ML20148K651

From kanterella
Jump to navigation Jump to search
Insp Repts 50-348/97-05 & 50-364/97-05 on 970330-0510. Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support
ML20148K651
Person / Time
Site: Farley  Southern Nuclear icon.png
Issue date: 06/09/1997
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML20148K635 List:
References
50-348-97-05, 50-348-97-5, 50-364-97-05, 50-364-97-5, NUDOCS 9706180232
Download: ML20148K651 (44)


See also: IR 05000348/1997005

Text

w.m.

,g..

._...~m.6...u

...,.._.._a.m_~.-#w.e4.-~.-_e.

--

- * - - -

-

- + -

-

4-..

  • . - -

-*A-u

e.-n*~~

~ - +

'

.

t

-

.

,

U.S. NUCLEAR REGULATORY COMMISSION (NRC)

REGION II

l

t

Docket Nos:

50-348 and 50-364

j

License Nos:

NPF-2 and NPF-8

Report No:

50-348/97-05 and 50-364/97-05

i

'

Licensee:

Southern Nuclear Operating Company Inc.

,

Facility:

Farley Nuclear Plant (FNP), Units 1 and 2

Location:

7388-North State Highway 95

Columbia, AL 36319

Dates:

March 30 through May 10, 1997

Inspectors:

T. Ross. Senior Resident Inspector

!

J, Bartley, Resident Inspector

R. Ca Mwell, Resident Inspector (In training)

,

G. Kuzo. Health Physics Ins)ector.(Sections

.

R1.1, R1.2 R2.1, R5.1,

R8.1-8,5)

!

W. Kleinsorge Reactor Inspector (Sections

M1.10 - M1.12)

R. Chou, Reactor Inspector (Section E1.1)

e

M. Ernstes. Operator Licensing Examiner

,

(Section 0.5)

,

Approved by:

P Skinner. Chief, Projects Branch 2

Division of Reactor Projects

I

,

l

Enclosure 2

l

9706180232 970609

PDR

ADOCK 05000348

G

PDR

.

'

EXECUTIVE SUMMARY

Farley Nuclear Power Plant. Units 1 and 2

NRC Inspection Report 50-348/97-05, 50-364/97-05

This integrated inspection included aspects of licensee operations,

engineering, maintenance, and plant support.

The report covers a 6-week

period of resident inspections.

Ooerations

0)erator attentiveness to MCB annunciator alarms and response to

e

clanging plant conditions were prompt. Interviews with members of the

operating crew revealed that they were consistently aware of plant

conditions and ongcing activities (Section 01.1).

e

Unit 1 refueling activities were well-controlled (Section 01.2).

Housekeeping and physical conditions were adequate, although certain

e

areas remained poor.

Licensee efforts to improve targeted areas was

evident.

Improvement in overall plant appearances and material

conditions has increased (Section 02.1).

Safety system walkdowns and tours verified accessible portions of

e

selected systems were well maintained and operational (Sections 02.1 and

i

02.2).

'

Tag orders were properly executed, with one identified exception

e

(Section 02.3).

A violation was identified for failure to notify the NRC of a change in

.

e

a licensed Senior Reactor Operator's medical status (Section 05.1).

{

Licensee efforts to identify, resolve, and prevent problems remained

e

effective, with one identified exception (Section 0/.1).

Maintenance

Maintenance and surveillance testing activities were generally conducted

e

in a thorough and competent manner by qualified individuals in

accordance with plant procedures and work instructions (Sections M1.1

through M1.7).

e

Over the years, numerous foreign objects and materials have been allowed

to enter the emergency core cooling system containment sumps.

Licensee

efforts to clean, inspect, and repair the sumps have been very thorough

to date (Section M1.7).

Enclosure 2

.

.

,

.

.

.

2

e-

A violation was issued for failing to include several specific Technical

. Specifications (TS) surveillance requirements in the Surveillance Test

'

Program.

Examples of other missed TS surveillance requirements have

been identified in recent reports.

Load rejection testing of emergency

diesel generators (EDGs) was inconsistent with the licensing basis

(Section M1.8).

The inspectors * issues regarding compliance and conformance with the

e

licensing basis of TS 4.8.1.1.2.e are identified as unresolved item

(URI) 50-348, 364/97-05-04 EDG 50% Load Reject Surveillance Testing.

pending the NRC's response to the licensee's TS interpretation request

and proposed TS amendment (Section M1.8).

e

Inservice inspection activities observed / reviewed were conducted in

accordance with procedures, licensee commitments and regulatory

requirements (Section M1.10).

e

A violation was identified associated with the control of the special

process of welding (Section M1.11),

o

A weakness was identified associated with the licensee's control of

contracted welders (Section M1.11).

e

Maintenance was subjected to independent audits, with appropriate action

generally taken for identified weaknesses (Section M1.12).

e

The issue of control of painting inside the penetration room boundary

(PRB) being limited to less than 1000 ft' in any 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> period was not

documented by an existing analysis. This is identified as URI

50-364/97-05-06, Painting Effects On PRF Operability pending review of

the licensee's analysis (Section M8.1).

Enaineerina

e

Calculations analyzing the SG loop C narrow support gap on Unit I were

acceptable.

Licensee promptly evaluated the potential for past damage

and restored the intended conditions by modifications (Section E1.1).

e

Penetration room filtration (PRF) system licensing bases operability is

identified as URI 50-348, 364/97-05-07. Licensing Basis for PRF System

During Post-LOCA Recirculation, pending additional review by the NRC

(Section E1.2).

Plant Sucoort

e

Radiological controls were good for routine operations and U1RF14 outage

activities. All personal exposures were within 10 CFR Part 20 limits.

Implementation of established ALARA program activities was verified

(Section R1.1).

Enclosure 2

.

'

3

Service air compressor system supplied Grade D respirable air in

e

accordance with 10 CFR 20 Appendix A requirements (Section R1.2).

Training and medical certifications for personnel using respiratory

e

protective equipment were conducted in accordance with the licensee

procedures and met the a)plicable requirements of 10 CFR Part 19 and

10 CFR Part 20 (Section

RS).

Health Physics control over the radiologically controlled area, and the

e

work activities conducted within it, was good.

Some contaminated areas

were cramped and physically restricted removal of anti-contamination

clothing (Section R2.1).

e

Security activities continued to be performed in a conscientious and

capable manner, assuring the physical protection of protected and vital

areas.

Problems with improper display of security badges by workers in

'

containment were resolved promptly (Section S1.1).

e

Significant weakness identified in the implementation of Open Flame

Permits (Section F1.1).

e

Life safety exits from the Turbine Building were inadequate (F2.3)

l

Enclosure 2

. -

... .

._

-

-

__

--

--_

-

. _ .

-

.

.

Report Details

Summary of Plant Status

Unit 1 was shutdown for its 14th refueling outage (U1RF14) during the entire

inspection report period.

U1RF14 was rescheduled to be completed in 65 days

instead of the original 55 days due to increased scope of steam generator (SG)

tube inspection and repair work.

Unit 2 operated continuously at 100% power for the entire inspection period,

except for a brief power reduction to 85% power during the weekend of May 3.

1997. for main turbine generator (MTG) governor valve testing.

I. Operations

01

Conduct of Operations

01.1 Routine Observations of Control Room Ooerations

a.

Insoection Scoce (Insoection Procedure (IP) 71707)

Inspectors conducted frequent inspections of ongoing plant operations in

the Main Control Room (MCR) to verify proper staffing, operator

attentiveness, adherence to approved operating procedures,

communications, and command and control of operator activities.

Inspectors reviewed operator logs and Technical Specifications (TS)

Limiting Condition of 0]eration (LCO) tracking sheets, walked down the

Main Control Boards (MC3), and interviewed members of the o)erating

shift crews to verify operational safety and compliance witi TSs.

The

inspectors attended morning plant status meetings and shift turnover

meetings to maintain awareness of overall facility operations,

maintenance activities, and recent incidents.

Morning reports and

Occurrence Reports (ors) were reviewed on a routine basis to assure that

the licensee properly reported and resolved potential safety concerns.

b.

Observations. Findinas and Conclusions

l

Overall control and awareness of plant conditions during the inspection

period remained adequate.

Inspectors observed that the Unit 2 MCBs and

emergency power board were nearly " blackboard" most of the inspection

j

period, with only a couple of persistent annunciators in alarm that were

recognized deficiencies.

Efforts to maintain MCB deficiencies at low

levels continued.

MCB deficiencies on Unit 2 increased to 15 or more

and have remained there.

Almost all of them involved nonsafety-related

instrumentation or equipment.

Operator attentiveness to MCB annunciator

alarms and response to changing plant conditions were promot. Interviews

with members of the operating crew revealed that they were consistently

aware of plant conditions and ongoing activities.

Pre-shift briefs of

the operating crews by the shift supervisors (SS) were generally concise

and informative.

Operator logs generally were of sufficient detail and

scope, with one notable exception.

Surveillance test procedure (STP)

FNP-1-STP-40.1. Revision 27. "B1F and B1H Sequencer Load Shedding

Enclosure 2

-

.

.

2

Circuit Test." was performed on April 12. 1997, but was not mentioned in

the Unit 1 reactor operator (RO) logs.

This omission was discussed with

Operations management.

01.2 Unit 1 Refuelina (IP 60710)

A resident inspector observed refueling activities from the MCR, Spent

Fuel Pool (SFP). and MCR balance of plant area, on 18 April,1997.

The

Westinghouse Refueling Manual FP-ALA-R14. Revision 0. J.M. FARLEY

Unit 1 Cycle XIV - XV Refueling, conducted under WA# WOO 475930, was

reviewed.

Refueling activities observed by the resident inspectors were

performed in a well controlled and methodical manner in accordance with

FNP-1-U0P-4.1

" Controlling Procedure for Refueling and the Westinghouse

Refueling Manual." Revision 9.

Communications between the various

stations were clear and concise.

The subcritical multiplication plot

(1/M plot) was accurate and timely.

Personnel were very familiar with

the procedure and knowledgeable of the process and systems.

No

significant incidents occurred during fuel handling and all observed

fuel assemblies were landed in their appropriate locations.

The

inspector concluded that fuel handling was accomplished in a

professional and competent manner.

02

Operational Status of Facilities and Equipment

02.1 General Tours of Soecific Safety-Related Areas (IP 71707)

General tours of safety-related areas were performed by the inspectors

to examine the physical condition of plant equipment and structures, and

to verify that safety systems were properly aligned.

These general

walkdowns included the accessible portions of safety-related structures,

systems, and components in the following areas:

e

Unit 1 containment

e

Unit 1 and 2 SFP, SFP heat exchangers (HXs), and SFP cooling pump

rooms

e

Unit 1 and 2 main steam valve rooms

e

Unit 1 and 2 piaing penetration rooms (PPR) on 100 foot elevation

e

Unit 1 and 2 PPRs on 121 foot elevation

e

Service water intake structure (SWIS)

e

Unit 1 component cooling water pump and heat exchanger (HX) rooms

e

Unit 1 and 2 vital 125 volt direct current (VDC) switchgear and

'

,

battery rooms

e

Unit 1 and 2 new fuel storage areas

Unit 1 and 2 service and instrument air compressors, dryers and

e

receivers

e

Emergency diesel generator (EDG) building

e

Unit 1 and 2 containment spray (CS)

aump rooms

e

Unit 1 and 2 residual heat removal (RHR) HX rooms

Unit 1 and 2 RHR pump rooms

e

Unit 1 and 2 charging pump rooms and hallway

e

Enclosure 2

_. __ ._

_

_ . _

. _ _ _ _ _

_ . _ . _ _ - -

_ _ _ _

_ _ _ _

-

.

e

i

l

3

e

Turbine building

'

e

Unit 1 and 2 penetration room filtration.(PRF) system rooms-

o

Unit 2 hot shutdown panel (HSDP) rooms

,

i

e

Unit 1 filter gallery on 139-foot elevation

4

e

Unit 1 vital 4160 volt alternating current (VAC) switchgear rooms,

trains A and B, including vital 600 VAC load centers

,

General material conditions and housekeeping for Unit 2 were adequate.

-Areas were generally clear of trash and debris.

Attempts to control the

,

impact of Unit 1 outage activities were obvious, as were additional

efforts at housekeeping in the outage unit.

Considerable effort to

)

i

improve physical appearances of plant areas and equipment was in

'

progress, 3rimarily in the form of extensive painting in the EDG and

auxiliary )uildings. These efforts have dramatically improved the

f

appearances of rooms, structures and equipment in targeted areas.

Minor

equipment and housekeeping problems identified by the inspectors during

their routine tours were reported to the responsible SS and/or

maintenance department for resolution.

Maintaining all critical areas

of the auxiliary building well lamped remained an ongoing challenge.

None of these problems represented operability concerns.

02.2 Biweekly Insoections of Safety Systems (IP 71707)

Inspectors used IP 71707 to verify the operability of the following

selected safety systems and/or equipment:

e

Unit 2 Hot Shutdown Panels

e

Unit 1 Accumulators

e

IB Emergency Diesel Generator

i

e

Unit 1 Containment Spray. Trains A and B

Accessible portions of the systems listed above were verified to be

properly aligned and ap) eared to be well maintained and in good

operating condition.

T1e inspectors did not identify any significant

issues that adversely affected system operability.

In addition,

accumulator pipe supports and components were walked down using

isometric system drawings.

02.3 Tao Orders (IP 71707)

During the course of routine inspections, portions of the following tag

orders (TO) and associated equipment clearance tags were examined by the

inspectors:

e TO# 97-0757-1: RHR

e TO# 97-1059-1: IB PRF EQ Upgrade

e TO# 97-1058-1: 1A PRF EQ Upgrade

e TO# 97-442-1: Service Water System (SWS) pumps 1C. 10, and 1E

e TO# 97-178-1: CS System and Chemical Addition Tank

e TO# 97-1165-1: SW to Containment Coolers 1A and IB

i

i

Enclosure 2

'

.__ -__

. - . . , . . . - - - . . - .

- - - . - - -

. - . _ - - - . - . - - - . - -

-

.

~

.

4

i

All tags and TOs examined by the inspectors were pro)erly executed and

,

implemented. However, one . tag order was identified )y the inspectors;

I

that used an air-operated valve, which fails to the open position, as

i

.part of the clearance boundary.

While walking down TO 97-1059 on May 8, 1997, the inspector noted that

01V48HV3538B, SFP.to 1B PRF Supply Damper, was tagged shut per the tag

order. This valve is air-operated and thus depended on air pressure to

maintain itself in the tagged closed position.

Furthermore, because of

the type of work being done on the IB PRF filter housing, this valve was

required to remain closed to ensure the 1A PRF system was not rendered

inoperable by short-circuiting the suction flow path from the s)ent fuel

pool.

The inspector interviewed the T0 author and determined t1at he

was not aware that HV3538B was a fail open valve nor was he aware of the

i

potential for compromising the operability of the other PRF train.

During discussions with additional operations personnel, the inspector

determined that other operations staff were also not aware of the

j

)otential for short-circuiting the SFP supply to the 1A PRF system if

iV3538B had failed open.

When informed of the inspector's concern

regarding opeNbility of the 1A PRF system, the SS premntly revised the

T0 to jack shut HV3538B and initiated OR 1-97-191.

Ine inspector

i

determined, through interviews with licensee personne . ,nat loads were

i

not moved in the spent fuel pool area while either 1A he or 1B PRF were

j

tagged out for the environmental qualification upgrade. Therefore, no

i

TS LC0 action statements were required to be entered while the PRF was

j

potentially inoperable.

02.4 TS LCO Trackina (IP 71707)

The inspectors routinely reviewed the TS LC0 tracking sheets filled out

by the shift foremen.

All tracking sheets for Unit 1 and 2 reviewed by

the inspectors were consistent with plant conditions and TS

requirements.

05'

Operator Training and Qualifications

.

!

05.1 Conditions of Ooerator Licenses

j

a.

Scooe (IP 71001)

The inspectors reviewed 10 CFR 55 and NRC Information Notice 94-14.

,

" Failure to implement requirements for biennial medical examinations and

'

notification to the NRC of changes in licensed operator medical

conditions." which was issued to remind licensees of the requirements to

i

notify the NRC of changes in a licensed operators physical or mental

condition.

10 CFR 55.21, Medical examination, requires an NRC-licensed

operator to be examined by a physician every 2 years to determine if the

individual meets the requirements of 10 CFR 55.33(a)(1).

If, during the

l

term of the license the operator develops a permanent physical or

i

mental condition that causes the operator to fail to meet the

l

Enclosure 2

.

_

..

.-

--

-

-_

. - -

_

-- --.

--

_.

.

.

.

.

5

requirements of 10 CFR 55.21. the facility licensee shall, in accordance

with 10 CFR 55.25. notify the Commission within 30 days of learning of

the diagnosis.

b.

Observations and Findinas

On April 9,1997, an NRC inspector reviewed applications for renewal of

Senior Reactor Operator licenses. The NRC Form 396. " Certification of

Medical Examination by Facility Licensee." of one of the applicants

indicated that he needed corrective lenses to meet the requirements of

10 CFR 55.33(a)(1).

However, the individual's current Senior Reactor

Operator license contained no restrictions.

Based upon a telephone

conversation with Farley Training Department personnel, it was

determined that the individual had been diagnosed as needing glasses

during a biennial physical conducted on March 21, 1995.

However, the

j

facility licensee failed to notify the NRC of the change. The licensee

conducted a review of all other licensed operators' medical conditions

to determine if any other changes in medical conditions had failed to be

reported.

None were found.

c.

Conclusion

The licensee's failure to notify the NRC within 30 days of a permanent

i

change in a licensed operator's medical status is identified as

!

violation (VIO) 50-348, 364/97-05-01. Failure to Notify NRC of Change of

Licensed Operator Medical Status.

l

07

Quality Assurance in Operations

l

07.1 Effectiveness of Licensee Control in Identifyina. Resolvino. and

Preventina Problems (IP 71707 and 40500)

The inspectors briefly reviewed all newly initiated ors and completed

l

ors approved during the inspection period to ensure that plant incidents

which affect or could potentially affect safety were properly documented

and processed in accordance with Administrative Procedure (AP)

FNP-0-AP-30. " Preparation and Processing of Incident Reports."

Revision 22.

Selected ors that had been completed were reviewed in

detail.

l

The inspectors concluded that the licensee's program for identifying and

l

l

resolving problems remained effective and was being accomplished in

accordance with FNP-0-AP-30.

Plant personnel and management exhibited

an appropriate threshold for identifying problems, initiating ors. and

,

assigning formal root cause determinations.

Each new OR received prompt

attention and was discussed in the morning status / plan of the day

meeting.

.

Enclosure 2

,_ ,_ _.

_

_ . _ . _ _ _ . _ _ _ _ _ . _ _ _ _ _ _ _ . _ _ _

-

.

.

.

6

Inspectors reviewed the following ors for accuracy, completeness and

reportability. and adequacy of corrective actions:

e

OR #1-9'7-132:

Non-temperature compensated Heise gauges

e

OR #1-97-191:

PRF T0 deficiency

e

OR #1-97-198:

DG 1B Rollup door stuck open

'

These ors were properly processed to completion.

In general. licensee

corrective actions for resolving problems continued to remain effective.

However. OR 97-132 was initiated to address an instance where approved

corrective actions were not fully implemented.

On April 9. 1997, while

touring the Unit 1 Auxiliary Building, the inspector found four non-

i

temperature compensated 0 - 100 psig Heise test gauges which were not

labeled with a restricted use tag. The gauges were staged for use in

local leak rate testing. The use of non-temperature compensated Heise

,

gauges without restricted use tags was contrary to the corrective

actions identified in Corrective Action Request (CAR) 2173 for

i

VIO 50-348, 364/95-18-03.

Licensee staff immediately impounded the four

gauges when informed by the inspector and initiated OR 1-97-132.

A

re-audit identified four additional non-temperature compensated Heise

test gauges in the Calibration Lab.

The licensee investigation

determined that these eight gauges, which were used by the Systems

j

Performance Group for local leak rate testing (LLRT), were stored under

i

a green tarp in a mechanical room. They were overlooked when the

actions for CAR 2173 were performed.

As further corrective action for

this event, the licensee: 1) performed two independent audits which did

,

not identify any more test equipment re

to lack of temperature compensation 2) quiring restricted use tags due

modified calibration equipment

checkout procedures to check for temperature compensation, and 3)

,

evaluated all work activities which used any of these eight gauges. The

'

!

inspectors independently reviewed work activities which used these

gauges and determined that they were not invalidated by the use of a

non-temperature compensated gauge.

Failure to fully implement all of

the corrective actions identified by CAR 2173 and NOV response letter

dated December 19, 1995 constitutes a minor violation consistent with

,

the guidelines of Section IV of the NRC Enforcement Policy.

This

non-cited violation (NCV) is identified as NCV 50-348, 364/97-05-09.

Failure to Fully Implement Corrective Actions.

08

Hiscellaneous Operations Issues (92901)

!

08.1

(Closed) LER 50-348/97-002: Safety-Related 4160 Volt AC Breakers Not

i

Seismically Oualified

(Closed) LEP 50-348/97-004: Safety-Related 600 Volt AC Breakers Position

Sensitive Seismic Oualification

i

!.

Inspectors verified that 4160 and 600 Volt AC safety-related breakers

'

that can not be maintained in their seismically qualified positions were

removed from their respective cubicles. placed an appropriate distance

.

Enclosure 2

l

i--

-

.-

.-.

.

.

_-.

-

.

.

.

i

7

.

away, and properly secured. A few minor discrepancies (e.g., lack of

i

blocking bolts on 4160 VAC breaker assembly wheels) were initially

f

identified by the inspectors and promptly corrected.

No repeat problems

were found.

The inspectors also reviewed applicable operating procedure

!

FNP-0-SOP-36.6. " Circuit Breaker Racking Procedure." Revision 12 and

Temporary Change Notice (TCN) 12A and interviewed responsible personnel

regarding proper handling and positioning of these breakers. One minor

>

procedure deficiency was identified and discussed with Operations

management regarding . inadequate instructions for removing 600 volt

breakers and placing them a prescribed distance away. Although

different than the corrective actions described in LER 97-004

,

Operations has decided it would rather place 600 volt load center

,

breakers in spare cubicles rather than on the floor, whenever possible.

!

By the end of the report period, applicable procedures were being

l

revised to allow this option. These LERs are closed.

,

>

08.2 (Closed) LER 50-364/96-001: Reduction /Restmotion of 2B Diesel Generator

!

Soeed Caused By Inadeauate Procedural Guicance

i

This LER was considered a minor issue and closed.

i

II. Maintenance

l

M1

Conduct of Maintenance

.

M1.1 General Comments

!

!

a.

Insoection Scoce (IP 61726 and 62707)

!

!

Inspectors observed and reviewed portions of various licensee corrective

j

and preventive maintenance activities, and witnessed routine

,

surveillance testing to determine conformance with plant procedures.

~

work instructions, industry codes and standards. TSs. and regulatory

requirements.

The inspectors observed all or portions of the following

l

maintenance and surveillance activities, as identified by their

i

associated work order (WO). work authorization (WA), or surveillance

!

test procedure (STP):

!

o WO# M96004128

ICCMS Probe Changeout

i

e WA# 00467851

01P16MOV3019B MOVATS testing

e WO# 00448943

Sequencer Panel B2H Sequence Start Undervoltage

Relay 0A-C

e WO# 00448910

Sequencer Panel B1H Sequence Start Undervoltage

Relay OB-C

e WO# 00448913

Sequencer Panel B1J Sequence Start Undervoltage

Relay OB-C

e WO# S00080418

1B PRF EQ U3 grade

e FNP-1-STP-80.11

DG 1B 1200 (W Load Rejection Test. Revision 7

Enclosure 2

.

-

.-

.-

_ _ -

-l

.

8

e FNP-2-STP-16.2

Containment Spray Pump 2B Inservice Test,

Revision 23

e FNP-0-MP-14.19

Emergency Diesel Generator 1-2A, 18, and 2B

Removal and Inspection of Air Start Check

Valves, Revision 2

e FNP-0-IMP-226.7B

Diesel Generator Single Circuit Emergency Start

Test, Revision 7

e FNP-0-SOP-38.0

Diesel Generators, Revision 56

e FP-ALA-R14

J.M. FARLEY Unit 1. Cycle XIV - XV Refueling,

Revision 0, FCR 08 Westinghouse Refueling

Manual

e WO #S00080409

1A PRF E0 Upgrade. DCP No. B97-1-9157

e WO #S00080408

1A PRF EO Upgrade, DCP No. B97-1-9157

e WO #S00080411

Rewire 1A PRF heater coil, DCP No. B97-1-9157

e WO #S00080410

Rework 1A PRF fan motor 01E15M001A(2A) DCP

No. B97-1-9157

e FNP-1-STP-228.5

NIS Power Range Channel N41 Calibration

N1C55NE0041. Revision 38

e FNP-1-STP-40.0

Safety Injection with Loss of Off-Site Power

Test, Revision 31

e FNP-1-STP-40,0

Retest of 01P16MOV3134, SW from RCP MTR CLRS

(Appendix S)

under WO #97003589

e FNP-1-STP-256.15

Loss Of Offsite Power Response Time Test,

Train A. Revision 14 (TCN 14B) under

1

WO #00467991

e FNP-1-STP-16.1

Containment Spray Pump 1A Inservice Test,

Revision 29 under WO #0079666

e FNP-0-MP-14.1

Emergency Diesel Generator 1-2A, 1B & 2B Refuel

(18 Month) Inspections Revision 23

i

e FNP-0-MP-84.4

Emergency Diesel Generator Vibration

j

Measurements, Revision 4

e FNP-0-SOP-42.0

Diesel Generator Fuel Oil Storage & Transfer

System, Revision 2C

'

1

e FNP-2-STP-24.1

2A, 28, and 2C Service Water Pump Quarterly

Inservice Test. Revision 23

e WO #S0068708, 11

SW Supply and Return Valve Replacements for

and 12

Containment Coolers IA and 10

e FNP-1-STP-80.14

Diesel Generator A Train Loss of Offsite Power

Test

e FNP-1-STP-80.15

Diesel Generator B Train Loss of Offsite Power

Test

e WA #W00477033

Preventive Maintenance (PM) Lubrication of 2C

Charging Pump

b.

Observations. Findinas and Conclusions

All of the maintenance work and surveillance testing observed by the

inspectors was performed in accordance with work instructicos,

procedures, and applicable clearance controls.

No adverse findings were

identi fied.

Safety-related maintenance and surveillance testing

Enclosure 2

,. _ __ _ _ _ _ _ ._._ _._ _ _ _ ___ _ _ - _ _ . . _ _ _. _ _ _

-

.

.

evolutions were well planned and executed.

Personnel demonstrated

. familiarity with administrative and radiological controls. . Surveillance

tests of safety-related equipment were consistently performed in a

deliberate step-by-step manner by personnel in close communication with

the MCR.

Overall, operators and technicians appeared knowledgeable.

experienced. and well trained for the tasks they performed.

M1.2 IB D/G Outaae Maintenance

'The inspector observed portions of the 18 Month 1B EDG maintenance and

testing work from March 30 - A)ril 4.1997. Specific evolutions

<

observed include portions of tle following:

e

Removal and inspection of air start check valves.

e

Replacement of Lube Oil HX and Jacket Water HX tube bundles due to

,

inlet tube sheet erosion concerns,

i

e

Diesel Generator circuit emergency start inspection done under WO #470331.

e

Various other refuel (18 Month) inspections.

e

Emergency Diesel Generator vibration measurements.

!

e

Inspection of the Diesel Generator fuel oil storage and transfer

i

l

system.

All work was completed per procedure in a professional manner.

Post

maintenance testing was completed satisfactorily.

M1.3 Manual Safety In.iection (SI) Hand Switch Test

The inspectors observed the test in the MCR and at the reactor trip

,

breakers.

The test was performed in accordance with FNP-1/2-STP-38.3.

'

" Verification of Manual SI Actuation Input." Revision 1.

All components

responded as required.

Refer to section M8.2 for more details.

!

M1.4 Unit 1 Gammametrics Probe Reolacement

l

l

The inspectors observed maintenance activities involving the pre-job

planning, removal, and installation of the Gamma-Metrics Detector.

01C55NE0048. This work was performed under WA #00464676. . Pre-job

planning was thorough.

Licensee personnel were knowledgeable and

sensitive to ALARA planning.

Maintenance and HP interfaced well to

minimize radiation exposures. Work was conducted per the WA and the

staff responded well to unexpected situations such as the detector being

i

l

much more activated than expected.

!

l

Enclosure 2

N

-

.

-

-.

.

,

. . -

-

.

.

-_

.

,

-_

-,.

.

_

- - . - . - --. .- .-- - - .

- - .

---

-

4

,

.

10

M1.5 Unit 1 Containment Cooler Coil Reolacement

An inspector observed portions of the work to remove all the original

containment cooler coils and replace them with new coils according to

design change package (DCP) 96-1-9054. All work witnessed by the

inspector was accomplished in accordance with authorized work orders.

Good cleanliness control was exhibited to prevent introducing foreign

material into the cooler piping.

During modification work, the

licensee's activity task manager identified two problems that warranted

being documented as ors: 1) Original cooler coils were missing mounting

bolts that attached the coils to the cooler frame (OR# 97-94) and 2)

Baffle gaskets were missing from some of the replacement coils

(OR# 97-151).

The inspector discussed each of these problems in detail

with the activity manager. After the containment cooler coils were

replaced, and the system returned to service, the inspector conducted a

walkdown of all four containment coolers. The inspector also reviewed

the post-modification testing (PMT) performed in accordance with

FNP-1-STP-17.0, " Containment Cooling System Train A(B) Operability

Test." Although both trains of containment coolers met the acceptance

criteria of STP-17.0, the inspector discussed testing the coolers

individually in order to verify sufficient SW flow through each one.

After further review, the licensee expanded the PMT to measure flow

through each cooler per WO #S97004055.

The inspector reviewed the

results which verified adequate flow.

M1.6 Unit 1 CS Addition Tank Deletion and Trisodium Phosohate Basket

Installation

i

On May 8 a resident inspector observed the visual examination (i.e..

VT-2) performed on welds associated with the Unit 1 "A" train Spray

Additive Tank removal design change, under WO# 0079666. The 1A

Containment Spray pump was started per FNP-1-STP-16.1, " Containment

Spray Pump 1A Inservice Test." Revision 29, and the weld checked at

,

operating pressure. A quality control (OC) ins)ector conducted a

i

detailed visual check of the weld area and blanc flange.

The OC

inspector and resident inspector observed no leakage.

A resident ins)ector conducted a walkdown of the new trisodium phosphate

(TSP) baskets Juilt on the containment basement floor in accordance with

DCP 95-1-8931.

The ins)ector also observed licensee efforts on May 13

to load 70 fifty pound Jags of TSP into each of the three baskets.

Upon

the completion of this work the inspector noticed and discussed the

following concerns with the responsible design change engineer:

1) All

three TSP baskets were slowly leaking at the bottom corners. 2) Actual

i

level of TSP in the baskets did not rise to the minnmum TS level marked

on the baskets, and yet the quantity loaded should have been sufficient,

3) Accuracy of TSP bag weight, and 4) Maintaining inventory control of

material lost during basket leak / repair.

Each of these observations was

,

adequately addressed by the licensee.

Subsequent walkdowns of the

Enclosure 2

,

. - - - . . - --

. . - . - - - - .---

.

_ . . _ - - - . .

'

i

r

j

-

.

!

11

finished and filled baskets by the inspector did not identify any

additional concerns.

.

M1.7 Emeraency Core Coolina System Containment Sumo Insoections and Foreian

Material Retrieval

On April 24, 1997 an SAER auditor and PMD engineer discovered that the

Unit 1 emergency core cooling system (ECCS) sump screens were not built

.

}

per design. Two of the four ECCS sumps in containment were missing a

.

l

'

structural, flat bar of. steel. OR #97-172 was initiated. Thorough

walkdowns of the Unit 1 ECCS sumps conducted by an inspector and

licensee personnel also identified numerous gaps in the sump screens

i

created by poor fitup. Many of the gaps were on the order of 1" x 1,"

which are considerably larger than the 1/8" x 1/8" screen mesh openings.

On May 2, the licensee made a containment entry into Unit 2 to examine

'

.

its ECCS sumps. Although gaps of comparable size were also discovered

in the Unit 2 screens, they were much fewer in number.

This inspection

also included the interior of the Unit 2 sumps and identified two pieces

'

of foreign material that were removed.

OR #97-183 was initiated for

Unit 2.

The Unit 2 ECCS sum) screen gaps were promptly repaired.

returning the ECCS sumps bacc to original design. An operability

i

determination (0D) 97-10 was developed by the licensee and reviewed by

the inspector.

It determined that operability of ECCS equipment had not

i

been adversely affected.

The inspector discussed with the licensee the

aotential that foreign material may have also fallen down inside the

!

ECCS sump suction piping for the CS and RHR systems.

Beginning May 8. the inspector observed maintenance personnel conduct

-

internal visual inspections of the Unit -1 ECCS sump, both the interior

grating and suction piping. A boroscope was used to inspect inside the

i

suction )iping.

Numerous articles of foreign debris were discovered

inside t1e interior grating (e.g. , many different lengths of duct tape,

metal washers, marking pen, weld rod segment, etc.) and sump suction

-

piping (e.g.. many different lengths of duct tape, short piece of

string, small strip of plastic, etc.).

The boroscope used by the

,

maintenance personnel could only inspect about six feet of the

hori2ontal run of piping.

By the end of the-inspection period, the

<

licensee was still cleaning out the foreign debris from the Unit 1 sumps

and enlisting the aid of a contractor who could exam the entire run of

suction piping.

Operations was also pursuing an OD to address the

operability impact of the discovered material in Unit 1.

Plans for

,

conducting internal visual examination of Unit 2 interior grating and

sump suction piping was still being discussed.

In order to track the

licensee *s ongoing corrective actions and operability evaluations this

.

issue is-identified as inspector followup item (IFI) 50-348,

364/97-05-02. Foreign Material In Containment ECCS Sumps.

4

'

Enclosure 2

-

--

- . .

-

-

.

'

.

.

12

M1.8 Failure to Meet Multiole TS Surveillance Recuirements

During the current Unit 1 outage (U1RF14), the licensee identified the

following TS Surveillance Requirements that were not being adequately

implemented and/or missed entirely:

a)

TS Table 4.3-1. Reactor Trip Instrumentation Surveillance

Requirements. Functional Unit 6 requires a quarterly channel

,

functional test and shiftly channel checks of the nuclear

'

instrumentation system (NIS) source range (SR) channels while in

Modes 2. 3. 4. and 5.

On March 19. 1997, during a review of its

Improved TS submittal, the licensee determined that when Unit 1

was shutdown on March 15 for U1RF14 the unit had entered Mode 2.

and then several minutes later Mode 3. without accomplishing the

surveillance requirements for NIS SR.

The TS surveillance

i

recuirements were not met until March 18 while the unit was in

Moce 5 after NIS SR N-32 was functionally tested.

OR# 97-139 was

,

initiated and LER 97-05 was written to document, resolve and

'

report the incident.

Since the root cause was considered to be

inadequate test procedures, the licensee also concluded that the

failure to meet these TS surveillance requirements has occurred

numerous times in the past during previous Unit 1 and 2 shutdowns.

,

b)

TS Table 4.3-1. Functional Unit 2.B. for NIS power range (PR).

neutron flux-low, requires quarterly channel calibration while in

'

Mode 2.

On April 8,1997, while conducting a review specifically

looking for TS mode change difficulties, the licensee determined

that Unit 1 entered Mode 2 on March 15 without accomplishing the

surveillance requirements of TS Table 4.3-1.

This incident was

also reported in LER 97-05.

Unit 1 was only in Mode 2 for about

seven minutes until it entered Mode 3.

Due to inadequate test

procedures and TS inconsistencies, the licensee concluded this TS

i

surveillance requirement had been missed during other Unit 1 and 2

shutdowns.

i

c)

on April 23, 1997, while conducting a special, comprehensive

review of TS mode change requirements, the licensee determined

that the 18 month TS surveillance requirement 4.8.1.1.2.c.8 had

not been performed on Unit 2 for EDG 1-2A or 1C.

OR# 97-162 was

initiated and LER 97-03 (Unit 2 only) was written to document,

resolve and report the incident.

TS 4.8.1.1.2.c.8 requires

verifying a simulated SI signal will override the test mode of an

operating EDG connected to its bus returning it to standby

operation. This surveillance is a TS requirement for both units.

However. FNP-0-STP-80.8. " Diesel Generator 1-2A 1000 KW Load

Rejection Test." and FNP-0-STP-80.9. " Diesel Generator 1C 1000 KW

Load Rejection Test." which perform the required surveillance

test, were only done on Unit 1.

Credit was then given for meeting

the TS surveillance requirement for both units. On April 24. the

1-2A EDG was successfully tested while connected to its vital 4160

Enclosure 2

'

.

.

.

13

VAC bus on Unit 2 (i.e.

Bus 2F). The 1C EDG was successfully

tested on Unit 2 the following day.

Although these were identified by the licensee, these are being cited as

a violation due to their repetitive nature and inadequate licensee

corrective action. These examples of failure to follow TS surveillance

requirements constitute a violation identified as VIO 50-348,

364/97-05-03, Failure To Follow Multiple TS Surveillance Requirements.

On April 25, 1997, the licensee also examined its compliance with TS

surveillance requirement 4.8.1.1.2.e which requires conducting a load

rejection test of 1200 - 2400 KW every five years without tripping the

EDG. and verifying that all fuses and breakers on the energized

emergency bus (es) are not tripped.

Similar to example c) above. the

licensee discovered that the applicable FNP-0-STP-80.11, " Diesel

Generator 1-2A 1200 KW Load Rejection Test." Revision 8. and

FNP-0-STP-80.12. " Diesel Generator 1C 1200 KW Load Rejection Test.'

Revision 6, were not being performed on both units.

Instead, STP-80.11

was routinely conducted only on Unit 1 and STP-80.12 was being conducted

on' Unit 2.

But, after additional evaluation, the licensee concluded

that TS 4.8.1.1.2.e could be satisfied for the shared A train EDGs by

only testing them on one unit and taking credit for both. A resident

inspector reviewed the licensee's evaluation and disagreed with its

conclusion. The inspector read the statement in TS 4.8.1.1.2.e. for

both units, that says " Verify that all fuses and breakers on the

energized emergency bus (es) are not tripped" seems to imply this

surveillance test is not just an EDG test.

Rather. each unit's

emergency bus (es) are also required to be tested during an EDG load

rejection to ensure their respective breakers and fuses do not trip.

The inspector conferred with NRC technical staff regarding this

difference in opinion, and then notified the licensee that their

position appeared inconsistent with TS requirements.

Following

discussions with the inspector. SNC concluded that a differing opinion

continued to exist. To reconcile this difference SNC formerly requested

a TS interpretation from the NRC by letter dated May 22, 1997.

In

addition, SNC also conducted a successful 1220 KW load rejection test of

the 1C EDG tied to its Unit 1 emergency bus: and depending on Unit 2

availability, the licensee was considering testing the 1-2A EDG. While

awaiting NRC respense to the May 22 letter, the licensee also has

submitted a TS amendment request dated May 28, 1997, that clarifies

TS 4.8.1.1.2.e.

In addition to the compliance implications of TS 4.8.1.1.2.e discussed

above the inspector also questioned the licensee on the adequacy of the

surveillance testing being conducted from a technical and licensing

basis.

Both STP-80.11 and 80.12 only require their respective EDG to

undergo a 1200 KW load rejection test, which is the minimum allowed by

TS. The TS load rating of the 1C EDG is 2850 KW and the 1-2A EDG is

4075 KW. According to the NRC's safety evaluation report (SER) that

approved the TS 4.8.1.1.2.e surveillance requirement, "the licensee has

Enclosure 2

- - - . -

'

.

.

.

14

i

devised a test that, by manually tripping two circuit breakers (leaving

the diesel generator output breaker closed), a load approaching 50% of

,

rating is rejected . ." The SER also stated. "the confidence gained

i

from... testing of loss of. half the rated load every five years is

sufficient to provide reasonable assurance on a continuing basis that

the diesel generator will not be lost due to a load rejection..." A 50%

load rejection for the 1C and 1-2A EDG would be 1400 KW and about

<

2030 KW, respectively. TS 4.8.1.1.2.e establishes a range that

specifically allows for testing each EDG at their own 50% load rating.

,

However, contrary to statements in the SER, the licensee's STPs only

test the 1-2A and 1C EDGs at 29% and 42% of their load rating.

respectively.

STP-80.11 and 80.12 only tri) one circuit breaker to

'

initiate the load rejection vice two descri)ed in the SER. The

inspec'or discussed these concerns at length with SNC management. The

licensee will evaluate the adequacy of surveillance testing methodology

in light of the current licensing basis and technical arguments.

These concerns are identified as unresolved item (URI) 50-348,

364/97-05-04. EDG 50% Load Reject Surveillance Testing pending NRC's

response to the licensee's TS interpretation request and proposed TS

amendment.

M1.9 SI/LOSP Intearated Test

On April 25, 1997, a resident inspector reviewed the results of

FNP-1-STP-40.0.

" Safety Injection with Loss of Off-Site Power Test."

Revision 31.

The test appeared to be challenging and complex. Test

completion was considered satisfactory with several relatively minor

exceptions, which were noted and rescheduled.

Test signoffs were

current and the pre-job checklist was com)lete. Test data packages

appeared to be complete and results met t1e defined acceptance criterta.

'

On May 5. a resident inspector observed FNP-1-STP-40.0 Appendix S.

" Retest of 01P16MOV3134. SW from RCP MTR CLRS " conducted under WO 97003589. The pre-job brief conducted by the Shift Supervisor was

clear, concise and identified potential areas of concern. The retest

was conducted satisfactorily after a procedural inaccuracy was

reconciled.

Overall. the test and retests appeared to adequately verify

SI operation with a loss of offsite power.

M1.10 Inservice Insoection

a.

Insoection Scooe (IP 737521

To evaluate the licen_ce's Inservice Inspection (ISI) program and the

program's implementation, the inspectors reviewed 3rocedures, observed

work in progress and reviewed selected records.

0)servations were

compared with ap)licable procedures, the Final Safety Analysis Report

(FSAR) and ASME 3&PV Code Sections V and XI,1903 Edition, Summer 1983

Addenda (83S83).

Enclosure 2

- .

.

. - _ _

. . _ _ _

_ _ _ _ _ . _ _ . _ . _ . . _

_

__

_ _ . _

_ _ _ _ . . _

'

.

1

.

4

e

15

i

4

}

Specific areas examined included the following:

observation of Liquid

Penetrant (PT) examination of Item Nos. ALA2-4517-37 and ALA2-4516-1;

.

manual Ultrasonic (UT) examination of Item No. ALA2-4516-1: data

,

acquisition and analysis activities associated with Eddy Current (ET)

examinations of Steam Generator (S/G) tubing; data acquisition and

5

analysis activities associated automated UT examinations of reactor

ve.;sel welds: review of video tape of the remote Visual (VT) examination

i

of the reactor vessel internals: direct VT examination of support -

ALA2-4516-SI-R206: Review of selected completed examination reports: and

J

review of the Repair and Replacement Program.

'

.

!

The inspectors performed an independent evaluation of indications to

I

confirm the licensee's ISI examiners' evaluations.

\\

j

The inspectors reviewed records for the Nondestructive Examination (NDE)

personnel and ecui) ment utilized to aerform ISI examinations. The

e

l

. records includec : 1DE equi) ment cali) ration and materials certificationi

and records attesting to N)E examiner qualification. certification and

i

visual acuity.

i

The inspector:; scrutinized FNP Occurrence Report OR No. 1-97-115.

b. ' Observations and Findinos

ISI examinations observed / reviewed were conducted in accordance with

properly approved procedures, by cualified and properly certified

examiners using properly certifiec/ calibrated equipment and materials.

The licensee had implemented the Containment Inspection Rule repair and

replacement (R/R) program by revisions to FNP-1-M-043 "Second Ten-Year

Inservice Inspection Program For Class 1. 2. and 3 Components" and

FNP-0-GMP-0.2. " Repair and Replacement Instructions for ASME Class 1. 2.

3. and MC Components.~ and the issuance of FNP-0-GNP-0.4. " Repair and

Replacement Instructions for ASME Class CC." FNP-0-100 .24. Visual

Examination VT-1 For IWE Components." FNP-0-100 .25, " Visual Examination

VT-3 For IWE Components." FNP-0-100 .26. " Visual Examination VT-1C."

FNP-0-100 .27. " Visual Examination VT-3C."

l

FNP-1-M-043 paragraph 1.9 states, in part. " Code Case N-416-1 (RR-47)

may be used in place of hydrotest in some situations. The NRC SER

recuires a surface examination on the root pass layer of Class 3 butt

anc socket welds on pressure retaining boundaries." The NRC SER had not

been identified and the root inspection option had not been addressed in

lower tier documents. The licensee indicated that they would take

appropriate action.

The issue documented in OR No. 1-97-115, was properly identified,

evaluated and closed out.

Enclosure 2

-

. _ . -

- - .

_ -.

_

____

_ _ . _ . _ ._ _ _._ _ __.-

____

'

.

.

e

,

16

c.

Conclusion

i

ISI activities observed / reviewed were conducted in accordance with

procedures, licensee commitments and regulatory requirements.

M1.11 Weldina

a.

Insoection Scoce (IP 62700)

To evaluate the licensee's welding program and the program's

implementation, the inspectors reviewed procedures, observed work in

progress, and reviewed selected records. Observations were compared

with applicable procedures, the FSAR and ASME B&PV Code Sections V and

XI. 83S83 and Section IX latest at the time of qualification.

Specific areas examined included the following: observation of welding

activities in the containment associated with the replacement of the

containment coolers; observation of welding activities in the auxiliary

building associated with the bypass of the Boron Injection Tank, and

observation of welding activities in the auxiliary building associated

with the replacement of service water valves; inspection of the welding

material issue station: and inspection of the welder qualification test

facility, The inspectors scrutinized Work Order (WO) Nos. 11276 and

11284 for the replacement of valve Nos. V044C and V0010C.

The inspectors reviewed records for welders. Quality control (OC)

inspectors, and materials utilized in the W0s. These records included:

Welding Procedure Specifications (WPS) and their supporting Procedure

Qualification Records (POR): Welder Performance Qualification (WP0)

records: records attesting to the maintenance of welder qualification:

receiving inspection reports and Certified Material Test Reports (CMTR)

for welding filler materials; and records attesting to QC inspectors

qualification, certification, and visual acuity.

b.

Observations and Findinas

The inspectors noted mechanical force in the form of a chain fall was

used to hold Service Water piping in place during fit-up activities

prior to welding.

This indicated that the pipe was flexed or cold

sprung into place, thereby inducing stresses in the piping.

Investigation by the inspectors revealed the following:

o

Programmatically the only guidance for cold spring is contained in

i

FNP-0-SPP-GW-002, Revision 18. " General Welding Standard For

Pressure Boundary Applications," paragraph 8.6 b., which states.

.

"There are no indications of excessive cold spring at the time of

.

joint fit-up." The licensee had no guidance to define

i

" indications of excessive cold spring".

e

The pipe deflections were not documented at the time of fit-up.

q

y

Enclosure 2

't

i

.

<u-i

<w

_ ,_ . . _ -

._ . _ _ _ - . _ _ . . _ _

_ _ _ _ _ . . _ . _ _ _ _ _ . _ .

.

i

,

.'

,

.

'

i

17

,

i

Prior to the application of the mechanical force (cold spring), no

e

1

formal analysis had been conducted to determine whether the stress

'

l

levels induced in the piping exceeded Code allowable levels.

The licensee informed the inspectors that they had approved the

e

use of cold spring at'a number of locations in the SWS, because

each instance did not appear visually to be " excessive." It was

'

recommended by 3rofessional pi)e fitters that aipe spring was

censidered by t1e licensee to 3e within the "scill of the craft"

i

<

for pipe fitters.

The introduction of unknown stress levels into safety-related piping

)

-

systems as shown above indicated a lack of control of the special

4

{

process of welding, and is identified as an exam)le of VID

50-348/97-05-05: Failure to Control the Special 3rocess of Welding. The

i

licensee documented this issue in OR 1-97-130.

'

ASME B&PV Code.Section IX,

requires the thickness of side bend

specimens, used for the evaluation of welder qualification test

assemblies. to be 3/8-inch thick.

Procedure FNP-0-SPP-WP-030. Revision

15. " Specification for Welder Qualification for Pressure Boundary

Applications " requires the thickness of side bend specimens to be

3/8-inch thick with no tolerance specified.

An inspection of bend

specimens used to evaluate welder performance test assemblies revealed

several specimens that were 1/32 to 1/16-inch under 3/8-inch in

thickness.

Because the side bend thickness is

stress applied to the outer fibers of the bend, proportional to the

undersized specimens

constitute a less rigorous test than intended by ASME B&PV Code

Section IX.

The licensee's failure to conduct bend testing on welder

test assemblies in accordance the ASME B&PV Code Section IX, indicated a

lack of control of the special process of welding, and is identified as

!

an example of VIO 50-348/97-05-05. The licensee documented this issue

i

in OR 1-97-150.

FNP-0-SPP-WF-001 Revision 12. " Procedure for Welding Filler Material

Control " Paragraph No. 8.4. states, " Work areas shall be kept clear of

unauthorized, unidentified or discarded welding filler materials.

FNP-0-SPP-WF-001, Revision 12. " Procedure for Welding Filler Material

Control," Paragraph No. 8,1. states in part,

"...it is the

responsibility of the welder to maintain control of filler materials

,

until used, discarded or returned to the storeroom." Further, the

'

licensee stated that it is their expectation that at the end of shift,

work areas are free of all welding filler materials.

Contrary to the

above on April 11, 1997. between the night shift and the day shift. the

'

inspectors found a significant quantity of partially used bare welding

filler material abandoned in the area of the Boric Acid Injection Tank.

Although some of the rods had flag tags that identified them as to ty)e,

there was no traceability to heat or batch identification. Many of tie

rods were of a length suitable for continued use.

The licensee's

failure to control welding filler materials indicated a lack of control

Enclosure 2

,,

. - -.- - -

_-

_- - --- -.-. - . - - - . - . -

. -

i

.

!

.

.

-

18

of the special process of welding, and is identified as an example of

j

VIO 50-348/97-05-05. The licensee documented this issue in OR 1-97-149.

j

The licensee's introduction of unknown stress levels into safety-related

pioing systems resulting from their failure to provide guidance to

j_

define " indications of excessive cold spring:" failure to conduct bend

testing on welder test assemblies in accordance the ASME B&PV Code.

Section IX resulting from their failure to provide tolerances on the

bend specimen thickness; and failure to control welding filler materials

i

resulting from their failure to adequately communicate their procedural

requirements and. expectations for welding filler material control to

their contract welders, demonstrates less than effective control of the

-

l

special process of welding and is a violation of Title 10 CFR 50

Appendix B. Criterion IX. which requires that measures be established to

2

4

assure that special processes including welding be controlled. This

'

-

violation is identified as VIO 50-348/97-05-05.

I

!

The licensee's Welding Manual procedures incorporates code requirements

without providing guidance for implementation, some examples are as

j

follows:

e

FNP-0-SPP-GU-003, paragraph 13.la states. " Undercut shall not

,

exceed 0.01 inch deep when its direction is transverse to a

4

primary tensile stress in the part that is undercut, nor more than

j

1/32-inch for all other situations." No guidance is provided to

determine the direction of primary tensile stress.

,

e

FNP-0-SPP-WP-030 requires the thickness of side bend specimens to

!

be 3/8-inch thick with no tolerance specified.

As discussed

'

!

above, the failure to specify a tolerance caused some specimens to

i

be made under size.

l

e

FNP-0-SPP-GW-002 states, "There are no indications of excessive

cold spring at the time of joint fit-up." As discussed above, the

,

failure to provide quantitative guidance for cold spring resulted

in the introduction of unknown stress levels into safety-related

4

.

piping systems.

j

l[

The Authorized Nuclear Inservice Inspector (ANII) determined that the

i

contract welders were uninformed concerning a number of requirements of

'

the licensee's Welding Manual and welding compliance issues.

In

i

addition structural contract welders were not provided with the means to

i

measure base metal temperature prior to the resumption of welding, to

assure compliance with interpass temperature requirements of the WPS.

l

This issue was documer*.ed in OR 1-97-092.

i

i

A licensee OC inspecte identified an instance where a contract welder

was welding prior to the completion of the welder's Performance

i

Qualification Test Record.

This issue was documented in OR 1-97-083.

i

Enclosure 2

!

1-.

-

_ _

-

-

. . - -

-

,

_

-

,-

. - .

,

-

,

F

19

A licensee QC ins]ector identified an instance where a contract welder

had made an unautlorized base material repair without benefit of a

repair procedure.

The contract welder burned through the material on

which he was welding, and subsequently made a unilateral decision to

effect a repair. The licensee viewed this decision and subsequent

unauthorized repair as a coverup. This issue was documented in

OR 1-97-071.

The inspectors identified a Welder Qualification Test (WOT) Record for

welder 420-04-1378 on test WOT No. ST-6, Revisicn 2. completed on March

i

6.1996, that was missing the certifying signature. .The licensee

indicated that they would conduct a records review to determine whether

'

welder 420-04-1378 3erformed any welding on or after March 6,1996 that

was only supported )y WOT No. ST-6, Revision 2 test.

If so, they will

take a)propriate actions. The licensee subsequently determined that the

'

test tlat the welder in question had taken was a licensee specific test

for "T." "K." and "Y" connections. They further determined that

although the welder had welded on 13 W0s since taking the test, those

i

W0s contained no "T." "K," or "Y" connections.

!

The inspectors identified no discrepancies associated with welding being

performed by the licensee's permanent employees.

Except as noted above the welding activities examined, were conducted by

properly qualified and certified welders, using correct and certified

welding filler materials in accordance with qualified Welding Procedure

Specifications. Procedure Qualification Records were reviewed and

determined to be adequate. Quality Control inspectors associated with

the repair and replacement activities were properly qualified and

certified.

c.

Conclusions

'

A violation was identified associated with the control of the special

process of welding. A weakness was identified associated with the

licensee's control of contracted welders.

M1.12 Audits

a.

Insoection Scooe (IP 62700)

To evaluate the licensee's Audit Program as it relates to maintenance,

the inspectors requested all the audits and self-assessments conducted

in the maintenance area during the previous 12 months. The inspectors

reviewed the two audits provided (96-STPm/34-1 Surveillance Testing -

Maintenance and 96-MAINT/15-1 Maintenance Department, Routine

Scheduled).

Enclosure 2

n_-

.

--. .

-.

. .

_ - .

. - -_- - - -.-._.- - - .-

_

.

.

'

.

.

t

20

b.

Observations and Findinas

i

Audit 96-STPm/34-1 contained no findings. Audit. 96-MAINT/15-1 - findings

included weaknesses related to: meteorological tower instruments not in

agreement with the FSAR: PMT guidelines not consistently followed: smoke

detector procedures performed without proper release; personal hold tag

discrepancies: hand-operated hoists used with out-of-date color codes:

-

and requirements of Purchase Orders not met. Appropriate corrective

actions were taken or planned.

The audit 96-MAINT/15-1 finding related to post maintenance testing

guidelines not consistently being followed, was addressed in Corrective

Action Report (CAR) No. 2201. Revision 1.

CAR 2001. Revision 1. did not

include an adequate job of determining the extent of the problem, as

only the specific examples identified by the auditors were corrected.

c.

Conclusions

i

The area of maintenance was subjected to independent audits, with

'

appropriate action generally taken for identified weaknesses.

l

M8

Miscellaneous Maintenance Issues (IP 92902)

M8.1 Paintina

a.

Insoection Scooe (62707)

The inspectors observed Jainting activities, and reviewed procedures and

paint data sheets from FiP-0-CP-MD-801, " Coating Program." Revision 7.

Also, the inspectors interviewed various licensee personnel including

'

supervisors, engineers, painters, and the painting foreman.

b.

Observations and Findinas

l

The licensee commenced a major 3ainting effort throughout the )lant this

!

spring. This effort included tie Auxiliary Building (AB) Tur)ine

Building, and Diesel Generator Building.

Overall the Sainters appear to

,

I

be doing a good job.

However, several problems with tie EDGs and an

issue with the Unit 2 PRF systems were identified as a result of the

painting.

e

Licensee personnel identified that the fusible links for the 1-2A

and 28 DG roll up doors had been painted on one side. The

I

licensee promptly instituted the appropriate compensatory actions

Jer the Fire Protection Program until the links were replaced.

ollowup testing of the painted links identified that the paint

raised the actuation point approximately 10 degrees F.

The slight

increase in actuation temperature was insignificant.

!

i

!

Enclosure 2

. - .

.-

j

,

.

l

21

e

On April 24. 1997, during a routine tour of the AB. the inspectors

noticed very strong paint fumes from recent painting efforts of

the RHR HX room (inside the 3enetration room boundary (PRB)).

The

paint was a modified epoxy-plenolic product with 56% solids and

thinned with up to 1 pint of thinner per gallon of paint.

One

'

gallon of paint would cover approximately 225 ft' if applied at

the recomended thickness of four mils.

The inspectors were

concerned about the potential operability effects of the volatile

organic compounds (VOC) on the PRF system charcoal filters.

The inspector discussed the control of painting inside the PRB

'

with licensee personnel.

The licensee staff stated that Sainting

inside the PRB was limited to less than 1000 ft' in any 2L hour

period which is about four gallons if applied per the paint data

sheet.

Neither the inspector nor the licensee staff were able to

find this limit proceduralized to control the painting. Although

the licensee did not have any direct procedural controls, the

inspector determined that this criteria was being followed. based

on interviews with o]erations personnel, the painting foreman, and

'

various painters.

T1is criteria was identified obliquely in the

" Precautions and Limitations" sections of FNP-1/2-STP-20.0.

" Penetration Room Filtration System Train A(B) Quarterly

Operability and Valve Inservice Test." Revisions 25 and 15.

FNP-1/2-STP-20.2. " Penetration Room Filtration System Train A(B)

Monthly Operability Test," Revisions 7 and 7. and

FNP-1/2-SOP-60.0. " Penetration Room Filtration System."

Revisions 10 and 12.

The procedures all stated "Do not run

Penetration Room Filtration within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> following significant

painting (>1000 ft') in the penetration rooms."

The licensee was not able to provide an existing analysis

2

documenting the 1000 ft limit.

On May 9. the inspectors

'

discussed the continuing painting efforts of rooms within the PRB

without an analysis with senior licensee management.

Licensee

management stated they would stop painting in rooms served by a

safety-related charcoal unit until the issue was resolved.

This

is identified as URI 50-364/97-05-06. Painting Effects On PRF

Operability pending review of the licensee's analysis.

e

On April 25. 1997, the ins)ectors toured the EDG building to

specifically inspect the EE fuel racks. valves, and other

components for paint related problems. The inspectors found no

overspray on the fuel racks.

However. some paint was found on the

valve stems for the air header drains on one EDG.

This condition

was identified to the EDG S0 and immediately corrected.

Enclosure 2

. _ _

_ _ - _ . _ _ _ . - - . . - - -

-

. - - - . - - .

- -

-

.

'

.

.

i

22

!

c.

Conclusions

Painting was generally well-controlled, although, some minor

deficiencies which did not affect operability were identified with

overpainting of components in the EDG building.

However, the painting

of rooms in the PRB, while controlled, did not appear to have an

analysis to document continued operability of the PRF charcoal filters.

M8.2 (Closed) VIO 50-348. 364/96-006-01: Failure to Perform Surveillance Test

of SI Handswitch Inout

(Closed) LER 50-348. 364/96-004: Surveillance Reauirements Not Met for

Manual Safety In.iection Inout into the Reactor Trio System

(Closed) LER 50-348. 364/96-004-01: Surveillance Reauirements Not Met

l

for Manual Safety In.iection Inout Into the Reactor Trio System

l

,

The licensee's review of Generic Letter 96-01 identified that the

18-month surveillance test for the manual SI input into the reactor trip

system had not been performed since initial preoperational startup

t

testing. The licensee implemented FNP-1/2-STP-38.3. " Verification of

'

Manual SI Actuation Input to Reactor Trip," to 3rovide guidance and a

means to document completion of the test.

The Jnit 2 SI Handswitch was

satisfactorily tested prior to Mode 2 entry after the Fall 96 outage.

The -inspectors observed the satisfactory performance of the Unit 1 SI

.

Handswitch test on April 23, 1997. The licensee also performed a

broadness review of events from January 1993 to August 1996 which

i

resulted in an LER or were identified as a near miss.

This review was

documented in Corrective Action Report 2208 and concluded that the

'

primary root cause appeared to be a failure of personnel to adequately

self-check. The inspectors verified the licensee's corrective actions

were appropriate and complete.

M8.3 (Closed) IFT 50-364/96-013-02: Increased Freauency Test Proaram for

Charaina Pumos Due to Claddina Crackina

,

This item was opened pending formal recommendations and actions for

performing increased frequency testing of the charging pumps due to

!

cladding cracks. Southern Company )rovided the formal recommendations

1

for increased frequency testing to INP by-letter dated April 9. 1997.

,

The recommendations were:

o

2A CCP: UT every six months for three cycles then UT every

36 months. VT after three cycles then every five years (actually

'

will be done every 54 months).

J

l

e

All other CCPs:

UT every 36 months and VT upon disassembly.

Based on a review of the available data and verification of the testing

incorporated into the PM data base, the inspectors concluded these

Enclosure 2

- -

- _ _

.-

--

.

.

'

.

.

1

23

intervals would be adequate to ensure that pump degradation would be

identified prior to any operability concerns.

,

1

M8.4 (Closed) LER 50-348. 364/96-002: Technical Soecifications Surveillance

Reauirements Not Met and Common Cause Failure Identified

This issue was discussed in detail in IR 50-348, 364/96-04 and closed

'

out as NCV 96-04-03. Failure To Adequately Test RCP Underfrequency

Reactor Trip Relays. No new issues were revealed by the LER.

III. Enaineerina

El

Conduct of Engineering (IP 37551)

i

E1.1 Overstressed Unit 1 Reactor Coolant looD oue To Inadeauate Gaos 8etween

'

SG Lateral Suocorts

a. Insoection Scooe (37700)

The inspectors reviewed the pipe stress and support calculations.

modification packages and inspection records and discussed the SG

support gap on SG loop C with the engineers from Westinghouse Electric

Company. Southern Nuclear Operating Company (SNC), and Southern Company

Services (SCS) to determine if licensee activities complied with

industrial standards. regulatory requirements, licensee commitments, and

American Society of Mechanical Engineers (ASME) and American Institute

of Steel Construction (AISC) codes.

b. Observations and Findinas

i

The licensee identified that excessive vibration had occurred on the RCP

in Loop C of Unit 1 during normal operation. The licensee 3erformed an

inspection at cold shutdown condition during the current scleduled

refueling outage and found that several of the lower lateral supports on

reactor coolant loop (RCL) C piping had excessive gaps and that support

LS-12 had a gap 0.7-inch smaller than designed.

The designed gaps are

established to allow for SG thermal growth to close toward, but not

touch the supports during normal operation temperature of 610 degrees F

( F).

The licensee determined that the excessive gaps would cause no

i

problem.

The smaller gap would cause binding to occur in Support LS-12

l

when the operating temperature exceeded 445 *F. which would induce

thermal expansion stress in Loop C piping, components, and supports.

l

The thermal expansion stress could represent a situation that caused

damage to the piping or supports.

!

i

I

Enclosure 2

..

.-

_.

.-

-

_ . _ . . _ _ . . _

._

..

.

.

.

24

j

The licensee took the following actions to correct the prot,lem:

-

Performed stress analyses and evaluation for the piping,

components,.and supports based on the ASME Code Section III and

AISC Code.

-

Inspected piping.. components, and sup] orts for cracks,

deformations, and distress based on tie ASME Code Section XI.

-

Modified the existing shims by providing adjustable shims to

adjust the gaps to the desired dimensions.

The ins]ectors reviewed the following calculations performed by

Westinglouse and SCS for the licensee:

j

1)

Westinghouse Calculation W-SMT-97-067. Farley 1 RCL Support

Interference Thermal Pipestress Run, Rev. 0

2)

Westinghouse Calculation W-SMT-97-066. 3D Finite Element Analysis

of the Hot Leg 50 Degrees Elbow Using Jamming Loads, Rev. 0

3)

Westinghouse Calculation W-SMT-97-061. Farley Unit 1

Uprating/ Jamming - RCL Fatigue Evaluation Rev. O

4)

Westinghouse Calculation CSE-04-97-0036, Analysis of Steam

T.nerator Lower Support Strut Jamming Condition. Rev. 1

5)

SCS Calculation SC-97-1-9162-001. Evaluation of LS-12 Embed Steam

Generator IC, Rev. O

Calculation W-SMT-97-067.used a 3D computer model and pipe stress

computer program PIPESTRESS for the system analysis.

The model included

three loops, a reactor vessel, and three steam generators. The model

also considered gaps, the local shell flexibility of the reactor vessel

nozzle shell junction, and the horizontal stiffness of the reactor

vessel supports.

The results indicated that the critical stress was 67

kips per square inch (ksi) at Node 3216 of the elbow area, which

exceeded the ASME Code allowable stress of 51 ksi.

Calculation W-SMT-97-066 used a 3D finite element program WECAN and the

loads from the calculation W-SMT-97-067 to get more accurate results

based on a finite element model.

The critical stress was 45.3 ksi at

Node 15792 at the safe end of the reactor nozzle.

The critical stresses

at the weld between the elbow and the SG and at the elbow were 43.2 ksi

i

and 40.6 ksi respectively. Both stresses were within the allowable

stress of 51 ksi and were acceptable.

Calculation W-SMT-97-061, performed for the fatigue analysis, was based

on the past plant operating data such as start-up cycles, transients,

and predicted future operations.

The critical accumulated usage factor

Enclosure 2

i

_

. _ _ _ _

_ . _ .

._ _____

__ ._

_ . _ . _

'

.

.

.

25

was 0.974 at the outlet nozzle of the reactor vessel. The calculated

usage factor was less than 1.0 and therefore the current piping

condition is acceptable.

Calculation CSE-04-97-0036 was performed to assess the condition of the

steel portion of support LS-12 utilizing a calculated direct force of

2494 kips and a shear force of 113 kips.

The stress ratio for the

postulated seismic event upset and faulted conditions were 1.22 and 0.98

respectively.

The 1.22 ratio exceeded the allowable value of 1.0.

Thus, the steel could have been overstressed during a seismic event.

The licensee concluded that the support was acceptable as is, though,

since no deformations or cracks were found during the licensee's

walkdown inspection.

Calculation SC-97-1-9162-001 evaluated the embedded steel and concrete

and determined that the concrete was acceptable. The stress in the

embedded steel was 12 Jercent over the allowable stress for the faulted

,

condition.

However, t1e licensee concluded this condition was also

l

acceptable because no cracks or deformations were found during the

walkdown inspection.

The inspectors-concluded that the calculations were adequate.

Based on

discussion with the inspectors, the licensee planned to incorporate into

the calculations and plant procedures several changes as listed below:

-

Add the cross reference for the qualification of the critical

stress 45.3 ksi at the nozzle of the SG to Calculation

W-SMT-97-066.

1

-

Clarify the critical node numbers selected for the fatigue

analysis in Calculation W-SMT-97-061, which were incorrect and did

i

not match the stresses in the analysis.

The selected stresses

were correct.

i

1

-

Develop a procedure for monitoring the support gaps during the

subsequent heatup and cooldown.

,

Design Change Package DCP 97-1-9162-0-001 was reviewed for adequacy of

its 10 CFR 50.59 evaluation and the shim modification.

The inspectors

!

concluded that the design change was acceptable.

4'

c.

Conclusions

The inspectors concluded that the calculations were acceptable based on

i

their review of portions of the calculations.

The licensee promptly

'

evaluated the potential of past damage to the piping or supports and

q

restored the intended conditions through the modifications.

i

.

'

.

Enclosure 2

<

i

!

1

.

.

. ._ .

__.

. _ ._ . _____._ __._.___.__

_

'

.

.

.

26

E1.2 Licensino Basis of PRF System

As documented in IR 50-348, 364/97-04, dated April 2.1997, the

'

inspectors concluded that the PRF system was required to operate during

post-LOCA recirculation for'any size LOCA and proposed various apparent

violations.

During the subsequent pre-decisional enforcement conference

on April '18. '1997. SNC management disagreed with the NRC inspectors and

stated the PRF system was only required to operate under large break

LOCA conditions (i.e.. Condition IV events).

Following the enforcement

conference the NRC determined that several violations of NRC

requirements had occurred and issued a Notice of Violation (NOV) by

letter dated May 6, 1997.

In this letter the NRC acknowledged that SNC

did not agree with the inspectors' conclusions regarding the licensing

,

basis for the PRF system and stated that the matter was under review by

the Office of Nuclear Reactor Regulation (NRR).

The issue is identified

'

as URI 50-348, 364/97-05-07. Licensing Basis for PRF System During Post-

LOCA Recirculation, pending additional review of this issue by the NRC.

i

E8

Miscellaneous Engineering Issues (92903)

,

'

E8.1

(Closed) URI 50-348. 364/96-013-04: Common Tao for SG Steam Flow

Transmitter and Narrow Ranae Water Level

(Closed) LER 50-348/96-007: IEEE-279 Reauirements Not Met for Protection

Channel III

By letter dated April 29. 1997, the licensee submitted a request for a

" proposed alternative" to Section 4.7.3. Control and Protection System

Interaction-Single Random Failure, of IEEE 279-1971 pursuant to 10 CFR 50.55a(a)(3).

SNC implemented interim administrative controls which

provide an acceptable alternative until necessary protection / control

system hardware changes can be im)lemented during the next Unit 1 and 2

refueling outages in 1998 (i.e.

J1RF15 and U2RF12).

The NRC has

reviewed SNC's administrative controls and considers them acceptable as

j

an interim measure until such time as it can review the licensee's

request. Resident inspectors have verified implementation of the-

interim administrative controls. interviewed responsible operators on

their knowledge of these controls, and reviewed applicable procedural

requirements in FNP-0-SOP-0 " General Instructions To Operations

Personnel." Revision 47.

This URI and LER are closed.

Enclosure 2

- ..

. . _ , . __ . _ _ _ _ _ _ _ _ . _ _ _ . _ _ _ _ . . _ . .

. _ _... _ . _

. _ ._

A

1

,

,

27

)

IV. Plant Support

R1

Radiological Protection and Chemistry (RP&C) Controls

R1.1 Radioloaical Controls

a.

Insoection Scoce (IP 83750)

Radiological controls associated with ongoing Unit 1 (U1) Refueling

!

j

Outage Number 14 (U1RF14) activities and with Unit 2 (U2) routine

operations were reviewed and evaluated by the inspectors.

Reviewed

i

program areas included area postings, radioactive waste (radwaste)

'

container bibels, controls for high and locked-high radiation areas,

i

i

arocedurf and radiation work permit (RWP) guidance and general

I

l

lousekee)ing and cleanliness.

Established controls were compared

1

against rinal Safety Analysis Report (FSAR) details and documented

!

procedural requirements to meet applicable sections of Technical

Specifications (TSs) and 10 CFR Part 20.

'

l

l

The insaectors made frequent tours of the radiologically controlled

l

areas (RCAs).

Radiation work permit guidance and selected survey

results were reviewed and discussed with responsible Health Physics (HP)

l

,

staff and supervisors. The inspectors directly observed worker and HP

technician performance and discussed results of radiation and

contamination surveys conducted for selected equipment and facility

locations. Specific radiological controls and adequacy of surveys

associated with movement of materials out of the U1 Containment

equipment hatch. a U2 power entry and for a piece of loose metal

retrieved from the U1 reactor cavity were reviewed and discussed in

detail.

Further, the inspector reviewed and discussed occurrence

reports for three personnel contamination events (PCEs) associated with

outage activities.

For the PCEs reviewed,

the inspectors evaluated and

discussed licensee assumptions, dose methods and skin dose results in

detail.

1

The irispectors discussed and reviewed "As low as Reasonably Achievable"

(ALARA) program implementation. individual worker doses, and dose

expenditures associated with the following U1RF14 outage job evolutions,

e

RWP 197-1435. Incore Drive Work

l

!

e

RWP 197-1438, Seal Table / Thimble Cleaning

e

RWP 197-1439. Gamma Metrics Detector Work

<

l

e

RWP 197 1465, Lower Internals Movement

.

e

RWP 197-1480, Scaffolding - Containment

i

e

RWP 197-1730. Nozzle Dam Removal

l

Enclosure 2

,

l

4

i

. _ , _ _ . _ _- --

-

. _ . - -

._

. .

.

.

I

28

a

b.

'"orvations and Findinas

dnd locked-high radiation area controls were verified to be

splemented in accordance with TS requirements.

Postings for

radiologically controlled areas were proper and in accordance with TS or

10 CFR 20 Subpart J requirements.

Containers holding radwaste,

contaminated materials and equipment were labeled in accordance with

i

10 CFR 20.1904 requirements.

In general, workers followed proper radiological controls.

Radiological

controls and surveys associated with the U2 power entry to inspect

j

i

containment coolers and for a piece of metal having contact dose rates

i

of 1630 rem per hour, which was retrieved from bottom of +he U1 reactor

i

cavity, were conducted in accordance with approved procedo,es.

However,

i

several instances of individuals reaching across radiation control

'

boundaries during movement of equipment into and out of the U1 equipment

hatch were identified on April 7,1997.

'

For individuals involved in licensed activities, year-to-date (YTD) dose

estimates were within regulatory limits.

The maximum total effective

dose equivalent (TEDE) value reported was approximately 1510 millirem

(mrem).

Licensee skin dose evaluations for the PCEs reviewed were

thorough and technically adequate. Assumptions and details regarding

physical location, length of exposure and isotopic characteristics of

'

particles or contamination were appropriate. All skin doses were within

regulatory limits with a maximum exposure of 10.7 rem to the skin of the

whole body for a worker installing service water valve parts in the U1

pipe penetration room on the 121 foot elevation.

From discussion with responsible staff and from review of planning

4

documents and dose expenditures, the inspectors verified implementation

of ALARA program activities in accordance with FNP-0-Radiation Control

Procedure (RCP)-19. Pre an( Post Jcb Planning for Work in Radiation

Controlled Areas of the Plant. Revision 10. dated January 9, 1997.

In

<

particular, the inspectors reviewed and discussed planning for

replacement of the gamma metrics detector and the removal and

reinstallation of the reactor vessel lower internals.

Significant

-

reduction in dose expenditure was identified for tasks associated with

the lower internals.

The current dose expenditure of approximately

807 millirem (mrem) was reduced significantly relative to previous dose

expenditures of 6095 mrem and 2179 mrem for the same tasks conducted

during the U1RF8 and U2RF8 outages, respectively.

c.

Conclusions

i

Radiological controls for routine U2 operations and U1RF14 outage

activities were good.

Several minor isolated instances of poor

J

radiation control practices were identified.

Personal doses were

Enclosure 2

.

-

-.

. . -

- - .

=

. - - _ - ._-

--

.

- -.

.

.

.

29

maintained within regulatory limits.

ALARA program activities were

implemented effectively.

R1.2 Internal Exoosure

a.

Insoection Scoce (IP 83750)

The inspectors discussed program guidance for monitoring and evaluating

possible internal ex)osures, and reviewed in detail licensee results for

investigative whole Jody counts conducted during the current Unit 1

outage.

'

In addition, guidance for testing and test results to ensure quality of

supplied breathing air for respiratory protective equipment were

reviewed and discussed.

'

b.

Observations and Findinas

As of April 11. 1997, six investigative whole-body counts associated

with events which could indicate potential internal exposure during

,

U1RF14 outage activities were conducted.

The maximum u)take was

,

approximately 1.6 derived air concentration-hours (DAC-irs) resulting in

a committed effective dose equivalent (CEDE) of 3.11 mrem.

Because the

'

doses did not exceed 10 mrem. i.e.

0.2 percent of the annual limit of

intake (ALI), the resultant internal exposures were not added to the

individuals' official exposure records,

i

l

The inspectors verified that the compressor systems used to supply

breathing air were tested to certify Grade D air for potential use

during outage activities.

Breathing system air samples were collected

quarterly in accordance with FNP-0-RCP-110. " Radiation Control and

Protection Procedure. Sampling of Service Air to Meet Res)iratory

Limits." Revision. 4. and FNP-1-RCP-1112. " Operation of t1e Containment

,

Preathing Air System." Revision.12.

Sample results collected in March

'

1997 verified that the supplied breathing air quality exceeded the

established limits for Grade D air specified in the Compressed Gas

Commodity Specification G7.1.1973.

c.

Conclusions

Controls for minimizing internal exposure were effective.

Potential

,

!

uptake of radionuclides were evaluated appropriately.

Licensee tests

'

verified that the service air compressor system supplied Grade D

respirable air in accordance with 10 CFR 20. Appendix A requirements.

.

Enclosure 2

.,

,

-

.

30

l

R2

Status of Radiological Protection Facilities and Equipment

R2.1 Tours of the Unit 1 and 2 Radioloaically Controlled Areas (RCAs)

(IP 71750)

1

During the course of the inspection aeriod, the inspectors conducted

tours of the Unit 1 and 2 auxiliary auilding RCAs.

In general, health

physics (HP) control over the RCA, and the work activities conducted

within it, were good.

R5

Staff Training and Qualifications in Radiation Protection and Chemistry

R5.1 Resoirator Trainina and Fit Testing

l

a.

Insoection Scoce (IP 83750)

The inspectors reviewed and evaluated General Employee Training (GET)

provided to meet the requirements of 10 CFR Part 19, and the specific

.

training and medical certification requirements specified by

j

10 CFR Part 20. The frequency of training and fit testing was compared

to the guidance listed in American National Standards Institute

(ANSI) Z88.2. Practices for Respiratory Protection, May 19, 1992.

Current training, fit testing and medical certification for selected

contractor and licensee personnel who used or were designated to use

i

respiratory protection equipment were reviewed and discussed with

!

licensee representatives.

n

i

In addition, the frequency of training and fit testing was compared to

j

the guidance listed in ANSI Z88.2. Practices for Respiratory Protection,

1

l

May 19, 1992.

!

b.

Observations and Findinas

'

.

The inspectors verified that GET. respiratory protection training, and

respiratory medical certifications were conducted in accordance with the

2

requirements of 10 CFR 19.12, 10 CFR 20.1703 and licensee 3rocedure

FNP-0-RCP-101, "Use and Testing of Respiratory Protection Equipment "

-

Revision 24.

From review of training records of selected individuals

'

!

listed on " Respiratory Protection Record," HP Form-257, issued during

l

March and April 1997, the inspectors verified that persons who used

respiratory protection equi) ment were trained and medically certified in

j

.

accordance with the applica)le procedures.

!

The frequency of verifying medical certification met recuirements

specified in 10 CFR 1703.

However, the inspectors notec that

FNP-0-RCP-101 only s)ecified training and fit testing to be conducted

,

every five years ratler than annually as recommended by ANSI Z88.2.

'

'

Licensee representatives informed the inspectors that revisions to the

procedure would require annual training and fit testing at a five year

i

Enclosure 2

,

i

.-

_

_

_

.

31

interval.

Following these discussions, licensee management stated that

the fit testing frequency would be reviewed.

c.

Conclusions

Training and medical certifications for personnel using respiratory

protective equipment were conducted in accordance with the licensee

procedures and met the applicable requirements of 10 CFR Part 19 and

10 CFR Part 20.

R8

Miscellaneous RP&C Issues (IP 83750, IP 84750)

R8.1

(Closed) VIO 50-348. 364/96-10-02: Failure to Follow a March 14. 1983

Order to Imolement and Maintain Commitments for Soecial Calibration of

the Containment Hiah Radiation Monitors (CHRMs)

Licensee STPs for the loop calibration of the CHRMs did not include

in-situ calibrations using electronic signal substitution for all range

decades above 10 Roentgens per hour (R/hr).

From review of

FNP-2-STP-227.18 and FNP-2-STP-227.19. the inspectors verified that

guidance was revised to include an electronic calibration check for each

decade of the required response range. The inspectors also verified

from review of data for completed U2 CHRM STPs conducted in November

1996 that the required electronic calibration was completed

satisfactorily. Completion of the in situ electronic calibration was

scheduled for the U1 CHRMs during the current outage.

This VIO is

closed.

R8.2 (Closed) VIO 50-348. 364/96-10-03: Failure to Label Casks of

Contaminated Resins in Accordance with 10 CFR 20.1904(a) Reauirements

Licensee documents and training emphasized labeling recuirements based

on dose rates rather than radionuclide quantities and cid not require

specific information detailed in 10 CFR 20.1904.

The ins)ectors

verified that FNP-0-RCP-57. " Radioactive and Potentially Radioactive

Material Handling " Revision 23. required appropriate labeling

information to be provided based on specific quantity of radioactive

material rather than measured dose rates.

From review of licensee

records the inspectors verified that management expectations regarding

container labeling requirements were verbally communicated in August

1996 to site health physics (HP) personnel and formal training regarding

the procedural revision was conducted during December 1996.

In December

1996. HP personnel conducted walk-downs of the RCA to verify compliance

with labeling requirements.

In addition, licensee representatives

stated that additional training regarding labeling requirements for

specific situations, e.g., liquids and alpha-emitting radionuclides or

liquids would be reviewed and discussed with HP staff and personnel.

l

The inspectors toured the RCA and verified implementation of the current

procedural requirements.

This violation is closed.

Enclosure 2

l

. _ . _ . _ .

._ .

_

... _ _ _ _ _ _ _ _ .. _ . _ _ _ . _ - _ _ _ _ . _

.

.

.

.

)

32

.R8.3 .(Closed) VIO 50-348. 364/96-10-04: Failure to Follow Procedures for

,

Prooer Personal Dosimetry Use

l

Observations by both NRC inspectors and licensee HP staff identified

'

individuals within established RCAs not adhering to HP manual

i

requirements nor training guidance for use and placement of personal

dosimetry including thermoluminescent dosimeters (TLDs) and digital

alarming dosimeters (DADS).

From review of documents and direct

observations, the inspectors verified implementation of licensee

corrective actions.

On August 27, 1996, a memorandum was issued from

the HP staff to all su)ervisors detailing requirements for use of

personal dosimetry. T1e inspectors also reviewed and discussed results

of periodic HP staff dosimetry observations conducted between October 29

and November 25. 1996.

By November 25. the documented error rate for

use of personal dosimetry was less than one percent.

On November 27,

1996 memorandum documented a request to HP personnel to increase

vigilance of dosimetry use by facility personnel.

During tours of-the

RCA, the inspectors did not identify programmatic problems associated

with use of personal dosimetry. This violation is closed.

R8.4 (Closed) VIO 50-348. 364/96-10-05: Failure to Have Adeauate Procedures

for Liauid Effluent Comoosite Samole Storaqe

,

Licensee procedures for storing composite liquid effluent samples

collected for quantification of non-gamma emitting radionuclides did not

require use of standard methods such as acidification to prevent

i

plate-out of radionuclides on the storage container. The inspectors

verified that applicable procedures involving the storage of composite

4

samples were revised to require proper acidification of the liquid

i

samples. The inspectors reviewed and discussed results of a Chemistry

'

Incidert Report (CIR) completed to determine the effect of

non-preservation of affected liquid sam)1es.

Results of the study were

documented in the Section 6.3. Program Jeviations of the FNP Annual

Radioactive Effluent Release Report, dated April 21, 1997.

Results of

the study indicated that for the worst case assumptions regarding

plate-out, historical doses were understated from 3 to 7 percent but

were within limits specified in the Offsite Dose Calculation Manual

,

!

(ODCM).

Based on licensee actions and documentation, this violation is

closed.

R8.5 (Closed) VIO 50-348. 364/96-13-05: Failure to Follow Radiation Work

l

Permit for Use of Prooer Protective Clothina

!

The ins)ectors observed personnel performing selected tasks within the

i

RCA witlout use of the protective clothing specified by the respective

RWPs. The inspectors reviewed and discussed the results of surveys and

immediate corrective actions as documented in Occurrence Reports (ors)

96-1002 and 96-1003.

In addition. the inspectors verified that

j

personnel were retrained in RWP adherence and that additional emphasis

!

to RWP adherence would be stressed in general employee training.

In

l

Enclosure 2

-

. -. .

-.

.

.

..

..

. _ _ _ . _ _ _ _ _ _ _ _ .

__ . _ _ . .

___

.

.

7

.

.

i

33

addition, an HP memorandum, dated October 25, 1996, to site personnel

detailed the poor radiological practices observed and importance of

. proper radiological practices.

The inspectors also reviewed and.

i

discussed initial implementation of a licensee initiative to track,

trend and take more effective corrective actions regarding poor

radiation worker practices.

During tours of the RCA, the ins)ectors

verified that selected tasks were conducted in accordance witi

established RWPs. This violation is closed.

S1

Conduct of Security and Safeguards Activities

i

S1.1 Routine Observations of Plant Security Measures (IP 71750)

i

During routine inspection activities, inspectors verified that

of site security program plans were being properly implemented. portions

This

was generally evidenced by: proper display of picture badges by plant

i

personnel: appropriate key carding of vital area doors: adequate

stationing / tours in the protected area by security personnel; proper

>

searching of packages / personnel at the primary access point and service

water intake structure: and adequate maintenance of security systems.

Security personnel activities observed during the inspection period were

l

performed well.

Site security systems were adequate to ensure physical

'

protection of the plant.

However, on April 29, 1997, the inspector

)

observed numerous individuals in Unit 1 containment who were not

}

displaying their security badges.

Certain of these individuals were

challenged by the inspector regarding their badges, all of whom had

their security badges inside their outer anticontamination clothing.

When questioned by the inspector, they expressed a belief that security

badges were not required to be displayed in containment.

FNP-0-AP-42,

" Access Control." Revision 25, requires " security badges will be

)rominently displayed in plain view at all times." But Section 8.3 of

NP-0-AP-42 does allow wearing the badge beneath outer anticontamination

clothing when working in hiah contamination areas. Although the

containment was posted as a contaminated area, the inspector realized

that the vast majority of Unit 1 containment floor space was clean or

only slightly contaminated.

Discussions were held with the Security

Chief and HP Superintendent regarding plant worker misconceptions and

the intent of FNP-0-AP-42. The Security Chief and HP Su3erintendent

3romptly corrected the situation.

Subsequent tours by tie inspectors

lave not identified any repeats problems.

F1

Control of Fire Protection Activities

F1.1 Weldina and Grindina - Unit 1

During the week of April 7,1997, an inspector ooserved numerous

examples of poor fire prouction practices in the Unit 1121 foot

i

elevation PPl.

Work activities during this week were extremely

i

intensive in the PPR, as was the quantity of tools, equipment and

material brought in to support the work. Welding and grinding was

!

Enclosure 2

<

,.-4

_

- , . - ,

i%

+ , . - .

.

.

.

34

pervasive throughout the PPR as part of many of the ongoing jobs

(e.g. , SWS valve replacements high head safety injection discharge line

replacement and reroute). All welding and grinding observed by the

inspector was accomplished by contractors.

During tours of the PPR and

discussions with craft personnel, the inspector ascertained the

following: 1) WO's did not identify applicable Open Flame Permits:

2) Open Flame Permits were not routinely posted for each job, inclusion

of many work activities on one Open Flame Permit made for confusion:

3) control of combustibles within a 35-foot area of the hot work was

very poor (in one instance the inspector observed a burlap bag ignite

and catch fire). 4) fire watches were tasked with ancillary duties,

which in a few cases recessitated the fire watch to leave the immediate

area 5) inadequate fire extinguishers (e.g., beyond inspection date,

partially discharged), 6) fire extinguishers were not in the immediate

area, and difficult to iocate, and 7) apparent discharging of fire

extinguishers without notifying Operations or supervision.

Furthermore,

during several containment tours in the month of April, the inspector

observed additional poor fire protection practices especially for

welding and grinding conducted in elevated areas.

These poor practices

involved floors not swept clean within 35 feet; and inadequate or

non-existent covers beneath work to collect sparks.

The quantity and

widespread nature of the aforementioned problems suggests a weakness in

the implementation of the licensee's fire protection program for

controlling open flame work.

Upon notification of the findings made

during the week of April 7. licensee management took prompt actions.

The inspectors will review the actions taken by the licensee to correct

this weakness.

F2

Status of Fire Protection Facilities and Equipment

F2.1 Half-Hour Kaowool Fire Barrier

Inspection Report 50-348, 364/96-09, issued November 8, 1996, documented

i

the failure to install Appendix R required fire barriers on various

electrical raceways on Unit 1 including BDE-15 (Train B charging pump

l

power cables) and BHF-24 in room 160. The failure to install an

A)pendix R required fire barrier on BDE-15 was cited as an example of

EEI 96-410/01013.

On November 14, 1996, while touring the AB. the

inspectors observed the installation of Kaowool on raceways BDE-15 and

BHF-24 in room 160. The wraps consisted of a 1-inch layer of Kaowool on

the sides and bottoms of the trays. A one-hour rated barrier requires

two 1-inch layers on all four sides.

l

!

The inspectors identified this discrepancy to the licensee on

'

November 14.

The licensee provided a co)y of Fire Protection Program

Reevaluation. Amendment 5 (precedes the :SAR documented Fire Protection

'

Program), which documented the installation and basis of " half-hour

barriers" on BDE-15 and BHF-24.

The inspectors reviewed FSAR

Appendix 98, Fire Protection Program, and found no mention of half-hour

'

Enclosure 2

.

-

=

---

_

.

.

--

.

.

.

35

barriers in it or Attachment B.10 CFR 50 Appendix R Exemptions.

FSAR

Appendix 98. Attachment B. Section 21.3 on page 9B.B-91 states that:

"The redundant charging Jump power cables are provided with a

barrier (two 1-inch thicc wra)s of Kaowool blanket) having a fire

rating greater than that of t1e projected fire in the following

rooms in fire area 1-004:

train A in rooms 161. 162. 163. and

168; train B in rooms 175. 160 and 159."

This issue was discussed further with the licensee on November 15. 26.

December 9. and March 20, 1997.

The licensee's )lanned corrective

action was to modify the FSAR Appendix 9B. Attac1 ment B to " clarify"

that these raceways were wrapped with half-hour barriers (1-inch Kaowool

fire wrap). The inspectors informed the licensee that this

" clarification" would misrepresent FSAR Appendix 9B. Attachment B, to

'

read as though the " clarification" was part of the original NRC-approved

exemptions.

The licensee's position was that there is a licensing basis for the

half-hour barriers based upon SERs and NRC inspections pre-dating

10 CFR 50. Appendix R requirements. The inspectors disagreed because

the use of half-hour barriers was not identified as a s)ecific exemption

from Appendix R requirements in FSAR Appendix 98. Attac1 ment B.

As

interim corrective action the licensee has taken action to ensure that

a one-hour roving fire watch is maintained on room 160 until this issue

is resolved.

This is identified as URI 50-348/97-05-08. Installation Of

Half-hour Kaowool Fire Barriers Without Appendix R Exemption, pending

NRR review.

,

F2.2 (Ocen) IFI 50-348. 364/96-006-07:

Fire Main Failures

l

This item was opened pending metallurgical analysis of the failed piping

and implementation of long term corrective actions.

Southern Company

Services (SCS) provided the results of the metallurgical analysis and

recommendations for action via letter dated December 5, 1996. A ten-

inch cast iron pipe failed due to a pressure excursion at a degraded

section of pipe.

A four-inch pipe failed as the result of localized

exterior corrosion (due to wet insulation).

SCS stated that there was

little in the way effective ins)ection that could be performed to

determine the integrity of the Juried cast iron-lined pipe.

However.

regarding the four-inch pipe failure, they did recommend visual

,

examination of readily accessible pi)e in areas where water would tend

l

to accumulate. As of May 7, 1997, tais recommendation had not been

'

implemented. This IFI will remain open pending resolution of necessary

corrective actions.

1

Enclosure 2

.._. ,---.

_-. - -

.

- . ..

- -

- - ._ - - - . - . - .-

.-

,

l

.

.

.

36

F2.3 Inadeauate Life Safety Exits from Turbine Buildino in Case of Evacuation

On May 1.1997, and then again on May 2. with an industrial safety

specialist. an inspector walked down the TB exits.

The inspector

identified numerous deficiencies with the exit signs and evacuation

design scheme for the turbine building from a Life Safety perspective.

Examples of these deficiencies were: 1) Missing Exit signs. 2) Burned

out and/or broken Exit signs. 3) Nonvisible Exit signs. 4) Exit sign for

,

a nonexit door. 5) Inadecuate fire barriers for allowing personnel to

)

safely exit the south enc of the TB. and 6) No directions or signs in

the 155-foot stairwells to guide personnel on how and where to evacuate

the TB. These problems were pointed out to the safety specialist and

discussed with plant management, who were evaluating necessary

corrective actions.

V. Manaaement Meetinas and Other Areas

X1

Review of Updated Final Safety Analysis Report (UFSAR) Commitments

A recent discovery of a licensee o)erating its facility in a manner

contrary to the UFSAR description lighlighted the need for a special

focused review that compares plant practices, procedures and/or

parameters to the UFSAR descriptions.

While performing the inspections

discussed in this report. the inspectors reviewed the applicable

portions of the UFSAR that related to the areas inspected.

The

inspectors verified that the UFSAR wording was consistent with the

observed plant practices, procedures and/or parameters, except for the

following discrepancies:

(a)

Table 7.3-1. FUNCTIONS INITIATED BY ENGINEERING SAFETY FEATURES

ACTUATION SYSTEM. This table implies that PRF will actuate

simultaneously with equipment that is started on a SI signal.

Phase A and phase B actuation equipment is identified separately

and later in the table and PRF is not identified as actuating

equipment.

(b)

Table 7.3-9. FAILURE MODE AND EFFECTS ANALYSIS. PENETRATION ROOM

FILTRATION SYSTEM.

This table lists the analysis concerning the

effect on the system if a failure occurs and a PRF component is

not automatically aligned during a Phase A CTMT isolation signal.

(This represents an identification problem.)

i

(c)

The Staff's SER. NUREG-75/034. SAFETY EVALUATION REPORT JOSEPH M.

l

FARLEY NUCLEAR PLANT UNITS 1 AND 2. dated May 2. 1975, states that

the PRF will actuate on a Safety Injection signal and this

statement has not been incorporated into the FSAR or into plant

design.

2

Enclosure 2

- .- _ . - . _ ._ _ _ _ _ _ . _ _ ____ __

~ _ _ . _ . _ _

.

.

.

.

37

(d)

FSAR Chapter 1.3, COMPARISON TABLES, Table 1.3.1. DESIGN

COMPARISON identifies that FNP system functions are similar to

those of the North Anna and Surry Nuclear Power Plants.

However,

with regard to the PRF system _(Section 7.3 of the FSAR) the FNP is

not similar.

(e)

FSAR page 7.3-11 section 7.3.2.1.1. Single Failure Criteria,

sentence 6 states that CTMT s) ray is activated on high-high

containment pressure signal, lowever it actuates on high-high-high

j

containment pressure.

(f)

FSAR page 6.2-84. section 6.2.3.3.2 references paragraph

,

j

15.4.1.3.4. which does not exist.

l

4

Responsible licensee management were informed on each of the above

discrepancies, many of which the licensee had already identified as part

a

of its FSAR Reverification Program.

Several of the discrepancies are

!

involved with the NRC/SNC reviews regarding PRF system design and

j-

licensing basis (Section E1.2).

X2

Exit Meeting Summary

J

The inspectors presented the inspection results to members of licensee

i

management on May 15. 1997, after the end of the inspection period.

The

i

licensee acknowledged the findings presented.

The inspectors asked the licensee whether any materials examined during

the inspection should be considered proprietary.

No proprietary

i

information was identified.

f

PARTIAL LIST OF PERSONS CONTACTED

)

l

Licensee

!

M. Ajluni, SNC (Corporate) Licensing Manager - Farley Project

-

j

W. Bayne, Chemistry Superintendent

C. Byrd, Southern Company Services (SCS) Support Design Engineering Manager

!

S. Casey. Engineering Su3 port Supervisor - Steam Generators

R. Coleman Maintenance Manager

!

J. Fridrichsen. SNC (Corporate) Senior Project Engineer

S. Fulmer. Technical Manager

J. Garlington. Nuclear Support General Manager

1

!

D. Graves. Health Physics Supervisor

l

D. Grissette. Operations Manager

j

P. Harlos Plant Health Physicist

i

T. Harrison. Williams Power Corporation (WPC) Site Manager

J. Hayes, Fire Marshall

'

2

R. Hill. General Manager - FNP IP 73753:

Inservice Inspection

C. Hillman, Security Chief

T. Liu. Westinghouse Electric Company (WEC) Farley Special Project Manager

,

i

l

Enclosure 2

4

I

4

,

-

, - - . - -

- - - -

- - . , -

-

-

-

.-

---

.

.

,

'

.

.

!

i

38

G. Lofthus. NDE Level III Inspector

i

R. Martin. Su)erintendent Operations Support

'

A. Maze. NDE project Supervisor

J. McGowan SNC (Cor) orate) SAER Manager

l

M. Mitchell. Health 3hysics Superintendent

'

B. Moore. SNC (Corporate) Nuclear Support Manager

C. Nesbit. Assistant General Manager - Support

j

J. Odom. Superintendent Unit 1 Operations

J. Powell. Su]erintendent Unit 2 Operations

C. Sterzil. WEC Farley Special Project Support Design Engineer

{

L. Stinson.-Assistant General Manager - Plant Operations

j

J. Thomas. Engineering Support Manager

i

J

P. Webb. Technical Training Supervisor

'

d

R. Winkler. Plant Modifications and Design (PMD) Supervisor

i

R. Yance. PMD Manager

i

!EC

J. Zimmerman Project Manager - Farley Nuclear Plant

-

i

INSPECTION PROCEDURES USED

i

IP 37551:

Onsite Engineering

'

i

IP 37700:

Design Changes and Modifications

j

IP 40500:

Effectiveness of Licensee Controls in Identifying. Resolving and

!

Preventing Problems

j

IP 60710:

Refueling Activities

)

IP 61726:

Surveillance Observations

1

IP 62700:

Maintenance Implementation

j

IP 62707:

Maintenance Observations

i

IP 71707:

Plant Operations

!

IP 71750:

Plant Support Activities

!

IP 73753:

Inservice Ins)ection

i

j

IP 83750:

Occupational

Radiation Exposure

?

IP 84750:

Radioactive Waste Treatment, and Effluent and Environmental

Monitoring

IP 92901:

Followup - Operations

IP 92902:

Followup - Maintenance

IP 92903:

Followup - Engineering

Enclosure 2

4

, _ _ .

..

- _ . . -

.

- . . _

_

_ _ __ _ _ __

_ _ . _ _ . . _ .

.

.

.

.

l

39

ITEMS OPENED CLOSED, AND DISCUSSED

Opened

[

IYgg Item Number

Status

Description and Reference

VIO- 50-348, 364/97-05-01

Open

Failure to Notify NRC of Change of

Licensed Operator Medical Status

(Section 05.1).

,

l

l

IFI

50-348, 364/97-05-02

Open

Foreign Material in Containment ECCS

l

Sumps (Section M1.7).

l

>

!

VIO

50-348, 364/97-05-03

Open

Failure to Follow Multiple TS

!

Surveillance Requirements

(Section M1.8).

URI

50-348. 364/97-05-04

Open

EDG 50% Load Reject Surveillance

Testing (Section M1.8).

VIO

50-348/97-05-05

Open

Failure to Control the Special

,

Process of Welding (Section M1.11).

l

URI

50-364/97-05-06

Open

Painting Effects on PRF Operability

!

(Section M8.1).

URI

50-348, 364/97-05-07

Open

Licensing Basis for PRF System

During Post-LOCA Recirculation

(Section E1.2).

URI

50-348/97-05-08

Open

Installation of Half-hour Kaowool

Fire Barriers Without Appendix R

,

Exemption (Section F2.1).

l

'

NCV

50-348, 364/97-05-09

Open

Failure to Fully Implement

Corrective Actions (Section 07.1)

i

Closed

.

Iygg Item Number

Status

Description and Reference

LER

50-348/97-002

Closed

Safety-Related 4160 Volt AC Breakers

Not Seismically Qualified

-

!

(Section 08.1).

LER

50-348/97-004

Closed

Safety-Related 600 Volt AC Breakers

Position Sensitive Seismic

Qualification (Section 08.1).

.

,

i

LER

50-364/96-001-00

Closed

Reduction / Resumption of 28 Diesel

l

Generator Speed (Section 08.2).

i.

Enclosure 2

<

. _ . _ _ _ _ _ . _ . _

_ _ _ . . _ _

.. . _ _ . _ . _ . _ . _

'

.

.

.

40

-VIO

50-348, 364/96-006-01

Closed

Failure to Per'orm Surveillance Test

of SI HandsC tch Input

(Section M8.2).

LER

50-348, 364/96-004

Closed

Surveillance Requirements Not Met

for Manual Safety Injection Input

into the Reactor Trip System

(Section M8.2).

LER

50-348, 364/96-004-01

Closed

Surveillance Requirements Not Met

For Manual Safety Injection Input

into the Reactor Trip System

(Section M8.2).

IFI

50-364/96-013-02

Closed

Increased Frequency Test Program For

Charging Pumps Due to Cladding

Cracking (Section M8.3).

LER

50-348. 364/96-002

Closed

Technical Specifications

,, 4

Surveillance Requirements Not Met

and Common Cause Failure Identified

(Section M8.4).

URI

50-348, 364/96-013-04

Closed

Common Tap for SG Steam Flow

Transmitter and Narrow Range Water

Level (Section E8.1).

LER

50-348/96-007

Closed

IEEE-279 Requirements Not Met for

Protection Channel III

(Section E8.1).

VIO

50-348, 364/96-10-02

Closed

Failure to Follow a March 14, 1983

Order to Implement and Maintain

Commitments for Special Calibration

of the Containment High Radiation

Monitors (CHRMs) (Section R8.1).

VIO

50-348, 364/96-10-03

Closed

Failure to Label Casks of

Contaminated Resins in Accordance

with 10 CFR 20.1904(a) Requirements

(Section R8.2).

VIO

50-348, 364/96-10-04

Closed

Failure.to Follow Procedures for

Proper Personal Dosimetry Use

(Section R8.3).

VIO

50-348, 364/96-10-05

Closed

Failure to Have Adequate Procedures

for Liquid Effluent Composite Sample

Storage (Section R8.4).

Enclosure 2

,

._ .

. . . . _ _ .

. ~ . _ - . . . . . - . - . _ . . _ . _ - . _ . _ -

_.__.____ . .

_ _ _ . - -

_ . . . _ .

.

.

,

'

-

!

.

.

i

41

VIO

50-348, 364/96-13-05

Closed

Failure to Follow Radiation Work

Permit for Use of Proper Protective

Clothing (Section R8.5).

NCV

50-348, 364/97-05-09

Closed

Failure to Fully Implement

Corrective Actions (Section 07.1)

~

Discussed

i

Iygg Item Number

Status

Description and Reference

. IFI

50-348, 364/96-006-07

Open

Fire Main Failures (Section F2.2).

4

.

5

2

-

i

l

1

1

i

Enclosure 2

!

i

f

4

--m-

,

..rw

--,, - <

-

- .-

. , - . - - . -

<.

s.---

-4

. - -

4

-