Annual Assessment Letter for Clinton Power Station (Report 05000461/2023006)
ML24058A292
Person / Time
Site: Clinton Constellation icon.png
Issue date: 02/28/2024
From: Robert Ruiz
NRC/RGN-III/DORS/RPB1
To: Rhoades D
Constellation Energy Generation
Shared Package
ML24057A080 List:
References
IR 2023006
Download: ML24058A292 (1)


Text

February 28, 2024

SUBJECT:

ANNUAL ASSESSMENT LETTER FOR CLINTON POWER STATION (REPORT 05000461/2023006)

Dear David Rhoades:

The NRC has completed its end-of-cycle performance assessment of Clinton Power Station, reviewing performance indicators (PIs), inspection results, and enforcement actions from January 1, 2023, through December 31, 2023. This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility. The NRC concluded that overall performance at your facility preserved public health and safety. The baseline inspection program was completed at your facility as defined in Inspection Manual Chapter 2515, Light-Water Reactor Inspection Program - Operations Phase.

The NRC determined the performance at Clinton Power Station during the most recent quarter was within the Licensee Response Column, the highest performance category of the NRCs Reactor Oversight Process (ROP) Action Matrix, because all inspection findings had very low safety significance (i.e., Green), and all PIs were within the expected range (i.e., Green).

Therefore, the NRC plans to conduct ROP baseline inspections at your facility.

The enclosed inspection plan lists the inspections scheduled through December 31, 2025.

The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last twelve months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes.

The NRC plans to conduct inspection procedure (IP) 71002, License Renewal Inspection, in 2024, and IP 71003, Post-Approval Site Inspection for License Renewal, in 2025. In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Please contact me at 630-829-9732 with any questions you have regarding this letter.

Sincerely, Robert Ruiz, Chief Reactor Projects Branch 1 Division of Operating Reactor Safety Docket Nos. 05000461 License Nos. NPF-62 Enclosure:

Inspection Plan Distribution via LISTSERV Signed by Ruiz, Robert on 02/28/24 Letter to David Rhoades from Robert Ruiz dated February 28, 2024.

SUBJECT:

ANNUAL ASSESSMENT LETTER FOR CLINTON POWER STATION (REPORT 05000461/2023006)

DISTRIBUTION:

Farrah Gaskins RidsNrrDorlLpl3 RidsNrrPMClinton Resource RidsNrrDroIrib Resource John Giessner Mohammed Shuaibi Diana Betancourt-Roldan Allan Barker David Curtis R3-DORS ROPassessment.Resource@nrc.gov ADAMS Accession Number: ML24058A292 Publicly Available Non-Publicly Available Sensitive Non-Sensitive OFFICE RIII RIII RIII RIII NAME NShah:gmp RRuiz DATE 02/27/2024 02/28/2024

Site Inspection Activity Plan 07201046 - Clinton Power Station (ISFSI)

01/01/2024 - 12/31/2025 Unit Start End Activity CAC Title Staff Count ISFSI Program Review Inspection

3/10/2025 3/14/2025 IP 60855 001001 Operation Of An ISFSI Prepared on 2/26/2024 9:45:59 AM 1 of 3

Site Inspection Activity Plan Clinton 01/01/2024 - 12/31/2025 Unit Start End Activity CAC Title Staff Count Corporate Security Baseline Inspection

1 1/22/2024 1/26/2024 IP 71130.01 000733 Access Authorization Biennial Problem Identification and Resolution Inspection

1 4/8/2024 4/26/2024 IP 71152B 000747 Problem Identification and Resolution Emergency Preparedness Baseline Inspection / Performance Indicator Verification

1 4/15/2024 4/19/2024 IP 71114.02 000717 Alert and Notification System Testing

4/15/2024 4/19/2024 IP 71114.03 000718 Emergency Response Organization Staffing and Augmentation System

4/15/2024 4/19/2024 IP 71114.05 000720 Maintenance of Emergency Preparedness

4/15/2024 4/19/2024 IP 71151 001397 Performance Indicator Verification Functional Engineering Inspection - Commercial Grade Dedication

1 5/20/2024 6/7/2024 IP 71111.21N.04 001832 Age-Related Degradation Security Baseline Inspection

1 2/12/2024 2/16/2024 IP 71130.04 000736 Equipment Performance, Testing, and Maintenance

5/20/2024 5/24/2024 IP 71130.01 000733 Access Authorization

5/20/2024 5/24/2024 IP 71130.09 001656 Security Plan Changes

5/20/2024 5/24/2024 IP 71151 001338 Performance Indicator Verification Security Baseline Inspection

1 7/22/2024 7/26/2024 IP 71130.02 000734 Access Control

7/22/2024 7/26/2024 IP 71130.05 000737 Protective Strategy Evaluation Clinton 2024 Licensed Operator Biennial Requalification Program Inspection

1 9/15/2024 9/21/2024 IP 71111.11B 000704 Licensed Operator Requalification Program and Licensed Operator Performance License Renewal Phase 2

1 10/21/2024 11/8/2024 IP 71002 000686 License Renewal Inspection Eplan and EAL Changes Review

1 11/1/2024 12/31/2024 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes Radiation Protection Baseline Inspection

1 12/9/2024 12/13/2024 IP 71124.05 000729 Radiation Monitoring Instrumentation

12/9/2024 12/13/2024 IP 71124.06 000730 Radioactive Gaseous and Liquid Effluent Treatment Material Control and Accountability

1 1/1/2025 12/31/2025 IP 71130.11 000742 Material Control and Accounting (MC&A)

Security Baseline Inspection

1 2/10/2025 2/14/2025 IP 71130.14 000743 Review of Power Reactor Target Sets Prepared on 2/26/2024 9:45:59 AM 2 of 3

Site Inspection Activity Plan

2/24/2025 2/28/2025 IP 71130.02 000734 Access Control

2/24/2025 2/28/2025 IP 71151 001338 Performance Indicator Verification Clinton January 2025 NRC Developed Initial License Exam

1 3/16/2025 3/22/2025 OV 000956 FB-OR-ONSITE VALIDATION OF INITIAL LICENSE EXAMINATION (OV)

6/1/2025 6/7/2025 OV 000956 FB-OR-ONSITE VALIDATION OF INITIAL LICENSE EXAMINATION (OV)

7/13/2025 7/19/2025 EXAD 000500 FB-OR-INITIAL LICENSE EXAM ADMINISTRATION (EXAD)

7/20/2025 7/26/2025 EXAD 000500 FB-OR-INITIAL LICENSE EXAM ADMINISTRATION (EXAD)

Cyber Security Inspection

1 4/7/2025 4/11/2025 IP 71130.10 000741 Cybersecurity Radiation Protection Baseline Inspection

1 6/2/2025 6/6/2025 IP 71124.07 000731 Radiological Environmental Monitoring Program

6/2/2025 6/6/2025 IP 71124.08 000732 Radioactive Solid Waste Processing & Radioactive Material Handling, Storage, & Transportation Comprehensive Engineering Team Inspection

1 6/9/2025 6/27/2025 IP 71111.21M 000713 Comprehensive Engineering Team Inspection Emergency Preparedness Exercise Inspection / Performance Indicator Review

1 7/21/2025 7/25/2025 IP 71114.01 000716 Exercise Evaluation

7/21/2025 7/25/2025 IP 71151 001397 Performance Indicator Verification Security Baseline Inspection

1 8/25/2025 8/29/2025 IP 71130.07 000739 Security Training

8/25/2025 8/29/2025 IP 71130.09 001656 Security Plan Changes License Renewal Phase 1

1 9/8/2025 9/19/2025 IP 71003 000687 Post-Approval Site Inspection for License Renewal Inservice Inspection Unit 1

1 9/8/2025 9/19/2025 IP 71111.08G 000701 Inservice Inspection Activities (BWR)

Radiation Protection Baseline Inspection

1 9/15/2025 9/19/2025 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls

9/15/2025 9/19/2025 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation

9/15/2025 9/19/2025 IP 71124.04 000728 Occupational Dose Assessment Eplan and EAL Changes Review

1 11/1/2025 12/31/2025 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes Prepared on 2/26/2024 9:45:59 AM 3 of 3