#REDIRECT [[IR 05000354/1985045]]
{{Adams
| number = ML20137B841
| issue date = 11/19/1985
| title = Notice of Violation from Insp on 850924-1027
| author name =
| author affiliation = NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
| addressee name =
| addressee affiliation =
| docket = 05000354
| license number =
| contact person =
| document report number = 50-354-85-45, NUDOCS 8511260365
| package number = ML20137B826
| document type = NOTICE OF VIOLATION OF A REGULATION, TEXT-INSPECTION & AUDIT & I&E CIRCULARS
| page count = 1
}}
 
{{IR-Nav| site = 05000924 | year = 2010 | report number = 027 }}
 
=Text=
{{#Wiki_filter:-
.
.
APPENDIX A NOTICE OF VIOLATION Public Service Electric and Gas Company  Docket No. 50-354
~ Hope Creek Generating Station  License No. CPPR-120 As a result of the inspection conducted on September 24-October 27, 1985, and in accordance with NRC Enforcement Policy (10 CFR 2, Appendix C), the following violation was identified:
10 CFR 50 Appendix B Criterion V, Instructions, Procedures and Drawings, requires that activities affecting quality shall be accomplished in accordance with instructions, procedures, or drawings. Drawing E-1408, Revision 19, August 26, 1985, Wire and Cable Notes and Details, requires cables in cable trays to be tied to the rungs at maximum intervals of 5 feet for vertical tray Contrary to the above, as of September 27, 1985, several safety-related cable trays at floor penetration E-4301-4 had vertical cable spans of six to twelve feet between the penetration seal and the first tie to a cable tray run This is a Severity IV Level Violation (Supplement II).
 
The immediate corrective actions for this item were completed during the inspec-tion and verified by the NRC inspector. Pursuant to the provisions of 10 CFR 2.201, Public Service Electric and Gas Company is hereby required to submit to this ' office within 30 days of the date of the letter which transaitted this Notice, a written statement or explanation in reply, including: (1) corrective steps which will be taken to avoid further violations; and (2) the date when full compliance will be achieved. Where good cause is shown, consideration will be given to extending this response tim gt2%$ p G
OFFICIAL RECORD COPY IR HC 85-45 - 0002. /15/85
}}

Latest revision as of 15:40, 25 September 2020

Notice of Violation from Insp on 850924-1027
ML20137B841
Person / Time
Site: Hope Creek, 05000924 PSEG icon.png
Issue date: 11/19/1985
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML20137B826 List:
References
50-354-85-45, NUDOCS 8511260365
Download: ML20137B841 (1)


Text

-

.

.

APPENDIX A NOTICE OF VIOLATION Public Service Electric and Gas Company Docket No. 50-354

~ Hope Creek Generating Station License No. CPPR-120 As a result of the inspection conducted on September 24-October 27, 1985, and in accordance with NRC Enforcement Policy (10 CFR 2, Appendix C), the following violation was identified:

10 CFR 50 Appendix B Criterion V, Instructions, Procedures and Drawings, requires that activities affecting quality shall be accomplished in accordance with instructions, procedures, or drawings. Drawing E-1408, Revision 19, August 26, 1985, Wire and Cable Notes and Details, requires cables in cable trays to be tied to the rungs at maximum intervals of 5 feet for vertical tray Contrary to the above, as of September 27, 1985, several safety-related cable trays at floor penetration E-4301-4 had vertical cable spans of six to twelve feet between the penetration seal and the first tie to a cable tray run This is a Severity IV Level Violation (Supplement II).

The immediate corrective actions for this item were completed during the inspec-tion and verified by the NRC inspector. Pursuant to the provisions of 10 CFR 2.201, Public Service Electric and Gas Company is hereby required to submit to this ' office within 30 days of the date of the letter which transaitted this Notice, a written statement or explanation in reply, including: (1) corrective steps which will be taken to avoid further violations; and (2) the date when full compliance will be achieved. Where good cause is shown, consideration will be given to extending this response tim gt2%$ p G

OFFICIAL RECORD COPY IR HC 85-45 - 0002. /15/85