ML20079E664

From kanterella
Jump to navigation Jump to search
Midland Independent Design & Const Verification Program, Monthly Status Rept 8 for Dec 1983
ML20079E664
Person / Time
Site: Midland
Issue date: 12/31/1983
From: Dougherty F, Levin H, Tulodieski D
TERA CORP.
To:
Shared Package
ML20079E648 List:
References
NUDOCS 8401170385
Download: ML20079E664 (38)


Text

4 i MIDLAPO IMJOENT DESIGN AfO CONSTRUCTION VERIFICATION PROGRAM MONTH Y STATUS REPORT NUMBER 8 PERIOD DECEMBER I,1983 THROUGH DECEMBER 31,1983 O

Prepared by: A An.v n Manager, Dbkn Ve(ificatiok he k.bt Manager, Construction Verification

/ '

Reviewed by: eu % --;,

Project Manager l

Approved by: k C. b, __

Princip#al-in-Chorge 0401170305 840113 PDR ADOCK 05000329 R PDR

i O

VERIFICAT;ON PROGRAM (IDCV)

MONTHLY STATUS REPORT NUMBER 8 PERIOD DECEMBER 1,1983 TiflOUGH DECEMBER 31,1983

1.0 INTRODUCTION

AND PURPOSE Monthly Status Reports have been instituted by agreement among Consumers Power Company (CPC), the Nuclear Regulatory Commission (NRC) and TERA to provide parties external to TERA's IDCV project team with up-to-date informo-tion relative to program progress and any impor: ant issues identified during the reporting period. This report coyers the period from December 1,1983 through December 31, 1983. A description of the scope, reporting periods and report issuance dates for Monthly Status Reports, as well as c summary of the background of the IDCV program, were presented in the initial Monthly Status Report dated May 27,1983.

2.0 IDCV PROGRAMi STATUS

SUMMARY

2.1 PROGRAMMATIC ACTIVITIES Attachment I provides on updated chronology of major project milestones. The project chronology from inception through the beginning of this reperting period con be found in the previous monthly status reports.

l The fif th OCR status meeting, originally planned for the end of December, was rescheduhd to January 4 to c foid conflict with the holidays. Programmatic l activities to be discussed at that meeting include clarification of the fact that the clock for the "10 doy" objective for responses to confirmed items starts with the OCR meeting where the item is first discussed. The "10 day clock" is used in determ ning when a confirmed item may be converted into o finding. It will also be noted that written responses are not needed for confirmed items but are B-84-07 i TERA CORPORATION

e i required for findings. Other items regarding status of OCRS and notification of revision of calculations will also be discussed.

By letter dated December 27 the NRC advised TERA of the acceptability of Law Engineering Testing Company to perform portions of the construction verifico-tion program. The NRC also formally accepted Revision 3 of the TERA Engineering Program Plan and Revision 4 of the PGAP for the Midland IDCVP.

During December TERA developed a structural engineering evoluotion of the diesel-generator building (DGB). Because of the timeliness of the issues involved, the engineering evoluotion was prepared in a format for public release.

This is on exception of the general IDCVP procedure of issuing only final reports and using the OCR process to identify matters requiring further reviews. In December review team members met in Ann Arbor to review DGB finite element and seismic stick models. The DGB engineering evoluotion is scheduled for release on January 4.

As noted in lost month's :.totus report, consideration is being given to o possible mid-course correction of the IDCVP. TERA project and management personnel have identified alternatives for making oppropriate corrections to the progtom.

Discussions among CPC, NRC, and TERA are contemplated but none is sched-

[ uled. TERA's near term priorities have been established so os not to foreclose

, desirable. refinements to the IDCVP.

I 2.2 DESIGN VERIFICATION ACTIVITIES 2.2.1

SUMMARY

l The most significaat activity in December was the completion of the engineering l evoluotion for the diesel-generator building. This evoluotion is scheduled for release on January 4.

l B-84-07 2 TERA CORPORATION

a %

Progress continued in all other arcos of the design verification review. Emphasi-was placed on completion of work previously initiated and dispositioning of OCRs.

2.2.2 AUXILIARY FEEDWATER SYSTEM PROGRESS In December the AFW system review continued, as it has in November, by concentrating on the disposition of OCRs and completien of supporting engineer-ing evoluotions. Lower priority is being given to completion of other engineering evaluations. No new engineering evaluations were initiated in December.

Review of auxiliary building structural topics continued but was slowed due to personnel being assigned to the engineering evaluation for the diesel-generator building. Specific subjects where progress was made in the civil / structural area included reviews of the SMA report, channel insert design criteria and support design, and foundation design for the auxiliary building.

Completion of engineering evaluations continued as previously requested infor-motion was received and evaluated. In the electrical and mechanical review areas verification of engineering evoluotions continued.

! An integrated engineering evaluation plan is being developed. This plan provides a correlation between the review matrix in the Engineering Program Plan and l

the related engineering evoluotions. The integrated plan eliminates redundant l effort in completing engineering evaluations and aids in the identification of l oreas requiring additional review to allow appropriate conclusions to be drawn.

l 2.2.3 STANDBY ELECTRIC POWER SYSTEM PROGRESS The technical review of the electrical load capacity, sequencing, and shedding of the diesel generator has been completed. The results of on independent load tabulation of the diesel generator (DG) loads has been compared to the DC design rating and to tha current Bechtel DG load calculation. The DG interlocks and permissives, as well as sequencer and load shed logic, were included in the l

B-84-07 3 TERA CORPORATION

,. 1 review. In particular, the primary undervoltage setpoint and the lood sequencer timer occuracy were examined. The review of the power distribution system (PDS) is in progress. The draft engineering evaluation for these DG ond PDS topics is scheduled for completion in January.

The evaluation of DG local operation, system interlocks, instrumentation, control systems, and actuation systems is also nearing completion, with certain aspects such as the system interlocks and ESFAS interface already completed.

Some of the detailed items being, reviewed include the DG pneumatic control system operability requirements and the storting air quality, as well as the 60-second coastdown interlock. The aroft engineering evaluation is also scheduled for completion in January.

The draft engineering evoluotion of the fire protection associated with the diesel generators has been completed. Diesel-generator building (DGB) wall penetra-tions and seal details were reviewed, along with fire detection system operabil-ity. Fire protection system features were examined in light of NFPA require-ments. The operation of the CO2 system was reviewed, including CO2 room flooding capability. Room pressurization and the associated Bechtel calculations v;ere also reviewed.

i The DG comber, tion air supply and engine exhaust draf t engineering evaluation has been completed. Intoke and exhaust as-built configurations were reviewed

! against vendor interface requirements and Bechtel design calculations. An alternate calculation of exhaust backpressure was performed due to variances in input parameters used in the design calculation.

The technical reviews of the DG and DC System Technical Specifications and the mechanical aspects of the underground fuel oil storage tanks were completed, and draft engineering evaluations are scheduled for completion in early January.

The fuel oil tank review included the effects of flooding. The draft engineering evaluation of the SEP system consolidated criteria and commitments is also l scheduled for completion in January. The review of the 125 VDC system is in progress and is scheduled to be completed in January.

B-84-07 4 TERA CORPORATICN

, 1 The review of the DGB as-built condition has been completed with the assistance 1pf Professors N <le J. Holley (MIT) and William J. Hall (University of lilinois).

The IDV reviewers met as a teom in Bethesde on December 16, 28, and 29 to consolidate their review process and finalize their draft report.

Review of the DGB concrete / steel design (Topic .111.7-2) and foundation design (Topic 111.6-2) was pursued - by reviewing calculations related to the finite element analysis which is used to verify the adequacy of the design.

The engineering evaluation was completed at the end of December and the report was scheduled to be released on January 4. The engineering evaluation's primary conclusion is that the existing cracks, generally being of small size, are not indicative of a condition that would compromise the capability of the DGB in meeting its intended performance requirements. The IDV team also concluded that significant future cracking is not anticipated and the DGB is expected to remain serviceable without further remedial action. Rec.ommendations concern-ing CPC's commitments to verify continued serviceability are also provided.

2.2.4 CONTROL ROOM HVAC SYSTEM PROGRESS The responses to confirmed items provided in the November 11, 1983 Bechtel letter have been reviewed and the associated OCRs are resolved.

The 20 review topics which cover the control room HVAC System Performance

Requirements review area have progressed to a near completion status. For the sample initially selected

o Criteria and commitments have been reviewed and con-solidated from the FSAR.

l l o P&lDs have been reviewed.

o Design basis combinations of events and natural phenom-ena have been tabulated and reviewed.

l o Layout drawings have been reviewed for mechanical con-siderations.

B4447 5

! TERA CORPORATION

\

o Calculations have been reviewed, o Specifications have been reviewed for functional require-ments and compliance to codes and standcrds commit-ments.

Engineering evoluotions are in preparation, leaving three areas to close -- OCRs, document revisions, and ossessment of the sample. Structural review of the ducts and duct supports is continuing. The status of structural review of the Auxiliary Building is discussed in Section 2.2.2 of this status report.

2.3 CONSTRUCTION VERIFICATION ACTIVITIES 2.3.1

SUMMARY

Activities undertaken and events which occurred during this reporting period which are important to the overall conduct of the construction verificaticn review portion of the IDCV program are os follows:

o The review of vendor and project NDE procedures was completed and the results of the review doc'amented on checklists. - A commary of observations extracted from the checklists has been prepared and included in Open items, OCR numbers 0-123 and 0-124. Further review is in progress to determine whether these items should be confirmed.

o Activities of ICV reviewers during this reporting period t

were focused .;pon the dispositioning of existing OCRs and Findings. Extending the ICV reviews into new areas has been held pending completion of selected CCP Phase I octivities. Recommencement of the Construction / Install-l

- otion Documentation and Physical Verification Reviews is onticipated in September 1984.

! 2.3.2 CONSTRUCTION DOCUMENTATION REVIEW PROGRESS Construction documentation revies relates to those ICV review categories which are principally concerned with the adequacy and completeness of availcSle documentation, as opposed to those ICV review categories which verify the l

B-84-07 6 TERA CORPORATION

o '

physical configuration nf installed components and commodities. The following ICV review categorie* ore part of construction documentation review:

o Review of Supplier Documentation o Review of Storage and Maintenance Documentation o Review of Construction / Installation Documentation.

A description of progress made and principal activities undertaken in the above review categories is as follows:

o ICV reviewers completed their review of selected vendoc and project NDE procedures. The results of the review were documented on checklists, and the checklists were further summarized onto OCRs 0-123 and 0-124. Open items 0-123 and 0-124 record the salient observctions of the NDE procedure review and record those inconsisten-cies noted when NDE procedures were compared to cpplicable Codes and Standards. ICV reviewers continue to evoluote the significance of the noted inconsistencies.

o ICV program management commenced collating the sum-maries and engineering evoluotions prepared to date with-in each of the ICV review categories. These summaries will be prepared as on cngineering evoluotion for each of the ICV review categories to stetus each review. The '

evoluotions so prepared would necessarily be supplement-ed with the evoluotion of the ultimate disposition of existing Confirmed items and Findings.

2.3.3 PHYSICAL VERIFICATION / SITE ACTIVITIES PROGRAM l

The activities described herein address those ICV review categories which 1

require ICV reviewers to observe, witness, or verify field activities and/or the l

os-built configuration of installed commodities and components. For the most

part, these activities require a strong site presence on the part of reviewers and l include the following review categories

o Review of Selected Verification Activities o Verification of Physical Configuration.

f-

! B-84-07 7 TERA CORPORATION

, n During this reporting period, ICV reviewers did not conduct any site activities.

- Neor term activities for the above review categories will relate to dispositioning existing Findings and Confirmed items. A recommencement of site verification reviews is anticipated in September subsequent to completion of selected CCP Phase 1 octivities.

3.0

SUMMARY

OF CONFIRMED AND RESOLVED ITEM REPORTS, FINDING f" 'RTS, AND FINDING RESOLUTION REPORTS Attachment 2 provides TERA's Tracking System Summary for Open, Confirmed, and Resolved (OCR) Item Reports, Finding Reports, and Finding Resolution Reports. This tool assists TERA in tracking the disposition of issues as they progress through the review process. Items that have changed status or that have been added during the reporting period are noted with on asterisk.

Attachment 2 provides retyped copies of Resolved item Reports (that have ciosed out Confirmed items), Confirmed items, Finding Reports, and Finding Resolution Reports. Several observations are also attached. The following paragraphs discuss items which have changed status in the post month.

During December eight new Confirmed items were identified, six potential items were resolved as observations, and two items were resolved as a result of receiving additional information.

Confirmed items C-125, C-130, and C-131 are all concerned with the civili structuroi review of the diesel-generator building. Specifically, the subjects of these items are as follows:

C-125 Stick model and compatibility with finite element model C- 130 Seismic force information not referenced C- 131 Analysis method for evoluotion of foundation.

Confirmed item C-129 is related to on apparent discrepancy in the required isolation time for the control room HVAC dampers.

B-84-07 8 TERA CORPORATION

l s 1 OCR item numbers 132 through 141 are all concerned with the review of the stcndby electric power (SEP) system. Items C-132 through C-135 are confirmed items in the SEP review concerned with the following subjects:

C-132 Discrepancy between FSAR and design documents regarding undervoltage set points C-133 Potential loss of pneumatic controls associated with diesel-generator C-134 Unit I/ Unit 2 interface C-135 Potential inconsistency with IEEE-308-1974.

Three items in the standby electric power system review were resolved as observations. Three other items in the same system were opened, but not yet confirmed. Further review is in progress on these items.

Two other items, 0-123 and 0-124, were opened during December but were not confirmed. Both items related to the ICV.

B-84-07 9 r

TERA COf<PORATION

. 4 ATTACHMENT I MIDLAND If0EPENDENT DESIGN AND CONSTRUCTION VERIFICATION PROGRAM TERA PROJECT 3201 PERIOD DECEMBER I,1983 THROUGH DECEMBER 31,1983 Date Milestone December 12-16,1983 DGB review team members review DGB finite element and seismic stick models at Bechtel's Ann Arbor, Michigan of fices.

December 16.1983 Seventh Menthly Status Report issued.

December 27,1983 NRC letter documenting acceptance of Revision 3 to the Engineering Program Plan, Revision 4 of the Project Quality Assurance Plan, and Law Engineer-ing.

December 27,1983 Meeting notice issued for January 4,1984 OCR status review meeting.

December 30,1983 Completion of engineering evaluation of diesel-generator building.

B-84-07 TERA CORPORATION

F ATTACHMENT 2 ,

OCR, FIPOING REPORT, AFD FIPOING RESOLUTION REPORT TRACKING SYSTEM MIDLAND l>0EPENDENT DESIGN APO CONSTRUCTION VEIT 1FICATION PROGRAM I/13/84 Resolved Finding Potential Open Confirmed item / Finding Resolution OCR No. Resp. LTR Open item item IM Observation Report Report Topic Commentr 0 01 RPS 12/2I/83 3/4/83 3/4/83 7/12/83 1.4-1 Tech Specs

~

002 RPS 12/21/83 3/4/83 3/4/83 7/12/83 1.4-l Tech Specs .

003 RPS 1/3/83 3/4/83 3/4/83 f.8-1 Overpressure Protection 004 RPS I/3/83 3/4/83 3/4/83 I.8-1 Overpressure Protection 005 FAD 1/4/83 3/4/83 3/4/83 I.1-I System Operating Limits 006 RPS 1/12/83 3/4/83 3/4/83 1.2-1 Acc. Anal. Consid.

007 RPS I/12/8 3 3/4/83 3/4/83 I.2-1 Acc. Anal. Consid.

006 LB 1/19/23 3/4/83 7/12/83 1.19-1 Control Systems 009 JAM I/20/83 3/4/83 3/4/83 11.1-1 Seismic Design 010 FAD I/20/83 3/4/83 4/14/83 7/12/83 , 1.10-1 Hydraulic Desigo Oil LB 1/27/83 3/4/83 3/4/83 8/8/83 I.19-1 Control Systems 012 LB 2/7/83 3/4/83 3/4/83 7/12/83 9/30/83 1.15-1 Power Supplies 013 RPS 2/8/83 3/4/83 7/12/8 3 1.5-1 Syst. Align./Switchover 014 RPS 2/8/83 3/4/83 7/12/8 3 1.5-1 Syst. Align./Switchover 015 JAM 2/10/83 3/4/83 10/11/83 111.1-1 Seismic Design / Input to Equipt Off. JAM 2/10/83 3/4/83 111. 5-1 Civil /Str. Design Consid.

017 FAD 2/17/83 3/4/83 3/4/83 10/5/83 1.11-1 Hect Removal Cop I.10-1 Hydraulic Design

  • Change in itotus During Reporting Period B-84-07 (Sheet 1)

' OCR, FDOING REPORT, APO FIbDING RESOLUTION REPORT TRACKING SYSTEM MIDLAPO IPOEPrMENT DESIGN APO CONSTRUCTION VERFICATION PROGRAM i/13/94 (cont *mued)

Resolved Finding Potential Open Confirmed item / Finding Resolutiot.

item item Observation Report Report Topic Comments OCR No. Resp. LTR M Item 3/4/83 3/4/83 11/11/ 8 3 1.11-1 Heat Removal Cap.

018 FAD 2/17/83 11/11/ 8 3 LB 2/21/ 8 3 3/4/83 8/8/83 1.141 Instrumentation 019 3/4/83 II/II/83 1.11-1 Heat Removal Cop. B-080 Related 020 FAD 2/24/83 3/4/83 1.9-1 Comp. Func. Req.

11.1 0 -1 Eq. Oool. 0-21, Rev. I, 0 21 FAD 2/24/83 3/4/83 4/14/8 3 3/4/83 8/8/83 1.I9-I Control Syst.

022 LB 2/24/83 LB 2/28/83 3/4/83 8/8/83 1.18-1 Instrumentation 023 I.19.1 Control RPS 3/1/83 3/4/83 1.2-1 Acc. Anal. Cornid.

024 RPS 3/l/83 3/4/83 3/4/83 1.2-1 Acc. Anal. Consid.

025 3/4/83 11/11/83 1.41 Overpress. Prof.

026 FAD 3/1/83 3/4/83 3/4/83 11/11/83 1.9-1 Comp. Fune. Req.

027 FAD 3/1/83 11.9-1 Env.Eng.

3/4/83 h/14/83 1.9-1 Comp. Fune. Req.

028 FAD 3/2/83 11/11/ 8 3 LB 2/22/83 3/4/83 3/4/83 1.18-1 Instrumentation 029 1.19.1 Control System 3/4/83 1.19-1 Control System 030 LB 1/19/83 3/4/E3 8/30/83 1.3-lc Pipe Supports C-31, Rev. I, 7/12/83 0 31 DDT 2 / 11/ 8 3 3/4/83 3/4/83 7/12/83 1.3-Ic Pipe Supports C-32, Rev. I, 7/12/83 032 DDT 2 /11/ 8 3 3/4/83 3/4/83 7/12/83 7/12/83 1.3-Ic Pipe Supports C-33, Rev. I, 7/12/83 033 DDT 2 /11/ 8 3 3/4/83 3/4/83 7/I2/83 B-84-07 (Sheet 2)

OCR, FM)ING REPORT, Ab0 FIFOING RESOLUTION REPORT TRACKING SYSTEM -

MIDLAFD IPOEITNDENT DESIGN AFD CONSTRUCTION WRFICATION PROGRAM I/13/84 (cmtinuero Resolved Finding Potential Open Confirmed item / Finding Resolution OCR No. Resp. LTR Open item item item Observation Report Report Topic Comments 034 DBT 2/11/83 3/4/83 3/4/83 7/12/83 7/12/83 1.3-le Pipe Supporis C-34, Rev. I, 7/12/83 035 DOT 2 /11/ 8 3 3/4/83 3/4/83 7/12/83 7/12/83 1,3-Ic Pipe Supports C-35, Rev. 2, 7/12/83 036 JAM 2 /11/ 8 3 3/4/83 3/4/83 7/12/8 3 II.2-1 Pressure Bounoory C-36, Rev. 2, 7/12/83 037 JAM I/20/83 3/4/83 3/4/83 8/30/83 111.1 1 Seismic Desiga/ Input to Equipment 038 FAD 3/1/83 3/4/83 3/4/83 1.15-l Power Supplies 039 LB 3/30/83 4/14/83 8/30/83 11.1 0 - 1 Env. Eq. Qual.

' 040 LB 3/8/83 4/14/83 9/30/83 1.16-1 Elec. Chorocter:stics 041 LB 3/25/83 4/14/83 9/30/83 1.15-1 Power Supplies 042 LB 3/31/83 4/14/83 9/30/83 I.10-1 Env. Eq. Gual.

043 FAD 3/15/83 4/14/83 10/6/83 12/2/83 1.10-1 System Hydraulic Design le'-2HFID-605 044 FAD 3/15/83 4/14/83 10/6/83 II.10-1 Env.Eq. Oval. Resolved as .

Observation 045 DOT 3/17/83 4/14/83 5/25/83 8/8/83 II/II/83 II.1-IC Electrical Equipment / C-45, Rev. I, 7/12/83 Storage & Maintenance 046 DDT 3/17/83 4/14/83 5/25/83 8/8/83 11/11/83 1.1-I C Mechanical Equipment /

Storoge & Maintenance 047 DBT 7/7/83 7/26/83 8/8/83 8/30/83 1.1-I C Mechanical Equipment / C-47, Rev.1, Storage A Maintenance 8/30/83 048 FAD 7/29/83 7/29/83 8/8/83 Il.101 Environmental Equipment Ovalification 049 RC 8/28/83 8/79/83 8/2?/83 II/II/83 II.bIc Cable 050 RC 8/28/83 8/79/83 8/29/83 II/II/83 II.bic Cable B-84-07 (Sheet 3) i

OCR, FIPONG REPORT, AM) FM) LNG HESOLUTION REPORT TRACKING SYSTEM -

MIDLAM) NXPLMXNT DESIGN Af0 CONSTRUCTION VERIFICATION PROGtAM l/13/84 (continued)

Resolved Firxting Potential Open Confirrr.ad item / Finding Resolution OR No. Resp. LTR Open item item item Observation Repor t, Report Topic Comments 051 JAM 8/12/83 8/30/83 8/30/83 III.1-1 Seismic Design / Input to Equipment 052 UBT 9/30/83 9/30/83 9/30/83 12/I/83 AllICV Twics for AFW Supplier Doc 053 FEP 9/27/83 9/29/83 9/2?/83 12/1/83 AllICV Topics for AFW ConstJinstallotion Documentation 054 FEP 9/27/83 9/29/83 9/29/83 12/1/83 AllICV Topics for AFW ConstJinstallation

- POCis 055 DBT 9/19/83 9/29/83 11/II/83 12/1/83 All ICV Topics Const./ installation Documentation -

WPs & PORs 056 DUT 9/26/83 9/29/83 11/11/83 12/1/83 AllICV Topics for AFW & SEP Suppliev/ Doc. -

Materials 057 DW 9/29/83 9/30/83 9/30/83 1.34-3 Pressurization Resolved as Observaticn 056 DW 10/6/83 80/6/83 1.12-3 Cooling / Heating Requirements 059 RPS b/II/83 9/30/83 1.3-1 Single Failure Resolved as 1.23-1 Failure Modes & E'fects Observation 060 DW 9/29/83 9/30/83 1.1-3 System Operating Limits 061 UW 9/29/83 9/30/83 I.18-3 Instrumentation Resolv>d as Observation 062 FAD 9/30/83 9/30/83 1.9-l Comp. Fe me. Req.

063 FAD 10/5/83 10/6/83 1.10-1 System Hydraulic Design Resolved as Observation 064 FAD 10/5/83 10/6/83 1.10-1 System Hydraulic Design Resolved as Observation B-84-07 (Sheet 4)

OCR, FDOING REPORT, APO Fl> DING RESOLUTION REPORT TRACKING SYSTEM .

MIDLAto l>OEPEF0FNT DES:GN Ato CONSTRUCTION VERIFICATION PROGRAM I/13/84 (continuM)

Resolved Finding Potential Open Confirmed item / Finding Resolution OCR No. Resp. LTR Open item item item Observation Report Report Topic Comments 065 FAD 10/4/83 10/6/83 All IDV Topics 066 DW 9/29/83 10/6/83 10/6/83 II/30/83 1.5-3 System A!ignment/Switchover I.7-3 System Isolation / Interlocks 067 DW 9/29/83 9/30/83 9/30/83 1.343 Pressurizotion Resolved as Observation

. 068 JAM 9/27/03 9/30/83 9/~a0/83 11. 4 1 EO/ Seismic 069 JAM 9/27/83 9/'t0/83 12/14/83 11.4 - 1 EO/ Seismic 070 JAM 9/27/83 9/30/83 12/14/83 1.41 EO/ Seismic Consolidated with C-069 071 JAM 9/27/83 9/30/83 12/14/83 III.1-1 Seismic Desic/

Input to Equipment 072 FAD 9/30/83 10/6/83 1.9-1 Comp. I une. Req.

11.2 - 1 Seismic Design - Pressure Boundary

073 DW 9/29/83 10/6/83 10/6/83 II/II/83 f.12-3 Cooling / Heating nequirements OCR-058 related~

074 DW 9/29/83 10/6/83 10/6/83 1.1-3 System Operat'eg Limits I.2-3 Acc. Anal. Consid.

1.1 S-3 Power Supplies 1

075 DW 9/29/83 10/6/83 10/6/83 1/6/84 f.!-3 System Operating timits

  • l.2-3 Acc. Anal. Consid.

076 DW f.l ?-3 C. Wing / Heating Requirements

  • 9/29/83 10/6/83 10/6/83 1/6/84 077 JAM 9/27/83 10/6/83 10/6/83 11. 4 1 EO/ Seismic 078 FAD 9/30/83 10/6/83 f.9-1 Comp. Func. Req.

B-84-07 (Sheet 5)

OCR, Fl>OING HEPORT, AfO FIPOING RESOLUllON REPORT TRACKING SYSTEM '

MIOLAFO itOEPEICENT DESIGN AfO CONSlHUCllON VETtlFICAllON PROGRAM i/13/84 (continue <0 Resolved Finding Potential Open Confirmed item / Finding Resolution OCR No. Resp. LlR Open item item item Observation Report Repor t Topic Comments 079 JAM 8/29/83 10/6/83 111. 5 - 1 Civil / Structural Design Consideratior.s Ill.6-1 Foundations 000 FAD 11/1/83 II/II/83 l.9-1 Comp. Fune. Req. Resolved os Observation 081 FAD 11/l/83 11/11/83 11/11/83 11.2 - 1 Pressure Bcondary I.9-1 Comp. Func. Req.

Ob2 DW 10/18/83 II/II/83 1.9-3 Comp. Fune. Req. Chemical ConcJ Dow Interface 083 DW 10/31/83 II/II/83 1.2-3 Acc. Anal. Consid.

084 DW 10/31 13 11/11/83 11/11/83 1.2-3 Acc. Anal. Consid.

085 DW 10/31/83 11/11/83 11/11/83 All IDV lopics Noted issues iden-tified in CR-HVAC review 066 FAO 10/13/83 h/II/83 11.1 2 -1 Fire Protection Resolved as Observation 087 FAD 10/13/8 3 II/II/83 11/11/ 8 3 11.1 2 -1 Fire Protection 088 FAD 10/ 3/83 II/II/83 11/11/ 8 3 11.I 2 -1 Fire Protection 089 FAD 10/13/83 11/11/ 8 3 11/11/ 8 3 11.1 2-1 Fire Protection C-089, Rev. I v !/29/83 090 FAD 10/13/83 lI/11/83 11.1 2 -1 Fire Protection Resolved as Observation -

'J91 RSC IC/18/83 il/l1/83 11/11/83 12/1/83 1.3-IC Pipe Supports Overinspection Prog.

U-84-07 (Sheet 6)

~

OCR, FIPOING REPORT, APO FIPOING RESOLUTION REPORT TRACKING SYSTEM MIDLAPO ltOEPEPOLNT DESIGN AND CONS 1RUC110N VERIFICATION PROGRAM I/13/84 (continue S Resolved Finding Potential Open Confirmed item / Finding Resolution OCR No. Resp. LTR Open item item item Observation Report Repor t Topic Comments 092 RSC 10/18/83 11/11/83 II/tt/83 1.3-I C Pipe Supports Overinspection Prog 093 DBT 11/10/83 11/21/83 II/28/83 IV.2-3C Const. Doc. Review HVAC Dr:ts 094 t>BT ll/10/83 11/21/83 11/28/83 IV.2-3C Physical Verif. HVAC Ducts 095 LX11 11/10/83 11/21/83 11/28/83 IV.2-3C Const. Doc. Review HVAC Welding Does 096 DBT ll/10/83 11/11/83 II/?B/83 IV.2-3C Const. Doc. Review HVAC Ducts and supporis 097 LDB 11/30/83 12/5/83 12/9/83 1.3-3 Single Foilure 1.5-3 System Alignment 098 DMW 11/7/83 (2/5/83 111.1 - 1 Seismic Design RG l.92 099 JAM ll/30/83 12/5/83 12/9/83 111.1 - 1 Seismic Design Slab Rotation 100 JAM 12/9/33 12/9/83 111. 1 - 1 Sei,mic Design Resolved as Observations 101 JAM 11/30/83 12/5/83 12/9/83 111. 1 - 1 Scismic Design DO-38(G) 102 JAf4 ll/30/83 12/5/83 (2/9/83 111. 1 - 1 Seismic Design Computer input 103 JAM 11/30/83 12/5/83 12/9/83  !!It-t Seismic Design 104 JAld il/30/83 12/5/83 12/9/83 111. 1 - 1 Seismic Design Moment of inertio -

Cole 105 JAM iI/30/83 12/5/83 12/9/83 111. 1 - 1 Seismic Design Program CE-207 106 JAM II/30/83 12/5/83 12/9/83 Ill.l-l Seismic Design Soil Structure Interaction 107 JAM 11/30/83 12/5/83 12/9/83 111. 1 - 1 Seismic Design Stick Model Assumptions 108 JAM iI/30/83 12/5/83 12/9/83 111. 1 - 1 Seismic Design Stick Modelinput B-84 07 (Sheet 7)

OCR, FN)tNG REPORT, APE) FNOING RESOLUTION REPORT TRACiGNG SYSTEM

  • MIDLADE) N)EPEPEX NT DESIGN APO CONSTRUCTION VERIFICATION PROGRAM i/13/84 (contiramo Resolved Finding Potential Open Confirmed item / Finding Resolution OCR No. Resp. LTR Open item En3 i em_ , Observation Report Report Topic Comments 109 LDB 12/1/83 12/6/83 62/14/83 1.19-2 DG Control Fuel Lockout i10 LDB 12/1/83 12/6/63 12/14/83 1.24-2 DG Load Copacity Load Teulation ill &S 12/2/83 12/6/83 12/14/83 1.24-2 DG loot l Capacity Undervoltage 162 GES 12/9/83 12/14/83 12/14/83 1.30-2 DG Exhaust 113 JAM iI/3/83 11/7/03 12/14/83 ll1.7-1 Conc / steel design i14 JAM II/3/83 11/7/83 12/14/83 ll1.7-1 Conc / steel design 115 JAM 11/10/83 11/10/83 12/14/83 111.7-1 Conc / steel design l16 JAM 11/10/83 11/10/83 12/14/83 ll1.7-1 Cone /stee! design l17 JAM 10/31/83 II/10/83 12/14/83 I l l.6-1 Foundations iII.7-1 C.ex/ steel design l18 JAM 10/31/83 12/14/83 111.6-1 Foundations i19 JAM 10/5/83 11/14/83 12/14/83 11.4-1 Seismic Qual.

120 JAM 10/26/83 11/14/83 12/14/83 11.4-1 Seismic Gucl 121 JAM 10/26/83 11/14/83 12/14/83 11.4-1 Seismic Gual.

122 JAM 10/26/83 11/14/83 12/14/83 11.4-1 Seismic Goo!.

123 DOT 12/20/83 12/28/83 Various ICV 'opics

  • 124 001 12/20/83 12/28/83 Various ICV topics
  • 125 JAM 12/30/83 1/6/84 1/6/84 lll.1-2 Seismic Design ' Stick Model 126 UMW 12/19/83 1/6/84 1.2-3 Acc. Anal. Consid. ' Air Inleakage 127 DMW I2/20/83 1/6/84 1.9.3 Comp. Func. Req. ' Resolved as Observation B-84-07 (Steet 8)

OCR, FIFOING RFPORT, AFD FIFOING RESOLUTION REPORT TRACKING SYSTEM .

MIDLAPO IPOEPFtOENT DESIGN AFD CONSTRUCTION VERFICATION PROGRAM i/13/84 (contnum0 Resolved Finding Potential Open Confirmed item / Finding Resolution OCR No. Resp. LTR Open item item item Observation Report Report Topic Comments 128 DMW 12/20/83 t/6/84 1.35-3 Ventilation

  • Resolved as Observation 129 DMW 12/30/83 I/6/84 1/6/84 1.9-3 Cornp Fune. Req. 'Domper isolation Time 130 JAM 12/20/83 t/6/84 1/6/84 1!l.7-2 Conc / steel design
  • Source of Sci .r.iic Forces 131 JAM 12/20/83 1/6/84 1/6/84 111.6-2 Foundations ' Footing Strips ill.7-2 Cone / steel design 132 GES 12/9/83 1/6/84 1/6/84 1.26-2 Electricoll nod Shedding 'Under-Voltage Setpoints 133 ES 12/21/83 I/6/84 1/6/84 1.19-2 DG Control
  • Pneumatic Ccatrol 134 ES 12/29/83 I/6/34 1/6/84 l .7-2 Interlocks ' Cross-unit -

Interface 135 ES 12/29/83 1/6/84 1/6/84 1.7-2 Interlocks *lEEE 308 136 CES 12/29/83 1/6/84 I.7-2 Interlocks

  • Resolved as Observation 137 CES 12/29/83 I/6/84 1.7-2 interlocks 'Redved as Observation -

138 CES 12/29/83 1/6/84 1.7-2 Interlocks

  • Resolved as Observation 139 &S 12/9/83 t/6/84 1.25-2 DG Load Sequencing
  • 140 CES 12/is/83 1/6/84 111.8-2 Oil Tanks
  • 141 GES 12/23/83 I/6/84 1.19-2 DC Controls
  • 1 B-84 07 (Sheet 9)

ATTACHMENT 3 CURRENT PERIOD COWIRMED AND RESOLVED ITEM REPORTS, FIFOING REPORTS, AND FINDING RESOLUTION REPORTS l

B-84-07 TERA CORPORATION

MIDLAPO ltOEPEPOENT DESIGN APO CONSTRUCTION VERIFICATION OPEN, COfflRMED Ato RESOLVED (OCR) ITEM REPORT TYPE OF REPORT: OPEN COPEIRMED " . f2 oos -R-075 RESOLVED X FTEM nty, wo, Q / ?Q /R"4 $RT PROKCT TE AM/PROKCT MCR. 9/30/83 DATE5 REPORTfD 70: LTR PRINCIPAL.IN.CHARCE IO/IZ/53 CPC/DE51CN ORG.

STRUCTURI(5), $YSTEM(5), OR COMPOPENT(5) INVOLVED:

Centrol. Roora KVAC System DCV PROGRAM AREA OR TA5x (IF APPLICABLEh Review Topics I.1-3 and I.2-3 Criteria Review System Operating Limits and Accident Analysis Considerations DESCRIPTION OF CONCERN:

Regulatory Guide 1.78 Item 10 of the Reg. Position requires that a 10 CFil inleakage be considered even for pressurized control rooms. Appendix 3A states compliance with the intent of Reg. Guide 1.78. It is not clear that the 10 CFM inleakage is considered. A statement of the basis for assumed inleakage and the justification for that basis should be provided.

l SIGNIF4CANCE OF CONCERN:

I The habitability requirements for the control room may not be satisfied for continuous release if a 10 CFM inleakage occurred.

OR RESOLUTION X RECOMMENDATION __

The referenced letter addresses the concern. A two-door vestibule is an adequate

' basis for eliminating significant inleakage. The vestibule, in combination with adequate administrative controls, will satisfy the intent of the Regulatory Guide.

COMMENTS SY SRT (IF REQUIREDh REFERENCES (INCL. REL ATED OCR ITEM REPORT NO.h Bechtel letter to Consumers Power BLC-18457, dated 11/11/83 _

SIGNATURE (Sh JWB A# 4A Ah _

HAI _

PRINCIPAL. SRT (IF REQUIRED)

Of.M ITEM REPORT 'LTR PROKCT MANAGER FOR PROKCT TEAM 94.CMARGE ORACINATOR 1/6/84 1/12/R4

_ /E/f/ /n /r/esfr3 DATE DATE DKTE DATE DATE

, o .

MIDLAPO ltOEPEPOENT DESIGN AtO CONSTRUCTION VERIFICATION OPEN, COfflRMED APO RESOLVED (OCR) ITEM REPORT TYPE OF REPORT: OPEN COfflRMED o - R 076 RESOLVED X ITEM ggy, wo,

- PROACT TEAM / PROJECT MGR.9/30/83 DATES REPORTED TO: LTR 9/29/B3 SRT PRINCIPAL-IN.CMARGE Iu/iz/oj CPC/ DESIGN ORG.

STRUCTURE (5), SYSTEM (5), OR COMPQr(NT(5) INVOLVED:

Control . Room HVAC - Air Handling Unit Cooling Coils --

g>CV PROGRAM AREA OR TASK (F APPLICABLE):

Review Topic I.12-3 Cooling / Heating Requirements DESCRIPTION OF CONCERN: Certain data are used in the calculation without clear reference to a data source which is controlled. Without such reference, the validity of the data is in question, specifically:

- Makeup flow = 2000 CFM references FSAR 9.4.1.2.3 without identifying calculational backup and the FSAR discusses only normal operation, not LOCA after 3 hours3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br /> isolation Aux Bldg Temp = 104 g no references

- Makeup Aic Temp = 96g FDB no references 79 FWB SIGNIFICANCE OF CONCERN:

Although the data appears reasonable, it is necessary to trace the data to a For example, controlled source in order to check the basis for the values used.

the makeup air conditions appear to be close to a 1% design basis from the ASHRAE Guide. This should be confirned and the reason for using 1% conditions stated. To complete the assessment of the design, this type of information is required. The adequacy of this data could affect the ability of the system to maintain control room temperatures.

OR RESOLUTION X RECOMMENDATION The referenced letter addresses the concern. Although not specifically identified in the calculation, the data is based on controlled data sources or published data in common use. This confirms the adequacy for use in the calculation.

COMMENTS SY SRT (IF REQUIRED):

REFERENCES (INCL. REL ATED OCR ITEM REPORT NO.):

-Calculation No. CPM 4321-01 (Q), Rev. 2

-Bechtel letter to Consumers Power BLC-18457. dated 11/11/83

$4GNATURE(5):

M /vd A8 _

HAl .lUR PRINCIPAL-SRT (IF REQUIRED)

LTR PROKCT MANAGER OC#1 TEM RfPORT M MARGE ORIGNATOR FOR PROKCT TEAM

/r/n/N 1/6/84 1/12/84

/e/n /n _ DATE DATE DATE DATE DATE _ _.

MIDLAPO ltOEPEtOENT DESIGN APO CONSTRUCTION VERIFICATION OPEN, COfflRMED APO RESOLVED (OCR) ITEM REPORT TYPE OF REPORT: OPEN COfflRMED . Y

. 320 008-C-125 RESOLVED ITEM REV.NO.

DATES REPORTED TO: LTR 12/30/83 SRT PROECT TEAM /PROKCT MCR. I/4/ 84 PRINCIPAL.lN-CHARGE 1/10/84 CPC/ DESIGN ORG.

STRUCTURE (5), SYSTEM (5), OR COMPOffNT(S) INVOLVED:

SEP - Diesel Generator Building IDCV PROGRAM AREA OR TASK (IF APPLICABLE): .

III.1-2 Seismic Design / Input to Equipment DESCRIPTION OF CONCERN:

1. No justification for ignoring the south wall openings in the development of the stick model properties.
2. No compatibility study between stick and finite element models. t SIGNIFICANCE OF CONCERN:

The two models may not be compatible in terms of equilibrium and deflection.

RECOMMENDATION v OR RESOLUTION

  • Process per PQAP. .

l COMMENTS BY SRT (!F REQUIREC):

REFERENCES (INCL. RELATED OCR ITEM REPORT NO.):

Calculation SQ-147(Q)

$4 GNAT cpl.1 JM1 HAL JWB OCR ITEM REPORT LTR PROECT MANAGER PRINCIPAL- SRT (IF REQulRED)

ORIGINATOR FOR PROKCT TEAM N.CHAFsGE 12/30/83 1/4/84 1/6/Ra 1/19/Ra DATE DATE DATE DATE DATE

MICA.MO INDEPEf0ENT DESIG4 APO CONSTRUCTION VERIFICATION OPEt4 COfflRMED Ato RESOLVED (OCR) ITEM REPORT TYPE OF REPORT OPEN CONFIRMED , l~ -B-126 Observation X RESOLVED X ITEM REV.NO.

DATES REPORTfD TO: LTR 17/19/83, ERT PROKCT TEAM /PROKCT MCR. 1/4/84 PRINCIPAL.IN. CHARGE l/11/84 CPC/ DESIGN ORG.

STRUCTURE (5), SYSTEM (5). OR COMPOtENT(S) INVOLVED:

Control Room HVAC IDcv PROGRAM AREA OR TASK (IF APPLICABLE):

Review Topic I.2-3 Accident Analysis Considerations Calculations Review DESCRIPTION OF CONCERN:

FSAR Section 6.4.2.3 states, "The toxic gas protection analy7,is, however, assumes a conservative inleakage of 82 cfm." The plant conditions under which this inleakage might occur are not identified. A review of calculations which address the toxic gas protection has been conducted atid these calculations do not include an analysis of an 82 cfm inleakage. The concern is that under some plant conditions, significant inleakage is feasible and the toxic effects have not been addressed in an analysis.

SIGNIFICANCE OF CONCERN:

Control room habitability could potentially be jeopardized.

i l

RECOMMENDATION OR RESOLUTION X  :

This item is resolved by classification as an Observation. The statements made in the FSAR are outdated. Inleakage is taken to be zero, as indicated in the resolution of OCR 3201-008-075. There are no adverse technical consequences, but the FSAR should be updated.

COMMENTS SY SRT (IF REQUIRED):

REFERENC.5 (INCL. RELATED OCR ITEM REPORT NO.h SIGNATURE (Sh I DfIW 4 N#/4h DMW oC)#4.I) V HAL JWB _

OCR ITEM REPORT LTW PROKCT MANAGER PRINCIPAL- 5RT (IF REQUIRED)

ORIGINATOR FOR PROKCT TEAM N. CHARGE 12/19/83 12/19/83 1 / 6 / R4 _ _,,, 1/12/R4 DATE DATE DATE DATE DATE

MIDLAto itOEPEPOENT DESIGN Ato CONSTRUCTION VERIFICATION OPEN, COfflRMED AtO RESOLVED (OCR) ITEM REPORT TYPE OF REPORT: OPEN COPEIRMEO O 27 Observation X RESOLVED x rTEM E,"yo', 3ms -B DATES REPORTfD TO: LTR 12/20/83 SRT PROKCT TE AM/PROKCT MCR. 1/4/84 PRINCIPAL.IN-CKARGE 1/11/R4 CDC/ DESIGN ORG. _

STRUCTURE (5), SYSTEM (5), OR COMPONENT (5) INVOLVED:

Control Room HVAC Air Handling Unit 0VM-01 A & B DCV PROGRAM AREA OR TASK (if AFPLICABLE):

Topic I.9-3 Component Functional Requirements DESCRIPTION OF CONCERN:

Sheet 14 of the referenced calculation states as a conclusion, " Change fan motor from 30 H.P. to 40 H.P." The referenced specification includes the higher system total pressure of 5.5 in w.g., which led to the above statement, but the motor H.P.

is still 30. The concern is whether adequate driver H.P. is specified to meet flow requirements.

SIGNIFICANCE OF CONCERN:

! If motor H.P. were inadequate, the design basis flow could not be obtained; however, l a simple calculation of fan power performed by the reviewer indicates 30 H.P. is adequate. The Bechtel calculation was just conservative in its conclusion.

RECOMMENDATION OR RESOLUTION X This item is resolved by classification as an observation based on the fact that the l design requirement was adequately addressed.

l COMMENTS BY SRT (IF REQUIRED):

I REFERENCES (INCL. RELATED OCR ITEM REPORT NO.):

Calculation R1-4321-9(Q)

Specification 7220-M-149(Q)

SIGNATURE (5):

DMW a v I I DMW_^ M I!__ HAL JWB PRINCIPAL- SRT (IF REQUIRED) l OCR ITEin REPORT LTR PROKCT MANAGER ORIGINATOR FOR PROKCT TEAM M MARGE l

l 12/20/83 12/20/83 _1/6/84 1/1 2/84 _

DATE DATE DATE DATE l DATE _

, --- - -----,r, - , y . --- -

MIDLAPO INDEPEPOENT DESIGN APO CONSTRUCTION VERIFICATION OPEN, COtFIRMED APO RESOLVED (OCR) ITEM PEPORT HYPE OF REPORT: OPEN CONFIRMED NO. 320 008-B-128 Observation X RESOLVED X ITEM REV.NO.

DATES REPORTfD TO: LTR 12/20/83 SRT PROKCT TE AM/PROKCT M*.,R.1/4/84 PRINCIPAL.IN. CHARGE 1/11/84 CPC/DE5tCN ORC.

STRUCTURE (5), SYSTEM (5). OR COMPOPENT(5) INv0LVED:

Control Room HVAC Air Handling Unit OVM-1 j DCV PROGRAM AREA OR TASK (IF APPL!OABLE):

l l

Topic I.35-3 Ventilation - Calculation Review DESCRIPTION OF CONCERN:

The balance of the system requires that the static pressure drop in the return air duct exceed that in the fresh air duct by 4" WG to pressurize the control room. The values calculated are 0.82" WG and 0.62" WG respectively. To be conservative, the fan sizing should have been based on (0.62 + .25) instead of 0.82.

l 5IGNIFICANCE OF CONCERN:

Although the method was slightly in error, the consequences are not significant, because 0.05" WG is within the accuracy of the calculation. When the actual system is balanced, it will be important to understand the flaw in the method, to ensure that the correct cont.rol room pressurization is established.

1 OR RE50;.UTION Y p RECOMMENDATION _

l j This item is resolved by classification as an " Observation." There is no physical consequence associated with the observation and the calculatico is being revised for other reasons.

COMMENTS SY SRT (IF REQUIRED):

REFERENCES (INCL. RELATED OCR ITEM REPORT NO.):

Calculation FM-4321-9(Q) Rev. 4 SIGNATURE (Sh DMW n/>M OCR iTEMtEPORT DMW ihE/rd LTh HAL PROKC" .'d.ANAGER JWB PRINCFAl.- SRT (IF REQUIRED)

ORIGINATOR FOR PRv1CT TEAM N. CHARGE 12/20/83 12/20/83 1/F/Rd 1/12/R4 DATE DATE Ot.TE DATE DATE i

,---.a - - - - - - - , - - . - - , _ . ,

MIDLAf0 ItOEPEPOENT DESKW APO CONSTRUCTION VERIFICATION OPEN, COtflRMED Ato RESOLVED (OCR) ITEM PEPORT TYPE F REPORT: IR D Y NO. 3 f.008 -C-12_9 DATES REPORTfD TO: LTR l2/30/63 SRT PROECT TE AM/PRCKCT MCR. 1/6/84 PRINCIPAL.lN-CHARCE I/I1/84_ CPC/DE51CN ORG.

STRUCT URE(5.1, SYSTEM (5), OR COMPOff NT(5) INVOLVED:

Control Room HVAC Hazcrdeus Gas Monitoring System DCV PROGRAM AREA OR TAS4 (IF APPLICABLE):

Component Functional P.equirements Topic I.9-3 OESCRIPTION OF CONCERN:

See Attached i

l

$lCNIFICANCE OF CONCERN:

There is a potential that the hazardous gas monitoring system would not detect the presence of certain gases fast enough to meet the design bases for the system.

This might result in concentrations in excess of tolerable limits.

RECOMMENDATION X OR RESOLUTION  :

Process per PQAP.

COMMENTS SY 3RT (IF REQUIRED):

j E Yp'NYfI$h"b}$-)N[hhe". [

2. Specification 7220-N-154(Q) Rev. 9
3. Bechtel calculation FM 0505-56(0) Rev. 0

$4GNATURE(9:

DMW /xm4N DflW .cs//4 HAL J@

OCR ITEWREPORT LTR PROKCT MANAGER PRINCIPAL. SRT (IF REQUIRED)

ORIGNATOR FOR PROKCT TEAM N CMARGE 12/30/83 12/30/83 J /F,/Ra 1/19 /R4 DATE DATE DATE DATE DATE

3201-008-C-129 ATTACHMENT TO OCR ITEM REPORT:

Description of Concern Reference 1 lists concentrations for various chemicals in Appendix A at which isolation should be initiated (within 4 seconds), given a sudden increase from

zero to the stated concentration. Reference 2 requires that the control room

.HVAC isolation dampers (OMO 6501 A & B and OMO 6502 A & B) isolate in 3 seconds. This means that after detecting ti.e sudden increase in hazardous gas, isolation occurs 7 seconds after reaching the concentrations listed in Appendix A. Reference 3 determines the required sensitivity for hazardous gas oetecticn for 5 second and 7 second isolation times.

The 7 second values for required sensitivity should, therefore, be specified; but some of the values correspond more closely to the 5 second values. Bromine and hydrogen bromide are additionally allowed in the specification to respond in 16 seconds and 5 seconds, respectively, without adjustment to the required sensitivity. (See Note 1 in Appendix A - Ref.1)

Two of the chemicals, sulfer trioxide and ethylene oxide, listed in the calculation (Ref. 3) are not included in Appendix A (Ref.1). They are included in Appendix D, Table 1 (Ref.1). This table lists gases which are sampled less i frequently because they are a lower priority. The basis for establishing these in the second level of testing priority is not identified.

A third level of sampling is provided in Table 2 of Appendix D (Ref.1). In the description to the table, a statement is made that the isolation dampers close in 2 seconds. The specification (Ref. 2) calls for 3 seconds.

On page 10 of Ref.1, paragraph 6.1.2(b), reference is made to Appendix A.

It appears this should be Appendix D.

The concern raised by the review of the specifications is that the specifica-tions are rot consistent with the calculation and may result in unacceptably l

l high toxic gas concentrations inside the control room.

1 l

i l

TERACORPORATION

i MIDLAPO itOEPEPOENT DESIGN APO CONSTRUCTION VERIFICATION I OPEN, COfflRMED APO RESOLVED (OCR) ITEM REPORT F N TYPE OF REPORT: O*E N CONFIRMED X N. 32 -006-C-130 t

RESOLVED ITEM ggy, wo, DATES REPORTED TO: LTR _.12/ 30/83 SRT PROKCT TEAM /PROKCT MCR.1/ 4/84 i PRINCIPAL.IN-CHARGE 1/11/84 CPC/C4 SIGN ORG.

STRUCTURE (5), SYSTEMIS), OR COMPOff NT(5) INv0LVED:

l SEP - System, Diesel Generator Building DCV PROGRAM AREA OR TASK (IF APPLICABLE),

111.7-2 Structural : Concrete / Steel Design DESCRIPTION OF CONCERN:

The seismic force values used in the referenced calculation have not been obtained within that calculation, neither is any reference given about how and where they were obtained.

$1CNIFICANCE OF CONCERN:

Correctness of the seismic force values used could not be verified.

RECOMMENDATION X OR RESOLUTION  :

Reference should be made to the source of the seismic force values used.

COMMENTS BY SRT (IF REQUIRED):

REFERENCES (INCL. REL ATED OCR ITEM REPORT NO.):

Calculation DQ-52.0(Q), Rev. 2, p. 74 SIGNATUR Sh JKA 3 JAM HAL JWB OCR ITEA4 REPORT LTR PROECT MANAGER PRINCIPAL- $RT (IF REQUIRED)

ORIGINATOR FOR PROKCT TEAM N-CHARGE 12/20/83 1/4/84 1/6/84 1/12/84 DATE DATE DATE DATE DATE

MIDLAFO itOEPEtOENT DESKW APO CONSTRUCTION VERIFICATION OPEP4 COfflRMED APO RESOLVED (OCR) ITEM REPORT F

TYPE OF REPORT: OPEN COPEIRMED X C O. 320t-008-C-131 RESOLVED ITEM REV.NO.

DATE5 REPORTfD TO: LTR_ lW30/83 SRT PROKCT TEAM /PROKCT MCR. 1/4/84 PRINCIPAL.IN-CHARCE 1/11/84 CPC/ DESIGN ORG.

STRUCTURE (5). SYSTEM (5) OR COMPDtENT(5) INVOLVED:

SEP - System, Diesel Generator Building CCV PROGRAM AREA OR TASK (IF APPLICABLE):

III.6-2 Structural: Foundations III.7-2 Structural: Concrete / Steel Design DESCRIPTION OF CONCERN:

In the evaluation of foundation footing strips of the north-south walls, the conclu-sion of the insignificance of the moments about vertical axis is based on method of analysis (i.e., check of no sliding of foundation) which may not be appropriate.

The elastic deformation of footing strip and soil without relative sliding is ignored.

SIGNIFICANCE OF CONCERN:

High moments about the vertical axis in the north-south wall footing strips as obtained in the finite element analysis may not be as unrealistic as claimed in the ,

referenced calculation. Therefore, the evaluation of these footings may be non-conservative and may underestimate the stresses.

RECOMMENDATION X OR RESOLUTION  :

Process per PQAP.

t COMMENTS BY SRT (IF REQUIRED):

REFERENCES (INCL. REL ATED OCR ITEM REPORT NO.):

Calculation DQ-52.0(Q), Rev. 2 (pp.120-125)

SIGNAT K(5):

JKA .

JAM HAl- .1WR l OCR 11tm REPORT LTR PROKCT MANAGER PRINCIPAL. $RT (IF REQUIRED)

ORIGNATOR FOR PROKCT TEAM N CHARGE 12/20/83 1/4/84 1/6/Ra 1/12 /R4 DATE DATE DATE DATE DATE

, == .

MIDLAPO ltOEPEtOENT DESIGN APO CONSTRUCTION VERIFICATION OPEN, COtflRMED APO RESOLVED (OCR) ITEM REPORT l

"0' l TYPE OF REPORT: OPCN CONFIRMED X gg, f,Uf,*oos-C-132 g

RESOLVED ITEM REV.NO.

DATES REPORTfD TO: LTR 12/12/83 SRT PROKCT TE AM/PROKCT MCR.1/4/84 PRINCIPAL-IN-CHARGE I/11/84 CPC/DE51CN ORG.

STRUCTURE (5), SYSTEM (5), OR COMPOtENT(5) INVOLVED:

Standby Electric Power - 4.16 KV Load Shed

~

DCV PROGRAM AREA OR TASK (IF APPLICABLE):

Topic I.26 4.16KV Loaa Shed DESCRIPTION OF CONCERN:

Drawings J-878, Sh-1, Rev. 3 (4.16KV Load Shed Logic Diagram) and E-75, Sh-4, Rev. 6 (4.16KV Load Shed Schematic Diagram) do not reflect the primary undervoltage setpoint specified in FSAR Table 2.3-2, Sh-2, Rev. 47.

SIGNIFICANCE OF CONCERN:

Load shed sequence may inadvertently initiate during bus transfer from station aux.

transformer to startup transformer, since the ESF undervoltage relay setpoints are specified at 60% instantar.eously instead of 59% with a 0.7 second time delay.

RECOMMENDATION X OR RESOLUTION  :

i Process per PQAP.

l COMMENTS BY SRT (IF REQUIRED):

REFERENCES (INCL. REL ATED OCR ITEM REPORT NO.):

See description plus FSAR 8.3.1.1.3, Load Shedding Circuits

$lGNATURE(5):

GR GES HAL JWB OCR ITEM REPORT LTR PROKCT MANAGER PRINCIPAL- SRT (IF REQUIRED)

OR!CINATOR FOR PROKCT TEAM N-CMARGE 12/9/03 12/12/83 1/6/84 1/12/84 DATE DATE DATE DATE DATE

, a* ,  ;

MIDLAPO ltOEPEPOENT DESIGN AND CONSTRUCTION VERIFICATION OPEN, COfflRMED APO RESOLVED (OCR) ITEM REPORT TYPE OF REPORT: OPEN CONFIRMED X

.- NO. 3 -oos-C-133 RESOLVED ITEM REV.NO.

DATES REPORTLD TO LTR 12/23/83 SRY ., PROKCT TEAM /PROKCT MCR.1/4/84 PRINCIPAL-IN-CHARCE i /11/R4 CPC/ DESIGN ORC.

STRUCTURE (5), SYSTEM (5), OR COMP 0tfNT(5) INVOLVED:

Standby Electric Power: Diesel Generator DCV PROGRAM AREA OR TASK (IF APPLICABLE):

Topic I.19-2 DG Control System (Pneumatic)

DESCRIPTION OF CONCERN:

The DG pneumatic control system is supplied air from the starting air system. The DG starting air compressors are on a non-class IE bus and are load shed upon loss of offsite power. Neither section 5.1.6 (starting air system) nor section 5.2.3 (control i systems) of material requisition M-18(Q), Rev. 9, specify control system operability requirements.

l $IGNIFICANCE OF CONCERN: ,

l Potential loss of both DGs due to loss of air subsequent to load shed. At 45 PSI of air, the low lube oil trip switches (2 out of 3 required) will operate and trip generator breaker and lock it out.

l l

RECOMMINDATION X OR RESOLUTION  :

l Process per PQAP.

l COMMENTS BY SRT (IF REQUIRED):

l l

REFERENCES (INCL. REL ATED OCR ITEM REPORT NO.):

IEEE 387-1977, Section5.1.2(1) l IEEE 323-1974, Section 6.2(1)

SIGNATURE (Sh GR GES HAL JWB OCR ITEM REPORT LTR PROKCT MANAGER PRINCIPAL. SRT (IF REQUIRED)

ORIGINATOR FOR PROECT TEAM N. CHARGE 12/21/83 12/23/83 1/6/R4 1/17/R4 DATE DATE DATE DATE DATE

a e* ,

MIDLAPO ltOEPEPOENT DESIGN APO CONSTRUCTION VERIFICATION OPEN, COPFIRMED APO RESOLVED (OCR) ITEM REPORT TYPE OF REPORT: OPEN COPEIRMED X f2 t- - C-134 RESOLVED ITEM REV.NO.

^

DATES REPORTfD TO: LTR 12/29/83 SRT PROECT TEAM /PROKCT MCR. _ l/4/84 PRINCIPAL lN.CHARCE 1/11/84 CPC/ DESIGN ORG.

STRUCTURE (5). SYSTEM (5), OR COMPOtENT(5) INVOLVED:

Standby Electric Power - LOP Sequencer IDCV PROGRAM AREA OR TASK (IF APPLICABLE):

Topic I.7-2 System Interlocks DESCRIPTION OF CONCERN:

A Unit 1 ESF 4KV bus undervoltage initiates the Unit 2 LOP sequencer. The Unit 2 B0P ESFAS logic diagrams (J-299, Sh-5, Rev. 7, and Sh-7, Rev. 9) do not reflect this input.

SIGNIFICANCE OF CONCERN:

This cross unit interface must be evaluated to determine acceptability of separation and single failure concerns and to demonstrate compliance with GDC 5.

l RECOMMENDATION X OR RESOLUTION  :

Process per PQAP.

1 COMMENTS BY SRT (IF REQUIRED):

REFERENCES (WCL. REL ATED OCR ITEM REPORT NO.):

None found.

SIGNATURE (Sh GR _

GES HAL JWB OCR ITEM REPORT LTR PROKCT MANAGER PRINCIPAL- SRT (if REQUIRED)

ORIGINATOR FOR PROECT TEAM N. CHARGE i 12/29/83 12/29/83 1/6/R4 1/12/R4 l

DATE DATE DATE DATE DATE

MIDLAPO IPOEPEPOENT DESIGN APO CONSTRUCTION VERIFICATION OPEN, COfftRMED APO RESOLVED (OCR) ITEM REPORT TYPE OF REPORT: OPEN CONFIRMED _ Y ,'.008- C-l 35 RESOLVED ITEM REV.NO.

DATES REPORTfD TO LTR 12/29/83 SPT PROKCT TEAM /PROKCT M:;R.1/4/84 PRINCIPAL.IN. CHARGE I/11/84 CPC/DE51CN ORG.

STRUCTURE (5). SYSTEM (5), OR COMPOtENT(5) INVOLVED:

Standby Electric Power - Diesel Generator DCV PROGRAM AREA OR TASK (IF APPLICABLE):

Topic I.7 System Interlocks DESCRIPTION CF CONCERN:

Diesel generator lockout blocks closure of ESF 4KV offsite incoming breaker. This design appears to be inconsistent with IEEE 308-1974.

SIGNIFICANCE OF CONCERN:

Engine malfunctions can block the restoration of offsite power even though no faults occurred on the associated bus. Thus, the preferred power supply is prevented from powering the ESF bus if it is available after engine malfunction lockout, i

Automatic controls do not select the most suitable power supply.

RECOMMENDATION X OR RESOLUTION  :

Process per PQAP.

i COMMENTS BY SRT (IF REQUIRELh REFERENCES (INCL. REL ATED OCR ITEM REPORT NO.):

IEEE 308-1974, Sections 5.2.l(3), 5.2.3(4), 5.2.5(1)

StGNATURE(Sh GR GES hAL JWB OCR ITEM REPORT LTR PROKCT MANAGER PRINCIPAL- SRT (IF REQUIRED)

ORIGINATOR FOR PROKCT TEAM M MARCE 12/29/83 12/29/83 1/6 /M 1/12/Rd DATE DATE DATE DATE DATE

.r- .- ----e ,e ,-e , , - , , , - , - , - , , , . - , , ,,.-,,,-r -,,<m -

, n , -

l MIDLAFO ltOEPEPOENT DESIGN APO CONSTRUCTION VERIFICATION OPEN, COfflRMED APO RESOLVED (OCR) 11EM REPORT TYPE OF REPORT: OPEN COrflRMED 0 008 -B-136 Observation X RESOLVED X ITEM REV.NO.

DATES REPORTfD TO: LTR 1/6/84 SRT PROKCT TEAM /PROKCT MCR. I/6/84 PRINCIPAL-IN. CHARGE 1/11/84 CPC/ DESIGN ORG.

STRUCTURE (5), SYSTEM (5), OR COMPOtENT(S) INVOLVED:

Standby Elcctric Power - Diesel Generator DCV PROGRAM AREA OR TASK (IF APPLICABLE):

Topic I.7-2 System Interlocks DESCRIPTION OF CONCERN:

Vendor device number PS-3387 is identified as 1PSH-9620Al on dwg E-81, sh 1, rev. 3, and as 1PSH-9611A14 on dwg E-402, sh 4A, rev. O.

SIGNIFICANCE OF CONCERN:

No technical concern - documentation problem.

RECOMMENDt.ilON OR RESOLUTION X  :

This item is resolved by classification as an observation. Process per PQAP.

I COMMENTS SY SRT (IF REQUIRED):

REFERENCES (INCL. REL ATED DCR ITEM REPORT NO.):

See above.

SIGNATURE (S):

GR GES HAL JWB OCR ITEM REPORT LTR PROECT MANAGER PRINCIPAL. SRT (IF REQUIRED)

ORIGINATOrt FOR PF.OECT TEA.W. N. CHARGE 12/29/83 1/6/84 1/6/R4 1/17/R4 DATE DATE DATE DATE DATE

MIDLAPO ltOEPEMENT DESIGN AfC CONSTRUCTION VERIFICATION OPEN, COtFIRMED APO RESOLV2D (OCR) ITEM REPORT

~ ~

TYFZ OF REPORT: OPEN COPFIRMED Observation X RESOLVED X TTEM . NO. ,

DATES REPORTfD TO LTR 1/6/84 5RT - PROKCT TEAM /PROKCT MCR.1/6/84 PRINCIPAL.IN-CHARGE 1/12/R4 CPC/ DESIGN ORG.

STRUCTURE (5), SYSTEM (5), OR COMPOtENT(5) NVOLVED:

Standby Electric Power - Diesel Generator DCV PROGRAM AREA OR TASK (IF APPLICABLE):

Topic I,7-2 Systeni Interlocks DESCRIPTlON OF CONCERN:

The control room does not have the capability for automatic versus manual mode selection of diesel generator frequency control, as stated in the FSAR.

$1CNIFICANCE OF CONCERN:

FSAR statement incorrect.

RECOYbENDATION OR RESOLUTION X  :

Process per PQAP as an observation.

COMMENTS BY $RT (IF REQUIRED):

REFERENCES (INCL. RELA 1ED OCR ITEM REPORT NO.):

FSAR 8.3.1.1.3 (I&C)

SIGNATURE (5):

GR GES HAL JWB OCR ITEM REPORT LTR PROKCT MANACER PRINCIPAL. SRT (IF REQUIRU))

OPUGINATOR FOR PROKCT TEAM N-CHARCE 12/29/83 - 1/6/84 1/6/R4 1/12/R4 DATE DATE DATE DATE DATE

e **o 1 l

MIDLAPO ltOEPENDENT DESIGN APO CONSTRUCTION VERIFICATION l OPEis CONFIRMED APO RESOLVED (OCR) ITEM REPORT TYPE OF REPORTe OPEN CONFIRMED O$ 2 o08-B-138 D

Observation X RESOLVED X ITE8' REV.NO.

DATES REPORTfD TO: LTR 1/6/84 SRT PROKCT TEAM /PROKCT Mr.R.1/6/84 PRINCIPAL.IN. CHARGE 1/12/84 CPC/ DESIGN ORG.

STRUCTURE (5), SYSTEM (S) OR COMPOrENT(S) INVOLVED:

Standby E:ectric Power - Diesel Generator DCV PROGRAM AREA OR TASK (IF APPLICABLE):

Topic I.7-2 System Interlocks DESCRIPTION O' CONCERN:

Drawings E-81, sh 1, rev. 3; and E-402, sh 4A, rev. O, illustrate pressure switches S-278 closing on increasing pressure, PS-33B7 closing on decreasing pressure, and PS-14B opening on decreasing pressure; whereas the OG instruction manual M18-373-5 shows PS-27B closing on decreasing presstire, PS-33B7 closing on increasing pressure, and PS-14B clositig on decreasing pressure.

SGNIFICANCE OF CONCERN:

May result in confusion in the preparation of calibration and surveillance precedures.

RECOMMENDATION OR RESOLUTION X  :

This item is resolved by classification as an observation. Process per PQAP.

a COMMENTS BY SRT (IF REQUIRED):

REFERENCES (INCL. RELATED OCR ITEM REPORT NO.):

See above.

SIGNATURE (5):

GR GES HAL JWB OCR ITEM REPORT LTR PROECT MANAGER PRINCIPAL- SRT (IF REQUIRED)

CFUCNATOR FOR PROKCT TEAM N. CHARGE 12/29/83 1/6/84 1/6/84 1/12/84 DATE DATE DATE DATE DATE

.