Forwards Quarterly Self-Monitoring Repts for Perry NPP Sanitary Waste Sys for Months of June,Jul & Aug.No Violations Occurred
ML20117N597
Person / Time
Site: Perry  FirstEnergy icon.png
Issue date: 09/13/1996
From: Stetz J
CENTERIOR ENERGY
To: Shelby R
LAKE COUNTY, OH
Shared Package
ML20117N598 List:
References
PY-CEI-LCDU-003, PY-CEI-LCDU-3, NUDOCS 9609190307
Download: ML20117N597 (1)


Text

  • l l

.. \

l GNTERDOR ENERGY PERRY NUCLEAR POWER PLANT Mail Address: l 10 CENTER ROAD PERRY, OHIO 44081 PERRY, OH10 44081 (216) 259-3737 l

1 September 13, 1996 PY-CEI/LCDU-0038L Lake County Department of Utilities Attention: Robert Shelby Mentor Waste Facility i P.O. Box 490 Painesville, Ohio 44077-0490 Gentlemen:

Enclosed are the Quarterly Self-Monitoring Reports for the Perry Nuclear Power Plant sanitary waste system for the months of June, July and August. All required samples were collected and analyzed in accordance  ;

with the self-monitoring program. No violations occurred during this l quarter.

Also included are the results from an isotopic analysis. No radioactive material was detected. .

If you have questions or require additional information, please contact Donna Tizzano at (216) 280-5514.

Very truly yours, John P. Stetz Sr. Vice President - Nuclear DGT:sc Enclosure cc: NRC Region III Administrator I NRC Resident Inspector -

fi NRC Project Manager NRC Document Control Desk ' Docket No. 50-440) 9609190307 960913 PDR ADOCK 05000440 s a PDR Operating Componies Cleveland Electric illuminating Toledo Ecison