May 9, 2024 KS-2024-012 10 CFR 50.59 10 CFR 72.48 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Kewaunee Power Station Facility Operating License No. DPR-43 NRC Docket No. 50-305 and 72-64
Subject:
Summary of Facility Changes, Tests and Experiments and Commitment Changes
Reference:
- 1. Letter from Bradly J. McMahon (Dominion Energy Kewaunee, Inc.) to Document Control Desk (NRC), Summary of Facility Changes, Tests and Experiments and Summary of Commitment Changes, dated May 10, 2022 - (ML22158A211)
Pursuant to 10 CFR 50.59(d)(2) and 10 CFR 72.48(d)(2), a report containing a brief description of any changes, tests, and experiments, including a summary of the evaluation of each, must be submitted to the NRC at intervals not to exceed 24 months.
There were no 10 CFR 50.59(d)(2) and 10 CFR 72.48(d)(2) Evaluations completed for the Kewaunee Power Station (KPS) since the prior submittal dated May 10, 2022 (Reference 1).
No commitment changes occurred during the last 24 months.
If you have any questions or require additional information, please contact me at 508-728-1421.
Sincerely, Joseph R. Lynch Regulatory Affairs Director Kewaunee Solutions, Inc.
Commitments made in this letter: None For Thomas P. Schneider Digitally signed by Thomas P.
Schneider Date: 2024.05.09 05:09:12 -05'00'
Kewaunee Solutions KS-2024-012 Page 2 of 2 Kewaunee Power Station, N490 Highway 42, Kewaunee, WI 54216 cc:
Regional Administrator, Region III Mr. Karl Sturzebecher, Project Manager U.S. Nuclear Regulatory Commission