D.1 Restore offsite 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> inoperable. circuit to OPERABLE OR AND status.

In accordance with the One required DG Risk Informed inoperable. OR Completion Time Program D.2 Restore required 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> DG to OPERABLE status. OR In accordance with the Risk Informed Completion Time Program LCO 3.8.4 The Division 1, Division 2, Division 3, and Division 4 DC [direct current] electrical power subsystems shall be OPERABLE.

CONDITION REQUIRED ACTION COMPLETION TIME A. One battery charger A.3 Restore battery 7 days on Division 1 or 2 charger to inoperable. OPERABLE status. OR In accordance with the Risk Informed Completion Time Program B. One battery on B.1 Restore battery to 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> Division 1 or 2 OPERABLE status.

inoperable. OR In accordance with the Risk Informed Completion Time Program

C. Division 1 or 2 DC C.1 Restore Division 1 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> electrical power and 2 DC electrical subsystem inoperable power subsystem OR for reasons other than to OPERABLE Condition A or B. status. In accordance with the Risk Informed Completion Time Program LCO 3.8.7 The Division 1, 2, 3, and 4 inverters, and A and B RPS solenoid bus inverters shall be OPERABLE.

CONDITION REQUIRED ACTION COMPLETION TIME A. Division 1 or 2 inverter A.1 Restore Division 1 7 days inoperable. and 2 inverters to OPERABLE status. OR In accordance with the Risk Informed Completion Time Program 2.2.4 Variations from TSTF-505, Revision 2 2.2.4.1 Application of the RICT Program to Modified Conditions, Required Actions, and Completion Times These are Conditions included in TSTF-505, Revision 2, which are applicable when one or more subsystems/channels are inoperable and there is no TS loss of function. The CT of these specific ACTIONS are modified to accommodate a RICT. Example:

CONDITION REQUIRED ACTION COMPLETION TIME A. One or more A.1 Restore [channel/ [24 hours]

[channel/subsystem/ subsystem/train] to train] inoperable. OPERABLE status.

The revised ACTIONS requirement states:

ACTIONS CONDITION REQUIRED ACTION COMPLETION TIME A. One or more A.1 Restore [channel/ [24 hours]

[channel/subsystem/ subsystem/train] to train] inoperable. OPERABLE status. OR


NOTE------------

Not applicable when

[all/two/four/both] required

[channel/subsystem/train]

are inoperable.

In accordance with the Risk Informed Completion Time Program The following Conditions are modified to permit the application of a RICT. The changed portion is indicated in italics.

LCO 3.3.5.1 The ECCS instrumentation for each Function in Table 3.3.5.1-1 shall be OPERABLE.

CONDITION REQUIRED ACTION COMPLETION TIME B. As required by B.3 Place channel in 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> Required Action A.1 trip.

and referenced in OR Table 3.3.5.1-1.


NOTE-----------------

Not applicable when trip capability is not maintained.

In accordance with the Risk Informed Completion Time Program C. As required by C.2 Restore channel to 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> Required Action A.1 OPERABLE status.

and referenced in OR Table 3.3.5.1-1.


NOTE-----------------

Not applicable when trip capability is not maintained.

In accordance with

the Risk Informed Completion Time Program D. As required by D.2.1 Place channel in 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> Required Action A.1 trip.

and referenced in OR Table 3.3.5.1-1.


NOTE-----------------

Not applicable when trip capability is not maintained.

In accordance with the Risk Informed Completion Time Program E. As required by E.2 Restore channel to 7 days Required Action A.1 OPERABLE status.

and referenced in OR Table 3.3.5.1-1.


NOTE-----------------

Not applicable when trip capability is not maintained.

In accordance with the Risk Informed Completion Time Program

F. As required by F.2 Place channel in 96 hours0.00111 days <br />0.0267 hours <br />1.587302e-4 weeks <br />3.6528e-5 months <br /> or in Required Action A.1 trip. accordance with the Risk and referenced in Informed Completion Table 3.3.5.1-1. Time Program from discovery of inoperable channel concurrent with HPCS or reactor core isolation cooling (RCIC) inoperable AND


NOTE-----------

The Risk Informed Completion Time Program is not applicable when trip capability is not maintained.

8 days or in accordance with the Risk Informed Completion Time Program G. As required by G.2 Restore channel to 96 hours0.00111 days <br />0.0267 hours <br />1.587302e-4 weeks <br />3.6528e-5 months <br /> or in Required Action A.1 OPERABLE status. accordance with the Risk and referenced in Informed Completion Table 3.3.5.1-1. Time Program from discovery of inoperable channel concurrent with HPCS or reactor core isolation cooling (RCIC)

Inoperable AND


NOTE-----------

The Risk Informed Completion Time Program is not applicable when trip capability is not maintained.

8 days or in accordance with the Risk Informed Completion Time Program

LCO 3.3.5.3 The RCIC System instrumentation for each Function in Table 3.3.5.3-1 shall be OPERABLE.

CONDITION REQUIRED ACTION COMPLETION TIME B. As required by B.2 Place channel in 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> Required Action A.1 trip.

and referenced in OR Table 3.3.5.3-1.


NOTE-----------------

Not applicable when trip capability is not maintained.

In accordance with the Risk Informed Completion Time Program D. As required by D.2.1 Place channel in 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> Required Action A.1 trip.

and referenced in OR Table 3.3.5.3-1.


NOTE-----------------

Not applicable when trip capability is not maintained.

In accordance with the Risk Informed Completion Time Program LCO 3.3.6.1 The primary containment and drywell isolation instrumentation for each Function in Table 3.3.6.1-1 shall be OPERABLE.

CONDITION REQUIRED ACTION COMPLETION TIME


NOTE---------------- D.1 Place channel in 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> Not applicable to MSL trip.

isolation Functions. OR D. One or more required --------NOTE-----------------

channels inoperable. Not applicable when trip capability is not maintained.

In accordance with the Risk Informed Completion Time Program

LCO 3.3.6.3 The RHR Containment Spray System instrumentation for each Function in Table 3.3.6.3-1 shall be OPERABLE.

CONDITION REQUIRED ACTION COMPLETION TIME B. As required by B.2 Place channel in 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> Required Action A.1 trip.

and referenced in OR Table 3.3.6.3-1.


NOTE-----------------

Not applicable when trip capability is not maintained.

In accordance with the Risk Informed Completion Time Program C. As required by C.2 Restore channel to 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> Required Action A.1 OPERABLE status.

and referenced in OR Table 3.3.6.3-1.


NOTE-----------------

Not applicable when trip capability is not maintained.

In accordance with the Risk Informed Completion Time Program

LCO 3.3.8.1 The LOP [loss of power] instrumentation for each Function in Table 3.3.8.1-1 shall be OPERABLE.

CONDITION REQUIRED ACTION COMPLETION TIME A. One or more channels A.1 Place channel in 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> inoperable. trip.

OR


NOTE-----------------

AND Not applicable when trip capability is not maintained.

A.2 ---------------------------------


NOTE-------------- In accordance with Only applicable for the Risk Informed Functions 1.c, 1.d, 1.e, Completion Time 2.c, 2.d, and 2.e Program Restore channel to 7 days OPERABLE status.

OR


NOTE-----------------

Not applicable when trip capability is not maintained.

In accordance with the Risk Informed Completion Time Program LCO 3.6.1.2 Each primary containment air lock shall be OPERABLE.

CONDITION REQUIRED ACTION COMPLETION TIME C. One or more required C.3 Restore air lock to 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> primary containment OPERABLE status.

air locks inoperable OR for reasons other than Condition A or B. --------NOTE-----------------

Not applicable if leakage exceeds limits or if loss of function.

In accordance with the Risk Informed Completion Time Program

LCO 3.6.5.2 The drywell air lock shall be OPERABLE.

CONDITION REQUIRED ACTION COMPLETION TIME C. Drywell air lock C.2 Restore air lock to 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> inoperable for reasons OPERABLE status.

other than Condition A OR or B.


NOTE-----------------

Not applicable if leakage exceeds limits or if loss of function.

In accordance with the Risk Informed Completion Time Program 2.2.4.2 Application of the RICT to Additional ACTIONS Requirements The following CPS TS Conditions proposed for the RICT program are not listed in TSTF 505, Revision 2.

LCO 3.3.6.4 The SPMU system instrumentation for each Function in Table 3.3.6.4-1 shall be OPERABLE.

CONDITION REQUIRED ACTION COMPLETION TIME B. As required by B.2 Place channel in 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> Required Action A.1 trip.

and referenced in OR Table 3.3.6.4-1.


NOTE-----------------

Not applicable when trip capability is not maintained.

In accordance with the Risk Informed Completion Time Program

C. As required by C.2 Restore channel to 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> Required Action A.1 OPERABLE status.

and referenced in OR Table 3.3.6.4-1.


NOTE-----------------

Not applicable when trip capability is not maintained.

In accordance with the Risk Informed Completion Time Program LCO 3.6.1.6 The LLS function of five safety/relief valves shall be OPERABLE.

CONDITION REQUIRED ACTION COMPLETION TIME A. One LLS valve A.1 Restore LLS valve 14 days inoperable. to OPERABLE status. OR In accordance with the Risk Informed Completion Time Program LCO 3.8.9 Division 1, 2, and 3 AC, Division 1, 2, 3, and 4, DC, and Division 1, 2, 3, and 4, uninterruptible AC bus electrical power distribution subsystems shall be OPERABLE.

CONDITION REQUIRED ACTION COMPLETION TIME A. One or more A.1 Restore Division 1 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> Division 1 or 2 AC and 2 AC electrical electrical power power distribution OR distribution subsystems to subsystems OPERABLE status. --------NOTE-----------------

inoperable. Not applicable if loss of function.

In accordance with the Risk Informed Completion Time Program

B. One or more B.1 Restore Division 1 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> Division 1 or 2 and 2 uninterruptible AC bus uninterruptible AC OR distribution bus distribution subsystems subsystems to --------NOTE-----------------

inoperable. OPERABLE status. Not applicable if loss of function.

In accordance with the Risk Informed Completion Time Program C. One or more C.1 Restore Division 1 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> Division 1 or 2 DC and 2 DC electrical electrical power power distribution OR distribution subsystems to subsystems OPERABLE status. --------NOTE-----------------

inoperable. Not applicable if loss of function.

In accordance with the Risk Informed Completion Time Program 2.3 Regulatory Review 2.3.1 Applicable Regulations Under Section 50.90, Application for amendment of license, construction permit, or early site permit, of Title 10 of the Code of Federal Regulations (10 CFR), whenever a holder of a license wishes to amend the license, including TSs in the license, an application for amendment must be filed, fully describing the changes desired.

The regulation at 10 CFR 50.36(c)(2) requires that TSs contain LCOs, which are the lowest functional capability or performance levels of equipment required for safe operation of the facility. When an LCO of a nuclear reactor is not met, the licensee shall shut down the reactor or follow any remedial action permitted by the TSs until the LCO can be met. Typically, the TSs require restoration of equipment in a timeframe commensurate with its safety significance, along with other engineering considerations. The regulation at 10 CFR 50.36(b) requires that TSs be derived from the analyses and evaluation included in the safety analysis report, and amendments thereto.

In determining whether the proposed TS remedial actions should be granted, the Commission will apply the reasonable assurance standards of 10 CFR 50.40(a) and 50.57(a)(3). The regulation at 10 CFR 50.40(a) states that in determining whether to grant the licensing request, the Commission will be guided by, among other things, consideration about whether the processes to be performed, the operating procedures, the facility and equipment, the use of the facility, and other technical specifications, or the proposals, in regard to any of the foregoing collectively provide reasonable assurance that the applicant will comply with the regulations in

this chapter, including the regulations in 10 CFR Part 20 of this chapter, and that the health and safety of the public will not be endangered.

The regulation at 10 CFR 50.36(c)(5) states that administrative controls are the provisions relating to organization and management, procedures, recordkeeping, review and audit, and reporting necessary to assure operation of the facility in a safe manner.

The regulation at 10 CFR 50.55a(h), Protection and safety systems, requires that for nuclear power plants with construction permits issued after January 1, 1971, but before May 13, 1999, protection systems must meet the requirements in IEEE Std 279-1968, Proposed IEEE Criteria for Nuclear Power Plant Protection Systems, or the requirements in IEEE Std 279-1971 1, Criteria for Protection Systems for Nuclear Power Generating Stations, or the requirements in IEEE Std 603-19911, Criteria for Safety Systems for Nuclear Power Generating Stations, and the correction sheet dated January 30, 1995. The CPS construction permit was issued on February 24, 1976. The CPS USAR, Chapters 6 and 7 (Reference 12), describes conformance to IEEE Std 279 by system.

2.3.2 Regulatory Guidance The NRC staff considered the following regulatory guidance during its review of the proposed changes:

  • RG 1.177, Revision 1, An Approach for Plant-Specific, Risk-Informed Decisionmaking:

Technical Specifications, May 2011 (Reference 9).

  • NUREG-1855, Revision 1, Guidance on the Treatment of Uncertainties Associated with PRAs in Risk-Informed Decisionmaking, March 2017 (Reference 10).
  • NUREG-0800, Standard Review Plan [SRP] for the Review of Safety Analysis Reports for Nuclear Power Plants: LWR Edition, Chapter 19, Section 19.2, Review of Risk Information Used to Support Permanent Plant-Specific Changes to the Licensing Basis:

General Guidance, June 2007 (Reference 11).

  • NEI 06 09 A, Risk Informed Technical Specifications Initiative 4b: Risk Managed Technical Specifications (RMTS), October 2012, Revision 0.

1 Available from Electric Power Research Institute, 3420 Hillview Avenue, Palo Alto, California 94304.

3.0 TECHNICAL EVALUATION

3.1 Method of Staff Review The NRC staff reviewed the licensees PRA peer review history and results, alternative methods and proposed approaches to determine if they are acceptable for use in the proposed RICT extensions. The NRC staff also reviewed the licensees proposed RICT program to determine if it provides the necessary administrative controls to permit completion time extensions for consistency with NEI 06-09-A.

An acceptable approach for making risk-informed decisions about proposed TS changes, including both permanent and temporary changes, is to show that the proposed licensing basis (LB) changes meet the five key principles stated in Section C of RG 1.174, Revision 3, and the three-tiered approach outlined in Section C of RG 1.177. These key principles and tiers are:

Principle 1: The proposed LB change meets the current regulations unless it is explicitly related to a requested exemption.

Principle 2: The proposed LB change is consistent with the defense in depth (DID) philosophy.

Principle 3: The proposed LB change maintains sufficient safety margins.

Principle 4: When the proposed LB change results in an increase in risk, the increase should be small and consistent with the intent of the Commissions policy statement (60 FR 42622, dated August 16,1995) on safety goals for the operations of nuclear power plants.

  • Tier 1: PRA Capability and Insights
  • Tier 2: Avoidance of Risk-Significant Plant Configurations
  • Tier 3: Risk-Informed Configuration Risk Management Principle 5: The impact of the proposed LB change should be monitored by using performance measures strategies.

Each of these key risk-informed principles and tiers are addressed in NEI 06-09-A. NEI 06-09-A provides a methodology for extending existing CTs, and thereby, delay exiting the operational mode of applicability or taking Required Actions if risk is assessed and managed within the limits and programmatic requirements established by a RICT program. The NRC staffs evaluation of the licensees proposed use of RICT program against the key safety principles is discussed below.

3.2 Review of Key Principles Revision 1 of RG 1.177 and RG 1.174, Revision 3, identify five key safety principles to be applied to risk-informed changes to the TSs. Each of these principles are addressed in NEI 06-09-A. The NRC staffs evaluation of the licensees proposed use of RICTs against these key safety principles is discussed below.

3.2.1 Key Principle 1: Evaluation of Compliance with Current Regulations Paragraph 50.36(c)(2) of 10 CFR require that LCOs are the lowest functional capability or performance levels of equipment required for safe operation of the facility. When an LCO of a nuclear reactor is not met, the licensee shall shut down the reactor or follow any remedial action permitted by the TSs until the condition can be met.

The CTs in the current TSs were established using experiential data, risk insights, and engineering judgement. The RICT program provides the necessary administrative controls to permit extension of CTs and, thereby, delay reactor shut down or Required Actions, if risk is assessed and managed appropriately within specified limits and programmatic requirements.

The addition of the option to determine the CT in accordance with the RICT program would allow an evaluation to determine a configuration-specific CT. The evaluation would be done in accordance with the methodology prescribed in NEI 06-09, and TS 5.5.17. The RICT is limited to a maximum of 30 days (i.e., back stop).

With the incorporation of the RICT program, the required performance levels of equipment specified in LCOs are not changed. Only the required CT for the Required Actions are modified by the RICT program such that 10 CFR 50.36(c)(2) will remain met. Based on the discussion provided above, the NRC staff finds that the proposed changes meet the first key safety principle of RG 1.174, Revision 3, and RG 1.177, Revision 1.

3.2.2 Key Principle 2: Evaluation of Defense in Depth (DID)

DID is an approach to designing and operating nuclear facilities that prevents and mitigates accidents that release radiation or hazardous materials. The key is creating multiple independent and redundant layers of defense to compensate for potential human and mechanical failures so that no single layer, no matter how robust, is exclusively relied upon.

DID includes the use of access controls, physical barriers, redundant and diverse key safety functions, and emergency response measures.

In RG 1.174, Revision 3, the NRC identified the following considerations used for evaluating how the LB change is maintained for the DID philosophy:

  • Preserve a reasonable balance among the layers of defense.
  • Preserve adequate capability of design features without an overreliance on programmatic activities as compensatory measures.
  • Preserve system redundancy, independence, and diversity commensurate with the expected frequency and consequences of challenges to the system, including consideration of uncertainty.
  • Preserve adequate defense against potential CCFs.
  • Maintain multiple fission product barriers.
  • Preserve sufficient defense against human errors.
  • Continue to meet the intent of the plants design criteria.

The proposed change represents a robust technical approach that preserves a reasonable balance among redundant and diverse key safety function that provide avoidance of core damage, avoidance of containment failure, and consequence mitigation. The three-tiered approach to risk-informed TS CT changes provides additional assurance that defense-in-depth will not be significantly impacted by such changes to the licensing basis. The licensee is

proposing no changes to the design of the plant or any operating parameter, no new operating configurations, and no new changes to the design basis in the proposed changes to the TS.

Since no changes to the design of the plant or any operating parameter, no new operating configuration, and no new changes to the design basis are proposed, the NRC staff finds that the 10 CFR 50.55a(h) requirements continue to be met.

The effect of the proposed changes when implemented will allow CTs to vary based on the risk significance of the given plant configuration (i.e., the equipment out-of-service at any given time) provided that the system(s) retain(s) the capability to perform the applicable safety function(s) without any further failures (e.g., one train of a two train system is inoperable). A configuration-specific RICT may not be used if the system has lost the capability to perform its safety function(s). These restrictions on inoperability of all required trains of a system ensure that consistency with the DID philosophy is maintained by following existing guidance when the capability to perform TS safety function(s) is lost.

The proposed RICT program uses plant-specific operating experience for component reliability and availability data. Thus, the allowances permitted by the RICT program are directly reflective of actual component performance in conjunction with component risk significance.

The RICT will be applied to extend CTs on key electrical power distribution systems. Failures in electrical power distribution systems can simultaneously affect multiple safety functions; therefore, potential degradation to DID during the extended CTs is discussed further below.

Use of Compensatory Measures to Retain DID In NEI 06-09, addresses potential compensatory actions and RMA measures by stating, in generic terms, that compensatory measures may include but are not limited to the following:

  • Reduce the duration of risk-sensitive activities.
  • Remove risk-sensitive activities from the planned work scope.
  • Reschedule work activities to avoid high risk-sensitive equipment outages or maintenance states that result in high-risk plant configurations.
  • Accelerate the restoration of out-of-service equipment.
  • Determine and establish the safest plant configuration.

NEI 06-09, requires that compensatory measures be initiated when the PRA calculated RMA time (RMAT) is exceeded, or for preplanned maintenance for which the RMAT is expected to be exceeded, RMAs shall be implemented at the earliest appropriate time. Therefore, quantitative risk analysis, the qualitative considerations, and the prohibition on loss of all trains of a required system assure a reasonable balance of DID is maintained to ensure protection of public health and safety.

3.2.2.1 Evaluation of Electrical Power Systems According to Revision 21 of the Updated Safety Analysis Report (USAR) (Reference 12), the plant is designed such that the safety functions are maintained assuming a single failure within the electrical power system. By incorporating an electrical power supply perspective, this concept is further reflected in a number of principal design criteria. Single-failure requirements

are typically suspended for the time that a plant is not meeting an LCO (i.e., in an ACTION statement). This section considers the plant configurations from a DID perspective.

The licensee has requested to use the RICT program to extend the existing CT for the following TS 3.8, Electrical Power Systems, condition(s). The NRC staffs evaluation of the proposed changes considered a number of potential plant conditions allowed by the proposed RICTs.

The NRC staff also considered the available redundant or diverse means to respond to various plant conditions. In these evaluations, the NRC staff examined the safety significance of different plant conditions resulting in both shorter and longer CTs. The plant conditions evaluated are discussed in more detail below.

The NRC staff reviewed information pertaining to the proposed electrical power systems TS conditions in the application, the USAR, and applicable TS LCO and TS Bases to verify that the capability of the affected electrical power systems to perform their safety functions (assuming no additional failures) is maintained. To achieve that objective, the staff verified whether each proposed TS conditions design success criteria reflect the redundant or absolute minimum electrical power source/subsystem required to be operable by the LCOs to support the safety functions necessary to mitigate postulated design-basis accidents (DBAs), safely shut down the reactor, and maintain the reactor in a safe shutdown condition. The NRC staff further reviewed the remaining credited power source/equipment to verify whether the proposed condition satisfies its design success criteria. In conjunction with reviewing the remaining credited power source/equipment, the NRC staff considered supplemental electrical power sources/equipment (not necessarily required by the LCOs and either safety or nonsafety-related) that is available at CPS and capable of performing the same safety function that would be performed by the inoperable electrical power source/equipment. In addition, the NRC staff reviewed the proposed RMA examples for reasonable assurance that these RMAs are appropriate to monitor and control risk for applicable TS conditions.

3.2.2.1.1 Loss of Power (LOP) Instrumentation (TS 3.3.8.1)

Description of the LOP Instrumentation Revision 21 of the CPS USAR, Chapter 8, Electric Power, and TS Bases Section B.3.3.8.1, Loss of Power (LOP) Instrumentation, indicate that the LOP instrumentation monitors the 4.16 kV (kilovolt) emergency buses. Offsite power is the preferred source of power for the 4.16 kV emergency buses. If the voltage monitors determine that insufficient power is available, the buses are disconnected from the offsite power sources and connected to the onsite DG power sources. Each 4.16 kV emergency bus has its own independent LOP instrumentation and associated trip logic. The voltage for the Division 1, 2, and 3, buses is monitored at two levels, which can be considered as two different undervoltage functions: loss of voltage and degraded voltage.

The OPERABILITY of the LOP instrumentation is dependent upon the OPERABILITY of the individual instrumentation channel relating to the loss of voltage and degraded voltage functions. Each Function must have a required number of OPERABLE channels for each 4.16 kV emergency bus with the setpoints within the allowable values specified in the TS. A channel is considered inoperable if its actual trip setpoint is not within its required allowable value.

Description of Loss of Voltage Functions (TS Table 3.3.8.1-1; Functions 1.a, 1.b, 2.a, 2.b)

Loss of voltage on a 4.16 kV emergency bus indicates that offsite power (provided by either of two offsite circuits) may be completely lost to the respective emergency bus and is unable to supply sufficient power for proper operation of the applicable equipment. Therefore, the power supply to the bus is transferred from offsite power to DG power when the associated bus voltage drops below the loss of voltage function allowable value. This ensures that adequate power will be available to the required equipment.

The loss of voltage function is also provided a time delay. The time delay allowable value is long enough to provide time for the offsite power supply to recover to normal voltages, but short enough to ensure that power is available to the required equipment.

According to TS Table 3.3.8.1-1, there are six channels of 4.16 kV emergency bus loss of voltage function instrumentation for each Division 1 and 2, and four channels for Division 3, which are required to be OPERABLE. Each channel of Division 1 and Division 2 consists of an inverse time delay relay providing a voltage function and a time delay function. Division 3 has four loss of voltage relays/channels and a single time delay relay.

Description of Degraded Voltage Functions (TS Table 3.3.8.1 Functions 1c, 1.d, 1.e, 2.c, 2.d, and 2.e)

A reduced voltage condition on a 4.16 kV emergency bus indicates that while offsite power may not be completely lost to the respective emergency bus, power may be insufficient for starting large motors without risking damage to the motors that could disable the ECCS function.

Therefore, power supply to the bus is transferred from offsite power to onsite DG power when the voltage on the bus drops below the degraded voltage function allowable value. This ensures that adequate power will be available to the required equipment.

The purpose of this instrumentation is to ensure that sufficient power will be available to support the ECCS function during a LOCA. During a LOCA, the ECCS and other safety systems will be initiated at the start of the event. This large loading of the safety buses results in a voltage transient of sufficient magnitude to start the degraded voltage timers. If the degraded voltage relays do not reset, which requires the voltage to be restored to a level above the relay reset setpoint, the bus undervoltage time delay relays will trip, resulting in bus transfer to the DGs.

According to TS Table 3.3.8.1-1, each division has two channels of degraded voltage relays and a single channel of time delay relay, which are required to be OPERABLE.

TS 3.3.8.1 - Changes Relating to LOP Instrumentation Refer to Section 2.2 of this SE for a detailed view of the TS changes.

Evaluation of TS Changes Relating to LOP Instrumentation According to TS 3.3.8.1, Action A.1, the current TS requires placement of any channel relating to loss of voltage or degraded voltage functions in the trip position within one hour. The licensee has proposed to extend the completion time as per the RICT program. According to Action A.2, the current TS requires restoration of any channel relating to the degraded voltage function within 7 days. The licensee has proposed to extend the completion time as per the RICT program. However, the extension in completion time will not be applicable if the trip

capability is not maintained. If any of the actions and associated completion times are not met, the associated bus DG is required to be declared inoperable immediately.

In its letter dated November 24, 2020, the licensee explained the loss of functions, as follows if any inoperable channel relating to loss of voltage or degraded voltage function is placed in the trip position:

The Division 1 and 2 emergency bus Loss of Voltage Function is monitored by two undervoltage relays on the emergency bus and two undervoltage relays on each of the two offsite power sources. This results in a total of six relay/channels for the Loss of Voltage Function for each Division. Each of these relays is an inverse time delay relay. The outputs of these relays are arranged in a two-out-of-two taken three times logic configuration to start the respective Divisional Diesel Generator. Any relay/channel failing will result in the respective Diesel Generator not starting.

The Division 3 emergency bus Loss of Voltage Function is monitored by four undervoltage relays whose outputs are arranged in a one-out-of-two taken twice logic configuration. The output of this logic inputs to a time delay relay. A failure of a channel associated with Function 2.a [Degraded Voltage Function for Division 3] will not result in a loss of the function. However, a failure of Function 2.b [Degraded Time Function for Division 3] will result in the Division 3 Diesel Generator not starting.

Each Division 1, Division 2, and Division 3 emergency bus Degraded Voltage Function is monitored by two undervoltage relays for each emergency bus whose outputs are arranged in a two-out-of-two logic configuration. The output of this logic inputs to a time delay relay on each emergency bus. Any relay/channel failing will result in the respective Diesel Generator not starting.

The NRC staff finds that based on logic explained by the licensee in its above response, in most cases of one or more channel failures, the Loss of Power Instrumentation will continue to serve its design function (i.e., detect loss of voltage or degraded voltage).

The TS change also has a Note stating that the RICT is not applicable when the trip capability is not maintained (i.e., unable to meet its design function).

In its letter dated November 24, 2020, the licensee also explained that in the RICT PRA modelling, the "Inoperability of One or more channels" is modeled as a failure of the autostart mode of the associated DG. The manual start mode of the associated DG is still considered available in the RICT model. The NRC staff finds this aspect of the RICT modelling reasonable and, therefore, acceptable.

The above extension in CT will only be applicable when One or more channels [are]

inoperable and will not result in a loss of the design function (i.e., unable to detect loss of voltage or degraded voltage). For instrumentation that has the potential for a configuration in which trip capability is not maintained, a Note was added to the Completion Time which prohibits applying a RICT when trip capability is not maintained. The associated DG, if declared inoperable, can be started manually, thus, providing a partial safety function for certain design events which do not require immediate/auto starting of DG.

The NRC staff finds that because of redundancies in the availability of the offsite and onsite power sources the LOP design has sufficient redundancy, diversity, and DID to protect against common cause failures and potential single failure when using the RICT Program. Therefore, the staff finds the above TS changes are acceptable.

3.2.2.1.2 AC Sources - Operating (TS 3.8.1)

Description of the AC Sources CPS USAR Section 8, and TS Bases B.3.8.1, describe the Unit Class 1E AC Electrical Power Distribution System AC Sources as consisting of the offsite power sources and the onsite standby power sources (DGs 1A, 1B, and 1C). As required by 10 CFR Part 50, Appendix A, General Design Criteria 17, the design of the AC electrical power system provides independence and redundancy to ensure an available source of power to the engineered safety feature (ESF) systems.

The Class 1E AC distribution system supplies electrical power to three divisional load groups, with each division powered by an independent Class 1E 4.16 kV ESF bus. Each ESF bus has two separate and independent offsite sources of power. Each ESF bus has a dedicated onsite DG. The ESF systems of any two of the three divisions provide for the minimum safety functions necessary to shut down the unit and maintain it in a safe shutdown condition.

Offsite power is supplied to the switchyard from the transmission network. From the switchyard, one 345 kV circuit provides AC power to each 4.16 kV ESF bus. An electrically and physically independent 138 kV power source provides a second completely independent circuit to each 4.16 kV ESF bus. The offsite AC electrical power sources are designed and located so as to minimize to the extent practical the likelihood of their simultaneous failure under operating and postulated accident and environmental conditions.

The onsite standby power source for each 4.16 kV ESF bus is a dedicated DG. A DG starts automatically on a LOCA signal (i.e., low reactor water level signal or high drywell pressure signal) or on an ESF bus degraded voltage or undervoltage signal. In the event of a loss of offsite power (LOOP), the ESF electrical loads are automatically connected to the DGs in sufficient time to provide for safe reactor shut down and to mitigate the consequences of a design basis accident such as a LOCA.

TS 3.8.1 - Changes Relating to AC Power - Operating Refer to Section 2.2 of this SE for a detailed view of the TS changes.

Evaluation of TS Changes Relating to AC Sources - Operating For each change identified below, the NRC staff reviewed the information pertaining to the proposed TS change in the LAR, the USAR, and applicable TS LCO and TS Bases to verify that the capability of the affected electrical power systems to perform their safety functions (assuming no additional failures) is maintained. To achieve that objective, the NRC staff verified that the proposed TS conditions design success criteria (as provided in Enclosure 1 of the LAR) reflect the redundant or absolute minimum electrical power source/subsystem required to be operable to support the safety functions necessary to mitigate postulated DBAs, safely shut down the reactor, and maintain the reactor in a safe shutdown condition. In addition, the staff

reviewed the proposed RMA examples for reasonable assurance that these RMAs are appropriate to monitor and control risk for the condition applicable to the proposed TS change.

TS 3.8.1, Condition A One offsite circuit inoperable, Action A.2 The licensee has proposed to apply the RICT program to TS 3.8.1, Condition A, One offsite circuit inoperable, Action A.2 to extend the CT from the current value of 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> to 30 days maximum per the RICT program if risk remains within the guidance of NEI 06-09-A. In the LAR, 2, Risk Management Action (RMA) Examples, the licensee provided examples of multiple RMAs that may be considered during a RICT program entry to reduce the risk impact and ensure adequate DID. In particular, Enclosure 12 of the LAR listed the example RMAs which are likely to be implemented during TS action 3.8.1.A, One offsite circuit inoperable.

TS 3.8.1, Condition B One required DG inoperable, Action B.4 The licensee has proposed to apply the RICT program to TS 3.8.1, Condition B, One required DG inoperable, Action B.4 to extend the CT from the current value of 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> to 30 days maximum per the RICT program for the Division 3 DG; and to extend the CT from the current value of 14 days to 30 days maximum per the RICT program for the Division 1 or 2 DG, if the risk remains within limits of the NEI 06-09-A guidance. In the LAR, Enclosure 12, Risk Management Action (RMA) Examples, the licensee provided examples of multiple RMAs that may be considered during a RICT program entry to reduce the risk impact and ensure adequate DID. In particular, Enclosure 12 of the LAR listed the example RMAs which are likely to be implemented during TS action 3.8.1.B, One required DG inoperable.

TS 3.8.1, Condition C Two offsite circuits inoperable, Action C.2 The licensee has proposed to apply the RICT program to TS 3.8.1, Condition C, Two offsite circuits inoperable, Action C.2 to extend the CT from the current value of 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> to 30 days maximum per the RICT program, if risk remains within the limits of the NEI 06-09-A guidance.

In the LAR, Enclosure 12, Risk Management Action (RMA) Examples, the licensee provided examples of RMAs that may be considered during a RICT program entry to reduce the risk impact and ensure adequate DID.

In its supplement dated November 24, 2020, the licensee provided the example RMAs which are likely to be implemented during RICT of TS 3.8.1, Condition C, Two offsite circuits inoperable.

TS 3.8.1, Condition D One required offsite circuit inoperable AND One required DG inoperable, Action D.1 or Action D.2 The licensee has proposed to apply the RICT program to TS 3.8.1, Condition D, One required offsite circuit inoperable AND One required DG inoperable, Action D.1 or Action D.2 to extend the CT from the current value of 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> to 30 days maximum per the RICT program, if the risk remains within the limits of the NEI 06-09-A guidance. In the LAR, Enclosure 12, Risk Management Action (RMA) Examples, the licensee provided examples of RMAs that may be considered during a RICT program entry to reduce the risk impact and ensure adequate DID. In particular, Enclosure 12 of the LAR listed the example RMAs which are likely to be implemented during TS action 3.8.1, Condition D, One required offsite circuit inoperable AND One required DG inoperable.

3.2.2.1.3 DC Sources - Operating (TS 3.8.4)

Description of the DC Sources CPS USAR Section 8, and TS Bases B.3.8.4 describe that each Division 1, 2, 3, and 4, battery has adequate storage capacity to meet the load duty cycle(s) discussed in the USAR, Section 8.3.2. Each DC battery subsystem is located in an area separated physically and electrically from the other subsystems to ensure that a single failure in one subsystem does not cause a failure in a redundant subsystem. There is no sharing between redundant Class 1E subsystems such as batteries, battery chargers, or distribution panels.

The batteries for a DC electrical power subsystem are sized to produce the required capacity at 80 percent of nameplate rating. The minimum design voltage limit is 105 volt (V). The battery cells are flooded lead acid construction with a nominal specific gravity of 1.215. This specific gravity corresponds to an open circuit battery voltage of approximately 120 V for a 58-cell battery (i.e., cell voltage of 2.065 volts per cell). The nominal float voltage of 2.22 Vpc corresponds to a total float voltage output of 128.8 V for a 58-cell battery. Each battery charger of Division 1, 2, 3, and 4, DC electrical power subsystems has ample power output capacity for the steady state operation of connected loads required during normal operation, while at the same time maintaining its battery bank fully charged. Each battery charger has sufficient excess capacity to restore the battery bank from the design minimum charge to its fully charged state within 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> while supplying normal steady-state loads.

TS 3.8.4 - Changes Relating to DC Power - Operating See Section 2.2 of this SE for a detailed view of TS changes.

Evaluation of TS Changes Relating to DC Sources - Operating For each change identified below, the NRC staff reviewed the information pertaining to the proposed TS change in the LAR, the USAR, and applicable TS LCO and TS Bases to verify that the capability of the affected electrical power systems to perform their safety functions (assuming no additional failures) is maintained. To achieve that objective, the NRC staff verified that the proposed TS conditions design success criteria (as provided in Enclosure 1 of the LAR) reflect the redundant or absolute minimum electrical power source/subsystem required to be operable to support the safety functions necessary to mitigate postulated DBAs, safely shut down the reactor, and maintain the reactor in a safe shutdown condition. In addition, the staff reviewed the proposed RMA examples for reasonable assurance that these RMAs are appropriate to monitor and control risk for the condition applicable to the proposed TS change.

TS 3.8.4, Condition A One battery charger on Division 1 or 2 inoperable, Action A.3 The licensee has proposed to apply the RICT program to TS 3.8.4, Condition A, One battery charger on Division 1 or 2 inoperable, Action A.3 to extend the CT from the current value of 7 days to 30 days maximum per the RICT program, if the risk remains within the guidance of NEI 06-09-A. In the LAR, Enclosure 12, Risk Management Action (RMA) Examples, the licensee provided examples of RMAs that may be considered during a RICT program entry to reduce the risk impact and ensure adequate DID. In particular, Enclosure 12 of the LAR listed the example RMAs which are likely to be implemented during TS action 3.8.4.A, One battery charger on Division 1 or 2 inoperable.

Considering that the CT extension will be implemented if the risk values are in accordance with the NEI 06-09-A guidance, and that additional RMAs will be implemented, the NRC staff finds that the plant will have adequate DID. Therefore, the NRC staff finds the application of the RICT program to TS 3.8.4, Condition A, One battery charger on Division 1 or 2 inoperable, Action A.3, acceptable.

TS 3.8.4, Condition B One battery on Division 1 or 2 inoperable, Action B.1 The licensee has proposed to apply the RICT program to TS 3.8.4, Condition B, One battery on Division 1 or 2 inoperable, Action B.1 to extend the CT from the current value of 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> to 30 days maximum per the RICT program, if risk remains within the guidance of NEI 06-09-A. In the LAR, Enclosure 12, Risk Management Action (RMA) Examples, the licensee provided examples of RMAs that are likely to implemented during a RICT program entry to reduce the risk impact and ensure adequate DID.

In the supplement dated November 24, 2020, the licensee provided the example RMAs which are likely to be implemented during RICT of TS 3.8.4, Condition B, One battery on Division 1 or 2 inoperable.

(c) TS 3.8.4, Condition C Division 1 or 2 DC electrical power subsystem inoperable for reasons other than Condition A or B, Action C.1 The licensee has proposed to apply the RICT program to TS 3.8.4, Condition C, Division 1 or 2 DC electrical power subsystem inoperable for reasons other than Condition A or B, Action C.1 to extend the CT from the current value of 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> to 30 days maximum per the RICT program, if risk remains within the guidance of NEI 06-09-A. In the LAR, Enclosure 12, Risk Management Action (RMA) Examples, the licensee provided examples of RMAs that are likely to be implemented during a RICT program entry to reduce the risk impact and ensure adequate DID.

In the supplement dated November 24, 2020, , the licensee provided the example RMAs which will be implemented during RICT of TS 3.8.4, Condition C, Division 1 or 2 DC electrical power subsystem inoperable for reasons other than Condition A or B.

3.2.2.1.4 Inverters - Operating (TS 3.8.7)

Description of the Inverters CPS USAR, Section 8, and TS Bases B.3.8.7, describe that the inverters are the preferred source of power for the uninterruptible AC buses and the RPS solenoid buses because of the stability and reliability they achieve. There is one inverter per uninterruptible AC bus (comprising a total of four divisional inverters) and one inverter per RPS solenoid bus (comprising a total of two RPS solenoid bus inverters). The function of the inverter is to provide AC electrical power to these buses. The inverters are powered from both AC and DC sources.

The DC source provides an uninterruptible power source for the instrumentation and controls (I&C) for the RPS, the ECCS initiation, miscellaneous isolations, and the RPS and main steam isolation valve (MSIV) solenoids.

The divisional inverters contain a solid-state transfer switch to automatically transfer to an alternate source if the inverter detects abnormal conditions, such as an internal inverter component failure or for handling fault clearing or inrush current demands. The transfer of the

divisional inverters to their alternate source will occur if the alternate source is either energized or deenergized.

TS 3.8.7 - Changes Relating to Inverters - Operating See Section 2.2 of this SE for a detailed view of TS changes.

Staff Evaluations of TS Changes Relating to Inverters - Operating For each change identified below, the NRC staff reviewed the information pertaining to the proposed TS change in the LAR, the USAR, and applicable TS LCO and TS Bases to verify that the capability of the affected electrical power systems to perform their safety functions (assuming no additional failures) is maintained. To achieve that objective, the NRC staff verified that the proposed TS conditions design success criteria (as provided in Enclosure 1 of the LAR) reflect the redundant or absolute minimum electrical power source/subsystem required to be operable to support the safety functions necessary to mitigate postulated DBAs, safely shut down the reactor, and maintain the reactor in a safe shutdown condition. In addition, the staff reviewed the proposed RMA examples for reasonable assurance that these RMAs are appropriate to monitor and control risk for the condition applicable to the proposed TS change.

TS 3.8.7, Condition A Division 1 or 2 inverter inoperable, Action A.1 The licensee has proposed to apply the RICT program to TS 3.8.7, Division 1 or 2 inverter inoperable, Action A.1 to extend the CT from the current value of 7 days to 30 days maximum per the RICT program, if risk remains within the guidance of NEI 06-09-A. In the LAR, 2, Risk Management Action (RMA) Examples, the licensee provided examples of RMAs that are likely to be implemented during a RICT program entry to reduce the risk impact and ensure adequate DID.

In its letter dated November 24, 2020, the licensee provided the example RMAs which are likely to be implemented during RICT of TS 3.8.7, Condition A Division 1 or 2 inverter inoperable.

3.2.2.1.5 Distribution Systems - Operating (TS 3.8.9)

Description of the Distribution Systems CPS TS Bases B.3.8.9 describes that the onsite Class 1E AC and DC electrical power distribution systems are divided into three independent AC, four independent DC, and four divisional uninterruptible AC bus electrical power distribution subsystems.

The primary AC distribution system consists of each 4.16 kV ESF bus that has at least one separate and independent offsite source of power, as well as a dedicated onsite DG source.

Each 4.16 kV ESF bus is normally connected to a preferred source. If all offsite sources are unavailable, the onsite emergency DGs supply power to the 4.16 kV ESF buses. The DC distribution system provides control power for the 4.16 kV breakers which is supplied from the Class 1E batteries.

The secondary plant AC distribution system includes 480 V ESF load centers and associated loads, motor control centers, and transformers. The 120 V uninterruptible AC buses are arranged in four divisions and are normally powered from an inverter supplied with DC power.

The alternate power supply for the uninterruptible AC buses is a Class 1E constant voltage

source transformer powered from the same division as the associated inverter. There are four independent 125 vpc (volt per cell) electrical power distribution subsystems.

TS 3.8.9 - Changes Relating to Distribution Systems - Operating See Section 2.2 of this SE for a detailed view of TS changes.

Evaluation of TS Changes Relating to Inverters - Operating For each change identified below, the NRC staff reviewed the information pertaining to the proposed TS change in the LAR, the USAR, and applicable TS LCO and TS Bases to verify that the capability of the affected electrical power systems to perform their safety functions (assuming no additional failures) is maintained. To achieve that objective, the NRC staff verified that the proposed TS conditions design success criteria (as provided in Enclosure 1 of the LAR) reflect the redundant or absolute minimum electrical power source/subsystem required to be operable to support the safety functions necessary to mitigate postulated DBAs, safely shut down the reactor, and maintain the reactor in a safe shutdown condition. In addition, the staff reviewed the proposed RMA examples for reasonable assurance that these RMAs are appropriate to monitor and control risk for the condition applicable to the proposed TS change.

TS 3.8.9, Condition A One or more Division 1 or 2 AC electrical power distribution subsystems inoperable, Action A.1 The licensee has proposed to apply the RICT program to TS 3.8.9, Condition A, One or more Division 1 or 2 AC electrical power distribution subsystems inoperable, Action A.1 to extend the CT from the current value of 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> to 30 days maximum per the RICT program, provided no loss of function occurs and if risk remains within the guidance of NEI 06-09-A. In the LAR, 2, Risk Management Action (RMA) Examples, the licensee provided examples of RMAs that are likely to be implemented during a RICT program entry to reduce the risk impact and ensure adequate DID.

In its letter dated November 24, 2020, the licensee provided the example RMAs which will be implemented during RICT of TS 3.8.9, Condition A, One or more Division 1 or 2 AC electrical power distribution subsystems inoperable.

TS 3.8.9, Condition B One or more Division 1 or 2 uninterruptible AC bus distribution subsystems inoperable, Action B.1 The licensee has proposed to apply the RICT program to TS 3.8.9, Condition B, One or more Division 1 or 2 uninterruptible AC bus distribution subsystems inoperable, Action B.1, to extend the CT from the current value of 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> to 30 days maximum per the RICT program, provided no loss of function occurs and if risk remains within the guidance of NEI 06-09-A. In the LAR, 2, Risk Management Action (RMA) Examples, the licensee provided examples of RMAs that are likely to be considered during a RICT program entry to reduce the risk impact and ensure adequate DID.

In its letter dated November 24, 2020, the licensee provided the example RMAs which are likely to be implemented during RICT of TS 3.8.9, Condition B, One or more Division 1 or 2 uninterruptible AC bus distribution subsystems inoperable.

TS 3.8.9, Condition C One or more Division 1 or 2 DC electrical distribution subsystems inoperable, Action C.1 The licensee has proposed to apply the RICT program to TS 3.8.9, Condition C, One or more Division 1 or 2 DC electrical distribution subsystems inoperable, Action C.1, to extend the CT from the current value of 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> to 30 days maximum per the RICT program, provided no loss of function occurs and if risk remains within the guidance of NEI 06-09-A. In the LAR, 2, Risk Management Action (RMA) Examples, the licensee provided examples of RMAs that are likely to be considered during a RICT program entry to reduce the risk impact and ensure adequate DID.

In the supplement dated November 24, 2020, the licensee provided the example RMAs which are likely to be implemented during RICT of TS 3.8.9, Condition C, One or more Division 1 or 2 DC electrical distribution subsystems inoperable.

3.2.2.1.6 Electrical Power Systems Evaluation Conclusion The NRC staff finds that while the redundancy is not maintained (e.g., one train of a two-train system is inoperable), the CT extensions in accordance with the RICT program are acceptable because: (1) the capability of the systems to perform their safety functions (assuming no additional failures) is maintained thereby maintaining DID, and (2) the licensees demonstration of identifying and implementing compensatory measures or RMAs, in accordance with the RICT program, are appropriate to monitor and control risk.

3.2.2.2 Evaluation of Instrumentation and Control (I&C) Systems The licensee has requested to use the RICT program to extend the existing CT for the following TS conditions. The NRC staffs evaluation of the proposed changes considered a number of potential plant conditions allowed by the new TSs and considered what redundant or diverse means were available to assist the licensee in responding to various plant conditions. The plant conditions evaluated are discussed in more detail below. See Section 2.2 for a detailed view of TS changes.

LCO 3.3.1.1 Reactor Protection System (RPS) Instrumentation LCO 3.3.4.1 End of Cycle Recirculation Pump Trip (EOC-RPT) Instrumentation LCO 3.3.5.1 Emergency Core Cooling System (ECCS) Instrumentation LCO 3.3.5.3 Reactor Core Isolation Cooling (RCIC) System Instrumentation LCO 3.3.6.1 Primary Containment and Drywell Isolation Instrumentation LCO 3.3.6.3 Residual Heat Removal (RHR) Containment Spray System Instrumentation LCO 3.3.6.4 Suppression Pool Makeup (SPMU) System Instrumentation LCO 3.3.6.5 Relief and Low-Low Set (LLS) Instrumentation LCO 3.3.8.1 Loss of Power (LOP) Instrumentation of the LAR provided information supporting the evaluation of the redundancy and diversity of instrumentation included in the TS changes proposed. The information provided in of the LAR was evaluated as described in the subsections below.

The NRC staff followed the guidance formulated in RG 1.174 and elaborated upon in RG 1.177, to assess the proposed changes consistency with DID criteria. The applicable DID criteria to the affected CPS I&C systems are:

  • Over-reliance on programmatic activities as compensatory measures associated with the change in the LB is avoided.
  • System redundancy, independence, and diversity are maintained commensurate with the expected frequency and consequences of challenges to the system (e.g., there are no risk outliers).
  • Defenses against potential CCF are maintained and the potential for the introduction of new common cause failure mechanisms is assessed.
  • The intent of the plants design criteria is maintained.

The licensee confirmed, and NRC staff verified that, in accordance with the CPS USAR in all applicable operating modes, the affected protective feature would perform its intended function by ensuring the ability to detect and mitigate the associated event or accident when the CT of a channel is extended. The RICT program is not being applied to shutdown modes. Therefore, the NRC staff concludes that the intent of the plants design criteria for the I&C functions identified in the amendment are maintained.

The NRC staff finds that while in an LCO condition, the redundancy of the function will be temporarily relaxed, and consequently the system reliability will be degraded accordingly. The NRC staff examined the design information from the CPS USAR and the risk-informed LCO conditions for the affected I&C functions. Based on this information, the NRC staff confirmed that under any given DBA evaluated in the CPS USAR, the affected I&C protective features maintains adequate DID by either necessary redundancy (e.g., at least one redundant channel) and/or necessary diversity (e.g., at least one alternative safety feature).

The licensee stated in the LAR that the proposed changes do not alter CPS I&C system designs. Consequently, the NRC staff concludes that the proposed changes do not alter the ways in which the CPS I&C systems fail, and do not introduce new CCF modes, and that system independence is maintained. The NRC staff finds that some proposed changes reduce the level of redundancy of the affected I&C systems, and this reduction may reduce the level of defense against some CCFs; however, the NRC staff finds, as described below, that such reduction in redundancy and defense against common cause failures are acceptable due to existing diverse means available to maintain adequate DID against a potential single failure during the RICT for the CPS I&C systems.

The following sections summarize the NRC staffs findings with respect to the DID principle for the functions identified in the LAR by identifying associated diverse means that maintain adequate DID against potential single failure during an RICT for the CPS I&C systems.

3.2.2.2.1 LCO 3.3.1.1 Reactor Program System (RPS) Instrumentation The LAR states that the RPS is a fail-safe system design (de-energizes to trip) and is comprised of four independent trip logic divisions as described in USAR, Section 7.2. In addition to RPS de-energizing the scram pilot valves and energizing the backup scram valves, CPS has redundant and diverse methods of shutting down the reactor in the unlikely event that the RPS does not SCRAM the reactor (anticipated transient without scram (ATWS), alternate rod

insertion (ARI), recirculation pump trip (RPT) breakers, and the standby liquid control system (SLCS)).

The logic trip arrangement, redundancy, and diverse inputs causing a trip of the RPS are discussed and shown in USAR Section 7.2 and Figures 7.2-2 thru 7.2-4, CPS TS LCO 3.3.3.1, Table 3.3.1.1-1 and Bases B3.3.1.1 and reflected in Attachment 5 of the LAR.

The NRC staff finds that the RPS design has sufficient redundancy, diversity, and DID to protect against common cause failures and potential failure during the RICT for the CPS I&C systems and does not rely on manual actions as the only diverse means; therefore, there is no over-reliance on programmatic activities as compensatory measures.

3.2.2.2.2 LCO 3.3.4.1 End of Cycle-Recirculation Pump Trip (EOC-RPT) Instrumentation The LAR states that the EOC-RPT instrumentation initiates a recirculation pump trip (RPT) to reduce the peak reactor pressure and power resulting from turbine trip or generator load rejection transients to provide additional margin to core thermal MCPR Safety Limits.

The logic trip arrangement, redundancy, and diverse inputs causing a trip of the EOC-RPT are discussed and shown in USAR Section 7.6.1.8, CPS TS LCO 3.3.4.1 and Bases B3.3.4.1 and reflected in Attachment 5 of the LAR.

The NRC staff finds that the EOC-RPS design has sufficient redundancy, diversity, and DID to protect against common cause failures and potential single failure during the RICT for the CPS I&C systems and does not rely on manual actions as the only diverse means; therefore, there is no over-reliance on programmatic activities as compensatory measures.

3.2.2.2.3 LCO 3.3.5.1 ECCS Instrumentation The LAR states that the purpose of the ECCS instrumentation is to initiate appropriate responses from the systems to ensure that fuel is adequately cooled in the event of a design basis accident or transient. The ECCS instrumentation actuates low-pressure core spray (LPCS), LPCI, high-pressure core spray (HPCS), ADS, and the DGs.

For instrumentation that has the potential for a configuration in which trip capability is not maintained, a Note was added to the CT which prohibits applying a RICT when trip capability is not maintained.

The logic trip arrangement, redundancy, and diverse inputs causing a trip of the ECCS are discussed and shown in USAR Sections 5.2.2, 6.3, and 7.3, CPS TS LCO 3.3.5.1, Table 3.3.5.1-1, and reflected in Attachment 5 of the LAR.

The NRC staff finds that the ECCS design has sufficient redundancy, diversity, and DID to protect against CCFs and potential single failure during the RICT for the CPS I&C systems and does not rely on manual actions as the only diverse means; therefore, there is no over-reliance on programmatic activities as compensatory measures .

3.2.2.2.4 LCO 3.3.5.3 Reactor Core Isolation Cooling (RCIC) System The LAR states that the RCIC system instrumentation is to initiate actions to ensure adequate core cooling when the reactor vessel is isolated from its primary heat sink (the main condenser)

and normal coolant makeup flow from the reactor feedwater system is unavailable, such that initiation of the low pressure ECCS pumps does not occur.

For instrumentation that has the potential for a configuration in which trip capability is not maintained, a Note was added to the CT which prohibits applying a RICT when trip capability is not maintained. The logic trip arrangement, redundancy, and diverse inputs causing a trip of the RCIC system are discussed and shown in USAR Section 7.4.1.1.3.2, CPS TS LCO 3.3.5.3, Table 3.3.5.3-1 and reflected in Attachment 5 of the LAR.

The NRC staff finds that the RCIC system design has sufficient redundancy, diversity, and DID to protect against common cause failures and potential single failure during the RICT for the CPS I&C systems and does not rely on manual actions as the only diverse means; therefore, there is no over-reliance on programmatic activities as compensatory measures.

3.2.2.2.5 LCO 3.3.6.1 Primary Containment and Drywell Isolation Instrumentation The LAR states that the primary containment and drywell isolation instrumentation automatically initiates closure of appropriate primary containment isolation valves (PCIVs) and drywell isolation valves. The function of the PCIVs, in combination with other accident mitigation systems, is to limit fission product release during and following postulated DBAs. Functional diversity is provided by monitoring a wide range of independent parameters.

For instrumentation that has the potential for a configuration in which trip capability is not maintained, a Note was added to the CT which prohibits applying a RICT when trip capability is not maintained.

The logic trip arrangement, redundancy, and diverse inputs causing a trip of the primary containment and drywell isolation instrumentation are discussed and shown in USAR Section 7.3.1.1.2, CPS TS LCO 3.3.6.1, Table 3.3.6.1-1, and reflected in Attachment 5 of the LAR.

The NRC staff finds that the primary containment and drywell isolation instrumentation design has sufficient redundancy, diversity, and DID to protect against common cause failures and potential single failure during the RICT for the CPS I&C systems and does not rely on manual actions as the only diverse means; therefore, there is no over-reliance on programmatic activities as compensatory measures.

3.2.2.2.6 LCO 3.3.6.3 Residual Heat Removal (RHR) Containment Spray System (CSS)

Instrumentation The LAR states that the RHR CSS is an operating mode of the RHR system that is initiated to condense steam in the containment atmosphere. This ensures that containment pressure is maintained within its limits following a LOCA.

For instrumentation that has the potential for a configuration in which trip capability is not maintained, a Note was added to the CT which prohibits applying a RICT when trip capability is not maintained.

The logic trip arrangement, redundancy, and diverse, inputs causing a trip of the RHR CSS are discussed and shown in USAR Section 7.3.1.1.4, CPS TS LCO 3.3.6.3, Table 3.3.6.3-1, and reflected in Attachment 5 of the LAR.

The NRC staff finds that the RHR CSS design has sufficient redundancy, diversity, and DID to protect against common cause failures and potential single failure during the RICT for the CPS I&C systems and does not rely on manual actions as the only diverse means; therefore, there is no over-reliance on programmatic activities as compensatory measures .

3.2.2.2.7 LCO 3.3.6.4 Suppression Pool Makeup (SPMU) System Instrumentation The LAR states that the SPMU system provides water from the upper containment pool to the suppression pool, by gravity flow, after a LOCA to ensure that primary containment temperature and pressure design limits are met.

For instrumentation that has the potential for a configuration in which trip capability is not maintained, a Note was added to the CT which prohibits applying a RICT when trip capability is not maintained.

The logic trip arrangement, redundancy, and diverse, inputs causing a trip of the SPMU system, are discussed and shown in USAR Section 7.3.1.1.10, CPS TS LCO 3.3.6.4, Table 3.3.6.4-1, and reflected in Attachment 5 of the LAR.

The NRC staff finds that the SPMU design has sufficient redundancy, diversity, and DID to protect against CCFs and potential single failure during the RICT for the CPS I&C systems and does not rely on manual actions as the only diverse means; therefore, there is no over-reliance on programmatic activities as compensatory measures.

3.2.2.2.8 LCO 3.3.6.5 Relief and Low Low Set (LLS) Instrumentation The LAR states that the safety relief valves (SRVs) prevent overpressurization of the nuclear steam system. Instrumentation is provided to support two modes (in addition to the ADS mode of operation for selected valves) of SRV operation.

The logic trip arrangement, redundancy, and diverse, inputs causing a trip of the LLS instrumentation are discussed and shown in USAR Section 7.3.1.1.1.4, 7.3.1.1.1.4.2, CPS TS LCO 3.3.6.5 and are reflected in Attachment 5 of the LAR.

The NRC staff finds that the LLC design has sufficient redundancy, diversity, and DID to protect against common cause failures and potential single failure during the RICT for the CPS I&C systems and does not rely on manual actions as the only diverse means; therefore, there is no over-reliance on programmatic activities as compensatory measures.

3.2.2.2.9 LCO 3.3.8.1 Loss of Power (LOP) Instrumentation The electrical aspects of the loss of power instrumentation is described in Section 3.2.2.1.1, Loss of Power (LOP) Instrumentation (TS 3.3.8.1), above. The defense-in-depth aspects of concern to instrumentation and controls were evaluated but this section does not repeat the detailed description of electrical and loss of power instrumentation descriptions above.

For instrumentation that has the potential for a configuration in which trip capability is not maintained, a Note was added to the CT which prohibits applying a RICT when trip capability is not maintained.

The logic trip arrangement, redundancy, and diverse, inputs causing a trip of the LOP instrumentation are discussed and shown in USAR Section 8.3.1.1.2, CPS LCO 3.3.8-1, TS Table 3.3.8.1-1, and reflected in attachment 5 of the LAR.

The NRC staff finds that the LOP design has sufficient redundancy, diversity, and DID to protect against common cause failures and potential single failure during the RICT for the CPS I&C systems and does not rely on manual actions as the only diverse means; therefore, there is no over-reliance of programmatic activities as compensatory measures .

3.2.2.2.10 Instrumentation and Control (I&C) Evaluation Conclusion Since the licensee did not propose any changes to the design basis, the independency and the fail-safe principle remain unchanged. The licensee stated in the LAR that the proposed changes did not include any TS loss of function conditions. However, it is recognized that while in an ACTION statement, redundancy of the given protective feature will be temporarily reduced, and, accordingly, the system reliability will be reduced. In the LAR, the licensee stated in the description of proposed changes to the I&C systems that at least one redundant or diverse means (e.g., other automatic features or manual action) to accomplish the safety functions (e.g., reactor trip, safety injection, or containment isolation) remain available during the use of the RICT. The NRC staff reviewed the licensees proposed TS changes to assess the availability of the redundant or diverse means to accomplish the safety function(s). The NRC staff finds that the availability of the redundant or diverse protective features provide sufficient DID to accomplish the safety functions, allowing for the extension of CTs in accordance with the RICT program. The NRC staff finds that the licensees proposed RICT program for the identified I&C systems is in compliance with 10 CFR 50.36(b).

The NRC staff reviewed the licensees proposed TS changes and supporting documentation.

The staff finds that while the I&C redundancy is reduced, the CT extensions implemented in accordance with the RICT program are acceptable because: (1) the capability of the I&C systems to perform their safety functions is maintained, (2) redundant or diverse means to accomplish the safety functions exist, and (3) the licensee will identify and implement risk management actions to monitor and control risk in accordance with the RICT program.

3.2.2.3 Evaluation of Balance of Plant Components The regulation in 10 CFR 50.36(c)(2) requires that TSs contain LCOs, which are the lowest functional capability or performance levels of equipment required for safe operation of the facility. When an LCO is not met, the licensee shall shut down the reactor or follow any remedial action permitted by the TSs. In Attachment 2, the licensee proposed a Note, Not applicable if loss of function, for TS LCO conditions to prohibit entering a RICT during a loss of function condition. However, the proposed change to TS LCO 3.7.6 (main turbine bypass system), Condition A, (requirements of LCO not met) appears to include a TS loss of function and has no such Note. Enclosure 1 to the LAR, Table E1-1, indicates that the design basis success criteria for TS 3.7.6.A requires all six turbine bypass valves to be operable, indicating loss of function with a failure of a single valve. Therefore, the NRC staff asked the licensee to justify that the proposed RICT for TS 3.7.6.A did not include a loss of function.

In its response, dated November 24, 2020, the licensee stated that the purpose of LCO 3.7.6 is to limit peak pressure in the main steam lines and maintain reactor pressure within acceptable limits during events that cause rapid pressurization, which is accomplished by either: (1) the main turbine bypass system, or (2) by limiting reactor power and implementing designated

thermal limits in accordance with the cycle-dependent COLR and modifications to the MCPR limits and LHGR limits. The cycle-specific analyses as documented in the COLR evaluate different combinations of turbine bypass valves (TBVs) that are out-of-service (OOS). The COLR for the current operating cycle supports full power operation with one TBV OOS, but also considers different conditions including all TBVs OOS. As a result, the LCO function of limiting peak pressure in the main steam lines and maintaining reactor pressure within acceptable limits continues to be met under the conditions analyzed in the cycle-specific analyses, which includes all TPVs OOS. Based on the number of TBVs out of service, the correct COLR thermal limit set is selected. By using the correct thermal limit, the analyzed design function of the TBVs will be met and no loss of function results.

The NRC staff finds that the licensees response clarifies that if a turbine bypass valve fails, LCO 3.7.6 function is maintained by limiting reactor power and implementing designated thermal limits in accordance with the cycle-dependent COLR and modifications to the MCPR limits and LHGR limits. Therefore, the staff finds that the licensees response demonstrates that no loss of function exists.

3.2.2.4 Key Principle 2: Conclusions The LAR proposes to modify the TS requirements to permit extending selected CTs using the RICT program in accordance with NEI 06-09-A. The NRC staff finds that extending the selected CTs with the RICT program following loss of redundancy, but maintaining the capability of the system to perform its safety function, is an acceptable reduction in DID provided that the licensee identifies and implements RMAs in accordance with the RICT program during the extended CT.

Quantitative risk analysis, qualitative considerations including compensatory measures, and retaining the current CT for loss of all trains of a required system, assure that DID is maintained to assure adequate protection of public health and safety. The NRC staff finds that the proposed changes are consistent with the DID philosophy because:

  • System redundancy (with the exceptions discussed above), independence, and diversity commensurate with the expected frequency and consequences of challenges to the system is preserved.
  • Adequate capability of design features without an overreliance on programmatic activities as compensatory measures is preserved.
  • The intent of the plants design criteria continues to be met.

Therefore, the NRC staff finds that the proposed change to modify the TS requirements to permit extending selected CTs using the RICT program in accordance with NEI 06-09-A meets the second key safety principle of RG 1.177 and is, therefore, acceptable. Additionally, the NRC staff concludes that the change is consistent with the DID philosophy as described in RG 1.174.

3.2.3 Key Principle 3: Evaluation of Safety Margins Section 2.2.2 of RG 1.177, Revision 1, states, in part, that sufficient safety margins are maintained when:

  • Codes and standards or alternatives approved for use by the NRC are met.
  • Safety analysis acceptance criteria in the final safety analysis report (FSAR) are met or proposed revisions provide sufficient margin to account for analysis and data uncertainties.

The licensee is not proposing in this application to change any quality standard, material, or operating specification. Acceptance criteria for operability of equipment are not changed and use of the RICT only when the system(s) retain(s) the capability to perform the applicable safety function(s) ensure that the current safety margins are retained. Safety margins are also maintained if PRA functionality is determined for the inoperable train which would result in an increased CT. Credit for PRA functionality, as described in NEI 06-09-A, is limited to the inoperable train, loop, or component. The reduced but available functionality may support a further increase in the CT consistent with available safety margin. The specified safety function is still being met by the operable train and therefore requires no evaluation of PRA functionality to meet the design basis success criteria.

3.2.3.1 Key Principle 3: Conclusions The NRC staff finds that the design-basis analyses for CPS remain applicable. Although the licensee will be able to have design-basis equipment out-of-service longer than the current TS allow and the likelihood of successful fulfillment of the function will be decreased when redundant train(s) are not available, the capability to fulfill the function will be retained when the available equipment functions as designed. Any increase in unavailability because less equipment is available for a longer time is included in the RICT evaluation and is expected to be insignificant given the relatively short duration of the extended CT. Therefore, sufficient safety margins are maintained with the implementation of the RICT program. The NRC staff concludes that the proposed changes meet the third key safety principle of RG 1.177 and are acceptable.

3.2.4 Key Principle 4: Change in Risk Consistent with the Safety Goal Policy Statement TS Section 5.5.17 Risk Informed Completion Time Program, states that the RICT must be implemented in accordance with NEI 06-09, Revision 0,Risk-Managed Technical Specification (RMTS) Guidelines.

NEI 06-09 provides a methodology for a licensee to evaluate and manage the risk impact of extensions to TS CTs. Permanent changes to the fixed TS CTs are typically evaluated by using the three-tiered approach described in Chapter 16.1 of the SRP, RG 1.177, and RG 1.174, Revision 1. This approach addresses the calculated change in risk as measured by the change in delta core damage frequency (CDF) and delta large early release frequency (LERF), as well as the incremental conditional core damage probability and incremental conditional large early release probability; the use of compensatory measures to reduce risk; and, the implementation of a configuration risk management program (CRMP) to identify risk-significant plant configurations.

The NRC staff evaluated the licensees processes and methodologies for determining that the change in risk from implementation of RICTs will be small and consistent with the intent of the Commissions Safety Goal Policy Statement, as discussed below. The NRC staff evaluated the licensees proposed changes against the three-tiered approach in RG 1.177, Revision 1, for the licensees evaluation of the risk associated with a proposed TS CT change. The results of the staffs review are discussed below.

3.2.4.1 Tier 1: PRA Capability and Insights The first tier evaluates the impact of the proposed changes on plant operational risk. The Tier 1 review involves two aspects: (1) the technical acceptability of the PRA models and their application to the proposed changes, and (2) a review of the PRA results and insights described in the licensees application.

3.2.4.1.1 PRA Technical Acceptability Scope of PRA RG 1.174 states that the scope, level of detail, and technical adequacy of the PRA are to be commensurate with the application for which it is intended and the role the PRA results play in the integrated decision process. The NRCs SE for NEI 06-09 states that the PRA models should conform to the guidance in RG 1.200, Revision 1, An Approach for Determining the Technical Adequacy of Probabilistic Risk Assessment Results for Risk-Informed Activities, January 2017 (Reference 13). The current version is RG 1.200, Revision 2, which clarifies the current applicable American Society of Mechanical Engineers/American Nuclear Society (ASME/ANS) PRA Standard is ASME/ANS RA-Sa-2009, Addenda to ASME RA-S-2008, Standard for Probabilistic Risk Assessment for Nuclear Power Plant Applications (Reference 14). For external hazards for which a PRA is not available, the guidance in NEI 06-09-A allows for the use of bounding analysis of the risk contribution of the hazard for incorporation into the RICT calculation or justification for why the hazard is not significant to the RICT calculation.

According to the LAR, the proposed RICT program is only applicable to operational conditions (or Modes) 1 and 2, therefore, risk evaluations for Modes 3, 4, and 5, are not relevant to the proposed change.

The NRC staff evaluated the PRA acceptability information provided by the licensee in of its submittal, including industry peer review results and the licensees self-assessment of the PRA models for internal events, including internal flooding, and fire, against the guidance in RG 1.200, Revision 2. The licensee screened out all external hazard events, except for seismic, as described in Section 3.2.4.1.2 of this SE, as insignificant contributors to RICT calculations. The CPS PRA model with modifications is used as the CRMP model as described in Section 3.2.4.1.2 of this SE. In addition, the licensee provided a bounding estimate of the seismic CDF and LERF and included those CDF and LERF values in the change-in-risk used to calculate RICTs consistent with the guidance in NEI 06-09-A 3.2.4.1.2 Evaluation of PRA Acceptability for Internal Events and Internal Fires Internal Events PRA (IEPRA) (Includes Internal Flooding)

The CPS PRA is comprised of a full-power, Level 1, IEPRA which evaluates the CDF and LERF risk metrics. The licensee discussed in Enclosure 2 of the LAR that the IEPRA (includes

internal floods) model had been assessed against RG 1.200, Revision 2. The NRC staff evaluated the scope of the PRA including: (1) peer-review history and results, (2) the Appendix X, independent assessment process, (3) credit for FLEX in the PRA, and (4) assessment of key assumptions and key sources of uncertainty. The NRC staff also performed a review of the remaining open facts and observations (F&Os) for the IEPRA, along with the dispositions provided in Enclosure 2 of the LAR and its supplements.

For both the CPS 10 CFR 50.69 (Reference 16) and the CPS TSTF-505 risk-informed applications, the PRA models were reviewed against the current PRA Standard across all technical elements at Capability Category (CC) II. Therefore, the staffs review of the IEPRA (includes internal floods) model for PRA acceptability was performed concurrently with the CPS 10 CFR 50.69 application. A detailed staff evaluation of the IEPRA peer review history is provided in the NRC staffs safety evaluation dated May 19, 2021 (Reference 17). The NRC staffs evaluation of the key assumptions and key sources of uncertainty specific to the TSTF-505 application are provided below.

Based on its review, and applicable precedent provided in the issuance of the SE for CPSs adoption of 10 CFR 50.69, the NRC staff finds that the IEPRA has been peer reviewed consistent with RG 1.200, Revision 2; F&Os were closed consistent with Appendix X guidance of NEI 07-12, Revision 0, Fire Probabilistic Risk Assessment (FPRA) Peer Review Process Guidelines, Draft Version H, November 2008 (Reference 18), as accepted, with conditions by the NRC staff; and any remaining open F&Os have been appropriately assessed for impact on the RICT program. Therefore, the NRC staff concludes that the internal events PRA, including internal flooding, is acceptable for use in the RICT program.

Internal Fire Events PRA The NRC staff review of the CPS fire PRA was based on the results of a full-scope peer review of the fire PRA and two F&Os closure reviews described in LAR Enclosure 2. The full-scope peer review of the fire PRA was performed in April 2018 using the NEI 07-12 process and the guidance in the ASME/ANS RA-Sa-2009 PRA Standard and RG 1.200, Revision 2.

The licensee stated that the 2018 fire PRA peer review F&Os were addressed in subsequent fire PRA updates and the resolutions to the F&Os were reviewed by independent review teams in two separate F&O Closures (December 2018 and November 2019) that included fire PRA F&Os. The second CPS fire PRA F&O closure review performed in November 2019 resulted in closing all finding level F&Os.

Extensive and detailed reviews of fire PRAs undertaken in support of LARs to transition to National Fire Protection Association-805 determined that implementation of some of the complex fire PRA methods often used non-conservative and over-simplified assumptions to apply the method to specific plant configurations. Accordingly, the NRC staff requested the following fire PRA information that did not appear to be addressed by other docketed information.

On October 27, 2020 (Reference 19), the NRC staff requested information about the use of reduced transient fire heat release rates (HRRs) below those prescribed in NUREG/CR-6850, EPRI/NRC Fire PRA Methodology for Nuclear Power Facilities, September 2005 (Reference 20), and NUREG/CR-6850, Supplement 1, Fire Probabilistic Risk Assessment Methods Enhancement, September 2010 (Reference 21), and justification if reduced HRRs were used.

Key factors for justifying reduced HRRs below those prescribed in NUREG/CR-6850 are discussed in guidance provided in the June 21, 2012, letter from Joseph Giitter, NRC, to Biff Bradley, NEI (Reference 22).

In its letter dated November 24, 2020, the licensee explained that for the cable spreading rooms (CSRs), three potential transient fire sizes were assessed (i.e., 60 kW (kilowatt), 145 kW, and 317 kW). The licensee stated that the cited results of fire tests reported in NUREG/CR-6850 for 60 kW, 145 kW, and 317 kW, fires were considered representative for spaces in the CSRs. The licensee explained that detailed fire modeling was performed for each of the three fire sizes and that the results of the fire modeling were averaged, and the average probability of fire damage was used in the fire PRA (i.e., product of the Severity Factor and Non-Suppression Probability).

The licensee justified the use of a reduced HRR by addressing factors described in the NRC letter dated June 21, 2012.

The licensee cited its transient combustible material control procedure and explained that Transient Combustible Permits (TCPs) are required and reviewed by the Fire Marshall and procedures provide specific guidance for storage and transporting combustible materials in Transient Combustible Free Zones. The licensee stated that per procedure, combustible materials are limited in Transient Combustible Free Zones to materials required to support work activity and are immediately removed from the area following completion of the task. The licensee presented a list of the TCPs from the last 4 years for the CSRs showing that the increase in combustible loading in British Thermal Units (BTUs) compared to the BTUs for cable loading for each TCP is only about 1% or lower. The licensee also showed that over this same time period (i.e., since 2016), there have been no compliance issues or violations associated with the use of transient combustibles in the CSRs.

Based on its review, the NRC staff finds the licensees use of reduced HRRs in the CSRs to be acceptable and consistent with NRC guidance because: (1) the reduced HRRs used are based on the results of fire tests reported in NUREG/CR-6850 that represent fires that could happen in the CSRs, (2) transient combustible controls are implemented for the areas where reduced HRRs are credited (i.e., CSRs) and are implemented through a TCP which requires materials to be removed immediately following completion of the task, (3) the historical increase in combustible loading in the CSRs when a TCP is used is very low, and (4) there have been no compliance issues or violations associated with the use of transient combustibles in the CSRs.

On October 27, 2020, the NRC staff requested information about the treatment of sensitive electronics and whether the treatment was consistent with the guidance in Frequently Asked Questions (FAQ) 13-0004, Clarifications on Treatment of Sensitive Electronics, dated December 3, 2013 (Reference 23), including the caveats about configurations that can invalidate the approach (i.e., sensitive electronics mounted on the surface of cabinets and the presence of louver or vents).

In its letter dated November 24, 2020, the licensee explained that its treatment of sensitive electronics is consistent with the guidance in FAQ 13-0004 in which the damage threshold for thermoset cable is used for sensitive electronics within an electrical cabinet. However, the response also explains that the caveats cited in FAQ 13-0004 about configurations that invalidate the approach were not explicitly addressed. The licensee stated that consideration of such configurations should have negligible impact on fire risk due to the functions associated with sensitive electronics (e.g., a single logic channel).

The licensee also stated that a gap in the analysis could exist where the exposed sensitive electronics are beyond the zone of influence (ZOI) of the ignition source determined by thermoset failure criteria allowed by FAQ 13-0004 but within a ZOI defined by the nominal damage criteria for sensitive electronics (i.e., criteria from NUREG/CR-6850). The licensee suggested that its treatment of the potential for fire to grow beyond the analyzed ZOI offset the this identified gap. As further justification of its treatment, the licensee provided an evaluation of a sampling of seven sensitive electronics cabinet configurations and determined that the sensitive electronics: (1) have no impact on a PRA credited function, (2) are not damaged in fire, or (3) failure is already accounted for in the fire PRA scenarios.

On February 26, 2021 (Reference 24), the NRC staff stated its view that the limited sampling was insufficient to determine the impact of the modeling assumption on the RICT calculations and with this observation and others discussed above, and the staff therefore requested justification that the licensees treatment of sensitive electronics will have negligible impact on the RICT calculations.

In its March 23, 2021, response, the licensee described its evaluation of a sampling of cabinet configurations. The licensee explained that a plant walkdown was conducted by the Site Risk Management Engineer and a Senior Reactor Operator to identify sensitive electronics in risk significant areas of the CPS. For each of these areas, the licensee explained that either sensitive electronics were not associated with fire PRA credited equipment or failures of the sensitive electronics are already accounted for by the failures of other targets in the target set (e.g., fire-induced failure of different components that support the same function). The licensee also stated that these insights are representative of sensitive electronics in other areas of the plant not explicitly evaluated as part of the walkdown and that this supports the conclusion that cabinet configurations that invalidate the use of FAQ 13-004 would have negligible impact on fire risk.

Based on its review of the information provided by the licensee, the NRC staff concludes that the licensees approach of using the thermal damage threshold from FAQ 13-0004 for sensitive electronics without explicit consideration of the caveats about cabinet configuration that invalidate the approach is acceptable for the application. It is found acceptable because the licensee showed that sensitive electronics existing in the plant either are not associated with fire PRA credited equipment or their failures are already accounted for by the failures of other targets in the target set in propagating and non-propagating fire scenarios.

On October 27, 2020, the NRC staff requested information about whether minimum joint human error probabilities (HEP) values less than 1E-05 were assumed in the fire PRA. NUREG-1921, EPRI/NRC-RES Fire Human Reliability Analysis Guidelines- Final Report, July 2012 (Reference 25), discusses the need to consider a minimum value for the joint probability of HFEs. NUREG-1921 refers to Table 2-1 of NUREG-1792, Good Practices for Implementing Human Reliability Analysis (HRA), April 2005 (Reference 26), which recommends that joint HEP values should not be below 1E-5. Table 4-4 of Electrical Power Research Institute (EPRI) 1021081, "Establishing Minimum Acceptable Values for Probabilities of Human Failure Events," 2 provides a lower limiting value of 1E-6 for sequences with a very low level of dependence. Therefore, the guidance in NUREG-1921 allows for assigning joint HEPs that are less than 1E-5, but only through assigning proper levels of dependency. The NRC staff also requested the results of a sensitivity study if a minimum joint HEP less than 1E-05 is used in the fire PRA.

2 Available from Electric Power Research Institute, 3420 Hillview Avenue, Palo Alto, California 94304.

In its response dated November 24, 2020, the licensee explained that for fire PRA dependency analysis a minimum joint HEP of 1E-06 was used unless the timeframe for completing one or more actions in the combination was longer than 15 hours1.736111e-4 days <br />0.00417 hours <br />2.480159e-5 weeks <br />5.7075e-6 months <br />. In these cases, a lower minimum joint HEP of 5E-07 was used.

The licensee also explained that a sensitivity study was performed in which a minimum joint HEP of 1E-05 was applied in the sensitivity case and calculated the RICTs for a sample of eight LCOs selected because they represent plant configurations for which the RICTs are most likely to change in the sensitivity case. The results of the sensitivity study show that the calculated RICTs essentially did not change as the decreases in all calculated RICTs are less than 1 percent. The NRC staff finds the licensees application of minimum joint HEP values acceptable because the licensee shows it meets the intent of the above guidance to establish an appropriate minimum joint HEP value, with allowance for further decrease consistent with the level of dependency of HEPs in the combination; and even though the minimum joint HEP value for the fire PRA is set at 1E-06 opposed to 1E-05, the licensees sensitivity study demonstrated that setting the minimum joint HEP for the fire PRA to 1E-05 rather than 1E-6 has a minimal impact on the RICT application.

On October 27, 2020, NRC staff requested information about how well sealed cabinets were treated in the fire PRA. Information was requested about how fire propagation outside of well-sealed motor control centers (MCC) cabinets greater than 440 V was evaluated and whether it was consistent with the NRC guidance in fire PRA FAQ 14-0009, Treatment of Well-Sealed MCC Electrical Panels Greater than 440V, dated April 29, 2015 (Reference 27). Information was also requested about whether well-sealed cabinets less than 440 V are included in the Bin 15 count of ignition sources consistent with guidance in NUREG/CR-6850.

In its November 24, 2020, response, the licensee explained that all MCCs are assumed not to be well-sealed and, therefore, all fires originating from MCC cabinets are assumed to damage external targets. Accordingly, the refinements using the guidance in FAQ 14-0009 were not applied. The licensee also explained all other cabinets are also assumed not to be well-sealed, and therefore, cabinets less than 440 V are included in the Bin 15 count and fires postulated for those cabinets are evaluated for the potential to damage external targets. The NRC staff finds the licensees treatment of well-sealed cabinets consistent with the above guidance.

Based on its review, the NRC staff finds that the licensees fire PRA has been adequately peer reviewed against the current versions of the PRA standard and RG 1.200, that the licensee has adequately closed the F&Os, and the licensee has performed the fire PRA using the most current NRC approved guidance. Therefore, the NRC staff concludes that the fire PRA is technically acceptable to support the RICT program.

3.2.4.1.3 Evaluation of External Hazards The NRC staffs SE for NEI 06-09 states that sources of risk besides internal events and internal fires (i.e., seismic and other external events) must be quantitatively assessed if they contribute significantly to configuration-specific risk. The SE further states that bounding analyses or other conservative quantitative evaluations are permitted where realistic PRA models are unavailable.

In addition, the SE concludes that if sources of risk can be shown to be insignificant contributors to configuration risk, then they may be excluded from the RMTS.

As discussed in Section 3.2.4 of this SE, the PRA models used for the RICT program include contributions from internal events, including internal flooding, and fire events. In addition, the

licensee provided a conservative estimate of the seismic CDF (SCDF) and seismic LERF (SLERF) and will include those CDF and LERF values into the change-in-risk used to calculate RICTs consistent with the guidance in NEI 06-09-A. The licensee addressed the risk from seismic events and other external hazards in the context of this application in Enclosure 4 to the LAR.

In the LAR Enclosure 4, Section 2, the licensee stated that for the overall process, consistent with NUREG-1855, Revision 1, external hazards may be addressed by: (1) screening the hazard on low frequency of occurrence, (2) bounding the potential impact and including it in the decisionmaking, and (3) developing a PRA model to be used in the RMAT/RICT calculation.

The licensee stated that as part of this process the following two aspects of the external hazard contribution to risk should be considered.

  • The first is the contribution from the occurrence of beyond design basis conditions, e.g.,

winds greater than design, seismic events greater than design-basis earthquake, etc.

These beyond design basis conditions challenge the capability of the SSCs to maintain functionality and support safe shutdown of the plant.

  • The second aspect addressed are the challenges caused by external conditions that are within the design basis, but still require some plant response to assure safe shutdown, e.g., high winds or seismic events causing loss of offsite power, etc. While the plant design basis assures that the safety-related equipment necessary to respond to these challenges are protected, the occurrence of these conditions nevertheless causes a demand on these systems that presents a risk.

The NRC staff reviewed Enclosure 4 to the LAR dated April 30, 2020, and supplemental information dated November 24, 2020, to determine the acceptability of the consideration of risk from seismic events and other external hazards for this application.

Seismic Hazard Contribution to the RICT In LAR Enclosure 4, the licensee provided a conservative estimate for the risk from seismic events for use in determining the configuration risk for the RICTs identified in the LAR. The licensee explained in the LAR Enclosure 4, Section 3.0, that RICT calculations will include a risk contribution from seismic events using a seismic penalty approach. A seismic penalty, commonly used in RICT calculations and for estimation of SCDF, is performed using a mathematical convolution of the seismic hazard and plant level seismic capacity curves. For SLERF, the penalty is obtained by multiplying the calculated SCDF by an average seismic conditional large early release probability (CLERP). The licensees approach for including the seismic risk contribution in the RICT calculation is to add a constant SCDF and SLERF to each RICT calculation. Section 3.3.5 of NEI 06-09 states that for stations without external events PRAs, the station should apply one of three acceptable methods to determine external event risk. The second method, used for CPS, is to perform a reasonable bounding analysis which must be case-specific, technically verifiable, and must be shown to be conservative from the perspective of RICT determination. For application to CPS RICT calculations, the licensee proposed to add a SCDF contribution of 6.4E-06 per year and a SLERF contribution of 1.6E-06 per year to the configuration-specific delta risk contribution from internal events (including internal flooding) and internal fire events.

The licensees proposed SCDF estimate is based on using the plant-specific seismic hazard curves developed in response to the Near-Term Task Force Recommendation 2.1 dated March

31, 2014 (Reference 28), and supplemented on August 21, 2014 (Reference 29), and a plant-level high confidence of low probability of failure (HCLPF) capacity of 0.30g (gravity) referenced to peak ground acceleration (PGA). HCLPF is the capacity representing 95 percent confidence that the conditional probability of failure of an SSC is 5 percent or less. The uncertainty parameter for seismic capacity was represented by a combined beta factor of 0.4. The HCLPF parameters used for the CPS SCDF estimate are those cited for the CPS in Table B-2 and C-2 of Results of Safety/Risk Assessment of Generic Issue 199, Implications of Updated Probabilistic Seismic Hazard Estimates in Central and Eastern United States on Existing Plants, dated September 2, 2010 (Reference 30). Approximate SCDF estimates were developed in Reference 30 using a method which includes integrating the mean seismic hazard curve and the mean plant-level fragility curve for each NPP. This method, developed by Kennedy (1997), is discussed in Section 10.8.9 of AMSE/ANS RA-Sa-2009 and has previously been used by the staff in the resolution of GI-194, Implications of Updated Probabilistic Seismic Hazard Estimates, and during reviews of various risk-informed license amendments. The 0.30g PGA value is consistent with the CPS individual plant examination of external events (IPEEEs) review level earthquake. The licensees estimation of the SCDF is performed by convolving the PGA based seismic hazard curve for the CPS site using the geometric mean of the 19 seismic hazard intervals (from 0.0005g to 10g) with the CPS PGA based HCLPF as shown in LAR Enclosure 4, Table E4-2. The NRC staff review finds that the method used to estimate the SCDF is acceptable because it is consistent with the approach used in Reference 30.

As described by the licensee in LAR Enclosure 4, Section 3, the proposed SLERF penalty of 1.6E-06 per year was determined by estimating the average seismic conditional large early release probability (CLERP) at 0.25 and multiplying it by the estimated SCDF of 6.4E-06 per year. The licensee explained that an estimate of the average seismic CLERP was determined using: (1) the average contribution of different accident types to SLERF using fragility information from completed seismic PRAs and generic guidance, and (2) the CLERP for the current CPS internal events PRA model of record for each accident type. The average percent contribution of different accident types to seismic LERF was then multiplied by the internal events PRA CLERP to produce a seismic CLERP for the designated accident types which were in turn used to calculate a sequence-weighted average seismic CLERP. The LAR indicates that the seismic PRA does not produce different accident scenarios from the internal events PRA but rather a different distribution of accident scenario types for seismic events. The LAR further explains that containment isolation failures were evaluated to ensure that random or seismically induced failures leading directly to LERF are insignificant risk contributors. The LAR presents a graphical approach for determining the average contribution of different accident types to SLERF based on fragility information from several cited sources. The graphic resembles an event tree in which the top events and end states are used to define the accident types of interest and the branch point probabilities are used to calculate the percent contribution of each accident type to the total SCDF. The branch point probabilities are determined by the seismic failure of components relevant to the branch points based on review of industry fragility information.

In its supplement dated November 24, 2020, the licensee provided an additional description of how the branch point probabilities in LAR Enclosure 4, Figure E4-1, were determined. The licensee explained that nodal probabilities for the seismic capacities assigned to each node (i.e.,

branch point) of the graphic are calculated using a typical double lognormal fragility probability model. The types of SSCs typical to a given node are discussed in the LAR (e.g., containment structure, RPV supports, DG or control building failures, off-site power, and containment isolation valves). The licensee explained that the seismic capacity was selected from the lower

end of the ranges for over 150 representative capacities compiled from a review of industry studies that include the EPRI 3002000709 report, Seismic Probabilistic Risk Assessment Implementation Guide, December 2013 (Reference 31), Lawrence Livermore National Laboratory report UCID-20571, "Compilation of Fragility Information from Available Probabilistic Risk Assessments," 3 and several plant-specific seismic PRAs performed in response to the NRC staffs 10 CFR 50.54(f) request for information dated March 12, 2012 (ADAMS Accession No. ML12053A340), with regard to Near Term Task Force Recommendation 2.1. The licensee explained that the SCDF fraction for each scenario type was determined by convolving the PGA based seismic hazard curve for the CPS site using the geometric mean of 10 seismic hazard intervals from 0.05g to 3g (which is a more coarse convolution than the convolution used to calculate the total seismic CDF but detailed enough for this use). Based on this convolution, the nominal fraction of seismic CDF for each scenario type was calculated to determine the seismic CLERP as discussed above.

In its supplement dated November 24, 2020, the licensee provided justification that the SLERF penalty for CPS is conservative. The licensee stated that its approach to estimate the SLERF is based on the combination of: (1) an estimated SCDF which is not necessarily conservative, (2) an average seismic CLERP which is estimated conservatively, and (3) use of a SLERF penalty in the RICT calculations which is conservative because the entire CDF and LERF is applied in every RICT calculation. The licensee discussed several conservatisms made in estimating the average seismic CLERP such as: (1) the seismic-induced loss of offsite power is assumed to occur at a probability of 1.0 for the entire seismic hazard curve, and (2) the low end of the capacity distributions compiled from generic sources was used to determine the node probabilities to estimate the nominal fraction of SCDF for each scenario type. The licensee also presented the results of a sensitivity study on the impact of the seismic penalty factor on the calculated RICTs by increasing the seismic penalty in the sensitivity case by a factor of two.

The results show that the seismic penalty factor has a very small impact on the RICT calculated for risk significant configurations (i.e., short RICTs).

The NRC staff finds the licensees development of its seismic CLERP acceptable because it used several conservative assumptions as discussed above and was derived using a combination of industry seismic PRA results and plant-specific information. Additionally, a seismic CLERP of 0.25 is within the range of seismic CLERP values observed by the staff for plants with current seismic PRAs. The NRC staff finds the licensees estimate of and use of its SLERF penalty acceptable for this application because: (1) reasonable or somewhat conservative assumptions are used in its estimation and application of this penalty in the RICT program and (2) the seismic penalty has a minor impact on the calculated RICTs.

The NRC staff finds that for RICTs associated with SSCs credited in the design basis to mitigate seismic events, the licensee's proposed methodology captures the risk associated with seismically induced failures of redundant SSCs because such SSCs are assumed to be fully correlated. By assuming full correlation, the seismic risk for those RICTs will not increase if one of the redundant SSCs is unavailable because simultaneous failure of all redundant trains would be assumed in a seismic PRA. During RICTs for SSCs not credited in the design-basis seismic event, but which could be used when credited SSCs fail, the proposed methodology for considering seismic risk contributions may be non-conservative because the seismically-induced failure of such SSCs during the RICT may not be included in the risk increase.

However, the occurrence and degree of non-conservatism depends on the plant high confidence in low probability of failure (HCLPF) value used for the RICT calculations, as 3 Available at https://www.osti.gov/servlets/purl/5455630.

compared to the HCLPF values for such SSCs. The degree of non-conservatism will be low or nonexistent if the plant HCLPF value is lower than most or all SSCs impacted by a seismic event. During RICTs for SSCs that are not used to mitigate a seismic event, the proposed methodology for considering seismic risk contributions is conservative because the seismically induced failure of such SSCs would not result in a risk increase associated with the plant configuration during the RICT, but the seismic penalty is still included in the calculation.

The licensee also calculated the total (i.e., across the entire hazard curve) seismically induced LOOP frequency of 1.7E-03 per year for CPS, which is about 6 percent of the total unrecovered LOOP frequency addressed in the IEPRA for the CPS. Additionally, the license calculated that the below design basis seismic-induced LOOP frequency is about 4 percent of the total unrecovered LOOP frequency already addressed in the internal events PRA for the CPS. The NRC staff evaluated the analysis and finds that the analysis adequately addresses the impact of seismically induced LOOP and finds it has an insignificant impact on the RICT program calculations.

In summary, the NRC staff finds the licensees proposal to use the SCDF contributions of 6.4E-06 per year, and a SLERF contribution of 1.6E-06 per year acceptable for the licensees RICT program for CPS because: (1) the licensee used the most current site-specific seismic hazard information, (2) the licensee used an acceptably low plant HCLPF value of 0.3g consistent with the information for the CPS in the GI-199 evaluation, (3) reasonable industry seismic PRA results and plant-specific information informed the calculation of the seismic CLERP, and (4) adding the seismic risk contribution to RICT calculations, which assumes the fully correlated failures, is conservative for SSCs credited in seismic events, while any potential non-conservative results for SSCs that are not credited in seismic events is small or nonexistent, as discussed above.

Extreme Winds and Tornado Hazards LAR Enclosure 4, Section 4, discusses the licensees evaluation of the risk from the extreme winds and tornadoes hazards. Evaluation of the extreme winds and tornado hazard has been updated since the licensees IPEEE. The basis for the insignificant impact of extreme winds and tornados (including tornado-generated missiles) for this application relies on the design of SSCs and tornado missile analysis. Table E4-7 of the same enclosure presents the licensees screening criteria used to disposition the risk for the extreme wind and tornado hazards. Table E4-7 indicates that criterion PS2 (Design-basis hazard cannot cause a core damage accident) and PS4 (Bounding mean CDF is < 1E- 6/y (year)) were used to screen the extreme wind and tornado hazard.

In the LAR, the licensee stated that wind damage is bounded by tornadoes and that the tornado wind speed that would be exceeded at a frequency of 1E-07 per year is less than the CPS design wind speed value according to NUREG/CR-4461, Revision 2, Tornado Climatology of the Contiguous United States, February 2007 (Reference 32), using the enhanced Fujita Scale.

The licensee stated that subsequent to its IPEEE screening evaluation of extreme winds it has performed a number of tornado missile protection (TMP) evaluations of CPS. The licensee stated that in 2007 an updated CPS TORMIS-based tornado missile risk analysis was performed. The 2007 TORMIS quantification results exceeded the 1E-06 per year CDF acceptance criterion. However, the evaluation identified the five largest contributors to tornado missile CDF, which, if removed, would reduce the tornado-missile CDF to 6.5E-07 per year.

The licensee stated that subsequent to the study, three of the associated targets were modified by installing missile shielding and two of the associated targets were re-assessed and it was

shown that the existing concrete enclosure and backfill provide adequate protection. Another tornado missile evaluation was performed in 2015-2016 in response to Regulatory Issue Summary 2015-06, Tornado Missile Protection, dated June 20, 2015 (Reference 33), and NRC Enforcement Guidance Memorandum 15-002, Enforcement Discretion for Tornado-Generated Missile Protection Noncompliance, dated June 10, 2015 (Reference 34). The licensee stated that the 2015-2016 tornado-missile evaluation did not alter the results of the conservatively performed 2007 tornado-missile evaluation study.

The licensee additionally stated that the high winds and tornado screening was performed considering SSCs out of service for maintenance and that there was no significant high winds risk impact from allowed maintenance configurations.

Based on the above, the NRC staff finds that the extreme winds and tornado hazard has an insignificant contribution to configuration risk and can be excluded from the calculation of the proposed RICTs.

External Flooding In the LAR Enclosure 4, Section 5, the licensee provided an evaluation of the risk from the external flooding hazard. The evaluation of external flooding hazards has been significantly updated since the licensees IPEEE. The licensees conclusion that the impact of external flooding on this application is insignificant is based on the results documented in the licensees flood hazard reevaluation report (FHRR) for CPS dated March 12, 2014 (Reference 35). Table E4-7 of the LAR Enclosure 4 presents the licensees screening criteria used to disposition the risk for the external flooding hazard. Table E4-7 also indicates that criterion C1 (event damage potential is less than events for which plant is designed) was used to screen the external flood hazard. The NRC staff evaluation issued November 18, 2015 (Reference 36),

concludes that the reevaluted flood hazard mechanisms at Clinton are bounded by the current design-basis.

In LAR Enclosure 4, Section 5, the licensee stated that the results of the FHRR show that flooding from all mechanisms except local intense precipitation (LIP) are bounded by the current LB and the plant response is considered adequate. In its CPS Mitigating Strategies Assessment dated March 24, 2016 (Reference 37), the licensee identified that the model used to develop the LIP flood-causing mechanism was found to incorrectly simulate rain-on-buildings.

The licensees revised calculation identifies the radwaste building as subject to 1.2 inches of standing water. The licensees March 24, 2016, letter concluded that no safe shutdown SSCs are located in the radwaste building. Therefore, the water leakage into the radwaste building would not impact CPS safety functions. The licensee additionally stated that there are no configuration specific considerations related to the hazard screening discussed above.

Based on the above, the NRC staff finds that the external flooding hazard has an insignificant contribution to configuration risk and can be excluded from the calculation of the proposed RICTs.

Other External Hazards The licensee provided its assessment of the external hazard risk for the RICT program in LAR , Information Supporting Justification of Excluding Sources of Risk Not Addressed by the PRA Models. In Enclosure 4, the licensee stated that this assessment is based on an update of the CPS IPEEE external hazard screening evaluation. The licensee listed the

hazards assessed in LAR Enclosure 4, Table E4-7. The NRC staff notes that this list is essentially the same list of hazards as presented in Table 4-1 of NUREG-1855, Revision 1. The NRC staff finds that the list of external hazards considered by the licensee is consistent with the hazards listed in Appendix 6-A of the ASME/ANS RA-Sa-2009 PRA Standard, which is endorsed in RG 1.200, Revision 2. NRC staff also notes that the Initial Preliminary Screening criteria and Progressive Screening criteria used and presented in LAR Table E4-8 are the same criteria presented in Supporting Requirements EXT-B1 and EXT-C1 of the ASME/ANS PRA Standard for screening external hazards, as endorsed by RG 1.200, Revision 2.

In LAR Table E4-7 and the supplement to the LAR dated November 24, 2020, the licensee provided a screening disposition for each non-seismic external hazard as well as other hazards and concluded that no unique PRA model for these hazards is required in order to assess configuration risk for the RICT program.

The licensee explained for the snow hazard that the CPS USAR addresses design snow and ice loads using the latest hazard information. The licensee also identified that snow or ice loading is screened using criteria in LAR Enclosure 4, Table E4-8; criterion C1 (event damage potential is less than events for which the plant is designed), and because it is a slow developing event, criterion C5 (event develops slowly, allowing adequate time to eliminate or mitigate the threat). The licensee explained that RMAs such as those described in the stations adverse weather procedures will ensure that the assumptions that resulted in screening the hazard will continue to be valid during the proposed RICTs. The licensee explained for the sand or dust storm hazard that CPS is not located in an area that is impacted by sand or dust storms.

The licensee also identified that in addition to criterion C1 that criterion C3 also applies to this hazard (event cannot occur close enough to the plant to affect it). The licensee explained for the ice cover hazard that the CPS USAR stipulates that the submerged location of the ultimate heat sink (UHS) pond suction prevents ice formation or ice jams from affecting the performance of the UHS. The licensee also explained that scheduled periodic reviews, as discussed in NEI 00-04, will be conducted to evaluate new insights from available information. If it is determined that there are changes that can impact categorization, the risk information and the categorization process will be updated. NRC staff finds that the bases for screening the snow, sand or dust storm, and ice cover hazards are acceptable because they consider the as-built, as-operated plant, use current hazard information, and will be updated if changes that can impact categorization are identified from periodic reviews.

The NRC staffs review of the information in the submittal as supplemented finds that the contributions from the other external hazards have an insignificant contribution to configuration risk and can be excluded from the calculation of the proposed RICTs because they either do not challenge the plant or they are bounded by the external hazards analyzed for the plant.

External Hazards Conclusion The NRC staff concludes that the licensee's approach for considering the impact of seismic events, non-seismic external hazards and other hazards for the CPS in the RICT calculations is acceptable because the licensee included a technically acceptable quantitative assessment of the seismic risk for the CPS and configuration specific tornado missile risk for the CPS consistent with the guidance in the NEI 06-09 and demonstrated the insignificant contribution to configuration risk from other external hazards on the proposed RICTs.

3.2.4.1.4 PRA Results and Insights The proposed change implements a process to determine TS RICTs rather than specific changes to individual TS CTs. NEI 06-09-A indicates that periodic assessment should be performed of the risk incurred due to operation beyond the front stop CTs resulting from implementation of the RICT program and comparison to the guidance of RG 1.174, Revision 3, for small increases in risk.

NEI 06-09-A further stipulates that configuration risk should be assessed to determine the RICT and establishes the criteria for incremental core damage probability (ICDP) and incremental large early release frequency (ILERP) on which to base the RICT. An ICDP of 1E-5 and an ILERP of 1E-6 are used as the risk measures for calculating individual RICTs. These limits are consistent with NUMARC 93-01, Revision 4F Industry Guideline for Monitoring the Effectiveness of Maintenance at Nuclear Power Plants, dated April 27, 2018 (Reference 38).

NEI 06-09-A as modified by the limitations and conditions in the associated SE requires that the cumulative impact of implementation of an RMTS be periodically assessed and shown to result in: (1) a total risk impact below 1E-5/reactor-year for changes to CDF, (2) a total risk impact below 1E-6/year for changes to LERF, and (3) the total CDF and total LERF must be reasonably shown to be less than 1E-4/reactor-year and 1E-5/reactor-year, respectively. The licensee indicated in Enclosure 5 of the submittal that the estimated total CDF and LERF meet the 1E-4/reactor-year CDF and 1E-5/reactor-year LERF criteria of RG 1.174 consistent with the guidance in NEI 06-09-A and that these guidelines will be satisfied for implementation of a RICT.

On October 27, 2020, the NRC staff requested a summary of how the SOKC investigation was performed in the baseline PRAs supporting the TSTF-505 application and how it will be addressed in risk metrics used in the RICT application. In its response dated November 24, 2020, the licensee showed that the combined impact on internal and fire events is a 1.5 percent increase in CDF and 0.6 percent increase in LERF and that there is adequate margin between the total mean CDF and LERF values (i.e., 8.86E-05 and 7.11E-06, respectively) and RG 1.174 guidelines to accommodate further increase before the total threshold vales are reached.

These updated values demonstrate that the estimated total CDF and LERF meet the 1E-4/reactor-year CDF and 1E-5/reactor-year LERF criteria of RG 1.174, consistent with the guidance in NEI 06-09-A.

The licensee has incorporated NEI 06-09-A in the RICT program of TS 5.5.17 and, therefore, it can calculate the RICT appropriately to assess and ensure that any risk increases are small and in accordance with RG 1.174, Revision 3, and the intent of RG 1.177, Revision 1. Also, the estimate of the current total CDF and LERF meets the intent of the RG 1.174, Revision 3, acceptance guidelines. Therefore, the NRC staff finds that the licensees RICT program is consistent with NEI 06-09-A guidance and is acceptable.

3.2.4.1.5 Key Assumptions and Uncertainty Analyses Using PRAs to evaluate TS changes requires consideration of the assumptions made within the PRA that can have a significant influence on the ultimate acceptability of the proposed changes.

The licensee considered PRA modeling uncertainties and their potential impact on the RICT program and identified, as necessary, applicable RMAs to limit the impact of these uncertainties. In Enclosure 9 of the LAR, the licensee discussed key assumptions and key sources of uncertainty along with providing the dispositions for impact on the risk-informed

application or applicable sensitivities. The licensees evaluation the CPS PRA model to identify the key assumptions and key sources of uncertainty for this application consistent with RG 1.200 definitions, using sensitivity and importance analyses to place bounds on uncertain processes, to identify alternate modeling strategies, and to provide information to users of the PRA.

In regard to the fire PRA, the licensee stated in LAR Enclosure 9, Section 4, that it used guidance from NUREG-1855, Revision 1, and guidance for fire PRA development including NUREG/CR-6850, EPRI/NRC-RES Fire PRA Methodology for Nuclear Power Facilities, to address the fire PRA uncertainty analysis. The licensee explained that plant-specific assumptions and sources of modeling uncertainty identified from the fire PRA were considered, as well generic industry sources of uncertainty from EPRI TR 1026511. The licensee explained that the fire PRA uncertainties were organized by the fire PRA topics presented in NUREG/CR-6850.

The licensee explained that it has used consensus modeling approaches from NUREG/CR-6850 and guidance from NUREG-7150 4 and fire PRA FAQs. In LAR Enclosure 9, Table E9-3, the licensee dispositioned the fire PRA modeling uncertainties stating in each case that they do not present a significant impact on the RICT calculations and no RMAs (or additional RMAs) were required to address the uncertainty.

The NRC staff reviewed the licensees dispositions for the RICT application provided in LAR , Tables E9-1, E9-2, and E9-3, to understand key assumptions and sources of modeling uncertainty and noted sources of uncertainty that did not appear to fully dispositioned and appeared to have the potential to impact the RICT calculations. In the LAR, the licensee stated that certain components were conservatively assumed to be failed because of the lack of cable data in certain locations, and because of this it performed two sensitivity studies to determine the impact. These components were referred to as unknown location (UNL) components. The licensee stated that based on the sensitivity results, it concluded that its approach does not introduce any epistemic uncertainties that would impact the RICT calculations. However, the licensee did not provide the results of the uncertainty analysis in the LAR. On October 27, 2020,, the NRC staff requested identification of the systems or components that were assumed to fail because of the lack of cable routing and requested the licensee to provide justification that this treatment has an inconsequential impact on the RICT program.

In its response dated November 24, 2020, the licensee identified the UNL components and stated that [m]ost of the UNL components are associated with systems that are not within the scope of the TSTF-505 RICT program and do not serve support function for the TSTF-505 RICT LCOs. The licensee also explained that it performed a sensitivity study of the impact of this treatment on calculated RICTs for a sampling of TS LCOs selected for this study because their estimated RICTs are less than 30 days. In the sensitivity case, the RICT calculation was based on fire PRA modeling in which all UNL failures were removed. The NRC staff notes that this removal of the UNL component failures has the effect of eliminating the possible impact of the conservatism associated with modeling the UNL components. Therefore, the NRC staff concludes that the UNL components will not pose a significant impact to the RICT program.

On October 27, 2020, the NRC staff requested that the licensee justify that the uncertainty associated with post-fire HRA modelling has an inconsequential impact on calculated RICTs for 4 Available at https://www.nrc.gov/reading-rm/doc-collections/nuregs/contract/cr7150/

components supporting TS LCO conditions in the RICT program. In its November 24, 2020, letter, the licensee responded that it evaluated FPRA HRA uncertainty as a part of its parametric uncertainty evaluation. Furthermore, the licensee presented the results of a sensitivity study for a set of TS LCOs to determine the impact of using point-values rather than parametric mean values on the calculated RICT values based on CDF. Based on the above, the NRC staff finds the licensees treatment of post-fire HRA modeling is consistent with guidance in NUREG-1855, Revision 1 and is therefore acceptable.

Based on the above, the NRC staff concludes the licensee performed an adequate assessment to identify the potential key sources of uncertainty, and key assumptions consistent with the guidance in NUREG-1855 and associated EPRI TR-1016737 and EPRI TR-1026511.

Therefore, the NRC staff finds that the licensee has satisfied the guidance in RG 1.177, Revision 1 (Sections 2.3.4 and 2.3.5), and RG 1.174, Revision 3 (Section 2.2.2), and that the identification of assumptions and treatment of model uncertainties for risk evaluation of extended CTs is appropriate for this application and consistent with the guidance identified in NEI 06-09-A.

PRA Scope and Acceptability Conclusions Based upon its review, the NRC staff finds that the licensee (1) has reviewed the PRA using endorsed guidance and adequately resolved all identified issues, (2) has established a periodic update and review process to update the PRA and associated CRMP model to incorporate changes made to the plant and PRA methods and data consistent with the RICT program, and (3) will calculate RICTs using NRC-accepted PRA methods. Therefore, the NRC staff concludes that the licensee has and will maintain a PRA that is technically adequate to support implementation of the RICT program.

Based on the above, the NRC staff finds that the licensee has satisfied the intent of RG 1.177, Revision 1, and RG 1.174, Revision 3, and that the scope of the PRA model and the use of a bounding analysis for seismic events is appropriate for this application.

3.2.4.1.6 Application of PRA Models in the RICT Program Table E1-1 in Enclosure 1 to the LAR, as supplemented by the licensee in its letters dated November 24, 2020, and March 23, 2021: (1) identifies each TS LCO condition in scope of the RICT program and, the SSCs covered by the LCO, as applicable, (2) indicates whether the SSC is modeled in the PRA, and (3) for the cases in which the SSCs are not explicitly modeled, explains how the PRA uses surrogate events that bound the function(s) of the TS LCO SCC(s).

The NRC staff noted for some LCOs identified in Table E1-1 of Enclosure 1 to the LAR, the licensee explained that the associated SSCs are not modeled in the PRAs but will be considered using a surrogate event. For certain LCOs, it was not clear to NRC staff whether the surrogate PRA modeling will be adequate to support the RICT calculations. The LAR, in Table E1-1 indicates that the relief function is not modeled and, therefore, surrogate modeling will be used. On October 27, 2020, the NRC staff requested clarification of the surrogate modeling that will be used to model TS LCO 3.3.6.5, Relief and Low-Low Set (LLS) Instrumentation, Condition A (one trip system inoperable). Specifically, NRC staff requested: (1) confirmation of which SSCs for this LCO are not explicitly modeled in the PRAs, (2) explanation of the surrogate modeling that will be used for the SSCs, and (3) justification that the surrogate modelling appropriately represents the failure of the design function associated with TS LCO Condition A. In its response dated November 24, 2020, the licensee clarified that the relief (or

overpressure) function of the SRVs is modeled in the PRAs, but that the pressure instrumentation providing the signal for the SRVs to open on high reactor pressure is not modeled. Therefore, both the relief and low-low set instrumentation (which open SRVs at lower pressure) is not included in the PRA models. The licensee explained that the two LLS SRVs (one on Division 1 and the other on Division 2) will be used as a conservative surrogate for the relief and LLS instrumentation. The NRC finds that the licensees surrogate modeling of the relief and LLS instrumentation serves as an appropriate substitute and appropriately represents the failure of the design function associated with TS LCO 3.3.6.5 Condition A.

Risk Assessment Approaches and Methods Changes to the PRA are expected to occur over time to reflect changes in PRA methods and changes to the as-built, as-operated, and maintained plant to reflect the operating experience at the plant as specified in RG 1.200, Revision 2. Changes in PRA methods are addressed by constraint e. of TS Administrative Section 5.5.17:

The risk assessment approaches and methods shall be acceptable to the NRC.

The plant PRA shall be based on the as-built, as-operated, and maintained plant; and reflect the operating experience at the plant, as specified in Regulatory Guide 1.200, Revision 2. Methods to assess the risk from extending the Completion Times must be PRA methods used to support this license amendment, or other methods approved by the NRC for generic use; and any change in the PRA methods to assess risk that are outside these approval boundaries require prior NRC approval.

The NRC staff finds that this constraint is acceptable because it adequately implements the RICT program using models, methods, and approaches consistent with applicable guidance that are acceptable to the NRC.

Credit for FLEX The NRC staffs memorandum dated May 30, 2017, Assessment of the Nuclear Energy Institute 16-06, Crediting Mitigating Strategies in Risk-Informed Decision Making, Guidance for Risk-Informed Changes to Plants Licensing Basis (Reference 39), provides the NRC staffs assessment of challenges to incorporating FLEX equipment and strategies into a PRA model in support of risk-informed decisionmaking in accordance with the guidance of RG 1.200, Revision 2. The review of the FLEX strategies and modeling for the PRA was performed as a combined effort with the CPS LAR for adoption of 10 CFR 50.69, which the NRC staff approved previously. The basis for acceptability is documented in the SE for 10 CFR 50.69 and the conclusions apply to this SE as well.

3.2.4.2 Tier 2: Avoidance of Risk-Significant Plant Configurations As prescribed in RG 1.177, Revision 1, the second tier provides that a licensee should provide reasonable assurance that risk-significant plant equipment outage configurations will not occur when specific plant equipment is taken out-of-service in accordance with the proposed TS change.

NEI 06-09-A does not permit voluntary entry into high-risk configurations, which would exceed instantaneous CDF and LERF limits of 1E-3/year and 1E-4/year, respectively. The guidance in NEI 06-09-A specifies that if the instantaneous CDF and LERF limits are exceeded for emergent

conditions, then implementation of RMAs is required. It further requires implementation of RMAs when the actual or anticipated risk accumulation during a RICT will exceed one-tenth of the ICDP or ILERP limit (the RMAT). Such RMAs may include rescheduling planned activities to lower risk periods or implementing risk-reduction measures. The limits established for entry into a RICT and for RMA implementation are consistent with the guidance of NUMARC 93-01, Revision 4F, endorsed by RG 1.160, Revision 4 5, as applicable to plant maintenance activities.

The RICT program requirements and criteria are consistent with the principle of Tier 2 to avoid risk-significant configurations.

Consistent with NEI 06-09-A, Enclosure 12 of the LAR identifies three kinds of RMAs:

  • actions to provide increased risk awareness and control,
  • actions to reduce the duration of maintenance activities, and
  • actions to minimize the magnitude of the risk increase).

The LAR also explains that RMAs will be implemented, in accordance with current plant procedures, no later than the time at which the ICDP or ILERP is reached and under emergent conditions when the instantaneous CDF and LERF thresholds are exceeded.

Based on the licensees incorporation of NEI 06-09-A in the TS as discussed in LAR and use of RMAs as discussed in LAR Enclosure 12, Risk Management Actions and the licensee supplements, and because the proposed changes are consistent with the guidance of RG 1.174, Revision 3, and RG 1.177, Revision 1, the NRC staff finds that the licensees Tier 2 program is acceptable and supports the proposed implementation of the RICT program.

3.2.4.3 Tier 3: Risk-Informed Configuration Risk Management The third tier provides that a licensee should develop a program that ensures that the risk impact of out-of-service equipment is appropriately evaluated prior to performing any maintenance activity.

NEI 06-09-A specifies that the RMTS risk assessment process should be integrated into station-wide work control processes and defines the necessary attributes of the RMTS program structure. In the conduct of RMTS, procedural guidance is required for conducting and using the results of the risk assessment. In Enclosure 8 of the LAR, Attributes of the Real-Time Risk Model, the licensee confirms that future changes made to the baseline PRA model, changes made to the baseline PRA model for translation to the online model, and changes made to the online model configuration files are controlled and documented by plant procedures.

Based on the licensees incorporation of NEI 06-09-A, in the TS, as discussed in LAR and the use of RMAs as discussed in LAR Enclosure 12, Risk Management Actions, as supplemented, and because the proposed changes are consistent with the Tier 3 guidance of RG 1.177, Revision 1, the NRC staff finds that the proposed changes are acceptable.

5 Available at https://www.nrc.gov/docs/ML1822/ML18220B281.pdf

3.2.4.4 Key Principle 4: Conclusions Based upon its review, the NRC staff concludes that the licensee has demonstrated the technical acceptability and scope of its PRA models that can support implementation of the RICT program for determining CTs. The licensee has properly considered key assumptions and sources of uncertainty. The licensees risk metrics are consistent with the approved methodology of NEI 06-09-A and the acceptance guidance in RG 1.177 and RG 1.174. The RICT program is controlled administratively through plant procedures and training. The RICT program follows the NRC-approved methodology in NEI 06-09-A. The NRC staff concludes that the RICT program satisfies the fourth key safety principle of RG 1.177 and is, therefore, acceptable.

3.2.5 Key Principle 5: Performance Measurement Strategies - Implementation and Monitoring Program RG 1.177, Revision 1, and RG 1.174, Revision 3, establish the need for an implementation and monitoring program to ensure that extensions to TS CTs do not degrade operational safety over time and that no adverse degradation occurs due to unanticipated degradation or common cause mechanisms. An implementation and monitoring program is intended to ensure that the impact of the proposed TS change continues to reflect the reliability and availability of SSCs impacted by the change. Revision 3 of RG 1.174 states that monitoring performed in conformance with the Maintenance Rule, 10 CFR 50.65, can be used when the monitoring performed is sufficient for the SSCs affected by the risk-informed application. According to LAR 1, the SSCs in the scope of the RICT program are also in the scope of the Maintenance Rule. In its letter dated November 24, 2020, the licensee described the approach and methods used for SSC performance monitoring as described in Regulatory Position C.3.2 referenced in RG 1.177 for meeting the fifth key safety principle. Furthermore, in Enclosure 11 of the LAR, the licensee confirmed that the cumulative risk is calculated at least every refueling cycle, but the recalculation period does not exceed 24 months, which is consistent with NEI 06-09-A. This evaluation assures that RMTS program implementation meets RG 1.174 guidance for small risk increases.

The NRC staff concludes that the RICT program satisfies the fifth key safety principle of RG 1.177, Revision 1, and RG 1.174 b, by, in part, monitoring the average annual cumulative risk increase as described in NEI 06-09 and using this average annual increase to ensure the program as implemented meets RG 1.174 guidance for small risk increases therefore, is acceptable. Additionally, the NRC staff concludes that the RICT program satisfies the fifth key safety principle of RG 1.177, Revision 1, and RG 1.174, because, in part, all the affected SSCs are within the Maintenance Rule program which can be used to monitor changes to the reliability and availability of these SSCs.

3.3 Variations from TSTF-505 The NRC staff evaluated the proposed use of RICTs in the variations stated above in Section 2.2.4 of this SE in conjunction with evaluating the proposed use of RICTs in each of the individual LCO, Required Actions, and CTs stated above in Section 2.2.3. The NRC staffs evaluation of the licensees proposed use of RICTs in the variations against the key safety principles is discussed above in Sections 3.2.1 through 3.2.5. Based on the above Sections 3.2.1 through 3.2.5, the NRC staff finds that each of the five key principles in RG 1.177, Revision 1, and RG 1.174, Revision 3, have been met. Evaluation of the acceptability of the specific proposed use of RICTs is included below.

3.3.1 Application of the RICT Program to Modified Conditions, Required Actions, and CTs Section 2.2.4.1 of this SE discusses changes proposed in the LAR that modify CTs to permit the application of a RICT.

Condition 3.6.1.C, One or more containment air locks inoperable for reasons other than Condition A or B.

  • LCO 3.6.5.2, states, The drywell air lock shall be OPERABLE. Condition 3.6.5.2.C, Drywell air lock inoperable for reasons other than Condition A or B.
  • Modified CTs in LCOs 3.3.5.1, 3.3.5.3, 3.3.6.1, 3.3.6.3, and 3.3.8.1 are evaluated in Section 3.1.2.3, Evaluation of Instrumentation and Control Systems.

For Condition 3.6.1.2.C, the potential for containment leakage beyond allowable limits must be assessed to ensure no loss of containment function is associated with the air lock inoperability.

The licensees proposed change to the associated Action C.3 permits consideration of the RICT for restoration of the affected airlock to operable status only when (C.1) action to evaluate overall containment leakage rate per LCO 3.6.1.1 has been immediately initiated using current airlock test results and (C.2) one air lock door is closed. These conditions provide reasonable assurance that any loss of function condition would be detected and preclude usage of the RICT. The licensee proposed the following TS Conditions to add the RICT program modified by a note that states, Not applicable if leakage exceeds limits or if loss of function. This approach retains the existing requirements and limits the use of a RICT to conditions in which the function can still be performed. The licensee must justify that the required function can still be performed absent an additional failure when a RICT is applied. Therefore, the proposed change to Action 3.6.1.2.C.3 is acceptable.

For Condition 3.6.5.2.C, the potential for containment leakage beyond allowable limits must be assessed to ensure no loss of containment function is associated with the drywell air lock inoperability. The licensees proposed change to the associated Action C.2 permits consideration of the RICT for restoration of the affected air lock to operable status only when (C.1) a door has been verified closed. These conditions provide reasonable assurance that any loss of function condition would be detected and preclude usage of the RICT. The licensee proposed the following TS Conditions to add the RICT program modified by a note that states, Not applicable if leakage exceeds limits or if loss of function. This approach retains the existing requirements and limits the use of a RICT to conditions in which the function can still be performed. The licensee must justify that the required function can still be performed absent an additional failure when a RICT is applied. Therefore, the proposed change to Action 3.6.5.2.C.2 is acceptable.

3.3.2 Application of the RICT to Additional ACTIONS Requirements Section 2.2.4.2 of this SE discusses changes proposed in the LAR that are not Actions listed in TSTF-505. Additional Actions proposed in LCO 3.3.6.4 are evaluated in Section 3.1.2.3.

Additional Actions proposed in LCO 3.8.9 are evaluated in Section 3.1.2.2, Evaluation of Electrical Power Systems.

Condition 3.6.1.6.A applies when one LLS valve is inoperable. Table E1-1 states the design success criterion of Condition 3.6.1.6.A is four of five LLS valves are operable to fulfill the safety

function. In Attachment 4 of the LAR, the licensee identified and provided additional justification for which the LAR proposed applying the RICT program, that varies from TSTF-505, Revision 2:

Industry guidance developed by the TSTF indicates that this action was excluded because the traveler will not modify Required Actions for systems that do not affect CDF or LERF or for which a RICT cannot be quantitatively determined.

However, CPS proposes to apply a RICT to this action because the function is modeled in the PRA and can be directly included in the RTR tool for the RICT program. As stated in the CPS TS Bases for Required Action A.1, with one LLS valve inoperable, the remaining operable LLS valves are adequate to perform the designed function.

Considering Action 3.6.1.6.A.1 and the associated design success criterion, the NRC staff finds that there is reasonable assurance that the existing requirement allows the use of a RICT for the condition in which the function can still be performed. Based on the above, the NRC staff determines that the proposed change to Action 3.6.1.6.A.1 is acceptable.

3.4 TS Administrative Controls Section The NRC staff reviewed the licensees proposed addition of a new program, the RICT program, to the Administrative Controls section of the TS. The NRC staff evaluated the elements of the new program to ensure alignment with the requirements in 10 CFR 50.36(c)(5) and to ensure the programmatic controls are consistent with the RICT program described in NEI 06-09-A.

TS 5.5.17 requires that the RICT program be implemented in accordance with NEI 06-09-A.

This is acceptable because NEI 06-09-A establishes an appropriate framework for an acceptable RICT program.

The TS states that a RICT may not exceed 30 days. The NRC staff determined that 30-day limit is appropriate because it allows sufficient time to restore SSCs to operable status while avoiding excessive out-of-service times for TS SSCs.

The TS states that the RICT may only be used in Modes 1 and 2. This provision ensures that the RICT is only used for determination of CDF and LERF for modes of operation modeled in the PRA.

The TS requires that while in a RICT, any change in plant configuration as defined in NEI 06 A must be considered for the effect on the RICT. The TS also specifies time limits for determining the effect on the RICT. These time limitations are consistent with those specified in NEI 06-09-A.

The TS contains requirements for the treatment of CCFs for emergent conditions in which the common cause evaluation is not complete. The requirements are to either: (1) numerically account for the increased probability of CCF or (2) to implement RMAs that support redundant or diverse SSCs that perform the functions of the inoperable SSCs and, if practicable, reduce the frequency of initiating events that challenge the function(s) performed by the inoperable SSCs. Key Principle 2 of risk-informed decisionmaking is intended to assure that the change is consistent with DID philosophy. The seven considerations supporting the evaluation of the impact of the change on DID are discussed in RG 1.174, including one to preserve adequate defense against potential CCF. The NRC staff finds that numerically accounting for an

increased probability of failure will shorten the estimated RICT based on the particular SSCs involved, thereby limiting the time when a CCF could affect risk. Alternatively, implementing actions that can increase the availability of other mitigating SSCs or decrease the frequency of demand on the affected SSCs will decrease the likelihood that a CCF could affect risk. The NRC staff concludes that both the quantitative and the qualitative actions minimize the impact of CCF and, therefore, support meeting Key Principle 2 as described in RG 1.174. These methods either limit the exposure time, help ensure the availability of alternate SSCs, or decrease the probability of plant conditions requiring the safety function to be performed. The NRC staff finds that these methods contribute to maintaining DID because the methods limit the exposure time or ensure the availability of alternate SSCs.

The TS contains a provision that risk assessment approaches and methods used shall be acceptable to the NRC. The plant PRA shall be based on the as-built, as-operated, and maintained plant; and reflect the operating experience at the plant, as specified in RG 1.200, Revision 2. Methods to assess the risk from extending the CTs must be PRA methods used to support this LAR, or other methods approved by the NRC for generic use. As stated in the NRC staffs SE for NEI 06-09-A:

NEI 06-09, Revision 0, requires an evaluation of the PRA model used to support the RMTS against the requirements of RG 1.200, Revision 1, and ASME RA-S-2002, Standard for Probabilistic Risk Assessment for Nuclear Power Plant Applications, for CC II. This assures that the PRA model is technically adequate for use in the assessment of configuration risk. This capability category of PRA is sufficient to support the evaluation of risk associated with OOS SSCs and establishing risk-informed CTs.

TS 5.5.17 was updated to reflect the current revision of RG 1.200 which incorporates ASME RA-S-2002 by reference.

The NRC staffs SE for NEI 06-09-A also states:

As part of its review and approval of a licensees application requesting to implement the RMTS, the NRC staff intends to impose a license condition that will explicitly address the scope of the PRA and non-PRA methods approved by the NRC staff for use in the plant-specific RMTS program. If a licensee wishes to change its methods, and the change is outside the bounds of the license condition, the licensee will need NRC approval, via a license amendment, of the implementation of the new method in its RMTS program. The focus of the NRC staffs review and approval will be on the technical adequacy of the methodology and analyses relied upon for the RMTS application.

The limitation and condition are being relocated from a license condition to the Administrative Controls section of the TS. Proposed TS 5.5.17 restates this limitation and condition from the NRC staffs SE in language that is appropriate for the Administrative Controls section of the CPS TS. This constraint appropriately requires the licensee to utilize the risk assessment approaches and methods previously approved by the NRC and/or incorporated in the RICT program, and requires prior NRC approval for any change in PRA methods to assess risk that are outside those approval boundaries. The NRC staff finds that this requirement is appropriately reflected in the Administrative Controls section of the CPS TS.

The regulations in 10 CFR 50.36(c)(5) require the TS to contain administrative controls providing provisions relating to organization and management, procedures, recordkeeping,

review and audit, and reporting necessary to assure operation of the facility in a safe manner.

The NRC staff has determined that Administrative Controls section of the TS will assure operation of the facility in a safe manner when the facility uses the RICT program. Therefore, the NRC staff has determined that the requirements of 10 CFR 50.36(c)(5) are satisfied.

4.0 ADDITIONAL CHANGES TO THE OPERATING LICENSE The licensee did not propose an additional change to the operating license or commit to implementation items in its TSTF-505 LAR.

5.0

SUMMARY

The NRC staff finds that the licensees proposed implementation of the RICT program for the identified scope of Required Actions is consistent with the guidance of NEI 06-09-A. The licensees methodology for assessing the risk impact of extended CTs, including the individual CT extension impacts in terms of ICDP and ILERP, and the overall program impact in terms of CDF and LERF, is accomplished using PRA models of sufficient scope and technical adequacy based on consistency with the guidance of RG 1.200, Revision 2. For external hazards, which do not have PRA models, the licensee will use bounding analyses in accordance with NEI 06-09-A guidance and TS Administrative Control. The RICT calculation uses the PRA model as translated into the real-time risk model, and the licensee has an acceptable process in place to ensure the quality of the translation. In addition, the NRC staff finds that the proposed implementation of the RICT Program addresses the RG 1.177 defense-in-depth philosophy and safety margins to ensure that they are adequately maintained and includes adequate administrative controls as well as performance monitoring programs.

Paragraph 50.36(a)(1) of 10 CFR states, in part: [a] summary statement of the bases or reasons for such specifications other than those covering administrative controls shall also be included in the application but shall not become part of the technical specifications.

Accordingly, along with the proposed TS changes, the licensee also submitted TS Bases changes that correspond to the proposed TS changes, to provide the reasons for those TSs.

6.0 STATE CONSULTATION

In accordance with the Commissions regulations, the Illinois State official was notified of the proposed issuance of the amendments on May 12, 2021. The State official had no comments.

7.0 ENVIRONMENTAL CONSIDERATION

The amendments change requirements with respect to installation or use of a facilitys components located within the restricted area as defined in 10 CFR Part 20. The NRC staff has determined that the amendments involve no significant increase in the amounts, and no significant change in the types, of any effluents that may be released offsite, and that there is no significant increase in individual or cumulative occupational radiation exposure. The Commission has previously issued a proposed finding that the amendments involve no significant hazards consideration (85 FR 36435, June 16, 2020), and there has been no public comment on such finding. Accordingly, the amendments meet the eligibility criteria for categorical exclusion set forth in 10 CFR 51.22(c)(9). Pursuant to 10 CFR 51.22(b) no environmental impact statement or environmental assessment need be prepared in connection with the issuance of the amendments.

8.0 CONCLUSION

The Commission has concluded, based on the considerations discussed above, that: (1) there is reasonable assurance that the health and safety of the public will not be endangered by operation in the proposed manner, (2) there is reasonable assurance that such activities will be conducted in compliance with the Commissions regulations, and (3) the issuance of the amendment(s) will not be inimical to the common defense and security or to the health and safety of the public.

9.0 REFERENCES

1 Simpson, P.R., Exelon Generation Company, LLC letter to U.S. Nuclear Regulatory Commission, "Application to Revise Clinton Power Station Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b," dated April 30, 2020 (ADAMS Accession No. ML20121A178).

2 Simpson, P.R., Exelon Generation Company, LLC, letter to U.S. Nuclear Regulatory Commission, "Response to Request for Additional Information Regarding License Amendment Requests to Adopt TSTF-505, Revision 2, and 10 CFR 50.69," dated November 24, 2020 (ADAMS Accession No. ML20329A433).

3 Simpson, P.R., Exelon Generation Company, LLC, letter to U.S. Nuclear Regualtory Commission, "Response to Request for Additional Information Regarding License Amendment Request to Adopt TSTF-505, Revision 2," dated March 23, 2021 (ADAMS Accession No. ML21082A268).

4 Technical Specifications Task Force letter to U.S. Nuclear Regulatory Commission, "TSTF-505, Revision 2, TSTF Comments on Draft Safety Evaluation for Traveler TSTF-505, Provide Risk-Informed Extended Completion Times and Submittal of TSTF-505, Revision 2," dated July 2, 2018 (ADAMS Package Accession No. ML18183A493).

5 Golder, J.M., U.S. Nuclear Regulatory Commission, letter to Biff Bradley, Nuclear Energy Institute, "Final Safety Evaluation For Nuclear Energy Institute (NEI) Topical Report (TR)

NEI 06-09, Risk-Informed Technical Specifications Initiative 4b, Risk-Managed Technical Specifications (RMTS) Guidelines," dated May 17, 2007 (ADAMS Accession No. ML071200238).

6 Nuclear Energy Institute, "Risk-Informed Technical Specifications Initiative 4b: Risk-Managed Technical Specifications (RMTS)," NEI 06-09, Revision 0-A, October 2012 (ADAMS Accession No. ML122860402).

7 U.S. Nuclear Regulatory Commission, "An Approach for Determining the Technical Adequacy of Probabilistic Risk Assessment for Risk-Informed Activities," Regulatory Guide 1.200, Revision 2, March 2009 (ADAMS Accession No. ML090410014).

8 U.S. Nuclear Regulatory Commission, "An Approach for Using Probabilistic Risk Assessment in Risk-Informed Decisions on Plant-Specific Changes to the Licensing Basis,"

Regulatory Guide 1.174, Revision 3, January 2018 (ADAMS Accession No. ML17317A256).

9 U.S. Nuclear Regulatory Commission, "An Approach for Plant-Specific, Risk-Informed Decisionmaking: Technical Specifications," Regulatory Guide 1.177, Revision 1, May 2011 (ADAMS Accession No. ML100910008).

10 U.S. Nuclear Regulatory Commission, "Guidance on the Treatment of Uncertainties Associated with PRAs in Risk-Informed Decisionmaking," NUREG-1855, Revision 1, March 2017 (ADAMS Accession No. ML17062A466).

11 U.S. Nuclear Regulatory Commission, "Review of Risk Information Used to Support Permanent Plant-Specific Changes to the Licensing Basis: General Guidance," NUREG-0800, Chapter 19, Section 19.2, June 2007 (ADAMS Accession No. ML071700658).

12 Gullott, D.M., Exelon Generation Company, LLC, letter to U.S. Nuclear Regulatory Commission, "Clinton Power Station, Updated Safety Analysis Report, Revision 21," dated March 31, 2020 (ADAMS Accession No. ML20217L480).

13 U.S. Nulear Regulatory Commission, "An Approach for Determining the Technical Adequacy of Probabilistic Risk Assessment Results for Risk-Informed Activities," Regulatory Guide 1.200, Revision 1, January 2017 (ADAMS Accession No. ML070240001).

14 American Society of Mechanical Engineers/American Nuclear Society, "Standard for Level 1/Large Early Release Frequency Probabilistic Risk Assessment for Nuclear Power Plant Applications, Addendum A to RA-S-2008," PRA Standard ASME/ANS RA-Sa-2009, June 2005.

15 U.S. Nuclear Regulatory Commission, "U.S. Nuclear Regulatory Commission Acceptance on Nuclear Energy Institute Appendix X Guidance 05-04, 07-12, and 12-13, Close-Out of Facts and Observations (F&Os)," dated May 3, 2017 (ADAMS Accession No. ML17079A427).

16 Simpson, P.R., Exelon Generation Company, LLC, letter to U.S. Nuclear Regulatory Commission, "Application to Adopt 10 CFR 50.69, Risk-informed Categorization and Treatment of Structures, Systems, and Components for Nuclear Power Reactors," dated April 30, 2020 (ADAMS Accession No. ML20121A241).

17 Wiebe, J. S., U.S. Nuclear Regulatory Commission, letter to David P. Rhoades, Exelon Generation Company, LLC, "Clinton Power Station, Unit No. 1 - Issuance of Amendment No. 237 Regarding Adoption of 10 CFR 50.69, Risk Informed Categorization and Treatment of Structures, Systems and Components of Nuclear Power Reactors (EPID L 2019 LLA 0098)," dated May 19, 2021 (ADAMS Accession No. ML21090A193).

18 Nuclear Energy Institute, "Fire Probabilistic Risk Assessment (FPRA) Peer Review Process Guidelines, Draft Version H," NEI 07-12, Revision 0, November 2008 (ADAMS Package Accession No. ML17086A431).

19 Wiebe, J.S., U.S. Nuclear Regulatory Commission, e-mail to Ken Nicely, Exelon Generation Company, LLC, "Clinton Nuclear Power Station - Request for Additional Information," dated October 27, 2020 (ADAMS Accession No. ML20307A659).

20 U.S. Nuclear Regulatory Commission, "EPRI/NRC Fire PRA Methodology for Nuclear Power Facilities," NUREG/CR-6850, September 2005 (ADAMS Accession No. ML052580075).

21 U.S. Nuclear Regulatory Commmission, "Fire Probabilistic Risk Assessment Methods Enhancement," NUREG/CR-6850, Supplement 1, September 2010 (ADAMS Accession No. ML203090242).

22 Giitter, J., U.S. Nuclear Regulatory Commission, letter to Biff Bradley, Nuclear Energy Institute, "Recent Fire PRA Methods Review Panel Decisions and EPRI 1022993, Evaluation of Peak Heat Release Rates in Eloectrical Cabinet Fires," dated June 21, 2012 (ADAMS Accession No. ML12171A583).

23 U.S. Nuclear Regulatory Commission, "Close-out of Fire PRA Frequently Asked Question 13-0004 on Clarification Regarding Treatment of Sensitive Electronics," FAQ 13-0004 ,

dated December 3, 2013 (ADAMS Accession No. ML13322A085).

24 Wiebe, J. S., U.S. Nuclear Regulatory Commission, e-mail to Ken Nicely, Exelon Generation Company, LLC, "Clarification of Second Round RAI - Clinton TSTF-505 License Amendment Request," dated February 26, 2021 (ADAMS Accession No. ML21057A101).

25 U.S. Nuclear Regulatory Commission, "EPRI/NRC-RES Fire Human Reliability Analysis Guidelines Final Report," NUREG-1921, July 2012 (ADAMS Accession No. ML12216A104).

26 U.S. Nuclear Regulatory Commission, "Good Practices for Implementing Human Reliability Analysis (HRA)," NUREG-1792, April 2005 (ADAMS Accession No. ML051160213).

27 U.S. Nuclear Regulatory Commisison, "Close-out of Fire PRA Frequently Asked Question 14-0009 on Treatment of Well-Sealed MCC Electrical Panels Greater Than 440V," FAQ 14-0009, dated April 29, 2015 (ADAMS Accession No. ML15114A441).

28 Kaegi, G.T., Exelon Generation Company, LLC, U.S. Nuclear Regulatory Commission, "Clinton Power Station Unit 1, Seismic Hazard and Screening Report (CEUS Sites),

'Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the NTTF Review of the Fukushima DAi-ichi Accident'," dated March 31, 2014 (ADAMS Accession No. ML14091A011).

29 Barstow, J., Exelon Generation Company, LLC, letter to U.S. Nuclear Regulatory Commission, "Supplemental Information Regarding Seismic Hazard and Screening Report (Central and Eastern United States (CEUS) Sites - Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1," dated August 21, 2014 (ADAMS Accession No. ML14234A124).

30 U.S. Nuclear Regulatory Commission, "Results of Safety/Risk Assessment of Generic Issue 199, 'Implications of Updated Probabilistic Seismic Hazard Estimates in Central and Eastern United States on Existing Plants'," dated September 2, 2010 (ADAMS Package Accession No. ML100270582).

31 Electric Power Research Institute, "Seismic Probabilistic Rick Assessment Implementation Guide," EPRI 3002000709, December 2013.

32 U.S. Nuclear Regulatory Commission, "Tornado Climatology of the Contiguous United States," NUREG/CR-4461, Revision 2, February 2007 (ADAMS Accession No. ML070810400).

33 U.S. Nuclear Regulatory Commission, "Tornado Missile Protection," NRC Regulatory Issue Summary (RIS) 2015-06, dated June 10, 2015 (ADAMS Accession No. ML15020A419).

34 U.S. Nuclear Regulatory Commmission, "Enforcement Discretion for Tornado-Generated Missile Protection Noncompliance," NRC Enforcement Guidance Memorandum (EGM) 15-002, June 10, 2015 (ADAMS Accession No. ML15111A269).

35 Exelon Generation Company, LLC, "Clinton Power Station Flood Hazard Reevaluation Report, Enclosure 1," dated March 12, 2014 (ADAMS Accession No. ML14079A420).

36 Govan, T., U.S. Nuclear Regulatory Commission, letter to Bryan Hanson, Exelon Generation Company, LLC, "Clinton Power Station, Unit No. 1 - Correction to Staff Assessment of Response to Request for Information Pursuant to 10 CFR 50.54(f) - Flood-Causing Mechanisms Reevalution (TAC NO. MF3654)," dated November 18, 2015 (ADAMS Accession No. ML15321A034).

37 Kaegi, G. T., Exelon Generation Company, LLC, letter to U.S. Nuclear Regulatory Commission, "Mitigating Strategies Flood Hazard Assessment (MSFHA) Submittal," dated March 24, 2016 (ML16084A859).

38 Vaughan, S., Nuclear Energy Institute, letter to U.S. Nuclear Regulatory Commission, "Submittal of NUMARC 93-01, Rev 4f, 'Industry Guideline for Monitoring the Effectiveness

of Maintenance at Nuclear Power Plants' for NRC Endorsement," dated April 27, 2018 (ADAMS Accession No. ML18120A069).

39 Reisi-Fard, M., memorandum to Joseph Giitter, U.S. Nuclear Regulatory Commission, "Assessment of The Nuclear Energy Institute 16-06, Crediting Mitigating Strategies in Risk-Informed Decision Making, Guidance for Risk-Informed Changes to Plants Licensing Basis," dated May 30, 2017 (ADAMS Accession No. ML17031A269).

Principal Contributors: H. Wagage J. Ashcraft K. West J. Evans V. Goel R. Vettori K. Tetter Date of issuance: June 28, 2021

ML21132A288 OFFICE NRR/DORL/LPL3/PM NRR/DORL/LPL3/LA NRR/DSS/STSB/BC(A) NRR/DSS/SCPB/BC NAME JWiebe SRohrer NJordan BWittick DATE 05/04/2021 05/20/2021 06/01/2021 06/01/2021 OFFICE NRR/DEX/EICB/BC NRR/DEX/EEEB/BC NRR/DEX/EMIB/BC NRR/DRA/APLA/BC NAME MWaters BTitus ABuford RPascarelli DATE 06/28/2021 01/21/2021 04/19/2021 04/28/2021 OFFICE NRR/DRA/APLB/BC NRR/DRA/APLC/BC OGC NRR/DORL/LPL3/BC NAME SRosenberg SVasavada STurk NLO NSalgado DATE 04/28/2021 04/28/2021 06/23/2021 06/28/2021 OFFICE NRR/DORL/LPL3/PM NAME JWiebe DATE 06/28/2021