ML20084Q009

From kanterella
Jump to navigation Jump to search
Informs of Internal Scheduling Conflict for 840627 Radiological Emergency Exercise Which Necessitates Postponing Drill Until 840725.Target Dates Based on Proposed Drill Date Listed
ML20084Q009
Person / Time
Site: Fort Saint Vrain Xcel Energy icon.png
Issue date: 05/11/1984
From: Warembourg D
PUBLIC SERVICE CO. OF COLORADO
To: Jay Collins
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
References
P-84143, NUDOCS 8405210063
Download: ML20084Q009 (2)


Text

.

public service company oe ecIlerado n 16805 WCR 19 1/2, Platteville, Colorado 80651 h r

/D 5

May 11, 1984 Fort St. Vrain Unit #1 P-84143 Mr. John T. Collins 33@MOMX*

Regional Administrator '

U. S. Nuclear Regulatory Commission g g 4g 611 Ryan. Plaza Drive, Suite 1000 g Arlington, TX 76011 (

SUBJECT:

1984 Fort St. Vrain Exercise REF: 1) Letter, Warembourg to -

Collins,3/22/84(P-84089)

2) Letter, Warembourg to Collins,4/10/84(P-84106)
3) Letter, Warembourg to Collins, 4/11/84 (P-84108)
4) Letter, Johnson to Lee, 4/27/84(G-84135)
5) Letter, Warembourg to Collins,5/4/84(P-84129)
6) Letter, Johnson to Lee, 5/4/84 (G-84147)

Dear Mr. Collins:

In reference 1), Public Service Company of Colorado (PSC) submitted a proposed schedule of items related to the 1984 Fort St. Vrain radiological emergency exercise. This schedule assumed that the conduct of the drill would take place on June 27, 1984.

Since submission of that schedule, a number of items have developed which necessitate postponing of the drill. Specifically, an internal scheduling conflict has developed; the State of Colorado has formally requested exemption from participation in the drill and PSC has followed this up with an exemption request (Reference 2, 4, 5); and the NRC has raised some questions on the scope and objectives of the exercise (Reference 3, 6). In addition, our conversations with your staff indicate that additional review time of our exemption request could be beneficial.

P'405210063 840511 b

PDR ADOCK 05000267 iQ F PDR

3 w.

When all these items are taken into consideration, we .think it would be prudent to postpone the exercise until July 25, 1984. Based on this exercise date, the following target dates are established:

1. Detailed Scenario On or before June 11, 1984
2. -Controller / Prompter Packages On or before June 11, 1984
3. Conduct F0SAVEX 84 July 25, 1984

'On a related matter, the NRC's request for additional information on -

the scope and objectives for the exercise (Reference 6), requested a written response by May 14, 1984. Since this letter was not received and distributed at the plant until May 11, 1984, the written response date of May 14, 1984, was unrealistic. Therefore, telephone responses were provided to Mr. J. B. Baird of your staff on May 11,>1984; a written response will be provided by May 18, 1984.

If I can provide any additional information, please let me know.

Very truly yours,

$d h Don W. Warembourg Manager, Nuclear Production Fort St.-Vrain Nuclear Generating Station DWW/djc

'cc: J. P. Byrnes - D0 DES Richard P. Holtz - 00 DES James. Montgomery - Region IV

James C. Baker -FEMA Robert A. Arnott - CDH f

>