Letter Sequence Approval |
---|
|
Results
Other: ML20062B275, ML20062B279, ML20062B282, ML20062B286, ML20062B419, ML20062B425, ML20062B959, ML20062C142, ML20062C627, ML20062D348, ML20126B604, ML20126C064, ML20147E632, ML20147E640, ML20147F089, ML20147F096, ML20148A060, ML20150A644, ML20150A665, ML20150F064, ML20195C143, ML20195C345, ML20195C351, ML20195C364, ML20195C374, ML20195C385, ML20195C400, ML20195C458, ML20195C462, ML20195C533, ML20197D480
|
MONTHYEARML20195C3451978-04-28028 April 1978 Informs That Structure of Walls in Control Bldg Does Not Meet Seismic Criteria for Sar.Reanalysis Confirms Control Bldg Will Maintain Structural Integrity & Plant Will Retain Functional Capability Under Design Loads Project stage: Other ML20195C3641978-05-26026 May 1978 Clarifies Items 2 & 3 of DG Eisenhut 780502 Memo Re Proposed Mod to Plant Spent Fuel Storage Rack Proceedings.Design Engineer Activities in Fuel Bldg Design Should Be Considered Supporting Role Project stage: Other ML20195C3851978-06-29029 June 1978 Affidavit of Chales M. Trammel,Iii.* Staff Concluded That an Amendment Authorizing Operation of Trojan Nuclear Power Plant Pending Upgrading of Seismic Capability of Control Bldg Walls Would Constitute a Decrease in Safety Margin Project stage: Other ML20195C4001978-06-29029 June 1978 Affidavit of LC Shao Re Control Bldg Design Errors Resulting in Substantially Weaker Walls than Intended by Original Design criteria.As-built Structure Has one-half of Seismic Capacity & Safety Margin Project stage: Other ML20195C3511978-06-29029 June 1978 Forwards Affidavits of CM Trammell & LC Shao Re Safety Significance of Control Bldg Design Deficiencies & NRC Findings Concerning Significant Hazards Considerations Project stage: Other ML20195C3741978-06-30030 June 1978 Forwards Proposed Schedule of Actions to Bring Plant Control Bldg Into Substantial Compliance Ww/Requirements & Intended Design Margins.Detailed Description of Actions,Design Changes & Mods Will Be Submitted Prior to 780901.W/o Encl Project stage: Other ML20195C4581978-08-19019 August 1978 Forwards NRC Questions & Licensee Responses,780804-17 Based on Info Provided by Bechtel Re Control Bldg.All Walls Except 1B,2 & 3 Have Dowel Capacities Exceeding Shear Capacities Controlled by Either Shear or Bending Project stage: Other ML20195C4621978-08-21021 August 1978 Forwards Final NRC Responses to Questions 6 & 10 Re Control Bldg Mods,Based on Info Provided by Bechtel.Equipment in Structure Should Continue to Be Capable of Resisting Seismic Loadings Resulting from Real Earthquakes Project stage: Other ML20195C5331978-08-22022 August 1978 Responds to Re Amendment Permitting Temporary Operation of Plant Independent of Public Hearing.Law Requires Hearing to Be Held in Connection W/Amend to OL Project stage: Other ML20150A6081978-08-30030 August 1978 Forwards Request for Addl Info Re Control Bldg Per Seismic Nonconformance Project stage: RAI ML20150A6141978-09-0101 September 1978 Forwards Preliminary Results of Stardyne Finite Element Analysis of Trojan Control-Auxiliary-Fuel Bldg Complex & Assessment of Seismic Load Resistance of Bldg as Presented at 780828 Meeting. Lic. NPF-1 Project stage: Meeting ML20195C1431978-09-0707 September 1978 Responds to Commissioner Davis Addressed to Commissioner Bradford & Expressing Concerns Re non-conformance to Specs of Control Bldg at Plant & Effect of Facility Shutdown on Rate Payers Project stage: Other ML20147C2411978-09-12012 September 1978 Forwards Corrected Supplementary Info Transmitted by Ltr Project stage: Supplement ML20150A6651978-09-20020 September 1978 Responds to Specified SSE Event.Stardyne Dynamic Analysis Was Used to Determine Structural Capacities & Forces. Concludes That Control Bldg Can Withstand SSE Event Safely Project stage: Other ML20150A6441978-09-20020 September 1978 Forwards Final Results of Rev & Evaluation of Recent Stardyne Finite Element Analysis for Existing Control Bldg of Subj Facil.Suppl Structural Evaluation Response to Specified SSE Event,& Response to Questions Encl Project stage: Other ML20150A6581978-09-21021 September 1978 Order Re Responses to NRC Interrogatories by Coalition for Safe Pwr & Consolidation.Cfsp Must:Respond W/In 14 Days to S1,S2,E1,G1,G2,G3,G8 & All Other Interrogatories;Clarify the Status of Spokesmen.Motion for Reconsideration Is Denied Project stage: Approval ML20062B9611978-09-28028 September 1978 Forwards 780628 Memo to R Mattson Re Info on Failures of safety-related Pipe Supports at Millstone 1 & Design Deficiencies on Similar Equipment at Shoreham.Aslb Notified of Pipe Support Base Plate Design Project stage: Approval ML20147E6321978-10-0303 October 1978 Transcript of Dj Broehl Testimony Re Plant History, Chronology of Events Since Apr 1978 & Summary of Licensee Efforts to Ensure Safe Interim Operation of Control Bldg Project stage: Other ML20147E6401978-10-0303 October 1978 Transcript of SR Christensen Testimony Re Description of Seismic Instrumentation & Engineering Investigations to Be Conducted Following Earthquake Project stage: Other ML20148A0601978-10-0606 October 1978 Direct Testimony of Harold Laursen Re Assignment to Eval Ability of Subj Facil Bldg Shear Walls to Resist Seismic Loading.Determined Shear Walls Can Withstand .25g Safe Shutdown Earthquake Project stage: Other ML20062C1421978-10-11011 October 1978 Notice of Evidentiary Hearing on Issue of Interim Operation & Limited Appearance.Hearing to Determine Whether Interim Operation Should Be Permitted Prior to Mods Required by Order Will Be Held on 781023 & 1030-1101 Project stage: Other ML20062B2821978-10-13013 October 1978 Testimony Describing Insp of Humboldt Bay Following 5.4 Richter Magnitude Earthquake on 750609 & Std Insp Procedures After Seismic Event.Procedures to Be Followed During Earthquake Detailed Project stage: Other ML20062B2751978-10-13013 October 1978 Forwards Ks Herring Testimony on Structural Adequacy of Trojan Control Bldg for Interim Operation & Rt Dodds & Je Knight Testimony on Seismic Features Relevant to Facility Safety Project stage: Other ML20062B2791978-10-13013 October 1978 Testimony Verifying That Reasonable Assurance Exists That Shear Walls Will Withstand SSE or Obe.Original Intended Margins of Safety Reduced & Should Be Restored Project stage: Other ML20062B2861978-10-13013 October 1978 Testimony Responding to ASLB Questions Re Effects of Seismic Event on Plant Features Important to Maintaining Safety of Facility.Certificate of Svc Encl Project stage: Other ML20148C0251978-10-13013 October 1978 Responds to NRC 781011-13 Questions Re Supplemental Structural Evaluation of Control Bldg,Particularly Shear Wall Capacity.Certificate of Svc Encl Project stage: Supplement ML20147F0891978-10-16016 October 1978 Testimony of Bart Withers,As Superintendent of Subj Facil W/Statement of Qual Attached.Describes Capability of Plant to Function & Plant Staff to Respond Properly Immediately Following a Seismic Event Project stage: Other ML20147F0961978-10-16016 October 1978 Licensee'S Testimony on Capability of Subj Facil to W/Stand Seismic Events.Statements of Qualifications,Ref & Append Are Attached.Description of Affected Structure & Deficiencies Such as Amount & Arrangement of Reinforcing Steel Provided Project stage: Other ML20062B4191978-10-16016 October 1978 Forwards Ks Herring Testimony Re Suppl to Stardyne Analysis & Effect on Structural Capacity of Control Bldg.Certificate of Svc Encl Project stage: Other ML20062B4251978-10-17017 October 1978 Testimony Re Suppl to Stardyne Analysis & Effect of Structural Capacity of Control Bldg.Structure Can Withstand SSE & Less Severe Obe,But Suppl Info Alters Earthquake Level Requiring Plant Insp Project stage: Other ML20062B9591978-10-19019 October 1978 Forwards Recent Memoranda Re Certain Problems Experienced in Connection W/Pipe Support Base Plate Design.Staff Determining If Problems Have Generic Implications for Operating Facilities.Aslb Will Be Kept Informed Project stage: Other ML20062C6271978-10-27027 October 1978 Forwards Further Response to NRC Staff Tech Questions Re Stardyne Analysis & Review.Includes Description of Criteria & Procedures Used & Explanation of Dev of New Acceleration time-history.Cert of Svc Encl Project stage: Other ML20062D3481978-11-0606 November 1978 Cross-examination or Testimony Re Analysis & Review by Licensee Poge of safety-related Matls in Control-Auxiliary- Fuel Bldg Complex Will Be Taken at 781211 Hearing.Nrc Given Time to Reply to Interrogs.Proposed Findings Due 781120 Project stage: Other ML20197D4691978-11-22022 November 1978 Forwards Suppl Document Supporting Floor Response Spectra Provided in 781027 & 781102 Submittals to NRC in Response to Request for Additional Info Project stage: Request ML20197D4801978-11-22022 November 1978 Forwards Suppl Documentation in Support of Floor Response Spectra Provided in 781027 & 781102 Responses to NRC Info Requests.W/Cert of Svc Encl Project stage: Other ML20150F0221979-01-0303 January 1979 FOIA Request for 20 Documents Listed Re ECCS Performance Calculations & Calculational Errors Identified by Westinghouse & Portland GE, & on Pipe Cracks in Containment Vessel of Trojan Plant Project stage: Request ML20150F0641979-03-28028 March 1979 Forwards Response to NRC 790308 Technical Questions Re Control Bldg Design Mods.Response Also Being Served on ASLB & All Parties to Control Bldg Proceeding Project stage: Other ML20126B6041980-03-0707 March 1980 Forwards Info Re Environ Qualification of Class IE Equipment in Response to Reporting Requirement of IE Bulletin 79-01B. Info Includes List of Class IE Components Required to Function Under Accident Resulting in Harsh Environ Project stage: Other ML20126C0641980-03-20020 March 1980 Forwards Summary Tables Describing Reinforcing Steel in Shear Wall Panels of Control Auxiliary Fuel Bldg Complex in Response to NRC Verbal Request Project stage: Other ML20062J5401980-10-22022 October 1980 Brief in Support of Exceptions to ASLB 800711 Initial Decision & to Aslab 800904 Order.Urges That Decision Be Modified to Include Accelerated Reporting Conditions & That Oral Argument Be Held Re Exceptions.W/Certificate of Svc Project stage: Other 1978-08-19
[Table View] |
Order Re Responses to NRC Interrogatories by Coalition for Safe Pwr & Consolidation.Cfsp Must:Respond W/In 14 Days to S1,S2,E1,G1,G2,G3,G8 & All Other Interrogatories;Clarify the Status of Spokesmen.Motion for Reconsideration Is DeniedML20150A658 |
Person / Time |
---|
Site: |
Trojan File:Portland General Electric icon.png |
---|
Issue date: |
09/21/1978 |
---|
From: |
Mark Miller Atomic Safety and Licensing Board Panel |
---|
To: |
NRC COMMISSION (OCM) |
---|
References |
---|
TAC-08348, TAC-11299, TAC-13152, TAC-8348, NUDOCS 7809280147 |
Download: ML20150A658 (11) |
|
|
---|
Category:LEGAL TRANSCRIPTS & ORDERS & PLEADINGS
MONTHYEARML20195E9011998-11-0404 November 1998 Comment Supporting Proposed Rule Re Reporting Requirements in 10CFR72.Concurs with NRC Conclusion That Test Rept & Subsequent Holding Period,Unnecessary ML20195B3551998-11-0303 November 1998 Comment on Proposed Rules 10CFR50 & 140 Re Financial Requirements for Permanently Shutdown Nuclear Power Reactors ML20198Q4531998-01-13013 January 1998 Comment Supporting Proposed Rules 10CFR50 & 140 Re Financial Protection Requirements for Permanently Shutdown Nuclear Power Reactors ML20198Q6311998-01-13013 January 1998 Comment on Proposed Rule 10CFR50 & 70 Re Criticality Accident Requirements. Trojan Staff Recommends Proposed Rule Be Revised to Clarify Applicability for Plants That Received NRC Staff Actions ML20136D5481997-03-0606 March 1997 Order Approving Application Re Planned Merger of Portland General Corp,Parent Holding Company for Portland General Electric,W/Enron Corp ML20134L3401997-01-22022 January 1997 Resolution 96-R-85, Resolution Supporting Merger of Centerior Energy Corp & Ohio Edison Under New Holding Co Called Firstenergy ML20058L5881993-11-19019 November 1993 Exemption from 10CFR50.120 Training Rule Requirements ML20058A6101993-11-17017 November 1993 Exemption from Certain Requirements of 10CFR50.54(w) Which Requires Licensee to Obtain & Maintain Min of $1.06 Billion of Decontamination Insurance Coverage ML20058M7001993-09-30030 September 1993 Exemption from 10CFR73.55 Requirements Re Physical Protection in Nuclear Power Reactors for Plant ML20057D9931993-09-30030 September 1993 Exemption to Portions of 10CFR50.54(q) That Apply to Operating Plants & Sections of 10CFR50.47(b) & 10CFR50 App E.Exemption Will Become Effective When Permanently Defueled Emergency Plan Implemented ML20126H4641992-12-29029 December 1992 Exemption from 10CFR50 App E (IV)(F)(2) to Defer Licensee Conducting Its Annual Emergency Plan Exercise Scheduled for 921215 Until First Quarter of 1993 ML20198D3231992-05-0707 May 1992 Exemption from Requirements of 10CFR50,Appendix J,Section III.d.2.(b)(ii) Re Containment Air Lock Pressure Test ML20246K1221989-07-0505 July 1989 Comment Opposing Proposed Rule 10CFR50, Acceptance of Products Purchased for Use in Nuclear Power Plant Structures,Sys & Components. NRC Guidance on Subj of Procurement Would Be More Appropriate than New Regulations ML20235S5401989-02-24024 February 1989 Comment Opposing Proposed Rules 10CFR50 & 55 Re Educ & Experience Requirements for Senior Reactor Operators & Supervisors at Nuclear Power Plants.Questions Ability of Proposed Rule to Achieve Objective ML20235R6861989-02-21021 February 1989 Comment on Proposed Rule 10CFR50 Re Maint Programs for Nuclear Power Plants.Rule Should Not Be Implemented Until Realistic Determination of Impact of Rule on Industry Has Been Made ML20206M8271988-11-21021 November 1988 Comments on Proposed Rule 10CFR26 Re Fitness for Duty Program.Numarc Recommendation That Proposed 300% Sample Size Excessive & That 100% Annual Sample Size Will Be Sufficient Supported ML20195E8711988-10-31031 October 1988 Comment Supporting Proposed Rule 10CFR20 Re Disposal of Waste Oil by Inceneration.Urges Commission to Finalize Rulemaking in Present Form & Ensure That Limited Capacity of Low Level Waste Disposal Sites Be Used Efficiently ML20155D5391988-10-0303 October 1988 Temporary Exemption from Schedular Requirements of Property Insurance Rule Effective 881004 (10CFR50.54) ML20150A9001988-07-0404 July 1988 Comment Opposing Proposed Rule 10CFR50 Re leak-before-break Technology.Further Use of Subj Technology for ECCS Would Reduce Safety Assurances & Safety Benefits.Experience Shows That pipe-thinning Progresses Faster than Expected ML20150F1391988-07-0202 July 1988 Comment Opposing Proposed Rule 10CFR50 Re Expansion of Applicability of Leak Before Break Technology to Functional & Performance Requirements for ECCS & Environ Qualification ML20150A9051988-06-30030 June 1988 Comment Opposing Proposed Rule 10CFR50 Re leak-before-break Technology for safety-related Equipment.Nrc Reliance on leak-before-break Is Irrational Response to Very Real Safety Problem.Nrc Should Implement Mandatory Piping Insp ML20153F6071988-04-29029 April 1988 Application for Amend to Indemnity Agreement B-78.Util Changing Business Name & Merging W/Up&L Merging Corp ML20153F6371988-02-24024 February 1988 Rebuttal Testimony of Jd Tucker Re Application of Pacificorp for Consent to Transfer of Licenses ML20153F7831988-02-24024 February 1988 Rebuttal Testimony of Jh Landon Re Application of Pacificorp for Consent to Transfer of Licenses ML20153F6561988-02-24024 February 1988 Rebuttal Testimony of Dp Steinberg Re Application of Pacificorp for Consent to Transfer of Licenses ML20153F7351988-02-24024 February 1988 Rebuttal Testimony of Vr Topham Re Application of Pacificorp for Consent to Transfer of Licenses ML20153F7001988-02-24024 February 1988 Rebuttal Testimony of OT Colby Re Application of Pacificorp for Consent to Transfer of Licenses ML20153F6681988-02-24024 February 1988 Rebuttal Testimony of RM Boucher Re Application of Pacificorp for Consent to Transfer of Licenses ML20153F6281988-01-0808 January 1988 Testimony of Jh Landon Re Application of Pacificorp for Consent to Transfer of Licences ML20153F6461988-01-0808 January 1988 Prefiled Testimony of Jd Tucker Re Application of Pacificorp to Consent to Transfer of Licenses ML20153F7171988-01-0808 January 1988 Prefiled Testimony of Fd Reed Re Pacificorp for Consent to Transfer of Licenses ML20153F7631988-01-0808 January 1988 Testimony of OT Colby Re Application of Pacificorp for Consent to Transfer of Licenses ML20153F9761988-01-0808 January 1988 Prefiled Testimony of Dp Steinberg Re Application of Pacificorp for Consent to Transfer of Licenses ML20153F6821988-01-0808 January 1988 Testimony of RM Boucher Re Application of Pacificorp for Consent to Transfer of Licenses ML20236S2891987-11-12012 November 1987 Exemption from Requirements of 10CFR50,App R,Section III.G.2 Re Fire Protection of Safe Shutdown Cables & Equipment Located Inside Containment Bldg ML20212N2471986-11-0303 November 1986 Partially Withheld Petition to Suspend OL Due to Util Failure to Disclose Conditions That Undermine Safety in Case of Seismic Event.Directors Should Issue Order Under 2.206 to Show Cause Why OL Should Not Be Suspended ML20126H5251981-04-0303 April 1981 Notification of New Address for Coalition for Safe Power. Certificate of Svc Encl ML20062J5401980-10-22022 October 1980 Brief in Support of Exceptions to ASLB 800711 Initial Decision & to Aslab 800904 Order.Urges That Decision Be Modified to Include Accelerated Reporting Conditions & That Oral Argument Be Held Re Exceptions.W/Certificate of Svc ML20126D1541980-04-0303 April 1980 Transcript of 800403 Evidentiary Hearing,Phase 2,in Portland,Or.Pp 4,454-4,497 ML20126D0281980-04-0101 April 1980 Transcript of Phase Two Evidentiary Hearing in Portland,Or. Pp 3913-4123 ML20126D2461980-03-22022 March 1980 Response to NRC Third Set of Interrogatories,Phase II of Control Bldg Proceeding.Expresses Concerns Re Effect of Noise in Work Areas & Effect of Vibration on Instruments,Not Mentioned in SER ML20126C0331980-03-11011 March 1980 Transcript of 800311 Hearing in Portland,Or.Pp 3,451-3,590 ML20126A8641979-12-29029 December 1979 Transcript of 791229 Hearing in Portland,Or.Pp 3426-3450 ML20244A6471979-04-17017 April 1979 Licensees' Response to 790402 Request of PA Public Util Commission for Hearing & Petition to Intervene Re 790313 Show Cause Order.Urges NRC to Hold Ruling in Abeyance. Certificate of Svc Encl ML20148J1371978-12-18018 December 1978 Intervenor ST of Or'S Motion for an Extension of Time in Which to File Exceptions to the 781005 Order of Aslb. Motion Granted 781023 ML20147J2331978-12-14014 December 1978 Transcript of Hearing on 781214 in Saleam or in the Matter of Portland Gen Elec.Pp 2883-2996 ML20147J2301978-12-13013 December 1978 Transcript of Hearing on 781213 in the Matter of Portland Gen Elec at Salem,Or.Pp 2739-2882 ML20150E7821978-12-12012 December 1978 Transcript of Hearing on 781212 at Salem,Or.Pp 2574-2738 ML20147E1261978-12-11011 December 1978 Transcript of 781211 Hearing in Salem,Or.Pp 2390-2573 ML20062E0271978-11-20020 November 1978 Proposed Findings Submitted by St of or Per ASLB Request of 781103.Suggested That Scope of the Hearing Should Be Limited & That Control Bldg Sheer Walls Are of Strength to W/Stand Earthquake.Cert of Svc Encl 1998-11-04
[Table view] Category:ORDERS
MONTHYEARML20136D5481997-03-0606 March 1997 Order Approving Application Re Planned Merger of Portland General Corp,Parent Holding Company for Portland General Electric,W/Enron Corp ML20062D3481978-11-0606 November 1978 Cross-examination or Testimony Re Analysis & Review by Licensee Poge of safety-related Matls in Control-Auxiliary- Fuel Bldg Complex Will Be Taken at 781211 Hearing.Nrc Given Time to Reply to Interrogs.Proposed Findings Due 781120 ML20150A6581978-09-21021 September 1978 Order Re Responses to NRC Interrogatories by Coalition for Safe Pwr & Consolidation.Cfsp Must:Respond W/In 14 Days to S1,S2,E1,G1,G2,G3,G8 & All Other Interrogatories;Clarify the Status of Spokesmen.Motion for Reconsideration Is Denied ML20062B3721977-09-15015 September 1977 Order Rescinding ASLB 780808 Memorandum & Order.Spent Fuel Storage Pool Presently Contaminated & Affects Installation & Use of New Spent Fuel Storage Racks 1997-03-06
[Table view] |
Text
.~~'
ff, %
l , b (;92 $
LNITED STATES OF AMERICA NI
- NUCLEAR FIGULATORY COICESSION i
( g'2.1goJ d i C) p In the Matter of ) 6'
)
4 f^ L.
. FORIIAND GENERAL ELECIRIC CQfAhT, ET AL. ) Docket No. 50-344 i )
(Trojan Nuclear Pour Plant) )
ORDER REGARDING RESPONSES TO IhTERROGATORIES, AND CONSOLIDATION ,
(Septetber 21, 1978)
I.
On Septaber 6,1978, the Staff filed a motion to ccupel Eugene Rosolic /
\ Coalition for Safe Powr (Intervenor) to respond fully to certain of the Staff's interrogatories datad August 9, 1978. This Intervenor's responses to the Staff's interrogatories wre dated August 25, 1978.
Much of the response consists of so-called "Prefatory Ccnrrnts", which are essentially a series of legal argunents not responsive to any interroga-tory. Such gratuitous argtrents, dealing with the burden of proof, limited resources, duties of URC and the Staff and the like, are not in ccepliance with the discovery procedures set forth in the Ccnmission's Rules of Practice (10 CFR 52.740). 10 CFR $2.7406, relating to interrogatories to parties, clearly provides that "Each interrogatory shall be answered separately and fully in writing t'nder oath or affirmation, unless it is objected to, in which event the reasons for objection shall be stated in lieu of an answer." This requiranent of separate and explicit responses to each interrogatory cannot be ciretnwented by setting up a diffuse legal I
, argtment to which vagtie references are nudo frcci time to time, l
3
.r MW#U//97 .
/
. 4 I
q '
I. '
L r [ h 3
r l [
f.
Interrogatory Si deals with the identification of and bases for any ,
disagreements'of Intervenor with the statements or conclusions contained in c the NRC Order dated May 26, 1978, or in the supporting safety evaluation prepared by the Staff. Interrogatory S2 concerns the bases of any specific i:
concerns which were not dealt with in the NRC Order and safety evaluation.
The response was that this deserves a reanalysis considering the new data that has ccee to light as of August 22. e In his request for hearing dated June 16, 1978, the Intervenor asserted that:
e "the NRC staff evaluation of the situation at the Trojan plant is not adequate. According to the Ccumission order, dated May 26, 1978, at no time did the NRC staff conduct ,
an independent on-site investigation of the control i building. Thus, the NRC staff has failed to fulfill its i obligation to the public and any order based upon the !
<3 resent NRC staff investigation would be arbitrary.
- ibrther, any order is not in our best interest and wuld not provide reasonable assurance that the health and rofety of the public wuld not be endangered. . . . It is our contention that no such (interim] operation should be allowd. The order of the Ccumission subverts its own rules and w uld :
unnecessary danger."place the public in undue and In his amended petition dated July 23, 1978, the Intervenor clairred that:
"The occurrence of a seismic event durire interim o'acration of the Trojan Nuclear Powr Plant. ..coufd exceed tv.e safe shutdom earthquake capability of the Control Building and !
result in the release of ionizing radiation."
i As the Staff contends, these assertions constitute attacks on the ,
- adequacy of the order and evaluation, and the interrogatories ask for an ,
l l
, ~ - .- . . ...
. g A
- - - -r----- --- - - - - - - - - - - - - - - --
L .
4
- . . - \
l identification of the inadequacies and the bases for tha conclusions. If the Intervenor cannot identify the inadequacies or descr'bc the bases for i his challenges, he should simply say so. If he can, he should answer fairiy and* fully. 'Ihese conclusions of the Intervenor antedated the new infor:ra-tion of August 22, 1978, and direct and responsive answers should be given.
If the new information adda to the scope or bases of the challenges, the Intervonor can and should supplcment his responses. All parties have been directed by the Board to regard interrogatories as continuire in nature, and pursuant to 10 GR $2.740(e)(3), they shall supplerent their responses
\ to include information thereafter acquired.
Interrogatory El involves the alleged need for the preparation of EIS.
Interrogatory E2 asks whether it is contended that the proposed codifica-tions will "significantly affect the quality of the huran enviroment",
and if so the bases for such a contention. D e response was to see the Prefatory ccanents. Rese ecmrents assert, acong other things, that it is the responsibility of NRC to carefully consider the envircrrrantal aspects of proposed actions, but they do not set forth the factual inforeation
- sought by these interrogatories. The replies must be viewd as evasive and unresponsive.
Interrogatory G1 involved the Intervenor's position on factual state-mcnts contained in specified docurents. As to a license evcat report (ER) and a supple:xnt, the response was that it was still under investiga-tion, without indicating by shczn or when the investigation would be
~
conpleted. Since the Intervenor wan given these docunents on July 2.4, 1978, d- -
. 4
~
l '
4 -- -
i I
he should give as complete a response as he can at this time, and supplcment it if and when the alleged investigation is completed. Re rcmaining doctments contain factual infonaation concerning the nature of the control building design errors, the method used to reanalyze its structural capacity, and the effects of the proposed modifications as well as the design criteria to be utilized for the nodifications. The Intervenor responds scmewhat disingenuously by treating the interrogatories as though he wns asked to ecmncnt on the minutes of meetings, says that these meetings are held in Washington, D. C., and states that he does not have the funds to fly there
. nor would he want to due to the increase in radiation exposure. W e Staff sus making a serious effort to identify the statcccnta or analyses in the referenced doctcents with which the Intervenor disagrees or that he contends are inaccurate or inadequate, and to discover the bases therefor.
Direct and responsive answers should be provided.
Interrogatory G2 involved the Intervenor's understanding of the meaning and significance of the Safe Shutdown Earthquake (SSE) term, and its relationship to interim operation. Interrogatory G3 asked for the Intervcnor's understanding of the nature and significance of the defects in the original analysis of tin control building. We responses were simply to see the prefatory cocments. Ituever, in his amended petition, l the Intervenor had asserted that the "rr.currence of an earthquake durire interim operatica.. .could exceed the safe shutdown eartiquake capability of the Control Building." he Staff is entitled to ascertain the bases I ,
,L
, ~ ~ . _ _ , .
. . ...y i
e ,
, . ,c a ,
9 5- 3,
. h for these assertions. These interrogatories do not require Intervenor to engage in extensive research or to ecxnpile data, but merely ask for an i l elaboration of his own understanding and reasoning. Full and direct responses should be made to these interrogatories. . a Interrogatory G8 asks for the identification of all books, docunents and papers that the Intervenor will employ in presenting his direct case.
The reply, to see prefatory cmments, is evasive and unresponsive.
Interrogatory G9 seeks a similar idene.ification of books and docuncnts l to be used in the cross-examination of prospective Staff witnesses. The .
response. that the Intervenor has not seen the Staff testimony or the final modification, is proper at this tica. However, the response should be supplemented after this infonnation has beccme available.
The Intervenor is directed to provide full and responsive answers under oath or affirmation et 7gatories S1, S2, El, E2, G1, G2, G3 and G8 within 14 days after . . .vice of this Order. Suppicmental responses shall be filed to include inforantion thereafter acquired, pursuant to the provisions of 10 TR $2.740(e)(3).
There ranain several nutters affecting the status of the Coalition For Safe Power (CFSP) which nust be clarified in writing. At the first Special Prehearing Conference on July 24, 1978, Mr. Rosolie was asked whether CFSP was a bona fide organization, with ucre than one mcInber sb possessed the requisite interest to qualify as an intervening party. He i stated that it was, and agreed to supply in writing the names and a 6 rw-- - #%.. e- a 'ye 4
addresses of several mmbers possessing the requisite interest. This infor-mation has never been received. .
I Relying upon the representation of Mr. Rosolic that he "as a mm.ber and officer of the GSP have been anpowered by trarbers to represent their interest in this matter", the Board granted the petition filed "On bchalf of myself, Eugene Rosolic, and the Coalition For Safe Power (CFSP)." By its Order of July 27, 1978, the Board provided that the request for hearing and intervention, filed by "Eugene Rosolie, acting on his own behalf and as a representativa of the Coalition For Safe Power (CFSP)...is granted on ,
\ the condition that one spokesman be designated to participate directly in these proceedings, and that one other umber of CFSP be pemitted to sit at counsel table" (Order, p. 3). The participation of CFSP was conditioned as follows:
"3. The Coalition For Safe Power shall represent the interests of its mmbers and petitioners through a single spokesman, with one officer or mmber pemitted to sit at counsel table" (Order, p. 9).
It was the intention of the Board to grcnt Mr. Rosolie a dual role, that uf directly representing both himself and CFSP. This was in effect a consolidation of parties, pursuant to our desire to reduce the nurber of voices asserting substantially the same interests and issues, and thereby restricting duplicative or repetitive evidence and argument (10 CFR SS2.714(c),
2.715(a). Apparently, Mr. Pasolic takes the same view of his status,as he filed a response to the Staff's interrogatories as "Eugene Rosolie, intervening on his om behalf and on behalf of the Coalition For Safe l
1
}
4
4 i
. o.
7- ;
l
, Power (GSP)." 'Ibic response was also signed "Eugene Rosolie, pro se and ,
on behalf of the Coalition For Safe Power" (Intervenor Coalition For Safe Power Response to Staff's Interrogatories, pp. 1, 4).
However, at the afternoon session of the second Special Prehearing Conference held on August 14, 1978, a self-proclaimed representative of -
i
- GSP (Susan M. Garrett) persistently endeavored to intervene and partici- '
i
/,> pate in the proceedings being conducted by the Board. In the interest of i orderly hearings, the Board never intended for different individuals I
ostensibly representing Eugene Rosolie/GSP to shuttle in and out of ,
different sessions, at least not without prioi leave granted pursuant to written motion and a showing of good cause. Accordingly, Eugene Rosolie/
GSP are directed to file the following inforcation in writing:
- 1. We names, addresses and descriptions of interest of several other umbers of GSP.
- 2. h e names, addresses and titles of all Atly designated (not "acting") officers of that organization.
- 3. A clarification of the status of Eugene Rosolie as the .
sole designated representative or spokestran of CFSP in
, this proceeding.
d
.. f A
1
T t
k , '
I II.
I i
on August 9, 1978, the Staff served interrogatories on the Consolidated l Intervenors (Nina Bell, C. Gail Parson and David B. PrCny). A response dated August 19,1978 (but postmarked August 31,1978) was filed by Nina Bell, one of these intervemrs. 'Ihis response does not purport to be on behalf of all of these intervenors, but is stated to be "on her cr-n behalf",
and asserts that it was "impossible for the three intervenors to prepare this cbcument together due to the great distance Intervenor McCoy mild
, have to travel / phone in order to do so."
i
,l By our Order of July 27, 1978, intervention by these three individuals ,
', was expressly condition upon than being "consolidated as intervenor parties for all purposes in this proceeding. They shall participate directly in all conferences and hearings through a single spokesman to be designated by thcm" (p. 8) . As a result of this consolidation for all purposes, it is incurbent upon these three intervenors to coordinate their responses so that the answers to interregatories reflect the group response of the Consolidated Intervenors as a single party to this proceeding. The Staff's f cution to ccepel a consolidated response to interrogatories is granted.
Nina Bell's excuse for a failure to ccordinate responses is untenable.
- 'Ihe "great distance" which Mr. McCoy resides fran the Trojan facility is 200 miles, and he has alleged that he is frequently in its vicinity in conjunction with his business of tuning and repairing schcol pianos, as wil as frequcnt travels to the area for "recreational and envirormentally oriented purposes" (Anended Petition, p. 1). As the Appeal Board noted in l
.(
i M
( . .
, r
. 1
-l h I
j ,
, ..j r t.
deciding Mr. McCoy's recent appeal frcm consolidation, 'Mr. McCoy can, of .
I course, connunicate with the other intervenors by mail or telephone and, I additionally, if necessary can arrange to meet with thcm when in the vicinity of their residences on other business" (AIAB-496, Septaber 12, 1978, slip opinion ftn. 3, p. 5) . Ms. Bell does not assert that any attecpt to meet ,
with the other intervenors to coordinate their joint response. Nor does she advance any reason why she could not have coordinated with Ms. Parson, who ,
also lives in the same city (Portland, Or6gon) that she does.
- It should be further noted that Ms. Bell's response contains a .
. "Prefatory Cmments" statment that is identical with that filed by Eugens Rosolie and discussed in Section I, supra. It is wholly inadequate as a response for the same reasons discussed above, as are the unresponsive answers which are also very similar to those of Mr. Rosolie.
'Ihe Consolidated Intervenors are directed to file a grcup response to the Staff's interrogatories within 14 days frcm the date of service of this Order.
III.
- On August 10, 1978, the Staff filed interrogatories and requests for production of documents upon the Intervenor Columbia Environmental Council.
Under our rules, responses should have been filed by August 30,1978 (10 CFR
$$2.710,2.740b). No responses by this Intervenor have been filed, and J
the Staff has filed a motion to ecupel responses, t .
.{
}
m
v . ,
3- .
} .
t In accordance with the provisions of 10 CFR 52.740:f), the Intervenor Colunbia Environmental Council is ordered to respond directly and fully to l the Staff's interrogatories dated August 10, 1978.
s W.
'Ihe Board has recently received a copy of an undated document filed by Intervenors Gail Parson and Nina Bell, entitled Objection to Order Concern-in6 Requests For Hearing And Intervention Petitions And Request For Revision Of Order Or Certification. Apparently these objections were not l
served upon the Board or the Staff.N These two Intervenors object to their consolidation with David B. McCoy by the Order of July 27, 1978, although they do not object to their consolidation with each other.
The reasons for this consolidation are set forth at pages 6-8 of our prior order, and we adhere to than. Objection is further made because of the alleged difficulties in coordinating with Mr. McCoy because he resides 200 miles fran the objectors. 'Ihe inadequacy of this ground for objection is discussed in Section II, suora. -
There has been no showing of any effort to camunicate with Mr. McCoy by telephone, mail, or in the course of his frequcnt visits to the Portland M In its notion for extension of time in which to respond, dated
- Septanber 20, 1978, the Staff indicated that it was not aware of the existence of this document until Septarber 18, 1978. In view of the
- disposition, w make of these objections and of the Staff's viea on this consolidation set forth in its responses to interrogatories of
- Ihvid B. McCoy and the Consolidated Intervonors, filed on Septanber 18, 1978, we dean it unmcessary to require any further response by the Staff.
1 j s I 1
, t
j -
I * .
l 1
l area. In addition, Mr. McCoy and Ms. Parson both atteniM the special pre-hearing conference held in Portland on August 14, 1978, a"d there was no i discernible difficulty in having their views freely expressed by their l designated spokesnan. And as the Appeal Board has observed, "nothing in the Licensing Board's order will prevent either Mr. McCoy or the other intervenors fran later endeavoring to obtain full or partial relief fran the provisions of that order should the consolidation turn out in practice to be necessarily and significantly prejudicial to the protection of their interests" (AIAB-496, Septanber 12, 1978, slip opinien pp. 5-6). 'Ihe cution for reconsideration or certification is denied.
IT IS SO ORDERED.
FCR 'nE A'ITIC SAFE 1Y KO LI NSU G ECAFD
,1 g h ;ff [, b^ Sig
!Parshall E. Miller, Chairfan Ihted at Bethesda, M1ryland this 21st day of Septanber 1978.
l e
.