IR 05000382/2017006: Difference between revisions
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
||
(3 intermediate revisions by the same user not shown) | |||
Line 3: | Line 3: | ||
| issue date = 03/01/2018 | | issue date = 03/01/2018 | ||
| title = Annual Assessment Letter for Waterford Steam Electric Station Unit 3, (Report 05000382/2017006) | | title = Annual Assessment Letter for Waterford Steam Electric Station Unit 3, (Report 05000382/2017006) | ||
| author name = Miller G | | author name = Miller G | ||
| author affiliation = NRC/RGN-IV/DRP/RPB-D | | author affiliation = NRC/RGN-IV/DRP/RPB-D | ||
| addressee name = Dinelli J | | addressee name = Dinelli J | ||
Line 9: | Line 9: | ||
| docket = 05000382 | | docket = 05000382 | ||
| license number = NPF-038 | | license number = NPF-038 | ||
| contact person = Miller G | | contact person = Miller G | ||
| document report number = IR 2017006 | | document report number = IR 2017006 | ||
| document type = Inspection Plan, Letter | | document type = Inspection Plan, Letter | ||
Line 18: | Line 18: | ||
=Text= | =Text= | ||
{{#Wiki_filter: | {{#Wiki_filter:rch 1, 2018 | ||
==SUBJECT:== | |||
ANNUAL ASSESSMENT LETTER FOR WATERFORD STEAM ELECTRIC STATION UNIT 3 (REPORT 05000382/2017006) | |||
==Dear Mr. Dinelli:== | |||
The U.S. Nuclear Regulatory Commission (NRC) has completed its end-of-cycle performance assessment of Waterford Steam Electric Station Unit 3, reviewing performance indicators (PIs), | |||
inspection results, and enforcement actions from January 1, 2017 through December 31, 2017. | |||
This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility. The NRC concluded that overall performance at your facility preserved public health and safety. | |||
The NRC determined the performance at Waterford Steam Electric Station Unit 3 during the most recent quarter was within the Licensee Response Column, the highest performance category of the NRCs Reactor Oversight Process (ROP) Action Matrix, because all inspection findings had very low safety significance (i.e., Green), and all PIs were within the expected range (i.e., Green). Therefore, the NRC plans to conduct ROP baseline inspections at your facility. | |||
The | |||
, | |||
, inspection | |||
, and | |||
The NRC | The enclosed inspection plan lists the inspections scheduled through December 31, 2019. This updated inspection plan now includes planned security inspections which were formerly transmitted under separate correspondence. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last twelve months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. | ||
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of the NRCs document system, Agencywide Documents Access and Management System (ADAMS). | |||
ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). | |||
-rm/adams.html (the Public Electronic Reading Room). | |||
Please contact me at (817) 200-1173 with any questions you have regarding this letter. | Please contact me at (817) 200-1173 with any questions you have regarding this letter. | ||
Sincerely, | Sincerely, | ||
/RA/ Geoffrey B. Miller, Branch Chief Projects Branch D Division of Reactor Projects Docket: 50 | /RA/ | ||
-382 License: NPF | Geoffrey B. Miller, Branch Chief Projects Branch D Division of Reactor Projects Docket: 50-382 License: NPF-38 Enclosure: | ||
-38 Enclosure: | |||
Waterford Steam Electric Station Unit 3 Inspection Plan | Waterford Steam Electric Station Unit 3 Inspection Plan | ||
Waterford 01/01/2018 - 12/31/2019 Unit Start End Activity CAC Title Staff Count MAT'L CONTROL & ACCOUNTING 1 3 01/22/2018 01/26/2018 IP 71130.11 000742 Material Control and Accounting (MC&A) | IP 22 Inspection Activity Plan Report Waterford 01/01/2018 - 12/31/2019 Unit Start End Activity CAC Title Staff Count MAT'L CONTROL & ACCOUNTING 1 3 01/22/2018 01/26/2018 IP 71130.11 000742 Material Control and Accounting (MC&A) | ||
RAD SAFETY 1,3 2 3 01/22/2018 01/26/2018 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 3 01/22/2018 01/26/2018 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation 3 01/22/2018 01/26/2018 IP 71151 000746 Performance Indicator Verification WAT 50.59 CHANGES, TESTS, EXPERIMENTS 3 3 04/02/2018 04/06/2018 IP 71111.17T 000709 Evaluations of Changes, Tests, and Experiments SECURITY TEAM INSPECTION 2 3 06/04/2018 06/08/2018 IP 71130.04 000736 Equipment Performance, Testing, and Maintenance 3 06/04/2018 06/08/2018 IP 71130.07 000739 Security Training TRIENNIAL FIRE PROTECTION INSPECTION 6 3 07/30/2018 08/03/2018 IP 71111.05XT 000697 Fire Protection - NFPA 805 (Triennial) | RAD SAFETY 1,3 2 3 01/22/2018 01/26/2018 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 3 01/22/2018 01/26/2018 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation 3 01/22/2018 01/26/2018 IP 71151 000746 Performance Indicator Verification WAT 50.59 CHANGES, TESTS, EXPERIMENTS 3 3 04/02/2018 04/06/2018 IP 71111.17T 000709 Evaluations of Changes, Tests, and Experiments SECURITY TEAM INSPECTION 2 3 06/04/2018 06/08/2018 IP 71130.04 000736 Equipment Performance, Testing, and Maintenance 3 06/04/2018 06/08/2018 IP 71130.07 000739 Security Training TRIENNIAL FIRE PROTECTION INSPECTION 6 3 07/30/2018 08/03/2018 IP 71111.05XT 000697 Fire Protection - NFPA 805 (Triennial) | ||
3 07/30/2018 08/03/2018 IP 92702 000238 Followup On Corrective Actions For Violations And Deviations 3 08/13/2018 08/17/2018 IP 71111.05XT 000697 Fire Protection - NFPA 805 (Triennial) | 3 07/30/2018 08/03/2018 IP 92702 000238 Followup On Corrective Actions For Violations And Deviations 3 08/13/2018 08/17/2018 IP 71111.05XT 000697 Fire Protection - NFPA 805 (Triennial) | ||
EP PROGRAM INSPECTION 1 3 08/06/2018 08/10/2018 IP 71114.02 000717 Alert and Notification System Testing 3 08/06/2018 08/10/2018 IP 71114.03 000718 Emergency Response Organization Staffing and Augmentation System 3 08/06/2018 08/10/2018 IP 71114.05 000720 Correction of Emergency Preparedness Weaknesses and Deficiencies 3 08/06/2018 08/10/2018 IP 71151 001397 Performance Indicator Verification 3 08/13/2018 08/17/2018 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes 3 08/13/2018 08/17/2018 IP 71151 001397 Performance Indicator Verification RAD SAFETY 2,4 2 3 09/10/2018 09/14/2018 IP 71124.02 000726 Occupational ALARA Planning and Controls 3 09/10/2018 09/14/2018 IP 71124.04 000728 Occupational Dose Assessment BIENNIAL PI&R INSPECTION 4 3 09/17/2018 09/21/2018 IP 71152B 000747 Problem Identification and Resolution 3 10/01/2018 10/05/2018 IP 71152B 000747 Problem Identification and Resolution | EP PROGRAM INSPECTION 1 3 08/06/2018 08/10/2018 IP 71114.02 000717 Alert and Notification System Testing 3 08/06/2018 08/10/2018 IP 71114.03 000718 Emergency Response Organization Staffing and Augmentation System 3 08/06/2018 08/10/2018 IP 71114.05 000720 Correction of Emergency Preparedness Weaknesses and Deficiencies 3 08/06/2018 08/10/2018 IP 71151 001397 Performance Indicator Verification 3 08/13/2018 08/17/2018 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes 3 08/13/2018 08/17/2018 IP 71151 001397 Performance Indicator Verification RAD SAFETY 2,4 2 3 09/10/2018 09/14/2018 IP 71124.02 000726 Occupational ALARA Planning and Controls 3 09/10/2018 09/14/2018 IP 71124.04 000728 Occupational Dose Assessment BIENNIAL PI&R INSPECTION 4 3 09/17/2018 09/21/2018 IP 71152B 000747 Problem Identification and Resolution 3 10/01/2018 10/05/2018 IP 71152B 000747 Problem Identification and Resolution This report does not include INPO and OUTAGE activities. Page 1 of 3 This report shows only on-site and announced inspection procedures. | ||
This report shows only on-site and announced inspection procedures. | |||
2/23/2018 10:41:08 AM Enclosure | |||
000737 Protective Strategy Evaluation | IP 22 Inspection Activity Plan Report Waterford 01/01/2018 - 12/31/2019 Unit Start End Activity CAC Title Staff Count FORCE-ON-FORCE PLANNING & EXERCISE WEEK 7 3 09/24/2018 09/28/2018 IP 71130.03 000735 Contingency Response - Force-On-Force Testing 3 10/15/2018 10/19/2018 IP 71130.03 000735 Contingency Response - Force-On-Force Testing INITIAL EXAM 4 3 09/30/2018 10/06/2018 OV 000956 VALIDATION OF INITIAL LICENSE EXAMINATION (OV) | ||
3 11/04/2018 11/10/2018 EXAD 000500 LICENSE EXAM ADMINISTRATION (EXAD) | |||
CYBER SECURITY INSPECTION 5 3 11/05/2018 11/09/2018 IP 71130.10P 000741 Cyber Security 3 11/26/2018 11/30/2018 IP 71130.10P 000741 Cyber Security SECURITY SOLO 1 3 12/03/2018 12/07/2018 IP 71130.02 000734 Access Control 3 12/03/2018 12/07/2018 IP 71151 001338 Performance Indicator Verification WATERFORD INSERVICE INSPECTION 1 3 01/14/2019 01/25/2019 IP 71111.08P 000702 Inservice Inspection Activities - PWR RP INSPECTION 2 3 01/14/2019 01/18/2019 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 3 01/14/2019 01/18/2019 IP 71124.02 000726 Occupational ALARA Planning and Controls 3 01/14/2019 01/18/2019 IP 71151 000746 Performance Indicator Verification WATERFORD EQ PROGRAMS INSPECTION 3 3 04/01/2019 04/19/2019 IP 71111.21N 000714 Design Bases Assurance Inspection (Programs) | |||
SECURITY SOLO INSPECTION 1 3 05/13/2019 05/17/2019 IP 71130.02 000734 Access Control 3 05/13/2019 05/17/2019 IP 71151 001338 Performance Indicator Verification BRQ 2 3 07/29/2019 08/03/2019 IP 71111.11B 000704 Licensed Operator Requalification Program and Licensed Operator Performance - | |||
Biennial SECURITY TEAM INSPECTION 2 3 10/07/2019 10/11/2019 IP 71130.05 000737 Protective Strategy Evaluation This report does not include INPO and OUTAGE activities. Page 2 of 3 This report shows only on-site and announced inspection procedures. | |||
2/23/2018 10:41:08 AM | 2/23/2018 10:41:08 AM | ||
IP 22 Inspection Activity Plan Report Waterford 01/01/2018 - 12/31/2019 Unit Start End Activity CAC Title Staff Count RP TEAM INSPECTION 5 3 11/04/2019 11/08/2019 IP 71124.05 000729 Radiation Monitoring Instrumentation 3 11/04/2019 11/08/2019 IP 71124.06 000730 Radioactive Gaseous and Liquid Effluent Treatment 3 11/04/2019 11/08/2019 IP 71124.07 000731 Radiological Environmental Monitoring Program 3 11/04/2019 11/08/2019 IP 71124.08 000732 Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation EP EXERCISE AND PI INSPECTION 4 3 11/18/2019 11/22/2019 IP 71114.01 000716 Exercise Evaluation 3 11/18/2019 11/22/2019 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes 3 11/18/2019 11/22/2019 IP 71151 001397 Performance Indicator Verification TI 2515/194 2 3 12/09/2019 12/13/2019 TI 2515/194 000512 Inspection of the Licensees Implementation of Industry Initiative Associated With the Open Phase Condition Design Vulnerabilities In Electric Power Systems (NRC Bulletin 2012-01) | |||
This report does not include INPO and OUTAGE activities. Page 3 of 3 This report shows only on-site and announced inspection procedures. | |||
IP 22 Inspection Activity Plan Report | |||
Waterford 01/01/2018 - 12/31/2019 | |||
Unit Start End Activity CAC Title Staff Count | |||
RP TEAM INSPECTION | |||
3 11/04/2019 | |||
11/08/2019 | |||
IP 71124.05 | |||
000729 Radiation Monitoring Instrumentation | |||
11/04/2019 | |||
11/08/2019 | |||
IP 71124.06 | |||
000730 Radioactive Gaseous and Liquid Effluent Treatment | |||
11/04/2019 | |||
11/08/2019 | |||
IP 71124.07 | |||
000731 Radiological Environmental Monitoring Program | |||
11/04/2019 | |||
11/08/2019 | |||
IP 71124.08 | |||
000732 Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and | |||
Transportation | |||
EP EXERCISE AND PI INSPECTION | |||
3 11/18/2019 | |||
11/22/2019 | |||
IP 71114.01 | |||
000716 Exercise Evaluation | |||
11/18/2019 | |||
11/22/2019 | |||
IP 71114.04 | |||
2/23/2018 10:41:08 AM | 2/23/2018 10:41:08 AM | ||
ML18052A527 SUNSI Review ADAMS: Non-Publicly Available Non-Sensitive Keyword: | |||
By: NHT/rdr Yes No Publicly Available Sensitive NRC-002 OFFICE DRP/SPE:D DRS/C:PSB1 DRS/D DRP/C:D DRP/D NAME JDixon JGroom AVegel GMiller TPruett SIGNATURE /RA/ /RA/ /RA/ /RA/ /RA RLantz for/ | |||
DATE 2/21/18 2/21/18 2/22/18 2/23/18 2/22/18 | |||
ML18052A527 SUNSI Review ADAMS: Non-Publicly Available Non-Sensitive Keyword: By: NHT/rdr Yes No Publicly Available Sensitive NRC-002 OFFICE DRP/SPE: D DRS/C: PSB1 DRS/D DRP/C: D DRP/D NAME JDixon JGroom AVegel GMiller TPruett SIGNATURE /RA/ /RA/ /RA/ /RA/ /RA RLantz for | |||
}} | }} |
Latest revision as of 19:38, 21 October 2019
ML18052A527 | |
Person / Time | |
---|---|
Site: | Waterford |
Issue date: | 03/01/2018 |
From: | Geoffrey Miller NRC/RGN-IV/DRP/RPB-D |
To: | Dinelli J Entergy Operations |
Miller G | |
References | |
IR 2017006 | |
Download: ML18052A527 (6) | |
Text
rch 1, 2018
SUBJECT:
ANNUAL ASSESSMENT LETTER FOR WATERFORD STEAM ELECTRIC STATION UNIT 3 (REPORT 05000382/2017006)
Dear Mr. Dinelli:
The U.S. Nuclear Regulatory Commission (NRC) has completed its end-of-cycle performance assessment of Waterford Steam Electric Station Unit 3, reviewing performance indicators (PIs),
inspection results, and enforcement actions from January 1, 2017 through December 31, 2017.
This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility. The NRC concluded that overall performance at your facility preserved public health and safety.
The NRC determined the performance at Waterford Steam Electric Station Unit 3 during the most recent quarter was within the Licensee Response Column, the highest performance category of the NRCs Reactor Oversight Process (ROP) Action Matrix, because all inspection findings had very low safety significance (i.e., Green), and all PIs were within the expected range (i.e., Green). Therefore, the NRC plans to conduct ROP baseline inspections at your facility.
The enclosed inspection plan lists the inspections scheduled through December 31, 2019. This updated inspection plan now includes planned security inspections which were formerly transmitted under separate correspondence. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last twelve months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes.
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of the NRCs document system, Agencywide Documents Access and Management System (ADAMS).
ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Please contact me at (817) 200-1173 with any questions you have regarding this letter.
Sincerely,
/RA/
Geoffrey B. Miller, Branch Chief Projects Branch D Division of Reactor Projects Docket: 50-382 License: NPF-38 Enclosure:
Waterford Steam Electric Station Unit 3 Inspection Plan
IP 22 Inspection Activity Plan Report Waterford 01/01/2018 - 12/31/2019 Unit Start End Activity CAC Title Staff Count MAT'L CONTROL & ACCOUNTING 1 3 01/22/2018 01/26/2018 IP 71130.11 000742 Material Control and Accounting (MC&A)
RAD SAFETY 1,3 2 3 01/22/2018 01/26/2018 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 3 01/22/2018 01/26/2018 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation 3 01/22/2018 01/26/2018 IP 71151 000746 Performance Indicator Verification WAT 50.59 CHANGES, TESTS, EXPERIMENTS 3 3 04/02/2018 04/06/2018 IP 71111.17T 000709 Evaluations of Changes, Tests, and Experiments SECURITY TEAM INSPECTION 2 3 06/04/2018 06/08/2018 IP 71130.04 000736 Equipment Performance, Testing, and Maintenance 3 06/04/2018 06/08/2018 IP 71130.07 000739 Security Training TRIENNIAL FIRE PROTECTION INSPECTION 6 3 07/30/2018 08/03/2018 IP 71111.05XT 000697 Fire Protection - NFPA 805 (Triennial)
3 07/30/2018 08/03/2018 IP 92702 000238 Followup On Corrective Actions For Violations And Deviations 3 08/13/2018 08/17/2018 IP 71111.05XT 000697 Fire Protection - NFPA 805 (Triennial)
EP PROGRAM INSPECTION 1 3 08/06/2018 08/10/2018 IP 71114.02 000717 Alert and Notification System Testing 3 08/06/2018 08/10/2018 IP 71114.03 000718 Emergency Response Organization Staffing and Augmentation System 3 08/06/2018 08/10/2018 IP 71114.05 000720 Correction of Emergency Preparedness Weaknesses and Deficiencies 3 08/06/2018 08/10/2018 IP 71151 001397 Performance Indicator Verification 3 08/13/2018 08/17/2018 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes 3 08/13/2018 08/17/2018 IP 71151 001397 Performance Indicator Verification RAD SAFETY 2,4 2 3 09/10/2018 09/14/2018 IP 71124.02 000726 Occupational ALARA Planning and Controls 3 09/10/2018 09/14/2018 IP 71124.04 000728 Occupational Dose Assessment BIENNIAL PI&R INSPECTION 4 3 09/17/2018 09/21/2018 IP 71152B 000747 Problem Identification and Resolution 3 10/01/2018 10/05/2018 IP 71152B 000747 Problem Identification and Resolution This report does not include INPO and OUTAGE activities. Page 1 of 3 This report shows only on-site and announced inspection procedures.
2/23/2018 10:41:08 AM Enclosure
IP 22 Inspection Activity Plan Report Waterford 01/01/2018 - 12/31/2019 Unit Start End Activity CAC Title Staff Count FORCE-ON-FORCE PLANNING & EXERCISE WEEK 7 3 09/24/2018 09/28/2018 IP 71130.03 000735 Contingency Response - Force-On-Force Testing 3 10/15/2018 10/19/2018 IP 71130.03 000735 Contingency Response - Force-On-Force Testing INITIAL EXAM 4 3 09/30/2018 10/06/2018 OV 000956 VALIDATION OF INITIAL LICENSE EXAMINATION (OV)
3 11/04/2018 11/10/2018 EXAD 000500 LICENSE EXAM ADMINISTRATION (EXAD)
CYBER SECURITY INSPECTION 5 3 11/05/2018 11/09/2018 IP 71130.10P 000741 Cyber Security 3 11/26/2018 11/30/2018 IP 71130.10P 000741 Cyber Security SECURITY SOLO 1 3 12/03/2018 12/07/2018 IP 71130.02 000734 Access Control 3 12/03/2018 12/07/2018 IP 71151 001338 Performance Indicator Verification WATERFORD INSERVICE INSPECTION 1 3 01/14/2019 01/25/2019 IP 71111.08P 000702 Inservice Inspection Activities - PWR RP INSPECTION 2 3 01/14/2019 01/18/2019 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 3 01/14/2019 01/18/2019 IP 71124.02 000726 Occupational ALARA Planning and Controls 3 01/14/2019 01/18/2019 IP 71151 000746 Performance Indicator Verification WATERFORD EQ PROGRAMS INSPECTION 3 3 04/01/2019 04/19/2019 IP 71111.21N 000714 Design Bases Assurance Inspection (Programs)
SECURITY SOLO INSPECTION 1 3 05/13/2019 05/17/2019 IP 71130.02 000734 Access Control 3 05/13/2019 05/17/2019 IP 71151 001338 Performance Indicator Verification BRQ 2 3 07/29/2019 08/03/2019 IP 71111.11B 000704 Licensed Operator Requalification Program and Licensed Operator Performance -
Biennial SECURITY TEAM INSPECTION 2 3 10/07/2019 10/11/2019 IP 71130.05 000737 Protective Strategy Evaluation This report does not include INPO and OUTAGE activities. Page 2 of 3 This report shows only on-site and announced inspection procedures.
2/23/2018 10:41:08 AM
IP 22 Inspection Activity Plan Report Waterford 01/01/2018 - 12/31/2019 Unit Start End Activity CAC Title Staff Count RP TEAM INSPECTION 5 3 11/04/2019 11/08/2019 IP 71124.05 000729 Radiation Monitoring Instrumentation 3 11/04/2019 11/08/2019 IP 71124.06 000730 Radioactive Gaseous and Liquid Effluent Treatment 3 11/04/2019 11/08/2019 IP 71124.07 000731 Radiological Environmental Monitoring Program 3 11/04/2019 11/08/2019 IP 71124.08 000732 Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation EP EXERCISE AND PI INSPECTION 4 3 11/18/2019 11/22/2019 IP 71114.01 000716 Exercise Evaluation 3 11/18/2019 11/22/2019 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes 3 11/18/2019 11/22/2019 IP 71151 001397 Performance Indicator Verification TI 2515/194 2 3 12/09/2019 12/13/2019 TI 2515/194 000512 Inspection of the Licensees Implementation of Industry Initiative Associated With the Open Phase Condition Design Vulnerabilities In Electric Power Systems (NRC Bulletin 2012-01)
This report does not include INPO and OUTAGE activities. Page 3 of 3 This report shows only on-site and announced inspection procedures.
2/23/2018 10:41:08 AM
ML18052A527 SUNSI Review ADAMS: Non-Publicly Available Non-Sensitive Keyword:
By: NHT/rdr Yes No Publicly Available Sensitive NRC-002 OFFICE DRP/SPE:D DRS/C:PSB1 DRS/D DRP/C:D DRP/D NAME JDixon JGroom AVegel GMiller TPruett SIGNATURE /RA/ /RA/ /RA/ /RA/ /RA RLantz for/
DATE 2/21/18 2/21/18 2/22/18 2/23/18 2/22/18