ML20085L114

From kanterella
Jump to navigation Jump to search
Fifth Monthly Status Rept for Independent Design & Const Verification Program for Sept 1983
ML20085L114
Person / Time
Site: Midland
Issue date: 10/17/1983
From: Beck J, Daugherty F, Levin H
TERA CORP.
To:
Shared Package
ML20085L101 List:
References
NUDOCS 8310210275
Download: ML20085L114 (51)


Text

< ,

MIDLAtO ltOEPEbOENT DESIGN AND CONSTRUCTION VERIFICATION PROGRAM MONTI-LY STATUS REPORT NUMBER 5 -

PERIOD SEPTEMBER 1,1983 THROUGH SEPTEMBER 30,1983 d

Prepared by: M Manager, Dhsign Vedfication

h. . .. m'%

Manager, Construction Verification

/ .

Project Manager Approved by: U

Princhal-in-Charge 8310210275 831017 PDR ADOCK 05000329 PDR R TERA CORPORATION

o i MIDLAPO INDEPENDENT DESIGN AIO CONSTRUCTION VERIFICATION PROGRAM (IDCV)

MONTHLY STATUS REPORT

- NUMBER 5 .

PERIOD SEPTEMBER 1,1983 THROUGH SEPTEMBER 30,1983

1.0 INTRODUCTION

AND PURPOSE Monthly Status Reports have been instituted by agreement between the Con:umers Power Company (CPC), the Nuclear Regulatory Commission (NRC) and TERA to provide parties external to TERA's IDCV project team with up-to-date information relative to program progress and any important issues identi-fied during the reporting period. This report covers the period from September I,1983 through September 30,1983. A description of the scope, reporting periods and report issuance dates for Monthly Status Reports, as well as a summary of the background of the IDCV program were presented in the initial Monthly Status Report dated May 27,1983.

2.0 IDCV PROGRAM STATUS

SUMMARY

2.1 Programmatic Activities Attachment I provides on updated chronology of major project milestones. The project chronology from inception through the beginning of this reporting period can be found in the previous monthly status reports. Several milestones warrant special highlight.

Revision 3 of The Engineering Program Plon and revision 4 of The Project Quality Assurance Plan were issued on September 6,1983. These revisions reflect changes in the project organization, improvements to administrative control procedures, formal issuance of Project Instructions PI-3201-006, Use of ~

Design Verification Checklists, and PI-3201-007, Use of Construction Verifica-tion Checklists.

l

1 i

e i Revision 3 of MED 4.40 - 0, APPD Manager of Engineering Directive was issued by Bechtel on September 28,1983 which provided clarification on Bechtel's internal procedures for the release of calculations (Revision 4 was later issued on October 10,1983 providing additional clarification). These revisions are intended to speed the release of calculations. From TERA's perspective, it appears that the new procedure represents imp.:avement that will facilitate the overall execution of the IDCVP.

A public meeting is planned for October 28,1983 of Bechtel's Ann Arbor,

~

Michigan offices to discuss outstanding Open, Confirmed, and Resolved item Reports, Finding Reports, and Finding Resolution Reports. The proposed agendo will be forwarded along with the meeting announcement to be issued in accordance with the IDCVP protocol.

2.2 Design Verification Activities 2.2.1 Summary The consolidated criteria and commitments list for the Auxiliary Feedwater (AFW) system was issued for use by AFW system reviewers offer incorporating additional criteria which were identified since the previous issue. A draft of the consolidated criteria and commitments list for the Control Room HVAC (CR-HVAC) system was issued for internal comment. Work continued in the development of a comparable list for the Standby Electric Power (SEP) system.

Considerable effort was expended during September for the review, confirma-tion, or resolution of Open and Confirmed items on the AFW system. Status changes to OCRs are discussed in detail in Section 3.0, and a status summary is presented in Attachment 2. The following is a brief discussion of the most significant activities relative to OCRs and Findings which have occurred in the post month:

e Finding 012 was resolved through the issvonce of a Finding Resolution Report based upon MCAR 68 which has been sent to the NRC as a 50.55(e) report.

2

  • s e item 040 was confirmed. It is concerned with a dis-crepancy between calculated maximum cable length and cable length per the circuit schedule.

e item 015 was issued as a Confirmed item. This item ,

discussed areas within the Bechtel vertical floor flexi-bility study which require additional information to allow the IDV review to continue.

e items 066 and 073 thru 076 were issued as Confirmed items to determine whether additional information exists regarding certain aspects of the CR-HVAC design.

A B&W calculation was received which determined the effect of changes to AFW porometers, This calculation will be reviewed in conjunction with SAR Change Notice (SCN) 4067 which was received shortly offer the end of the reporting period.

2.2.2 Auxiliary Feedwater System Progress Review of mechanical calculations supporting the flow diagram and the set point for AFW low suction p essure were begun. Reviews of implementing documents for the component functional requirements were initiated. These calculations, ,

as well as other calculations which were reviewed previously, and the imple-menting documents form the basis for on engineering evuluotion covering component functional requirements, system hydraulic design, and system heat removal capability. B&W document 86-1143885-01 was received and reviewed in September. This document and SCN 4067 will be used in the disposition of several Confirmed items.

Reviews of equipment environmental and seismic qualification packages were conducted in September and will continue in October.

Additional information received in response to Confirmed item C-022 was reviewed. Furthu information is required to determine the appropriate disposi-tion of this item.

A preliminary evoluotion of the Systems Interaction review crea was prepared.

Further progress in this area depends upon progress in the actual performance of 3

l the Systems interaction program. TERA has requested additional information which is being developed as the system interaction program progresses.

In the civil / structural review creo, a preliminary summary of the enronology of seismic analysis has been prepared; however, odditional clarification is required to complete this area of review. The auxiliary building underpinning model analysis and structural review continued and is nearing completion. Additional information was received from Bechtel and was reviewed. Additional informo-tion collection and reviews of computer printcuts are scheduled to be conducted in Ann Arbor during the first week in October.

Additional MCARs and SCREs were requested and received and will be reviewed to ensure that the sample selection process is sensitive to previous problems.

2.2.3 Standby Electric Power System Progress The SEP system design verificotton is progressing in the following major creas:

e Identification and evoluotion of criteria and commitments for all disciplines e Requests for additional documentation e Review of electrical calculations.

Progress continued in the identification, review, and evoluotion of the criteria and commitments for the SEP system. The review topics associated with each criterio/ commitment are being added to the consolidated list. The finalized consolidated criteria and commitments document will be issued in October.

Work packages have been identified and scoped to encompass the balance of the SEP system review topics and items, with each work package culminating in on engineering evoluotion. On the basis of each work package scope, additional documentation requirements are being identified.

The following calculations have been received and are under review:

4

OPE-l Emergency Diesel Generator Sizing (including SAR change notice)

QPE-4 8 and 5 kV Cable Sizing GPE-5 125 V Battery and Charger Sizings

+

GPE-6 Voltage Regulation Study GPE-7 Inverter Sizing System descriptions for relevant electrical and mechanical systems continue to be reviewed and will be utilized to facilitate the detailed engineering evoluo-tions.

Similar to the AFW system, a review of oppropriate MCARs and SCKtis was also initiated to assist in the sompte selection process.

2.2.4 Control Room HVAC System Progress The criterio review portion of the Control Room HVAC System review has been completed and a consolidated criteria and commitments list has been issued for ,

use in subsequent portions of the review. The review of the system P&lD is essentially complete.

Calculations have been reviewed which cover the following topics:

e System operating limits e Accident analysis considerations e System pneumatic design e Cooling / heating requirements f e Filtration e Pressurization e Ventilation.

Completion of the review was on hold awaiting receipt of three calculations which were being revised. These calculations have been received and the review will be completed in October. In parallel with that activity, the review of the l

5

seismic qualification methodology for HVAC duct which began in September will continue. Completion is anticipated in early November.

The review of electrical topics which was initiated with a joint mechanical /

electrical failure modes and effects review has progressed into the implemento-tion document and drawing review stages. A substantial number of logic diagrams and schematic diograms pertaining to the system were requested and received. Specific steps have been identified to complete the review activities for each of the opplicable review topics. The review of electrical schematics and associated evaluations for all electrical topics is scheduled for completion in

. October.

The structural review of the Auxiliary Building as discussed under the AFW review has been extended to incorporate aspects of the seismic design pertinent to the Control Room HVAC. For o discussion of progress in the combined structural review, see the AFW System discussion.

2.3 Construction Verificotton Activities 2.3.1 Summary Activities undertaken and events which occurred during this reporting period which are important to the overall conduct of the construction verification review portion of the IDCV program are os follows:

e During this reporting period, a shift in the focus of TERA ICV program .

octivities occurred. This shift was precipitated by the following events and resulted in redirecting resources from the review of AFW system compo-nents to components and commodities within the CR HVAC system boun-daries.

- Understandings developed with cognizant NRC and CPC personnel that the report to be prepared by TERA in support of Ford Amend-ment activities need not necessarily oddress the Construction Verifi-

- cation review as the review relates to installed components and commodities within the AFW system.

6

- Realization on the part of ICV reviewers and program management of the full impact that CCP status has, and continues to have, upon ICV reviews directed towards the AFW system.

- Completion, to the extent allowable by CCP status, of the ICV review of ovailable construction / installation documentation associ-oted with the following categories of AFW system components and commodities. This review cannot be considered complete until such time that verification from the CCP is obtained stating that the CCP has completed Phase I activities associated with ICV selected items within the AFW system sompte boundaries.

-- Piping runs

- Pipe hangers and supports

- Valves

- Rotating Equipment

- Cable trays / conduit and supports

- Selected portions of the CR HVAC system (those considered in the ZACK scope of worl<) are currently available for ICV field verifico-tion review activities.

e TERA reviewers completed their field activities associated with the verification review of the honger verification program and have initiated the preparation of on engineering evoluotion of the results of our verifico-tion review.

2.3.2 Construction Documentation Review Progress Construction documentation review relates to those ICV review categories which are principally concerned with the adequacy and completeness of ovailable documentation as opposed to those ICV review categories which verify the physical configuration of installed components and commodities. The following ICV review categories are part of construction documentation review.

7

e Review of Supplier Documentation e Review of' Storage and Maintenance Documentation e Review of Construction / Installation Documentation A description of progress made and principal activities undertaken in each of the above review categories are os follows:

Review of Supplier Documentation e During the week beginning September 12, 1983, ICV reviewers were on site and completed their review of material selection and associated vendor-supplied verification documentation. Certain inconsistencies were observed during the review which have been opened fer further evaluation.

e ICV reviewers completed their evaluation of information obtained concern-ing the completeness of vendor documentation submittals associated with selected components within the AFW system. Inconsistencies observed during this evaluation were noted and recorded in Confirmed item C-052.

A similar evaluation is currently being performed for selected vendor-supplied equipment within the CR HVAC and SEP systems.

- e A review of vendor-supplied NDE procedures and associated verification documentation was initiated and as of the writing of this report is approximately 70 percent complete.

Review of Storage and Maintenance Documentation e ICV reviewers continue to review and evoluote information provided to .

TERA by Bechtel in response to findings documented in OCR's 045, 046, and 047. TERA received, and is currently evaluating, the following documentation.

- Bechtel letter #BLC-17798 dated August 25,1983

- CPC Audit Report, Audit #M02-19-3, addressing the inspection and maintenance of safety-related vendor-supplied hardware 1

I 8

O

- NCR 6262

- Bechtel IOM dated May 6,1983

- Report entitled "Tosk Force Proposal for Reorganization .

of the Storage and Maintenance Program" o ICV reviewers completed a preliminary engineering evoluotion of the storage and maintenance review of selected components within the CR HVAC or..! SEP systems. The preliminary engineering evoluotion is currently under review by ICV program management and is being inte-grated with the review of programmatic modifications os discussed above.

e TERA site personnel were contacted by cognizant Bechtel personnel to verify the notification lead time necessary to ensure TERA's presence during the vendor's inspection of the AFW pumps and turbine.

Review of Construction / Installation Documentation e To the extent allowable by CCP status, ICV reviewers completed their review of construction installation documentation associated with selected cable trays / conduits and supports within the AFW system sompte boun-daries.

e A preliminary evoluotion of the results of the ICV review of available construction / installation documentation for the following selected items within the AFW system was completed during this reporting period.

- Pipe Runs

- Pipe Hongers and Supports

- Volves

- Rotating Equipment

- Cable trays / conduit and supports inconsistencies observed as a result of the evoluotion were noted and recorded in Confirmed items C-053 and C-054. A related Open item was identified associated with site welding procedures and procedure quahfico-tions which are currently being pursued by ICV reviewers.

9

o e Personnel conducting the construction / installation documentation review were redirected by ICV program management to focus their attention upon selected components and commodities within the CR HVAC system. ICV reviewers have commenced the identification, acquisition, n<similation and

, review of pertinent documentation.

2.3.3 Physical Verification / Site Activities Program The activities described herein address those ICV review categories which require ICV reviewers to observe, witness, or verify field activities and/or the os-built configuration of installed commodities and components. For the most part, these activities require a strong site presence on the part of reviewers and include the following review categories:

e Review of Selected Verification Activities e Verification of Physical Configuration Review of Selected Verification Activities e TERA completed the overview of the hanger overinspection program.

During the week beginning September 26,1983, ICV reviewers observed site personnel in the performance of ASME, Section ill, Class I and ll pipe support reinspections. Document control and program training activities within the hanger overinspection program were also reviewed for the purpose of completing applicable verification checklists.

e Additional nonconformance report files associated with the cable over-inspection activities were obtained at the site os a prerequisite in developing an expanded sample base recommended as a resolution to Confirmed item C-050, relating to cable misrouting.

e Results of the cable overinspection program have been categorized by TEP.A reviewers as a first step in attempting to develop a statistical model with which to evoluote the overinspection program results. The assimi-lated dato is currently being reviewed for the purpose of ascertaining whether or not a statistical modeling technique is appropriate and feasible.

10

Verification of Physical Configuration e Anticipating the commencement of physical verification activities for selected CR HVAC components and commodities, ICV prograr6 manage-ment commenced mobilizing the physical verification team. Near term octivities relate to determining the completion status of the installation of ICV selected items with physical verification activities tentatively sched-uled to commence during the latter part of October.

3.0

SUMMARY

OF CONFIRMED AND RESOLVED ITEM REPORTS, FINDING REPORTS, AND FINDING RESOLUTION REPORTS Attachment 2 provides TERA's Tracking System Summary for Open, Confirmed, and Resolved (OCR) Item Reports, Finding Reports, and Finding Resolution Reports. This tool assists TERA in tracking the disposition of issues os they progress through the review process. Items that have changed status or that have been added during the reporting period are noted with on asterisk.

Attachment 2 provides retyped copies of Resolved item Reports (that have closed out Confirmed items), Confirmed items, Finding Reports, and Finding Resolution Reports. Several Observations are also ottoched. The following paragraphs discuss items which have changed status in the post month.

No Findings were identified during the period; however, Finding F-012 associated with a loss of power to the FOGG relays during a station blackout was resolved (see Finding Resolution Report 3201 -008-Z-012). Resolution was based upon specific corrective action taken to power the FOGG relays with Class IE DC backed 120 VAC power, Bechtel engineering review of all power supplies to Class IE interlocks for volves and prime movers requiring Class IE DC backed power, and revised instructions for power supply design verification activities.

Confirmed item 3201 008-C-017 associated with apparent inconsistencies in the minimum required AFW flow was resolved. A flow rate of 850 gpm was clarified by the project.

II

~ _ _ _ ._. _. __ _____ _ __.. .__ _ _ _ - ~ _ _ . _ . _ _ _ _ _ _ _ _ __.

Open items 3201-008-0-041,0-044, and 0-057 were resolved; 0-044 and 0-057 as Observations. In accordance with Project Instruction PI-3201-005, Documen- j totion of Observations, these Observations are being forwarded to CPC to allow them to take appropriate and timely action in correcting these items 1which are

, not considered sufficiently serious to warrant classification as Confirmed items and cannot be dismissed directly as Resolved items, but which should be reviewed and corrected. Five other Observations (3201-008-B-058, B-059, B-061, B-063, and B-064) were identified during the period. Thirteen new Open items (3201 -008-0-055, 0-056, 0-058, 0-060, 0-062, 0-065, 0-069 thru 0-072 and 0-077 thru 0-079) were identified during the period.

Twelve Confirmed items were identified during the period concerning:

e 3201-008-C-015 - Functionability under a seismic event of certain equipment and piping located on flexible floors.

e 3201-008-C-040 - Unsizing of cable due discrepancies in the installed length.

e 3201-008-C-043 - Seismic and quality classification of essential piping.

e 3201-008-C-052 - Completeness of vendor supplied docu-mentation.

e 3201-008-C-053 - Completeness of construction / instal-lation documentation.

e 3201-008-C-054 - Miscellaneous inconsistencies associ-ated with project quality control instructions (PQCls).

e 3201-008-C-066 - Control room HVAC system olignment at subsequent phases of on accident involving airborne radioactive release, e 3201-008-C-068 - Discrepancy in the required seismic qualification level for the AFW motor driven pump.

e 3201-008-C-073 - Limiting accident conditions for sizing the Control Room HVAC air handling unit cooling coils.

e 3201-008-C-074 - Criteria for Control Room environ-mental conditions during a station blackout (loss of all oc power).

e 3201-008-C-075 - Assumptions of inleakage to the Control Room.

12

e 3201-008-C-076 - Bases for dato used to evoluote the ability of the Control Room HVAC to maintain control room temperature.

e 3201-008-C-007 - Inconsistencies in the FSAR. ,

These items as well as other outstanding items will be discussed at the October 28,1983 public meeting at Bechtel's Ann Arbor offices.

4 i

f 13

ATTACHMENTI PROJECT ClitONOLOGY MIDLAtO INDEPEf0ENT DESIGN AND -

CONSTRUCTIOil VERIFICATION PROGRAM ERA PROJECT 3201 PERIOD SEPTEMBER 1,1982 TI-ROUGH SEPTEMBER 30,1983 Date Milestone September 1-23,1983 TERA Construction Review Team on-site conducting construction / installation docu-mentation review.

September 6,1983 Revision 3 of the Engineering Program Plan and Revision 4 of the Project Quality Assuron::e Plan issued.

September 7,1983 Meeting summary issued for second meet-ing on Confirmed items held on August 26,1983.

September 8,1983 IDV Civil / Structural reviewers at Bechtel's Ann Arbor offices reviewing calculation packages for release.

September 12-15, 1983 TERA Construction Review Team on-site conducting review of vendor supplied material selection criteria and associated verification documentation.

September 20,1983 Fourth IDCVP Monthly Status Report issued.

September 21,1983 Meeting between TERA and CPC to discuss project financial status, schedule and administrative matters.

September 26-30,1983 TERA reviewers on-site witnessing pipe honger over-inspection activities.

September 29,1983 NRC inspection and Enforcement Head-quarters staff at TERA's Bethesda offices observing IDCVP octivities and obtaining programmatic information.

Attachment l l

ATTACHMENT 2 OCR, FIFOING REPORT, APO FIPOING RESOLUTlON REPORT TRACKING SYSTEM MIDLAPO IPOEPEPOENT DESIGN APO CONSTRUCTION VERIFICATION PROGRAM ,

10/17/83 OCR No. Resp. LTR Potential Open Confirmed Resolved Finding Finding Topic Comments Open item item item item / Fleport Resolution Ervation Report 0 01 RPS 12/21/83 3/4/83 3/4/83 7/12/83 1.4-1 Tech Specs

. 002 RPS 12/21/83 3/4/83 3/4/83 7/12/83 1.4-1 Tech Specs 003 RPS 1/3/83 3/4/83 3/4/83 1.8-1 Overpressure Protection 004 RPS 1/3/83 3/4/83 3/4/83 1.8-1 Overpressure Protection 005 RPS 1/4/83 3/4/83 3/4/83 1.1-1 System Operating Limits 006 RPS 1/12/83 3/4/83 3/4/83 1.2-1 Accident Annlysis Considerations 007 RPS 1/12/8 3 3/4/83 3/4/83 1.2-1 Accident Analysis Considerations 008 LB 1/19/83 3/4/83 7/12/83 I.19-1 Control Systems 009 CS 1/20/83 3/4/83 3/4/83 11.1-1 Seismic Design i 010 FAD 1/20/83 3/4/83 4/14/83 7/12/83 I.10-1 Hydraulic Design Oli LB 1/27/83 3/4/83 3/4/83 8/8/83 1.19-1 Control Systems Power Supplies

  • 012 LB 2/7/83 3/4/83 3/4/83 7/12/83 9/30/83 1.15-1 013 RPS 2/8/83 3/4/83 7/12/8 3 1.5-1 Syst. Align./Switchover
  • Change in Status During Reporting Period a

9

D

+

OCR, FibOING REPORT, APO FPOING RESOLUTION REPORT TRACKING SYSTEM MIDLAto POEPEPOENT DESIGN APO CONSTRUCTION VERIFICATION PROGRAM 10/17/83 (continued)

Resp. LTR Potential Open Confirmed Resolved Finding Findi Topic Comments OCR No.

Open item item item item / Report eso ution Ervation Report 0:4 RPS 2/8/83 3/4/83 7/12/83 1.5-1 Syst. Align./Switchover Seismic Des?gn/ Input

  • 015 CS 2/10/83 3/4/83 10/l1/83 lll.1-1 to Equipment 016 CS 2/10/8 3 3/4/83 111. 5 -1 Civil /Stu Design Consid.

Heat Removal Cap

  • 3/4/83 3/4/83 10/S/83 1.11-1

! 017 FAD 2/17/83 1.10-1 Hydraulic Design 018 FAD 2/17/83 3/4/83 3/4/33 1.11-1 Heat Removal Cap.

019 LB 2/21/8 3 3/4/83 8/8/83 1.18-1 Instrumentation 020 FAD 2/24/83 3/4/83 3/4/83 1.11-1 HeatRemovolCop.

l.9-1 Comp. Func. Req.

11.1 0 -1 Eq. Qual. 0-21, Rev. I, 021 FAD 2/24/83 3/4/83 4/14/83 022 LB 2/24/83 3/4/83 8/8/83 1.19-1 Control Syst.

023 LB 2/28/83 3/4/83 8/8/83 1.18-1 Instrumentation 1.19-1 Contre!

.?

OCR, Fl>OING REPORT, Ato FitOING RESOLUTK)N REPORT TRACKING SYSTEM MIDLAPD itOEPEPOENT DESIGN Ato CONSTRUCTION VERIFICATION PROGRAM 10/17/83 (cor.tinued) ,

Open Confirmed Resolved Finding Findi Topic Comments OCR No. Resp. LTR Potential Open item Item item item / Repor t eso ution Cservation Report 1.2-1 Acc. Anal. Consid.

024 RPS 3/1/83 3/4/83 3/4/83 1.2-1 Acc. Anal. Consid.

025 RPS 3/1/83 3/4/83 f.8-l Overpress. Prof.

023 RPS 3/l/83 3/4/83 3/4/83 1.91 Comp. Func. Req.

027 FAD 3/l/83 3/4/83 11.9 -1 Env.Eng.

4/14/83 1.9-1 Comp. Fune. Req.

028 FAD 3/2/83 3/4/83 LB 3/4/83 3/4/83 1.18-1 Instrumentation 029 2/22/83 1.19-1 Control System 3/4/83 1.19-1 Control System 030 LB 1/19/83 3/4/83 1.3-Ic Pipe Supports C-31, Rev. I, 7/l2/83 0 31 CS 2 /11/ 8 3 3/4/83 3/4/83 8/30/83 7/12/83 1.3 lc Pipe Supports C-32, Rev. I,7/12/83 032 CS 2 /11/ 8 3 3/4/83 3/4/83 7/12/83 7/12/83 1.3-Ic Pipe Supports C-33, Rev. I, 7/12/83 033 CS 2 /11/ 8 3 3/4/83 3/4/83 7/12/83 7/12/83 1.3-Ic Pipe Supports C-34, Rev. I, 7/12/83 034 CS 2 /11/ 8 3 3/4/83 3/4/83 7/12/83 7/12/83 1.3-Ic Pipe Supports C-35, Rev. 2, 7/12/83 03S CS 2 /11/ 8 3 3/4/83 3/4/83 7/12/83 s

9 a

9

OCR, FIPOING REPORT, Ato FilOING RESOLUTION REPORT TRACKING SYSTEM MIDLAto IPOEPEIOENT DESIGN AIO CONSTRUCTION VERIFICATION PROGRAM .

10/17/83 (continued) ,

Confirmed Resolved Finding Finding Topic Comments OCR No. Resp. LTR Potential Open Open item item item item / Report Resos tion Tservation Eport i

11.2 -1 Pressure Boundary C-36, Rev. 2, 7/12/83 1 036 CS 2 /11/ 8 3 3/4/83 3/4/83 7/12/83 8/30/83 111.1- 1 Seismic Design / Input 037 CS 1/20/83 3/4/83 3/4/83 to Equipment 1.15-! Power Supplies l 038 LB 3/l/83 3/4/83 3/4/83 4/14/83 8/30/83 II.10-1 Env. Eq. Oval.

03P LB 3/30/83 4/14/83 9/30/83 1.16-I Elec. Characteristics 040 LB 3/8/83 9/30/83 1.15-1 Power Supplies 041 LB 3/25/83 4/14/83 4/14/83 9/30/83 f.IO-l Env.Eq. Oval.

042 LB 3/31/83 10/6/83 1.10-1 System Hydraulic Design 043 FAD 3/15/83 4/14/83

11. 1 0 - 1 Env. Eq. Oval. Resolved as 044 FAD 3/15/83 4/14/83 10/6/83 Observatlon*

II.I-IC Electrical Equipment / C-45, Rev. I, 7/12/83 045 DBT 3/17/83 4/14/83 5/25/83 8/8/83 Storage & Maintenance 8/8/83 1.1-1C Mechanical Equipment /

C43 DDT 3/17/83 4/14/83 5/25/83

- Storage & Maintenance 1.1-lC Mechanical Equipment / C-47, Rev. I, 047 DBT 7/7/83 7/26/93 8/8/83 8/30/83 Storage & Maintenance 8/30/83

OCR, FitOING REPORT, APO FIPOING RESOLUTION REPORT TRACKING SYSTEM MIDLAto IPOEPEPOENT DESIGN APO CONSTRUCTION VERIFICATION PROGRAM 10/17/83 (continued) ,

OCR No. Resp. LTR Potential Open Confirmed Resolved gindin F Findin Topic Comments Open item item item item / Hepor t eso ution Observatjon Report 048 FAD 7/29/83 7/29/83 8/8/83 11.10-1 Environmental Equipment Ouctification 049 RC 8/28/83 8/29/83 8/29/83 II.4-Ic Cable 050 RC 8/28/83 8/29/83 8/29/83 II.4-Ic Cable OSI JAM 8/I2/83 8/30/83 8/30/83 111. 1 - 1 Seismic Design / Input to Equipment 052 DBT 9/30/83 9/30/83 9/30/83 All ICV Topics for AFW Supplier Doc

  • 053 FEP 9/27/83 9/29/83 9/29/83 AllICV Topics for AFW Const./ installation Documentation
  • 054 FEP 9/27/83 9/29/83 9/29/83 All ICV Topics for AFW Const./ Installation

- POCis* (

055 DBT 9/19/83 9/29/83 All ICV Topics Const./ installation Documentation -

WPs & PORs*

056 DBT 9/26/83 9/29/83 All ICV Topics for AFW & SEP Supplier / Doc. -

Materials

  • 057 DW 9/29/83 9/30/83 9/30/83 1.34-3 Pressurization Resolved as

, Observation

  • 4

W OCR, FitOING REPORT, AIO FilOING RESOLUTION REPORT TRACKING SYSTEM MIDLAFO IPOEPEPOENT DESIGN Ato CONSTRUCTION VERIFICATION PROGRAM ,

10/17/83 (continued)

OCR No. Resp. LTR Potentiol Open Confirmed Resolved Finding Findi Topic Comments Open item item item item / Report eso ution Observation Repor1 Cooling / Heating Requirements

  • 058 DW 10/6/83 10/6/83 1.12-3 I.3-1 Single Failure Resolved as 059 RPS 8/lI/83 9/30/83 Observation *
l.23-1 Foilure Modes & Effects System Operating Limits
  • 060 DW 9/29/83 9/30/83 1.1-3 061 DW 9/29/83 9/30/83 1.18-3 Instrumentation Resolved as Observation
  • Component Functiorel
  • 062 FAD 9/30/83 9/30/83 1.91 Requirements FAD 10/6/83 1.10-1 System Hydraulic Design Resolved as 063 10/5/83 Observation
  • 064 FAD 1C/5/83 10/6/83 1.10-1 System Hydraulic Design Resolved as Observation
  • All IDV Topics
  • 065 FAD 10/4/83 10/6/83 System Alignment /Switchover
  • 066 DW 9/29/83 10/6/83 10/6/83 1.5-3 1.7-3 System isolotion/ Interlocks 9/30/83 1.34-3 Pressurization Resolved as 067 DW 9/29/83 9/30/83 Observation *

,r

^

OCR, FibOING REPORT, Ato FitOING RESOLUTION REPORT TRACKING SYSTEM MIDLAbo IPOEPEbOENT DESIGN Ato CONSTRUCTION VERIFICATION PROGRAM .

10/17/83 (continued) ,

Resp. LTR Potential Open Confirmed Resolved Finding Findi Topic Comments OCR No.

Open item item item item / Repor t eso ution Cservation Report 068 DS 9/27/83 9/30/83 9/30/83 II.4-1 EQ/ Seismic 069 DS 9/27/83 9/30/83 11. 4 - 1 EQ/ Seismic 070 DS 9/27/83 9/30/83 1.4-1 EO/ Seismic ,

071 JM 9/27/83 9/30/83 Ill.l-1 Seismic Design /

Input io Equipment Component Functional

  • 072 FAD 9/30/83 10/6/83 1.9-1 Requirements

!!.2-1 Seismic Design - Pressure Boundary Cooling / Heating Requirements

  • 073 DW 9/29/83 10/6/83 10/6/83 1.I2-3 System Operating Limits
  • 074 DW 9/29/83 10/6/83 10/6/83 1.1-3 l.2-3 Accident Analysis Considerations 1.15-3 Power Supplies System Operating Limits
  • 075 DW 9/29/83 10/6/83 10/6/83 f.1-3 1

1.2-3 Accident Analysis Considerations Cooling / Heating Requirements

  • 073 DW 9/29/83 10/6/83 10/6/83 1.12-3 077 DS 9/27/83 10/6/83 10/6/83 il.4-1 EO/ Seismic m

b l

l

OCR, FINDING REPORT, APO FIPOING RESOLUTION REPORT TRACKING SYSTED MIDLAto IPOEPEPOENT DESIGN APO CONSTRUCTION VERIFICATION PROGRAM 10/17/83 (continued) .

OCR No. Resp. LTR Potential Open Confirmed Resolveq Finding Finding Topic Comments Open item item item item / Report Hesolution

, Observation Repor1 078 FAD 9/30/83 10/6/83 1.91 Component Functional Requirements

  • 079 JA 8/29/83 10/6/83 111. 5 - 1 CiviliStructural Design
  • Considerations lif.6-1 Foundations 1

i 1

W i

4 4

l 1

i ATTACHMENT 3 CURRENT PERIOD CONFlRMED AND RESOLVED ITEM REPORTS, FINDING REPORTS, AtO FINDING RESOLUTION REPORTS l

l t

l i

-,,,,--,-g - -, , m --

y-,, , . - , _ _ y -

ng ,__ e,_-, .--_-y , , _ - , ,. - - , , - - . -w y., , ,,--- ,,--, _ , , n , y.,,. . ,,, , g , , y. -- ,--- --,-y,--,+

MIDLAPO IPOEPEPOENT DESIGN APO CONSTRUCTION VERIFICATION FitOING RESOLUTION REPORT

, Fil.E NO. 3201-008 Y NON.5AFETY DOC NO. 3201-008.2 012 CLAS5: 5AFETY REV.NO.

PRINCIPAL-IN. CHARGE I G/12 /81 DATES REPORTED TO: 'PROKCT TEAM /PROKCT MCR. 9/22/83 SRT _1_0/13/83 CPC/DE51CN ORG. '

STRUCTURE (S), SYSTEM 5(5), OR COMPOtENT(5) INVOLVED:

Steam Isolation Valves 2M0-3277A and B F0GG Relays 3x-1, 3x-2, 3x-4, 3x-5 DESCRIPTION OF FIPOING (OR REFERENCE DOC. NO. OF FirOING REPORTh See Doc No. 3201-008-F012 which indicates that on loss of all AC (Station Blackout) the FOGG relays would de-energize, causing valves 2M0-3277A and B to shut. t'ith the valves shut, steam would

< not reach the AFN turbine and AFW flow would be interrupted. This would cause loss of reactor cooldown capability during blackout.

DESCRIPTION OF RESOLUTION:

Bechtel MCAR Report 68, dated August 15, 1983, detailed the corrective actions taken which include:

1. Revise design drawings so as t'o power F0GG relays with Class 1E DC backed 120 VAC power.
2. Bechtel engineering review of all power supplies to Class 1E interlocks for valves and prime movers requiring Class 1E DC backed power.
3. Engineering instructions to include a review of power supplies conforaance to FSAR requirements during design verification.

RESOLUTION BASED UPON FOLLOWING DOCUMENTATION:

Bechtel }K'AR Report #68, dated August 15, 1983.

Reviewer Comment: power supply requirements for the FOGG interlock relays were not detailed on logic Diagram J-501(Q) . Had such requirements been documented on the logic Diagram, this oversight might not have occurred.

COMMENTS BY $RT OF REQUIREDh HAL _

JB M $

SRUlf REQUIRED)

$KD PROKCT MANAGER PRINCIPAL h-CHARGE FINDING RESOLUTION REPORT ORGIN. (LTR) FOR PROKCT TEAM 9/30/83 10/13/83 10/14/83 9/21/83 DATE DATE DATE DATE

MIDLAto ItOEPEtOENT DESIGN APO CONSTRUCTION VERIFICATION OPEN, COfflRMED AfO RESOLVED (OCR) ITEM REPORT TYPE OF REPORT: OPEN CONFIRMED X O. 320 - SC 015 RESOLVED ITEM REV.NO.

PROJECT TEAM /PROKCT MGR.10/4/83 DATES REPORTED TO: LTR 10/3/83 SRT PRINCIPAL-IN-CHARGE 10/12/83 CPC/DEslGN ORG.

STRUCTURE (s), SYSTEM (s), OR COMPOffNT(S) INVOLVED:

Auxiliary Building, AFW & CR-HVAC Systems & Components DCV PROGRAM AREA OR TASK (IF APPLICABLE):

Topic III.1-1 Seismic Design / Input to Equipment DESCRIPTION OF CONCERN:

The referenced study may not provide a sufficient basis for the implication in the Civil & Structural Design Criteria (C-501Q,P.41.C) that vertical response1.due Theto floor bases flexibility can be neglected. The following specific issues are noted:

for sample selection and justification for equipment qua'ntification for the amplified

2. The methodology for addressing loads do not appear to have been provided. 3. Final calc 55(Q) uses results of calc increased ground spectra is unclear.

SQ-ll3(Q)' which is preliminary. 4. The effects of floor flexibility on block walls and vice versa is not specifically indicated.

SIGNIFICANCE OF CONCERN:

The functionability of certain equipment and piping located on flexible floors may be compromised under a seismic event.

X OR RESOLUTION  :

RECOMMENDATION

1. Review sampling criteria utilized in referenced study (with Bechtel).
2. Selectively review SQRT packages for equipment mounted on flexible floors to assess margins available for increased vertical loads (TERA).
3. Review SMA seismic margins evaluation of vertical floor flexibility effects (TERA)
4. Resolve referencing issues noted above (with Bechtel).
5. Review methodology for addreesing increased ground spectra (with Bechtel).
6. Review effects of floor flexibility on block walls (with Bechtel).

COMMENTS BY SRT (IF REQUIRED):

REFERENCES (INCL. REL ATED OCR ITEM REPORT NO.): and appended Vertical Floor Flexibility Study (Aux. Bldg.) dated 5/11/82 (IOM 069434) calc packages SQ-119(Q), 55Q&S0-141(Q);C-501,Rev.12 SIGNATURE (5):f D JAh} HAL $ JBQ,p" JA SRT (IF REQUIRED)

PROJECT MANAGER PRidCIPAL-OCR ITEM REPORT LTRS { IN-CHARGE FOR PROJECT TEAM ORIGINATOR 10/11/83 10/13/83 10/3/83 10/4/83 DATE DATE DATE DATE DATE l

MIDLAPO NOEPEtOENT DESIGN APO CONSTRUCTION VERIFICATION OPEN, COfflRMED APO RESOLVED (OCR) ITEM REPORT  ;

TM REPORT: MN W IRMED NO -008 -R-017 RESOLVED X REM REv.NO.

l PRO. LECT TEAM /PROKCT M~,,R.10/4/83 DATE5 REPORTED TO: LTR 9/30/83 SRT .

PRINCPAL.IN. CHARGE 10/12/63 CPC/ DESIGN ORG.

STRUCTURE (5). SYSTEM (5). OR COMPOPENT(5) NVOLVED: l AFW Pumps DCV PROGRAM AREA OR TASK (F APPLICABLE):

Component Functional Requirements (I.9-1) System Hydraulic Design (I.10-1) i System Heat Removal Capability (I.ll-1) (Criteria & Commitments / Review of Calcs) l DESCRIPTION OF CONCERN:

There are inconsistencies in the minimum required AFW flow. B&W document BAW 1512, Rev.1 (Ref.1), lists values of 500 gpm and 720 gpm. The B&W B0P Criteria Document (Ref. 2) requires 850 gpm and a B&W calculation (Ref. 3) is consistent with this  ;

value, although (as reported in other OCRs) this calculation may not be consistent  ;

with appropriate design parameters. The 850 gpm figure may not provide enough water to remove the heat being generated at the time specified in the B&W Criteria Document (i.e., 30 sec. after reactor trip).

I SIGNIFICANCE OF CONCERN:

This would result in a temperature increase in the primary system until the decay heat rate falls to the point where 850 gpm is adequate.

l i

~

RECOMMENDATION OR RESOLUTION X  :

Reference (4) clarifies the project position that 850 gpm is the flow which the AFW ,

system is required to supply. The adequacy of this value and the correctness of input parameters for calculating this figure will be evaluated in the review of responses to other 0CRs.

l COMMENTS BY 5RT (F REQUIRED):

)

REFERENCE 5 (INCL. RELATED OCR ITEM REPORT NDJs (1) Conceptual Design Study for Auxiliary Fee &ater System Feed Rate Control for B&W 177-Fuel Assembly Plant, BAW 1612, Rev.1.

'"" " ~

b k N 'Ek0 $ N. D i Nb8 b 1 kN NAnb bn 8b8b

rA.,% HAL J "LTRI PROKCT MANAGER prs 4CPAL- SRT (IF REQUIRED)

OCR ITM RE PORf /

ORIGNAT 3R I FOR PROKCT TEAM N CHARGE o/in/n1 o/in/n3 10/5/83 10/13/83 DATE DATE DATE

~DATE DATE l

l

. . MIDLAND INDEPENDENT DESIGN AND CONSTRUCTION VERIFICATION OPEN, CONFIRMED AND RESOLVED (OCR) ITEM REPORT TYPE OF REPORT: OPEN E ' "

CONFIRMED DO NO 040 RESOLVED ITEM REV.NO.

DATES REPORTED TO: LTR 9/28/83 SRT PROJECT TEAM / PROJECT MCR. 9/30/83 PRINCIPAL.lN-CHARGE 10/17/R1 CPC/ DESIGN ORC.

STRUCTURE (5), SYSTEM (S), OR COMPONENT (S) INVOLVED:

aft l Cable 2AB5526A IDCV PROGRAM AREA OR TASK (IF APPLICABLE):

AFil Electrical Characteristics 1.16-1 DESCRIPTION OF CONCERN: A check of the maximun cable length for cable 2AB5526A (power to valve 2\10-3970A) using the procedure of QPE-8 Rev. 2 resulted in a maximun length (408 ft) that is less than the stated actual installed length (435 ft) shown op the Circuit Schedule dated September 1983. The cable 2AB5526A appears to be undersized.

The calculation of maximum cable length was performed using 5.8 amps (Ref.1) for max.

current in the 3/C #14 AhU cable. Several other cable lengths were checked and found -

to be satisfactory.

SIGNIFICANCE OF CONCERN:

Cable may be inproperly sized resulting in overheating and degraded performance over life. The Bechtelcheck of cable lengths in the circuit schedule did not identify the undersized cable. There may be other safety rela.ted cables which are undersized.

G RECOMMENDATION X OR RESOLUTION  :

Confirm and process per PQAP. Solicit input from Bechtel regarding the specific parameters for the maximum cable length calculation for cable 2AB5526A.

l COMMENTS BY SRT (IF REQUIRED):

l l

REFERENCES (INCL. RELATED OCR ITEM REPORT NO.)
1) Dwg. E-18 (Q) Sh.9, Rev. 14 l 2) Dwg E-37, Circuit Schedule Rev. 67
, 3) 600V Cable Ampacity, Sizing..
QPE-8, Rev.2 SIGNATURE (S):

l I

fYo OCR ITEM REPORT b.bol4 -

LTR h 0ah SRT (IF REGUIRED)

PROJECT MANAGER FR!NCIPAL.

ORICINATOR FOR PROJECT TEAM IN-CHARGE V-$lf-F3 f.28-63 9 {3c lD /s//3/9 )

DATE DATE DATE DATE DATE

MIDLAFO INDEPEPOENT DESIGN AND CONSTRUCTION VERIFICATION OPEN, CONFIRMED Abo RESOLVED (OCR) ITEM REPORT m w NT: N N RMED C NO. 20: s.R 041 RESOLVED X ITEM O REV.NO.

DATES REPORTED TO: LTR 9/21/83 SRT PROECT TEAM /PROECT MCR. 9/30/83 PRINCIPAL-N CHARCE 10/12/83 CPC/DESlCN ORC.

STRUCTURE (S), SYSTEM (S), OR COMPOPENT(S) NVOLVED: '

Valve 2M0-3968B Cond. Stor. Suction Isolation Valve 2M0-3226 ,AFN Turb. Stm Supp.. Block Valve IDCV PROGRAM AREA OR TASK OF APPLICABLlD AFU Power supplies Topic 1.15-1 DESCRIPTION OF CONCERN: Valves 2M0-3968B and 210-3226 are AC powered and would not be operable during station blackout, nor would their position be indicated to the operator.

Concern 1) is that during nomal plant operation, operator could close either valve disabling AFW systen for station blackout condition. Concern 2) is that valvb position indication would not be available to the operator during station blackout.

SIGNIFICANCE OF CONCERN If either of mentioned valves is closed during blackout, the operator would be required to diagnose this condition from indications other than valve position and then it would require a period of time to napually open either or both valves.

RECOMMENDATION OR RESOLUTION _ X  :

In the consideration of the station blackout event, it is not a requirement to take a single failure in addition to the event.

The valves 2M0-3968B and 2M0-3226 are both nomally open as shown on P5ID's M-439 SH 3B and M-432 SH 1A. For the valves to be closed during plant operation would reouire an op,erator error which is a failure that need not be considered for the blackout event. In other words, the possibility that valves 2M0-3968B and 2M0-3226 would be closed is a concern that is outside the scope of the blackout event.

COMMENTS BY SRT (IF REQUIRED):

See OCR 3201-008-0-041 REFERENCES (INCL. RELATED OCR ITEM REPORT NO.):

b M SRT (IF REQUIRED)

OCR ITEM REPORT LTR PROJGCT MANAGER 4RINCIPAL-ORIGINATOR FOR PROECT TEAM N-CHARGE 9/21/83 f/fg/63 () /30/t3 /,//.2 /p>

DATE 'DATE DATE DATE DATE l 7  ;.. _ _ _ _ _

. MIDLAbO INDEPEM)ENT DESIGN AND CONSTRUCTION VERIFICATION OPEN, CONFIRMED'AND RESOLVED (OCR) ITEM REPORT TYPE OF REPORT: OPEN CONFIRMED DO NO. OI-008.R _ 04 2 RESOLVED X ITEM REV.NO.

DATES RCPORTED TO: LTR 9/28/83 SRT PROJECT TEAM / PROJECT MGR. 9/30/83 PRINCIPAL-IN-CHARCE 10/12/83 CPC/ DESIGN ORC.

STRUCTURE (S), SYSTEM (S), OR COMPONENT (S) INVOLVED:

Electrical Penet. ration Assemblies (E-20)

IDCV PROGRAM AREA OR TASK (IF APPLICABLE):

Enviror. mental / Equipment Qualification Topic II.10-1 DESCRIPTION OF CONCEPN:

'Ihe qualification report does not specifically show why the organic materials list used in the aging analysis does not coincide with the erganic materials 1,ist as supplied by the manufacturer. Sufficient drawings or data are not supplied to justify the differences.

SIGNIFICANCE OF CONCERN:

The organic materials aging analysis serves as the basis for qualified life.

The penetration assembly may be inadequately qualified or may be qualified for.a life different from that stated in the report E-20.

RECOMMENDATION OR RESOLUTION X  :

The reference 7 (to the report) manufacturer's list of organic materials was found, with Bechtel assistance, to coincide with the generic list of organic materials on page EQ 2.1-11. Two of the materials in reference 7 were eliminated from the penetration by a change to Conax penetration modules. An additional material was eliminated as not being required for the safety related function. All other nanufact-l j urer materials were properly traced and identified.

l COMMENTS BY SRT (IF REQUIRED):

{

REFERENCES (INCL. RELATED OCR ITEM REPORT NO.):

l Equipment Qualification Report E-20 -

i l SIGNATURE (5): s l 0%N [.hvN & M SRT (tF REQUIRED)

OCR ITEM REPORT LTR PROJECT MANAGER @RINCIPAL-ORIGINATOR FOR PROJECT TEAM IN-CHARGE TDB 93 T-28-A3 1 k n Jo/13lV3 DATE OATE DATE DATE ' DATE

\

t

' s MIDLAto If0EPEf0ENT DESIGN Af0 CONSTRUCTION VERIFICATION OPEN, COfflRMED Abo RESOLVED (OCR) ITEM REPORT FILE NO. 3201-008 COtFIRMED X TYPE OF REPORT: OPEN DOC NO. 3201008 C 043 RESOLVED ITEM REV.NO.

PROF.CT TEAM /PROECT MGR. 9/30/83 DATES REPORTED TO: LTR 9/30/83SRT '

PRINCIPAL IN-CHARGE I 0/ I 2 / 63 CPC/ DESIGN ORG.

STRUCTURE (S), SYSTEM (S), OR COMPOtENT(S) ItWOLVED:

AFW - Piping and Valves DCV PROGRAM AREA OR TASK (IF APPLICABLE):

System Hydraulle Design (1.10-1)

Seismic Design - Pressure Boundary (11.2-1)

The resolution of OCR #3201-008-R-010 (Ref. 1) regarding the DESCRIPTION OF CONCERN:

appropriate classification of condensate storage tank suction piping (10"-2HBD-605) identified the fact that the piping was seismically quallfled as a special category 1.e. seismic, non-Q-listed. The piping in question is essential to the AFW function.

Accordingly, per FSAR Table 3 2-1, this piping should be seismically quallfled and designed to ASME Section Ill. Reference 2 states the pipir.g is Class D (designed to B.31.1). The FSAR states in Appendix 3B " Quality assurance requirements are not applied to quality Group D cu.iponents".

SIGNIFICANG OF CONCERN:

If appropriate The case in question appsars to be an exception to FSAR Table 3 2-1.

controls to address such exceptions are not in place, the piping will not conform to stated criteria for essential components. This would constitute a failure to meet FSAR design commitments for the AFW system.

OR RESOLUTION  :

RECOMMENDATION X Process as a confirmed item in accordance with the PQAP.

COMMENTS BY SRT (IF REQUIRED):  !

Attachment 2, page 6 (3201-008-C-010)

(1) TERA Monthly Report #2, July 15, 1983, (2) Piping Class Sheets, 7220-M-481(Q), Rev. 22 f;

REFERENCES (INCL RELATED OCR ITEM REPORT NO.):

i SIGNATURE (5):{ k fil}L JB FAD

  1. FAD [t HAL t T'h t

LTR IN PROECT MANAGER PRINdlPAL- SRT (IF REQUIRED) j OCR ITEM REPORT FOR PROJECT TEAM IN-CHARGE ORIGINATOR 10/13/83 9/30/83 10/6/83 9/30/83 DATE DATE DATE DATE DATC

MIDLAto itOEPEf0ENT DESIGN Af0 CONSTRUCTION VERIFICATION OPEN, COff lRMED Ato RESOLVED (OCR) ITEM REPORT COtflRMED gg TYPE OF REPORT: OPEN _ ,

RESOLVED X ITEM REV.NO.

0bservation X SRT PROICT TEAM /PROKCT MGR.10/5/83 DATES REPORTED TO: LTR 9/10/83 _

  • PRINC! PAL.IN-CHARGE , i n /1 ? /R1 CPC/ DESIGN ORG.

STRUCTURE (5), SYSTEM (S), OR COMPOtENT(S) INVOLVED:

AFW Level Control Valve Position Switches DCV PROGRAM AREA OR TASK (IF APPLICABLE):

Equipment qualification (11.10-1)

DESCRIPTION OF CONCERNr The level control valves (2LV3975A1, A2, etc.) are listed in the EQ report as being required for LOCA, MSLB, and HELB cases and as being qualified for the harsh environ-ment (program J255A) . The acsociated position switches No (2ZS 3975 Al, A2isetc.)

justification are presented listed as required for LOCA and MSLB but not for HELB.The J255A program appears to have for not requiring the switches for the HELB case.

correctly included these switches.

SIGNIFICANCE OF CONCERN:

If this is not an isolated case, the potential in exists whichfor required they switches not must function.

being properly qualified for the environment OR RESOLUTION X RECOMMENDATION Process as an Observation in accordance with PI-3201-005 I

COMMENTS BY SRT (IF REQUIRED):

(

REFERENCES (INCL. RELATED OCR ITEM REPORT NO.):

(1) Equipment Qualification Report, Table 1-2 (2) J255A Equipment Qualification Package d

$1GNATURE(S)

FAD ftG6 FAD . ,k HAL}bb J@

PRihCIPAL- SRT (IF REQUIRED)

PROICT MANAGER OCR ITEM REPORT'9LTR FOR PROKCT TEAM IN-CHARGE ORIGINATOR 10/6/83 10/13/83 9/30/83 9/30/83 DATE DATE DATE DATE DATE

MIDLAto itOEPEtOENT DESIGN APO CONSTRUCTION VERIFICATION OPEN, COWIRMED Ato RESOLVED (OCR) ITEld REPORT X C 052 TYPE OF REPORT: OPEN CONFIRMED O. 32 -

RESOLVED ITEM REV. NO. O PRO.ECT TEAM /PROKCT MGR. 9/30/83 DATES REPORTED TO: LTR 9/30/83 SRT PRINCIPAL-IN-CHARGE 10/12/83 CPC/ DESIGN ORG.

STRUCTURE (5), SYSTEM (5), OR COMPOPENT(5) INVOLVED:

Various vendor supplied components in the AFW system.

DCV PROGRAM AREA OR TASK (lF APPLICABLE):

Supplier Documentation Review: Completeness of vendor submittals DESCRIPTlON OF CONCERN:

The following documentation was not available/not recorded as being received from the vendor although specified as a requirement.

- Pumps 2P005A & 2P005B: ASME Design Specs for Sect III, Class 3 appurtenances.

- Motor for pump 2P005A: Certification of Paint Finish

- Turbine 2G005B: 1) Verfication of Electrical Panel Performance Tests

2) Certification that driver is capable of fully automatic start
3) Certification of Paint Finish (See attached sheet)

SIGNIFICANCE OF CONCERN:

The significance of this concern is directly dependent upon whether the documentation has simply been misplaced or never created. Such a determination remains to be made.

The variable nature of the noted inconsistencies appears to eliminate any detectable trend relat1ve to a type or category of document typically not supplied by vendors.

The number of inconsistencies, based upon the sample size, indicates a potential defect in the process used to verify the completeness of vendor submittals when gauged against specification and purchase order requirements.

~

X OR RESOLUTION  :

RECOMMENDATION

- Determine process used to verify the completeness of vendor documentation submittals, focusing upon documentation not included in the Quality Assurance data packages.

- Determine whether adequate mechanisms exist within the CCP to address the noted concerns and selectively evaluate.

- Reconcile noted concerns with designated Bechtel personnel, focusing uoon code and qualification-related concerns.

- Assess the significance of specific concerns on a case basis.

COMMENTS BY SRT (IF RECUlRED):

REFERENCES (INCL. RELATED OCR ITEM REPORT NO.):

As noted above under Statement of Concern D DB HAL [L M SRT (IF REQUIRED)

LTR PROXCT MANAGER PRINCIP'AL-OCR ITEM REPORT IN-CHARGE ORIGINATOR FOR PROJECT TEAM 9/30/83 9/30/83 10/13/83 9/30/83 DATE DATE DATE DATE DATE J

DESCRIPTION OF CONCERN

- Value 2LV-3975 AIV: 1) Acoustic Data Report

2) Certification of Paint Finish a 3) Statement of Compliance w/QA Requirements.

- Value 2M0-3965AV: Controlled copy of Subvendor QA Manual

- Value 25V-3969A: 1) Instructions for site storage

2) Post-weld heat treatment verification documentation
3) Certification of Paint Finish
4) Acoustic Data Report
5) Weld rod control procedures

- Panel 2C-ll4: 5 color 8 x 10 prints of each view

- Switchgear 2A-05: Certification of Paint Finish

- Transmitter 2FT-3969A: 1) Completed Bechtel Data Sheet

2) QA data package incorrectly identifios transmitter 2FT-3969A as 2PT-3969A
3) Certification of Paint Finish

- Transmitter 2LT-3975AA2: 1) RFI Susceptibility Documentation

2) Certification of Paint Finish

- Air Cooler 2VM-54A: 1) Heat Treatment Verification Report

2) Repair Procedures

- - . _ , . - - _ , , _m_-_y _._-,y._. ,.,,, _. , . _. , _ c. .._-,-_ -, , , ._,,_. _.

MiDLAto itOEPEFOENT DESIGN MO CONSTRUCTION VERIFICATION OPEN, COtflRMED MO RESOLVED (OCR) ITEM REPORT TYPE OF REPORT: OPEN CONFIRMED X [{ 3[,,*h 3 oc - 053 RESOLVED (TEM REV. NO. O SRT PROECT TEAM /PROICT MGR. 9/29/83 DATES RIPORTED TO: LTR 9/28/83 PRINCIPAL-IN. CHARGE IU/ I 2/63_ CPC/ DESIGN ORG.

STRUCTURE (S), SYSTEM (5), OR COMPOtENT(S) INVOLVED:

AFW System: Various components and commodities as enumerated in the Description of Concern DCV PROGRAM AREA OR TASK (IF APPLICABLE):

Vefirication of Construction / Installation Documentation DESCRIPTION OF CONCERN:

TERA acquired and assembled documentation necessary to verify the completeness and adequacy of the installation and installation inspection for selected components and commodities within the AFW system. As a result of our progress to date in evaluating available documentation, the following observations are noted and recorded.

(See attached sheet)

SIGNIFICANCE OF CONCERN:

- Lack of complete and consistent dncumentation necessary to verify the quality of installed components and commodities promotes que:;tions as to 1) the quality of the installation and 2) the effectiveness of the processes which are used to verify the quality of the installation.

- Phase I of the CCP is designed to address items similar to those noted in the Description of Concern. These items are, therefore, indicative of the types of situations to be encountered as the CCP progresses through Phase I activities.

X OR RESOLUTION  :

RECOMMENDATION

- Monitor and observe the CCP's approach in reconciling and resolving the inconsis-tencies noted in this OCR. i

- Verify resolution of specific items noted and expand sample at later stages of the CCP.

- In light of the fact that Phase I has as yet to commence, it is recommended that By this OCR be forwarded as a confirmed item in accordance with the IDCVP PQAP.

proceeding in such a manner, CCP personnel may become more sensitized to the types g(jgcgnsjstgngigthegsgl h g nji g te ds j e { p g es y .

COMMENTS BY SRT (IF REQUIRED):

REFERENCES (INCL. RELATED OCR ITEM REPORT NO.):

Applicable PQCI's and related documentation, e.

SIGNATURE (p b FEP M D tN HAL b: JBM SRT (IF REQUIRED)

LTR PROECT MANAGER PRINCIPAL-OCR ITEM REPORT IN-CHARGE ORIGINATOR FOR PROICT TEAM 9/28/83 9/29/83 10/13/83 9/27/83 DATE DATE DATE DATE DATE

DESCRIPTION OF CONCERN Item Description of Concern

1. Line 10" - 2HBC-537, No welding records on file.

. Hangers H-1 & H-9

2. Line 10" - 2HBC - 25, No welding records on file.

Hangers H-3

3. Line 4" - 2EBC-1, No installation records on file.

Hangers H106, H500, H501

4. Conduit 2AJD006 QClR Log Nunter 35411 assigned but no records on file.
5. . Line 6" - 2 EBB-6, No weld records on file for either shop Field weld @ DP-250 or field weldments.
6. Line 4" - 2EBC-1, Installation Inspection Report not on file.

Field weld FW-12

7. Line 6" - 2 EBB-6, QA records cannot be correlated to the Hanger H-10 specific hanger.

(In evaluating hanger H-10, no QA records were located for hanger H-9 on the same line.)

8. Line 4" - 2EBC-1, NDE report for defect removal prior to weld Shop weld B, Spool S-634 repair was not on file; IR shows "PT" done but 7-MR-06-98X NDE report number is not listed.
9. Pumps, and associated Vendor instruction manual not listed on the drivers, 2P005A & 2P005B IR as a referenced document nor evidence of the manual being used during installation.
10. Line 6" - 2 EBB-6, Radiography performed to ASME classed as Field weld FN-16 " unofficial . " No final NDE report on file.
11. Line 6" - EEBB-13, Welder ID reccrded on NDE report but not Hanger H-11 recorded on IR.

MIDLAND ltOEPEPOENT DESIGN APO CONSTRUCTION VERIFICATION OPEN, COPFIRMED A>O RESOLVED (OCR) ITEM REPORT NO TYPE OF REPORT: OPEN COtFIRMED X O. 3 40M RESOLVED ITEM REV.NO. O PROECT TEAM /PROECT MCR. 9/29/83 DATES REPORTED TO: LTR _9/28/83_ SRT CPC/DEslGN ORG.

PRINCIPAL.IN-CHARCEl O/ I 2/83 STRUCTURE (5), SYSTEM (s), OR COMPOtENT(S) INVOLVED:

Projbet Quality Control Instructions (PQCI's) to be used/used in the inspection of selected AFW system components.

DCV PROGRAM AREA OR TASK (IF APPLICABLE):

Verification of Construction / Installation Documentation.

DESCRIPTION OF CONCERN:

The attached listing of PQCI's were reviewed and evaluated to contain the deficiencies / inconsistencies as noted.

SIGNIFICANCE OF CONCERN:

Incorrect, conflicting, ' outdated or redundant instructions contained within a PQCI may affect the consistent application of the instruction to all inspections -

i.e., inspections already performed in addition to the re-inspections planned as an integral part of the CCP Phase I activities.

X OR RESOLUTION  :

RECOMMENDATION

- Develop a detailed understanding and observe activities to be undertaken by the CCP in determining the technical adequacy of previous inspections when compared l

l to current inspection requirements.

l

- Address and resolve the inconsistencies noted in this 0CR.

- Brief Stone & Webster on related details to help them focus CIO activities.

COMMENTS BY SRT (IF REQUIRED):

I J

REFERENCES (INCL. RELATED OCR ITEM REPORT NO.):

As noted above in Description of Concern.

rx h6 DBI HAL PROXCT MANAGER h}b JW PRlWCIPAL- ~5RT (IF REQUIRED)

OCR ITEM REPORT LTR FOR PROECT TEAM IN. CHARGE ORIGINATOR 9/28/83 9/29/83 10/13/83 9/27/83 DATE DATE DATE DATE GATE

. ~ _ . _ _ _ _ _ . - _ , . _ . _ _ _ __ _ _ _ _ _ _ _ _ _ _ _ _ . _ _ _ _ _ _ _ _ _ , _ . _ _ . . _ . . . . _. __

DESCRIPTION OF CONCERN

1. PQCI MW-1.00, Rev 2., 2/21/83: Welding and NDE of Mechanical, Equipment Inspection Activity 2.2 for installation does not reference the inspector to a " Temporary Attachment Record" even though Activity 3.1 and " Scope,"

Para. "A," do reference use of the " Temporary Attachment Record." Though

. minor in nature, this inconsistency is conducive to not having available, at the time of inspection, documentation that a temporary attachment was made and, therefore, the supporting data (i.e., welder, material, location, etc.) may never be made available. (Note that this procedure was rendered

" INACTIVE" on 9/14/83.)

2. PQCI M-4.00, Rev 2, 2/21/83: Completed Installation of Mechanical Equipment Activity 3.2 note refers to Special Instruction #8 but Special Instruction
  1. 8 is not in the PQCI.
3. PQCI PW-1.00, Rev 7, 6/6/83: Fabrication, Welding, Heat Treating, and NDE of ASME Sect III Piping
a. Activity 3.lK does not require dncumentation of the removal of attachment welds as stipulated under " Scope B"
b. Attachment 2.8: One part of this " Composite" disagrees with Attachment 2.5A regarding the requirement for scribe lines on socket welds used to verify insertion and pull-back criteria. Attachment 2.5A states, "5)

No external scribes will be required," where as General Welding Standard GWS-SN, Rev 3, Amendment 3, stipulates the requirement for scribe lines and the criteria.

c. Attachment 2.8: Two revisions of the same welding standard are provided.

GWS-SN is represented from both Revision 3 and Revision 4.

d. An unidentified sheet containing a Paragraph 5.0, Preheat and Interpass Temperature, is not labelled for identity or source and is in conflict with two other unidentified sheets containing the same paragraph number, Paragraph 5.0.

MIDUDO ltOEPEPOENT DESKW APO CONSTRUCTION VERIFICATION OPEN, COfflRMED Ato RESOLVED (OCR) ITEM REPORT TYPE OF REPORT: OPEN CONFIRMED NO. 320t.008 -B-057 RESOLVED X ITEM REV.NO. O Observatlon DATFS REPORTfD TO: LTR 9/29/83 $RT PROECT T2AM/PROKCT MCR. 9/29/83 PRINCIPAL.IN-CHARGE 10 / I ? /83 CPC/ DESIGN ORG.

STRUCTURJ(5), SYSTEM (5), OR COMPOffNT(5) INVOLVED:

Control, Room HVAC DCV PROGRAM AREA OR TASK (IF APPLICABLE):

Check of calculations for Topic I.34-3, Pressurization DESCRIPTION OF CONCERN:

Errors were made in portions of the calculation as follows:

1. The calculation is numbered F-4321-07 instead of FM-4321-07, which is the correct identification.
2. On pages 4 and 5, the coefficient A is taken to be 1.6 x 10-5 intending to be That reference the maximum value in the rgnge of values stated in NAA-SR-10100.

gives a range of 1.6 x 10- to 1.2 x 10-5 SIGNIFICANCE OF CONCERN:

The error was made in a conservative directior. :nd the leakage rate resulting is still insignificant compared to the total; therefore, there is minor consequence in terms of the validity of the calculation.

RECOMMENDATION OR RESOLUTION X  :

There is no need to examine the technical consequences of the error for the reason stated above. Also, the error occurred in a portion of the calculation which has no impact on the conclusions or any other design aspect. This item is resolved by classification as an Observation.

COMMENTS BY SRT (IF REQUIRED):

REFERENCES (INCL. RELATED OCR ITEM REPORT NO.h Calculation FM-4321-07 Rev.0 5IGNATURE(Sh ,

M $A AA$A Y$ M OCit'lTEM REPORT ' /LTR PROECT MANAGER FOR PROKCT TEAM

' PRINCIPAL.

N. CHARGE SRT (IF REQUIRED)

ORIGNATOR 9/zr/33 1/zs hi 1 YIU /e//3/f1

' DATE ' DATE MTR DATE DATE

MIDLAto itOEPEtOENT DESIGN Ato CONSTRUCTION VERIFICATION OPEN, COtflRMED Ato RESOLVED (OCR) ITEM REPORT TYPE OF REPORT: OPEN CONFIRMED O. 32 1 8.B 059 RESOLVED X ITEM REY.NO. O Observation PROECT TEAM / PROJECT MGR. 8/l2/83 DATES REPORTED TO: LTR 8/11/83 SRT -

PRINCIPAL.!N-CHARGE 8/12/83 CPC/ DESIGN ORG.

STRUCTURE (s), SYSTEM (5), OR COMPOtENT(S) INVOLVED:

Entire AFW system (mechanical and electrical)

DCV PROGRAM AREA OR TASK (IF APPLICABLE):

Topics I.3-1 (Single Failure) and 1.23-1 (Failure Modes and Effects)

DESCRIPTION OF CONCERN:

Although Bechtel has a Thermal Power Organization (TPO) Standard TP0 2.1.19 for the

" Application of the Single Failure Criterion," there was no clear indication that the standard was being applied by translation of criteria into implementation action statemen ts. There were, however, several letters involving single failure and failure modes and effects, especially related to selection of a pump discharge configuration done by Bechtel . There also was a B&W study of ESFAS single failure.

Independent single failure and failure modes and effects analysis found no design errors beyond that documented in finding 3201 -008-F-012.

SIGNIFICANCE OF CONCERN:

Although it is obvious from the design review that single failure is indeed consi-dered, it is our opinion that such consideration needs to be more than an " inherent" process. It should be a directed process, incorporated both into design instructions and verification procedures for all safety-related systems.

OR RESOLUTION X  :

RECOMMENDATION It is recommended that Bechtel consider formal incorporation of single-failure-proof design requirements into the Design and Verification Procedures / Instructions.

COMMENTS BY SRT (IF REQUIRED):

REFERENCES (INCL. RELATED OCR ITEM REPORT NO.):

Meeting Summary,1/21/83, Dougherty & Snaider (TERA) with Lewis (Bechtel)

Telecon Summary, 8/9/83, Bates (TERA) with Kelly (Bechtel)

[ g SIGNATURE (S):[

R.P.Snaider R.P.Snaider HAL Ih JM PRINtlP L. SRT (IF REQUIRED)

/ LTR OCR ITEM REPOR 66 PROJECT MANAGER FOR PROJECT TEAM IN-CHARCE ORIGINATOR 8/11/83 9/30/83 10/13/83 8/11/83 DATE DATE DATE DATE DATE

MIDLAfC ltOEPEtOENT DESIGN APO CONSTRUCTION VERIFICATION OPEN, COWIRMED AIO RESOLVED (OCR) ITEM REPORT TYPE OF REPORT: OPEN CONFIRMED . 32 -006 -B-061 RESOLVED X REM REV. NO. O Observation DATES REPORTfD TO: LTR 9/29/83 SRT PROECT TEAM /PROECT MOR. 9/30/8L PRINCIPAL.IN-CHARGE 10/12/83 CPC/ DESIGN ORG.

STRUCTURE (5), SYSTEM (5) OR COMPOPENT(5) INVOLVED:

Various, items on P&ID for Control Room HVAC review DCV PROGRAM AREA OR T ASK (IF AFPLICABLE):

J.18-3 Instrumentation - P&ID review DESCRIPTlON OF CONCERN:

Instrument panel numbers on the P&ID have been designated in two slightly different ways. For example, OC020 and OC20 are two designations for the same panel.

SIGNIFICANCE OF CONCERN:

There is a potential for misinterpreting panel designations with these two identifications, particularly if the letterina is small; however, for this specific item the potential is judged to be small.

RECOMMENDATION OR RESOLUTION X  :

For the drawings reviewed, the designation of panels would be difficult to misinterpret. This item is resolved by classification as an Observation.

COMMENTS BY SRT (IF REQUIRED):

REFERENCES (INCL. REL ATED OCR ITEM REPORT NO.):

Drawing M-465 SH2 (Q) Rev. 9 SIGNATURE (5):

42 sk 4A bb '

HAL W dW PRINCIPAL. SRT (IF REQUIRED)

OCMMEM REPORT / LTR PROECT MANAGER FOR PROKCT TEAM N-CHARGE ORIGINATOR f// f/n S/j,/n 9/30/83 10/13/83

~

DATE DATE DATE DATE DATE

MIDLMO ItOEPEPOENT DESIGN APO CONSTRUCTION VERIFICATION OPEN, COfflRMED MO RESOLVED (OCR) ITEM REPORT TYPE OF REPORT: OPEN COPEIRMED NO. 32 l 063 RESOLVED X ITEM REV.NO.

0bservatIon X SRT PROECT TEAM / PROJECT MGR. 10/5/83 '

DATES REPORTED TO: LTR 10/5/83 PRINCIPAL-IN-CHARGE 10/12/83 CPC/ DESIGN _ ORG.

STRUCTURE (S), SYSTEM (S), OR COMPOPENT(S) INVOLVED:

AFW System DCV PROGRAM AREA OR TASK (IF APPLICABLE):

System Hydraulic Design (i.10-1)

DESCRIPTION OF CONCERN:

Sheet 9 ofBoth Calculation FM-4117-21(Q) discusses in conclusion 1 two cases whi are described as " Pump running with AFWAS". Subsection I.A should evaluated.

read " Pump running without AFWAS". This appears to be a minor transcription error.

Page 14 clearly stetes that the calculation was run for the no AFWAS case.

SIGNIFICANCE OF CONCERN: in the conclusion A important case would have been overlooked if the statementis clear that a transcription err were correct as written; however, it which has no significance.

OR RESOLUTION X  :

RECOMMENDATION This item should be considered an observation and processed per PI-3201-005 COMMENTS BY SRT (IF REQUIRED):

REFERENCES (INCL. RELATED OCR ITEM REPORT NO.):

Calculation FM-4117-21 (Q) g, SIGNATURE (!

FAD b k FAD et,k HAL k JM SRT (IF REQUIRED) t'D!) PROJECT MANAGER PRidlPAL-OCR ITEM REPORT ' LTR IN-CHARGE FOR PROJECT TEAM ORIGINATOR 10/13/83 10/5/83 10/6/83 10/5/83 DATE DATE DATE DATE DATE

MIDLAFO ltOEPEtOENT DESIGN APO CONSTRUCTION VERIFICATION OPEN, COtFIRMED APO RESOLVED (OCR) ITEM REPORT TYPE OF REPORT: OPEN COrflRMED f2 8.064 RESOLVED X ITEM REV.NO.

Observation X PROJECT TEAM / PROJECT MGR. 10/5/83 DATES REPORTED TO: LTR _ 10/5/83 SRT PRINCIPAL.IN. CHARGE 10/12/B3 CPC/ DESIGN ORG._

STRUCTURE (S), SYSTEM (D, OR COMPOPENT(S) INVOLVED:

AFW System DCV PROGRAM AREA OR TASK (IF APPLICABLE):

System Hydraulic Design (1.10-1)

DESCRIPTION OF CONCERN: The Sheet 15 of calculation FM-4117-21(Q) refers to data sources 34A, 340, Theand 34C.

correct reference list on page 13A does not contain references 34A, B, and C. listed in the correct references are 35A, B, and C. Furthermore, the drawings are not order. That is to correct the errors the reference list,page 13A,should read:

"35 Hanger isometrics a) H634, sh. 3(Q), (b) H634, sh. 4(Q), (c) H633, sh. 3(Q)"

And the last full sentence on sh. 15 should change references 34a, b, and c to 35 a. b. and c.

SIGNIFICANCE OF CONCERN:

A user would readily find that the drawings and calculations These did not errors appear match to be and trans-that the reference numbers were incorrect.

cription errors.

OR RESOLUTION X  :

RECOMMENDATION This item should be considered an observation and processed per PI-3201-005 COMMENTS BY SRT (IF REQUIRED):

REFERENCES (INCL. RELATED OCR ITEM REPORT NO.):

1) Calculation FM-4117-21(Q)
2) Isometrics H633, sh, 3 and 4, and H634 SIGNATI, 5):

FAD} 8Lk g FAD HAL } h Jg PRINCTPAL- SRT (IF REQUIRED)

OCR ITEM REPORT ' LTR [$T) PROJECT MAtat,ER FOR PROJECT TEAM IN-CHARGE ORIGINATOR 10/13/83 10/5/83 10/6/83 10/5/83 DATE DATE DATE DATE DATE

,~ -_ __

MIDLAFO If0EPEf0ENT DESIGN abo CONSTRUCTION VERIFICATION OPEN, COfflRMED Af0 RESOLVED (OCR) ITEM REPORT F 3 CONFIRMED X TYPE OF REPORT: OPEN D .3 l- 8.C-066 RESOLVED ITEM REV.NO.

DATES REPORTED TO: LTR 9/29/83 SRT PROECT TEAM /PROECT MGR. 10/5/83 PRINCIPAL-IN-CHARGE IO/12/83 CPC/ DESIGN ORG. .

STRUCTURE (5), SYSTEM (5), OR COMPONENT (S) INVOLVED:

HEPA filters in makeup air and recirculating portions of HVAC system and associated air handling units IDCV PROGRAM AREA OR TASK (IF APPLICABLE):

Topics 1.5-3 System Alignment /Switchover and 1 7-3 Sy stem isolation / Interlocks DESCRIFTION OF CONCERN:

Af ter an accident involving an airborne radioactive release, the Control Room can be isolated and pressurized for three hours. The system alignment during '

subsequent phases of the event is not identified, Knowledge of the proper align-ment is needed to correctly analyze control room habitability.

SIGNIFICANCE OF CONCERN:

The dose for personnel in the Control Room will be different for various system alignments depending upon if air is supplied through the system makeup air handling units as opposed to the supply of outside air by infiltration as Control Room pressure drops. The calculated dose should be consistent with intended alignment for the system.

RECOMMENDATION X OR RESOLUTION  :

Process per PQAP.

COMMENTS BY SRT {lF REQUIRED):

REFERENCES (INCL. RELATED OCR ITEM REPORT NO.):

i SIGNATURE (S):

DW }bfe. , DW hb HALj J@

OCR ITEM REPORTP#' LTR itN PROECT MANAGER PRINdPAL-IN-CHARGE SRT (IF REQUIRED)

ORIGINATOR P ** ' FOR PROECT TEAM 9/29/83 10/6/83 10/13/83 9/29/83 DATE DATE DATE DATE DATE

l MIDLAto itOEPEtOENT DESIGN APO CONSTRUCTION VERIFICATION OPEN, COfflRMED Ato RESOLVED (OCR) ITEM REPORT 1 TYPE OF REPORT: OPEN COtFIRMED O. 320 8.B.067 RESOLVED X ITEM REV.NO.

Observation X PROECT TEAM /PROKCT MGR. 9/30/83 l SRT

  • DATES REPORTED TO: LTR 8/19/83 PRINCIPAL.lN-CHARGE 10/ t u03 CPC/ DESIGN ORG.

STRUCTURE (S), SYSTEM (S), OR COMPOMENT(S) INVOLVED:

CR-HVAC pressurization system DCV PROGRAM AREA OR TASK (IF APPLICABLE):

Control Room HVAC Design Verification Review Topic l.34-3, Pressurization DESCRIPTION OF CONCERN:

Two different statements are made within the FSAR regarding the magnitudeSection of pressure differential which is maintained by the pressurization system.

9.4 (pages 9.4-6 and 9.4-7) states the pressure is 1/8" to 1/4" w.g. and Section 6.4 (page 6.4-7) states the pressure is 1/4" w.g.

SIGNIFICANCE OF CONCERN:

The review of system design will be based on a 1/4" w.g. commitment. The statement in Section 9.4 is considered an adequate basis, but less definitive. There is no reason to conclude that 1/8" w.g. is not an adequate positive pressure differential; the only concern is consistency of the stated commitment.

~

X  :

e COMMENDATION OR RESOLUTION 1/4" w.g.

The eview will proceed based on the more limiting commitment, i.e.,

if the design is not adequate for this condition, the basis for selecting the This item is resolved by particular pressure differential will be examined.

classification as an observation.

COMMENTS BY SRT OF REQUIRED):

j REFERENCES ONCL. REL ATED OCR ITEM REPORT NO.h SIGNATURE (S):

DW l b hib DW tw HALk JB M PRINCIPAL. SRT (IF REQUIRED)

OCR ITEWL REPORTN.. LTR M PROXCT MANAGER FOR PROECT TEAM IN-CHARGE ORIGINATOR 9/29/83 9/30/83 10/13/83 9/29/83 DATE DATE i DATE DATE DATE l

MIDLAfo itOEPEtOENT DESIGN APO CONSTRUCTION VERIFICATION OPEN, COtFIRMED Ato RESOLVED (OCR) ITEM REPORT N

.COTIRMED X NO. 3 - B-C-068 TYPE OF REPORT: OPEN __

RESOLVED ITEM REV. NO.

PROECT TEAM /PROXCT MCR, 9/30/83 SRT '

DATES REPORTED TO: LTR 9/27/83 PRINCIPAL-IN-CHARGE 10 / ) 2 / 83 CPC/ DESIGN ORG.

STRUCTURE (5), SYSTEM (5), OR COMPOENT(S) INVOLVED:

AFW Motor Driven Pump - 2P-05-A DCV PROGRAM AREA OR TASK (IF APPLICABLE):

Equipment Qualification (Seismic) 11.4-1 DESCRIPTION OF CONCERN:

Vertical ZPA used in the qualification analysis for the motor is lower (0.089 )

than required in the specifications (0.14g).

SIGNIFICANCE OF CONCERN:

Consistency between The analysis may not conservatively qualify this motor.

similar calculations is not maintained.

X OR RESOLUTION  :

RECOMMENDATION Any supporting cales or qualification data should be reviewed to establish con-servatism of the motor qualification analysis, or the motor should be re-qualified to 0.149 .

COMMENTS BY SRT (IF REQUIRED):

REFERENCES (INCL. RELATED OCR ITEM REPORT NO.):

7220-M14-118 Seismic Analysis - Motors 7220-M14- Specifications 7220-M14-124 Seismic Analysis - Pump SIGNATURE (S):

DS p, r, JM( [

f HAL h M SRT (IF REQUIRED)

) PROXCT MANAGER PRINDIPAL-OCR ITEM REPORT LTRy FOR PROXCT TEAM IN CHARGE ORIGINATOR 9/30/83 10/13/83 9/27/83 9/30/83 DATE DATE DATE DATE DATE l

MIDLMO INDEPEPOENT DESIGN MO CONSTRUCTION VERIFICATION OPEN, COWlRMED MO RESOLVED (OCR) ITEM REPORT X

FILE NO. 3201 008 TYPE OF REPORT: OPEN COtflRMED DOC NO. 320 i.006 -C -073 RESOLVED ITEM REV.NO.

DATES REPORTfD TO- LTR n/29/83 5RT PROKCT TE Av/PROKCT M*R. 9/30/83 PRINCIPAL.lN-CHARGE 10/12 /63 CPC/DE51CN ORG.

STRUCTURE (5), SYSTEM (5) OR COMPOeENT(5) INVOLVED:

Control. Room HVAC - Air Handling Unit Cooling Coils DCV PROCRAM AREA OR T ASK (IF APPLICABLE):

Review Topic I.12-3, Cooling / Heating Requirements DESCRIPTION OF CONCERN:

The calculation is intended to check the cooling coil load. In the assumptions for the calculation, the conditions for a post-LOCA are presumed to exist. No statement is made regarding other accident conditions. The concern is whether other accidents would cause more limiting demands. For example, are adjacent wall temperatures higher during a steam or feedwater line break?

SIGNIFICANCE OF CONCERN:

The cooling coil sizing appears marginal. If there are conditions which increase the load, a higher control room temperature would e.v.ist.

RECOMMENDATION Y OR RE50mVTION  :

l Process per PQAP.

COMMENTS BY SRT (IF REQUIRED):

REFERENCES (INCL. REL ATED OCR ITEM REPORT NO.):

Calc. No. CPM 4321-01(Q), Rev. 2 5IGNATURE(5):

A g/8 d HAL k JM OC41 TEM F@ PORT / LTR PROKCT MANAGER PRINCIPAL. SRT (IF REGUIREO)

ORIGINATOR FOR PROECT TEAM N. CHARGE M f /fy //7, m 10/6/83 10/13/83 DATE DATE DATE DATE DATE

MIDLAto ItOEPEPOENT DESIGN Ato CONSTRUCTION VERIFICATION OPEN, COtflRMED APO RESOLVED (OCR) ITEM REPORT X

TYPE OF REPORT: OPEN COtEIRMED O. 0 008- C -0%

RESOLVED ITEM REV.NO.

DATES REPORTfD TO: LTR_ Q/90 g SRT PROKCT TEAM /PROKCT MOR. 9/30/O

  • PRlNCIPAL IN.CHARCE 20/12 /63 CPC/ DESIGN ORG.

STRUCTURE (5), SYSTEM (5), OR COMPOtENT(5) INVOLVED:

Control Room HVAC System - Applicable to all mechanical and electrical aspects DCV PROGRAM AREA OR TASK (IF APPLICABLE):

Topic Numbers I.1-3, I.2-3, and I.15-3 DESCRIPTION OF CONCERN.

The specific criteria for control room environmental conditions during a station blackout are not identified. The system's functional requirements may depend upon whether a temperature limit exists.

SIGNIFICANCE OF CONCERN:

Both personnel habitability and equipment qualification could be affectc- t the operating limits established during a station blackout.

RECOMMENDATION y OR RESOLUTION  :

Process per PQAP.

COMMENTS BY SRT (IF REQUIRED):

REFERENCES (INCL. REL ATED OCR ITEM REPORT NO.):

$1CNATURE(5):

Ajgj HAL h h Jg MM '/ LTR PROECT MANAGER PRIN6 PAL- SRT (IF REQUIRED)

Oth ITEM REPORT N CMARGE ORIGINATOR FOR PROKCT TEAM 9/pp /sy 10/6/83 10/13/83 g>, Jr ;

DATE DATE DATE DATE DA'TE

MIDLMO itOEPEPOENT DESIGN MO CONSTRUCTION VERIFICATION OPEN, COtflRMED APO RESOLVED (OCR) ITEM REPORT FILE NO. 3?D I-DCE CONFlRMED X TYPE OF REPORT: OPEN DOC NO. 3201-006 -C-075 RESOLVED ITEM REV.NO.

DATE5 REPORTED TO: LTR Q/?Q/M 5RT PROECT TEAM /PROXCT M*R. 9/30/83 PRINclPAL.lN. CHARGE 10/12/D3 CPC/ DESIGN ORG.

STRUCTUREIS), SYSTEM (5). OR COMPONENT (5) INVOLVED:

Control. Room HVAC System DCV PROCRAM AREA OR TASK (IF APPLICABLE):

Review Topics I.1-3 and I.2-3 Criteria Review System Operating Limits and Accident Analysis Considerations DESCRIPTION OF CONCERrc Regulatory Guide 1.78 Item 10 of the Reg. Position requires that a 10 CR1 inleakage be considered even for pressurized control rooms. Appendix 3A states compliance with the intent of Reg. Guide 1.78. It is not clear that the 10 CFM inleakage is considered. A statement of the basi- for assumed inleakage and the justification for that basis should be provided.

SIGNIFICANCE OF CONCERN:

The habitability requirerents for the control room may not be satisfied for continuous release if a 10 CFM inleakage occurred.

RECOMMENDATION Y OR RESOLUTION  :

Process as per PQAP.

COMMENTS BY SRT (IF REQUIRED):

REFERENCES (INCL. REL ATED OCR ITEM REPORT NO.):

SIGNATURE (5):

ss}h/ ,b,fkh HAL _

JW _

SRT (IF REQUIRED)

Odt ITEM REPORT 7 L.TR PROKCT MANAGER PRINCIPAL-DRIGINATOR FOR PROKCT TEAM N. CHARGE r/7,/pr 9/rs/s y 10/6/83 10/13/83 DATE DATE DATE

' DA'TE DATE

O MIDLMO ltOEPEPOENT DESIGN APO CONSTRUCTION VERIFICATION OPEN, COtflRMED APO RESOLVED (OCR) ITEM REPORT TYPE OF REPORT: OPEN COrflRMED X

. f20 8 - C-076 RESOLVED ITEM REV.NO.

DATES REPORTfD TO: LTR 9/29/83 $RT - PROKCT TEAM /PROKCT MCR.9/30/83 PRINCIPAL.lN-CHARGE IO/iz/o3 C'C/ DESIGN ORG.

STRUCTURE (5). SYSTEM (5), OR COMPOtENT(S) INVOLVED:

Control Room HVAC - Air Handling Unit Cooling Coils g>CV PROGRAM AREA OR TASK (IF APPLICABLE):

Review Topic I.12-3 Cooling / Heating Requirements DESCRIPTION OF CONCERN: Certain data are used in the calculation without clear reference to a data source which is controlled. Without such reference, the validity of the data is in question, specifically:

- Makeup flow = 2000 CFM references FSAR 9.4.1.2.3 without identifying calculational backup and the FSAR discusses only normal operation, not LOCA after 3 hours3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br /> isolation Aux Bldg Temp = 104 g no references i

- Makeup Air Temp = 96 gFDB no references 79 FWB SIGNIFICANCE OF CONCERN:

Although the data appears reasonable, it is necessary to trace the data to a controlled source in order to check the basis for the values used. For example, the makeup air conditions appear to be close to a 1% design basis from the ASHRAE Guide. This should be confirmed and the reason for using 1% conditions stated. To complete the assessment of the design, this type of information is required. The adequacy of this data could affect the ability of the system to maintain control room temperatures.

RECOMMENDATION y OR RESOLUTION  :

Process as per PQAP.

COMMENTS BY SRT (IF REQUIRED):

REFERENCES (INCL. REL ATED OCR ITEM REPORT NO.):

l

! Calculation No. CPM 4321-01 (Q), Rev. 2 SIGNATURE (5):

@ JB i

Ag[N pg HAL

/ LTR PROKCT MANAGER PRINCIPAL. SRT (IF REQUIRED)

OCR' ITEM RfPORT N.CMARGE ORICINATOR FOR PROKCT TEAM S/zf/n p // p /f r 10/6/83 10/13/83 DATE DATE DATE DATE DATE

MIDLAPO llOEPEf0ENT DESIGN APO CONSTRUCTION VERIFICATION OPEN, COfflRMED Af0 RESOLVED (OCR) ITEM REPORT N

TYPE OF REPORT: OPEN CONFIRMED X NO. 3 1 C.077 RESOLVED ITEM REV.NO.

DATES REPORTF.D TO: LTR 9/27/83 SRT PROKCT TEAM /PROECT MGR. 10/5/83 PRINCIPAL.IN-CHARGE I O/12 /83 CPC/ DESIGN ORG.

STRUCTURE (5), SYSTEM (S), OR COMPONENT (S) INVOLVED:

AFW Motor Driven Pump - 2P-05-A IDCV PROGRAM AREA OR TASK (IF APPLICABLE):

Equipment Qualification (Seismic) 11.4-1 1

DESCRIPTION OF CONCERN:

1) Section 3 10.4 of the FSAR does not appear to be the latest revision or is incomplete.
2) Information appears to be missing in cross references between Section 3.10 and 3.9 (e.g. Section 3.10.4.1.13 refers to Section 3.9 but Section 3.9.2.2 refers to Section 3.10. Table 3.9-17 has been deleted and refers to Section 3.10.4).

SIGNIFICANCE OF CONCERN:

Information regarding qualification of equipment may be missing or not up to date.

~

RECOMMENDATION X OR RESOLUTION  :

Determine whether TERA has the latest revision of the FSAR. Reconcile the ncied ,

differences.

l I

COMMENTS BY SRT (IF REQUIRED):

REFERENCES (INCL. RELATED OCR ITM REPORT NO.):

FSAR Sections 3.9 and 3.10  ;

l SIGNATURE (S): 1 DS p,r, JM O 27/ "At 6 Je  !

OCR ITEM REPORT LtR [ PROECT MANAGER FOR PROECT TEAM PRINDIPAL-IN-CHARGE SRT (IF REQUIRED) l

(

ORIGINATOR 9/27/83 9/30/83 10/6/83 10/13/83 DATE DATE DATE DATE DATE

-