ML19241B438

From kanterella
Jump to navigation Jump to search
Submits Estimate of Time Required to Complete Power Ascension Program.Requests Removal of 70% Power Restraints Due to Increased Peak Power Demand
ML19241B438
Person / Time
Site: Fort Saint Vrain 
Issue date: 07/09/1979
From: Warembourg D
PUBLIC SERVICE CO. OF COLORADO
To: Kuzmycz G
Office of Nuclear Reactor Regulation
References
P-79147, NUDOCS 7907170156
Download: ML19241B438 (1)


Text

w public Service Company f Odondo O

a P. O.

Box 361, Platteville, Colorado 80651 i i

, L July 9,19 79 Fo r t S t.

Vrain Unit No. 1 P-79147 3

Mr. George Kuzmycz Project Manager, Special Projects Division of Project Management U. S. Nuclear Regulatory Commission Washington, D.C.

20555 l

Docket No. 50-267

SUBJECT:

Power Ascension Program

Dear Mr. Kuz=ycz:

As per your request, the following is our estimatio'1 of the time required to complete testing and obtain 70% of rated power. The plant has been up to 11% power.

At the present time load has been reduced to 2% power to effect repair on two leaking valve-I* is anticipated that repairs will be completed by July 12, 1979. Ass Jng testing and power ascension af-ter the valve repair proceeds as planned, the plant will obtain 40% power by July 20,1979, and 70% power by July 23, 1979.

At that time, unless the Commission releases the plant from 70% hold, we will maintain 70% power.

To the best of our knowledge all Nuclear Regulatory Co= mission imposed 70%

res traints have been resolved.

The fluctuation test program (RT-500E) es-tablishes procedures and imposes restrictions for exceeding 70%. We would propose to cocply with the requirements and restrictions i= posed by RT-500E.

We would appreciate it if the Co=micsion would consider removing all pre-vious 70% hold restrictions and rel. ease us to tes t under RT-500E, both be-low and above 70% power predicated, of cnurse, on the fluctuation test re-sults below 70% power.

This request is based on the seriousness of our system capability to meet this summer's peak demand.

The foreccs ted peak demand for July is 2,69 7 W, and Auguet's is 2,5 75 W, while c,ur available sys tem generating capability includ!ng Fort St. Vrain's 200 W and firm purchases f rom other sources only leaves a spinning reserve of 30 and 152 MW for July and August, respectively.

Your pronpt attention in this matter will be appreciated.