IR 05000461/2024002

From kanterella
Jump to navigation Jump to search
Integrated Inspection Report 05000461/2024002
ML24221A239
Person / Time
Site: Clinton Constellation icon.png
Issue date: 08/09/2024
From: Robert Ruiz
NRC/RGN-III/DORS/RPB1
To: Rhoades D
Constellation Energy Generation
References
IR 2024002
Download: ML24221A239 (1)


Text

SUBJECT:

CLINTON POWER STATION - INTEGRATED INSPECTION REPORT 05000461/2024002

Dear David Rhoades:

On June 30, 2024, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Clinton Power Station. On July 18, 2024, the NRC inspectors discussed the results of this inspection with Andrew Krukowski, Plant Manager, and other members of your staff. The results of this inspection are documented in the enclosed report.

No NRC-identified or self-revealing findings were identified during this inspection.

Licensee-identified violations which were determined to be of very low safety significance and Severity Level IV are documented in this report. We are treating these violations as non-cited violations (NCVs) consistent with Section 2.3.2 of the Enforcement Policy.

If you contest the violations or the significance or severity of the violations documented in this inspection report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN:

Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region III; the Director, Office of Enforcement; and the NRC Resident Inspector at Clinton Power Station.

August 9, 2024 This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Robert Ruiz, Chief Reactor Projects Branch 1 Division of Operating Reactor Safety Docket No. 05000461 License No. NPF-62

Enclosure:

As stated

Inspection Report

Docket Number:

05000461

License Number:

NPF-62

Report Number:

05000461/2024002

Enterprise Identifier:

I-2024-002-0056

Licensee:

Constellation Nuclear

Facility:

Clinton Power Station

Location:

Clinton, IL

Inspection Dates:

April 01, 2024, to June 30, 2024

Inspectors:

Z. Helgert, Project Engineer

J. Kutlesa, Senior Emergency Preparedness Inspector

A. Muneeruddin, Resident Inspector

J. Steward, Senior Resident Inspector

Approved By:

Robert Ruiz, Chief

Reactor Projects Branch 1

Division of Operating Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Clinton Power Station, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information. Licensee-identified non-cited violations are documented in report section: 71152

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

PLANT STATUS

Unit 1 began the inspection period at rated thermal power (RTP). On May 25, 2024, Unit 1 lowered reactor power to 77 percent RTP to perform a planned control rod sequence exchange and control rod scram time testing. On May 26, 2024, the unit returned to RTP and continued to operate at or near RTP for the remainder of the inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed activities described in IMC 2515, Appendix D, Plant Status, observed risk significant activities, and completed on-site portions of IPs. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.01 - Adverse Weather Protection

Seasonal Extreme Weather Sample (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated readiness for seasonal extreme weather conditions prior to the onset of seasonal hot temperatures for the following systems:

fire protection, service water, flume coolers, and the switchyard May 29 through June 3, 2024

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (3 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1)standby gas treatment (VG) train A during VG train B outage window on May 7, 2024 (2)control room heating, ventilation, and cooling (VC) train B during VC train A outage window on May 14, 2024 (3)standby liquid control trains A and B on May 30, 2024

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (5 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1) Fire Areas CB-1a and CB-1c; elevations 712'-719'; diesel generator (DG) building Unit 2 basement and hallway and control building heating, ventilation, and air conditioning (HVAC) equipment area on May 10, 2024
(2) Fire Areas D-1, D-2, and D-3; elevation 712'; division 1, 2, and 3 DG building diesel fuel tank rooms on May 10, 2024
(3) Fire Area CB-1i; control building; elevation 815'; division 1 and 2 control room HVAC areas on May 15, 2024
(4) Fire Areas N/A; main power transformers; unit auxiliary transformers; emergency reserve auxiliary transformer; reserve auxiliary transformers A, B, and C on May 21, 2024
(5) Fire Areas N/A; elevation 699'-737'; flex equipment storage building and independent spent fuel storage facility installation pad and travel path on May 29, 2024

Fire Brigade Drill Performance Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated the onsite fire brigade training and performance during an unannounced fire drill on June 11, 2024.

71111.06 - Flood Protection Measures

Flooding Sample (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated internal flooding mitigation protections in the screen house building specific to the division 1, 2, and 3 shutdown service water system on May 14, 2024.

71111.07A - Heat Exchanger/Sink Performance

Annual Review (IP Section 03.01) (1 Sample)

The inspectors evaluated readiness and performance of:

(1) residual heat removal pump room heat exchanger 1B on May 1, 2024

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)

(1) The inspectors observed and evaluated licensed operator performance in the control room during a planned downpower to 77 percent RTP for control rod scram time testing on May 25, 2024.

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1) The inspectors observed and evaluated licensed operator requalification simulator training on April 18, 2024.

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (3 Samples)

The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components (SSCs) remain capable of performing their intended function:

(1)elevated vibration on component cooling water pump C per Action Request (AR) 4755413 on May 13, 2024 (2)review of the maintenance rule program periodic assessment report which covers the period from October 15, 2021, through October 11, 2023, completed on June 27, 2024 (3)failure of limit switch #5 on inboard main steam isolation valve (MSIV) 1B21-F022D on June 28, 2024

Quality Control (IP Section 03.02) (1 Sample)

The inspectors evaluated the effectiveness of maintenance and quality control activities to ensure the following SSC remains capable of performing its intended function:

(1)commercial grade dedication of a 5-watt 8.25K ohm resistor used in the temporary modification of a failed limit switch that inputs into the reactor protection system trip logic for inboard MSIV 1B21-F022D on April 11, 2024

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (6 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:

(1)review of plant aggregate risk and risk management actions for the week of May 6, 2024, during standby gas treatment system B and division 4 battery charger system outage windows (2)elevated online risk due to planned 138kV line outage window on May 19, 2024 (3)elevated online risk due to planned system outage window for the emergency reserve auxiliary transformer on May 20 and May 21, 2024 (4)elevated online risk due to planned system outage window for the division 2 diesel generator air compressor/receiver and during remote shutdown panel operability checks on May 28, 2024 (5)elevated online risk due to emergent system outage window for the division 3 DG heat exchanger on June 12, 2024 (6)risk informed completion time evaluation for Technical Specification (TS) 3.7.1 associated with the planned replacement of 1SX062B, fuel pool cooling B heat exchanger shutdown service water outlet valve on June 13, 2024

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (4 Samples)

The inspectors evaluated the licensees justifications and actions associated with the following operability determinations and functionality assessments:

(1)main turbine bypass valve #5 fast-acting solenoid failed to actuate during surveillance testing per AR 4764072 on April 10, 2024 (2)two small pits were identified below minimum wall thickness on 1SXH6AA per AR 4766935 on May 9, 2024 (3)main turbine bypass valve #2 and main turbine bypass valve #4 fast-acting solenoids failed to actuate during surveillance testing per Clinton Power Station (CPS) 9072.01 on June 20, 2024 (4)air void identified in residual heat removal B line per AR 4776938 on June 21, 2024

71111.18 - Plant Modifications

Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02) (1 Sample)

The inspectors evaluated the following temporary or permanent modifications:

(1)inboard MSIV 1B21-F022D temporary modification to substitute limit switch #3 with optical isolator for limit switch #5 for reactor protection system input on April 5, 2024

71111.24 - Testing and Maintenance of Equipment Important to Risk

The inspectors evaluated the following testing and maintenance activities to verify system operability and/or functionality:

Post-Maintenance Testing (PMT) (IP Section 03.01) (7 Samples)

(1)standby gas treatment system train B flow/heater operability following a planned maintenance window per Work Order (WO) 5510542 on May 15, 2024 (2)control room HVAC train A PMT following a planned maintenance window on May 23, 2024 (3)standby liquid control train B pump and valve operability following a planned maintenance window per WOs 5524780 and 5524779 on May 31, 2024 (4)division 2 emergency diesel generator operability run following a planned starting air compressor maintenance window on June 6, 2024 (5)emergency reserve auxiliary transformer PMT following a planned maintenance window on June 11, 2024 (6)1SX062B, fuel pool cooling B heat exchanger shutdown service water outlet valve PMT following a planned maintenance window on June 17, 2024 (7)component cooling pump C PMT following a planned maintenance window on June 26, 2024

Surveillance Testing (IP Section 03.01) (4 Samples)

(1)surveillance of fuel pool cooling pumps 1A, 1B, and associated valves per WOs 5482445 and 5444564 on April 25, 2024 (2)division 2 diesel generator 24-hour run and hot restart operability per WO 5308133 on May 17, 2024 (3)fire protection valve lineup checklist (safety related) per WO 5372213 on May 17, 2024 (4)residual heat removal pump A, 1E12-C002A comprehensive pump testing per WO 5271051 on June 28, 2024

71114.02 - Alert and Notification System Testing

Inspection Review (IP Section 02.01-02.04) (1 Sample)

(1) The inspectors evaluated the following maintenance and testing of the alert and notification system:
  • annual siren inspection and maintenance records for the period of April 2022 to April 2024
  • weekly alert notification system (siren) tests for the period of April 2022 to April 2024

71114.03 - Emergency Response Organization Staffing and Augmentation System

Inspection Review (IP Section 02.01-02.02) (1 Sample)

(1) The inspectors evaluated the readiness of the emergency preparedness organization.

71114.05 - Maintenance of Emergency Preparedness

Inspection Review (IP Section 02.01 - 02.11) (1 Sample)

(1) The inspectors evaluated the maintenance of the emergency preparedness program.

71114.06 - Drill Evaluation

Required Emergency Preparedness Drill (1 Sample)

(1)emergency planning drill observed in the simulator and in the technical support center on April 30,

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:

MS06: Emergency AC Power Systems (IP Section 02.05)===

(1) April 1, 2023, through March 31, 2024

MS07: High Pressure Injection Systems (IP Section 02.06) (1 Sample)

(1) April 1, 2023, through March 31, 2024

MS08: Heat Removal Systems (IP Section 02.07) (1 Sample)

(1) April 1, 2023, through March 31, 2024

EP01: Drill/Exercise Performance (DEP) Sample (IP Section 02.12) (1 Sample)

(1) April 1, 2022, through March 31, 2024 EP02: Emergency Response Organization (ERO) Drill Participation (IP Section 02.13) (1 Sample)
(1) April 1, 2022, through March 31, 2024 EP03: Alert And Notification System (ANS) Reliability Sample (IP Section 02.14) (1 Sample)
(1) April 1, 2022, through March 31, 2024

71152A - Annual Follow-up Problem Identification and Resolution Annual Follow-up of Selected Issues (Section 03.03)

The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:

(1) Licensee identified that prior NRC approval should have been requested to release the Clinton Lake Marina property for unrestricted use. The inspectors reviewed the issue against the following success criteria identified in IP 71152, Section 03.04:

1. Deficient conditions associated with safety system performance or regulatory

compliance are promptly brought to the attention of main control room operators so operability and functionality can be assessed. When appropriate, TSs action statements or compensatory measures are initiated.

2. The licensee appropriately prioritizes issues in accordance with safety,

security, or radiological significance so that licensee resources and oversight are assigned commensurate with the actual or potential consequences of the issue in accordance with their problem identification and resolution (PI&R) program.

3. The licensee thoroughly evaluates issues to ensure that resolutions address

causes and extent of conditions commensurate with their safety, security, and radiological significance in accordance with the corrective action program procedure and quality assurance plan.

4. The licensee effectively schedules and completes corrective action

development commensurate with their safety significance using the work control process.

5. The licensee ensures the final corrective actions completed adequately

address the original issue observed.

6. The licensee tracks action tracking items to completion in the corrective

action program.

Inspector conclusions for this sample are documented in the Results section under 71152.

(2) Review and assessment of the stations corrective actions following failure of protecting division 2 direct current (DC) motor control center (MCC) after the implementation of Engineering Change (EC) 641708, as documented in AR 4777232 on June 28,

INSPECTION RESULTS

Licensee-Identified Non-Cited Violation 71152A This violation of very low safety significance was identified by the licensee and has been entered into the licensee corrective action program and is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

Violation: 10 CFR 50.83(a) requires, in part, that prior written NRC approval is required to release part of a facility or site for unrestricted use at any time before receiving approval of a license termination plan.

Contrary to the above, on September 17, 2003, the licensee failed to obtain prior written NRC approval before releasing a part of their facility for unrestricted use. Specifically on January 18, 2023, it was identified that the licensee transferred 172.7 acres of land from the Clinton Lake Marina to DeWitt County, Illinois, without obtaining prior written NRC approval.

Significance/Severity: Green. Severity Level IV. In accordance with the NRC Enforcement Policy, because this violation impacted the regulatory process it is being dispositioned using traditional enforcement. The licensee has submitted a request consistent with 10 CFR 50.83 seeking approval to release the land by letter RS-23-073 dated June 7, 2023, on the docket.

The property released meets the definition of non-impacted areas in accordance with 10 CFR 50.2 as it has no reasonable potential for residual radioactivity more than natural background and thus has no potential or actual consequences associated with its release.

The violation is categorized as Severity Level IV because no actual or potential safety consequences exist, and the violation was determined to be similar to traditional enforcement examples under Section 6.9.d of the NRC Enforcement Policy, dated January 12, 2024.

Corrective Action References: AR 4549014 Licensee-Identified Non-Cited Violation 71152A This violation of very low safety significance was identified by the licensee and has been entered into the licensee corrective action program and is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

Violation: Title 10 CFR Part 50.65(a)(4), Requirements for Monitoring the Effectiveness of Maintenance at Nuclear Power Plants, requires, in part, that before performing maintenance activities (including but not limited to surveillance, post-maintenance testing, and corrective and preventive maintenance), the licensee shall assess and manage the increase in risk that may result from the proposed maintenance activities.

Contrary to the above, from March 30, 2024, to May 22, 2024, the licensee failed to manage the increase in risk from a proposed maintenance activity which was implemented by the licensee in EC 641708. Specifically, the licensee identified that they had failed to display protected equipment postings on division 2 DC MCC as required per station procedure OP-AA-108-117, Protected Equipment Program.

Significance/Severity: Green. Using IMC 0609, Appendix K, Maintenance Risk Assessment and Risk Management Significance Determination Process, Flowchart 2, Assessment of RMAs, the inspectors determined the finding screened to very low safety significance (Green) because the incremental core damage probability was less than 1E-6 and the incremental large early release probability was less than 1E-7.

Corrective Action References: AR

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On July 18, 2024, the inspectors presented the integrated inspection results to Andrew Krukowski, Plant Manager, and other members of the licensee staff.
  • On April 19, 2024, the inspectors presented the emergency preparedness inspection results to Norha Plumey, Site Vice President, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

AR 4776476

Unsecured Material Left in Secured Material Zone

05/25/2024

Corrective Action

Documents

AR 4777837

FMD ID - A Tower Deficiencies

05/31/2024

Drawings

ELC-005

Flume Cooler Power Distribution - Overview

08/27/2018

Miscellaneous

Site Certification Letter for Summer Readiness

05/15/2024

MA-AA-716-026

Station Housekeeping/Material Condition Program

71111.01

Procedures

WC-AA-107

Seasonal Readiness

CPS 3314.01

Standby Liquid Control (SC)

2c

CPS

3314.01E001

Standby Liquid Control Electrical Lineup

9a

CPS

3314.01V001

Standby Liquid Control Valve Lineup

10b

CPS

3314.01V002

Standby Liquid Control Instrument Valve Lineup

CPS 3319.01

Standby Gas Treatment (VG)

17c

CPS

3319.01E001

Standby Gas Treatment Electrical Lineup

CPS

3319.01V001

Standby Gas Treatment Valve Lineup

CPS 3402.01

Control Room HVAC (VC)

33c

CPS

3402.01E001

Control Room HVAC Electrical Lineup

10e

CPS

3402.01P001

Control Room HVAC (VC) Shifting Train A to Train B

8d

71111.04

Procedures

CPS

3402.01V001

Control Room HVAC Valve Lineup

17a

Corrective Action

Documents

AR 4774524

Unusual Conditions Near RATs and MPTs

05/16/2024

Corrective Action

Documents

Resulting from

Inspection

AR 4773359

Questions from NRC Walkdown

05/10/2024

71111.05

Fire Plans

CPS

Prefire Plan Legend

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

1893.04M003

CPS

1893.04M310

719 Control: HVAC Equipment Area Prefire Plan

6c

CPS

1893.04M340

2 Control: General Access Area Prefire Plan

6e

CPS

1893.04M370

25 Control: Control Room HVAC Prefire Plan

7b

CPS

1893.04M500

2 Diesel Generator: Div 3 Diesel Fuel Tank Room Prefire

Plan

5b

CPS

1893.04M501

2 Diesel Generator: Div 1 Diesel Fuel Tank Room Prefire

Plan

5b

CPS

1893.04M502

2 Diesel Generator: Div 2 Diesel Fuel Tank Room Prefire

Plan

6a

CPS

1893.04M503

2-719 Diesel Generator: Unit 2 Basement and Hallway

Prefire Plan

6b

CPS

1893.04M838

Flex Equipment Storage Building Prefire Plan

CPS

1893.04M910

MPT, RAT A&C, & Bus Ducts Prefire Plan

2b

CPS

1893.04M911

Transformers: UATs, RAT B, ERAT, RAT MSC, ERAT MSC

& Bus Ducts Prefire Plan

5c

CPS

1893.04M913

Independent Spent Fuel Storage Facility Installation (ISFSFI)

Prefire Plan

0a

Fire Drill

Scenario: CB762-

1F-01

Fire in MMD Storage Area by U2 CCW Expansion Tank with

Victim

06/11/2024

IMP05-2024-003

Hourly Fire Watch Inspection Log: Control Building 825'

VC-A Room

05/13/2024

Miscellaneous

IMP05-2024-004

Hourly Fire Watch Inspection Log: Control Building 825'

VC-A Room

05/14/2024

OP-AA-201-003

Fire Drill Performance

OP-AA-201-005

Fire Brigade Qualification

OP-AA-201-007

Fire Protection System Impairment Control

Procedures

OP-AA-201-008

Pre-fire Plan Manual

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

IP-M-0197

Evaluation of Potential Inleakage through Screen House

Penetration Seals Below Probable Maximum Flood Level

Calculations

IP-M-0336

Internal Flooding in the Shutdown Service Water (SX) Pump

Rooms and SX Tunnel with Division II Pump Room Hatch

Cover Off

71111.06

Engineering

Changes

ECN No. 28837

Revise S22-1018 Rev. AC to Show Shutdown Service Water

(SX) Pipe Tunnel Hatch Cover Not Installed and Revise

M22-1001-BC Rev. E To Show SX Pipe Tunnel Hatch

Opening Is Not a Flood Barrier.

11/09/1994

Miscellaneous

Clinton Unit 1

RHR Room

Cooling Coils

1VY05AA and

1VY05AB

Eddy Current Examination Final Report

71111.07A

Work Orders

WOs 5186587

and 5186183

04/30/2024

AR 4776537

Scram Time Testing Data Not Collected Twice

05/26/2024

Corrective Action

Documents

AR 4776539

Rods Difficult to Withdraw during Scram Time Testing

05/26/2024

Miscellaneous

SE-LOR-05

CPS Licensed Operator Training Simulator Exercise Guide:

Loss of AC Power - Degraded Grid

CPS 3005.01

Unit Power Changes

CPS 3304.01

Control Rod Hydraulic and Control (RD)

CPS 3304.02

Rod Control and Information System (RC&IS)

23d

71111.11Q

Procedures

CPS 9813.01

Control Rod Scram Time Testing

43a

AR 4755413

Elevated Vibration on 1CC01PC

03/04/2024

AR 4765941

Follow Up to IR 04755413 1CC01PC Vibration

04/12/2024

AR 4766607

Follow up to IR 04765941 1CC01PC

04/15/2024

AR 4770501

NPSH Concern For CCW

04/29/2024

Corrective Action

Documents

ARs 4773056 and

4775771

06/29/2024

91002875

Evaluation

04/11/2024

CPS-1569

Support Refute Matrix: Component Cooling Pump C High

Vibes - 1CC01PC

04/16/2024

71111.12

Miscellaneous

Engage Health IR

1B21-F022 MSIV Closure Failed to Trip RPS (a)(1)

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

4756831

Determination

MA-AA-716-230-

1002

Vibration Analysis/Acceptance Guideline

Procedures

SM-AA-300-1001

Procurement Engineering Process and Responsibilities

Corrective Action

Documents

AR 4780307

Div 3 DG Work Removed from Schedule Out of Process

06/12/2024

AR 4775119

NRCID: Discrepancy in Work Week Risk Profile

05/19/2024

AR 4780354

NRC ID Door 460 and 281 Do Not Close Without Assistance

06/12/2024

Corrective Action

Documents

Resulting from

Inspection

AR 4780362

NRC ID - Division 2 Battery Styrene Spaces

06/12/2024

Miscellaneous

RICT Record for Tagout 01-SX-1SX062B-001

05/28/2024

ER-AA-600

Risk Management

ER-AA-600-1042

On-line Risk Management

ER-AA-600-1052

Risk Management Support of RICT

ER-AA-600-1053

Calculation of RMAT and RICT for Risk Informed Completion

Time Program

ER-CL-600-2001

Clinton RICT System Guidelines

On-line Work

Control Process

WC-AA-101

OP-AA-108-117

Protected Equipment Program

OP-AA-108-118

Risk Informed Completion Time

71111.13

Procedures

WC-AA-101-1006

On-line Risk Management and Assessment

AR 4764072

BPV #5 No Indication of Fast Acting Solenoid

04/07/2024

AR 4766935

1SXH6AA-2" UT Indicate Pipe Repair/Replacement Needed

04/16/2024

AR 4776938

Air Void Identified at Location RHB-7 Line 1RH117A2

05/28/2024

Corrective Action

Documents

ARs 4776778,

4777913, and

4779811

06/10/2024

EC 371659

GL 2008-01 UT Testing Acceptance Criteria Div2

EC 629718

ASME Code Reconciliation for Revised Allowable Stress

Values

Engineering

Changes

EC 641272

Division I, II, and III SX Pipe Wall Thinning Analysis

71111.15

Miscellaneous

COLR Clinton 1

CL1C22 Core Operating Limits Report

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

TS 3.7.6 Main

Turbine Bypass

System

Clinton Operating License Manual

21-7

Operability

Evaluations

ESOMS

Operations Narrative Log

04/07/2024

CPS 9072.01

Steam Bypass Valve Tests

Procedures

CPS 9820.01

Power Distribution Limits

34b

Work Orders

WO 5507331

NDE - Air Void Monitoring - RHR B Location RHB-7

05/28/2024

EC 641078

Substitute LS #3 with an Optical Isolator for LS #5 for RPS

Input from MSIV 1B21-F022D

Engineering

Changes

EC 641099

Use of LS3 in Place of LS5 as Source of MSIV Closure

Indication Input to RPS for 1B21-F022D

71111.18

Work Orders

WOs 5515768-

07, 5515768-14,

5515768-17, and

5374869-44

Various Work Orders

04/08/2024

AR 4541645

No Indication that 1DG008H Opened

2/15/2022

AR 4668968

1FC02PA Pump Outboard Bearing Oil Discolored

04/10/2023

AR 4766421

Replacement Admin Control Locks Needed for Locked

Valves

04/14/2024

AR 4767029

1FP076 Lock Broken, Currently Unlocked

04/15/2024

AR 4769571

Div 2 DG Kiene Valve Has Evidence of Oil Spray

04/25/2024

AR 4772661

9067.01D001 VG B Dnstrm HEPA Filter DP Not Acquired at

Start

05/07/2024

AR 4774729

RAT SVC Breaker 52-1 SF6 Pressure was Below the Fill

Spec

05/16/2024

AR 4774731

RAT SVC Breaker 52-2 SF6 Pressure was Below the Fill

Spec

05/16/2024

AR 4775823

ERAT MSC TCR Ground/Disconnect Interlock Broken

(0AP106E)

05/22/2024

AR 4776078

Deficiency Identified with ERAT MSC FP

05/23/2024

AR 4780414

Oil Bubbler Discoloration on 1CC01PC Inboard Oil Bubbler

06/13/2024

AR 4781704

Elevated Iron and Copper in Oil Sample for 1CC01PC

06/19/2024

71111.24

Corrective Action

Documents

AR 4782921

CC Check Valve Inspection Request

06/25/2024

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

AR 4767313

1FP076 Degraded Lock/1FP027 Packing Leakage

04/17/2024

AR 4768354

NRC ID: 1FC02PA Pump Outboard Bearing Oil Discolored

04/22/2024

Corrective Action

Documents

Resulting from

Inspection

AR 4774728

NRC ID Minor Oil Leaks during 9080.01

05/16/2024

Engineering

Changes

EC 330661

Scribe Level Band Markings on the EDG Lube Oil Dipsticks

AR 4772647

0VG02CB HS Green and Red Lights Lit While Running

05/07/2024

AR 4772665

0VG03CB HS Green and Red Lights Lit While Running

05/07/2024

CPS 3203.01

Component Cooling Water (CC)

37c

CPS

3402.01P002

Control Room HVAC (VC) Shifting Train B to Train A

0a

CPS

3506.01C002

Diesel Generator 1B Pre-Start Checklist

2e

CPS

3506.01C002

Diesel Generator 1B Pre-Start Checklist

2e

CPS

3506.01C005

Diesel Generator Start Log

1c

CPS

3506.01C005

Diesel Generator Start Log

1c

CPS

3506.01D002

Diesel Generator 1B Operating Logs

CPS 9052.01

LPCS/RHR A Pumps & LPCS/RHR A Waterleg Pump

Operability

50f

CPS 9061.10

Fuel Pool Cooling Valve Operability

48e

CPS 9067.01

Standby Gas Treatment System Train Flow/Heater

Operability

2c

CPS 9071.12

Deluge Spray Nozzle Flow Test

27e

CPS

9071.12C001

Deluge Spray Nozzle Flow Test Checklist

26c

CPS

9071.19C001

Fire Protection Valve Lineup Checklist (Safety Related)

2b

CPS 9080.02

Diesel Generator 1B Operability - Manual and Quick Start

Operability

Procedures

CPS 9080.02

Diesel Generator 1B Operability - Manual and Quick Start

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Operability

CPS

9080.02D001

Diesel Generator 1B Operability - Manual and Quick Start

Data Sheet

43f

CPS 9080.13

Diesel Generator 1A (1B) 24 Hour Run and Hot Restart -

Operability

OP-AA-108-103

Locked Equipment Program

WO 4966827-05

OP 1SX062B PMT

06/04/2024

WO 4966827-12

EM 1SX062B PMT - Thermal O/L Bypass Test

(CPS 9381.01)

06/04/2024

WO 4966827-24

ES 1SX062B: VT2 Maintenance PMT - 9843.02

06/02/2024

WO 5115667-02

1DG158 Replace Internal O-Rings, B Air Start Motor

Shutoff

05/29/2024

WO 5115668-02

1DG157, Replace Internal O-Rings, B Air Start Motor

Shutoff

05/29/2024

WO 5189990-02

OP PMT 0AP03E ERAT Winding Temp Indication and

Cooling Fans

05/22/2024

WO 5192709

Test ERAT Fault Pressure and Associated Relays

05/22/2024

WO 5263672-02

0VC08PA - Change Pump Oil & Lubricate Coupling

05/14/2024

WO 5263824-05

OP PMT Functional Test For 0AP104E (52-2) ERAT SVC

Breaker

05/22/2024

WO 5269067-02

OP 1DG01KB Loop Calibration Ops PMT Verify Proper

Frequency

05/29/2024

WO 5282395

OP 9061.06 CT/DW Isolation Valve Operability -

1SX012B/62B

06/04/2024

WO 5288019-03

0VC03CA Fan/Motor Inspection

05/14/2024

WO 5308133

OP 9080.13 DG 1B 24 HR Run and Hot Restart

04/24/2024

WO 5322589

9071.12E20 OP Deluge Spray Nozzle Flow Test (0VC09SA)

05/14/2024

WO 5322590

9071.12C20 OP Deluge Spray Nozzle Flow Test (0VC07SA)

05/14/2024

WO 5444564

OP Fuel Pool Cooling Pump 1B and 1A Valve IST Testing

04/22/2024

WO 5482445

OP Fuel Pool Cooling Pump 1A and 1B Valve Testing

04/22/2024

WO 5510542

OP 9067.01 SGTS Train B Flow/Heater Operability

05/07/2024

WO 5517225-02

OP 1CC01PC PMT Pump Clinton Power Station

04/12/2024

Work Orders

WO 5517225-15

OP 1CC01PC Uncoupled Run Clinton Power Station

06/05/2024

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

WO 5517225-16

CMO 1CC01PC Perform Vibration Uncoupled Run

06/05/2024

WO 5517225-17

MM - 1CC01PC - Oil Sample, Alignment, Runout Checks

Mag Center

06/04/2024

WO 5524779

OP 9015.01 OP SLC Pump Operability (SLC Pump B)

05/26/2024

WO 5524780

OP 9015.01 SLC Valve Operability

05/26/2024

WO 5536326

9080.02B22 OP 1DG01KB DG 1B Operability Monthly Test -

Div 2

05/30/2024

WO 5536326-02

OP Diesel Generator 1B Prestarts per 9080.02

05/29/2024

WO 5536326-06

OP DG 1B Operability Monthly Test Alternate Means to

Validate Air Start Oil Mist

05/29/2024

N/A

Semi-Annual Clinton Power Siren Report

04/01/2002 -

04/16/2024

N/A

PNS System Maintenance Report

07/28/2022

71114.02

Miscellaneous

N/A

PNS System Maintenance Report

06/21/2023

N/A

Training Records for ERO Staff

Various

Miscellaneous

NOSA-CPS-22-

(AR 4478147)

Emergency Preparedness Audit Report

05/11/2022

EP-AA-1000

Exelon Nuclear Standardized Radiological Emergency Plan

71114.03

Procedures

EP-AA-1003

Exelon Nuclear Radiological Emergency Plan Annex for

Clinton Station

EP-AA-1003,

Addendum 2

Evacuation Time Estimates for Clinton Power Station Plume

Exposure Pathway Emergency Planning Zone

Calculations

KLD TR -1248

Clinton Power Station Development of ETE

06/18/2022

Letters of

Agreement

Clinton Fire Dept., Decatur Memorial Hospital, Dewitt County

EMS & Sheriff, Illinois State University, Monticello School

District 25, Richland Community College, Maroa Fire District,

National Weather Service

Various

71114.05

Miscellaneous

SE-LOR-05

Loss of AC Power - Degraded Grid

71114.06

Miscellaneous

CPS 2024 Off Year Exercise Scenario Guide

04/30/2024

Miscellaneous

LS-AA-2001

Collection and Reporting of NRC ROP Performance

Indicator Data

71151

Procedures

LS-AA-2110

Monthly Data Elements for Emergency Response

Organization (ERO) Drill Participation

2nd Qtr 2022

- 1st Qtr

24

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

LS-AA-2120

Monthly Data Elements for Drill and Exercise Performance

2nd Qtr 2022

- 1st Qtr

24

LS-AA-2130

Monthly Data Elements for NRC Alert and Notification

System (ANS) Reliability

2nd Qtr 2022

- 1st Qtr

24

NEI 99-02

Regulatory Assessment Performance Indicator Guideline

Corrective Action

Documents

ARs 4520270 and

4549014

01/18/2023

71152A

Miscellaneous

Safety Evaluation Related to Partial Site Release Request

for Facility Operating License No. NPF-62 Constellation

Energy Clinton Power Station, Unit No. 1 Docket No. 50-461

06/24/2024