KEWAUNEE SOLUTIONS August 25, 2022 KS-2022-008 Attn: Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 10 CFR 50.54(p)(2)
Subject:
Kewaunee Power Station (KSP) ISFSI Submittal of Security Plan, Training and Qualification Plan and Safeguards Contingency Plan, Revision 5.
Kewaunee Power Station NRC License No. DPR-43 NRC Docket Nos. 50-305 & 72-64 In accordance with the provisions of 10 CPR 50.54, "Conditions of licenses," paragraph (p)(2),
Kewaunee Solutions (KS) is submitting changes to the Kewaunee Power Station Security Plan, Training and Qualification Plan, and Safeguards Contingency Plan, Revision 5 (the Plan) as the enclosure to this letter. The Revision Summary of the Plan provided in the enclosure describes each change. Changes to this document were implemented on June 28, 2022. In accordance with 10 CFR 50.54(p)(2) KS is submitting these changes within two months of implementation.
On May 10, 2021, EnergySolutions, LLC (ES) and Dominion Energy Kewaunee, Inc. (DEK)
(collectively, the Applicants) submitted a license transfer application (LTA) for the Kewaunee Power Station (KPS) (Accession No. ML21131A141). The U.S. Nuclear Regulatory Commission (NRC) approved the transfer of License No. DPR-43 for the KPS by order dated March 31, 2022 (the Order, Accession No. ML22014A392). The closing of the transfer occurred on June 28, 2022. The Kewaunee Power Station Security Plan, Training and Qualification Plan, and Safeguards Contingency Plan was revised at that time to reflect the change in KPS ownership and operation including the new KS organization and security management positions.
KS has concluded that the changes do not decrease the safeguards effectiveness of the Plan.
Unauthorized Disclosure of Safeguards Information Will Be Subject to Civil and Criminal Sanctions j
, l Classified By:
Name: Eileen M Moore
Title:
Security Manager Organization: Kewaunee Solutions Effective Date: 4/13/2022 ENCLOSURE CONTAINS SAFEGUARDS INFORMATION UPON SEPARATION THIS PAGE IS DECONTROLLED Kewaunee Power Station, N490, State Highway 42, Kewaunee, WI 54216 Safeguards Information Sool
- JtJ)SSZ/p
- vre tt IJ/v/ 55
Kewaunee Solutions KS-2022-008 Page 2 of 3 Safeguards Information The enclosure contains Safeguards Information. It is therefore requesteq that this information be withheld from public disclosure in accordance with 10 CFR 2.390, "Public inspections, exemptions, requests for withholding," paragraph (d)(l), and 10 CFR 73.22, "Protection of Safeguards Information: Specific Requirements," paragraph (a)(4). This cover letter when detached from Enclosure 1 does not contain safeguards information.
If there are questions regarding this matter, please contact me at (508) 728-1421.
Respectfully, h
. Digitally signed by Joseph R.
Josep R. Lynch Lynch Date: 2022.08.25 12:41 :41 -04'00' Joseph K Lynch Kewaunee Solutions (KS)
Licensing Manager jrlynch@energysolutions.com
Enclosures:
- 1. Kewaunee Power Station Security Plan, Training and Qualification Plan, and Safeguards Contingency Plan, Revision 5, (Safeguards Information)
ENCLOSURE CONTAINS SAFEGUARDS INFORMATION UPON SEPARATION THIS PAGE IS DECONTROLLED Safeguards Information
Kewaunee Solutions KS-2022-008 Page 3 of3 cc: w/Enclosure Safeguards* Information
. NRC Region III Administrator U.S. Nuclear Regulatory Commission 2443 Warrenville Road, Suite 210 Lisle, Illinois 60532-4352 cc: w/o Enclosure Director, Division of Spent Fuel Management Office of Nuclear Material Safety arid Safeguards -
U. S. Nuclear Regulatory Commission One White Flint North 11555 Rockville Pike Rockville, MD 20852-2738 Mr. Karl Sturzebecher NRC Project Manager-Kewaunee Power Station U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Mr. Jeff Kitsembel Division of Energy Regulation & Analysis Public Service Commission of Wisconsin P.O. Box 7854 Madison, WI 53707-7854 ENCLOSURE CONTAINS SAFEGUARDS INFORMATION UPON SEPARATION THIS PAGE IS DECONTROLLED Safeguards Information
Safeguards Information (92 Pages)
Kewaunee Power Station Training and Qualification Plan, and Safeguards Contingency Plan, Revision 5, (Safeguards Information)
Unauthorized Disciosure of Safeguards Information Will Be Subject to Civil and Criminal Sanctions Classified By:
Name: Eileen M Moore
Title:
Security Manager Organization: Kewaunee Solutions Effective Date: 4/13/2022 ENCLOSURE CONTAINS SAFEGUARDS INFORMATION UPON SEPARATION THIS PAGE IS DECONTROLLED