Letter Sequence Other |
|---|
TAC:08348, (Approved, Closed) TAC:11299, (Approved, Closed) TAC:12369, (Approved, Closed) TAC:13152, (Approved, Closed) TAC:8348, (Approved, Closed) |
Initiation
- Request, Request, Request, Request, Request, Request, Request, Request, Request
- Acceptance...
- Supplement, Supplement, Supplement
Results
- Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval
Other: 05000344/LER-1978-020, Forwards LER 78-020/03X-3, 05000344/LER-1978-020-03, /03L-0:on 780622,during Design Review for Piping Stress at Wall Penetrations,One Sys Was Found to Have Stress Exceeding Allowable Code.Caused by Design Error.Grouting Around Pipe Removed & Stress Reduced, ML19207C007, ML19209A322, ML19209A323, ML19209A336, ML19209A363, ML19209A432, ML19209A435, ML19209B063, ML19209B180, ML19209B241, ML19209D051, ML19209D056, ML19225A294, ML19241A963, ML19241A969, ML19241C194, ML19242B129, ML19242B972, ML19247B146, ML19248C628, ML19248C934, ML19249D678, ML19250C450, ML19253C727, ML19254D131, ML19254F178, ML19256F544, ML19256F546, ML19256F990, ML19256F993, ML19260C591, ML19261A687, ML19261D547, ML19261D820, ML19263E970, ML19267A290, ML19267A296, ML19269D190, ML19270E836, ML19270G402, ML19270H454, ML19271A997, ML19275A272, ML19282A785, ML19289C608, ML19289F192, ML19290C976, ML19294B198... further results
|
MONTHYEARML19268C2631966-10-31031 October 1966 Compressive & Transverse Strength Tests of 8-Inch Brick Walls. Addl Info Re Masonry Walls & Certificate of Svc Encl Project stage: Other ML19209A3631974-02-25025 February 1974 Burn Tests on Silastic Rubber-Coated Glass Drop Cloths. Prof Qualifications of Ew Edwards Encl Project stage: Other ML19256F5461974-06-30030 June 1974 Miscellaneous Paper C-74-12,Pullout Resistance of Reinforcing Bars Embedded in Hardened Concrete, Prepared by Engineer Waterways Experiment Station Project stage: Other ML20195C3451978-04-28028 April 1978 Informs That Structure of Walls in Control Bldg Does Not Meet Seismic Criteria for Sar.Reanalysis Confirms Control Bldg Will Maintain Structural Integrity & Plant Will Retain Functional Capability Under Design Loads Project stage: Other ML20195C3641978-05-26026 May 1978 Clarifies Items 2 & 3 of DG Eisenhut 780502 Memo Re Proposed Mod to Plant Spent Fuel Storage Rack Proceedings.Design Engineer Activities in Fuel Bldg Design Should Be Considered Supporting Role Project stage: Other ML18004B9711978-06-0202 June 1978 Addresses Pipe Support Base Plate Problem.Discusses Review of Support Redesigns & Capability of Anchor Bolts to Withstand Cyclic Loadings Project stage: Approval ML20195C3511978-06-29029 June 1978 Forwards Affidavits of CM Trammell & LC Shao Re Safety Significance of Control Bldg Design Deficiencies & NRC Findings Concerning Significant Hazards Considerations Project stage: Other ML20195C3851978-06-29029 June 1978 Affidavit of Chales M. Trammel,Iii.* Staff Concluded That an Amendment Authorizing Operation of Trojan Nuclear Power Plant Pending Upgrading of Seismic Capability of Control Bldg Walls Would Constitute a Decrease in Safety Margin Project stage: Other ML20195C4001978-06-29029 June 1978 Affidavit of LC Shao Re Control Bldg Design Errors Resulting in Substantially Weaker Walls than Intended by Original Design criteria.As-built Structure Has one-half of Seismic Capacity & Safety Margin Project stage: Other ML20195C3741978-06-30030 June 1978 Forwards Proposed Schedule of Actions to Bring Plant Control Bldg Into Substantial Compliance Ww/Requirements & Intended Design Margins.Detailed Description of Actions,Design Changes & Mods Will Be Submitted Prior to 780901.W/o Encl Project stage: Other 05000344/LER-1978-020-03, /03L-0:on 780622,during Design Review for Piping Stress at Wall Penetrations,One Sys Was Found to Have Stress Exceeding Allowable Code.Caused by Design Error.Grouting Around Pipe Removed & Stress Reduced1978-07-21021 July 1978 /03L-0:on 780622,during Design Review for Piping Stress at Wall Penetrations,One Sys Was Found to Have Stress Exceeding Allowable Code.Caused by Design Error.Grouting Around Pipe Removed & Stress Reduced Project stage: Other ML20195C4581978-08-19019 August 1978 Forwards NRC Questions & Licensee Responses,780804-17 Based on Info Provided by Bechtel Re Control Bldg.All Walls Except 1B,2 & 3 Have Dowel Capacities Exceeding Shear Capacities Controlled by Either Shear or Bending Project stage: Other ML20195C4621978-08-21021 August 1978 Forwards Final NRC Responses to Questions 6 & 10 Re Control Bldg Mods,Based on Info Provided by Bechtel.Equipment in Structure Should Continue to Be Capable of Resisting Seismic Loadings Resulting from Real Earthquakes Project stage: Other ML20195C5331978-08-22022 August 1978 Responds to Re Amendment Permitting Temporary Operation of Plant Independent of Public Hearing.Law Requires Hearing to Be Held in Connection W/Amend to OL Project stage: Other ML20150A6081978-08-30030 August 1978 Forwards Request for Addl Info Re Control Bldg Per Seismic Nonconformance Project stage: RAI ML20150A6141978-09-0101 September 1978 Forwards Preliminary Results of Stardyne Finite Element Analysis of Trojan Control-Auxiliary-Fuel Bldg Complex & Assessment of Seismic Load Resistance of Bldg as Presented at 780828 Meeting. Lic. NPF-1 Project stage: Meeting ML20195C1431978-09-0707 September 1978 Responds to Commissioner Davis Addressed to Commissioner Bradford & Expressing Concerns Re non-conformance to Specs of Control Bldg at Plant & Effect of Facility Shutdown on Rate Payers Project stage: Other ML20147C2411978-09-12012 September 1978 Forwards Corrected Supplementary Info Transmitted by Ltr Project stage: Supplement ML20150A6441978-09-20020 September 1978 Forwards Final Results of Rev & Evaluation of Recent Stardyne Finite Element Analysis for Existing Control Bldg of Subj Facil.Suppl Structural Evaluation Response to Specified SSE Event,& Response to Questions Encl Project stage: Other ML20150A6651978-09-20020 September 1978 Responds to Specified SSE Event.Stardyne Dynamic Analysis Was Used to Determine Structural Capacities & Forces. Concludes That Control Bldg Can Withstand SSE Event Safely Project stage: Other ML20150A6581978-09-21021 September 1978 Order Re Responses to NRC Interrogatories by Coalition for Safe Pwr & Consolidation.Cfsp Must:Respond W/In 14 Days to S1,S2,E1,G1,G2,G3,G8 & All Other Interrogatories;Clarify the Status of Spokesmen.Motion for Reconsideration Is Denied Project stage: Approval ML20062B9611978-09-28028 September 1978 Forwards 780628 Memo to R Mattson Re Info on Failures of safety-related Pipe Supports at Millstone 1 & Design Deficiencies on Similar Equipment at Shoreham.Aslb Notified of Pipe Support Base Plate Design Project stage: Approval ML20062A5471978-09-29029 September 1978 Notifies That Staff Is Unable to File Testimony on Interim Oper of Subj Facil Before 781013 Re Finite Element Analysis. Urges That ASLB Commence Hearing on 781018 or 781023 Project stage: Request ML20147E6401978-10-0303 October 1978 Transcript of SR Christensen Testimony Re Description of Seismic Instrumentation & Engineering Investigations to Be Conducted Following Earthquake Project stage: Other ML20147E6321978-10-0303 October 1978 Transcript of Dj Broehl Testimony Re Plant History, Chronology of Events Since Apr 1978 & Summary of Licensee Efforts to Ensure Safe Interim Operation of Control Bldg Project stage: Other ML20148A0601978-10-0606 October 1978 Direct Testimony of Harold Laursen Re Assignment to Eval Ability of Subj Facil Bldg Shear Walls to Resist Seismic Loading.Determined Shear Walls Can Withstand .25g Safe Shutdown Earthquake Project stage: Other ML20062C1421978-10-11011 October 1978 Notice of Evidentiary Hearing on Issue of Interim Operation & Limited Appearance.Hearing to Determine Whether Interim Operation Should Be Permitted Prior to Mods Required by Order Will Be Held on 781023 & 1030-1101 Project stage: Other ML20062B2821978-10-13013 October 1978 Testimony Describing Insp of Humboldt Bay Following 5.4 Richter Magnitude Earthquake on 750609 & Std Insp Procedures After Seismic Event.Procedures to Be Followed During Earthquake Detailed Project stage: Other ML20062B2861978-10-13013 October 1978 Testimony Responding to ASLB Questions Re Effects of Seismic Event on Plant Features Important to Maintaining Safety of Facility.Certificate of Svc Encl Project stage: Other ML20148C0251978-10-13013 October 1978 Responds to NRC 781011-13 Questions Re Supplemental Structural Evaluation of Control Bldg,Particularly Shear Wall Capacity.Certificate of Svc Encl Project stage: Supplement ML20062B2791978-10-13013 October 1978 Testimony Verifying That Reasonable Assurance Exists That Shear Walls Will Withstand SSE or Obe.Original Intended Margins of Safety Reduced & Should Be Restored Project stage: Other ML20062B2751978-10-13013 October 1978 Forwards Ks Herring Testimony on Structural Adequacy of Trojan Control Bldg for Interim Operation & RT Dodds & Je Knight Testimony on Seismic Features Relevant to Facility Safety Project stage: Other ML20062B4191978-10-16016 October 1978 Forwards Ks Herring Testimony Re Suppl to Stardyne Analysis & Effect on Structural Capacity of Control Bldg.Certificate of Svc Encl Project stage: Other IR 05000344/19780201978-10-16016 October 1978 IE Inspec Rept 50-344/78-20 on 780905-29 During Which No Items of Noncompliance Were Noted.Major Areas Inspec Incl: Plant Opers,Maint,Surveillance Test,Facil Security & Licensee Event Followup Project stage: Request ML20147F0961978-10-16016 October 1978 Licensees Testimony on Capability of Subj Facil to W/Stand Seismic Events.Statements of Qualifications,Ref & Append Are Attached.Description of Affected Structure & Deficiencies Such as Amount & Arrangement of Reinforcing Steel Provided Project stage: Other ML20147F0891978-10-16016 October 1978 Testimony of Bart Withers,As Superintendent of Subj Facil W/Statement of Qual Attached.Describes Capability of Plant to Function & Plant Staff to Respond Properly Immediately Following a Seismic Event Project stage: Other ML20062B4251978-10-17017 October 1978 Testimony Re Suppl to Stardyne Analysis & Effect of Structural Capacity of Control Bldg.Structure Can Withstand SSE & Less Severe Obe,But Suppl Info Alters Earthquake Level Requiring Plant Insp Project stage: Other ML20062B9591978-10-19019 October 1978 Forwards Recent Memoranda Re Certain Problems Experienced in Connection W/Pipe Support Base Plate Design.Staff Determining If Problems Have Generic Implications for Operating Facilities.Aslb Will Be Kept Informed Project stage: Other ML20062C6271978-10-27027 October 1978 Forwards Further Response to NRC Staff Tech Questions Re Stardyne Analysis & Review.Includes Description of Criteria & Procedures Used & Explanation of Dev of New Acceleration time-history.Cert of Svc Encl Project stage: Other ML20062D3481978-11-0606 November 1978 Cross-examination or Testimony Re Analysis & Review by Licensee Poge of safety-related Matls in Control-Auxiliary- Fuel Bldg Complex Will Be Taken at 781211 Hearing.Nrc Given Time to Reply to Interrogs.Proposed Findings Due 781120 Project stage: Other ML20197D4691978-11-22022 November 1978 Forwards Suppl Document Supporting Floor Response Spectra Provided in 781027 & 781102 Submittals to NRC in Response to Request for Additional Info Project stage: Request ML20197D4801978-11-22022 November 1978 Forwards Suppl Documentation in Support of Floor Response Spectra Provided in 781027 & 781102 Responses to NRC Info Requests.W/Cert of Svc Encl Project stage: Other ML19305A0701978-12-11011 December 1978 Limited Appearance Statement by Rd Pollard of Ucs to Explain the Kind of Inquiry Possible,Yet Untapped,W/Respect to Any Person of Pollards Competence & Commitment in Field of Nuclear Plant Licensing Project stage: Other ML19305A0631978-12-18018 December 1978 Forwards Limited Appearance Statement by Rd Pollard of Ucs. W/Encls Project stage: Other ML19270E8361978-12-21021 December 1978 Partial Initial Decision Re Whether Operation of Facility Should Be Permitted in Spite of Identified Design Deficiencies in Control Bldg & Prior to Mod.Decision Is to Allow Interim Operation Project stage: Other ML19267A2961978-12-22022 December 1978 Amend 35 to License NPF-1.Modifies Waiver Portions of Tech Specs & FSAR Criteria Which Have Not Been Followed Due to Design Deficiency in Control Bldg Shear Walls Project stage: Other ML19267A3021978-12-22022 December 1978 Notice of Issuance of Amend 35 License NPF-1 Project stage: Approval ML19267A2901978-12-22022 December 1978 Forwards Partial Initial Decision,Amend 35 to License NPF-1 & Notice of Issuance Project stage: Other 05000344/LER-1978-020, Forwards LER 78-020/03X-31978-12-26026 December 1978 Forwards LER 78-020/03X-3 Project stage: Other ML19308A2121978-12-26026 December 1978 Reportable Occurrence on 780622: Piping Penetrations Not Designed to Be Solidly Grouted Were Found to Be Solidly Grounted.During Subsequent Design Review,Excessive Support or Pipe Stresses Found on 11 Isometrics. Probable DELETE-RO Project stage: Other 1978-12-26
[Table View] |
Text
..A.
INTIED STATES OF AMERICA d IE / s NUCLEAR REGUIEIORY 01NISSIN
$\\jIN I
[
C THE AItHIC SAFE 1Y AND LICENSIBU BOARD d
96 e
@a **M Marshall E. Miller, Esquire, Chairman Dr. Kenneth A. McCollcxn, Mmber 9
'M' p
Dr. Hugh C. Paxton, Mmber g
iA In the Matter of
)
)
POKrIAND GENERAL ELECTRIC CWPANY, et al.
)
Docket No. 50-344
)
(Trojan Nuclear Plant)
)
(Ccntrol Building)
MIFICATION OF ORDER PERMITTING INIERIM OPERATION OF TRQIAN NUCLEAR FIANT (Novsber 30, 1979)
By an Order contained in our Partial Initial Decision following evidentiary irarings in Phase I of this proceeding, interim operation of the Trojan Nuclear Plant was permitted subject to certain specified conditions and modifications of Facility Operating License No. NPF-1 (8 NRC 717, at 747-48). Thereafter the Board attspted to establish a schedule for the empletion of discovery and other matters leading to the expeditious ccnmencment of an evidentiary hearing on Phase II, dealing with the scope and timeliness of modifications required to bring the Control Building and the facility into substantial conpliance with the license, from a safety standpoint.N The Board's persistent efforts to ccnduct an evidentiary hearing on Phase II have been frustrated by the failure of the Staff to emplete its Safety Evaluation Report (SER). The Staff, in turn, has attributed its failure to file an SER to N ee the Board's Orders dated January 30, March 8, April 12, June 5, July 26, S
August 2, Sept aber 18, October 11, and October 17, 1979.
1534 532 h
7912120 b
. the failure of the Licensee to supply in full all information requested by the Staff regarding the proposed modifications to the Control Building (Orders dated Septaber 18, October 11 and October 17,1979).
The Board is concerned that there were safety related pipes and corresponding supports and restraints in the Trojan Building cmplex that were not analyzed to determine whether they were adequate to meet design basis conditicns during interim operation. The Board's Partial Initial Decision allowing interim operation assumed that all safety related equipment had been checked to assure its ability to withstand a Safe Shutdown Earthquake (SSE).
It is now apparent that this had not been done.
This, in turn, has caused the Board to reevaluate the extended length of time it has taken the Staff to cmplete the SER on nodifications to strengthen the walls in the Control Building. From the weekly reports to the Board, it is very difficult to tell what progress is being made toward coupleting the SER.
Essentially, no quantitative inforantion is being given in these weekly reports.
Although the Board was not directly and clearly so informed by the Licensee or the Staff, it appears that the Trojan facility is presently shut down and is not operating.
In response to a telephone call placed by the secretary of the Board chairman to Staff counsel an Novenber 28, 1979, we were informed orally that the Trojan facility has not gone back into operation, that operation would not resme until the Licensee had resolved a problen regarding the ability of certain thin block walls to resist earthquake-generated reaction forces, and that the IEC Division of Inspection and Enforement will not allow operation until this probl e is resolved.
1534 333
. This problem of the adequacy of certain thin block walls (non-shear walls) to resist the earthquake-generated reaction forces from equipnent or piping attached to such walls, was first mentioned in a rather limited way in the Staff's weekly report to the Board dated October 26, 1979. The matter was briefly alluded to in Staff reports dated November 9 and 16. However, a Stumary of Meeting Held on October 26, 1979, prepared on Novmber 8,1979 by Mr. C. M. Tranmell, Project Manager, was received by the Board on Novaber 16, 1979. This stnmary indicates song other things that on October 12, 1979, the Trojan facility was shut down to repair primary-to-secondary leakage in the A and D stean generators, and to conduct an inspection of piping supports in inaccessible areas as reqyired by IE Bulletin 79-14. There was also some discussion of the problem with certain walls.
A detailed report dated Nov mber 13, 1979, entitled Newly Discovered Problems With Reaction Forces On Certain Concrete Block (Non-Shear) Walls at Trojan, was furnished to the Board and parties. At page 4, it was stated:
"In any event, as indicated in the NRC's imwlimte action letter of October 22, 1979, any necessary investigations and corrective actions uust be completed prior to any resunption of operation."
It appears that persmnel of the NRC Office of Inspection and Enforement are performing their responsibilities regarding investigation of the wall problem and corrective action required to resolve it. However, that is not the end of the matter as frr as the Licensee is concerned. We regard this Board as having continuing jurisdiction and responsibilities over the Trojan control building design errors and resulting seismic capability and safety margins. The bifurcation of Phase I and Phase II evidentiary hearings was a matter of convenience in handling different types of issues expeditiously but there was no loss of jurisdiction by the Board between these two phases of evidentiary hearings. Moreover, it was 1534 234
. never contenplated that interim operation of the plant would be unduly prolonged before modification plans were completed and sulxnitted to the Staff for safety evaluation, and to the Board for an adjudication of their adequacy frcm a safety standpoint. Accordingly, it is hereby Ordered as follows:
1.
Operation of the Trojan nuclear facility shall not be resumed pending further order of this Licensing Board.
2.
The Staff shall 1-Mntely inform the Board, explicitly and clearly, what unresolved problens renain which might have a bearing upon the seismic and other issues in this proceeding.
This information shall be kept current upon a regular basis.
3.
'Ihe Licensee shall imnediately render a full written report to the Board as to the status of all informatirn requested of it by the Staff and not fully supplied to the Staff's satisfaction.
Current and updated information as to the wall problem and any other matters which might affect the issues in this proceeding shall also be furnished upon a regular basis.
4.
The Staff shall furnish a date reasonably anticipated for the ccrapletion and filing of its SER, and a full justification and explanation for any further slippage in that regard.
5.
All parties shall state and docunent their views as to how long interim operation of the Trojan facility should be permitted, in the absence of the sulxnission of firm plans for control room 1534 335
. modifications, adequate frm a safety standpoint to brirg the facility into substantial cmpliance with the license.
It is so ordered.
ETR DE AIUiIC SAFEIY AND LIGIEING BOARD Oh ah b/
Mars ull E. Miller, Ch, m'n Dated at Bethesda, Maryland this 30th day of Novmber 1979.
1534 336