|
---|
Category:GENERAL EXTERNAL TECHNICAL REPORTS
MONTHYEARML20203N4171986-04-30030 April 1986 Rev 2 to Tdi Owners Group App Ii:Generic Maint Matrix & Justifications ML20100B6361985-01-21021 January 1985 Rept on Welding Allegations ML20091K9701984-05-25025 May 1984 Request for Exemption from Branch Technical Position BTP-CMEB 9.5-1 for Control Panels C43 & C44 ML20084M0241984-04-27027 April 1984 Const Implementation Overview,Weekly Rept 46,840423-27 ML20084L9381984-04-19019 April 1984 Main Control Room Fire Analysis & Evaluation for C31 Control Panel ML20083P8971984-04-17017 April 1984 Midland Independent Design Const Verification Program Monthly Status Rept,Number 11 for Mar 1984 ML20087H9031984-03-16016 March 1984 Midland Independent Design & Const Verification Program Monthly Status Rept Number 10 for Feb 1984 ML20081C3731984-02-29029 February 1984 Seismic Margin Review,Miscellaneous Subsystems & Components ML20084F9061984-02-24024 February 1984 Const Implementation Overview,Weekly Rept Number 37, for 840220-24 ML20084F9261984-02-17017 February 1984 Const Implementation Overview,Weekly Rept Number 36, for 840210-17 ML20080M7381984-02-15015 February 1984 Independent Design & Const Verification Program Monthly Status Rept 9 for Jan 1984 ML20084F8941984-02-10010 February 1984 Const Implementation Overview,Weekly Rept Number 35, for 840206-10 ML20086M2541984-02-0909 February 1984 Balance-Of-Plant Class 1,2 & 3 Piping,Pipe Supports & Valves, Vol IX to Seismic Margin Review ML20084F8391984-02-0303 February 1984 Const Implementation Overview,Weekly Rept Number 34, for 840130-0203 ML20083G8741984-01-0404 January 1984 Structural Evaluation of Midland Diesel Generator Bldg: Assessment of Structural Performance Capability & Serviceability as Potentially Affected by Settlement Induced Cracking ML20083G5871984-01-0404 January 1984 Midland Independent Design & Const Verification Program: Structural Evaluation of Diesel Generator Bldg ML20079E6641983-12-31031 December 1983 Midland Independent Design & Const Verification Program, Monthly Status Rept 8 for Dec 1983 ML20083D9831983-12-0909 December 1983 Auxiliary Bldg Crack Mapping Evaluations for Grillage 8 Initial Jacking & Rejacking ML20083C6631983-11-30030 November 1983 Midland Independent Design & Const Verification (Idcv) Program, Monthly Status Rept 7 for Nov 1983 ML20081J2801983-10-31031 October 1983 Evaluation of Change & Nonconformance Documents,Independent Assessment of Underpinning ML20082A9691983-10-31031 October 1983 Midland Independent Design & Const Verification Program, Monthly Status Rept 6 for Oct 1983 ML20085L1141983-10-17017 October 1983 Fifth Monthly Status Rept for Independent Design & Const Verification Program for Sept 1983 ML20082G4971983-09-20020 September 1983 Midland Summary Rept ML20080E7881983-08-31031 August 1983 Vol IV to Seismic Margin Review:Svc Water Pump Structure Margin Evaluation ML20076C1621983-08-16016 August 1983 Midland Independent Design & Const Verification Program, Monthly Status Rept 3 for Jul 1983 ML20077A7081983-07-31031 July 1983 Rev 3 to NSSS Equipment & Piping, Vol Viii to Seismic Margin Review ML20077H9721983-07-25025 July 1983 Rev 3 to Diesel Generator Bldg, Vol V to Seismic Margin Review ML20076N2391983-07-15015 July 1983 Midland Independent Design & Const Verification Program, Monthly Status Rept 2 for 830528-830630 ML20024D0181983-06-30030 June 1983 Midland Independent Design & Const Verification Program Monthly Status Rept 2, Second Monthly Status Rept for 830528-0630 ML20085D8091983-06-30030 June 1983 Seismic Margin Review,Vol Iii,Auxiliary Bldg ML20072H4981983-06-30030 June 1983 Reclassification of Flued Head Fittings at Midland Plant Units 1 & 2 ML20076G0631983-06-0202 June 1983 Rev 2 to Midland Energy Ctr Spatial Sys Interaction Program/Seismic Mgjec Project Quality Plan ML20071M3581983-05-27027 May 1983 Midland Independent Design & Const Verification Program Monthly Status Rept 1, Covering Period from Project Inception Through 830527 ML20072E5851983-05-27027 May 1983 Independent Design & Const Verification Program,Monthly Status Rept No 1,Period Inception Through 830527 ML20072M2281983-05-18018 May 1983 Independent Assessment of Auxiliary Bldg Underpinning Weekly Rept 34, for 830508-14 ML20072M2121983-05-10010 May 1983 Independent Assessment of Auxiliary Bldg Underpinning Weekly Rept 33, for 830501-07 ML20072M2051983-05-0505 May 1983 Independent Assessment of Auxiliary Bldg Underpinning Weekly Rept 32, for 830424-30 ML20076N2791983-04-30030 April 1983 Revised Visual Insp of Cracks in Containments Near Anchorages in Rooms 110 & 116 ML20023C6841983-04-30030 April 1983 Vol 5 of Seismic Margin Review:Diesel Generator Bldg. ML20023B9021983-04-29029 April 1983 Addendum to 41st ALAB-106 Quarterly Rept,Apr-June 1983. ML20072M1891983-04-27027 April 1983 Independent Assessment of Auxiliary Bldg Underpinning Weekly Rept 31, for 830417-23 ML20072M1771983-04-21021 April 1983 Independent Assessment of Auxiliary Bldg Underpinning Weekly Rept 30, for 830410-16 ML20072M1691983-04-15015 April 1983 Independent Assessment of Auxiliary Bldg Underpinning Weekly Rept 29, for 830403-09 ML20072M1521983-04-0707 April 1983 Independent Assessment of Auxiliary Bldg Underpinning Weekly Rept 28, for 830327-0402 ML20083D3531983-04-0101 April 1983 Proposal for Third-Party Const Implementation Overview, Midland Nuclear Cogeneration Plant ML20072M1461983-04-0101 April 1983 Independent Assessment of Auxiliary Bldg Underpinning Weekly Rept 27, for 830320-26 ML20073D6441983-03-31031 March 1983 Control Room Design Review Final Rept ML20073B9291983-03-31031 March 1983 Quarterly Rept, for Apr-June 1983 ML20073C6111983-03-31031 March 1983 Seismic Margin Review,Midland Energy Ctr Project,Vol II: Reactor Containment Bldg ML20072M1341983-03-23023 March 1983 Independent Assessment of Auxiliary Bldg Underpinning Weekly Rept 26, for 830313-19 1986-04-30
[Table view] Category:TEXT-SAFETY REPORT
MONTHYEARML20058L8721992-12-31031 December 1992 1992 Annual Rept,Cpc ML20126D7211992-12-16016 December 1992 Potential Part 21 Rept Re Actual Performance of Rosemount Supplied Bailey Bq Differential Pressure Transmitters Differing from Rosemount Original Spec.Bailey Controls Encl.Evaluation Not Yet Performed ML20246N1221988-12-31031 December 1988 CMS Energy 1988 Annual Rept ML20154J4101988-05-12012 May 1988 Addendum 1 to Supplemental Part 21 Rept 145 Re Potential Problem w/F-573-156 Pressure Sensor/Lube Oil Trip.Initially Reported on 880429.Addl 1-1/8-inch Diameter W/Deep Counterbone in Pressure Head Added to Activate Valve ML20153B6191988-04-29029 April 1988 Part 21 Rept Re Potential Defect in Component of Dsr or Dsrv Standby Diesel Generators Supplied to Utils.Recommends Return of Subj Components in Onsite Warehouse Storage & Suggests Surveillance of Devices Already Installed ML20196J3801987-12-31031 December 1987 CMS Energy Corp 1987 Annual Rept ML20215G2441987-06-16016 June 1987 Part 21 Rept Re Failure of Load Sequencing Equipment Supplied in Aug 1977 During Scheduled Testing.Caused by Open Electrical Connection on One Crimp Lug.Since 1978,insulated Lugs Used on All Equipment ML20216E4721987-05-28028 May 1987 Part 21 Rept 140 Re Potential Defect in Air Pressure Regulators Mfg by Bellofram.Dripwell Gasket May Fail Due to Mismachining of Gasket Seating Surface Causing Loss of Control Air & Starting Air Pressure ML20207R9041986-12-31031 December 1986 CPC 1986 Annual Rept ML20214A0951986-11-14014 November 1986 Insp & Evaluation Re Adequacy of Stabilization Plan,In Response to Util 860701 Request for Withdrawal of Applications to Extend CP & Util Motions Seeking Withdrawal of OL Application ML20215G6801986-10-10010 October 1986 Part 21 Rept Re Vendor Tests of air-operated Diaphragm Valves Revealing Natural Frequencies Less than Required Values of 33 Hz.Initially Reported on 841227.No Adverse Effects Noted During Testing ML20215G5351986-10-10010 October 1986 Part 21 Rept Re Vendor Tests of air-operated Diaphragm Valves Revealing Natural Frequencies Less than Required Values of 33 Hz.Initially Reported on 841227.No Adverse Effects Noted During Testing ML20205F6141986-08-13013 August 1986 Part 21 Rept Re Connecting Rod Bolts for Dsrv Engines.Listed Procedures Recommended for Next Connecting Rod Insp, Including Replacement of Bolts Due to Cracked Threads & Large Grooves & Galls in Threads ML20206U0591986-07-0202 July 1986 Part 21 Rept Re Potential Defect in Component of Dsrv Standby Diesel Generators,Involving Problem W/Fastening of Engine Connecting Rod Assembly Which Could Result in Engine Nonavailability.Procedure Will Be Issued by 860718 ML20197H2581986-05-0808 May 1986 Part 21 Rept 135 Re Defect W/Lube Oil Sump Tank Foot Valve of Standby Diesel Generator.Caused by Extrusion of Liner Matl Due to Overpressurization.Corrective Actions Being Developed.List of Affected Sites Modified ML20203N4171986-04-30030 April 1986 Rev 2 to Tdi Owners Group App Ii:Generic Maint Matrix & Justifications ML20205N6811986-04-14014 April 1986 Final Part 21 & Deficiency Rept 86-03 Re Consolidated Pipe & Valve Supply,Inc Certified Matl Test Repts.Initially Reported on 860321.Six raised-face Orifice Flanges Statused & Segregated Per QA Procedures ML20205N7381986-04-14014 April 1986 Interim Deficiency & Part 21 Rept 86-02 1 Re Elastomer Liner in Clear Flow Co Foot Valves Used in Lube Oil Sump Tanks of Tdi Diesel Generators.Initially Reported on 860321. Action Will Not Be Pursued Unless Facility Reactivated ML20140H5991986-03-24024 March 1986 Second Interim Deficiency Rept 86-01 Re Error in Bechtel Computer Analysis Program.Initially Reported on 860121.No Corrective Actions Will Be Pursued & No Further Repts Will Be Submitted Unless Project Reactivated ML20154N3431986-03-10010 March 1986 Initial Part 21 Rept 135 Re Potential Problem W/Lube Oil Sump Tank Foot Valve of Dsrv Standby Diesel Generator for Facilities.Cause Not Determined.Recommends Utils Inspect Condition of Foot Valve Liners & Notify Tdi of Findings ML20153F5391986-02-14014 February 1986 Interim Part 21 & Deficiency Rept Re Error in Bechtel Computer Analysis Program ME101.Initially Reported on 860121.No Corrective Actions or Further Repts Will Be Submitted Until Project Reactivated ML20137N6101986-01-10010 January 1986 Interim Part 21 & Deficiency Rept 85-08 Re Isolated Failures of Betts Spring Co Intake & Exhaust Valve Springs Reported by Tdi.Initially Reported on 851218.Corrective Actions Will Be Pursued If Units Reactivated ML20141N8361985-12-31031 December 1985 CPC 1985 Annual Rept ML20138M3891985-12-12012 December 1985 Topical Rept Evaluation of Rev 1 to BAW-1847, Leak Before Break Evaluation of Margins Against Full Break for Rcs.... Rept Presents Acceptable Justification to Eliminate Dynamic Effects of Large Ruptures in Piping ML20198C4981985-11-0606 November 1985 Part 21 Rept Re Potential Defect in Dsr or Dsrv Standby Diesel Generator Intake & Exhaust Valve Springs Mfg by Betts Spring Co.Users Recommended to Inspect Engines for Broken Springs & Identify Original Mfg ML20138B9531985-10-0909 October 1985 Interim Deficiency Rept Re Larger than Anticipated Util Movement Where Freezewall Crossed safety-related Utils at Monitoring Pits 1,2,3 & 4.Initially Reported on 850917.No Action Will Be Taken ML20138C3111985-10-0808 October 1985 Interim Deficiency Rept Re Limitorque motor-operated Butterfly Valves Not Opening Electrically After Closed Manually.Initially Reported on 850912.No Corrective Actions Will Be Taken Unless Facility Reactivated ML20138C3251985-10-0808 October 1985 Interim Deficiency Rept Re Loose Set Screws on Anchor Darling Swing Check Valves & Disc Nut Pin Problems Causing Inoperability.Initially Reported on 850912.No Further Corrective Action Will Be Taken Unless Facility Reactivated ML20132B0261985-09-0303 September 1985 Part 21 Rept Re Possibility of Engine Ingestion of Unwelded Part in American Air Filter Standby Diesel Generator Intake Silencer.Immediate Hold Should Be Placed on Diesel Engines/Intake Silencers Not Yet in Svc ML20132D3191985-07-10010 July 1985 Interim Part 21 & Deficiency Rept Re Rupture During Testing by Wj Woolley Co of Inflatable Seal,Mfg by Presray Corp,Used in Personnel Air Locks in Reactor Containment Sys.Initially Reported on 850614 ML20129G0601985-04-26026 April 1985 Interim Deficiency Rept Re Potential for Cracking of Check Valves in on-engine Mounted Starting Air Piping of Tdi Diesel Generators.Initially Reported on 850401.Cause Not Determined.No Corrective Actions.Related Correspondence ML20112J3951985-03-22022 March 1985 Interim Part 21 & Deficiency Rept Re Failure of Gulf & Western MSIV Actuator Latch Roller Bearing.Matter Will Not Be Pursued Unless Plants Reactivated ML20100B6361985-01-21021 January 1985 Rept on Welding Allegations ML20114D3571984-12-21021 December 1984 Interim Deficiency Rept Re Diesel Fuel Oil Tank Soils Borings.Initially Reported on 841121.No Corrective Actions Necessary Due to Present Project Shutdown ML20100K9791984-11-27027 November 1984 Part 21 & Interim Deficiency Rept Re Ruskin Mfg Co Interlocking Blade Fire Dampers.Initially Reported on 841121.Corrective Action Will Not Be Pursued & No Further Repts Will Be Made Unless Plant Reactivated ML20100D9841984-11-21021 November 1984 Deficiency Rept Re Diesel Fuel Oil Tank Boring Logs.Util Response to Dow Chemical Co 841113 Request for Admissions Encl ML20100E4451984-11-15015 November 1984 Interim Deficiency Rept Re Cardinal Industrial Products Corp Spare Studs Received W/O Ultrasonic Exam.Initially Reported on 841010.Corrective Actions Will Not Be Pursued Unless Midland Reactivated ML20100E2621984-11-15015 November 1984 Interim Part 21 & Deficiency Rept Re Rosemount 1153 Series B Transmitters Potentially Leaking.Initially Reported on 841010.Four Units Shipped to Facilities.Corrective Actions Will Not Be Pursued ML20100E2371984-11-15015 November 1984 Interim Part 21 & Deficiency Rept Re Tdi Fuel Control Level Cap Screws.Initially Reported on 841010.No Corrective Actions Will Be Pursued & No Further Repts on Subj Made Unless Midland Reactivated ML20099E3531984-11-0909 November 1984 Interim Deficiency Rept Re Small Bore Piping Anchor Design. Initially Reported on 840816.Listed Corrective Actions Will Not Be Pursued & No Further Repts Will Be Made Unless Facilities Reactivated ML20093C3211984-10-0101 October 1984 Rev 0 to QA Program Plan for Shutdown Phase ML20093H3961984-08-0202 August 1984 Interim Deficiency Rept Re Seismic Qualification of Power Supplies for Eccas & Ni/Rps Equipment.Initially Reported on 840705.No Activity Being Currently Pursued.No Further Repts Will Be Made Unless Facilities Reactivated ML20093H8521984-08-0202 August 1984 Interim Deficiency Rept Re Field Installation of Itt Grinnell Struts & Extension Pieces.Initially Reported on 840705.No Activity Being Currently Pursued.No Further Repts Will Be Made Unless Facilities Reactivated ML20096A7781984-07-27027 July 1984 Final Deficiency Rept Re Defective Capstan Springs in Pacific Scientific Mechanical Shock Arrestors.Initially Reported on 840106.W/o Description of Investigation & Corrective Actions.Related Correspondence ML20093H8111984-07-27027 July 1984 Final Part 21 & Deficiency Rept Re Capstan Springs in Mechanical Shock Arrestors Supplied by Pacific Scientific. All Suspect Shock Arrestor Capstan Springs Will Be Inspected for Cracks & Defective Springs Replaced ML20093H8871984-07-20020 July 1984 Interim Deficiency Rept Re Reactor Coolant Pump Seals & Seal Covers.Initially Reported on 840622.No Activity Currently Being Pursued.No Further Repts Will Be Made Unless Facilities Reactivated ML20090G2141984-07-18018 July 1984 Idcvp:Control Room HVAC Sys Performance Requirements, Draft Topical Rept ML20093H4751984-07-17017 July 1984 Interim Deficiency Rept Re Core Flood Line Piping Supports in Reactor Pressure Vessel Connection Supplied by Bechtel. Overstressing Could Occur in Pipe Supports.No Commitment Made for Further Repts ML20096A2951984-07-11011 July 1984 Final Deficiency Rept Re Concrete Embedment Design Using Shear Lugs Located Outside Compression Zone.Initially Reported on 821203.Use of Shear Lugs Outside Compression Zone Is Proper Design Technique.Related Correspondence ML20093G7891984-07-11011 July 1984 Final Deficiency Rept Re Concrete Embedment Design Using Shear Lugs Located Outside Compression Zone.No Corrective Action Required.Not Reportable Under 10CFR50.55(e) 1992-12-31
[Table view] |
Text
. .P+ V4fh Ji
., . ,,Midlcnd Plant p) p U
Unito 1 and 2 (,
Independant Assessmant of Underpinning Weekly Report No. 33 May 1, 1983 through May 7, 1983 i
6 Personnel on Site 1
i Stone & Webster Michigan, Inc. l i
W. Kilker 5/2 - 5/7 P. Barry 5/2 - 5/3 L. Rouen 5/2 - 5/6 Parsons, Brinckerhoff Michigan, Inc.
J. Batner 5/2 - 5/6 Meetings Attended Date Represented Purpose j 5/2 Stone & Webster Daily Meetings !
through Bechtel ,
5/5 consumers Power t Parsons 5/3 - 5/5 ,
Activities T
Construction -
Piers E/W 12: These piers have been completed and loaded for nearly 2 months.
Unless non-routine rejacking or other unusual actvitity is performed at these piers no activity description will be included in this or future reports.
Piers E/W9: These piers have been completed and loaded for approximately 5 weeks.
As in the case of E/W12 piers, activity descriptions on these piers will be generally omitted from future weekly reports.
Pier Ell: No activity.
KC11 Drift: The excavation and lagging is virtually complete with only one drift set remaining to be installed. A sizable portion of the excavation was through unreinforced concrete - particularly in the northeast segment of the drift nearest pier E12. Along the southwestern side of the drift the thickness of concrete decreased to approximately li ft. with clay fill making-up the remainder of the excavated section.
Pier E8: No further work (beyond the previously reported depth of 24 ft.) was performed on this pier. Drawing changes to the bell support system delayed the release for fabrication of not only the bell support steel but the lagging ring beam sets above the bell.
I 1
i 8307140373 830630 PDR ADOCK 05000329 t g PDR
, 6tG4G kW. VUNSe l
Midland Plant Units 1 and 2 ()
Independent Assessment of Underpinning 2
()
Pier E10 Drift: The excavation and lagging support has been complete. The excavated material consisted of approximately 1 ft. of unreinforced concrete l I
underlain by clay fill.
East Access Shaft (Zone between access pits to E12 and E11): A cut slope in this area slumped on May 7 after a period of heavy rainfall. The Contractor cleared the area and installed wood lagging to prevent further slippage.
Pier W11: The pier load time deflection criteria was satisfied and the load transfer to wedges and the required routine rejacking of the pier was performed.
KC2 Drift: The excavation was completed to 8 ft. south of a line formed by the south side of piers W11 and W12. The excavated material consisted of unreinforced concrete and sand / clay fill with a horizontal layer of fill sandwiched between concrete in certain areas.
Pier W8: The pier excavation and lagging was installed to El. 587 - a depth of approximately 13 ft. The excavated material was generally a clay fill. Minor groundwater seepage entered the excavation at El. 587 Pier W10 Drift: The excavation and lagging support was completed. The excavated material consisted 1 ft. of unreinforced concrete underlain by a mixture of clay and sand fill. The pier template was located in preparation for the pier excavation.
Slope lay-backs north of piers E/W10: The Contractor excavated the: slope lay-back on approximately a 1:1 slope in the existing fill materials.
SWPS: The Contractor began the installation of dewatering wells within the pumphouse. To-date the activity has consisted of the completion of 2 SPT borings.
51= Quality Control. Documentation and Records:
- 1. Assessed the proposed procedure for verifying the concrete vibrator frequency.
- 2. Observed the identification procedures used to control fabricatec materials in the on-site fabrication shop.
3 Reviewed the qualifications and certifications of several QC inspectors that performed inspections on piers E/W9, 11 and 12. The inspection activities included excavation and lagging, mechanical splicing, rein-forcing steel placement, concrete placement, bearing plate installation and load transfer,
'4 Reviewed the issuance and use of the QA/QC Inspection Reports on the inspection activities tabulated under Item 3 above.
( '
- 5. Observed the Engineering and QC inspection of the SPT borings performed
- in the SWPS.
Observations Construction - The advancement of theedrifts to KC2 and KC11 piers was hampered by the presence of unreinforeed concrete - in the case of KC11 by the sheer quantity and at KC2 by the delay caused in determining the nature of a segment of " formed" concrete.
i
~ ~ ~ ~~ ~' ' ~
3}.O.No. 14358
' Midland Plant Units 1 and 2
() ()
Independent Assessment of Underpinning 3 The Contractor responded to the slippage of the soil mass extending into the access shaft north of the KC11 drift by quickly installing lagging to prevent further slope deterioration. .
I The lagging set spacing at pier W8 is generally on the order of 1) inches. A random verification of the backpacking quality indicated the granular backpacking i material is generally filling any void space between the excavated soil and l lagging sets. However, the inspection process is still hampered somewhat by the presence of the backpacking material extending well into the louvered area ,
between lagging sets.
The pier W11 load transfer was completed by locking-off the load to the jackstand wedges. The Owner / Contractor will discuss with the NRC the engineering data !
obtained from this pier and others loaded to date.
The delay of more than one week in field activities on partially completed pier E8 ,
due to design changes in the construction support system, in the Assessment Team's [
opinion, does not represent an endorsable planning / construction methodology. [
The Assessment Team feels the Contractor should be better prepared to complete a j pier prior to initiating the excavation. g Quality Control. Documentation and Records - The fabrication shop was properly I and clearly identifying and segregating QC " accepted" and "on-hold" materials.
The review of the inspector's certifications to perform inspections on numerous critical activities at 6 of the piers installed to-date indicated that the qualification and certification requirements were met by these individuals and that the issuance and use of the QC Inspection Reports was correct.
The Assessment Team requested a clarification on the assignment of the responsibility for verification of the concrete vibrator frequency. The Contractor agreed to address this concern.
The Assessment Team raised a concern about the practice of allowing field work to proceed beyond a stage in the construction where a NCR " hold-tag" has been installed on a certain item (s). If this practice is to continue there should be a means of documenting Engineering approval for the continuation of the field work.
The Assessment Team has an on-going concern over the lack of timely disposition of numerous outstanding QC hold-tags that have appeared on installed material.
The majority of the NCRs written that have apneared as " hold-tags" in the work area have dealt with the temporary support system - drift sets, anchor bolts, drift set plates and pier lagging. If the work is going to proceed on a reasonable schedule the Organization (Engineering, Quality Assurance and Con-struction) must address and eliminate the numerous delays associated with non-conformances relating to these temporary support system details. As an example, at the present time in the pier W8 drift and pier excavation these are approximately 30 NCR " hold-tags". While some of the tags are a matter of only a few days old others have been in place nearly two weeks. It is our opinion that the nature of i-the majority of these non-conformance is such that complete dispostion should be I
accomplished easily within a few days .
J.O.
No. 14358
' -
- Midland PL:nt Unita 1 and 2 ('~) (')
Independent Assessment of Underpinning 4 Design Work Packaces and Procedures - The Assessment Team performed an overview of the design work package relating to the installation and load transfer to piers E/W 10, KC2, KC3, KC10 and KC11. In general, the package was complete.
However, the Team discussed with the Owner the degree to which drawings and procedures should be actually included in the " package" or referenced as existing.
Non-Conformance Identification Reports Status of previous issues: (NIR numbers no longer listed have been closed-out.)
NIR NO. Description Date (0pened) (Closed )
5 Concrete Mix 2/10/83 Qualification 6 Lagging Spacers 3/21/83 7 Backpacking Material 4/5/83 in Wet areas-Pier W11 8 Load Transfer Method- 4/5/83 ology - Pier E12 9 Release of Pier W9 4/13/83 F- for Load Transfer 10 Verification of 4/21/83 Vibrator Frequency
//
~
b -
V w wo Project Engineer Project Manager I
l 1
1
- q o o DAILY INDEPENDENT ASSESSMENT TEAM MEETING .
Date: May 2, 1983 Bechtel Stone / Webster CPCo Attendees: M,POAD D. Lavelle P. Barry R. Sevo , G. Murray ,
J. Fisher J. Gaydos .
1 Parsons s
, n ,
J. Ratner , ,
.s , j
~
- 1. D. Lavelle provided a copy of the latest data for the load' test of pier. 11. - '
The pier is maintained on jacks at 110 per cent of specified load. Bechtel and CPCo intend to have a conference call with the NBC,pb discuss the test ' , 'J results. ,
- 2. J. Fisher stated that the " Administrative Guideline" for Construction Aid Procedure had been distributed for final comment. The Assessment Team has been provided with a copy. ..
- ' , i 3 D. Lavelle will provide a copy of the NCRs written on wcid fabrication _
last week. ._ ,
N -
s -
E 4. J. Fisher read E. Cvikl's response to the April 28th queption concerning r unreinforced KC piers. These piers are designed as pedestals in accordance with ACI 318. Soil support allows these piers to be constructed with plain concrete.
- 5. P. Barry questioned why expansion achers in the east drift,that have hold [
tags ,were put "in service" by the fact that the drift excavation was allowed -
to proceed beyond the point of -infraction. These NCRs were written when s after a reinspection the excavation had progressed past the affected drift sets. In the West drift the excavation waited until the drift sets including , '
expansion anchors were properly installed. Bechtel is aware of the situation ~
and will provide an explanation.
V l
l 1
~m . , c ,y. . _
..._7 ._
(,,.-
[4 (-
y y,A " o v ('~] x (I;j %7 .
,A*
- . I 1 ,
' s, g ; * , g '. % .
DAILY INDEPENDENT ASSES 3" INT TEAM MEETING
~
p.
, .- s ;.
l: ' -[ " 3 Date: May 3, 1983
,i Q \
~ ,, ,
.,?, -
Bechtel Stone / Webster MPOAD CPCo
- f. s J"-Att~endees:
~U s ', J. Fi der W. Kilker J. Shah -----
-d v~
D .
J. Gaydos L.
Rouen
'~'
s v '
% Parsons
' v ,' ' ',
'- .J. Ratner
( \ 1. J. Fisher explained that the delay in completing the shaft portion of, pier E8 :
is due to lack of approval for the shop drawing showing changes in the lagging sets just above the bell elevation. Approval is expected shortly so fabrication j can proceed. ;
t
~
- 2. J. Fisher and J. Shah explained the basis for determination of whether or j not work troceeds in a particular area after an NCR has been issued by ,
MPQAD. Aftpi issuing a particular NCR, MPQAD discusses the matter with Resident Engitt,aering in terms of impact on proceeding with cor.struction.
%, At that, time the NCR is worded in terms of prohibiting or allowing work
_ ? to procped "around" the subject of the NCR. L. Rouen agreed that this type
,N o,f action or, discussion on an NCR would be appropriate providing there was
- . s s s g a 1aethod'~ofVdocementing the Engineering concurrence.
In the case of the
' '- - ' E3 drift Hilti-bolt related NCRs,' it was determined that the nature of the
- - nq3.-confo!cances was such that work could proceed. J. Fisher said FSO had
, disposi31oned these particular NCRs to Engineering.and were awaiting resolution.
3 Cf.neral'discucsion of the up-date on pier W11 lead test.
- \
I 1
. \
- x. ;
i e
- . , .~ _ m. --
. , , - - - . _ . . v .y ..
o o
DAILY INDEPENDENT ASSESSMENT TEAM MEETING Date: May 4, 1983 Attendees: Bechtel Stone / Webster MPQAD CPCo J. Gaydos L. Rouen J. Shah G. Murray E. Cviki W. Kilker A. Blocher l
I Parsons J. Ratner ,
t
- 1. W. Kilker said the Assessment Team observed the NCR on pier W9 concrete i placement has not been removed. FSO will investigate. l l
- 2. There was a discussion of backpacking of lagging sets on pier E8. The Assessment Team observed that the lagging spacers were on the average ,
1-1/8 inches thick and that the backpacking material was still being placed to the inside face of the lagging. In the opinion of the Team both of these conditions continue to hamper somewhat the backpacking operation and in particular the inspection process. FSO will take action.
3 E. Cviki advicea that the shop drawings for E8 ring beam lagging sets should be signed out today allowing fabrication to commence. However, J' field work will not begin until all fabrication is completed.
a 6
o o
l DAILY INDEPENDENT ASSESSMENT TEAM MEETING l Date: May 5, 1983 Stone / Webster MPQAD CPCo Attendees: Bechtel E. Cviki W. Kilker R. Sevo -----
J. Gaydos L. Rouen J. Fisher D. Lavelle Parsons J. Ratner
- 1. D. Lavelle.and W. Kilker discussed the potential impact on construction with the use of the proposed Construction Aid Procedure. D. Lavelle said defining certain of the construction operation and installation as Construction Aids should have a positive impact on the underpinning activity.
- 2. J. Fisher provided a Mergentime schedule for the installation of pier E8 and E8 grillage.
3 W. Kilker reported the Team's observation of the QC hold tag on pier W9 concrete pour. FSO will investigate to determine state of disposition.
E' 4. J. Fisher reported that FSO concurred with lagging spacer sizes on pier E8.
In order to expedite the inspection process spacers in the future will be on the order of 1-3/8 1/2 inches thickness.
S. L. Rouen questioned the assigning of responsibility for checking the concrete viberators - would it go to Field Engineers or QC. FSO will take action to discuss the responsibility.
- 6. J. Gaydos provided a copy of all NCRs related to tolerances to the Assessment Team.
7 J. Rhtner questioned why the lower level plates at jack #4 on pier W11 do net level up with adjacent plates. FSO will take action to determine that load application is appropriate.
i
. ,. ,. - ,~ . .- . , , . - - . . - - , . - - .
o
?,
~,
o o I
DAILY INDEPENDENT ASSESSMENT TEAM MEETING Date: May 6, 1983 4
[
No meeting was held on this date.
T
r
't
)RINCIPAL STAFF '
VB^ L enF 1 STONE & WEBSTER MICHIGAN, INC. 0/RA scs v7 y A/RA p,30 P.O. Box 2325. BOSTON, M ASSACHUSETTS O2107 -DPRP
}9!.O j DL OC i
$R De
_t l
.g 1
.-] ;
. _-g
' [F E & y United States Nuclear Regulatory Commission May 10, 1983 Midland Site Resident Inspection Office Route 7 J.O. No. 14358 Midland, MI 48640 Ref. MPF 33 Attention Mr. R. Cook RE: DOCKET NO. 50-329/330 MIDLAND PLANT - UNITS 1 and 2 INDEPENDENT ASSESSMENT OF UNDERPINNING REPORT NO. 33 A copy of the Independent Assessment of the Underpinning Weekly Report No. 33 for the period May 1, 1983 through May 7, 1983, is enclosed with this letter.
Included as attachments, are the minutes of the daily meetings held during the week between members of the Assessment Team and Site Engineering, Construction, and Quality Assurance personnel.
If you have any questions with respect to this report, please contact me at (617) 589-2067).
Very truly yours,
- k. *tbyscq 4
A. Stanley Lucks Project Manager Enclosures ASL/ka l
l l
l MAY 161983