MONTHYEARML0823100182008-08-12012 August 2008 Application for Renewed Operating License, Withheld Reference Drawing Project stage: Request ML0826102942008-09-25025 September 2008 Federal Register Notice Regarding Renewal of Facility Operating License No. DPR-42 for an Additional 20-Year Period Project stage: Request ML0833702312008-12-0303 December 2008 Project Manager Change for the License Renewal Review for Kewaunee Power Station Project stage: Other ML0833702452008-12-0909 December 2008 Revision of Schedule for the Conduct of Review of the Kewaunee Power Station License Renewal Application Project stage: Approval ML0905300032009-03-23023 March 2009 Request to Supplement the Kewaunee Power Station License Renewal Application in Regards to the Use of the Work Control Process as an Aging Management Program Project stage: Other ML0907607862009-04-0303 April 2009 License Renewal Application Review, Request for Additional Information - Balance of Plant Scoping and Screening Project stage: RAI ML0908609462009-04-15015 April 2009 Revision of Schedule for the Conduct of Review of the Kewaunee Power Station License Renewal Application Project stage: Approval ML0911201992009-04-30030 April 2009 RAI, Review of the License Renewal Application - Scoping & Screening Methodology Project stage: RAI ML0914703822009-05-28028 May 2009 Plan for the Aging Management Program Regulatory Audit Regarding the Kewaunee Power Station License Renewal Application Review Project stage: Other ML0911903892009-07-0707 July 2009 Request for Additional Information Regarding the Review of the Kewaunee Power Station License Renewal Application - Leak-Before-Break Project stage: RAI ML0918109582009-07-13013 July 2009 Request for Additional Information for the Review of the Kewaunee Power Station License Renewal Application - Aging Management Programs Project stage: RAI ML0919000812009-07-13013 July 2009 Scoping and Screening Audit Report Regarding the Kewaunee Power Station, License Renewal Application Project stage: Other ML0918805552009-07-16016 July 2009 Request for Additional Information Regarding the Review of the Kewaunee Power Station License Renewal Application - Structures Scoping/Fire Protection Project stage: RAI ML0921006032009-07-28028 July 2009 LRA Review - Slides Public Meeting July 28, 2009 Project stage: Request ML0921907572009-08-0606 August 2009 Response to Request for Additional Information for the Review of the License Renewal Application-Structures Scoping/Fire Protection Project stage: Response to RAI ML0922306182009-08-0606 August 2009 Response to Request for Additional Information for the Review of the License Renewal Application - Leak Before Break/Boral Project stage: Response to RAI ML0921006122009-08-10010 August 2009 Summary of Public Meeting Related to the Review of the Kewaunee Power Station License Renewal Application Project stage: Meeting ML0919004492009-08-12012 August 2009 AMP Audit Report Regarding the Kewaunee Power Station, License Renewal Application Project stage: Other ML0923200932009-08-17017 August 2009 Response to Request for Additional Information for Review of License Renewal Application - Aging Management Programs Project stage: Response to RAI ML0921205462009-08-28028 August 2009 Request for Additional Information for the Review of the Kewaunee Power Station License Renewal Application - Aging Management Review Results Project stage: RAI ML0927100452009-09-25025 September 2009 Supplemental Information for the Review of the License Renewal Application - Changes to the Work Control Process Aging Management Program Project stage: Supplement ML0927905852009-10-13013 October 2009 Revision of Schedule for the Conduct of Review of the Kewaunee Power Station License Renewal Application Project stage: Approval ML0923900632009-10-13013 October 2009 Request for Additional Information Regarding the Review of the Kewaunee Power Station License Renewal Application - Aging Management Review Results Project stage: RAI ML0927905822009-10-14014 October 2009 Plan for the Aging Management Program Regulatory Audit Regarding the Kewaunee Power Station License Renewal Application Review Project stage: Other ML0928004412009-10-16016 October 2009 Summary of Conference Call with Dominion Energy Kewaunee Inc., to Discuss the ASME Section XI Inservice Inspection Aging Management Program Project stage: Other ML0918908362009-11-20020 November 2009 Request for Additional Information Regarding the Review of the Kewaunee Power Station License Renewal Application Project stage: RAI ML0932400382009-11-27027 November 2009 Summary of Conference Call with Dominion Energy Kewaunee, Inc., to Discuss Inaccessible Cables Program Project stage: Other ML0932302572009-11-27027 November 2009 Summary of Conference Call with Dominion Energy Kewaunee, Inc., to Discuss Program for Neutron Absorbing Material Project stage: Other ML0932600032009-12-14014 December 2009 Wcp AMP Audit Report Regarding the Kewaunee Power Station License Renewal Application Project stage: Other ML0933104432009-12-16016 December 2009 Request for Additional Information Regarding the Review of the Kewaunee Power Station License Renewal Application - AMRs Project stage: RAI ML0934313392009-12-16016 December 2009 Summary of Telephone Conference Call on December 9, 2009, Between Dominion Energy Kewaunee Inc., and U.S. NRC to Discuss Tables Referenced in the Work Control Process Amendment Letter Project stage: Other ML0933103602009-12-17017 December 2009 Safety Project Manager Change for the License Renewal Review for the Kewaunee Power Station Project stage: Other ML1001100612009-12-28028 December 2009 Response to Request for Additional Information for the Review of the License Renewal Application Project stage: Response to RAI ML0935003062010-01-0404 January 2010 Request for Additional Information Regarding the Review of the Kewaunee Power Station License Renewal Application - AMRs Project stage: RAI ML1001104472010-01-13013 January 2010 Summary of Telephone Conference Call with Dominion Energy Kewaunee, Inc., to Discuss Duplicate RAI Number Project stage: RAI ML1002200662010-01-21021 January 2010 Response to Request for Additional Information for the Review of the License Renewal Application - Aging Management Review/Aging Management Program Project stage: Response to RAI ML1003318792010-02-0202 February 2010 Response to Request for Additional Information for the Review of the Kewaunee Power Station License Renewal Application Aging Management Review/Aging Management Program Project stage: Response to RAI ML1003210772010-02-16016 February 2010 Summary of Telephone Conference Call Between Dominion Energy Kewaunee, Inc. and USNRC to Discuss Certain Request for Additional Information on Structural Items Project stage: RAI ML1006903992010-03-11011 March 2010 Request for Additional Information for the Review of the Kewaunee Power Station, License Renewal Application Project stage: RAI ML1007107412010-03-31031 March 2010 Summary of Telephone Conference Call Between Dominion Energy Kewaunee, Inc. and the NRC to Discuss Certain RAI Responses on Two Mechanical Systems Project stage: RAI ML1009503792010-04-14014 April 2010 Request for Additional Information for the Review of the Kewaunee Power Station License Renewal Application Project stage: RAI ML1012504442010-05-10010 May 2010 Revision of Schedule for the Conduct of the Review of the Kewaunee Power Station License Renewal Application TAC MD9408) Project stage: Approval ML1014103222010-05-27027 May 2010 Request for Additional Information for the Review of the Kewaunee Power Station License Renewal Application Project stage: RAI ML1016102332010-06-0101 June 2010 Completion of License Renewal Commitment 41 Re Fatigue Analysis of Surge Line Hot Leg Nozzle. Report No. 0900090.401 Enclosed Project stage: Other ML1016003242010-06-16016 June 2010 Letter Change in Schedule for Review of the Kewaunee Power Station License Renewal Application Safety Evaluation Project stage: Approval ML1011903452010-07-15015 July 2010 Transmittal of Kewaunee Safety Evaluation Report with Open Items Related to License Renewal of Kewaunee Power Station Project stage: Approval ML1021601272010-08-0404 August 2010 Record of Conference Call - Discuss Dominion Kewaunees Response to Recent Steam Generator Divider Plate RAI Project stage: Other ML1025003572010-09-10010 September 2010 Request for Additional Information for the Review of the Kewaunee Power Station License Renewal Application Project stage: RAI ML1023901982010-09-16016 September 2010 Summary of Telephone Conference Call Between Dominion Energy Kewaunee, Inc. and NRC Concerning a D-RAI Pertaining to the Kewaunee Power Station License Renewal Application Project stage: RAI ML1024402012010-09-16016 September 2010 Summary of Telephone Conference Call Between Dominion Energy Kewaunee, Inc. and the U.S. Nuclear Regulatory Commission Concerning a Draft Request for Additional Information Pertaining to the Kewaunee Power Station License Renewal Applicatio Project stage: Draft RAI 2009-07-07
[Table View] |
Text
November 27, 2009 LICENSEE:
Dominion Energy Kewaunee, Inc.
FACILITY:
Kewaunee Power Station
SUBJECT:
SUMMARY
OF TELEPHONE CONFERENCE CALL BETWEEN DOMINION ENERGY KEWAUNEE, INC. AND U.S. NUCLEAR REGULATORY COMMISSION TO DISCUSS THE (XI.E3) ELECTRICAL AGING MANAGEMENT PROGRAM (TAC NO. MD9408)
On November 19, 2009, the U.S. Nuclear Regulatory Commission (NRC or the staff) conducted a conference call (teleconference) with representatives from Dominion Energy Kewaunee, Inc.
(DEK). The purpose of the teleconference was to discuss DEK responses to the staffs requests for additional information (RAIs) regarding the Kewaunee Power Station (KPS) Non-EQ Inaccessible Medium-Voltage Cables Program.
In a letter dated July 13, 2009 (Agencywide Documents and Access Management System
[ADAMS] Accession Number ML091810958), the staff submitted its RAIs related to KPS aging management programs. In the RAI letter, the staff had a request that was related to the Non-EQ Inaccessible Medium-Voltage Cables Program (XI.E3) (RAI B2.1.21-1). DEK responded to the staffs RAI in a letter dated August 17, 2009 (ADAMS Accession Number ML092320093). During the teleconference the staff indicated that the response to RAI B2.1.21-1 did not provide enough information for the staff to make its evaluation. The main issue discussed during the teleconference is summarized below.
Need to provide additional updates to LRA Section B2.1.21 and USAR Appendix A, Section A2.1.21 for the Non-EQ Inaccessible Medium-Voltage Cables Program The applicants RAI response did not update license renewal application (LRA) Section B2.1.21 and associated Updated Safety Analysis Report (USAR) supplement to specify that inspection for water collection is performed based on actual plant experience with water accumulation in the in-scope manhole of the tertiary auxiliary transformer consistent with Generic Aging Lessons Learned Aging Management Program XI.E3 and Standard Review Plan for License Renewal of Nuclear Power Plants Table 3.6.2.
Dominion Energy Kewanee, Inc.
As a result of the discussions, DEK indicated that they will supplement their response to RAI B2.1.21-1 to provide additional information to the staff regarding the update of LRA Section B2.1.21 and USAR Appendix A, Section A2.1.21 of the KPS LRA. A list of teleconference participants is enclosed.
/RA/
Samuel Hernandez, Project Manager Projects Branch 1 Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-305
Enclosure:
As stated cc w/ encl: See next page
ML093240038 OFFICE LA:DLR PM:DLR:RPB1 BC:DLR:RPB1 PM:DLR:RPB1 NAME SFigueroa SHernandez BPham (JDozier for)
SHernandez DATE 11/23/09 11/25/09 11/27/09 11/27/09
ENCLOSURE LIST OF PARTICIPANTS TELEPHONE CONFERENCE CALL DOMINION ENERGY KEWAUNEE, INC.
KEWAUNEE POWER STATION November 19, 2009 PARTICIPANTS AFFILIATION Samuel Hernandez U.S. Nuclear Regulatory Commission (NRC)
Clifford Doutt NRC Duc Nguyen NRC Paul Aitken Dominion Energy Kewaunee, Inc. (Dominion)
Charlie Sorrell Dominion Paul Thomas Dominion Mark Hotchkiss Dominion
Kewaunee Power Station cc:
ENCLOSURE Resident Inspectors Office U.S. Nuclear Regulatory Commission N490 Hwy 42 Kewaunee, WI 54216-9510 Mr. Chris L. Funderburk Director, Nuclear Licensing and Operations Support Dominion Resources Services, Inc.
Innsbrook Technical Center - 2SE 5000 Dominion Boulevard Glen Allen, VA 23060-6711 Mr. Thomas L. Breene Dominion Energy Kewaunee, Inc.
Kewaunee Power Station N490 Highway 42 Kewaunee, WI 54216 Mr. Michael J. Wilson, Director Nuclear Safety & Licensing Dominion Energy Kewaunee, Inc.
Kewaunee Power Station N490 Highway 42 Kewaunee, WI 54216 Mr. William R. Matthews Senior Vice President - Nuclear Operations Innsbrook Technical Center - 2SE 5000 Dominion Boulevard Glen Allen, VA 23060-6711 Mr. Alan J. Price Vice President - Nuclear Engineering Innsbrook Technical Center - 2SE 5000 Dominion Boulevard Glen Allen, VA 23060-6711 Mr. William D. Corbin Director - Nuclear Engineering Innsbrook Technical Center - 3NE 5000 Dominion Boulevard Glen Allen, VA 23060-6711 Mr. Paul C. Aitken Supervisor - License Renewal Project Innsbrook Technical Center - 3NE 5000 Dominion Boulevard Glen Allen, VA 23060-6711 Mr. David A. Sommers Supervisor - Nuclear Engineering Innsbrook Technical Center - 2SE 5000 Dominion Boulevard Glen Allen, VA 23060-6711 Ms. Lillian M. Cuoco, Esq.
Senior Counsel Dominion Resources Services, Inc.
120 Tredegar Street Riverside 2 Richmond, VA 23219 Mr. Stephen E. Scace Site Vice President Dominion Energy Kewaunee, Inc.
Kewaunee Power Station N490 Highway 42 Kewaunee, WI 54216 Mr. David R. Lewis Pillsbury Winthrop Shaw Pittman, LLP 2300 N Street, N.W.
Washington, DC 20037-1122 Mr. Ken Paplham E 4095 Sandy Bay Rd.
Kewaunee, WI 54216 Mr. Jeff Kitsembel, P.E.
Public Service Commission of Wisconsin P.O. Box 7854 Madison, WI 53707-7854
Kewaunee Power Station cc:
Mr. David A. Heacock President and Chief Nuclear Officer Dominion Energy Kewaunee, Inc.
Innsbrook Technical Center - 2SW 5000 Dominion Boulevard Glen Allen, VA 23060-6711