WF3 Cpcs Installation Inspection Plan Email
ML22108A179
Person / Time
Site: Waterford Entergy icon.png
Issue date: 04/14/2022
From: Shiattin Makor
NRC/RGN-IV/DORS/EB2
To: Champagne J, Harris A, Talazac C
Entergy Operations
References
Download: ML22108A179 (2)


Text

From:

Makor, Shiattin To:

HARRIS, ALAN J; Champagne, Jacob A; TALAZAC, CHRISTOPHER P; Truss II,William Wallace

Subject:

WF3 CPCS Installation Inspection Plan Date:

Thursday, April 14, 2022 6:57:00 AM Attachments:

WF3 CPCS RF24 Inspection Plan.pdf Mr. Harris,

This e-mail serves to document that the United States (U.S.) Nuclear Regulatory Commission (NRC) staffs plan to perform an inspection of Waterford Steam Electric Station, Unit 3 (WF3) Core Protection Calculator (CPCS) Digital Upgrade and transmit the inspection plan to support preparation for the CPCS Installation Inspection scheduled to begin the week of May 2, 2022.

This inspection activity falls under IMC 2515, Appendix C, Special and Infrequently Performed Inspections and will use IP 52003, Digital Instrumentation and Control Modification. IP52003 is not a baseline ROP inspection, rather it is a Special and Infrequently Performed Inspection (IMC 2515 Appendix C). Details of the requested materials were previously requested for the Factory (Adams Ascension ML21195A066) and Site Acceptance Testing Inspection (Adams Ascension ML21285A024). For the Installation Inspection, please make sure the requested materials previously made available in electronic format using the online document portal are the most recent versions. If you have any questions, please contact me at the phone number listed below to discuss alternative options.

Regards,

Shiattin Makor, Senior Reactor Inspector US Nuclear Regulatory Commission Division of Reactor Safety, Engineering Branch 2 Email: shiattin.makor@nrc.gov Phone: 817-200-1507 Cell: 214-293-8800

This e-mail does not contain new or amended information collection requirements subject to thePaperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collectionrequirements were approved by the Office of Management and Budget, Control Number 31500011. The NRC may not conduct or sponsor, and a person is not required to respond to, a request for information or an information collection requirement unless the requesting document displays a currently valid Office of Management and Budget control number.

Confidential Notice: This email, including all attachments, may constitute a Federal Record or other Government property that is intended only for the use of the individual or entity to which it is addressed. This email also may contain information that is privileged, confidential, or otherwise protected from disclosure under applicable law. If you are not the intended recipient or the employee or agent responsible for delivering the transmission to the intended recipient, you are hereby notified that any dissemination, distribution, copying or use of this email or its contents is strictly prohibited. If you have received this email in error, please notify the sender by responding to

the email and then immediately delete the email.

Shiattin Makor, Reactor Inspector US Nuclear Regulatory Commission Division of Reactor Safety, Engineering Branch 2 Email: shiattin.makor@nrc.gov Phone: 817-200-1507 Cell: 214-293-8800