August 5, 2021 Mr. David P. Rhoades Senior Vice President Exelon Generation Company, LLC President and Chief Nuclear Officer (CNO)
Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555
SUBJECT:
BRAIDWOOD STATION, UNITS 1 AND 2; BYRON STATION, UNIT NOS. 1 AND 2; CALVERT CLIFFS NUCLEAR POWER PLANT, UNITS 1 AND 2; CLINTON POWER STATION, UNIT NO. 1; DRESDEN NUCLEAR POWER STATION, UNITS 2 AND 3; JAMES A. FITZPATRICK NUCLEAR POWER PLANT; LASALLE COUNTY STATION, UNITS 1 AND 2; LIMERICK GENERATING STATION, UNITS 1 AND 2; NINE MILE POINT NUCLEAR STATION, UNITS 1 AND 2; PEACH BOTTOM ATOMIC POWER STATION, UNITS 2 AND 3; QUAD CITIES NUCLEAR POWER STATION, UNITS 1 AND 2; AND R. E. GINNA NUCLEAR POWER PLANT PROPOSED ALTERNATIVE TO ELIMINATE CERTAIN DOCUMENTATION REQUIREMENTS FOR PRESSURE RETAINING BOLTING (EPIDS L-2021-LLR-0153, -0154, AND -0155)
Dear Mr. Rhoades:
By application dated December 1, 2020 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML20336A008), as supplemented by letters dated April 20 and July 7, 2021 (ADAMS Accession Nos. ML21110A092 and ML21188A242, respectively), Exelon Generation Company, LLC (Exelon, the licensee) submitted a request in accordance with paragraph 50.55a(z)(1) of Title 10 of the Code of Federal Regulations (10 CFR) for a proposed alternative to certain requirements of 10 CFR 50.55a, Codes and standards, for Braidwood Station (Braidwood), Units 1 and 2; Byron Station (Byron), Unit Nos. 1 and 2; Calvert Cliffs Nuclear Power Plant (Calvert Cliffs), Units 1 and 2; Clinton Power Station (Clinton), Unit No. 1; Dresden Nuclear Power Station (Dresden), Units 2 and 3; James A. FitzPatrick Nuclear Power Plant (FitzPatrick); LaSalle County Station (LaSalle), Units 1 and 2; Limerick Generating Station (Limerick), Units 1 and 2; Nine Mile Point Nuclear Station (NMP), Units 1 and 2; Peach Bottom Atomic Power Station (Peach Bottom), Units 2 and 3; Quad Cities Nuclear Power Station (Quad Cities), Units 1 and 2; and R. E. Ginna Nuclear Power Plant (Ginna) (collectively, the facilities).
Specific editions and addenda of Section XI of the American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel (BPV) Code are incorporated by reference in 10 CFR 50.55a with conditions.Section XI specifies, in part, requirements for documentation of repair and replacement activities at nuclear power plants. The proposed alternative would allow the licensee to forgo preparation and completion of a repair and replacement plan and certain forms for the routine replacement of pressure retaining bolting that is not included within Examination Categories B-G-1, B-G-2, or C-D at these facilities.
The regulations in 10 CFR 50.55a(z) state, in part, that alternatives to the requirements in paragraphs (b) through (h) of 10 CFR 50.55a may be authorized by the U.S. Nuclear Regulatory Commission (NRC) if the licensee demonstrates that: (1) the proposed alternative provides an acceptable level of quality and safety, or (2) compliance with the specified requirements would result in hardship or unusual difficulty without a compensating increase in the level of quality and safety.
The NRC staff has reviewed Exelons December 1, 2020, application, as supplemented, and concludes, as set forth in the enclosed safety evaluation, that the licensee has adequately addressed the regulatory requirements set forth in 10 CFR 50.55a(z)(1) for the current 10-year inservice inspection intervals at the facilities. Therefore, the NRC staff authorizes the licensee to use the proposed alternative described in its December 1, 2020, application, as supplemented, at Braidwood, Units 1 and 2; Byron, Unit Nos. 1 and 2; Calvert Cliffs, Units 1 and 2; Clinton, Unit No. 1; Dresden, Units 2 and 3; FitzPatrick; LaSalle, Units 1 and 2; Limerick, Units 1 and 2; NMP, Units 1 and 2; Peach Bottom, Units 2 and 3; Quad Cities, Units 1 and 2; and Ginna. This authorization is only for the remainder of the current 10-year inservice inspection intervals for each facility. As discussed in an April 26, 2021, e-mail (ADAMS Accession No. ML21117A044), the NRC staffs review of Exelons additional request to use the proposed alternative for the sixth 10-year ISI intervals at Dresden and Quad Cities is being performed separately under EPIDs L-2021-LLR-0030 and L-2021-LLR-0029, respectively.
All other ASME BPV Code requirements for which relief was not been specifically requested and approved remain applicable, including third-party review by the Authorized Nuclear Inservice Inspector.
If you have any questions, please contact Blake Purnell at 301-415-1380 or via e-mail at Blake.Purnell@nrc.gov.
Sincerely, Nancy L. Salgado, Chief Plant Licensing Branch III Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. STN 50-456, STN 50-457, STN 50-454, STN 50-455, 50-317, 50-318, 50-461, 50-237, 50-249, 50-333, 50-373, 50-374, 50-352, 50-353, 50-220, 50-410, 50-277, 50-278, 50-254, 50-265, and 50-244
Enclosure:
Safety Evaluation cc: Listserv Nancy L.
Salgado Digitally signed by Nancy L. Salgado Date: 2021.08.05 13:17:25 -04'00'
Enclosure SAFETY EVALUATION BY THE OFFICE OF NUCLEAR REACTOR REGULATION PROPOSED ALTERNATIVE TO ELIMINATE CERTAIN DOCUMENTATION REQUIREMENTS FOR PRESSURE RETAINING BOLTING BRAIDWOOD STATION, UNITS 1 AND 2 BYRON STATION, UNIT NOS. 1 AND 2 CALVERT CLIFFS NUCLEAR POWER PLANT, UNITS 1 AND 2 CLINTON POWER STATION, UNIT NO. 1 DRESDEN NUCLEAR POWER STATION, UNITS 2 AND 3 JAMES A. FITZPATRICK NUCLEAR POWER PLANT LASALLE COUNTY STATION, UNITS 1 AND 2 LIMERICK GENERATING STATION, UNITS 1 AND 2 NINE MILE POINT NUCLEAR STATION, UNITS 1 AND 2 PEACH BOTTOM ATOMIC POWER STATION, UNITS 2 AND 3 QUAD CITIES NUCLEAR POWER STATION, UNITS 1 AND 2 R.E. GINNA NUCLEAR POWER PLANT EXELON GENERATION COMPANY, LLC DOCKET NOS. STN 50-456, STN 50-457, STN 50-454, STN 50-455, 50-317, 50-318, 50-461, 50-237, 50-249, 50-333, 50-373, 50-374, 50-352, 50-353, 50-220, 50-410, 50-277, 50-278, 50-254, 50-265, AND 50-244
1.0 INTRODUCTION
By application dated December 1, 2020 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML20336A008), as supplemented by letters dated April 20 and July 7, 2021 (ADAMS Accession Nos. ML21110A092 and ML21188A242, respectively), Exelon Generation Company, LLC (Exelon, the licensee) submitted a request in accordance with paragraph 50.55a(z)(1) of Title 10 of the Code of Federal Regulations (10 CFR) for a proposed alternative to certain requirements of 10 CFR 50.55a, Codes and standards, for Braidwood Station (Braidwood), Units 1 and 2; Byron Station (Byron), Unit Nos. 1 and 2; Calvert Cliffs Nuclear Power Plant (Calvert Cliffs), Units 1 and 2; Clinton Power Station (Clinton), Unit No. 1; Dresden Nuclear Power Station (Dresden), Units 2 and 3; James A. FitzPatrick Nuclear Power Plant (FitzPatrick); LaSalle County Station (LaSalle), Units 1 and 2; Limerick Generating Station (Limerick), Units 1 and 2; Nine Mile Point Nuclear Station (NMP), Units 1 and 2; Peach Bottom Atomic Power Station (Peach Bottom), Units 2 and 3; Quad Cities Nuclear Power Station (Quad Cities), Units 1 and 2; and R. E. Ginna Nuclear Power Plant (Ginna) (collectively, the facilities).
The licensees April 20 and July 7, 2021, supplements were in response to a request for additional information issued by the U.S. Nuclear Regulatory Commission (NRC) staff on March 1, 2021 (ADAMS Accession No. ML21062A065).
Specific editions and addenda of Section XI of the American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel (BPV) Code are incorporated by reference in 10 CFR 50.55a with conditions.Section XI specifies, in part, requirements for documentation of repair and replacement activities at nuclear power plants. The proposed alternative would allow the licensee to forgo preparation and completion of a repair and replacement plan and certain forms for the routine replacement of pressure retaining bolting that is not included within Examination Categories B-G-1, B-G-2, or C-D at these facilities.
This safety evaluation (SE) only applies to the review of the proposed alternative for the current 10-year inservice inspection (ISI) intervals at Exelons facilities (see Section 3.1.2 of this SE).
As discussed in an April 26, 2021, e-mail (ADAMS Accession No. ML21117A044), the NRC staffs review of Exelons additional request to use the proposed alternative for the sixth 10-year ISI intervals at Dresden and Quad Cities is being performed separately under EPIDs L-2021-LLR-0030 and L-2021-LLR-0029, respectively.
2.0 REGULATORY EVALUATION
The regulations in 10 CFR 50.55a(g)(4) state, in part, that ASME BPV Code Class 1, 2, and 3 components (including supports) must meet the requirements, except the design and access provisions and the preservice examination requirements, set forth in Section XI of the applicable editions and addenda of the ASME Code to the extent practical within the limitations of design, geometry, and materials of construction of the components.
Paragraph 50.55a(g)(4)(ii) of 10 CFR requires, in part, that inservice examination of components and system pressure tests conducted during successive 10-year ISI intervals (i.e.,
each interval after the initial 10-year interval) must comply with the latest edition and addenda of the ASME BPV Code (or the optional ASME BPV Code cases) incorporated by reference in 10 CFR 50.55a(a) 18 months before the start of the 10-year interval (with some exceptions) subject to the conditions listed in 10 CFR 50.55a(b).
The NRC Regulatory Guide (RG) 1.147, Revision 19, Inservice Inspection Code Case Acceptability, ASME Section XI, Division 1, dated October 2019 (ADAMS Accession No. ML19128A244), is incorporated by reference into 10 CFR 50.55a(3)(ii). RG 1.147 identifies ASME BPV Code cases that the NRC has approved for use as a voluntary alternative to the mandatory ASME BPV Code,Section XI, provisions that are incorporated by reference into 10 CFR 50.55a. Licensees are permitted to use the ASME BPV Code cases listed in RG 1.147 without prior NRC approval provided that they meet the conditions of 10 CFR 50.55a(b)(5).
The regulations in 10 CFR 50.55a(z) state, in part, that alternatives to the requirements in paragraphs (b) through (h) of 10 CFR 50.55a may be authorized by the NRC if the licensee demonstrates that: (1) the proposed alternative provides an acceptable level of quality and safety, or (2) compliance with the specified requirements would result in hardship or unusual difficulty without a compensating increase in the level of quality and safety.
Appendix B, Quality Assurance Criteria for Nuclear Power Plants and Fuel Reprocessing Plants, to 10 CFR Part 50 establishes quality assurance requirements for the design, fabrication, construction, and testing of structures, systems, and components (SSCs). The pertinent requirements of Appendix B apply to all activities affecting the safety-related functions of those SSCs and include designing, purchasing, fabricating, handling, shipping, storing, cleaning, erecting, installing, inspecting, testing, operating, maintaining, repairing, refueling, and modifying SSCs.
3.0 TECHNICAL EVALUATION
3.1 Licensees Request 3.1.1 ASME Code Components Affected All pressure retaining bolting subject to the ASME BPV Code,Section XI, that is not classified as Examination Category B-G-1 (Class 1 pressure retaining bolting greater than 2 inches in diameter), B-G-2 (Class 1 pressure retaining bolting that is 2 inches in diameter or less), or C-D (Class 2 pressure retaining bolting greater than 2 inches in diameter).
3.1.2 Applicable Code Edition and Addenda The licensee identified the currently applicable ASME BPV Code editions and addenda for each plant in its December 1, 2020, and April 20, 2021, letters as shown in the table below. In addition, the table shows the associated 10-year ISI interval, including the start and end dates, for each plant.
PLANT ISI INTERVAL ASME BPV CODE EDITION START END Braidwood Unit 1 4th 2013 Edition 8/29/2018 7/28/2028 Braidwood Unit 2 4th 2013 Edition 11/5/2018 10/16/2028 Byron Units 1 and 2 4th 2007 Edition, through 2008 Addenda 7/16/2016 7/15/2025 Calvert Cliffs Units 1 and 2 5th 2013 Edition 7/1/2019 6/30/2029 Clinton 4th 2013 Edition 7/1/2020 6/30/2030 Dresden Units 2 and 3 5th 2007 Edition, through 2008 Addenda 1/20/2013 1/19/2023 FitzPatrick 5th 2007 Edition, through 2008 Addenda 8/1/2017 6/15/2027 LaSalle Units 1 and 2 4th 2007 Edition, through 2008 Addenda 10/1/2017 9/30/2027 Limerick Units 1 and 2 4th 2007 Edition, through 2008 Addenda 2/1/2017 1/31/2027 NMP Unit 1 5th 2013 Edition 8/23/2019 8/22/2029 NMP Unit 2 4th 2013 Edition 8/23/2018 8/22/2028 PLANT ISI INTERVAL ASME BPV CODE EDITION START END Peach Bottom Units 2 and 3 5th 2013 Edition 1/1/2019 12/31/2028 Quad Cities Units 1 and 2 5th 2007 Edition, through 2008 Addenda 4/2/2013 4/1/2023 Ginna 6th 2013 Edition 1/1/2020 12/31/2029 3.1.3 Applicable Code Requirements The licensee has requested an alternative to the following ASME BPV Code,Section XI, requirements:
IWA-4141 (2007 Edition, through 2008 Addenda, and 2013 Edition) requires the Owner to provide or cause to be provided a Repair Replacement Program, a Repair Replacement Plan, and specification requirements for repair/replacement activities.
IWA-4142 (2007 Edition, through 2008 Addenda, and 2013 Edition) requires the organization that performs repair/replacement activities to establish a Quality Assurance Program for control of their activities in accordance with the Repair/Replacement Program and Plans.
IWA-4150(c) (2007 Edition, through 2008 Addenda, and 2013 Edition) requires a Repair/Replacement Plan to be prepared in accordance with the Repair/Replacement Program whenever a repair/replacement activity is to be performed.
IWA-4150(d) (2007 Edition, through 2008 Addenda, and 2013 Edition) requires that Repair/Replacement Plans be subject to review by enforcement and regulatory authorities having jurisdiction at the plant site.
IWA-4511 (2007 Edition, through 2008 Addenda, and 2013 Edition) requires personnel performing nondestructive examination required by the Construction Code to be qualified and certified in accordance with the Construction Code identified in the Repair/Replacement Plan.
IWA-6210(e) (2007 Edition, through 2008 Addenda) or IWA-6211(e) (2013 Edition) requires the Owner to prepare the Owners Report for Repair/Replacement Activity, Form NIS-2 upon completion of all required activities associated with the Repair/Replacement Plan.
IWA-6210(f) (2007 Edition, through 2008 Addenda) or IWA-6211(g) (2013 Edition) requires the Owner to submit Forms NIS-1 and NIS-2 to the inspector and obtain the required signatures.
IWA-6350 (2007 Edition, through 2008 Addenda, and 2013 Edition) requires Repair/Replacement Plans and Form NIS-2 to be retained.
Code Case N-532-5, Repair/Replacement Activity Documentation Requirements and Inservice Inspection Summary Report Preparation and Submission,Section XI, Division 1, may be used as an alternative to the ASME BPV Code,Section XI, requirements for the completion of Form NIS-1, Form NIS-2, or an ISI summary report. This code case substitutes the Form NIS-2 with Form NIS-2A. Code Case N-532-5 is the latest version of this code case approved by the NRC for general use by licensees in RG 1.147, Revision 19.
3.1.4 Licensees Proposed Alternative and Basis for Use The proposed alternative would allow the licensee to forego preparation and completion of a Repair/Replacement Plan and associated Form NIS-2 (or NIS-2A) for replacement of pressure retaining bolting that is not classified as Examination Category B-G-1, B-G-2, or C-D at its facilities. The proposed alternative will not be applied to activities that involve replacement of bolting that has experienced unacceptable service-induced degradation or when involving a design change. This proposed alternative will apply to bolting replacement during normal maintenance work activities due to damage or loss unless involving Examination Category B-G-1, B-G-2, or C-D components. Unacceptable service-induced degradation that cannot apply this proposed alternative is defined as follows:
Fractures and crack like flaws not caused by maintenance activities.
More than one deformed or sheared thread in the zone of thread engagement that is due to a service-induced condition.
Corrosion that reduces the bolt cross sectional area by more than 5 percent.
Bending, twisting, or deformation of bolts determined to be from a service-induced condition.
Degradation of protective coatings on bolting surfaces.
Replacement bolting will receive Construction Code and Owners Requirements nondestructive examination (NDE) as part of the normal procurement and receipt inspection processes which identify applicable Construction Code and Owners Requirements. The Construction Code and Owners Requirements for NDE will be documented in the procurement and receipt records.
Documentation of the work activity and replacement bolting will be achieved through the normal processes of procurement, planning, and maintenance. The proposed alternative would use current work control, procurement, and records retention processes to assure adequate controls of these routine bolting replacements. A log will be maintained that identifies the work packages where the proposed alternative has been used. The Authorized Inspection Agency (AIA) will have access to the site work control systems and the log, which will allow the AIA to review work package instructions and associated procurement documentation. Close-out reviews will continue to be completed through the normal post-work review process to assure appropriate documentation of work performed and material traceability is achieved.
The licensee stated, in part, that: The procurement and work activity records will document technical requirements and work activities to allow subsequent review for adequacy and traceability, thereby meeting the intent of Code requirements and maintaining an acceptable level of quality and safety.
3.2 NRC Staffs Evaluation The licensee requested to forego preparation and completion of a Repair/Replacement Plan and the associated Form NIS-2 (or NIS-2A) for routine replacement of pressure retaining bolting that is not classified as Examination Category B-G-1, B-G-2, or C-D. Instead, the documentation of the work activity and replacement bolting will be achieved using current work management systems, procurement specifications, installation procedures, work order documentation, and record retention processes in accordance with the licensees Quality Assurance Program (QAP). For example, in accordance with the licensees QAP, safety-related bolting materials receive a quality receipt inspection by a qualified individual, which includes physical inspections and a review of the applicable documentation. When bolting is installed, bolting material traceability information, such as a unique material identifier or purchase order number, is documented in the work order and available for review as part of the completed work order package. Close-out reviews will continue to be completed through the normal post-work review process to assure appropriate documentation of work performed and material traceability is achieved. These processes and work control systems, including the associated work orders and procurement documentation, will be available at each site for review by the AIA and the NRC when requested.
The current Form NIS-2 (or NIS-2A) is used to document that repair/replacement activities were performed in accordance with the requirements of Section XI of the ASME BPV Code. Since this proposed alternative would forgo preparation and completion of the Form NIS-2 (or NIS-2A), the AIA will have access to the site work control systems for review at their discretion.
Should the AIA choose to review completed work orders that fall under this proposed alternative, the work management system will be used to document any AIA comments during the review of the work order records.
The licensees July 7, 2021, supplement states, in part:
For routine replacement of bolting, where no service induced degradation has been identified (i.e., lost bolting, bolting damaged during disassembly), the only ASME Section XI requirements currently invoked beyond normal work and procurement processes are administrative in nature and include completion of a Repair/Replacement Plan and completion of a Form NIS-2 (or NIS-2A). For these replacements, the Repair/Replacement Plan provides no additional information other than reiteration of the work package instructions for bolting replacement. Similarly, since there are no additional technical requirements under Section XI for routine bolting replacement, completing the Form NIS-2 (or NIS-2A) is merely generating an additional document for activities that are already covered through the work control process and procedures, along with the procurement process and procedures. The NIS-2 (or NIS-2A) does not contain any specific information; therefore, it does not provide any information beyond indicating the bolting was replaced in accordance with the Owners processes and procedures, which ensure the Owners responsibilities under ASME Section XI have been met.
Furthermore, the licensee stated that a log will be maintained that identifies the work packages where the proposed alternative has been used. The AIA and the NRC will have access to the log, providing them the opportunity to review the work package instructions and associated procurement documentation.
The NRC staff reviewed the licensees application, as supplemented, for the proposed alternative to eliminate the preparation and completion of a Repair/Replacement Plan and associated Form NIS-2 (or NIS-2A) for pressure retaining bolting that is not included within Examination Categories B-G-1, B-G-2, or C-D. The proposed alternative will only be used for routine replacement of bolting (i.e., replacement of lost bolting or bolting damaged during disassembly) where no service induced degradation has been identified. The NRC staff determined that this proposed alternative is limited to certain administrative requirements in the ASME BPV Code,Section XI, and it does not change any technical requirements in the ASME BPV Code,Section XI, or the Construction Code associated with bolting materials, installation, or maintenance. In addition, the proposed alternative does not change any process associated with repair/replacement activities or the QAP except for the documentation process for the routine replacement of bolting. The NRC staff has reasonable assurance that the licensees implementation of the proposed alternative for routine replacement of bolting will continue to meet the requirements of Appendix B to 10 CFR Part 50 because the licensee will use its QAP when implementing this proposed alternative. Therefore, the NRC staff concludes that the proposed alternative will provide an acceptable level of quality and safety.
4.0 CONCLUSION
As set forth above, the NRC staff determined that the licensees proposed alternative to eliminate certain documentation requirements for pressure retaining bolting provides an acceptable level of quality and safety. Accordingly, the NRC staff concludes that the licensee has adequately addressed the regulatory requirements set forth in 10 CFR 50.55a(z)(1).
Therefore, the NRC staff authorizes the licensee to use the proposed alternative described in its application, as supplemented, at Braidwood, Byron, Calvert Cliffs, Clinton, Dresden, FitzPatrick, LaSalle, Limerick, NMP, Peach Bottom, Quad Cities, and Ginna. This authorization is for the remainder of the current 10-year ISI intervals for each facility, which are listed Section 3.1.2 of this SE.
All other ASME BPV Code requirements for which relief was not been specifically requested and approved remain applicable, including third-party review by the Authorized Nuclear Inservice Inspector.
Principal Contributors: Yamir Diaz-Castillo Blake Purnell Date of issuance: August 5, 2021