Notice of Violation from Insp on 871102-06.Violation Noted: Emergency Diesel Generator Test Data Logs Not Completed as Specified in 850909 Operations Dept Memo
ML20236X828
Person / Time
Site: Farley  Southern Nuclear icon.png
Issue date: 12/04/1987
From: Herdt A
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML20236X820 List:
References
50-348-87-31, 50-364-87-31, NUDOCS 8712100298
Download: ML20236X828 (2)


Text

.  ;

i ENCLOSURE 1 i 1

NOTICE OF VIOLATION I

Alabama Power Company Docket Nos. 50-348 and 50-364 I i Farley Units 1 & 2 License Nos. NPF-2 and NPF-8 During the Nuclear Regulatory Commission (NRC) inspection conducted on November 2-6, 1987, a violation of NRC requirements was identified. In accordance with the " General Statement of Policy and Procedure for NRC Enforcement Actions," 10 CFR Part 2, Appendix C (1987), the violation is listed 1 below:

Technical Specification (TS) 6.8.1.c requires that written procedures be established, implemented, and maintained covering surveillance and test activities of safety-related equipment. Farley Nuclear Piant (FNP)

Administrative Procedure, FNP-0-AP-16, " Conduct of Operation" allows operations memorandum be used as a vehicle for disseminating information or instructions relative to the conduct of operations. FNP Intra Department Memorandum dated September 9,1985, provides instructions for filling out Emergency Diesel Generator (EDG) Test Data Logs in order to comply with NRC Regulatory Guide 1.108 requirements.

Contrary to the above, the EDG Test Data Logs from October 1985 to present were not completed as specified in the September 9,1985, Operations Intra Department Memorandum. Examples of omissions include not logging reasons for invalid EDG tests and failures, not logging EDG start times, and not properly logging reasons for EDG starts.

In addition, the Intra Department Memorandum is incorrect in that Criteria B(b) of the memorandum does not comply with NRC Regulatory Guide 1.108 for evaluation of valid and invalid EDG tests and failures. Adherence to this memorandum could result in an improper evaluation of a EDG test and failure.

This is a Severity Level IV violation (Supplement I).

Pursuant to the provisions of 10 CFR 2.201, Alabama Power Company is hereby required to submit a written statement or explanation to the Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555, with a copy to the Regional Administrator, Region II, and a copy to the NRC Resident Inspector, within 30 days of the date of the letter transmitting this Notice.

This reply should be clearly marked as a " Reply to a Notice of Violation" and should include [for each violation]: (1) admission or denial of the violation, (2) the reason for the violation if admitted, (3) the corrective steps which have been taken and the results achieved, (4) the corrective steps which will be taken to avoid further violations, and (5) the date when full compliance 8712100298 871204 PDR G ADOCK 05000348 PDR

o

)

r.

Alabama Power Company 2 Docket Nos. 50-348 and 50-364 Farley Units 1 & 2 License Nos. NPF-2 and NPF will be achieved. Where good cause is shown, consideration will be given to extending the response time. If an adequate reply is not received within the time specified in this Notice, an order may be issued to show cause why the license should not be modified, suspended, or revoked or why sud other action as may be proper should not be taken.

FOR THE NUCLEAR REGULATORY COMMISSION OR1 Git 4AL 5 pH R. HERDT Alar. R. Herdt, Chief Engineering Branch Division of Reactor Safety Dated at Atlanta, Georgia this ( day of December 1987 I

)