|
|
(3 intermediate revisions by the same user not shown) |
Line 2: |
Line 2: |
| | number = ML12292A094 | | | number = ML12292A094 |
| | issue date = 10/17/2012 | | | issue date = 10/17/2012 |
| | title = 10/04/2012 - Summary of Public Meeting to Discuss the Prairie Island Nuclear Generating Plant, Unit 2 Steam Generators Replacement Activities | | | title = Summary of Public Meeting to Discuss the Prairie Island Nuclear Generating Plant, Unit 2 Steam Generators Replacement Activities |
| | author name = Hills D E | | | author name = Hills D |
| | author affiliation = NRC/RGN-III/DRS/EB1 | | | author affiliation = NRC/RGN-III/DRS/EB1 |
| | addressee name = Lynch J | | | addressee name = Lynch J |
Line 13: |
Line 13: |
| | page count = 2 | | | page count = 2 |
| }} | | }} |
| | |
| | =Text= |
| | {{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE ROAD, SUITE 210 LISLE, IL 60532-4352 October 17, 2012 Mr. Jim Lynch Site Vice President Prairie Island Nuclear Generating Plant Northern States Power Company, Minnesota 1717 Wakonade Drive East Welch, MN 55089 |
| | |
| | ==SUBJECT:== |
| | |
| | ==SUMMARY== |
| | OF THE OCTOBER 4, 2012, PUBLIC MEETING TO DISCUSS THE PRAIRIE ISLAND NUCLEAR GENERATING PLANT, UNIT 2 STEAM GENERATORS REPLACEMENT ACTIVITIES |
| | |
| | ==Dear Mr. Lynch:== |
| | |
| | On October 4, 2012, the U. S. Nuclear Regulatory Commission (NRC) held a public meeting at the NRC Region III office located in Lisle, IL. The meeting was between the NRC, and Xcel Energy representatives to discuss the licensees activities pertaining to the replacement of the Prairie Island Nuclear Generating Plant (PINGP), Unit 2 steam generators. |
| | The NRC began the meeting with a discussion of the purpose, agenda, and format of the meeting. The licensee then provided a presentation of their completed, in-progress, and future activities regarding the replacement of PINGPs, Unit 2 steam generators. During their presentation, the licensee also discussed plans for disassembly, removal, and disposition of the existing PINGP, Unit 2 steam generators. In addition, the licensee addressed in detail any applicable operating experience related to San Onofre Nuclear Generating Station (SONGS) steam generators issue for the new replacement steam generators for PINGP, Unit 2. The licensee provided information on the significant design differences between SONGS steam generators and PINGP, Unit 2 replacement steam generators. The NRC staff and management asked the licensee questions throughout the licensees presentation. |
| | |
| | J. Lynch The licensees meeting slides can be found in the Agencywide Documents Access and Management System (ADAMS) at ML12277A176. A list of principal meeting attendees can be found in the Enclosure 1. |
| | At the end of the meeting, members of the public were given the opportunity to ask questions of NRC officials and engage the licensee. |
| | Sincerely, |
| | /RA by A. M. Stone For/ |
| | David E. Hills, Chief Engineering Branch 1 Division of Reactor Safety Docket Nos. 50-306 License Nos. DPR-60 cc w/encl: Distribution via ListServTM |
| | |
| | ==Enclosures:== |
| | As stated |
| | |
| | PUBLIC MEETING PRINCIPAL ATTENDEES October 4, 2012 XCEL Energy K. Fili, Vice President, XCEL Nuclear Projects K. Davison, Director, PINGP Site Operations G. Eckholt, Manager, PINGP Project Licensing S. Marty, Manager, Steam Generator Replacement Project R. Pearson, Engineer, Steam Generator Replacement Project G. Adams, Engineer, Project Licensing Nuclear Regulatory Commission S. Reynolds, Director, Division of Reactor Safety, Region III D. Hills, Chief, Engineering Branch 1, Division of Reactor Safety, Region III A. Shaikh, Reactor Inspector, Division of Reactor Safety, Region III N. Shah, Project Engineer, Division of Reactor Projects, Region III D. Funk, Security Inspector, Division of Reactor Safety, Region III M. Holmberg, Reactor Inspector, Division of Reactor Safety, Region III T. Bilik, Reactor Inspector, Division of Reactor Safety, Region III J. Neurauter, Reactor Inspector, Division of Reactor Safety, Region III E. Sanchez-Santiago, Reactor Inspector, Division of Reactor Safety, Region III P. Chandrathil, Public Affairs Officer, Office of Public Affairs, Region III J. Bozga, Reactor Inspector, Division of Reactor Safety, Region III P. Zurawski, Resident Inspector at PINGP, Division of Reactor Projects, RIII T. Wengert, Project Manager, Division of Operating Reactor Licensing, NRR A. Johnson, Materials Engineer, Division of Engineering, NRR Enclosure 1 |
| | |
| | J. Lynch The licensees meeting slides can be found in the Agencywide Documents Access and Management System (ADAMS) at ML12277A176. A list of principal meeting attendees can be found in the Enclosure 1. |
| | At the end of the meeting, members of the public were given the opportunity to ask questions of NRC officials and engage the licensee. |
| | Sincerely, |
| | /RA by A. M. Stone For David E. Hills, Chief Engineering Branch 1 Division of Reactor Safety Docket No. 50-306; License No. DPR-60 cc w/encl: Distribution via ListServTM |
| | |
| | ==Enclosures:== |
| | As stated DISTRIBUTION: |
| | Cayetano Santos RidsNrrPMPrairieIsland Resource RidsNrrDorlLpl3-1 Resource RidsNrrDirsIrib Resource Chuck Casto Cynthia Pederson Steven Orth Jared Heck Allan Barker Christine Lipa Carole Ariano Linda Linn DRPIII DRSIII Patricia Buckley Tammy Tomczak DOCUMENT NAME: G:\DRSIII\DRS\Work in Progress\Ltr 1017Oct 4 Public Meeting Summary AAS.docx Publicly Available Non-Publicly Available Sensitive Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII RIII NAME A.Shaikh:ls DHills DATE 10/17/12 10/17/12 OFFICIAL RECORD COPY}} |
|
---|
Category:Letter
MONTHYEARML24240A1692024-09-18018 September 2024 Cy 2023 Summary of Decommissioning Trust Fund Status IR 05000305/20240022024-08-22022 August 2024 NRC Inspection Report 05000305/2024002 ML24151A6482024-06-0303 June 2024 Changes in Reactor Decommissioning Branch Project Management Assignments for Some Decommissioning Facilities ML24136A1952024-05-14014 May 2024 2023 Annual Radiological Environmental Operating Report ML24130A0022024-05-0909 May 2024 Summary of Facility Changes, Tests and Experiments and Commitment Changes IR 05000305/20240012024-05-0202 May 2024 NRC Inspection Report No. 05000305/2024001 ML24121A2472024-04-29029 April 2024 and Three Mile Island, Unit 2 - 2023 Occupational Radiation Exposure Annual Report ML24101A0422024-04-22022 April 2024 Solutions Inc. – Exemption from Select Requirements of 10 CFR Part 73 ((Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ML24106A0492024-04-15015 April 2024 2023 Annual Radioactive Effluent Release Report ML24080A0702024-03-20020 March 2024 Decommissioning Trust Fund Annual Report ML24079A0162024-03-19019 March 2024 Annual Property Insurance Status Report ML24073A2312024-03-13013 March 2024 and Three Mile Island Nuclear Station, Unit 2 - Management Change ML24061A0202024-02-15015 February 2024 (Ksp) ISFSI, Submittal of Security Plan, Training and Qualification Plan and Safeguards Contingency Plan, Revision 6 ML23339A1332024-01-26026 January 2024 Exemption from the Req of 10 CFR Part 50.82(a)(8)(i)(A) to Use the Kewaunee Decommissioning Trust Fund for the Management of Site Restoration Activities IR 05000305/20230022023-12-27027 December 2023 NRC Inspection Report 05000305/2023002 (Drss); 07200064/2023001 (Drss) ML23332A1922023-11-28028 November 2023 Solutions, Inc., Request for Exemptions from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23278A1002023-10-0505 October 2023 Response to Request for Additional Information (RAI) Application for Kewaunee Solutions (Ks) Site Restoration Activities ML23222A1522023-08-29029 August 2023 Letter RAI KPS Exemption Site Restoration Final Repaired IR 05000305/20230012023-08-17017 August 2023 NRC Inspection Report No. 05000305/2023001-Kewaunee Power Station ML23171B0822023-07-0505 July 2023 Letter - Kewaunee Power Station - Issuance of Exemption from Certain Requirements from 10 CFR Part 20, Appendix G, Section Iii.E ML23132A0012023-05-11011 May 2023 2022 Annual Radiological Environmental Operating Report ML23116A2182023-04-26026 April 2023 2022 Annual Radioactive Effluent Release Report ML23089A3042023-03-30030 March 2023 Decommissioning Fund Status Report ML23093A0312023-03-29029 March 2023 Solutions, Inc., Request for Exemptions from 10 CFR 50.82(a)(8)(i)(A) and 50.75(h)(1)(iv) for Site Restoration Activities ML23088A2752023-03-29029 March 2023 Solutions, Inc., Request for Exemption from 10 CFR 20, Appendix G, Section Iii.E ML23087A0402023-03-27027 March 2023 Annual Property Insurance Status Report ML23087A0292023-03-27027 March 2023 2022 Annual Report of Occupational Radiation Exposure ML22361A1022023-02-24024 February 2023 Reactor Decommissioning Branch Project Management Changes for Some Decommissioning Facilities and Establishment of Backup Project Manager for All Decommissioning Facilities ML23024A0122023-01-26026 January 2023 Letter to Energysolutions Transmitting Threshold Determination for Merger/Restructuring IR 05000305/20220022023-01-0303 January 2023 NRC Inspection Report Nos. 05000305/2022002(DRSS) Kewaunee Power Station ML22292A2302022-11-25025 November 2022 U.S. Nuclear Regulatory Commissions Analysis of Dominion Energy Kewaunees Decommissioning Funding Status Report for Kewaunee Power Station, Docket No. 50-305 ML22290A0052022-10-13013 October 2022 Resubmittal of Kewaunee Power Station Independent Spent Fuel Storage Installation (ISFSI) Only Emergency Plan (Ioep) and IOEP- Emergency Action Level (EAL) Basis Document, Revision 0KS ML22241A0302022-08-25025 August 2022 (Ksp) ISFSI Submittal of Security Plan, Training and Qualification Plan and Safeguards Contingency Plan, Revision 5 ML24061A0182022-08-25025 August 2022 (Ksp) ISFSI Submittal of Security Pla11, Training and Qualification Plan and Safeguards Contingency Plan Revision 5 IR 05000305/20220012022-08-0101 August 2022 NRC Inspection Report Nos. 05000305/2022001(DNMS) - Kewaunee Power Station ML22215A1512022-07-27027 July 2022 Executed Financial Assurance Instruments for the Kewaunee License Transfer License No. DPR-43 (Docket Nos. 50-305, 72-64) ML22209A1252022-07-26026 July 2022 Amendment No. 11 to Indemnity Agreement No. B-53 for Kewaunee Power Station (KPS) - Signed by Kewaunee Solutions, Inc ML22175A1132022-06-30030 June 2022 Solutions, Inc. - Letter for Review and Acceptance of the Energysolutions, LLC Decommissioning Quality Assurance Program with Enclosure ML22160A5272022-06-28028 June 2022 Enclosure 1 - Amendment No. 221 to Renewed Facility Operating License No. DPR-43 ML22160A5262022-06-28028 June 2022 Letter - KPS - Issuance of Conforming License Amendment Regarding Indirect Transfer of License from DEK, Inc. to Kewaunee Solutions, Inc ML22160A5282022-06-28028 June 2022 Enclosure 2 - Amendment No. 11 to Indemnity Agreement B-53 ML22188A0812022-06-23023 June 2022 ISFSI, Virgil C. Summer Nuclear Station, Unit 1 & ISFSI, North Anna Power Station, Units 1 & 2 & ISFSI, Surry Power Station, Units 1 & 2 & ISFSI - Submission of Revision 32 of the Quality Assurance Topical Report ML22172A2452022-06-22022 June 2022 Notification of Planned Closing Date and Required Regulatory Approvals for the Kewaunee License Transfer Transaction ML22175A0662022-06-17017 June 2022 Designation of Additional Reviewing Official for ISFSI and 10 CFR Part 37 Program Security Background Investigations ML22166A3392022-06-13013 June 2022 Notification of Nuclear Insurance ML22138A2552022-05-10010 May 2022 Submittal of 2021 Annual Radiological Environmental Operating Report ML22158A2112022-05-10010 May 2022 Summary of Facility Changes, Tests and Experiments and Summary of Commitment Changes ML22091A1892022-04-0101 April 2022 Independent Spent Fuel Storage Installation - Annual Radioactive Effluent Release Report ML22108A0352022-04-0101 April 2022 License Transfer to Kewaunee Solutions, Inc ML22089A2432022-03-30030 March 2022 Decommissioning Funding Status Report, Financial Test and Independent Public Accountants' Letter of Attestation 2024-09-18
[Table view] Category:Meeting Summary
MONTHYEARML19289D4842019-10-24024 October 2019 Summary for NEIMA-Kewaunee Meeting on 9/24/2019 ML16190A3452016-07-13013 July 2016 Inc. Pre-Submittal Meeting Regarding Load Drop Analysis for Spent Fuel Cask Handling Operations at Kewaunee Power Station (L53130) ML15223B2832015-08-11011 August 2015 Summary of Public Meeting to Discuss NRC Activities at the Kewaunee Power Station ML13205A0832013-07-24024 July 2013 Summary of Public Meeting to Discuss the 2012 Kewaunee Power Station End-of-Cycle Performance Assessment ML12352A2822012-12-31031 December 2012 Summary of Meeting with Dominion Energy Kewaunee on Implementation of Orders Japan Lessons Learned Effort ML12292A0942012-10-17017 October 2012 Summary of Public Meeting to Discuss the Prairie Island Nuclear Generating Plant, Unit 2 Steam Generators Replacement Activities ML11173A2772011-06-22022 June 2011 Summary of the Public Meeting with Dominion Energy Kewaunee, Inc., to Discuss the Kewaunee Power Station End-Of-Cycle Performance Assessment for 2010 ML1024402012010-09-16016 September 2010 08/31/10 Summary of Telephone Conference Call Between Dominion Energy Kewaunee, Inc. and the U.S. Nuclear Regulatory Commission Concerning a Draft Request for Additional Information Pertaining to the Kewaunee Power Station License Renewal A ML1023901982010-09-16016 September 2010 08/26/10 Summary of Telephone Conference Call Between Dominion Energy Kewaunee, Inc. and NRC Concerning a D-RAI Pertaining to the Kewaunee Power Station License Renewal Application ML1014106432010-06-0909 June 2010 May 20, 2010 Summary of Meeting Regarding the Licensee'S Proposed Response to the Request for Additional Information on Generic Letter 2004-02 ML1012601102010-05-18018 May 2010 Summary of Public Meetings Conducted to Discuss the Draft Supplement Environmental Impact Statement Related to the Review of the Kewaunee Power Station License Renewal Application ML1012600702010-05-0505 May 2010 Summary of Public Meeting to Discuss the 2009 Kewaunee End-Of-Cycle Performance Assessment ML1007107412010-03-31031 March 2010 Summary of Telephone Conference Call Between Dominion Energy Kewaunee, Inc. and the NRC to Discuss Certain RAI Responses on Two Mechanical Systems ML1001104472010-01-13013 January 2010 Summary of Telephone Conference Call with Dominion Energy Kewaunee, Inc., to Discuss Duplicate RAI Number ML0932400382009-11-27027 November 2009 Summary of Conference Call with Dominion Energy Kewaunee, Inc., to Discuss Inaccessible Cables Program ML0932302572009-11-27027 November 2009 Summary of Conference Call with Dominion Energy Kewaunee, Inc., to Discuss Program for Neutron Absorbing Material ML0926008992009-09-28028 September 2009 (KPS) - Summary of 9/15/09 Meeting Regarding the Licensee'S Proposed Response to the Request for Additional Information on Generic Letter 2004-02 ML0921801372009-08-12012 August 2009 Summary Site Audit Related to the Review of the License Renewal Application for Kewaunee Power Station ML0921006122009-08-10010 August 2009 07/28/2009 Summary of Public Meeting Related to the Review of the Kewaunee Power Station License Renewal Application ML0918205652009-07-0808 July 2009 Summary of Conference Calls with Dominion Energy Kewaunee, Inc., to Discuss Response to Follow-Up Question Regarding Severe Accident Mitigation Alternatives Request for Additional Information for Kewaunee Power Station ML0916904292009-06-17017 June 2009 Summary of Public Meeting with NRC and Members of the Kewaunee Power Station Emergency Preparedness Staff to Discuss the June 2009 Kewaunee Emergency Preparedness Exercise ML0913300252009-05-21021 May 2009 Summary of Meeting with Kewaunee to Discuss a Future Amendment to Convert the Plant TS from Custom to Improved TS Format ML0913403292009-05-14014 May 2009 Summary of Meeting Between NRC Region III Management and Dominion Energy Kewaunee, Inc. Representatives to Discuss the 2008 Kewaunee End-of-Cycle Performance Assessment ML0900801102009-02-0505 February 2009 Summary of Meeting Between NRC Staff and Kewaunee to Discuss a Future Amendment to Convert Technical Specifications to the Improved Standard TS Format ML0830904522008-11-17017 November 2008 10/22/08 Summary of Public License Renewal Overview and Environmental Scoping Meeting Related to the Review of the Kewaunee Power Station License Renewal Application ML0815607282008-05-29029 May 2008 Ltr. 05/29/08 Kewaunee Re Non-Public Meeting Summary ML0810202352008-04-11011 April 2008 Summary of Meeting Between NRC Region III Management and Dominion Energy Kewaunee, Inc. Representatives to Discuss the Nrc'S Assessment ML0802304472008-01-25025 January 2008 Summary of Meeting with Dominion Energy Kewaunee Inc. Licensee'S Amendment Request on Seismic Methodology for Analysis of Auxiliary Building Crane ML0729601702007-10-31031 October 2007 Public Meeting Summary on the Reactor Oversight Process ML0729005732007-10-17017 October 2007 Summary of Public Meeting with Dominion Energy Kewaunee to Discuss the Ongoing Substantive Cross-Cutting Issues ML0725306142007-09-21021 September 2007 Public Meeting Summary on the Reactor Oversight Process ML0721900152007-08-0909 August 2007 8/2/07 Public Meeting Summary on the Kewaunee Appeal of a Frequently Asked Question on the Mitigating Systems Performance Index ML0709504642007-04-0505 April 2007 Summary of Public Meeting with Dominion Energy Kewaunee, Inc. Regarding the Kewaunee End-of-Cycle Plant Performance Assessment ML0703304272007-02-26026 February 2007 Summary of January 25, 2007, Meeting with Dominion Energy Kewaunee Inc., on the Licensee'S Amendment Request Regarding the Use of TORMIS Methodology ML0634605062006-12-12012 December 2006 Summary of Public Meeting with Dominion to Discuss Revised Risk Assessment Information and Future Actions for Kewaunee Power Station ML0618405302006-07-0303 July 2006 Public Meeting Summary with Kewaunee to Discuss Improvement Initiatives ML0609005782006-03-30030 March 2006 Public Meeting Summary Kewaunee End-of-Cycle Plant Performance Assessment ML0604000982006-02-24024 February 2006 Summary of Meeting with Dominion Energy Kewaunee, Inc., to Discuss the Applicability of Dominion Safety and Core Design Methods to Kewaunee Power Station ML0532103612005-11-16016 November 2005 Kewaunee Public Meeting Summary, Regulatory Conference for Flooding Issue and Management Meeting ML0527702352005-09-29029 September 2005 Summary of the August 9, 2005, Public Meeting to Discuss the Kewaunee End-of-Cycle Plant Performance Assessment ML0513100572005-05-12012 May 2005 Summary of Meeting with Nuclear Management Company, LLC Regarding the Auxiliary Feedwater Amendment Request Dated May 5, 2005, and the Internal Flooding Design Basis ML0507505452005-03-18018 March 2005 3/18/05, Kewaunee, Summary of Telephone Conference Steam Generator Water Chemistry Excursion (TAC No. M40695) ML0435801802004-12-22022 December 2004 Summary of Public Meeting with Nuclear Management Company, Llc. to Discuss Engineering Initiatives ML0418202382004-05-21021 May 2004 Public Meeting Summary with Nuclear Management Company, LLC Re Kewaunee 2003 End-of-Cycle Assessment ML0333709182003-12-15015 December 2003 Summary of Meeting with Nuclear Management Company, LLC, Regarding Amendment Requests to Use Alternate Source Term Methodology at Prairie Island and Kewaunee ML0323103952003-08-18018 August 2003 Point Beach & Kewaunee Meeting Summary Reactor Vessel Head Replacement Activities ML0323101482003-08-18018 August 2003 Point Beach & Kewaunee Meeting Summary Reactor Vessel Head Replacement Activities ML0312504092003-04-21021 April 2003 Public Meeting Summary with Nuclear Management Co. LLC Kewaunee to Discuss Kewaunee Performance Re EOC ML0222502832002-08-20020 August 2002 Summary of Meeting Between the NRC Staff and Nuclear Management Company, LLC Upcoming Power Uprate and Associated Submittals for Kewaunee ML0214900232002-05-31031 May 2002 Meeting with Nuclear Management Company, LLC, to Discuss Their Response to Interim Compensatory Measure B.2.b of the Security Orders 2019-10-24
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE ROAD, SUITE 210 LISLE, IL 60532-4352 October 17, 2012 Mr. Jim Lynch Site Vice President Prairie Island Nuclear Generating Plant Northern States Power Company, Minnesota 1717 Wakonade Drive East Welch, MN 55089
SUBJECT:
SUMMARY
OF THE OCTOBER 4, 2012, PUBLIC MEETING TO DISCUSS THE PRAIRIE ISLAND NUCLEAR GENERATING PLANT, UNIT 2 STEAM GENERATORS REPLACEMENT ACTIVITIES
Dear Mr. Lynch:
On October 4, 2012, the U. S. Nuclear Regulatory Commission (NRC) held a public meeting at the NRC Region III office located in Lisle, IL. The meeting was between the NRC, and Xcel Energy representatives to discuss the licensees activities pertaining to the replacement of the Prairie Island Nuclear Generating Plant (PINGP), Unit 2 steam generators.
The NRC began the meeting with a discussion of the purpose, agenda, and format of the meeting. The licensee then provided a presentation of their completed, in-progress, and future activities regarding the replacement of PINGPs, Unit 2 steam generators. During their presentation, the licensee also discussed plans for disassembly, removal, and disposition of the existing PINGP, Unit 2 steam generators. In addition, the licensee addressed in detail any applicable operating experience related to San Onofre Nuclear Generating Station (SONGS) steam generators issue for the new replacement steam generators for PINGP, Unit 2. The licensee provided information on the significant design differences between SONGS steam generators and PINGP, Unit 2 replacement steam generators. The NRC staff and management asked the licensee questions throughout the licensees presentation.
J. Lynch The licensees meeting slides can be found in the Agencywide Documents Access and Management System (ADAMS) at ML12277A176. A list of principal meeting attendees can be found in the Enclosure 1.
At the end of the meeting, members of the public were given the opportunity to ask questions of NRC officials and engage the licensee.
Sincerely,
/RA by A. M. Stone For/
David E. Hills, Chief Engineering Branch 1 Division of Reactor Safety Docket Nos. 50-306 License Nos. DPR-60 cc w/encl: Distribution via ListServTM
Enclosures:
As stated
PUBLIC MEETING PRINCIPAL ATTENDEES October 4, 2012 XCEL Energy K. Fili, Vice President, XCEL Nuclear Projects K. Davison, Director, PINGP Site Operations G. Eckholt, Manager, PINGP Project Licensing S. Marty, Manager, Steam Generator Replacement Project R. Pearson, Engineer, Steam Generator Replacement Project G. Adams, Engineer, Project Licensing Nuclear Regulatory Commission S. Reynolds, Director, Division of Reactor Safety, Region III D. Hills, Chief, Engineering Branch 1, Division of Reactor Safety, Region III A. Shaikh, Reactor Inspector, Division of Reactor Safety, Region III N. Shah, Project Engineer, Division of Reactor Projects, Region III D. Funk, Security Inspector, Division of Reactor Safety, Region III M. Holmberg, Reactor Inspector, Division of Reactor Safety, Region III T. Bilik, Reactor Inspector, Division of Reactor Safety, Region III J. Neurauter, Reactor Inspector, Division of Reactor Safety, Region III E. Sanchez-Santiago, Reactor Inspector, Division of Reactor Safety, Region III P. Chandrathil, Public Affairs Officer, Office of Public Affairs, Region III J. Bozga, Reactor Inspector, Division of Reactor Safety, Region III P. Zurawski, Resident Inspector at PINGP, Division of Reactor Projects, RIII T. Wengert, Project Manager, Division of Operating Reactor Licensing, NRR A. Johnson, Materials Engineer, Division of Engineering, NRR Enclosure 1
J. Lynch The licensees meeting slides can be found in the Agencywide Documents Access and Management System (ADAMS) at ML12277A176. A list of principal meeting attendees can be found in the Enclosure 1.
At the end of the meeting, members of the public were given the opportunity to ask questions of NRC officials and engage the licensee.
Sincerely,
/RA by A. M. Stone For David E. Hills, Chief Engineering Branch 1 Division of Reactor Safety Docket No. 50-306; License No. DPR-60 cc w/encl: Distribution via ListServTM
Enclosures:
As stated DISTRIBUTION:
Cayetano Santos RidsNrrPMPrairieIsland Resource RidsNrrDorlLpl3-1 Resource RidsNrrDirsIrib Resource Chuck Casto Cynthia Pederson Steven Orth Jared Heck Allan Barker Christine Lipa Carole Ariano Linda Linn DRPIII DRSIII Patricia Buckley Tammy Tomczak DOCUMENT NAME: G:\DRSIII\DRS\Work in Progress\Ltr 1017Oct 4 Public Meeting Summary AAS.docx Publicly Available Non-Publicly Available Sensitive Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII RIII NAME A.Shaikh:ls DHills DATE 10/17/12 10/17/12 OFFICIAL RECORD COPY