Forwards Revised Schedule for Plant Equipment Setpoint Methodology Program Plan.Methodology Revised to Incorporate Latest ISA Std Draft.Setpoint Program Design Team for FY90 Onsite,Trained & Began Work on 900312
ML17285B142
Person / Time
Site: Columbia Energy Northwest icon.png
Issue date: 03/29/1990
From: Sorensen G
WASHINGTON PUBLIC POWER SUPPLY SYSTEM
To: Martin J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
References
GO2-90-062, GO2-90-62, NUDOCS 9004100288
Download: ML17285B142 (7)


Text

ACCELERATED D UTION DEMONST$&TION SYSTEM REGULATORY INFORMATION DXSTRXBUTION SYSTEM (RIDS)

ACCESSION NBR:9004100288 DOC.DATE: 90/03/29 NOTARIZED: NO DOCKET FACXL:50-397 WPPSS Nuclear Project, Unit 2, Washington Public Powe 05000397 AUTH. NAME AUTHOR AFFXLIATION SORENSEN,G.C. Washington Public Power Supply System RECXP.NAME RECXPXENT AFFXLIATION MARTIN,J.B. Region 5, Ofc of the Director

SUBJECT:

Forwards revised schedule for plant equipment. setpoint methodology program plan.

DISTRIBUTION CODE: A001D COPIES RECEIVED LTR ENCL SIZE:

TITLE: OR Submittal: General Distribution NOTES:

RECIPIENT COPIES RECIPIENT COPIES ID CODE/NAME LTTR ENCL ID CODE/NAME LTTR ENCL PD5 LA 1 1 PD5 PD 1 1 SAMWORTH,R 5 5 INTERNAL: ACRS 6 6 NRR/DET/ECMB 9H 1 1 NRR/DOEA/OTSBll 1 1 NRR/DST 8E2 1 1 NRR/DST/SELB 8D 1 1 NRR/DST/SICB 7E 1 1 NRR/DST/SRXB 8E 1 1 NUDOCS-ABSTRACT 1 1

/ 1 1

0 1

OGC/HDS2 RES/DSIR/EIB 1

1 0

1 EXTERNAL: LPDR 1 1 NRC PDR 1 NSIC 1 1 1'OTE TO ALL "RIDS" RECIPIENTS:

PLEASE HELP US TO REDUCE WASTEl CONTACT THE.BOCUMENT CONTROL DESK, ROOM Pl-37 (EXT. 20079) TO ELIMINATEYOUR NAME FROM DISTRIBUTION LISTS FOR DOCUMENTS YOU DON'T NEED)

TOTAL NUMBER OF COPXES REQUIRED: LTTR 27 ENCL 25

A H

WASHINGTON PUBLIC POWER SUPPLY SYSTEM P.O. Box 968 ~ 3000 George Washinglon Way ~ Richland, Washington 993S2 March 29, 1990 G02-90-062 Hr. J. B. Hartin Regional Administrator U.S. Nuclear Regulatory Commission Region V 1450 Maria Lane, Suite 210 Walnut Creek, CA 94596

Dear Mr. Hartin:

Subject:

NUCLEAR PLANT NO. 2, OPERATING LICENSE NPF-21 WNP-2 EgUIPHENT SETPOINT HETHODOLOGY PROGRAM PLAN

Reference:

Letter, G02-90-029, GC Sorensen (SS) to JB Hartin (NRC),

same subject, dated February 20, 1990 In the reference letter the Supply System committed to. provide a new schedule for both the harsh environment accuracy effects- as well as the overall equipment setpoint methodology program plan within 30 days. This revised schedule was required because of the delays in executing the contract with Bechtel and mob'lizing qualified personnel to do the work. The purpose of this" letter is to rovide our revi sed schedule.

The'etpoint program design team for FY90 is on site, trained, and began work on t)is effort March 12, 1990. Additionally, the methodology has been revised to iqcorporate the latest ISA standard draft (December 1989) and the Supply System is presently completing efforts with Bechtel Corporation to computerize the setpoint calculation effort. These additional efforts have resulted in the attached schedule which does not limit the original harsh environment schedule slip to 60 days as had been expected. The Supply System is considering the possibility of adding additional resources in order to increase our confidence that the new schedule will be maintained.

90041002SS 9'0032I PDR ADOCK 05000397 P PDC

Pyge Two WNP-2 EQUIPMENT SETPOINT

.HETHODOLOGY PROGRAM PLAN As shown by 'the attached schedule, inclusion of harsh environment accuracy utilizing recent ISA standard methodology has first priority in the overall program. This effort will require recalculation of setpoints (instrumentation and electrical equipment) for approximately 240 equipment pieces. Retrieval of applicable design basis information for this equipment is underway and the magnitude of the effort can only be estimated at this time. Until such time that we can quantify the data retrieval effort based upon actual experience the harsh environment schedule has been extended to account for this potential difficulty.

The Supply System is working very diligently to attempt to meet the attached schedules. These schedules are based on best estimates and are predicated on availability of data. In some cases, completion of the scheduled work may result in the initiation of new work, making it very difficult to say with absolute certainty that the scheduled date of October 31, 1990 for 100% completion of harsh environment setpoint work can be maintained.

The Supply System will advise you as to any concerns with the schedule viability as the magnitude of the program becomes quantifiable through actual experience.

Very truly yours, G. C. Sorensen, Manager Regulatory Programs HLA/bk Attachment cc: NS Reynolds - BCP8R RB Samworth - NRC DL Williams - BPA Document Control Desk - NRC NRC Site Inspector - 901A

'4. 0 'ILESTONES RESPONSIBILITIES SCHEDULES p

~ ~ $ I The organizations/departments listed below are responsible for'ompleting the following program scope elements within the scheduled completion dates.

4. 1 Methodolo Determination Considerin Sco e Elements a 0 Review industry methods including April 1989 ISA draft for application to WNP-2.

Responsible Organi zati on - Generation Engineering, El ectri cal/I&C Systems Task Completion Date: August 4, 1989 (Completed)

b. Incorporate ISA Revision 5 (December 1989) draft.

Responsible Organization - Generation Engineering, El ectri cal/I&C Systems Task Completion Date: February 1, 1990 (Completed)

C. Formulate I&C/Electrical equipment methodology.

Responsible Organization - Generation Engineering (with input from Plant Technical and Equipment Engineering)

Electrical/I&C Systems Task Completion Date: September 1,- 1989 (Completed)

d. 1) Assemble methodology
2) Issue associ'ated Engineering Standard
3) Provide setpoint calculation computer program Responsible Organization Generation Engineering, Electrical/I&C Systems and Bechtel Power Corp (computer program)

Task Completion Dates: 1) January 1, 1990 (Completed)

2) April 20, 1990
3) April 30, 1990 4.2 NRC Staff A royal Provide NRC (NRR) Staff WNP-2 methodology for review.

Responsible Organization - Licensing Task Completion Date: Hay ll, 1990

, .4.3 E ui ment Identification

a. 1) List of safety related equipment requiring setpoint calculations.
2) List of safety related equipment requiring consideration of harsh environment effects.

Responsible Organization

- Generation Engineering, Electrical/IKC, Hechanical and Nuclear Systems Task Completion Date: 1) November 30, 1990

2) October 31, 1989 (Completed)
b. Perform safety analysis to indicate safety function completion times for equipment located in harsh environments.

Responsible Organization - Generation Engineering, Electrical/18C Systems with review by Mechanical and Nuclear Systems Task Start Date: November 1, 1989 (Completed)

Task Completion Date: December 31, 1989 (Completed) 4.4 Recalculate Set oint to Include Environmental Accurac Effects Responsible Organization - Generation Engineering with aid (if required) by Equipment Engineering Task Completion Date: 'ctober 31, 1990 4.5 uglification Test Determination and Retest Responsible Organization - Equipment Engineering Task Completion Date: To Be Scheduled 4.6 Consolidate Reconcile Set oint Calculations Identify equipment with existing multiple setpoint calculations and supersede as appropriate (including ISCR's).

Responsible Organization - Generation Engineering, Assigned System Engineers and Plant Technical Task Complete Date: June 1, 1992

4.7 Set oint Calculations for Other than Harsh Environment Safet Related

~Eni ment Responsible Organization - Generation Engineering, provide setpoint calculations, Assigned System Engineers Pl ant Technical to review and revise Master Data Sheets Task Start Date: November 1, 1990 - (Focus on Technical Specification equipment to support implementation of the Improved Technical Specification submittal).

Task Complete Date: June 1, 1992 4.8 Recalibration for Harsh Environment E ui ment if re uired Responsible Organization - Plant Technical/Maintenance Task Completion Date: January 31, 1991 4.9 Recalibration of E ui ment for Other than Harsh Environment E ui ment Responsible Organization - Plant Technical/Maintenance Task Completion Date: December 1, 1992