MONTHYEARML20217K9681999-10-19019 October 1999 Ack Receipt of Transmitting Rev 40 to Physical Security Plan for Washington Nuclear Plant 2.Based on Determination That Changes Do Not Decrease Effectiveness of Plan,No NRC Approval Required ML17284A8981999-10-14014 October 1999 Forwards Rev 0 to WNP-2 Cycle 15,COLR 99-15, IAW Requirements of TS 5.6.5 ML17284A9061999-09-24024 September 1999 Forwards Final Rept for 990812 out-of-sequence Drills for Energy Northwest Washington Nuclear Power Project 2 (Lab, Food Control Point & Milk Sampling).No Deficiences & No Areas Requiring C/A Identified in Three Drills ML17284A8881999-09-24024 September 1999 Informs NRC of Change in Schedule Pertaining to Final Implementation of Reactor Stability long-term Solution for WNP-2 ML17292B7591999-09-24024 September 1999 Forwards Rev 24 to WNP-2 Emergency Plan,Iaw 10CFR50.4(b), 50.54(q) & 10CFR50 App E.Detailed Synopsis of Changes,Encl ML17292B7581999-09-22022 September 1999 Forwards NRC Forms 396 & 398 for Nl Hancock,License SOP-50027-3,AR Herrington,License OP-50013-3,WH Sawyer, License SOP-50023-3 & Dl Strote,License SOP-50031-3,for Renewal of Licenses.Without NRC Forms 396 & 398 ML17284A8811999-09-0909 September 1999 Forwards Response to NRC 990623 RAI to Support Review of Pending Request for Amend to Reactor pressure-temp Limit Curve TS GO2-99-168, Forwards Rev 40 to Physical Security Plan.Rev Withheld,Per 10CFR2.790(a)(3)1999-09-0808 September 1999 Forwards Rev 40 to Physical Security Plan.Rev Withheld,Per 10CFR2.790(a)(3) ML17284A8711999-08-30030 August 1999 Informs Staff of Errors in world-wide-web Database Related to WNP-2 Reactor Vessel Structural integrity.Marked-up Pages Containing Errors or Omissions Will Be Forwarded by 991201 ML17284A8751999-08-30030 August 1999 Provides Correct Page from License NPF-21 Marked to Show Rev Addressed in 990729 Application for Amend,Which Included Page That Was Inadvertently Included as Attachment 4.Replace Attachment 4 with Attached Page & Disregard Attachment 5 ML17284A8721999-08-30030 August 1999 Forwards Proprietary Info to Support Review of Request for Amend to License NPF-21,re Min Critical Power Ratio Safety Limits Tss,As Requested During 990816 Conversation. Proprietary Encl Withheld ML17292B7531999-08-24024 August 1999 Requests That Eleven Individuals Listed Below Take BWR Generic Fundamentals Examination to Be Administered on 991006 ML17292B7511999-08-24024 August 1999 Forwards Fitness for Duty (FFD) Semiannual Performance Data Rept for Jan-June 1999,per 10CFR26.71(d) ML17284A8701999-08-19019 August 1999 Forwards NRC Form 396, Certification of Medical Exam by Facility Licensee & NRC Form 398, Personal Qualification Statement - Licensee, for Jd Prescott (License SOP-50262-1).Without Encls ML17292B7501999-08-19019 August 1999 Informs Staff That Licensee Has Completed Review of NRC SER for B&Wog Util Resolution Guidance Document Addressing ECCS Suction Strainer Blockage ML17284A8681999-08-12012 August 1999 Submits Two ISI Program Plan Relief Requests for NRC Review & Approval,Per 10CFR50.55a(a)(3)(i).Proposed Alternatives Provide Acceptable Level of Quality & Safety ML20211A9501999-08-12012 August 1999 Discusses 990720-21 Workshop Conducted in Region IV Ofc,Re Exchange of Info in Area of Use of Risk Insights in Regulatory Activities.List of Attendees,Summary of Topic & Issues,Agenda & Copies of Handouts Encl ML20210L1461999-08-0303 August 1999 Informs That NRC Plans to Administer Gfes of Written Operator Licensing Exam on 991006.Requests Submittal of Ltr Identifying Individuals Taking Exam,Personnel Allowed Access to Exams & Mailing Address for Exams ML17284A8541999-08-0202 August 1999 Forwards Proprietary Addl Info to Support Review of Pending Request for Amend to MCPR Safety Limit Ts.Info Consists of Proprietary Ltr from Abb Combustion Engineering,Inc.Encl Withheld ML17284A8531999-07-30030 July 1999 Forwards Estimate of Number of Licensing Action Requests Planned for Submittal in Future,As Requested in Administrative Ltr 99-02.Twenty-nine Submittals Scheduled for Fy 2000 & Four for Fy 2001 ML17284A8301999-07-22022 July 1999 Clarifies Change of Licensee Name from Wpps to Energy Northwest & Change of Facility Name from Wppss Nuclear Project Number 2 to WNP-2,as Requested in 990719 Telcon with Js Cushing of NRC.Marked-up OL Pages,Encl ML17292B7451999-07-20020 July 1999 Forwards Rev 23 to WNP-2 Emergency Plan,Iaw 10CFR50.4(b) & 50.54(q) & 10CFR50 App E.Rev 23 Provides Updated Description Re Establishment of Separate Emergency Operation Centers for Benton & Franklin Counties ML17292B7391999-07-16016 July 1999 Submits Withdrawal of Request for Amend to Secondary Containment & Standby Gas Treatment Sys Ts.Util Currently Plan to re-submit Amend Request in Entirety by 991112 ML17292B7381999-07-12012 July 1999 Forwards NRC Form 396 & NRC Form 398,for If Sumsion,License OP-50487 & Ga Westergard,License SOP-50415 for Renewal of Operator Licenses.Without Encls ML17292B7171999-07-0606 July 1999 Provides Notification of Early Completion on 990630 of Exception Noted in 990629 Ltr.Equipment within Scope of GL 98-01,Suppl 1, Y2K Readiness of Computer Sys at Nuclear Power Plants, Evaluated & Y2K Ready ML17292B7181999-07-0202 July 1999 Responds to 990623 RAI to Support Review of Evaluation of Planar Indication Found on Weld Number 24RRC(2)A-1 During 1998 RO ML17292B7161999-06-30030 June 1999 Forwards Addl Info Requested in 990513 Ltr to Support Review of Pending Response to GL 95-07, Pressure Locking & Thermal Binding of Safety-Related Power Operated Gate Valves. ML17292B7131999-06-29029 June 1999 Forwards Response to NRC GL 98-01,Suppl 1, Y2K Readiness of Computer Sys at Npps. ML17292B7091999-06-21021 June 1999 Forwards Proprietary Response to NRC 990603 RAI Re Licensee Request for Amend to MCPR Safety Limit Tss.Proprietary Info Withheld IAW Requirements of 10CFR2.790 ML17292B7041999-06-17017 June 1999 Forwards NRC Forms 396 & 398 for Three Individuals Listed Below for Renewal of Operator Licenses.Without Encls ML17292B7031999-06-10010 June 1999 Forwards Response to NRC 990511 RAI Re License Request for Amend to Secondary Containment & SGTS Tss.Results of Addl Benchmark of Gothic Computer Code Performed to Demonstrate Modeling Capability of Drawdown Response,Encl ML17292B6841999-06-0404 June 1999 Forwards Response to NRC 990326 RAI Re WNP-2 GL 96-05 Program for Periodic Verification of design-basis Capability of MOVs ML17292B6851999-06-0101 June 1999 Forwards 1999 Quality Audit of WNP-2 Emergency Preparedness Program, Per NUREG-0654,Section Ii,Criteria P.9.Seven Problem Evaluation Requests & Nine Recommendations for Improvement Were Issued as Result of Audit Activities ML17292B6831999-05-25025 May 1999 Informs That Request for NRC Approval of Changes to Emergency Plan Requesting Reduction in on-shift HP Staffing, Is Retracted.Util Will Resubmit Request with Required Addl Info at Later Date ML17292B6751999-05-25025 May 1999 Forwards Proprietary ABB-CE Ltr Re WNP-2 Cycle 15 SLMCPR & Core Reload Design Rept,Per Util Request for Amend Re MCPR Safety Limits.Proprietary Info Withheld,Per 10CFR2.790 ML20206U4501999-05-19019 May 1999 Ack Receipt of Which Transmitted Rev 39 to Physical Security Plan,Per 10CFR50.54(p).No NRC Approval Is Required,Since Changes Do Not Decrease Effectiveness of Security Plan ML17292B6661999-05-0707 May 1999 Requests Exemption to Requirement in 10CFR55.59(a)(2) Re Annual Operating Test requirements.One-time Exemption from Requirement to Period Not to Exceed 15-months from Last Date of Passing Operating Exam for Licensee at Facility ML17292B6531999-05-0303 May 1999 Forwards Response to NRC 990402 RAI Re Licensed Operator Positive Drug Test.Encl Withheld,Per 10CFR2.790 ML17292B6561999-04-29029 April 1999 Forwards Rev 0 to Calculation ME-02-98-04, Fracture Mechanics Evaluation of N1 Safe End & Calculation Mod Record CMR-98-0243, Fracture Mechanics Evaluation of N1A Nozzle Safe End, as Suppl Info to ISI Exam ML17292B6421999-04-19019 April 1999 Responds to NRC 990319 Ltr Re Violations Noted in Insp Rept 50-397/99-01.Corrective Actions:Provisions Are Presently in Place to Maintain Adequate Level of Security GO2-99-073, Forwards Rev 39 to WNP-2 Physical Security Plan,Per 10CFR50.54(p).Changes Do Not Decrease Effectiveness of Approved Plan.Encl Withheld IAW 10CFR73.21 & 10CFR2.7901999-04-19019 April 1999 Forwards Rev 39 to WNP-2 Physical Security Plan,Per 10CFR50.54(p).Changes Do Not Decrease Effectiveness of Approved Plan.Encl Withheld IAW 10CFR73.21 & 10CFR2.790 ML17292B6401999-04-13013 April 1999 Requests That WNP-2 Operator Requalification Program Be Granted one-time Extension Beyond Requirement in 10CFR55.59(a)(2) for Annual Operating Tests ML17292B6371999-04-12012 April 1999 Forwards Response to NRC 990211 RAI Re Util Request for Amend to Secondary Containment & SBGTS TS ML17292B6281999-04-0606 April 1999 Informs NRC That Insp Interval Ending Date for ISI Program Plan Has Been Extended by One Year to Dec 12,2005 Due to Changes in Plant Refueling Outage Schedule ML20196K6961999-03-30030 March 1999 Ack Receipt of ,Transmitting Rev 38 to Physical Security Plan for Plant.No NRC Approval Is Required,In Accordance with 10CFR50.54(p) GO2-99-060, Submits Rept of Status of WNP-2 Decommissioning Fund as of 981231,IAW 10CFR50.75(f)(1)1999-03-26026 March 1999 Submits Rept of Status of WNP-2 Decommissioning Fund as of 981231,IAW 10CFR50.75(f)(1) ML17292B6131999-03-24024 March 1999 Forwards Rev 0 to Calculation ME-02-98-04, Fracture Mechanics Evaluation of N1 Nozzle Safe End. Info Will Be Used to Assist NRC in Review of WNP-2 ISI Activities Associated with Evaluation of Planar Indication ML20204F0261999-03-19019 March 1999 Forwards Insp Rept 50-397/99-01 on 990201-04 & 0303-05.No Violations Noted.Areas of Physical Security Plan Effectively Implemented with Listed Exceptions ML17292B6001999-03-16016 March 1999 Responds to Weakness Noted in Insp Rept 50-397/98-24. Corrective Actions:Developed Document to Identify Areas Needing Improvement,Assigned Responsibility for Actions & Provided Milestones for Achievement ML17292B5941999-03-16016 March 1999 Forwards NRC Form 396, Certification of Medical Exam by Facility Licensee, & NRC Form 398, Personal Qualification Statement - Licensee, for MD Comstock,Mc Naulty & RR Nelson.Without Encls 1999-09-09
[Table view] Category:INCOMING CORRESPONDENCE
MONTHYEARML17284A8981999-10-14014 October 1999 Forwards Rev 0 to WNP-2 Cycle 15,COLR 99-15, IAW Requirements of TS 5.6.5 ML17284A9061999-09-24024 September 1999 Forwards Final Rept for 990812 out-of-sequence Drills for Energy Northwest Washington Nuclear Power Project 2 (Lab, Food Control Point & Milk Sampling).No Deficiences & No Areas Requiring C/A Identified in Three Drills ML17292B7591999-09-24024 September 1999 Forwards Rev 24 to WNP-2 Emergency Plan,Iaw 10CFR50.4(b), 50.54(q) & 10CFR50 App E.Detailed Synopsis of Changes,Encl ML17284A8881999-09-24024 September 1999 Informs NRC of Change in Schedule Pertaining to Final Implementation of Reactor Stability long-term Solution for WNP-2 ML17292B7581999-09-22022 September 1999 Forwards NRC Forms 396 & 398 for Nl Hancock,License SOP-50027-3,AR Herrington,License OP-50013-3,WH Sawyer, License SOP-50023-3 & Dl Strote,License SOP-50031-3,for Renewal of Licenses.Without NRC Forms 396 & 398 ML17284A8811999-09-0909 September 1999 Forwards Response to NRC 990623 RAI to Support Review of Pending Request for Amend to Reactor pressure-temp Limit Curve TS GO2-99-168, Forwards Rev 40 to Physical Security Plan.Rev Withheld,Per 10CFR2.790(a)(3)1999-09-0808 September 1999 Forwards Rev 40 to Physical Security Plan.Rev Withheld,Per 10CFR2.790(a)(3) ML17284A8751999-08-30030 August 1999 Provides Correct Page from License NPF-21 Marked to Show Rev Addressed in 990729 Application for Amend,Which Included Page That Was Inadvertently Included as Attachment 4.Replace Attachment 4 with Attached Page & Disregard Attachment 5 ML17284A8721999-08-30030 August 1999 Forwards Proprietary Info to Support Review of Request for Amend to License NPF-21,re Min Critical Power Ratio Safety Limits Tss,As Requested During 990816 Conversation. Proprietary Encl Withheld ML17284A8711999-08-30030 August 1999 Informs Staff of Errors in world-wide-web Database Related to WNP-2 Reactor Vessel Structural integrity.Marked-up Pages Containing Errors or Omissions Will Be Forwarded by 991201 ML17292B7531999-08-24024 August 1999 Requests That Eleven Individuals Listed Below Take BWR Generic Fundamentals Examination to Be Administered on 991006 ML17292B7511999-08-24024 August 1999 Forwards Fitness for Duty (FFD) Semiannual Performance Data Rept for Jan-June 1999,per 10CFR26.71(d) ML17284A8701999-08-19019 August 1999 Forwards NRC Form 396, Certification of Medical Exam by Facility Licensee & NRC Form 398, Personal Qualification Statement - Licensee, for Jd Prescott (License SOP-50262-1).Without Encls ML17292B7501999-08-19019 August 1999 Informs Staff That Licensee Has Completed Review of NRC SER for B&Wog Util Resolution Guidance Document Addressing ECCS Suction Strainer Blockage ML17284A8681999-08-12012 August 1999 Submits Two ISI Program Plan Relief Requests for NRC Review & Approval,Per 10CFR50.55a(a)(3)(i).Proposed Alternatives Provide Acceptable Level of Quality & Safety ML17284A8541999-08-0202 August 1999 Forwards Proprietary Addl Info to Support Review of Pending Request for Amend to MCPR Safety Limit Ts.Info Consists of Proprietary Ltr from Abb Combustion Engineering,Inc.Encl Withheld ML17284A8531999-07-30030 July 1999 Forwards Estimate of Number of Licensing Action Requests Planned for Submittal in Future,As Requested in Administrative Ltr 99-02.Twenty-nine Submittals Scheduled for Fy 2000 & Four for Fy 2001 ML17284A8301999-07-22022 July 1999 Clarifies Change of Licensee Name from Wpps to Energy Northwest & Change of Facility Name from Wppss Nuclear Project Number 2 to WNP-2,as Requested in 990719 Telcon with Js Cushing of NRC.Marked-up OL Pages,Encl ML17292B7451999-07-20020 July 1999 Forwards Rev 23 to WNP-2 Emergency Plan,Iaw 10CFR50.4(b) & 50.54(q) & 10CFR50 App E.Rev 23 Provides Updated Description Re Establishment of Separate Emergency Operation Centers for Benton & Franklin Counties ML17292B7391999-07-16016 July 1999 Submits Withdrawal of Request for Amend to Secondary Containment & Standby Gas Treatment Sys Ts.Util Currently Plan to re-submit Amend Request in Entirety by 991112 ML17292B7381999-07-12012 July 1999 Forwards NRC Form 396 & NRC Form 398,for If Sumsion,License OP-50487 & Ga Westergard,License SOP-50415 for Renewal of Operator Licenses.Without Encls ML17292B7171999-07-0606 July 1999 Provides Notification of Early Completion on 990630 of Exception Noted in 990629 Ltr.Equipment within Scope of GL 98-01,Suppl 1, Y2K Readiness of Computer Sys at Nuclear Power Plants, Evaluated & Y2K Ready ML17292B7181999-07-0202 July 1999 Responds to 990623 RAI to Support Review of Evaluation of Planar Indication Found on Weld Number 24RRC(2)A-1 During 1998 RO ML17292B7161999-06-30030 June 1999 Forwards Addl Info Requested in 990513 Ltr to Support Review of Pending Response to GL 95-07, Pressure Locking & Thermal Binding of Safety-Related Power Operated Gate Valves. ML17292B7131999-06-29029 June 1999 Forwards Response to NRC GL 98-01,Suppl 1, Y2K Readiness of Computer Sys at Npps. ML17292B7091999-06-21021 June 1999 Forwards Proprietary Response to NRC 990603 RAI Re Licensee Request for Amend to MCPR Safety Limit Tss.Proprietary Info Withheld IAW Requirements of 10CFR2.790 ML17292B7041999-06-17017 June 1999 Forwards NRC Forms 396 & 398 for Three Individuals Listed Below for Renewal of Operator Licenses.Without Encls ML17292B7031999-06-10010 June 1999 Forwards Response to NRC 990511 RAI Re License Request for Amend to Secondary Containment & SGTS Tss.Results of Addl Benchmark of Gothic Computer Code Performed to Demonstrate Modeling Capability of Drawdown Response,Encl ML17292B6841999-06-0404 June 1999 Forwards Response to NRC 990326 RAI Re WNP-2 GL 96-05 Program for Periodic Verification of design-basis Capability of MOVs ML17292B6851999-06-0101 June 1999 Forwards 1999 Quality Audit of WNP-2 Emergency Preparedness Program, Per NUREG-0654,Section Ii,Criteria P.9.Seven Problem Evaluation Requests & Nine Recommendations for Improvement Were Issued as Result of Audit Activities ML17292B6751999-05-25025 May 1999 Forwards Proprietary ABB-CE Ltr Re WNP-2 Cycle 15 SLMCPR & Core Reload Design Rept,Per Util Request for Amend Re MCPR Safety Limits.Proprietary Info Withheld,Per 10CFR2.790 ML17292B6831999-05-25025 May 1999 Informs That Request for NRC Approval of Changes to Emergency Plan Requesting Reduction in on-shift HP Staffing, Is Retracted.Util Will Resubmit Request with Required Addl Info at Later Date ML17292B6661999-05-0707 May 1999 Requests Exemption to Requirement in 10CFR55.59(a)(2) Re Annual Operating Test requirements.One-time Exemption from Requirement to Period Not to Exceed 15-months from Last Date of Passing Operating Exam for Licensee at Facility ML17292B6531999-05-0303 May 1999 Forwards Response to NRC 990402 RAI Re Licensed Operator Positive Drug Test.Encl Withheld,Per 10CFR2.790 ML17292B6561999-04-29029 April 1999 Forwards Rev 0 to Calculation ME-02-98-04, Fracture Mechanics Evaluation of N1 Safe End & Calculation Mod Record CMR-98-0243, Fracture Mechanics Evaluation of N1A Nozzle Safe End, as Suppl Info to ISI Exam ML17292B6421999-04-19019 April 1999 Responds to NRC 990319 Ltr Re Violations Noted in Insp Rept 50-397/99-01.Corrective Actions:Provisions Are Presently in Place to Maintain Adequate Level of Security GO2-99-073, Forwards Rev 39 to WNP-2 Physical Security Plan,Per 10CFR50.54(p).Changes Do Not Decrease Effectiveness of Approved Plan.Encl Withheld IAW 10CFR73.21 & 10CFR2.7901999-04-19019 April 1999 Forwards Rev 39 to WNP-2 Physical Security Plan,Per 10CFR50.54(p).Changes Do Not Decrease Effectiveness of Approved Plan.Encl Withheld IAW 10CFR73.21 & 10CFR2.790 ML17292B6401999-04-13013 April 1999 Requests That WNP-2 Operator Requalification Program Be Granted one-time Extension Beyond Requirement in 10CFR55.59(a)(2) for Annual Operating Tests ML17292B6371999-04-12012 April 1999 Forwards Response to NRC 990211 RAI Re Util Request for Amend to Secondary Containment & SBGTS TS ML17292B6281999-04-0606 April 1999 Informs NRC That Insp Interval Ending Date for ISI Program Plan Has Been Extended by One Year to Dec 12,2005 Due to Changes in Plant Refueling Outage Schedule GO2-99-060, Submits Rept of Status of WNP-2 Decommissioning Fund as of 981231,IAW 10CFR50.75(f)(1)1999-03-26026 March 1999 Submits Rept of Status of WNP-2 Decommissioning Fund as of 981231,IAW 10CFR50.75(f)(1) ML17292B6131999-03-24024 March 1999 Forwards Rev 0 to Calculation ME-02-98-04, Fracture Mechanics Evaluation of N1 Nozzle Safe End. Info Will Be Used to Assist NRC in Review of WNP-2 ISI Activities Associated with Evaluation of Planar Indication ML17292B5991999-03-16016 March 1999 Informs That Listed Property & Liability Insurance Coverage for WNP-2 Is in Force,In Compliance with Licensing Responsibilities Delineated in 10CFR50.54(w)(3) ML17292B5911999-03-16016 March 1999 Forwards 1998 Environ Operating Rept, Per Reporting Requirements of Section 5.4.1 of WNP-2 Epp.No Design or Operational Changes or Tests in 1998 Involved Unreviewed Environ Question ML17292B5941999-03-16016 March 1999 Forwards NRC Form 396, Certification of Medical Exam by Facility Licensee, & NRC Form 398, Personal Qualification Statement - Licensee, for MD Comstock,Mc Naulty & RR Nelson.Without Encls ML17292B6001999-03-16016 March 1999 Responds to Weakness Noted in Insp Rept 50-397/98-24. Corrective Actions:Developed Document to Identify Areas Needing Improvement,Assigned Responsibility for Actions & Provided Milestones for Achievement ML17292B5901999-03-11011 March 1999 Forwards Hard Copy of Addl Occupational Exposure Data Requested in GL 94-04,per 990303 e-mail.Original Electronic Version Was Corrupted ML17292B5681999-03-0101 March 1999 Forwards Radioactive Effluent Release Rept for 1998, IAW 10CFR50.36a(a)(2) & TS 5.6.3 & Complete Copy of WNP-2 ODCM Per TS 5.5.1 ML17292B5651999-02-22022 February 1999 Forwards Relief Request 2ISI-20,proposing Alternate Exam Expected to Reduce Dose Significantly & Still Provide Adequate Safety & Quality.Attached Relief Request Will Be Used to Support ALARA Dose Reduction Efforts During Maint ML17292B5581999-02-0404 February 1999 Requests Change to Co Which Modified WNP-2 OL to Reflect Schedule for Implementing Thermo-Lag 330-1 Fire Barrier C/As.Change Requested to Reflect That Final Implementation of C/As Will Be Completed During Fall 1999 Not Spring 1999 1999-09-09
[Table view] |
Text
CATEGORY 1 REGULATORY INFORMATION DISf'RIBUTION SYSTEM (RIDE)
ACCESSION NBR:9908100214 DOC.DATE: 99/08/02 NOTAR1ZED: YES DOCKET FACIL:50-397 .WPPSS Nuclear Project, Unit 2, Washington Public Powe 05000397 gAUTH,.NAME AUTHOR AFFILIATION CO9LEMAN,D.W. Washington Public Power Supply System RECIP.NAME RECIPIENT AFFILIATION Records Management Branch (Document Control Desk)
SUBJECT:
Forwards proprietary addi info to support review of pending recpxest for amend to MCPR safety limit TS.Info consists of proprietary ltr from ABB Combusting Engineering,Inc.Encl withheld.
DISTRIBUTION CODE: AP01D COPIES RECEIVED:LTR ENCL SIZE: T TITLE: Proprietary Review Distribution - Pre Operating License & Operating R E
NOTES:
RECIPIENT, COPIES RECIPIENT COPIES ID CODE/NAME LTTR ENCL ID CODE/NAME LTTR ENCL LPD4-2 LA 1 1 CUSHING,J 1 1 INTERNAL: ACRS 1 1 - FILE CENTER 01 1 1 OGC/RP 1 0 EXTERNAL: NRC PDR D
0
'E NOTE TO ALL "RIDS" RECIPIENTS:
PLEASE HELP US TO REDUCE WASTE.'TO HAVE YOUR NAME OR ORGANIZATION REMOVED FROM DISTRIBUTION LISTS OR REDUCE THE NUMBER OF COPIES RECEIVED BY YOU OR YOUR ORGANIZATION, CONTACT THE DOCUMENT CONTROL DESK (DCD) ON EXTENSION 415-2083 TOTAL NUMBER OF COPIES REQUIRED: LTTR 6 ENCL
I~
sr ~R WASHINGTON PUBLIC POWER SUPPLY SYSTEM P.O. Box 968 ~ Richland, Washington 99352-0968 August 2, 1999 G02-99-149 Docket No. 50-397 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555 Gentlemen:
Subject:
WNP-2, OPERATING LICENSE NPF-21 REQUE~ST FOR AMENDMENT MIIIIMIMCRITICAL POWER RATIO SAPRTT LIMITS (SUPPLEMENTAL INFORMATION)
Reference:
Letter, dated July 26, 1999, Jack Cushing (NRC) to JV Parrish (SS),
"Supplemental Request for Additional Information (RAI) for the Washington Public Power Supply System Nuclear Project NO. 2 (TAC NO. MA5212)"
In the reference, the staff requested that additional information be provided to support review of our pending request for an amendment to the Minimum Critical Power Ratio Safety Limit Technical Specifications.
The additional information is included as an attachment, which consists of a letter from ABB Combustion Engineering, Inc. Some of the material in the attachment has been identified as proprietary and is marked accordingly (i.e., bracketed) ~ Therefore, pursuant to the requirements of 10 CFR 2.790, an affidavit. is enclosed to support the withholding of this information from public disclosure.
Should you have any questions or desire additional information regarding this matter, please call me or PJ Inserra at (509) 377-4147.
ull, DW Coleman Manager, Regulatory Affairs Mail Drop PE20 Attachment cc: EW Merschoff - NRC RIV DL Williams - BPA/1399 JS Cushing - NRR PD Robinson - Winston 0 Strawn NRC Sr. Resident Inspector - 927N
'rr'rr08i002i 4 'rr'F08 PDR P
02 PDR Sl, n I 4~)~P r
1
~
y
'E 4
~i
STATE OF WASHINGTON )
Subject:
Letter ABBWP-99476, dated July 30, 1999, "WNP-2, Operating License NPF-21, Rctlucst
)
for Amendment, Mnimum Critical Popover COUNTY OF BENTON ) Ratio Safety Limits (Supplemental Information)"
I, T.C. Messersmith, being duly sworn, subscribe to and say that I am the Acting Manager, Regulatory Affairs, for the WASHINGTON PUBLIC POWER SUPPLY SYSTEM, the applicant herein; that I have the full authority to execute this oath; that I have reviewed the foregoing; and that to the best of my knowledge, information, and belief the statements made in it are true.
The attachment to this letter contains information [marked in brackets] which is considered by ABB Combustion Engineering, to be proprietary. Attached is an affidavit executed by T. Rodack, Director, Mechanical Design and Advanced Projects (Nuclear Fuels), of ABB Combustion Engineering Nuclear Power, Inc., dated luly 30, 1999, which provides the basis on which it is claimed that the subject document should be withheld from public disclosure under the provisions of 10 CFR 2.790.
The Washington Public Power Supply System treats the subject document as proprietary information on the basis of statements by the owner. In submitting this information to the NRC, the Supply System requests that the subject document be withheld from public disclosure in accordance with 10 CJ R 2.790.
DATE , 1999 T.C. Messersmith Acting Manager, Regulatory Affairs On this date personally appeared before me T.C. Messersmith, to me known to be the individual who executed the foregoing instrument, and acknowledged that he signed the same as his free act and deed for the uses and purposes herein mentioned.
GIVEN under my hand and seal this K day of 1999.
otary Public in and for the STATE OF WASHINGTON Residing at My Commission Expires
ll (gllillljg/f/ling V
I 0/J g IJ Ci
'>i ~~8g(( 5~
il/~It(>ii<nni~(0
AFFIDAVITPURSUANT TO 10 CFR 2.790 I, T. Rodack depose and say that I am the Director, Mechanical Design and Advanced Projects (Nuclear Fuels), of ABB Combustion Engineering Nuclear Power, Inc. (ABB CENP), duly authorized to make this affidavit, and have reviewed or caused to have reviewed the information which is identified as proprietary and referenced in the paragraph immediately below. I am submitting this affidavit in conjunction with the application of the Washington Public Power Supply System, and in conformance with the provisions of 10 CFR 2.790 of the Commission's regulations.
The information for which proprietary treatment is sought is contained in the following document:
ABBWP-99-076, "WNP-2, Operating License NPF-21, Request for Amendment, Minimum Critical Power Ratio Safety Limits (Supplemental Information), July 30,1999 This document has been appropriately designated as proprietary.
I have personal knowledge of the criteria and procedures utilized by ABB CENP in designating information as a trade secret, privileged or as confidential commercial or financial information.
Pursuant to the provisions of paragraph (b) (4) of Section 2.790 of the Commission's regulations, the following is furnished for consideration by the Commission in determining whether the information sought to be withheld from public disclosure, included in the above referenced document, should be withheld.
- 1. The information sought to be withheld from public disclosure, is owned and has been held in confidence by ABB CENP. It consists of information regarding Safety Limits and Critical Power Ratio correlations.
- 2. The information consists of test data or other similar data concerning a process, method or component, the application of which results in substantial competitive advantage to ABB CENP.
- 3. The information is of a type customarily held in confidence by ABB CENP and not customarily disclosed to the public. ABB CENP has a rational basis for determining the types of information customarily held in confidence by it and, in that connection, utilizes a system to determine when and whether to hold certain types of information in confidence. The details of the aforementioned system were provided to the Nuclear Regulatory Commission via letter DP-537 from F. M. Stem to Frank Schroeder dated December 2, 1974. This system was applied in determining that the subject document herein is proprietary.
- 4. The information is being transmitted to the Commission in confidence under the provisions of 10 CFR 2.790 with the understanding that it is to be received in confidence by the Commission.
The information, to the best of my knowledge and belief, is not available in public sources, and any disclosure to third parties has been made pursuant to regulatory provisions or proprietary agreements which provide for maintenance of the information in confidence.
- 6. Public disclosure of the information is likely to cause substantial harm to the competitive position of ABB CENP because:
- a. A similar product is manufactured and sold by major competitors of ABB CENP.
Development of this information by ABB CENP required tens of thousands of dollars and hundreds of manhours of effort. A competitor would have to undergo similar expense in generating equivalent information.
C. In order to acquire such information, a competitor would also require considerable time and inconvenience to develop
methods regarding Safety Limit calculations and Critical Power Ratio correlations.
The information consists of material regarding Safety Limit and Critical Power Ratio correlations, the application of which provides a competitive economic advantage. The availability of such information to competitors would enable them to modify their product to better compete with ABB CENP, take marketing or other actions to improve their product's position or impair the position of ABB CENP's product, and avoid developing similar data and analyses in support of their processes, methods or apparatus.
In pricing ABB CENP's products and services, significant research, development, engineering, analytical, manufacturing, licensing, quality assurance and other costs and expenses must be included. The ability of ABB CENP's competitors to utilize such information without similar expenditure of resources may enable them to sell at prices reflecting significantly lower costs.
Use of the information by competitors in the international marketplace would increase their ability to market nuclear fuel by reducing the costs associated with technology development. In addition, disclosure would have an adverse economic impact on ABB CENP's potential for obtaining or maintaining foreign licensees.
4 Further the deponent sayeth not.
T. Rodack, Director Mechanical Design and Advanced Projects (Nuclear Fuels)
Sworn to before me this B + day of , 1999 Notary Public My commission expires: S'I