Ack Receipt of NRC Re PGE-1020.Response Schedule Will Be Confirmed by 790615
ML19261D547
Person / Time
Site: 05000514, 05000515, Trojan  File:Portland General Electric icon.png
Issue date: 06/11/1979
From: Rachel Johnson
PORTLAND GENERAL ELECTRIC CO.
To: Schwencer A
Office of Nuclear Reactor Regulation
References
TAC-07551, TAC-11299, TAC-7551, NUDOCS 7906190473
Download: ML19261D547 (1)


Text

.

f EC o,

r$-

ND 4*b(Wd ec June 11, 1979 Director of Nuclear Reactor Regulation ATTN:

Mr. A. Schwencer, Chief Operating Reactors Branch #1 Division of Operating Reactors U.S. Nuclear Regulatory Cocmission Washington, D. C. 20555

Dear Sir:

We received on June 4, 1979, your letter of May 18 requesting additional information concerning PGE-1020, which we understand was not mailed to us until May 30 and to other parties until June 6 because of clerical errors.

We tentatively believe we will be able to answer a number of the 50 requests for information about mid-June and the balance of the requests at approximately the end of the month. We understand that this will enable you to maintain your review schedule. We will be in a better position to confirm that response schedule af ter our meeting with the Staf f on Friday, June 15.

Sincerely, R. W. Johnson Corporate Attorney Portland General Electric Company RWJ/GAZ/4kk3A19 2309 194 c:

Service list 7906190473 y(,.o l S: Ie

.