Forwards Proposed Equipment Setpoint Methodology Program Plan,Per Cj Bosted Request.Proposed Program Manpower Intensive & Will Probably Require Participation & Support of Supply Sys Technical Support Svcs Contractor
ML17285A672
Person / Time
Site: Columbia Energy Northwest icon.png
Issue date: 08/02/1989
From: Sorensen G
WASHINGTON PUBLIC POWER SUPPLY SYSTEM
To: Martin J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
References
GO2-89-134, NUDOCS 8908180218
Download: ML17285A672 (7)


Text

gc CE~RATED DI~BU'n ON DE MON STRlIION SYSTEM REGULATORY INFORMATION DISTRIBUTION SYSTEM (RIDS)

ACCESSION NBR:8908180218 DOC.DATE: 89/08/02 NOTARIZED: NO DOCKET FACIL:50-397 WPPSS Nuclear Project, Unit 2, Washington Public Powe 05000397 AUTH. NAME AUTHOR AFFILIATION SORENSEN,G.C. Washington Public Power Supply System RECIP.NAME RECIPIENT AFFILIATION MARTINiJ.B. Region 5, Ofc of the Director

SUBJECT:

~ Forwards proposed equipment setpoint methodology program plan,per CJ Bosted request.

DISTRIBUTiON CODE: IE01D COPlES RECEIVED:LTR ENCL SIZE:

TITLE: General (50 Dkt)-Insp Rept/Notice of Violation Response NOTES:

RECIPIENT COPIES RECIPIENT COPIES ID CODE/NAME LTTR ENCL ZD CODE/NAME . LTTR ENCL PD5 1 1 SAMWORTH,R 1 1 h AEOD 1 PD'NTERNAL:

ACRS 2 2 1 AEOD/DEIIB 1 1 AEOD/TPAD 1 1 DEDRO 1 1 NRR SHANKMANiS 1 1 NRR/DEST DIR 1 1 NRR/DLPQ/PEB 1 1 NRR/DOEA DIR 11 1 1 NRR/DREP/EPB 10 1 1 NRR/DREP/RPB 10 2 2 NRR/PMAS/ILRB12 1 1 NUDOCS-ABSTRACT 1 1 OE XZ~MANi J 1 1 OGC/HDS2 1 1 02 1 1 RES MORISSEAU,D 1 1 RGNS FILE 01 1 1 EXTERNAL: LPDR 1 1 NRC PDR 1 1 NSZC 1 1 D

D NOIR 'ZO ALL RIDS" RECIPIERIS'ZZASE S

HELP US IO REDUCE RASTE CGHFACT 'XHE DOCUMERI CONTROL DESK I RXN Pl-37 (EXT. 20079) K) XZJMQCLXR YOUR NAME PKH DZSTEGSPZZQH LISTS FOR DOCUMEÃZS YOU DOHiT NEED)

TOTAL NUMBER OF COPIES REQUIRED: LTTR 25 ENCL 25

WASHINGTON PUBLIC POWER SUPPLY SYSTEM ~

P.O. Box 968 ~ 3000 George Washington Way ~ Richland, Washington 99352 August 2, 1989 j ~

~ r G02-89-134 C i Docket No. 50-397

~

Mr. 'J. B. 'Martin Regional Administrator U. S. Nuclear Regulatory Commission Region V 1450 Maria Lane, Suite 210 Walnut Creek, CA 94596

Dear Mr. Martin:

Subject:

NUCLEAR PLANT NO. 2 OPERATING LICENSE NPF"21 WNP-2 EQUIPMENT SETPOINT METHODOLOGY PROGRAM PLAN At the request of C. J. Bosted, Resident Inspector, attached hereto is the pro-posed WNP-2 Equipment Setpoint Methodology Program Plan. The Supply System has been working on this plan for several months. The methodology was originally targeted to be complete in draft form by April 1989, but was delayed in order to allow consideration of recently published ISA-RP67.04, Part II draft (4/ll/89).

The proposed program is very manpower intensive, and will probably require the par ticipation and support of the Supply System's Technical Support Services Contractor. That Contractor is scheduled to be selected and functional the first quarter of CY 1990. As the program is evolving and based on a draft ISA standard, we anticipate that changes will become necessary as information is gained. The dates included herein are tentative and will have to be adjusted to also reflect manpower avai 1 abi 1 i ty.

The Supply System requests that the NRC communicate any questions and/or concerns they may have as soon as practicable.

G. C. Sorensen, Manager

. Regulatory Programs HLA/bk cc: Document Control Desk - NRC NS Reynolds BCP8R RB Samworth - NRC DL Williams - BPA/399 NRC Site Inspector 901A 8908k 80218 890802 PDR ADOCK 05000397 P

PNU

MNP-2 EQUIPMENT SETPOINT METHODOLOGY PROGRAM PLAN

1.0 BACKGROUND

During the SSFI audit conducted in August 1987, NRC reviewers identified that existing WNP-2 setpoint methodology did not include consideration of service environment (normal and accident) effects on instrument setpoint accuracies. The Supply System acknowledged this fact but indicated that calculational conservatism offset any effects of environment. Additional-ly, preliminary investigations concluded that many safety related instruments accomplished their intended safety function prior to being affected by abnormal environments.

The Supply System had previously submitted the WNP-2 setpoint methodology to the NRC in May 1985 (Docket Lett'er G02-85-238) and requested in August, 1987 that the NRC approve that methodology. The NRC responded with an SER in November 1988 providing acceptance 'of the WNP-2 'methodology recognizing that it did not yet include environmental/seismic influence criteria. This methodology will become the basis for all WNP-2 setpoint calculations along with new guidance provided by ISA.

2.0 SCOPE The setpoint program shall'ddress and resolve the following issues:

2.1 E ui ment to be Included in the Pro ram The program shall address the following equipment types:

a. Instrumentation to include mechanical switches, electronic switches, analog control setpoints and analog transducers.
b. Electrical equipment to include time delay relays, solid state undervoltage relays and limit/position switches not within the NOVATS program scope.

Mechanical equipment, including relief valves, is not within this program scope.

2.2 Safet Related Yersus Non-Safet Related E ui ment The program shall address all safety related equipment requiring setpoints irrespective of whether that equipment is identified specifically in the Technical Specifications or not. Additionally, non-safety related equipment actuating annunciators which require the Operators to enter into or control within an Emergency Procedure shall also be included within the setpoint program. Although not required, other non-safety related equipment may also benefit from implementation of the program methodology.

2.3 Environmental/Seismic Effects on E ui ment Set pints The program shall provide the meth'odology and application of that methodology for adjustment of equipment setpoints to include effects of environment/seismic resultant inaccuracies.

2.4 Safet Function Com letion Time To minimize the necessity for field setpoint adjustment, the program shall include analysis taking credit for equipment safety function completion time and its relation to the time at which environment/seismic effects "become affecting. This may reduce the number of existing setpoints requiring change'.

2.5 Set oint Calculation Consolidation The program shall addres~ nsolidation of Plant Technical ISCR's and Engineerl'ng calculations into a single calculation per EPN.

2.6 Current Industr Practice The program shall address current industry/ISA methodology and investigate application to WNP-2.

3.0 PROGRAM MILESTONE ELEMENTS 3.1 Industry Methods Investigation 3.2 Formulation of WNP-2 Methodology 3.3 NRC staff approval (verbal approval is sufficient) 3.4 List of equipment requiring setpoint calculations, by EPN, including-analysis to reduce list, where possible by identifying that equipment

.which performs its safety function prior to effects of environmental conditions.

3.5 Determine environmental and seismic accuracy effects for each EPN.

3.6 Determine if qualification tests are required for equipment without required environmental or seismic accuracy data.

3.7 Consolidate Setpoint Calculations 3.8 Provide Setpoint Calculations 3.9 Recalibration of Equipment

4. 0 MILESTONES/RESPONSIBILITIES/SCHEDULES The organizations/departments listed below are responsible for completing the following program scope elements within the scheduled completion dates.

4.1 Methodolo Determination Considerin Sco e Elements

a. Review indu'stry methods including April 1989 ISA draft for application to WNP-2.

Responsible Or ganization - Generation Engineering, Electrical/18C Systems Task Completion Date: August 4, 1989

b. Formulate I&C/Electrical equipment methodology.

Responsible Organization - Generation Engineering (with input from Plant Technical and Equipment Engineering) Electrical/18C Systems.

Task Completion Date: September 1, 1989.

c. Assemble methodology and issue associated Engineering Standard.

Responsible Organization - Generation Engineering, Electrical/18C Systems Task Completion Date: November 1, 1989.

4,2 NRC Staff A royal Provide NRC (NRR) staff WNP-2 methodology for review.

Responsible Organization - Licensing Task Completion Date: November 1, 1989 4.3 E ui ment Identification

a. List of equipment requiring setpoint calculations.

Responsible Organization - Generation Engineering, Electrical/

18C, Mechanical and Nuclear Systems Task Completion Date: March 1, 1990

b. Perform safety analysis to indicate safety function completion times for equipment located in harsh environments.

Responsible Organization - Generation Engineering, Electrical/IBC Systems with review by Mechanical and Nuclear Systems Task completion Date: May 1, 1990

4.4 Environmental/Seismic Accuracy Effects Responsible Organization - Generation Engineering with aid (if required) by Equipment Engineering I

Task Completion n~>>: July 1, 1990

(}uglification Test Determination and Retest Responsible Organization - Equipment Engineering Task Completion Date: To be determined.

4.6 Consolidate/Reconcile Set oint Calculations Identify equipment with existing multiple setpoint calculations and supercede as appropriate (including ISCR's).

Responsible Organization - Generation Engineering, Assigned System Engineers and Plant Technical Task Completion Date: September 1, 1990 4.7 Set oint Calculations Responsible Organization - Generation Engineering, provide setpoint calculations, Assigned System Engineers Plant Technical to review and revise Haster Data Sheets Task Start Dat'e: July 1, 1990 (Focus on Technical Specification equipment to support implementation of the improved Technical Specifica-tion submittal.) V Task Completion Date: December 1, 1991 4.8 Recalibration of E ui ment Responsible Organization - Plant Technical/Haintenance Task Completion Date: December 1, 1992