Advises of Listed Organizational & Personnel Changes, Effective 900707.J Burn Will Be New Director of Projects, C Powers Promoted to Director of Engineering & J Baker Promoted to Plant Manager
ML17285B366
Person / Time
Site: Columbia Energy Northwest icon.png
Issue date: 07/05/1990
From: Sorensen G
WASHINGTON PUBLIC POWER SUPPLY SYSTEM
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
GO2-90-118, NUDOCS 9007110106
Download: ML17285B366 (4)


Text

ACCELERATED DISTRIBUTION DEMONS'QATION SYSTEM

~s ~

~~

REGULATORY INFORMATION DISTRIBUTION SYSTEM (RIDS)

ACCESSION NBR:9007110106 DOC.DATE: 90/07/05 NOTARIZED: NO DOCKET FACIL:50-397 WPPSS Nuclear Project, Unit 2, Washington Public Powe 05000397 AUTH. NAME AUTHOR AFFILIATION SORENSEN,G.C. Washington Public Power Supply System RECIP.NAME RECIPIENT AFFILIATION Document Control Branch (Document Control Desk)

R

SUBJECT:

Advises of listed organizational & personnel changes, effective 900707. I DISTRIBUTION CODE:

TITLE: Changes MOOSD COPIES RECEIVED:LTR of Personnel/Address 3 ENCL 0 SIZE: D NOTES RECIPIENT COPIES RECIPIENT COPIES ID CODE/NAME LTTR E CL ID CODE/NAME LTTR E CL A

PD5 LA 1 PD5 PD 1 SAMWORTH,R . 1 D

INTERNAL: ACRS -

ASLAP ASLBP IRM STEVENSON g L D IRM TECH ADV OC/LFMB OGC/HDS2 01 SECY/DSB

. EXTERNAL: LPDR NRC PDR D

D D

NOTE TO ALL "RIDS" RECIPIENTS:

PLEASE HELP US TO REDUCE WASTE! CONTACT THE DOCUMENT CONTROL DESK, ROOM Pl-37 (EXT. 20079) TO ELIMINATEYOUR NAME FROM DISTRIBUTION LISTS FOR DOCUMENTS YOU DON'T NEED!

TOTAL NUMBER OF COPIES REQUIRED: LTTR 14 ENCL

WASHINGTON PUBLIC POWER SUPPLY SYSTEM P.O. Box 968 ~ 3000 George Washington Way ~ Richland, Washington 99352 July 5, 1990 Docket No. 50-397 G02-90-118 U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555 Gentlemen:

Subject:

ORGANIZATIONAL CHANGES WASHINGTON PUBLIC POWER SUPPLY SYSTEM The purpose of this letter is to advise you of the following organizational and personnel changes which have been announced at the Supply System. The following changes will be effective July 7, 1990:

~ A new directorate will be established to focus management attention on several new initiatives and important ongoing projects. Joe Burn, Director of Engineering since December 1983, will be the new Director of Projects. He will be responsible for several megawatt enhancement projects at Plant 2, aimed at, increasing the electrical output of the 1, 100-megawatt unit; continued preservation of Projects 1 and 3, including the WNP-3 synchronous condenser project to increase the reliability of BPA's Puget Sound transmission system; the Plant 2 control-room simulator program; the Hanford Generating Project, and WNP-4/5 activities.

~ Chris Powers, Plant 2 Manager since April 1985, will be promoted to Director of Engineering. Chris will be responsible for the design engineering support to WNP-2, nuclear fuels, materials, equipment engineering, as well as non-destructive testing programs.

~ Jack Baker, Assistant Plant 2 Manager since April 1985, will be promoted to Plant Manager job.

These changes are viewed as strengthening the overall operation and support of WNP-2. The areas which will become the responsibility of the Director of Projects have been the responsibility of the Director of Engineering. By pulling these functions out, into a new Directorate, the Director of Engineering will be able to focus on those functional areas which provide the design engineering support for WNP-2. The creation of the Projects Directorate provides the senior level management focus which these projects deserve.

9007ii0106 900705 PDR ADOCK 05000397 PDC go~~

H

.~- A i)0

U. S. Nuclear Regulatory Commission Page 2 July 5,, 1990 ORGANIZATIONAL CHANGES WASHINGTON PUBLIC POWER SUPPLY, SYSTEM The professional qualifications and experiences of Mr. Burn, Mr. Powers and Mr. Baker are provided in the LINP-2 FSAR; Chapter 13.

Should you have any questions related to these changes please contact me.

Very truly yours, G. C. orensen, Manager Regulatory Programs (MD-280)

GCS/tmd cc: J. B. Martin, Region V NRC R. B. Samworth, NRC N. S. Reynolds, Bishop, Cook, Purcell 8 Reynolds C. J. Bosted, NRC (901A)

D. L. Williams (399)