(KPS) - Summary of 9/15/09 Meeting Regarding the Licensee'S Proposed Response to the Request for Additional Information on Generic Letter 2004-02
ML092600899
Person / Time
Site: Kewaunee Dominion icon.png
Issue date: 09/28/2009
From: Tam P
Plant Licensing Branch III
To:
Dominion Energy Kewaunee
tam P, NRR/DORL, 415-1451
Shared Package
ML092600030 List:
References
GL-04-002, TAC MC4691
Download: ML092600899 (3)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 September 28, 2009 LICENSEE: Dominion Energy Kewaunee, Inc.

FACILITY: Kewaunee Power Station (KPS)

SUB..IECT:

SUMMARY

OF SEPTEMBER 15, 2009, MEETING REGARDING THE LICENSEE'S PROPOSED RESPONSE TO THE REQUEST FOR ADDITIONAL INFORMATION ON GENERIC LETTER 2004-02 (TAC NO. MC4691)

On September 15, 2009, the Nuclear Regulatory Commission (NRC) staff held a Category 1 public meeting by telephone with Dominion Energy Kewaunee, Inc. (the licensee). The purpose of the meeting was to discuss the licensee's proposed response to a Request for Additional Information (RAI) dated August 14, 2009 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML092040006) regarding Generic Letter 2004-02, "Potential Impact of Debris Blockage on Emergency Recirculation during Design-Basis Accidents at Pressurized-Water Reactors." Attendees of the meeting are listed in Enclosure 1.

As outlined in its handout slides (Enclosure 2, ADAMS Accession No. ML092600018; , ADAMS Accession No. ML092600376; and Enclosure 4, ADAMS Accession No. ML092600643), licensee personnel, supported by the licensee's contractors, presented an overview of the KPS sump design and an outline of the proposed RAI response for each question.

The NRC personnel stated that additional discussion or information would be needed for a few of the RAI questions. The NRC personnel also stated that they would need to further evaluate some of the questions in light of the discussion. The following RAI questions need further discussion as indicated:

RAlltem Discussion 2 Thermobestos Zone of (break) Influence of 5.45D; acceptability of stainless steel banded aluminum jacket vs. stainless steel riveted stainless jacket (used at KPS).

5,6,7, and 12 The NRC staff plans on combining these questions regarding the debris generation, transport, and erosion of TempMat, fiberglass and Thermobestos debris. The NRC staff will reframe these questions based on an improved understanding of the material used at KPS.

8 KPS personnel contend that the KPS containment is very clean, resulting in a much lower latent debris quantity than other pressurized-water reactors. The NRC staff requested that the licensee provide information on sampling and results. The NRC staff also requested that the licensee justify the assumption of 100 pound mass latent debris.

-2 15 The NRC staff requested to review computational fluid dynamics velocity plots prior to submission of the RAI response to verify that the parameters being provided are the specific parameters needed by the reviewers.

16 The NRC staff requested additional information/basis for addition of debris in test flume from a single drop zone vs. containment transport zones.

17 NRC personnel stated that they will review this question and provide feedback to the licensee regarding information to be provided in the response (if any).

19.c.ii The NRC staff requested additional discussion regarding test protocol to introduce 25 percent of latent fiber prior to flume pump start.

40 The NRC staff requested additional discussion of refueling cavity drain blockage potential and impact in consideration of screen on drain standpipe.

A subsequent telephone conference will be scheduled to complete the discussion of the licensee's proposed response.

No comment was received via the Public Meeting Feedback form.

Please direct any inquiries to me at 301-415-1451.  ?

<?fl~

Pet~r S. Tam, Senior Project Manager Plant Licensing Branch 111-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-305

Enclosures:

1. List of Attendees 2-4. Licensee Handout cc w/encl: Distribution via ListServ

NRC and Dominion Energy Kewaunee, Inc. (DEK)

Meeting of September 15, 2009 List of Attendees (in alphabetical order)

Organization S. Bailey NRC/NRRISafety Issue Resolution Branch J. Bleigh Performance Contracting, Inc. (DEK's contractor)

T. Breene DEK S. Cain Alden Research Laboratories, Inc. (DEK's contractor)

L. Christensen DEK J. Dillich DEK J. Gadzala DEK D. Guzonas Atomic Energy of Canada Limited (DEK's contractor)

C.Hott NRC/NRRISafety Issue Resolution Branch J. Kitsembel Wisconsin State Public Service Commission P. Klein NRC/NRRISG Tube Integrity and Chemical Engineering Branch C. Kudla Performance Contracting, Inc. (DEK's contractor)

J. Lehning NRC/NRRISafety Issue Resolution Branch T. Olson DEK S. Putman DEK D. Rhodes Atomic Energy of Canada Limited (DEK's contractor)

C. Sly DEK D. Sommers DEK S. Smith NRC/NRRISafety Issue Resolution Branch P.Tam NRC/NRR/Plant Licensing Branch 111-1 R. Torres NRC/NRRISafety Issue Resolution Branch

Package - ML092600030 Summary - ML092600899 Enclosures 2,3, and 4 - ML092600018, ML092600376, and ML092600643 Mee rmq NorIce- ML092380171 OFFICE NRRlLPL3-1/PM NRRlLPL3-1/LA NRRlDSS/SSIB/BC(A) NRRlLPL3-1/BC(A)

NAME PTam THarris SBailev PTam DATE 9/22/09 9/22/09 9/24/09 9/28/09