IR 05000382/2017008

From kanterella
Jump to navigation Jump to search
NRC Design Bases Assurance Inspection Report 05000382/2017008
ML17362A424
Person / Time
Site: Waterford Entergy icon.png
Issue date: 12/28/2017
From: Thomas Farnholtz
Region 4 Engineering Branch 1
To: Dinelli J
Entergy Operations
References
IR 2017008
Download: ML17362A424 (33)


Text

December 28, 2017

SUBJECT:

WATERFORD STEAM ELECTRIC STATION, UNIT 3 - NRC DESIGN BASES

ASSURANCE INSPECTION REPORT 05000382/2017008

Dear Mr. Dinelli:

On November 16, 2017, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at your Waterford Steam Electric Station, Unit 3 and discussed the preliminary results of this inspection with you and other members of your staff. On December 14, 2017, the inspectors discussed the final results of this inspection with Mr. D. Brenton, General Manager-Plant Operations, and other members of your staff. The results of this inspection are documented in the enclosed report.

Nuclear Regulatory Commission inspectors documented two findings of very low safety significance (Green). These findings involved violations of NRC requirements. The NRC is treating these violations as non-cited violations (NCVs) consistent with Section 2.3.2.a of the Enforcement Policy.

Additionally, the inspectors documented one Severity Level IV traditional enforcement violation associated with impacting the ability of the NRC to perform its regulatory oversight function.

The NRC is treating this violation as non-cited violation (NCV) consistent with Section 2.3.2.a of the Enforcement Policy.

From December 2016 to December 2017, the NRC issued four Severity Level IV traditional enforcement violations associated with impacting the ability of the NRC to perform its regulatory oversight function. As a result of the four Severity Level IV traditional enforcement violations, the NRC determined that the additional inspection was not warranted because the cause of the most recent violation occurred in 2006 and 2014 and current Waterford procedures and practices should prevent recurrence. Therefore, the NRC will not conduct Inspection Procedure 92723, Follow up Inspection for Three or More Severity Level IV Traditional Enforcement Violations in the Same Area in a 12-Month Period.

If you contest the violations or significance of these NCVs, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region IV; the Director, Office of Enforcement; and the NRC resident inspector at the Grand Gulf Nuclear Station. If you disagree with a cross-cutting aspect assignment in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region IV; and the NRC resident inspector at the Grand Gulf Nuclear Station.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA/

Thomas R. Farnholtz, Chief Engineering Branch 1 Division of Reactor Safety

Docket No. 50-382 License No. NPF-38

Enclosure:

Inspection Report 05000382/2017008 w/Attachments:

1. Supplemental Information 2. Additional Information Request

cc w/enclosure: Electronic Distribution

Enclosure U.S. NUCLEAR REGULATORY COMMISSION

INSPECTION REPORT

Docket:

05000382 License:

NPF-38 Report Nos.:

05000382/2017008 Enterprise Identifier:

I-2017-008-0023 Licensee:

Entergy Operations, Inc.

Facility:

Waterford Steam Electric Station, Unit 3 Location:

17265 River Road Killona, LA 70057 On-site Dates:

October 23 through November 16, 2017 Exit Date:

December 14, 2017 Team Leader:

G. George, Senior Reactor Inspector, Engineering Branch 1 Inspectors:

J. Braisted, Reactor Inspector, Engineering Branch 1 N. Okonkwo, Reactor Inspector, Engineering Branch 2 G. Callaway, Senior Reactor Technology Instructor, Technical Training Center Accompanying Personnel:

A. Athar, Reactor Operations Engineer, ROP Assessment Branch, Nuclear Reactor Regulation C. Baron, Contractor, Beckman and Associates S. Gardner, Contractor, Beckman and Associates Approved By:

Thomas R. Farnholtz Branch Chief, Engineering Branch 1 Division of Reactor Safety

SUMMARY

The NRC continued monitoring licensees performance by conducting an Inspection

Procedure 71111.21M, Design Bases Assurance (Teams), inspection at Waterford Steam Electric Station, Unit 3, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information. NRC and self-revealed findings, violations, and additional items are summarized in the table below.

List of Findings and Violations

Three examples of Failure to Establish and Maintain Preventive Maintenance Procedures for Safety-Related Electrical Equipment Cornerstone Significance Cross-cutting Aspect Report Section Mitigating Systems Green NCV 05000382/2017008-01 Closed Not Applicable 71111.21M The team identified three examples of a Green non-cited violation of Waterford Steam Electric Station, Unit 3, Technical Specification 6.8.1.a, for failure to establish, implement, and maintain written procedures for activities referenced in Appendix A of Regulatory Guide 1.33,

Revision 2, dated February 1978. Specifically, prior to November 16, 2017, the licensee failed to establish and maintain procedures covered in Regulatory Guide 1.33, Appendix A,

Section 9, Procedures for Performing Maintenance, to implement maintenance for safety-related 1600 A, 600 V non-segregated metal-enclosed bus ducts, safety-related 4.16 kV G.E. Magne-Blast circuit breakers, and safety-related 480 V G.E. switchgear AKR breakers.

Failure to Meet RG 1.9 Emergency Diesel Testing Requirements during Surveillance Test Results in Missed Surveillance Cornerstone Significance Cross-cutting Aspect Report Section Mitigating Systems Green NCV 05000382/2017008-02 Closed H.11 - Human Performance,

Challenge the Unknown 71111.21M The team identified a Green non-cited violation of Waterford Steam Electric Station, Unit 3,

Technical Specification Limiting Condition for Operation 3.8.1.1 for failure to maintain operability of two separate independent diesel generators. Specifically, on May 23, 2017, the licensee failed to verify that the train A emergency diesel generator energized all auto-connected shutdown loads through the load sequencer and operated for greater than or equal to five minutes in accordance with Technical Specification Surveillance Requirement 4.8.1.1.2.

Two Examples of Failure to Submit and Receive Prior Authorization of Alternatives to ASME OM Code Leak Testing Requirements Cornerstone Significance Cross-cutting Aspect Report Section Not Applicable Severity Level IV NCV 05000382/2017008-03 Closed Not Applicable 71111.21M The team identified two examples of a Severity Level IV, non-cited violation of 10 CFR 50.55a(z), for failure to submit and obtain authorization prior to implementation of multiple alternatives to leak testing requirements of the American Society of Mechanical Engineers (ASME) Operation and Maintenance (OM) of Nuclear Power Plants Code.

Specifically, prior to November 16, 2017, the licensee did not submit and receive prior authorization to alternative leak testing requirements for safety injection valves SI-512A and SI-602B.

Additional Tracking Items

Type Issue Number Title Report Section Status URI 05000382/2017008-

Potential Failure to Obtain a License Amendment for Changes to Diesel Generator Surveillance Test Interval 71111.21M Open

TABLE OF CONTENTS

INSPECTION SCOPES

...............5

REACTOR SAFETY

..................................................................................................................

INSPECTION RESULTS

..............................................................................................................

EXIT MEETINGS AND DEBRIEFS

............................................................................................ 16 LIST OF

DOCUMENTS REVIEWED

...................................................................................... A1-1

ADDITIONAL REQUESTS..................................................................................................... A2-1

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures in effect

at the beginning of the inspection unless otherwise noted. Currently approved inspection

procedures with their attached revision histories are located on the public Web site at

http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html.

Samples were declared complete when the inspection procedure requirements most

appropriate to the inspection activity were met consistent with Inspection Manual Chapter 2515,

Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed

selected procedures and records, observed activities, and interviewed personnel to assess

licensee performance and compliance with Commission rules and regulations, license

conditions, site procedures, and standards.

REACTOR SAFETY

Inspection Procedure 71111.21M - Design Bases Assurance (Team) Inspection

From October 23, 2017, to November 16, 2017, the team inspected the following

components and listed applicable attributes, permanent modifications, operating experience,

and operator actions.

Components - 71111.21M (5 Samples)

(1) Emergency feedwater turbine steam supply valves, MSMVAAA401A and 401B:

a) Component maintenance history and corrective action program reports to verify the

monitoring of potential degradation.

b) Calculations for valve thrust and torque to verify the capability of the valve to perform

its required function under the most limiting conditions.

c) Evaluation of the electric heat tracing installed downstream of the motor-operated

valves to verify excessive condensate will not be generated in the event of a cold

start of the emergency feedwater turbine.

d) Procedures for testing the bypass of motor-operated valve thermal overloads under

accident conditions to verify operability of valve.

(2) 125 VDC Bus 3AB-DC-S

a) Component maintenance history and corrective action program reports to verify the

monitoring of potential degradation.

b) Calculations for electrical distribution, system load flow/voltage drop, short-circuit,

and electrical protection to verify that bus capacity and voltages remained within

minimum acceptable limits.

c) The protective device settings and circuit breaker ratings to ensure adequate

selective protection coordination of connected equipment during worst-case short

circuit conditions.

d) Procedures for circuit breaker preventive maintenance, inspection, and testing to

compare maintenance practices against industry and vendor guidance.

(3) High pressure safety injection pump B:

a) Component maintenance history and corrective action program reports to verify the

monitoring of potential degradation.

b) Calculations for system flow, system flow balance, net positive suction head,

surveillance test acceptance criteria minimum flow, and runout flow.

c) The impact of minimum and maximum allowable electrical power supply frequency

on pump performance and net positive suction head.

d) Procedures for operation of the high pressure safety injection system under accident

conditions.

e) Routing of pump motor cables.

f) Corrective action documents issued in the past five years.

g) Procedures for preventive maintenance, inspection, and testing to compare

maintenance practices against industry and vendor guidance.

h) Motor sizing calculations to verify input assumptions and design loading to ensure

adequate design for pumping capacity. The team put special emphasis on pump

motor testing methodology, the values assigned to acceptance criteria, and whether

the values supported design parameters and assumptions.

(4) Safety injection sump outlet motor-operated valve, SI-602A:

a) Component maintenance history and corrective action program reports to verify the

monitoring of potential degradation.

b) Calculations for the determination of allowable leakage, target torque values for

stroke testing, maximum rim-pull force, and torque switch settings to ensure valve

functionality.

c) Procedures for valve and operator preventive maintenance, inspection, and testing to

compare maintenance practices against industry and vendor guidance.

d) Site specific commitments to NRC Generic Letter 89-10, Safety-Related

Motor-Operated Valve Testing and Surveillance.

(5) 480 VAC Class 1E switchgear, Bus 3B31S:

a) System health reports, component maintenance history, and corrective action

program reports to verify the monitoring and correction of potential degradation.

b) Calculations for electrical distribution, system load flow/voltage drop, short-circuit,

and electrical protection to verify that bus capacity and voltages remained within the

minimum acceptable limits.

c) The protective device settings and feeder circuit breaker ratings to ensure adequate

selective protection coordination of connected equipment during worst-case short

circuit conditions.

d) Procedures for preventive maintenance, inspection, and testing to compare

maintenance practices against industry and vendor guidance; including the cable

aging management program.

e) Results of completed preventative maintenance on switchgear and breakers,

including breaker tracking.

Large Early Release Frequency Containment Related Structures, Systems, or

Components - 71111.21M (1 Sample)

(1) Containment isolation actuation system:

a) Pressurizer low pressure and containment high pressure transmitter environmental

qualification files and replacement history to maintain pressure transmitters

environmental qualification.

b) Calculations for measurement loop uncertainty and response time test acceptance

criteria.

c) Surveillance test procedures for emergency safety features relay testing and plant

protection system channel testing.

Modifications to Mitigation Structures, Systems, or Components - 71111.21M (6 Samples)

(1) Engineering Change 530, Ultimate Heat Sink Water Replenishment for Tornado Event

(2) Engineering Change 40828, Evaluation of Replacement Bushings for Unit Auxiliary

Transformer

(3) Engineering Change 46556, CC ISV0807A Solenoid Preventative Maintenance

Equivalency

(4) Engineering Change 44782, Emergency Diesel Generator Governor Upgrade

(5) Engineering Change 55752, Replace SI-512B with a Swing Check Valve

(6) Engineering Change 63801, Emergency Feedwater Circuitry Modification

Operating Experience - 71111.21M (3 Samples)

(1) NRC Generic Letter 1988-03, Resolution of Generic Safety Issue 93, Steam Binding of

Auxiliary Feedwater Pumps

(2) NRC Information Notice 2013-05, Battery Expected Life and its Potential Impact on

Surveillance Requirements

(3) NRC Information Notice 2014-03, Turbine-Driven Auxiliary Feedwater Pump Overspeed

Trip Mechanism Issues

Evaluation of Inspection Sample Related Operator Procedures and Actions

(1) Control room operator actions resulting from a simulated small break loss-of-coolant

accident followed by a post reactor trip loss-of-offsite power with a single failure of

component cooling water pump B.

a) Control room crew expected to enter procedures for standard post trip actions and

loss of coolant accident recovery.

b) Following the component cooling water pump B trip, the crew was expected to

restore cooling to emergency diesel generator B, using component cooling water

pump AB, and prior to emergency diesel generator failure.

INSPECTION RESULTS

Three examples of Failure to Establish and Maintain Preventive Maintenance Procedures for

Safety-Related Electrical Equipment

Cornerstone

Significance

Cross-cutting

Aspect

Report

Section

Mitigating

Systems

Green

NCV 05000382/2017008-01

Closed

Not Applicable

71111.21M

The team identified three examples of a Green non-cited violation of Waterford Steam Electric

Station, Unit 3, Technical Specification 6.8.1.a, for failure to establish, implement, and maintain

written procedures for activities referenced in Appendix A of Regulatory Guide 1.33,

Revision 2, dated February 1978. Specifically, prior to November 16, 2017, the licensee failed

to establish and maintain procedures covered in Regulatory Guide 1.33, Appendix A,

Section 9, Procedures for Performing Maintenance, to implement maintenance for

safety-related 1600 A, 600 V non-segregated metal-enclosed bus ducts, safety-related 4.16 kV

G.E. Magne-Blast circuit breakers, and safety-related 480 V G.E. switchgear AKR breakers.

Description:

Example 1: The team identified that the licensee failed to establish a procedure to perform

maintenance and inspection of safety-related 1600 A, 600 V non-segregated metal enclosed

bus ducts as recommended by the vendor. The vendor manual, TD-G080.0735, General

Electric Important Instructions for Armor-Clad Indoor Feeder Busway, GEH-2636, included

recommendations for cleaning dust and dirt on the busway, checking for signs of overheating,

megger checks, visually check for loose bolts at the joints, proper spring tension, excessive

wear, arc spatter, and sooty deposits. No procedure for performing maintenance or plans for

performing maintenance were established for the safety-related metal-enclosed bus ducts.

This represented a failure to establish procedures for activities covered by Regulatory

Guide 1.33, Appendix A, Section 9, Procedures for Performing Maintenance.

Example 2: The team identified that the licensee failed to revise safety-related 4.16 kV G.E.

Magne-Blast circuit breaker preventive maintenance procedures to include auxiliary switch

contact resistance and functional tests. Entergy maintenance procedures are written to

include requirements set forth in the Entergy preventive maintenance templates. The Entergy

preventive maintenance templates for circuit breakers include vendor recommendations and

industry best practices, such as EPRI Technical Report 109641, Guidance on Routine

Preventive Maintenance for Magne-Blast Breakers. EPRI Technical Report 109641, Section

7, Preventive Maintenance Tasks, provides guidance on performing auxiliary switch contact

resistance tests and justifies the tests inclusion using industry operating experience. The

Task Content section of the Preventive Maintenance Template, EN-Switchgear - Medium

Voltage - 1KV-7KV, Revision 3, requires during inspections, cleaning and testing, and

breaker overhauls to Perform contact resistance test. The teams review of maintenance

Procedure ME-003-327, 4.16 KV

G.E Magne Blast Breaker, Revision 18, identified that the

procedure did not include the performance of auxiliary switch contact resistance tests as

required by the preventive maintenance template. This represented a failure to maintain

procedures for activities covered by Regulatory Guide 1.33, Appendix A, Section 9,

Procedures for Performing Maintenance.

Example 3: The team identified that the licensee failed to revise 480 V G.E. AKR circuit

breakers preventive maintenance procedures to include reduced control voltage tests. Entergy

maintenance procedures are written to include requirements set forth in the Entergy preventive

maintenance templates. The Entergy preventive maintenance templates for circuit breakers

include vendor recommendations and industry best practices, such as EPRI Technical

Report 112938, Routine Preventive Maintenance Guidance for AK and AKR Type Circuit

Breakers. EPRI Technical Report 112938 provides guidance on performing reduced control

voltage tests. In September 2008, Preventive Maintenance Template, EN-Switchgear - Low

Voltage, was changed to include a required reduced control voltage test in the visual

inspection task for low voltage circuit breakers. However, as of September 12, 2017,

Maintenance Procedure ME-003-330, 480 V

G.E Switchgear Breakers, Revision 310 did not

include the performance of reduced control voltage tests required by the preventive

maintenance template. This represented a failure to maintain procedures for activities covered

by Regulatory Guide 1.33, Appendix A, Section 9, Procedures for Performing Maintenance.

This represented a failure to establish procedures for activities covered by Regulatory

Guide 1.33, Appendix A, Section 9, Procedures for Performing Maintenance.

Corrective Action(s): In response to this issue, the licensee created corrective actions to

evaluate the appropriateness and scheduling for each preventive maintenance task. This

finding does not represent an immediate safety concern.

Corrective Action Reference(s): Condition Reports CR-WF3-2017-08574,

CR-WF3-2017-08611, CR-WF3 2017-08632, CR-WF3-2017-08635, and CR-WF3-2017-08737

Performance Assessment:

Performance Deficiency: The team determined that the failure to establish and maintain

maintenance procedures for activities covered by Regulatory Guide 1.33, Appendix A,

Section 9, Procedures for Performing Maintenance, was a performance deficiency.

Screening: This performance deficiency was more than minor, and therefore a finding,

because it was associated with the procedure quality attribute of the Mitigating Systems

Cornerstone and adversely affected the cornerstone objective to ensure the availability,

reliability, and capability of systems to respond to initiating events to prevent undesirable

consequences. Specifically, the failure to incorporate the testing, and inspection requirements

into preventive maintenance procedures could cause unacceptable conditions to go

undetected.

Significance: In accordance with Inspection Manual Chapter 0609, Appendix A, The

Significance Determination Process (SDP) for Findings At Power, dated July 19, 2012, the

finding screened as having very low safety significance (Green) because it was a design or

qualification deficiency that did not represent a loss of operability or functionality; did not

represent an actual loss of safety function of the system or train; did not result in the loss of

one or more trains of non-technical specification equipment; and did not screen as potentially

risk-significant due to seismic, flooding, or severe weather.

Cross Cutting Aspect: The team determined that this finding did not have a cross-cutting

aspect because the most significant contributor did not reflect current licensee performance.

Enforcement:

Violation: Waterford Steam Electric Station, Unit 3, Technical Specification 6.8.1.a, requires

that written procedures shall be established, implemented, and maintained to cover the

applicable procedures recommended in Appendix A of Regulatory Guide RG 1.33, Revision 2,

dated February 1978. Appendix A, Section 9, Procedures for Performing Maintenance

recommends in part that, Maintenance that can affect the performance of a safety-related

equipment should be properly pre-planned and performed in accordance with written

procedures, documented instructions, or drawings appropriate to the circumstance.

Contrary to the above, prior to November 16, 2017, the licensee failed to establish and

maintain written procedures for performing maintenance that can affect the performance of

safety-related equipment. Specifically, the licensee failed to establish and maintain

procedures covered in Regulatory Guide 1.33, Appendix A, Section 9, Procedures for

Performing Maintenance, to implement maintenance for safety-related 1600 A,

600 V non-segregated metal-enclosed bus ducts, safety-related 4.16 kV G.E. Magne-Blast

circuit breakers, and safety-related 480 V G.E. Switchgear AKR Breakers.

Enforcement Action(s): This violation is being treated as a non-cited violation, consistent with

Section 2.3.2 of the Enforcement Policy.

Failure to Meet RG 1.9 Emergency Diesel Testing Requirements during Surveillance Test

Results in Missed Surveillance

Cornerstone

Significance

Cross-cutting

Aspect

Report

Section

Mitigating

Systems

Green

NCV 05000382/2017008-02

Closed

H.11 - Human

Performance,

Challenge the

Unknown

71111.21M

The team identified a Green non-cited violation of Waterford Steam Electric Station, Unit 3,

Technical Specification Limiting Condition for Operation 3.8.1.1 for failure to maintain

operability of two separate independent diesel generators. Specifically, on May 23, 2017, the

licensee failed to verify that the train A emergency diesel generator energized all auto-

connected shutdown loads through the load sequencer and operated for greater than or equal

to five minutes in accordance with Technical Specification Surveillance Requirement 4.8.1.1.2

Description:

Technical Specification Surveillance Requirement 4.8.1.1.2 requires the licensee to

demonstrate each diesel generators operability by verification, for a simulated loss-of-offsite

power and simulated loss-of-offsite power in conjunction with safety injection actuation system

test signal, that the following is met:

Verifying the diesel starts on the auto-start signal, energizes the emergency busses and the

permanently connected loads within 10 seconds after the auto-start signal, energizes the auto-

connected shutdown loads through the load sequencer and operates for greater than or equal

to 5 minutes while its generator is loaded with the shutdown loads. After energization, the

steady-state voltage and frequency of the emergency busses shall be maintained at

4160 +420, -240 volts and 60 +1.2, -0.3 Hz during this test.

The surveillance requirement for demonstrating operability is consistent with the

recommendations of Regulatory Guide 1.9, Selection of Diesel Generator Set Capacity for

Standby Power Supplies, Revision 4, March 2007. The licensee performs Operating

Procedure OP-903-115, Integrated Emergency Diesel Generator/Emergency Safety Features

Test - Train A, Revision 39, to accomplish this Surveillance Requirement.

Procedure OP-903-115 contains Component List(s) which identifies all the emergency safety

features loads required to auto-connect on the emergency diesel generator bus for both the

simulated loss-of-offsite power and the simulated loss-of-offsite power concurrent with a safety

injection actuation signal. In various steps, Procedure OP-903-115 directs the operators to

verify all components listed on the Component List are energized while performing the

various tests.

On May 23, 2017, Procedure OP-903-115 was performed without verifying all components on

the Component List were energized. Specifically, the surveillance test was performed

without verifying that the listed safety components, boric acid makeup pump B and dry cooling

tower fan 6A, auto-connected and were energized. In the test results, as documented in Work Order 52685292, the licensee acknowledged the components were not available because of

equipment issues and determined the test was satisfactory. On May 24, 2017, the licensee

initiated Condition Report CR-WF3-2017-04435 for the unavailable components, further

determining that the train A emergency diesel generator was operable because the addition of

the loads was within the capacity of the diesel generator.

Regulatory Guide 1.9, Revision 4, Section 2.2.5, LOOP Test, states that the loss-of-offsite

power test must demonstrate that the emergency diesel generator energizes all

auto-connected shutdown loads through the load sequencer. It further states, If the required

loads are not available, one or more equivalent load(s) may be used. Based on Regulatory

Guide 1.9, the inspectors determined that the licensee failed to perform a satisfactory

surveillance test, in accordance with Surveillance Requirement 4.8.1.1.2, because all auto-

connected loads were not energized and equivalent loads were not energized on the safety

bus when the licensee determined the components were not available. This resulted in a

missed surveillance, in accordance with Surveillance Requirement 4.0.3, and a failure to meet

Technical Specification Limiting Condition for Operation 3.8.1.1 when reactor startup

commenced on June 1, 2017.

Corrective Action(s): The licensee entered these issues into the corrective action program,

initiated the Surveillance Requirement 4.0.3 risk evaluation, and scheduled the performance of

Surveillance Requirement 4.8.1.1.2 at the first opportunity.

Corrective Action Reference(s): Condition Reports CR-WF3-2017-09106 and

CR-WF3-2017-09125

Performance Assessment:

Performance Deficiency: The team determined that the failure to perform the emergency

diesel generator surveillance test in accordance with written test procedures was a

performance deficiency.

Screening: This performance deficiency was more than minor, and therefore a finding,

because it was associated with the equipment performance attribute of the Mitigating Systems

Cornerstone and adversely affected the cornerstone objective to ensure the availability,

reliability, and capability of systems to respond to initiating events to prevent undesirable

consequences. Specifically, the failure to ensure all components would auto-connect did not

ensure that the emergency diesel generator and sequencer would be capable of carrying

required loads during an event.

Significance: In accordance with Inspection Manual Chapter 0609, Appendix A, The

Significance Determination Process (SDP) for Findings At Power, dated July 19, 2012, the

finding screened as having very low safety significance (Green) because it was a design or

qualification deficiency that did not represent a loss of operability or functionality; did not

represent an actual loss of safety function of the system or train; did not result in the loss of

one or more trains of non-technical specification equipment; and did not screen as potentially

risk-significant due to seismic, flooding, or severe weather.

Cross Cutting Aspect: This finding had a human performance cross-cutting aspect, associated

with challenge the unknown, because the licensee failed to stop when faced with uncertain

conditions. Specifically, individuals failed to stop work when it was determined that the

surveillance test procedure could not be performed as written [H.11].

Enforcement:

Violation: Waterford Steam Electric Station, Unit 3, Technical Specification 3/4.8.1, A.C.

Sources, Limiting Condition for Operation 3.8.1.1 which requires that two separate and

independent diesel generators shall be operable in Modes 1, 2, 3, and 4.

Contrary to the above, from June 1, 2017, to November 16, 2017, the licensee failed to

maintain two separate and independent diesel generators operable in Modes 1, 2, 3, and 4.

Specifically, the licensee failed to perform a satisfactory surveillance test on train A emergency

diesel generator, in accordance with Surveillance Requirement 4.8.1.1.2, because all auto-

connected loads were not energized and equivalent loads were not energized on the safety

bus when the licensee determined the components were not available.

Enforcement Action(s): This violation is being treated as a non-cited violation, consistent with

Section 2.3.2 of the Enforcement Policy.

Two Examples of Failure to Submit and Receive Prior Authorization of Alternatives to ASME

OM Code Leak Testing Requirements

Cornerstone

Significance

Cross-cutting

Aspect

Report

Section

Not Applicable

Severity Level IV

NCV 05000382/2017008-03

Closed

Not Applicable

71111.21M

The team identified two examples of a Severity Level IV, non-cited violation of

CFR 50.55a(z), for failure to submit and obtain authorization prior to implementation of

multiple alternatives to leak testing requirements of the American Society of Mechanical

Engineers (ASME) Operation and Maintenance (OM) of Nuclear Power Plants Code.

Description:

Example 1: Reactor coolant loop 2 hot leg injection check valve, SI-512B, is an ASME Code

Class 1, 3-inch swing check valve that is inservice testing Categories A and C with an active

safety function. During the teams inspection of Engineering Change 55752, Replace SI-512B

with a Swing Check Valve, the team reviewed completed work orders associated with leak

rate testing. ASME OM Code required leak rate testing for SI-512B is performed using

Procedure OP-903-008, Reactor Coolant System Isolation Leakage Test. The team noted

that the licensee had modified the procedure based on an evaluation performed in Engineering

Change 47766, Safety Injection Check Valve Leak Test Method, approved on January 8,

2014. The changes to the test methodology involved measuring the pressure rise downstream

of the valve and correlating that rise to a leak rate. If the pressure rise was less than

pounds per square inch, gauge, over a 30-minute period, the test result was considered

satisfactory and recorded as less than the acceptance criteria of 1 gallon per minute. If

pressure were to rise above 30 pounds per square inch, gauge, a leak rate would be obtained

by another test.

The team determined that this test did not conform to the leak testing requirements of the

ASME OM Code, Subsection ISTC, Inservice Testing of Valves, Paragraph ISTC-3630,

Leakage Rate for Other Than Containment Isolation Valves, and the licensee did not obtain

prior authorization for this alternative test. The team also observed that the alternative test did

not guarantee a valid leak rate result because it assumed another downstream check valve,

SI-510B, was leak tight and that the piping system downstream of SI-512B was water solid,

without the test verifying those assumptions. These observations called into question whether

or not the alternative test, as written, would have obtained a valid result.

Example 2: Safety injection sump outlet header A isolation valve, SI-602A, is a 24-inch

butterfly valve that is ASME Code Class 2 and inservice testing Category A with an active

safety function. The team reviewed completed work orders associated with leak rate testing.

Required leak rate testing for valve SI-602A is performed in accordance with

Procedure OP-903-128, Category A Leak Test. The team noted that the procedure allows for

two tests for determining SI-602A valve leakage, depending on whether or not a spool piece is

removed. One of the tests allows the use of a leak detection fluid. If no evidence of leakage

exists (i.e., bubbles), the test result is recorded as satisfactory and no further leak testing is

performed. If evidence of leakage exists, a leak rate is then obtained by another test.

The team determined that this test does not conform to the leak testing requirements of the

ASME OM Code, Subsection ISTC, Inservice Testing of Valves, Paragraph ISTC-3630,

Leakage Rate for Other Than Containment Isolation Valves, and the licensee did not obtain

prior authorization for this alternative test. Although the use of leak detection fluid is not

complicated, the team observed that the test did not provide specific instructions, for example,

as to how much fluid to use, how long to wait, or where to apply the fluid. These observations

called into question whether or not the alternative test, as written, would have obtained a valid

result.

Corrective Action(s): For SI-512B, the licensee performed an operability determination which

concluded that SI-512B met technical specification leakage rate acceptance criteria of

gallon per minute or less based on a review of the reactor coolant system leak rate program.

For SI-602A, an initial review conducted by the licensee identified that the last time the use of

leak detection fluid alone for the leakage rate test of SI-602A occurred in 2006. All other tests

since 2006 obtained leak rates by tests in compliance with the ASME OM Code and were less

than the specified leakage rate limit.

Corrective Action Reference(s): Condition Report CR-WF3-2017-09143 and

CR-WF3-2017-09201.

Performance Assessment:

The team determined that the failure to submit and receive prior authorization for alternatives

to leak testing requirements for safety injection valves SI-512B and SI-602A was a violation of

CFR 50.55a(z).

Screening: The team determined this violation was associated with a minor performance

deficiency.

Significance: The team determined the violation to be a Severity Level IV violation similar to

violation example 6.1.d.2 in the NRC Enforcement Policy.

Enforcement:

Severity: Because this violation affected the NRCs ability to perform its regulatory function,

the inspectors evaluated this violation using the traditional enforcement process in accordance

with the NRC Enforcement Policy, dated November 1, 2016. This violation was more than

minor because there was a reasonable likelihood the change would require NRC review and

approval prior to implementation, similar to violations assessed in Section 2.1.3 of the NRC

Enforcement Manual. The team determined the violation to be a Severity Level IV violation

similar to violation example 6.1.d.2 in the NRC Enforcement Policy.

Violation: 10 CFR 50.55a(z), Alternatives to codes and standards requirements, requires, in

part, Alternatives to the requirements of paragraphs (b) through (h) of this section or portions

thereof may be used when authorized by the Director, Office of Nuclear Reactor Regulation, or

Director, Office of New Reactors, as appropriate. A proposed alternative must be submitted

and authorized prior to implementation.

Paragraph (f) of 10 CFR 50.55a, Inservice testing requirements, requires, in part, Systems

and components of boiling and pressurized water cooled nuclear power reactors must meet

the requirements of the ASME BPV Code and ASME OM Code as specified in this paragraph.

Paragraph (4) of 10 CFR 50.55a(f), Inservice testing standards requirement for operating

plants, requires, in part, that Throughout the service life of a boiling or pressurized water-

cooled nuclear power facility, pumps and valves that are classified as ASME Code Class 1,

Class 2, and Class 3 must meet the inservice test requirements (except design and access

provisions) set forth in the ASME OM Code and addenda that become effective subsequent to

editions and addenda specified in paragraphs (f)(2) and (3) of this section and that are

incorporated by reference in paragraph (a)(1)(iv) of this section, to the extent practical within

the limitations of design, geometry, and materials of construction of the components.

Contrary to the above, prior to November 16, 2017, ASME Code Class 1 and 2 valves did not

meet the inservice test requirements of the ASME OM Code and the alternatives were not

submitted and authorized prior to implementation. Specifically, the licensee did not submit and

receive prior authorization to alternative leak testing requirements for safety injection

valves SI-512A and SI 602B, which are ASME Code Class 1 and 2 valves, respectively.

Enforcement Action(s): This violation is being treated as a non-cited violation, consistent with

Section 2.3.2 of the Enforcement Policy.

Unresolved Item

(Open)

Potential Failure to Obtain a License Amendment for

Changes to Diesel Generator Surveillance Test Interval

71111.21M

Description:

The team identified an unresolved item for the licensees failure to perform a 10 CFR 50.59

safety evaluation and subsequently obtain a license amendment for changes to the

surveillance testing frequency of the emergency diesel generators.

The licensees process for changing surveillance test intervals is controlled by Technical Specification 6.5.18, Surveillance Frequency Control Program. The licensees changes to

the surveillance test intervals are made in accordance with NEI 04-10, Risk Informed Method

for Control of Surveillance Frequencies, Revision 1, as written in procedure EN-DC-355,

Engineering Evaluation of Proposed Surveillance Test Interval Changes, Revision 2.

The team reviewed the licensees changes to the surveillance test interval, as required by

Technical Specification Surveillance Requirements 4.8.1.1.2.e, for emergency diesel

generators. The licensee changed the surveillance test interval for the train A and B

emergency diesel generators from both emergency diesel generators tested every 18 months

to each emergency diesel generator tested every 36 months. The team determined that

testing the emergency diesel generators once every 36 months was contrary to guidance in

Regulatory Guide 1.9, Application and Testing of Safety-Related Diesel Generators in

Nuclear Power Plants, Revision 4. Specifically, Section 2.3.2.3, Refueling Outage Testing,

requires the capability of the overall emergency diesel generator design should be

demonstrated during every refueling outage not exceeding a period of 24 months.

The team determined that the licensee did not correctly evaluate the change to the

surveillance interval in accordance with surveillance frequency control program change

process. Specifically, the licensee did not correctly evaluate NEI 04-10, step 1, Check for

Prohibitive Commitments, and step 2, Can Commitments be Changed? of the change

process. The team determined that this change would require a 10 CFR 50.59 safety

evaluation and subsequent license amendment because it would result in more than a

minimal increase in likelihood of a malfunction of a component important to safety as

previously described in the final safety analysis report. Specifically, the test interval would no

longer meet the applicable acceptance standard, Regulatory Guide 1.9, to which the licensee

is committed.

Planned Closure Action(s): The NRC inspectors will review the final corrective actions,

pending NRC resolution of applicability of 10 CFR 50.59 to the surveillance frequency control

program.

Licensee Action(s): Prior to this inspection, the licensee identified this 10 CFR 50.59 issue in

the corrective action program because of industry operating experience. At the time of this

inspection, the licensee had not completed the final corrective action and 10 CFR 50.59

activities. These corrective actions will be completed once industry guidance on the NRC

resolution of applicability of 10 CFR 50.59 to the surveillance frequency control program was

available.

Corrective Action Reference(s): Condition Reports CR-WF3-2017-05590 and

CR-WF3-2017-5602

NRC Tracking Number: 05000382/2017008-04

EXIT MEETINGS AND DEBRIEFS

The inspection team verified no proprietary information was retained or documented in this

report.

On November 16, 2017, the team presented the preliminary results of the Inspection

Procedure 71111.21M inspection to Mr.

J. Dinelli, Senior Vice President, and other members

of the licensee staff.

On December 14, 2017, the team presented the final results of the Inspection

Procedure 71111.21M inspection to Mr.

D. Brenton, General Manager-Plant Operations, and

other members of the licensee staff.

LIST OF DOCUMENTS REVIEWED

Calculations

Number

Title

Revision/Date

ECC99-008

TORMIS ANALYSIS: Tornado Generated Missile Strike at

Waterford 3

ECE89-008

Electrical Design Criteria

ECE90-006

EDG Loading and Fuel Oil Consumption

ECE91-016

Battery 3AB-S Cell Sizing

ECE91-055

AC Short Circuit Calculations

ECE91-056

Relay Settings and Coordination Curves for 6,9KV, 4.16KV

and 480 Volt Buses

ECE91-060

Battery 3AB-S SBO

ECE91-195

Load Study for PDP 3AB-DC-S, 346AB, 346AB-1 and 3FDAB 2

ECE91-252

Short Circuit Study for 3AB-S

ECE93-003

Voltage at Motor-Operated Valve

February 12,

1994

ECE9I-050

Degraded Voltage Relay Set-point & Plant Load Study

ECI01-007

Determination of ECCS Measurement Channels Functional

Safety Significance

ECI92-019

Plant Protection System Uncertainty Calculation

ECI93-058

Transmitter Uncertainties

ECI95-011

HPSI Cold Leg Injection Flow Instrumentation Loop

Uncertainty Calculation

ECI99-001

ESF Response Time Acceptance Criteria Basis

ECM00-004

Emergency Feedwater Turbine Steam Supply RELAP Model

ECM05-003

High Pressure Safety Injection System Capacity

ECM07-001

NPSH Analysis of Safety Injection and Containment Spray

Pumps

ECM89-018

SI 602 A&B Pressure Requirements

ECM91-011

NPSH for Safeguard Pumps in Recirculation with

Valve SI-106A(B) Failed Open

ECM92-037

MOV Design Basis Review Calculation No. SI.002

ECM92-042

MOV Design Basis Review Calculation MS-401A&B

ECM97-022

Wet Cooling Tower Makeup requirements

A

Calculations

Number

Title

Revision/Date

ECS04-019

Risk Assessment of Sl-6028 Not Fully Closed

ECS91-016

SI-602 Leakage Study

ECS98-015

Containment P&T Response Analysis

EE2-12-05

4.16KV Switchgears High Resistance Grounding

EE2-16-06

Station Service Transformer Impedance and MCC Bus

Reactor Calculation

HVAC-059

Battery Room Air Flow Required To Limit Hydrogen

Concentration To 1%

HVAC-070

Hydrogen Generation By Station Batteries

IM1024

Piping Stress Qualification for IM1024 due to Replacement of

Valve SI-512B

MN(Q)-6-29

SIS Maximum Operating Suction Pressure

MNQ9-17

Tornado Multiple Missile Protection of Cooling Towers

MNQ93

Heat Removal Capacities of DCT and WCT After LOCA

SQ-MN-352

- 2500# FLOWSERVE Check Valve

SQ-MN-370

Size 3 Class 2500 (CF8M) Swing Check Valve

Drawings

Number

Title

Revision/Date

2-441-0653-3

SMB-00 & 000 STANDARD UNITS WITH: A1 H0BC-

H3BC WORM GEAR ASSEMBLY B1 SEISMIC

SUPPORT BRACKET

February 20,

1987

2B8124

BODY SMB-00-HBC2 ACTUATOR LIMITORQUE -

200 ELECTRIC ACTUATED CONTROL VALVE

B

75B70058, Sh.16 Electrical Diagram 52 Control CKT

75B70058, Sh.17 Electrical Diagram 52 Control CKT

75D700340, Sh.

Connection Diagram

75D701437

Indoor AKD-5 Power Master SWGR

B-289, Sh. 110

Power Distribution and Motor Data Panel 3AB-DC-S

B-289, Sh. 110A

Power Distribution and Motor Data Panel 3AB-DC-S

B-289, Sh. 157

Power Distribution and Motor Data 480V SWGR Front

View

Drawings

Number

Title

Revision/Date

B-289, Sh. 16

Power Distribution and Motor Data 4.16KV SWGR 3B3-S

One-line Diagram

B-289, Sh. 16-1

Power Distribution and Motor Data 4.16KV SWGR 3B3-S

One-line Diagram

B-289, Sh. 16A

Power Distribution and Motor Data 4.16KV SWGR 3B3-S

Protective Relay Settings

B-289, Sh. 20

Power Distribution and Motor Data 480V SWGR 3A31-S

One-line Diagram

B-289, Sh. 21

Power Distribution and Motor Data 480V SWGR 3B31-S

One-line Diagram

B-289, Sh. 21-1

Power Distribution and Motor Data 480V SWGR 3B31-S

One-line Diagram

B-289, Sh. 22

Power Distribution and Motor Data 480V SWGR 3AB31-S

One-line Diagram

B-289, Sh. 22-1

Power Distribution and Motor Data 480 SWGR 3AB31-S

One-line Diagram

B-424, Sh. 1535

Emergency FW Pump Turbine Steam Shut-off Valve 611

B-424, Sh. 1541

Emergency FWPT Governor Valve

B-424, Sh. 2389S Control Wiring Diagram, 480V MCC 3B31-S Undervoltage

Relays Sh.1

B-424, Sh. 2390

Control Wiring Diagram, 480V Bus 3B31-S Undervoltage

Relays Sheet 2

B-424, Sh. 2390S Control Wiring Diagram, 480V Bus 3B31-S Undervoltage

Relays Sheet 1

B-424, Sh. 2397S Control Wiring Diagram, Station Services Transformer

3B31-S Feeder

B-424, Sh. 2410S Control Wiring Diagram, 480V Bus 3AB31-S Undervoltage

Relays Sh.1

B-424, Sh. 2506S Control Wiring Diagram, 480V MCC 3B313-S Feeder

B-424, Sh. 2507S Control Wiring Diagram, 480V MCC 3B314-S Feeder

B-424, Sh. 2925

Control Wiring Diagram, Annunciator Display Cabinet D

CP-1

B-424, Sh. 3016S Control Wiring Diagram - EFAS Test Module Channel A

B-424, Sh. 3017S Control Wiring Diagram - EFAS Test Module Channel A

B-424, Sh. 509

Control Wiring Diagram, High Pressure Safety Injection

Pump B

Drawings

Number

Title

Revision/Date

B-424, Sh. E1535 Control Wiring Diagram - Emergency Feedwater pump

Turbine Shutoff Valve VA 2MS-V611a

B-424, Sh. E509

Control Wiring Diagram, High Pressure Safety Injection

Pump B

G-167, Sh. 1

Safety Injection System Flow Diagram

July 8, 1991

G-167, Sh. 2

Safety Injection System Flow Diagram

July 8, 1991

G-250S07

Reactor Aux. Bldg. El. -35.00 Conduit Details & Sections

G-285

Main One Line Diagram

G-286

1977-1165 MW Installation Key Auxiliary One Line

Diagram

G-287, Sh. 1

25VDC and 120VAC One Line Diagram

G-317-S01

Reactor Aux Bldg. - El. +7.00 Conduit, Trays &

Grounding - Sh.1

G-329

Reactor Aux. BLDG-El-4.00 Conduit, Trays and

Grounding, Sh. 4

G-335-S01

Reactor Auxiliary Building - EL-35.00 Conduit, Tray &

Grounding-Sh. 3

G-344-S01

Electrical Equipment Room SWGR, MCC & Panel Detail

Sh. 1

T025W2000HM, Type O Plus C, IEEE, Condenser Bushing

Procedures

Number

Title

Revision/Date

01-002-000

Annunciator and Control Room Instrumentation Status Control 309

ECT-64802

Emergency Feedwater Control Valves EFWMVMA 224B and

EFWMVAAA223A

ECT-64803

Emergency Feedwater Control Valves EFWMVAAA 224A and

EFWMVAAA223B

EN-AD-101

NMM Procedure Process

EN-DC-115

Engineering Change Process

EN-DC-115

Engineering Change Process

EN-DC-153

Preventative Maintenance Component Classification

EN-DC-310

Predictive Maintenance Program

EN-DC-324

Preventive Maintenance Program

Procedures

Number

Title

Revision/Date

EN-DC-335

PM Basis Template

EN-DC-355

Engineering Evaluation of Proposed Surveillance Test Interval

change

EN-LI-101

CFR 50.59 Evaluations

EN-LI-102

Corrective Action Program

EN-MA-101

Conduct of Maintenance

EN-MA-101-

Maintenance Work Preparation Process

EN-MA-119-01 Control, Storage, and Inspection of Lifting Equipment

EN-OP-104

Operability Determination Process

EN-WM-105

RAB Train "AB" Thermography Route

June 21,

2011

ME-001-012

Temporary Power from Temporary Diesel for 3A2 and 3B2 4kV

Buses (MODES 1-6)

313

ME-003-210

Performance Test on DC Battery

ME-003-230

Battery Service Test

315

ME-003-240

Performance Test on DC EBATAB Battery

313

ME-003-301

480 VAC Overcurrent Protective Integrated Device Functional

Test

ME-003-327

4.16 kV G.E. Magne-Blast Breaker

ME-003-330

480 Volt GE Switchgear Breakers

310

ME-003-410

Motor-Operated Valve Thermal Overload Channel Calibration

311

ME-004-021

Emergency Diesel Generator

ME-004-061

Unit Auxiliary Transformer

308

ME-004-115

4.16/6.9 kV G.E. Magne-Blast Breaker Overhaul

ME-004-141

Low Voltage Switchgear

2

ME-004-142

480 Volt GE Switchgear AKR Breaker Overhaul

ME-004-161

Low Voltage Power Distribution Panels

ME-004-211

Station Battery Quarterly

ME-007-043

Viper Testing of MOVs

ME-007-047

VOTES Testing of MOVs

Procedures

Number

Title

Revision/Date

ME-007-073

Testing Procedure, Unit Auxiliary Transformer Power Factor

Testing

MI-003-219

Plant Protection System Sensor Bi-stable Response Time

Verification Channel A, B, C, or D

301

MI-003-222

Matrix Response Time Verification for Reactor Protection

System and Engineered Safety Features Actuation System

Channels A, B, C, or D

307

MI-003-302

Containment Pressure (Narrow Range) Loop Check and

Calibration CB IP6701 SMA, SMB, SMC, or SMD

304

MI-003-316

Pressurizer Pressure (Wide Range) Loop Check and

Calibration RC IP0102 A, B, C, or D

2

MI-003-514

Emergency Feedwater Control Loop Check and Calibration

311

MI-003-515

Emergency Feedwater Control Loop Check and Calibration

309

MI-005-204

Calibration of Temperature Instruments

MI-005-464

Plant Protection System Power Supply Calibration

305

MI-005-705

Engineered Safety Features Actuation System Auxiliary Relay

Cabinet 3A or 3B Power Supply and Ground Detector Test

301

MI-013-522

PPS Ground Detection Test

MM-006-053

Check Valve Inspection (Swing)

OP-002-007

Freeze Protection and Temperature Maintenance

OP-006-001

Plant Distribution (7KV, 4KV and SSD) System

26

OP-009-002

Emergency Diesel Generator

341

OP-009-008

Safety Injection System

OP-100-014

Technical Specification and Technical Requirements

Compliance

337, 341

OP-500-004,

Attach. 4.113

480V Bus SB Bkr Trip/Trouble

OP-500-004,

Attach. 4.85

SS Xfmr. 3B31-S Ground/Temp Hi

OP-500-011

Control Room Cabinet M

OP-500-012

Control Room Cabinet N

OP-500-013

Control Room Cabinet SA

OP-500-014

Control Room Cabinet SB

OP-901-521

Severe Weather and Flooding

25

Procedures

Number

Title

Revision/Date

OP-902-002

Loss of Coolant Accident Recovery

OP-903-008

Reactor Coolant System Isolation Leakage Test

OP-903-011

High Safety Injection Pump Operability Check

OP-903-029

Safety Injection Actuation Signal Test

OP-903-030

Safety Injection Pump Operability Verification

OP-903-033

Cold Shutdown IST Valve Tests

OP-903-066

Electrical Breaker Alignment Check

2

OP-903-094

ESFAS Subgroup Relay Test - Operating

OP-903-095

ESFAS Subgroup Relay Test - Shutdown

OP-903-100

MOV Overload Bypass Test

310

OP-903-107

Plant Protection System Channel A B C D Function Test

310

OP-903-108

SI Flow Balance Test

OP-903-108,

Att. 10.3

Completed Flow Balance for HPSI Pump B

OP-903-115

Integrated Emergency Diesel Generator/Emergency Safety

Features Test - Train A

OP-903-116

Train B Integrated Emergency Diesel Generator/ Engineering

Safety Features Test

OP-903-128

Category A Leak Test

SEP-ISI-104

ASME SECTION XI, DIVISION I INSERVICE INSPECTION

PROGRAM

SEP-WF3-

IST-1

WF3 INSERVICE TESTING BASES DOCUMENT

SEP-WF3-

IST-2

WF3 INSERVICE TESTING PLAN

SEP-WF3-

IST-3

WF3 INSERVICE TESTING CROSS REFERENCE

DOCUMENT

UNT-006-033

Technical Specifications Surveillance Frequency List

W2.109

Procedure Development, Review and Approval

Engineering Changes

Number

Title

Revision/Date

EC 31892

Documentation of Waterford 3's Response to NRC Generic

Letter No. 96-01 "Testing of Safety-Related Logic Circuits"

EC 40828

Evaluation of Replacement Bushing for UAT

EC 44782

Emergency Diesel Generator Governor Upgrade

April 23, 2014

EC 47766

Safety Injection Check Valve Leak Test Method OP-903-008

EC 53772

Issue Markup to ECC99-008 For EDG Lines (Tormis) not

Protected for Tornado Missiles

EC 54307

Leak Repair of EDG Fuel Oil Feed Tank Vent Pipes

EC 55752

Replace SI-512B with a Swing Check Valve

EC 59135

Child EC For SI-512B Hard Seat Option

EC 61267

EDG Day Tank Vent Lines Installation Clarification

EC 64801

Emergency Feedwater Circuitry Modification

Environmental Qualification Documents

Number

Title

Revision

EC 40278

Mark-up of LPLEQA8.1D LPLEQA8.1C

EC 59039

Mark-up of EQMI-8.1 LPLEQA8.1D

EC 73625

Mark-up of EQMI-8.1

LPL-EQA08.01C Rosemount 1153 Series D Transmitters

LPL-EQA-8.01D

Rosemount Model 1154 Series H Transmitters

LPL-EQA-8.01D

Rosemount Model 1154 Series H Transmitters

LPL-EQA-8.0I

Rosemount Model 3154N Transmitters

LPL-EQMI-08.01 Rosemount Model 1153 Series A, B &D, 1154 &1154

Series H Transmitters and 1159 Remote Seals

LPL-EQMI-8.01B Rosemount Model 3152N, 3153N, and 3154N Series

Transmitters and 3159 Remote Seals

Vendor Documents

Number

Title

Revision/Date

15-111494-001

SWING CHECK VALVE STAINLESS STEEL. NOREM

TRIM BUTT WELD ENDS. SIZE: 3 CLASS: 2500

Form 2432

Instruction Manual Type 9200 T-Ring Butterfly Valve

Bodies

March 1974

Vendor Documents

Number

Title

Revision/Date

GEK-721

Instructions for Type AKD-6 Low voltage

August 1977

Letter-C&D

Technologies

Battery Cover Crack

May 15, 2013

Lou-1564.261-B

Ebasco Purchase Specification for Metal-Enclosed

600Volt Class Draw-out type Class 1E Buses 3A31-S,

3B31-S, 3AB31-S, Transformer 3A315-S, 3B315-S & Non-

Class 1E Buses 3A32, 3B32

RAL-21146

Design and Seismic Analysis Report (Size 3 Class 2500

(CF8M) Swing Check Valve Drawing 15-111494-001)

RS-1476

Standby Battery Vented Cell Installation and Operating

Instruction

TD-A1800.0095

Allis-Chalmers Installation Operation Maintenance

Instruction Induction Motors/Generators Horizontal 500,

580, 30 Frames M3514-02

October 31,

1996

TD-F994.0085

Swing check Valve, Size 3 Class 2500 Operation and

Maintenance Manual

TD-G080,0735

General Electric Important Instructions for Armor-Clad

Indoor Feeder Busway, GEH-2636

TD-G080.0625

General Electric Station Service Ventilated Dry

Transformer

TD-G080-0095

General Electric Switchgear Magne-Blast Breaker

TD-G080-0145

GE Low Voltage Switchgear Tech Manual

TD-L200.0055

LIMITORQUE VALVE CONTROLS TYPE SB-1 AND SMB

AND 00 FOR OPERATING AT HIGH TEMPERATURE

TD-S440.0015

Struthers Dunn Type A112 & 112 Relays

July 31, 1997

TD-W120.3115

Westinghouse MCCB AB De-ion breaker

TD-W120.3135

Westinghouse MCCB

TD-W120.3145

Westinghouse Tri-Pac Breaker

April 1976

W290.0055

2301A Load Sharing and Speed Control

W290.0065

Digital Reference Unit

W290.0075

EDG Proportional Governor/Actuator

Design Basis Documents

Number

Title

Revision

W3-DBD-001

Safety Injection System

305

Design Basis Documents

Number

Title

Revision

W3-DBD-002

Emergency Diesel Generator & Automatic Load

Sequencer

305

W3-DBD-003

Emergency Feedwater System

2

W3-DBD-006

Main Steam System

W3-DBD-008

Electrical Distribution (DC Portion)

W3-DBD-009

Reactor Coolant System & Steam Generator Blowdown

System

304

W3-DBD-011

Electrical Distribution (AC Portion)

W3-DBD-012

Plant Protection System Design Basis Document

W3-DBD-014

Safety Related, Air Operated Valves

303

W3-DBD-026

Containment Isolation and Leakage Rate Testing

Quality Assurance Audit Reports

Number

Title

Date

QA-4-2016-W3-1 Engineering (Design Control)

April 14, 2016

QA-8-2017-W3-1 Engineering Programs

March 13, 2017

QA-8-2017-W3-2 Engineering Programs

April 25, 2017

Miscellaneous

Number

Title

Revision/Date

CN7C7244

Connection To Auxiliary Transformer

DC

System Health Report, 125VDC Distribution

Q2-2017

EG

System Health Report, Emergency Diesel Generator

Q2-2017

EN-Motor

EN-Motor-Medium Voltage (>600V/<15KV)

ER-W3-2004-

0575-001

Reclassify SI-602 A & B as IST Category A

LO-WLO-2017-

00011

2017 Pre NRC DBAI Focus Self-Assessment

October 10, 2017

Procurement

Eval. 00155992

Switch, Temperature Hot Spot, Indicating

---

SD-CC

Component Cooling Water System Description

SD-SI

Safety Injection

Miscellaneous

Number

Title

Revision/Date

SPEC-15-00002-

W

Reactor Coolant Hot Leg Injection Check Valve SI

MVAAA512 B Replacement

SSD

SSD - 480V Station Service Distribution

Q2-2017

STI 17-001

Integrated EDG/ESF Test

WLP-OPS-DG00 Emergency Diesel Generator Training

Condition Reports

CR-WF3-

2014-05582

CR-WF3-

2014-05662

CR-WF3-

2014-05690

CR-WF3-

2014-05131

CR-WF3-

2016-01754

CR-WF3-

2017-01231

CR-WF3-

2017-04865

CR-WF3-

2017-07888

CR-WF3-

2017-08621

CR-WF3-

2017-08618

CR-WF3-

2017-08589

CR-WF3-

2017-08448

CR-WF3-

2015-05792

CR-WF3-

2016-05473

CR-WF3-

2017-02670

CR-WF3-

2017-07682

CR-WF3-

2015-06557

CR-WF3-

2016-05478

CR-WF3-

2017-02727

CR-WF3-

2017-06067

CR-WF3-

2015-07737

CR-WF3-

2017-02633

CR-WF3-

2017-04436

OE-NOE-

2005-00338

CR-WF3-

2017-06067

CR-WF3-

2014-05529

CR-WF3-

2014-05341

CR-WF3-

2014-05413

CR-WF3-

2014-05690

CR-WF3-

2017-07223

CR-WF3-

2014-05131

CR-WF3-

2004-02847

CR-WF3-

1998-00516

CR-WF3-

2015-04850

CR-WF3-

2008-05183

CR-WF3-

2017-07462

CR-WF3-

2015-04850

CR-WF3-

2008-05183

CR-WF3-

2017-05602

CR-WF3-

2017-5590

CR-WF3-

2017-04435

CR-WF3-

2017-0572

CR-WF3-

2017-7462

CR-WF3-

2017-03768

CR-WF3-

2016-07647

CR-WF3-

2016-07921

CR-WF3-

2016-04038

CR-WF3-

2016-04038

CR-WF3-

2015-07975

CR-WF3-

2015-05346

CR-WF3-

2015-07907

CR-WF3-

2015-06950

CR-WF3-

2009-05400

CR-WF3-

2014-05458

CR-WF3-

2017-01148

CR-WF3-

2017-01055

CR-WF3-

2017-01045

CR-WF3-

2017-01046

CR-WF3-

2017-01047

CR-WF3-

2014-05369

CR-WF3-

2014-05131

CR-WF3-

2014-05841

Condition Reports Generated During this Inspection

CR-HQN-

2017-01724

CR-HQN-

2017-01906

CR-WF3-

2017-07462

CR-WF3-

2017-08432

CR-WF3-

2017-08448

CR-WF3-

2017-08511

CR-WF3-

2017-08518

CR-WF3-

2017-08519

CR-WF3-

2017-08521

CR-WF3-

2017-08559

CR-WF3-

2017-08568

CR-WF3-

2017-08572

Condition Reports Generated During this Inspection

CR-WF3-

2017-08574

CR-WF3-

2017-08580

CR-WF3-

2017-08582

CR-WF3-

2017-08583

CR-WF3-

2017-08585

CR-WF3-

2017-08589

CR-WF3-

2017-08606

CR-WF3-

2017-08611

CR-WF3-

2017-08616

CR-WF3-

2017-08618

CR-WF3-

2017-08621

CR-WF3-

2017-08627

CR-WF3-

2017-08632

CR-WF3-

2017-08634

CR-WF3-

2017-08635

CR-WF3-

2017-08678

CR-WF3-

2017-08680

CR-WF3-

2017-08689

CR-WF3-

2017-08737

CR-WF3-

2017-08757

CR-WF3-

2017-08940

CR-WF3-

2017-08962

CR-WF3-

2017-08982

CR-WF3-

2017-08983

CR-WF3-

2017-09093

CR-WF3-

2017-09106

CR-WF3-

2017-09107

CR-WF3-

2017-09108

CR-WF3-

2017-09125

CR-WF3-

2017-09132

CR-WF3-

2017-09140

CR-WF3-

2017-09143

CR-WF3-

2017-09144

CR-WF3-

2017-09164

CR-WF3-

2017-09165

CR-WF3-

2017-09185

CR-WF3-

2017-09201

Work Orders

WR37471

2694

15069

27321 01

44570 01

48893 01

53699

57714 01

24211 01

25122 01

27292

153521 01

154929 01

183024 01

183173 01

2639 01

263714

263714

309077

357372

395966

396915

411850

411921

50010020

51523197 01

51523197 04

51523197 06

51655055 01

51663303 01

51663303 01

2320766 01

2333000 01

2369790

2369908 01

2433042

2442300

2475662

2475662

2485562 01

2496264 01

2504349 01

2505058 01

2507904 01

2507904 02

2514258 01

2523350 01

2534002

2550025

2570374 01

2577433

2581739 01

2591365 01

2610648

2610648

2628265

2645751

2647626

2655753 01

2679221 01

2680941

2683228

2683228

2685151

2737542 01

ADDITIONAL REQUESTS

Paperwork Reduction Act Statement

This letter does not contain new or amended information collection requirements subject

to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information

collection requirements were approved by the Office of Management and Budget, control

number 3150-0011. The NRC may not conduct or sponsor, and a person is not required to

respond to, a request for information or an information collection requirement unless the

requesting document displays a currently valid Office of Management and Budget control

number.

Modification Selections

Number

Title

System Inspector

40828

EVALUATION OF REPLACEMENT BUSHINGS FOR UAT

N Okonkwo

44782

EDG GOVERNOR UPGRADE (BASE EC)

EG

S Gardner

46556

CC ISV0807A SOLENOID PREVENTATIVE

MAINTENANCE EQUIVALENCY

CC

J Braisted

55752

REPLACE SI-512B WITH A SWING CHECK VALVE

SI

J Braisted

63801

Emergency Feedwater Circuitry Modification

EFW

C Baron

LBDCR Change to OP-100-014 Revision 337, Ultimate Heat

Sink

UHS

C Baron

EC 530

Ultimate Heat Sink Water Replenishment for Tornado Event

UHS

C Baron

Component Selections

No. Component

Inspector

Turbine Emergency Feedwater Steam Supply Valves, MSMVAAA401A

AND 401B, (DC valves)

C Baron

25V dc Bus 3AB-DC-S

S Gardner

High Pressure Safety Injection Pump B and Motor

C Baron

Sump Outlet Motor-Operated Valve Safety Injection SI-602A

J Braisted

480 Vac Class 1E switchgear, Bus 3B31S

N Okonkwo

Containment isolation System/Actuation System

G George

Operating Experience

Number

Title

Inspector

IN 2013-05

Battery Expected Life and its Potential Impact

on Surveillance Requirements

S Gardner

IN 2014-03

Turbine-Driven Auxiliary Feedwater Pump

Overspeed Trip Mechanism Issues

A Athar

GL 88-03

Resolution of Generic Safety Issue 93, "Steam

Binding of Auxiliary Feedwater Pumps"

A Athar

Problem Identification CRs

CR

Subject

Inspector

Diesel generator day tank degradation

Jon Braisted

3B31 issue

Nnaerika Okonkwo

Additional Requests

1. Please create an item (link) in Certrec for each component listed.

2. Provide the following documents for each component, in addition to Section II of the RFI:

a. Preventive maintenance, surveillance, and test procedures; and

normal/abnormal/emergency operating procedures.

b. Frequency of preventive maintenance.

c. A List with brief description of corrective action documents for previous 3 years.

Provide an additional list of operability evaluations which discuss degraded or

nonconforming conditions.

d. Vendor Manuals.

3. Please the following program procedures in one certrec item:

a. Corrective Action Program

b. Operability Determinations

c. Engineering Change

d. Procedure Change

e. 50.59 Procedures

f.

Preventive Maintenance Programs

4. Please provide electronic copies of the following CRs and corrective actions in one

certrec item:

2014-5162

2014-5375

2014-5414

2014-5446

2014-5662

2014-5173

2014-5377

2014-5417

2014-5448

2014-5670

2014-5175

2014-5384

2014-5419

2014-5450

2014-5690

2014-5212

2014-5385

2014-5420

2014-5452

2014-5704

2014-5213

2014-5388

2014-5421

2014-5458

2014-5708

2014-5224

2014-5390

2014-5422

2014-5497

2014-5714

2014-5304

2014-5392

2014-5423

2014-5520

2014-5720

2014-5341

2014-5407

2014-5429

2014-5529

2014-5725

2014-5343

2014-5412

2014-5441

2014-5582

2014-5730

2014-5374

2014-5413

2014-5445

2014-5584

2014-5732

ML17362A424

SUNSI Review

ADAMS:

Non-Publicly Available

Non-Sensitive

Keyword:

By: GGeorge

Yes No

Publicly Available

Sensitive

NRC-002

OFFICE

SRI:EB1

RI:EB1

RI:EB2

SRTI:TTC

ROE:NRR/IPAB

C:PBD

NAME

GGeorge

JBraisted

NOkonkwo

GCallaway

AAthar

GMiller

SIGNATURE

/RA/

/RA/

/RA/

/RA/

/RA/

/RA/

DATE

2/26/17

2/21/17

2/26/17

2/20/17

2/27/17

2/27/17

OFFICE

C:EB1

NAME

TFarnholtz

SIGNATURE

/RA/

DATE

2/28/17