MONTHYEARIR 05000461/20240052024-08-29029 August 2024 Updated Inspection Plan and Assessment Follow-Up Letter for Clinton Power Station (Report 05000461/2024005) ML24220A2772024-08-0707 August 2024 Request for Information for the NRC Quadrennial Comprehensive Engineering Team Inspection: Inspection Report 05000461/2025010 ML24179A3112024-06-27027 June 2024 05000461; Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information IR 05000461/20230062024-02-28028 February 2024 Annual Assessment Letter for Clinton Power Station (Report 05000461/2023006) ML24054A7112024-02-23023 February 2024 Request for Information for NRC Commercial Grade Dedication Inspection: Inspection Report 05000461/2024011 ML24064A1222024-02-0606 February 2024 Biennial Problem and Identification Inspection Request for Information IR 05000461/20230052023-08-25025 August 2023 Updated Inspection Plan and Assessment Follow-Up Letter for Clinton Power Station (Report 05000461/2023005) IR 05000461/20220062023-03-0101 March 2023 Annual Assessment Letter for Clinton Power Station, Unit 1 (Report 05000461/2022006) ML23005A0682023-01-0505 January 2023 Notification of NRC Fire Protection Team Inspection Request for Information: Inspection Report 05000461/2023010 IR 05000461/20234012022-11-0808 November 2022 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000461/2023401 IR 05000461/20220052022-08-22022 August 2022 Updated Inspection Plan for Clinton Power Station (Report 05000461/2022005) IR 05000461/20210062022-03-0202 March 2022 Annual Assessment Letter for Clinton Power Station, Unit 1 (Report 05000461/2021006) ML21333A0832021-11-29029 November 2021 Request for Information for an NRC Triennial Baseline Design Bases Assurance Inspection (Teams), Inspection Report Report 05000461/202201 IR 05000461/20210052021-09-0101 September 2021 Updated Inspection Plan for Clinton Power Station; Report 05000461/2021005 ML21215A5732021-08-0303 August 2021 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information IR 05000461/20210132021-03-17017 March 2021 Information Request to Support Upcoming Temporary Instruction 2515/194 Inspection; Inspection Report 05000461/2021013 ML21071A1882021-03-12012 March 2021 Information Request to Support Upcoming Problem Identification and Resolution Inspection at Clinton Power Station IR 05000461/20200062021-03-0404 March 2021 Annual Assessment Letter for Clinton Power Station Unit 1 (Report 05000461/2020006) ML20329A0662020-11-24024 November 2020 Information Request for an NRC Triennial 10 CFR 50.59 (Evaluation of Changes, Tests and Experiments) Baseline Inspection IR 05000461/20200052020-09-0101 September 2020 Updated Inspection Plan for Clinton Power Station, Unit 1 (Report 05000461/2020005) ML20183A1932020-06-30030 June 2020 Notification of NRC Fire Protection Team Inspection Request for Information; Inspection Report 05000461/2020010 IR 05000461/20190062020-03-0303 March 2020 Annual Assessment Letter for Clinton Power Station, (Report 05000461/2019006) IR 05000461/20190052019-08-28028 August 2019 Updated Inspection Plan for Clinton Power Station (Report 05000461/2019005 ML19136A1852019-05-15015 May 2019 Byron Station, Clinton Power Station, Dresden Nuclear Power Station, LaSalle County Station, and Quad Cities Nuclear Power Station-Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency IR 05000461/20180062019-03-0404 March 2019 Annual Assessment Letter for Clinton Power Station (Report 05000461/2018006) ML19037A4772019-02-0606 February 2019 Information Request to Support Upcoming Problem Identification and Resolution Inspect at Clinton Power Station ML19003A1912019-01-0303 January 2019 Request for Information for an NRC Triennial Baeline Design Bases Assurance Inspection; Inspection Report 05000461/2019011 IR 05000461/20180052018-08-28028 August 2018 Mid-Cycle Assessment Letter for Clinton Power Station, Unit 1 (Report 05000461/2018005) ML18088A5662018-03-28028 March 2018 Information Request for an NRC Triennial 10 CFR 50.59 (Evaluation of Changes, Tests and Experiments) Baseline Inspection 05000461/2018010 IR 05000461/20170062018-03-0202 March 2018 Annual Assessment Letter for Clinton Power Station, Unit 1 (Report 05000461/2017006) ML17333A0782017-11-28028 November 2017 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000461/2018002 IR 05000461/20170052017-08-28028 August 2017 Updated Inspection Plan for Clinton Power Station, Unit 1 and Quarterly Assessment Letter (Report 05000461/2017005) ML17146B2492017-03-31031 March 2017 Inspection Plan for Clinton Power Station for Triennial Fire Protection Baseline Inspection Report 2017 008 ML17076A3382017-03-16016 March 2017 Notification of NRC Baseline Inspection and Request for Information 05000461/2017002 IR 05000461/20160062017-03-0101 March 2017 Annual Assessment Letter for Clinton Power Station, Unit 1 (Report 05000461/2016006) IR 05000461/20160052016-08-31031 August 2016 Mid-Cycle Assessment Letter for Clinton Power Station, Unit 1 (Report 05000461/2016005) ML16098A3242016-04-0707 April 2016 Information Request to Support Upcoming Temporary Instruction 191 Inspection at Clinton Power Station ML16076A2542016-03-15015 March 2016 Ltr. 03/15/16 Clinton Power Station, Unit 1 - Request for Information for an NRC Triennial Baseline Component Design Bases Inspection; Inspection Report 05000461/2016009 (Jen) ML16076A2462016-03-15015 March 2016 Ltr. 03/15/16 Clinton Power Station - Notification of NRC Inspection and Request for Information (Vlm) IR 05000461/20150062016-03-0202 March 2016 Annual Assessment Letter for Clinton Power Station Unit 1 (Inspection Report 05000461/2015006) IR 05000461/20150052015-09-0101 September 2015 Mid-Cycle Assessment Letter for Clinton Power Station, Unit 1 (Report 05000461/2015005) IR 05000461/20140012015-03-0404 March 2015 Annual Assessment Letter for Clinton Power Station, Unit 1, (Report 05000461/2014001) ML14245A2362014-09-0202 September 2014 Mid-Cycle Assessment Letter for Clinton Power Station, Unit 1 ML14177A3812014-06-25025 June 2014 Notification of NRC Supplemental Inspection (95001) and Request for Information IR 05000451/20130012014-03-0404 March 2014 Annual Assessment Letter for Clinton Power Station, Unit 1 (Report 05000451/2013001) ML13308B1302013-11-0101 November 2013 Ltr 11/1/13 Clinton Fire Protection Request for Information ML13246A2152013-09-0303 September 2013 2013 Clinton Power Station Mid-Cycle Letter Combined IR 05000461/20130082013-07-25025 July 2013 IR 05000461-13-008, May 20 - 24, 2013, June 3 - 7, 2013, and June 17 - 21, 2013, Clinton Power Station, Component Design Bases Inspection (CDBI) IR 05000461/20120012013-03-0404 March 2013 Annual Assessment Letter for Clinton Power Station (Report 05000461/2012001) ML13038A3122013-02-0707 February 2013 Request for Information for an NRC Triennial Baseline Component Design Bases Inspection Report 05000461-13-008 2024-08-07
[Table view] Category:Letter
MONTHYEARIR 05000461/20240032024-11-0505 November 2024 Integrated Inspection Report 05000461/2024003 ML24317A1432024-11-0404 November 2024 Constellation Energy Generation, LLC, 2024 Annual Report - Guarantees of Payment of Deferred Premiums ML24285A1442024-10-24024 October 2024 Ltr. to Estavio Elizondo, Sr., Chairman, Kickapoo Traditional Tribe of Texas Re CPS Section 106 Consultation ML24285A1472024-10-24024 October 2024 Ltr. to Geoffrey M. Standing Bear, Principal Chief, Osage Nation Re CPS Section 106 Consultation ML24285A1452024-10-24024 October 2024 Ltr. to Gail Cheatham, Kickapoo Tribe of Indians of the Kickapoo Reservation in Ks Re CPS Sect 106 Consult IR 05000461/20244032024-10-24024 October 2024 – Security Baseline Inspection Report 05000461/2024403 ML24285A1462024-10-24024 October 2024 Ltr. to Gena Kakkak, Chairwoman, Menominee Indian Tribe of Wisconsin Re CPS Section 106 Consultation ML24285A1422024-10-24024 October 2024 Ltr. to Darwin Kaskaske, Chairman, Kickapoo Tribe of Oklahoma Re CPS Section 106 Consultation IR 05000461/20244022024-10-24024 October 2024 – Security Baseline Inspection Report 05000461/2024402 ML24285A1482024-10-24024 October 2024 Ltr. to Joseph Rupnick, Chairman, Prairie Band Potawatomi Nation Re CPS Section 106 Consultation ML24283A1642024-10-23023 October 2024 Summary of the 2024 Environmental Audit Related to the Review of the License Renewal Application Environmental Report (EPID Number L-2024-LNE-0000)(Docket Number:50-461) ML24285A1412024-10-21021 October 2024 Ltr. to Craig Harper, Chief, Peoria Tribe of Oklahoma Re CPS Section 106 Consultation ML24285A1432024-10-21021 October 2024 Ltr. to Douglas Lankford, Chief, Miami Tribe of Oklahoma Re CPS Section 106 Consultation RS-24-093, Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-10-10010 October 2024 Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests ML24275A2442024-10-0303 October 2024 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief, Division of Operating Reactor Licensing ML24215A2932024-09-27027 September 2024 Scoping Summary Letter 05000461/LER-2023-002-01, Reactor Core Isolation Cooling Inoperable Prior to Mode Change2024-09-24024 September 2024 Reactor Core Isolation Cooling Inoperable Prior to Mode Change ML24211A2302024-09-11011 September 2024 – Request for Partial Site Release for Facility Operating License No. NPF-62 IR 05000461/20240112024-09-0909 September 2024 Commercial Grade Dedication Inspection Report 05000461/2024011 RS-24-087, Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors for Clinton Power Station2024-09-0909 September 2024 Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors for Clinton Power Station IR 05000461/20240052024-08-29029 August 2024 Updated Inspection Plan and Assessment Follow-Up Letter for Clinton Power Station (Report 05000461/2024005) ML24222A3952024-08-23023 August 2024 Regulatory Audit Report to Support the Review of the Amendments to Revise Reactor Water Cleanup Valve Isolation Timing IR 05000461/20240022024-08-0909 August 2024 Integrated Inspection Report 05000461/2024002 ML24222A6772024-08-0909 August 2024 Response to Request for Additional Information for Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition ML24220A2772024-08-0707 August 2024 Request for Information for the NRC Quadrennial Comprehensive Engineering Team Inspection: Inspection Report 05000461/2025010 ML24212A2212024-08-0202 August 2024 License Renewal Regulatory Audit Regarding the Environmental Review of the License Renewal Application (EPID Number: L-2024-LNE-0000) (Docket Number: 50-461) ML24157A3242024-07-11011 July 2024 Issuance of Amendment No. 254 Revision of Reactor Water Cleanup Isolation Valve Timing ML24158A0772024-07-0303 July 2024 Notice of Consideration of Approval of Partial Site Release, Public Meeting, and Request for Comments (EPID L-2023-LLA-0088) - Letter ML24163A3252024-06-28028 June 2024 Aging Management Regulatory Audit Plan ML24163A3242024-06-28028 June 2024 LRA - Portal Letter ML24179A3112024-06-27027 June 2024 05000461; Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML24176A0272024-06-25025 June 2024 Confirmation of Initial License Examination, July 2025 RS-24-061, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-06-14014 June 2024 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations ML24079A0762024-05-23023 May 2024 Issuance of Amendments to Adopt TSTF 264 ML24142A3352024-05-21021 May 2024 Quad Cities—Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes ML24290A0942024-05-21021 May 2024 Letter from Rachael Mangum (Achp) to Stephen Koenick (NRC) License Renewal Application for the Clinton Power Station Unit 1 Dewitt County, Il, Achp Project Number: 020924 IR 05000461/20240122024-05-20020 May 2024 Biennial Problem Identification and Resolution Inspection Report Report 05000461/2024012 RS-24-055, 2023 Corporate Regulatory Commitment Change Summary Report2024-05-17017 May 2024 2023 Corporate Regulatory Commitment Change Summary Report RS-24-050, Additional Information Supporting Request for License Amendment to Revise Technical Specifications Related to Reactor Water Cleanup Isolation Instrumentation2024-05-0909 May 2024 Additional Information Supporting Request for License Amendment to Revise Technical Specifications Related to Reactor Water Cleanup Isolation Instrumentation IR 05000461/20240012024-05-0707 May 2024 Integrated Inspection Report 05000461/2024001 ML24103A1032024-05-0101 May 2024 SHPO Consultation Letter for Clinton License Renewal ML24103A0992024-04-30030 April 2024 Achp Scoping Letter for Clinton License Renewal ML24120A3432024-04-30030 April 2024 Ltr. to Darwin Kaskaske, Chairman, Kickapoo Tribe of Oklahoma; Re., CPS Section 106 Consultation RS-24-041, Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-04-30030 April 2024 Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests ML24103A1152024-04-30030 April 2024 Ltr. to Geoffrey Standing Bear, Principal Chief, the Osage Nation; Re., CPS Section 106 Consultation ML24120A3452024-04-30030 April 2024 Ltr. to Lester Randell, Chairman, Kickapoo Tribe of Indians of the Kickapoo Reservation in Kansas; Re., CPS Section 106 Consultation ML24120A3442024-04-30030 April 2024 Ltr. to Gena Kakkak, Chairman, Menominee Indian Tribe of Wisconsin; Re., CPS Section 106 Consultation ML24120A3462024-04-30030 April 2024 Ltr. to Douglas Lankford, Chief, Miami Tribe of Oklahoma; Re., CPS Section 106 Consultation ML24107B0312024-04-29029 April 2024 Notice of Intent to Prepare an Environmental Impact Statement and Conduct Scoping Process ML24103A2042024-04-12012 April 2024 Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition 2024-09-09
[Table view] |
Inspection Report - Clinton - 2024005 |
---|
|
|
Text
SUBJECT:
UPDATED INSPECTION PLAN AND ASSESSMENT FOLLOW-UP LETTER FOR CLINTON POWER STATION (REPORT 05000461/2024005)
Dear David P. Rhoades:
The enclosed inspection plan lists the inspections scheduled through June 30, 2026, for the Clinton Power Station. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last 12 months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes.
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
August 28, 2024 Please contact me at 630-829-9732 with any questions you have regarding this letter.
Sincerely, Robert Ruiz, Chief Reactor Projects Branch 1 Division of Operating Reactor Safety Docket No. 05000461 License No. NPF-62 Enclosure:
Inspection Plan cc: Distribution via LISTSERV Signed by Ruiz, Robert on 08/28/24
ML24241A032
SUNSI Review
Non-Sensitive
Sensitive
Publicly Available
Non-Publicly Available OFFICE RIII RIII NAME NShah:anm RRuiz DATE 08/28/2024 08/28/2024
Site Inspection Activity Plan 07201046 - Clinton Power Station (ISFSI)
07/01/2024 - 06/30/2026 Unit Start End Activity CAC Title Staff Count ISFSI Program Review Inspection
3/10/2025 3/14/2025 IP 60855 001001 Operation Of An ISFSI Prepared on 8/21/2024 9:45:48 AM 1 of 3
Site Inspection Activity Plan Clinton 07/01/2024 - 06/30/2026 Unit Start End Activity CAC Title Staff Count Security Baseline Inspection
1 7/22/2024 7/26/2024 IP 71130.02 000734 Access Control
7/22/2024 7/26/2024 IP 71130.05 000737 Protective Strategy Evaluation Security Baseline Inspection
1 7/22/2024 7/26/2024 IP 71130.09 001656 Security Plan Changes Radiation Protection Baseline Inspection
1 8/26/2024 8/30/2024 IP 71124.05 000729 Radiation Monitoring Instrumentation
8/26/2024 8/30/2024 IP 71124.06 000730 Radioactive Gaseous and Liquid Effluent Treatment
8/26/2024 8/30/2024 IP 71151 000746 Performance Indicator Verification Clinton 2024 Licensed Operator Biennial Requalification Program Inspection
1 9/15/2024 9/21/2024 IP 71111.11B 000704 Licensed Operator Requalification Program and Licensed Operator Performance Eplan and EAL Changes Review
1 11/1/2024 12/31/2024 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes Material Control and Accountability
1 1/1/2025 12/31/2025 IP 71130.11 000742 Material Control and Accounting (MC&A)
Comprehensive Engineering Team Inspection
1 1/27/2025 2/14/2025 IP 71111.21M 000713 Comprehensive Engineering Team Inspection Clinton January 2025 NRC Developed Initial License Exam
1 2/16/2025 2/22/2025 OV 000956 FB-OR-Onsite Validation Of Initial License Examination (OV)
6/1/2025 6/7/2025 OV 000956 FB-OR-Onsite Validation Of Initial License Examination (OV)
7/13/2025 7/19/2025 EXAD 000500 FB-OR-Initial License Exam Administration (EXAD)
Security Baseline Inspection
1 2/10/2025 2/14/2025 IP 71130.14 000743 Review of Power Reactor Target Sets
2/24/2025 2/28/2025 IP 71130.02 000734 Access Control
2/24/2025 2/28/2025 IP 71151 001338 Performance Indicator Verification Cyber Security Inspection
1 4/7/2025 4/11/2025 IP 71130.10 000741 Cybersecurity Radiation Protection Baseline Inspection
1 6/2/2025 6/6/2025 IP 71124.07 000731 Radiological Environmental Monitoring Program
6/2/2025 6/6/2025 IP 71124.08 000732 Radioactive Solid Waste Processing & Radioactive Material Handling, Storage, & Transportation Clinton License Renewal IP 71002
1 6/9/2025 6/27/2025 IP 71002 000686 License Renewal Inspection Prepared on 8/21/2024 9:45:48 AM 2 of 3
Site Inspection Activity Plan Emergency Preparedness Exercise Inspection / Performance Indicator Review
1 7/21/2025 7/25/2025 IP 71114.01 000716 Exercise Evaluation
7/21/2025 7/25/2025 IP 71151 001397 Performance Indicator Verification Security Baseline Inspection
1 8/25/2025 8/29/2025 IP 71130.07 000739 Security Training
8/25/2025 8/29/2025 IP 71130.09 001656 Security Plan Changes License Renewal Phase 1
1 9/8/2025 9/19/2025 IP 71003 000687 Post-Approval Site Inspection for License Renewal Inservice Inspection Unit 1
1 9/8/2025 9/19/2025 IP 71111.08G 000701 Inservice Inspection Activities (BWR)
Radiation Protection Baseline Inspection
1 9/15/2025 9/19/2025 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls
9/15/2025 9/19/2025 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation
9/15/2025 9/19/2025 IP 71124.04 000728 Occupational Dose Assessment Eplan and EAL Changes Review
1 11/1/2025 12/31/2025 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes Corporate Security Baseline Inspection
1 1/19/2026 1/23/2026 IP 71130.08 000740 Fitness-For-Duty Program Radiation Protection Baseline Inspection
1 2/2/2026 2/6/2026 IP 71124.05 000729 Radiation Monitoring Instrumentation Functional Engineering Inspection - Age Related Degradation
1 3/2/2026 3/20/2026 IP 71111.21N.04 001832 Age-Related Degradation Emergency Preparedness Baseline Inspection / Performance Indicator Verification
1 3/30/2026 4/3/2026 IP 71114.02 000717 Alert and Notification System Testing
3/30/2026 4/3/2026 IP 71114.03 000718 Emergency Response Organization Staffing and Augmentation System
3/30/2026 4/3/2026 IP 71114.05 000720 Maintenance of Emergency Preparedness
3/30/2026 4/3/2026 IP 71151 001397 Performance Indicator Verification Clinton 2026 biennial PIR
1 4/6/2026 4/24/2026 IP 71152B 000747 Problem Identification and Resolution Force-on-Force Planning and Exercise Weeks - CLI
1 6/22/2026 6/26/2026 IP 71130.03 000735 Contingency Response - Force-On-Force Testing Prepared on 8/21/2024 9:45:48 AM 3 of 3