Letter Sequence Meeting |
|---|
|
Initiation
- Request, Request, Request, Request, Request, Request, Request, Request, Request
- Acceptance...
- Supplement, Supplement, Supplement
Results
- Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval
Other: 05000344/LER-1978-020, Forwards LER 78-020/03X-3, 05000344/LER-1978-020-03, /03L-0:on 780622,during Design Review for Piping Stress at Wall Penetrations,One Sys Was Found to Have Stress Exceeding Allowable Code.Caused by Design Error.Grouting Around Pipe Removed & Stress Reduced, ML19207C007, ML19209A322, ML19209A323, ML19209A336, ML19209A363, ML19209A432, ML19209A435, ML19209B063, ML19209B180, ML19209B241, ML19209D051, ML19209D056, ML19225A294, ML19241A963, ML19241A969, ML19241C194, ML19242B129, ML19242B972, ML19247B146, ML19248C628, ML19248C934, ML19249D678, ML19250C450, ML19253C727, ML19254D131, ML19254F178, ML19256F544, ML19256F546, ML19256F990, ML19256F993, ML19260C591, ML19261A687, ML19261D547, ML19261D820, ML19263E970, ML19267A290, ML19267A296, ML19269D190, ML19270E836, ML19270G402, ML19270H454, ML19271A997, ML19275A272, ML19282A785, ML19289C608, ML19289F192, ML19290C976, ML19294B198... further results
|
MONTHYEARML19209A3631974-02-25025 February 1974 Burn Tests on Silastic Rubber-Coated Glass Drop Cloths. Prof Qualifications of Ew Edwards Encl Project stage: Other ML19256F5461974-06-30030 June 1974 Miscellaneous Paper C-74-12,Pullout Resistance of Reinforcing Bars Embedded in Hardened Concrete, Prepared by Engineer Waterways Experiment Station Project stage: Other ML20195C3451978-04-28028 April 1978 Informs That Structure of Walls in Control Bldg Does Not Meet Seismic Criteria for Sar.Reanalysis Confirms Control Bldg Will Maintain Structural Integrity & Plant Will Retain Functional Capability Under Design Loads Project stage: Other ML20195C3641978-05-26026 May 1978 Clarifies Items 2 & 3 of DG Eisenhut 780502 Memo Re Proposed Mod to Plant Spent Fuel Storage Rack Proceedings.Design Engineer Activities in Fuel Bldg Design Should Be Considered Supporting Role Project stage: Other ML18004B9711978-06-0202 June 1978 Addresses Pipe Support Base Plate Problem.Discusses Review of Support Redesigns & Capability of Anchor Bolts to Withstand Cyclic Loadings Project stage: Approval ML20195C3511978-06-29029 June 1978 Forwards Affidavits of CM Trammell & LC Shao Re Safety Significance of Control Bldg Design Deficiencies & NRC Findings Concerning Significant Hazards Considerations Project stage: Other ML20195C3851978-06-29029 June 1978 Affidavit of Chales M. Trammel,Iii.* Staff Concluded That an Amendment Authorizing Operation of Trojan Nuclear Power Plant Pending Upgrading of Seismic Capability of Control Bldg Walls Would Constitute a Decrease in Safety Margin Project stage: Other ML20195C4001978-06-29029 June 1978 Affidavit of LC Shao Re Control Bldg Design Errors Resulting in Substantially Weaker Walls than Intended by Original Design criteria.As-built Structure Has one-half of Seismic Capacity & Safety Margin Project stage: Other ML20195C3741978-06-30030 June 1978 Forwards Proposed Schedule of Actions to Bring Plant Control Bldg Into Substantial Compliance Ww/Requirements & Intended Design Margins.Detailed Description of Actions,Design Changes & Mods Will Be Submitted Prior to 780901.W/o Encl Project stage: Other 05000344/LER-1978-020-03, /03L-0:on 780622,during Design Review for Piping Stress at Wall Penetrations,One Sys Was Found to Have Stress Exceeding Allowable Code.Caused by Design Error.Grouting Around Pipe Removed & Stress Reduced1978-07-21021 July 1978 /03L-0:on 780622,during Design Review for Piping Stress at Wall Penetrations,One Sys Was Found to Have Stress Exceeding Allowable Code.Caused by Design Error.Grouting Around Pipe Removed & Stress Reduced Project stage: Other ML20195C4581978-08-19019 August 1978 Forwards NRC Questions & Licensee Responses,780804-17 Based on Info Provided by Bechtel Re Control Bldg.All Walls Except 1B,2 & 3 Have Dowel Capacities Exceeding Shear Capacities Controlled by Either Shear or Bending Project stage: Other ML20195C4621978-08-21021 August 1978 Forwards Final NRC Responses to Questions 6 & 10 Re Control Bldg Mods,Based on Info Provided by Bechtel.Equipment in Structure Should Continue to Be Capable of Resisting Seismic Loadings Resulting from Real Earthquakes Project stage: Other ML20195C5331978-08-22022 August 1978 Responds to Re Amendment Permitting Temporary Operation of Plant Independent of Public Hearing.Law Requires Hearing to Be Held in Connection W/Amend to OL Project stage: Other ML20150A6081978-08-30030 August 1978 Forwards Request for Addl Info Re Control Bldg Per Seismic Nonconformance Project stage: RAI ML20150A6141978-09-0101 September 1978 Forwards Preliminary Results of Stardyne Finite Element Analysis of Trojan Control-Auxiliary-Fuel Bldg Complex & Assessment of Seismic Load Resistance of Bldg as Presented at 780828 Meeting. Lic. NPF-1 Project stage: Meeting ML20195C1431978-09-0707 September 1978 Responds to Commissioner Davis Addressed to Commissioner Bradford & Expressing Concerns Re non-conformance to Specs of Control Bldg at Plant & Effect of Facility Shutdown on Rate Payers Project stage: Other ML20147C2411978-09-12012 September 1978 Forwards Corrected Supplementary Info Transmitted by Ltr Project stage: Supplement ML20150A6441978-09-20020 September 1978 Forwards Final Results of Rev & Evaluation of Recent Stardyne Finite Element Analysis for Existing Control Bldg of Subj Facil.Suppl Structural Evaluation Response to Specified SSE Event,& Response to Questions Encl Project stage: Other ML20150A6651978-09-20020 September 1978 Responds to Specified SSE Event.Stardyne Dynamic Analysis Was Used to Determine Structural Capacities & Forces. Concludes That Control Bldg Can Withstand SSE Event Safely Project stage: Other ML20150A6581978-09-21021 September 1978 Order Re Responses to NRC Interrogatories by Coalition for Safe Pwr & Consolidation.Cfsp Must:Respond W/In 14 Days to S1,S2,E1,G1,G2,G3,G8 & All Other Interrogatories;Clarify the Status of Spokesmen.Motion for Reconsideration Is Denied Project stage: Approval ML20062B9611978-09-28028 September 1978 Forwards 780628 Memo to R Mattson Re Info on Failures of safety-related Pipe Supports at Millstone 1 & Design Deficiencies on Similar Equipment at Shoreham.Aslb Notified of Pipe Support Base Plate Design Project stage: Approval ML20062A5471978-09-29029 September 1978 Notifies That Staff Is Unable to File Testimony on Interim Oper of Subj Facil Before 781013 Re Finite Element Analysis. Urges That ASLB Commence Hearing on 781018 or 781023 Project stage: Request ML20147E6401978-10-0303 October 1978 Transcript of SR Christensen Testimony Re Description of Seismic Instrumentation & Engineering Investigations to Be Conducted Following Earthquake Project stage: Other ML20147E6321978-10-0303 October 1978 Transcript of Dj Broehl Testimony Re Plant History, Chronology of Events Since Apr 1978 & Summary of Licensee Efforts to Ensure Safe Interim Operation of Control Bldg Project stage: Other ML20148A0601978-10-0606 October 1978 Direct Testimony of Harold Laursen Re Assignment to Eval Ability of Subj Facil Bldg Shear Walls to Resist Seismic Loading.Determined Shear Walls Can Withstand .25g Safe Shutdown Earthquake Project stage: Other ML20062C1421978-10-11011 October 1978 Notice of Evidentiary Hearing on Issue of Interim Operation & Limited Appearance.Hearing to Determine Whether Interim Operation Should Be Permitted Prior to Mods Required by Order Will Be Held on 781023 & 1030-1101 Project stage: Other ML20148C0251978-10-13013 October 1978 Responds to NRC 781011-13 Questions Re Supplemental Structural Evaluation of Control Bldg,Particularly Shear Wall Capacity.Certificate of Svc Encl Project stage: Supplement ML20062B2751978-10-13013 October 1978 Forwards Ks Herring Testimony on Structural Adequacy of Trojan Control Bldg for Interim Operation & RT Dodds & Je Knight Testimony on Seismic Features Relevant to Facility Safety Project stage: Other ML20062B2791978-10-13013 October 1978 Testimony Verifying That Reasonable Assurance Exists That Shear Walls Will Withstand SSE or Obe.Original Intended Margins of Safety Reduced & Should Be Restored Project stage: Other ML20062B2821978-10-13013 October 1978 Testimony Describing Insp of Humboldt Bay Following 5.4 Richter Magnitude Earthquake on 750609 & Std Insp Procedures After Seismic Event.Procedures to Be Followed During Earthquake Detailed Project stage: Other ML20062B2861978-10-13013 October 1978 Testimony Responding to ASLB Questions Re Effects of Seismic Event on Plant Features Important to Maintaining Safety of Facility.Certificate of Svc Encl Project stage: Other ML20147F0961978-10-16016 October 1978 Licensees Testimony on Capability of Subj Facil to W/Stand Seismic Events.Statements of Qualifications,Ref & Append Are Attached.Description of Affected Structure & Deficiencies Such as Amount & Arrangement of Reinforcing Steel Provided Project stage: Other ML20147F0891978-10-16016 October 1978 Testimony of Bart Withers,As Superintendent of Subj Facil W/Statement of Qual Attached.Describes Capability of Plant to Function & Plant Staff to Respond Properly Immediately Following a Seismic Event Project stage: Other IR 05000344/19780201978-10-16016 October 1978 IE Inspec Rept 50-344/78-20 on 780905-29 During Which No Items of Noncompliance Were Noted.Major Areas Inspec Incl: Plant Opers,Maint,Surveillance Test,Facil Security & Licensee Event Followup Project stage: Request ML20062B4191978-10-16016 October 1978 Forwards Ks Herring Testimony Re Suppl to Stardyne Analysis & Effect on Structural Capacity of Control Bldg.Certificate of Svc Encl Project stage: Other ML20062B4251978-10-17017 October 1978 Testimony Re Suppl to Stardyne Analysis & Effect of Structural Capacity of Control Bldg.Structure Can Withstand SSE & Less Severe Obe,But Suppl Info Alters Earthquake Level Requiring Plant Insp Project stage: Other ML20062B9591978-10-19019 October 1978 Forwards Recent Memoranda Re Certain Problems Experienced in Connection W/Pipe Support Base Plate Design.Staff Determining If Problems Have Generic Implications for Operating Facilities.Aslb Will Be Kept Informed Project stage: Other ML20062C6271978-10-27027 October 1978 Forwards Further Response to NRC Staff Tech Questions Re Stardyne Analysis & Review.Includes Description of Criteria & Procedures Used & Explanation of Dev of New Acceleration time-history.Cert of Svc Encl Project stage: Other ML20062D3481978-11-0606 November 1978 Cross-examination or Testimony Re Analysis & Review by Licensee Poge of safety-related Matls in Control-Auxiliary- Fuel Bldg Complex Will Be Taken at 781211 Hearing.Nrc Given Time to Reply to Interrogs.Proposed Findings Due 781120 Project stage: Other ML20197D4801978-11-22022 November 1978 Forwards Suppl Documentation in Support of Floor Response Spectra Provided in 781027 & 781102 Responses to NRC Info Requests.W/Cert of Svc Encl Project stage: Other ML20197D4691978-11-22022 November 1978 Forwards Suppl Document Supporting Floor Response Spectra Provided in 781027 & 781102 Submittals to NRC in Response to Request for Additional Info Project stage: Request ML19305A0701978-12-11011 December 1978 Limited Appearance Statement by Rd Pollard of Ucs to Explain the Kind of Inquiry Possible,Yet Untapped,W/Respect to Any Person of Pollards Competence & Commitment in Field of Nuclear Plant Licensing Project stage: Other ML19305A0631978-12-18018 December 1978 Forwards Limited Appearance Statement by Rd Pollard of Ucs. W/Encls Project stage: Other ML19270E8361978-12-21021 December 1978 Partial Initial Decision Re Whether Operation of Facility Should Be Permitted in Spite of Identified Design Deficiencies in Control Bldg & Prior to Mod.Decision Is to Allow Interim Operation Project stage: Other ML19267A3021978-12-22022 December 1978 Notice of Issuance of Amend 35 License NPF-1 Project stage: Approval ML19267A2901978-12-22022 December 1978 Forwards Partial Initial Decision,Amend 35 to License NPF-1 & Notice of Issuance Project stage: Other ML19267A2961978-12-22022 December 1978 Amend 35 to License NPF-1.Modifies Waiver Portions of Tech Specs & FSAR Criteria Which Have Not Been Followed Due to Design Deficiency in Control Bldg Shear Walls Project stage: Other 05000344/LER-1978-020, Forwards LER 78-020/03X-31978-12-26026 December 1978 Forwards LER 78-020/03X-3 Project stage: Other ML19308A2121978-12-26026 December 1978 Reportable Occurrence on 780622: Piping Penetrations Not Designed to Be Solidly Grouted Were Found to Be Solidly Grounted.During Subsequent Design Review,Excessive Support or Pipe Stresses Found on 11 Isometrics. Probable DELETE-RO Project stage: Other ML20150F0221979-01-0303 January 1979 FOIA Request for 20 Documents Listed Re ECCS Performance Calculations & Calculational Errors Identified by Westinghouse & Portland GE, & on Pipe Cracks in Containment Vessel of Trojan Plant Project stage: Request 1978-04-28
[Table View] |
Text
.
r
' g eg Department of Energy
..c'f, ^, ';" "
LABOR & INDUSTRIES OUILDING. ROOM 111. SALEM CPEGCN 97310 PHONE 378-404o u
60 -3h June 27, 1979 Charles Goodwin Portland General Electric 121 SW Salmon Street g p} pgpqy p n) y g
jf h[a n tt][ h.-d y g.
5 du i
[
Portland, OR 97204
Dear Mr. Goodwin:
At its June 12, 1979 meeting, the energy Facility Siting Council authorized the department to request certain information about the Trojan Nuclear Plant from Portland General Electric pursuant to CAR 345-10 015.
The purpose of this information is to determine whether any improvements in the auxiliary feedwater syste;., environmental qualitication of equipment or control and protective system interactions would make a significant difference in the level of Trojan safety.
Attachments 1, 2 and 3 identify the scope of this information request.
Even so, the attachments are general in nature and will require PGE's thoughtful consideration when performing its analyses so that the resulting information is useful to both organizations.
It is suggested that PGE discuss its progress with 000E periodically so both are assured that the proper areas are being explored.
000E recognized that the information requested may require a substantial effort on the part of PGE.
This effcrt may require the hiring of additional persons or the letting oi contracts outside the company.
Nonetheless, ODGE expects PGE management to assign the resources needed to meet the completion dates established belcw.
00GE also recognizes that some of what is being requested of PGE may already exist in other forms, e.g., studies by the NRC or the industry and existing standards. References to these other d% uments is acceptable if copies are provided to 000E and if PGE provides a technical justification for its re1iance en the documen't.
OCOE suggests that PGE consider documenting i s response to these information requests in a form which could be included page for page in the Trojan Final Safety Analysis Report (FSAF) cr ir, a separate binder (e.g., PGE-1020) which could be referenced ir, the FSAR. This approach would provide documents which could be referred to in the future, both by regulators and PGE. thus preventing duplication of this effort.
r L
%el
/7 p
A
//
32S 223 7 9. 0 ' ] UL,u (w
^o o
u.
Charles Goodwin,
June 27, 1979 Page 2 PGE is requestad to provide the information relating to the auxiliary feedwater system, envircnmental qualification of equipment and control / protective system interacticas by November 30, August 31, and December 3:
1979, respectively.
PGE should expect follow-up questions frca 000E upon submission of these reports.
Sincerely, ontgim
/
/
Lynn Frank Director LF/DG:cs 3483A cc: Ed Whelan, PGE R. H. Engelken, NRC V C. Trammel, NRC A. Nistad, EFSC 4
(
t 0 4
m
t-
'p.
O<.au.o g
q, a w,
't e ~
l L<
}
,. -->..i..
.~.. J C ',1 J G.. J'3_,_._
Auxiliary Feedwater Systen Purpose - To identify, by use of risk assessnient methodology, whether changes to the Trojan auxiliary feedwater fluid and electrical systems would improve its reliability.
Discussion - Unlike most safety related equipment, the auxiliary feedwater system is used routinely for ncrmal plant shutdowns as well as during accident conditions.
The more frequent use of this equipment makes its reliability more important; particularly 'since its f ailure results in the need to operate other safety equipment, thereby reducing the margins of safety provided by the various backup cooling systems.
000E believes that a risk assessment, utilizing f ault trees, would provide the best mechanism for identifying a) how the system can f ail anc b) whether improvements would improve reliability.
The risk assessment should ccnsider mechanical (e.g., cue to aging, quality control, or design deficiencies), procedural (e.g., operations, tests or maintenance) and human errors. Where meaningful failure rate data is available, it should be identified and used to estimate overall reliability of the system.
The results of the risk assessment should be used by PGE to evaluate the effectiveness of various measures which could improve reliability. For example, what is the benefit of using alternative pump drivers, of converting the electric driven pumps to a third safety related pump, eliminating valves which could be mispositioned, of continually running the pumps or of starting the pumps earlier? PGE should identify and evaluate other potential modifications.
A a
(:
1 4
.sL]x,,
t.
Environmental Qualification of Equipment Purpose - To determine the ability of Trojan safety equipment to perform its function in an accident envircnment and to identify where changes would improve equipment reliability.
Discussion - During an accident equipment needed to mitigate the consequences of the accident must perform in an unusual environment of high temperatures, pressures, radintion levels, humidity and chemical conditicns.
PGE's Final Safety Analysis Report, NRC's Safety Evaluation Report and PGE's response to Bulletin 79-01 provides some information on the qualification of equipment; however, the information is either incomplete or has not been assembled in a cohesive presentation.
Information should include, but not be limited to, the follcwing:
1.
Justification of a) the choice of the accident environment, and b) tne selection of time periods during which equipment must remain operable (reference documents which can be reviewed to verify that all appropriate equipment and its location have been considered);
9 2.
Identify the environment that can be withstood by existing equipment and the time period during which equipment will remain operable; 3.
Justify the adequacy.of tests used to qualify equipment with particular emphasis on the duration of tests and the need for concurrent versus sequential testing for temperatures, pressure etc.;
and
~
4.
Identify the cost to replace or qualify Trojan equipment so that it will perform its functions during an accident.
ww
s
=
Control / Protective System Interactions Purcose - To identify, by use of risk assessment methodologies, whether changes to the existing Trajan control and protective systems would increase the reliability of these systems.
Discussion - In some cases at Trojan, control signals are derived frcm inoividual protection channels.
Isolation suplifiers are used to prevent failures in the control circuitry from adversely affecting the protection cb *ne ls (FSAR Secte 7.7.3.1).
At the Zion Nuclear Plant improper action by plant operators caused loss of both pcottc+ ion and oatrol functions. Trojan procedures provide cuct?c.* r pr 2c.de this type of event.
Nonetheless, it is apparent t.
- e. er ecview is needed to determine whether other adverse interact uns can occur.
Thc folion:og process parameters required for protective functions provide
, *o control systems: reactor power, pressurizer pressure, pressur izer level, steam generator level and average coolant temperature
,F5l.I 7.2.2.3).
PGE also identified four additional interactions:
turbine impulsa pressure, feed flow, steam flow and steamline pressure (PGE letter to 000E May 25, 1979). PGE should reference documents that could be checked to verify that all interactions have been identified.
000E believes that a risk assessment, utilizing f ault tree analysis, would provide the information needed to determine a) how the shared functions might be disadvantageous and b) where beneficial changes could be made.
The risk assessment should consider all failure methods incitJing mechanical, procedure and human errors for each of the previously identified process parameters. For example, isolation amplifiers should be analy.'d to determine how they could permit or cause adverse interaction; due to failure of components, improper maintenance or testing procedures, etc. Meaningful failure rate data should be used, when available, to estimate overall reliability of the existing arrangements.
The results of the risk asse1sment should be used to identify areas where improvement would be useful and to compare the alternative to the existing design. PGE should identify the costs of the potential improvements as well.
DG:cs 3521A Qs g }\\
4 m
h !I.1Kji.f7.Ih7 6 ti y
Q.., L u QN{h QN U d h
E7
.d y
's
.. ~. _. -
~.
_.. -.. ~....... _.