Category:Letter
MONTHYEARML24285A1422024-10-24024 October 2024 Ltr. to Darwin Kaskaske, Chairman, Kickapoo Tribe of Oklahoma Re CPS Section 106 Consultation ML24285A1462024-10-24024 October 2024 Ltr. to Gena Kakkak, Chairwoman, Menominee Indian Tribe of Wisconsin Re CPS Section 106 Consultation IR 05000461/20244032024-10-24024 October 2024 – Security Baseline Inspection Report 05000461/2024403 ML24285A1482024-10-24024 October 2024 Ltr. to Joseph Rupnick, Chairman, Prairie Band Potawatomi Nation Re CPS Section 106 Consultation ML24285A1472024-10-24024 October 2024 Ltr. to Geoffrey M. Standing Bear, Principal Chief, Osage Nation Re CPS Section 106 Consultation ML24285A1442024-10-24024 October 2024 Ltr. to Estavio Elizondo, Sr., Chairman, Kickapoo Traditional Tribe of Texas Re CPS Section 106 Consultation IR 05000461/20244022024-10-24024 October 2024 – Security Baseline Inspection Report 05000461/2024402 ML24285A1452024-10-24024 October 2024 Ltr. to Gail Cheatham, Kickapoo Tribe of Indians of the Kickapoo Reservation in Ks Re CPS Sect 106 Consult ML24283A1642024-10-23023 October 2024 Summary of the 2024 Environmental Audit Related to the Review of the License Renewal Application Environmental Report (EPID Number L-2024-LNE-0000)(Docket Number:50-461) ML24285A1432024-10-21021 October 2024 Ltr. to Douglas Lankford, Chief, Miami Tribe of Oklahoma Re CPS Section 106 Consultation ML24285A1412024-10-21021 October 2024 Ltr. to Craig Harper, Chief, Peoria Tribe of Oklahoma Re CPS Section 106 Consultation RS-24-093, Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-10-10010 October 2024 Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests ML24275A2442024-10-0303 October 2024 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief, Division of Operating Reactor Licensing ML24215A2932024-09-27027 September 2024 Scoping Summary Letter 05000461/LER-2023-002-01, Reactor Core Isolation Cooling Inoperable Prior to Mode Change2024-09-24024 September 2024 Reactor Core Isolation Cooling Inoperable Prior to Mode Change ML24211A2302024-09-11011 September 2024 – Request for Partial Site Release for Facility Operating License No. NPF-62 IR 05000461/20240112024-09-0909 September 2024 Commercial Grade Dedication Inspection Report 05000461/2024011 RS-24-087, Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors for Clinton Power Station2024-09-0909 September 2024 Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors for Clinton Power Station IR 05000461/20240052024-08-29029 August 2024 Updated Inspection Plan and Assessment Follow-Up Letter for Clinton Power Station (Report 05000461/2024005) ML24222A3952024-08-23023 August 2024 Regulatory Audit Report to Support the Review of the Amendments to Revise Reactor Water Cleanup Valve Isolation Timing ML24222A6772024-08-0909 August 2024 Response to Request for Additional Information for Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition IR 05000461/20240022024-08-0909 August 2024 Integrated Inspection Report 05000461/2024002 ML24220A2772024-08-0707 August 2024 Request for Information for the NRC Quadrennial Comprehensive Engineering Team Inspection: Inspection Report 05000461/2025010 ML24212A2212024-08-0202 August 2024 License Renewal Regulatory Audit Regarding the Environmental Review of the License Renewal Application (EPID Number: L-2024-LNE-0000) (Docket Number: 50-461) ML24157A3242024-07-11011 July 2024 Issuance of Amendment No. 254 Revision of Reactor Water Cleanup Isolation Valve Timing ML24158A0772024-07-0303 July 2024 Notice of Consideration of Approval of Partial Site Release, Public Meeting, and Request for Comments (EPID L-2023-LLA-0088) - Letter ML24163A3252024-06-28028 June 2024 Aging Management Regulatory Audit Plan ML24163A3242024-06-28028 June 2024 LRA - Portal Letter ML24179A3112024-06-27027 June 2024 05000461; Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML24176A0272024-06-25025 June 2024 Confirmation of Initial License Examination, July 2025 RS-24-061, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-06-14014 June 2024 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations ML24079A0762024-05-23023 May 2024 Issuance of Amendments to Adopt TSTF 264 ML24142A3352024-05-21021 May 2024 Quad Cities—Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes ML24290A0942024-05-21021 May 2024 Letter from Rachael Mangum (Achp) to Stephen Koenick (NRC) License Renewal Application for the Clinton Power Station Unit 1 Dewitt County, Il, Achp Project Number: 020924 IR 05000461/20240122024-05-20020 May 2024 Biennial Problem Identification and Resolution Inspection Report Report 05000461/2024012 RS-24-055, 2023 Corporate Regulatory Commitment Change Summary Report2024-05-17017 May 2024 2023 Corporate Regulatory Commitment Change Summary Report RS-24-050, Additional Information Supporting Request for License Amendment to Revise Technical Specifications Related to Reactor Water Cleanup Isolation Instrumentation2024-05-0909 May 2024 Additional Information Supporting Request for License Amendment to Revise Technical Specifications Related to Reactor Water Cleanup Isolation Instrumentation IR 05000461/20240012024-05-0707 May 2024 Integrated Inspection Report 05000461/2024001 ML24103A1032024-05-0101 May 2024 SHPO Consultation Letter for Clinton License Renewal ML24120A3462024-04-30030 April 2024 Ltr. to Douglas Lankford, Chief, Miami Tribe of Oklahoma; Re., CPS Section 106 Consultation ML24120A3432024-04-30030 April 2024 Ltr. to Darwin Kaskaske, Chairman, Kickapoo Tribe of Oklahoma; Re., CPS Section 106 Consultation ML24120A3442024-04-30030 April 2024 Ltr. to Gena Kakkak, Chairman, Menominee Indian Tribe of Wisconsin; Re., CPS Section 106 Consultation ML24120A3452024-04-30030 April 2024 Ltr. to Lester Randell, Chairman, Kickapoo Tribe of Indians of the Kickapoo Reservation in Kansas; Re., CPS Section 106 Consultation ML24103A1152024-04-30030 April 2024 Ltr. to Geoffrey Standing Bear, Principal Chief, the Osage Nation; Re., CPS Section 106 Consultation ML24103A0992024-04-30030 April 2024 Achp Scoping Letter for Clinton License Renewal RS-24-041, Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-04-30030 April 2024 Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests ML24107B0312024-04-29029 April 2024 Notice of Intent to Prepare an Environmental Impact Statement and Conduct Scoping Process ML24103A2042024-04-12012 April 2024 Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition ML24089A2222024-04-11011 April 2024 LRA - Acceptance and Opportunity for Hearing - Letter ML24092A3452024-04-0101 April 2024 Updated Safety Analysis Report (Usar), Revision 23 2024-09-09
[Table view] Category:License-Operator
MONTHYEARML24179A3112024-06-27027 June 2024 05000461; Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML24176A0272024-06-25025 June 2024 Confirmation of Initial License Examination, July 2025 ML23258A0212023-09-15015 September 2023 Form 5.1-1 Post-Examination Check Sheet (Clinton 2023) IR 05000461/20233012023-09-12012 September 2023 NRC Initial License Examination Report 05000461/2023301 ML23258A0162023-08-24024 August 2023 Form 2.1-1 Examination Prep Checklist (Clinton 2023) ML23258A0132023-08-24024 August 2023 Form 1.3-1 Examination Security Agreement (Clinton 2023) ML23258A0232023-08-0101 August 2023 Post-Exam Comments (None, Clinton 2023) ML23258A0222023-08-0101 August 2023 Licensee Post-Exam Submittal Letter (Clinton 2023) ML23191A8772023-07-11011 July 2023 Operator Licensing Examination Approval Clinton Power Station July 2023 ML23258A0522023-07-0808 July 2023 Form 3.4-1 Events and Evolutions Checklist (Clinton 2023) ML23258A0502023-07-0808 July 2023 Form 2.3-1 Examination Outline Quality Checklist (Clinton 2023) ML23258A0942023-07-0606 July 2023 Form 2.3-4 Written Examination Quality Checklist (Clinton 2023) ML23258A0932023-07-0606 July 2023 Form 2.3-2 Operating Test Quality Checklist (Clinton 2023) RS-23-077, Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-06-16016 June 2023 Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations ML23258A0952023-04-0606 April 2023 Licensee Exam Submittal Letter (Clinton 2023) ML23258A0562023-02-0606 February 2023 Licensee Outline Submission Letter (Clinton 2023) ML22341A6042022-12-0808 December 2022 Confirmation of Initial License Examination IR 05000461/20223012022-04-13013 April 2022 NRC Initial License Examination Report 05000461/2022301 RS-22-045, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations2022-03-25025 March 2022 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations ML22157A3782022-01-28028 January 2022 ES-201-3 Pre Exam ML22153A5222022-01-28028 January 2022 ES-301-5 Clinton 2022 ML22157A3772022-01-28028 January 2022 ES-201-3 Post Exam Security Agreement ML22157A3752022-01-28028 January 2022 ES-201-1 Exam Prep Checklist ML22153A5202022-01-28028 January 2022 ES-201-2 Clinton ML22157A3822022-01-28028 January 2022 ES-403-1 Clinton 2022 ML22153A4722022-01-28028 January 2022 ES-301-6 ML22153A4682022-01-28028 January 2022 ES-301-4 U-604643, U-604643 ILT Exam Outline - Clinton 20222022-01-28028 January 2022 U-604643 ILT Exam Outline - Clinton 2022 ML22157A3872022-01-28028 January 2022 Post Exam Submittal Letter Clinton 22 ML22153A5172022-01-28028 January 2022 ES-201-2 Clinton 2022 NRC Written Outline Only ML22153A4782022-01-28028 January 2022 ES-301-3 ML22153A4762022-01-28028 January 2022 U-604644 - CPS Submittal of Integrated Initial License Training Examination Materials - 75-Day ML22010A0992022-01-11011 January 2022 Operator Licensing Examination Approval ML21215A5732021-08-0303 August 2021 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML21174A3062021-06-25025 June 2021 Confirmation of Initial License Examination IR 05000461/20213012021-04-29029 April 2021 NRC Initial License Examination Report 05000461/2021301 ML21144A3022021-04-13013 April 2021 Administered RO Admin JPM ML21144A3222021-04-13013 April 2021 ES-401-3 ML21144A3132021-04-13013 April 2021 Administered SRO Written Exam ML21144A2582021-04-13013 April 2021 Scenarios ML21144A2402021-04-13013 April 2021 LTR 75 Day Submittal ML21144A2372021-04-13013 April 2021 ES-301-4 ML21144A2442021-04-13013 April 2021 ES-401-6 ML21144A2232021-04-13013 April 2021 ES-201-1 ML21144A2382021-04-13013 April 2021 ES-301-6 ML21144A3232021-04-13013 April 2021 ES-D-1 ML21144A2152021-04-13013 April 2021 ES-401-4 ML21145A0332021-04-13013 April 2021 ES-201-2 Written Outline ML21144A2292021-04-13013 April 2021 ES-201-3 ML21144A2312021-04-13013 April 2021 Post Exam Submittal Letter 2024-06-27
[Table view] Category:Part 55 Examination Related Material
MONTHYEARML24179A3112024-06-27027 June 2024 05000461; Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML24176A0272024-06-25025 June 2024 Confirmation of Initial License Examination, July 2025 ML23258A0212023-09-15015 September 2023 Form 5.1-1 Post-Examination Check Sheet (Clinton 2023) IR 05000461/20233012023-09-12012 September 2023 NRC Initial License Examination Report 05000461/2023301 ML23258A0162023-08-24024 August 2023 Form 2.1-1 Examination Prep Checklist (Clinton 2023) ML23258A0132023-08-24024 August 2023 Form 1.3-1 Examination Security Agreement (Clinton 2023) ML23258A0222023-08-0101 August 2023 Licensee Post-Exam Submittal Letter (Clinton 2023) ML23258A0232023-08-0101 August 2023 Post-Exam Comments (None, Clinton 2023) ML23191A8772023-07-11011 July 2023 Operator Licensing Examination Approval Clinton Power Station July 2023 ML23258A0502023-07-0808 July 2023 Form 2.3-1 Examination Outline Quality Checklist (Clinton 2023) ML23258A0522023-07-0808 July 2023 Form 3.4-1 Events and Evolutions Checklist (Clinton 2023) ML23258A0932023-07-0606 July 2023 Form 2.3-2 Operating Test Quality Checklist (Clinton 2023) ML23258A0942023-07-0606 July 2023 Form 2.3-4 Written Examination Quality Checklist (Clinton 2023) RS-23-077, Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-06-16016 June 2023 Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations ML23258A0952023-04-0606 April 2023 Licensee Exam Submittal Letter (Clinton 2023) ML23258A0562023-02-0606 February 2023 Licensee Outline Submission Letter (Clinton 2023) ML22341A6042022-12-0808 December 2022 Confirmation of Initial License Examination IR 05000461/20223012022-04-13013 April 2022 NRC Initial License Examination Report 05000461/2022301 RS-22-045, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations2022-03-25025 March 2022 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations ML22157A3872022-01-28028 January 2022 Post Exam Submittal Letter Clinton 22 ML22153A4762022-01-28028 January 2022 U-604644 - CPS Submittal of Integrated Initial License Training Examination Materials - 75-Day ML22153A5202022-01-28028 January 2022 ES-201-2 Clinton U-604643, U-604643 ILT Exam Outline - Clinton 20222022-01-28028 January 2022 U-604643 ILT Exam Outline - Clinton 2022 ML22153A5172022-01-28028 January 2022 ES-201-2 Clinton 2022 NRC Written Outline Only ML22153A4722022-01-28028 January 2022 ES-301-6 ML22157A3772022-01-28028 January 2022 ES-201-3 Post Exam Security Agreement ML22153A4782022-01-28028 January 2022 ES-301-3 ML22157A3782022-01-28028 January 2022 ES-201-3 Pre Exam ML22153A5222022-01-28028 January 2022 ES-301-5 Clinton 2022 ML22157A3752022-01-28028 January 2022 ES-201-1 Exam Prep Checklist ML22157A3822022-01-28028 January 2022 ES-403-1 Clinton 2022 ML22153A4682022-01-28028 January 2022 ES-301-4 ML22010A0992022-01-11011 January 2022 Operator Licensing Examination Approval ML21215A5732021-08-0303 August 2021 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML21174A3062021-06-25025 June 2021 Confirmation of Initial License Examination IR 05000461/20213012021-04-29029 April 2021 NRC Initial License Examination Report 05000461/2021301 ML21144A2232021-04-13013 April 2021 ES-201-1 ML21145A0402021-04-13013 April 2021 ES-301-5 ML21144A2292021-04-13013 April 2021 ES-201-3 ML21144A3022021-04-13013 April 2021 Administered RO Admin JPM ML21144A3232021-04-13013 April 2021 ES-D-1 ML21144A2302021-04-13013 April 2021 ES-403-1 ML21144A3222021-04-13013 April 2021 ES-401-3 ML21144A3202021-04-13013 April 2021 ES-401-1 ML21144A3192021-04-13013 April 2021 ES-301-2 ML21144A2642021-04-13013 April 2021 Sim JPM ML21144A3132021-04-13013 April 2021 Administered SRO Written Exam ML21144A3102021-04-13013 April 2021 Administered Sim JPM ML21144A3182021-04-13013 April 2021 ES-301-1 ML21145A0332021-04-13013 April 2021 ES-201-2 Written Outline 2024-06-27
[Table view] |
Text
David Rhoades Senior Vice President Constellation Energy Generation, LLC President and Chief Nuclear Officer (CNO)
Constellation Nuclear 4300 Winfield Road Warrenville, IL 60555
SUBJECT:
CLINTON POWER STATION - CONFIRMATION OF INITIAL LICENSE EXAMINATION, JULY 2025
Dear David Rhoades:
In a Microsoft Teams conversation on June 10, 2024, between Matt Beeler, Initial License Exam Lead and Travis Iskierka-Boggs, Senior Operations Engineer, arrangements were made for the administration of operator licensing examinations at Clinton Power Station during the week of July 14, 2025.
As agreed, upon during the telephone conversation, the staff of the U.S. Nuclear Regulatory Commission (NRC) will prepare the examinations based on the guidelines in Revision 12 to NUREG-1021, Operator Licensing Examination Standards for Power Reactors.
To meet the above schedule, your staff has furnished the agreed upon reference materials identified in NUREG-1021, Examination Standard (ES)-2.1, Section F, Reference Material for Operator Licensing Initial Examinations. Additional requests may be made as examination development progresses.
The outline for the written examination was provided to your staff for review and comment and feedback has been received from your staff. The operating test outlines for the JPMs and the required dynamic scenarios and all new or modified JPMs will be available for your staffs review and comment prior to the pre-onsite validation visit scheduled for the week of February 17, 2025. The NRC developed written exam will be provided to your staff prior to April 4, 2025, and the facility developed operating test will be provided to the NRC for review prior to April 4, 2025. The NRC will make an examination validation visit to your facility the week of June 2, 2025. All materials shall be complete and ready to use.
We request that any personal, proprietary, sensitive unclassified, or safeguards information in your response be contained in a separate enclosure and appropriately marked. Delays in receiving the required materials, or the submittal of inadequate or incomplete materials, may cause the examinations to be cancelled or rescheduled.
To conduct the requested written examinations and operating tests, your staff will need to provide adequate space and accommodations and to make the simulation facility available on the dates noted above. In accordance with ES-3.5, Administering Operating Tests, your staff June 25, 2024 D. Rhoades 2
should retain the original simulator performance data (e.g., system pressures, temperatures, and levels) generated during the dynamic operating tests until the NRC takes licensing action on all the applications and any adjudicatory actions on any hearing demands are complete.
ES-1.2, Guidelines for Taking NRC Examinations, contains a number of NRC guidelines for the written examinations and operating tests as they are being administered.
To permit timely NRC review and evaluation, your staff should submit preliminary reactor operator and senior reactor operator waiver or excusal requests (if any) (Office of Management and Budget (OMB) control number 3150-0090) at least 60 days before the first examination date (if possible). Contact Travis Iskierka-Boggs to determine the method for submission of the waiver or excusal requests. Preliminary reactor operator and senior reactor operator license applications (OMB control number 3150-0090) and medical certificate ions (OMB control number 3150-0024) should be submitted at least 30 days before the first examination date. If the NRC does not receive the preliminary applications at least 30 days before the examination date, a postponement may be necessary. Final, signed applications certifying that all training has been completed and requesting any waivers or excusals, as applicable, should be submitted at least 14 days before the first examination date.
Although the guidelines for waiver or excusal requests call for their receipt at least 30 days before the first examination date (preliminary) and 14 days before the first examination date (final), the requests should be submitted as early as possible in the process (see the 60-day guideline above). Resolutions resulting from verbal inquiries by the facility licensee to the NRC are not binding. Submittals addressing waivers or excusals, or both, should be in writing (i.e., using NRC Form 398 or as directed by Travis Iskierka-Boggs when contacting him to determine the method for submission). The NRC will document its final decision on whether to grant a waiver or excusal on the final (not preliminary) NRC Form 398 submitted for the applicant. The NRC will not provide its decision until the final application is submitted to the agency.
Paperwork Reduction Act Statement
This letter contains information collection requirements that are subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). These information collections were approved by the OMB, approval number 3150-0018.
The burden to the public for these mandatory information collections is estimated to average 400 hours0.00463 days <br />0.111 hours <br />6.613757e-4 weeks <br />1.522e-4 months <br /> per examination or response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the information collections. Send comments regarding this information collection to the Freedom of Information Act, Library, and Information Collections Branch (T6-A10M),
U.S. Nuclear Regulatory Commission, Washington, DC 20555 0001, or by email to infocollects.resource@nrc.gov, and to the OMB reviewer at: OMB Office of Information and Regulatory Affairs (3150-0018), Attn: Desk Officer for the Nuclear Regulatory Commission, 725 17th Street, NW Washington, DC 20503; email: oira submission@omb.eop.gov.
Public Protection Notification
The NRC may not conduct or sponsor, and a person is not required to respond to, a collection of information unless the document requesting or requiring the collection displays a currently valid OMB control number.
D. Rhoades 3 In accordance with 10 CFR 2.390, Public inspections, exemptions, requests for withholding, a copy of this letter and its enclosures will be available electronically for public inspection through the NRCs Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible on the NRCs website at http://www.nrc.gov/reading-rm/adams.html.
Thank you for your cooperation in this matter. Matt Beeler has been advised of the policies and guidelines referenced in this letter. If you have any questions about the NRCs examination procedures and guidelines, please contact Travis Iskierka-Boggs, Chief Examiner at 630-829-9818 or me at 630-829-9631.
Sincerely, Paul J. Zurawski, Chief Operations Branch Division of Operating Reactor Safety Docket No. 50-461 cc: Distribution via LISTSERV A. Corrigan, Training Manager Signed by Zurawski, Paul on 06/25/24
D. Rhoades 4
Letter to David Rhoades from Paul J. Zurawski dated June 25, 2024.
SUBJECT:
CLINTON POWER STATION - CONFIRMATION OF INITIAL LICENSE EXAMINATION, JULY 2025
DISTRIBUTION:
Michelle Simmons RidsNrrDorlLpl3 RidsNrrPMClinton Resource RidsNrrDroIrib Resource Jack Giessner Mohammed Shuaibi Diana Betancourt-Roldan Allan Barker David Curtis Karla Stoedter R3-DORS Ikeda Betts Maryia Bahdanovich-Kniazkova
ADAMS Accession Number: ML24176A027 OFFICE RIII/DORS/OB/CE RIII/DORS/OB:BC NAME TIskierka-Boggs PZurawski DATE 06/24/24 06/25/24 OFFICIAL RECORD COPY