ML14002A437
ML14002A437 | |
Person / Time | |
---|---|
Site: | River Bend |
Issue date: | 01/02/2014 |
From: | Geoffrey Miller NRC/RGN-IV/DRS/EB-2 |
To: | Olson E Entergy Operations |
Miller G | |
References | |
EA-13-110 IR-13-007 | |
Download: ML14002A437 (58) | |
See also: IR 05000458/2013007
Text
UNITE D S TATE S
NUC LEAR RE GULATOR Y C OMMI S SI ON
R E G IO N I V
1600 EAST LAMAR BLVD
AR L INGTON , TEXAS 7 60 11 - 4511
January 2, 2014
Mr. Eric W. Olson
Site Vice President
Entergy Operations, Inc.
River Bend Station
5485 US Highway 61N
St. Francisville, LA 70775
SUBJECT: RIVER BEND STATION - NRC TRIENNIAL FIRE PROTECTION INSPECTION
REPORT 05000458/2013007 AND NOTICE OF VIOLATION
Dear Mr. Olson:
On December 30, 2013, the U.S. Nuclear Regulatory Commission (NRC) completed an
inspection at the River Bend Station and discussed the results of this inspection with
Mr. T. Evans and other members of your staff. The inspectors documented the results of this
inspection in the enclosed inspection report.
NRC inspectors documented five findings of very low safety significance (Green) in this report.
Four of these findings involved violations of NRC requirements. The NRC evaluated these
violations in accordance with Section 2.3.2.a of the NRC Enforcement Policy, which appears on
the NRCs Web site at http://www.nrc.gov/about-nrc/regulatory/enforcement/enforce-pol.html.
The NRC determined that three of these violations met the criteria to be treated as non-cited
violations. The NRC determined that one violation did not meet the criteria to be treated as a
non-cited violation because the licensee failed to restore compliance within a reasonable period
of time after the violation was identified. Specifically, the licensee failed to implement all of the
required corrective actions for multiple spurious operations concerns prior to November 2, 2012,
which marked the expiration of enforcement discretion for multiple spurious operations
contained in Enforcement Guidance Memorandum 09-002. The violation is cited in the
enclosed Notice of Violation (Notice) and the circumstances surrounding it are described in
detail in the inspection report.
You are required to respond to this letter and should follow the instructions specified in the
enclosed Notice when preparing your response. If you have additional information that you
believe the NRC should consider, you may provide it in your response to the Notice. The NRCs
review of your response to the Notice will also determine whether further enforcement action is
necessary to ensure your compliance with regulatory requirements.
E. Olson -2-
If you contest the violations or significance of these non-cited violations, you should provide a
response within 30 days of the date of this inspection report, with the basis for your denial, to
the Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington DC 20555-
0001; with copies to the Regional Administrator, Region IV; the Director, Office of Enforcement,
United States Nuclear Regulatory Commission, Washington, DC 20555-0001; and the NRC
Resident Inspector at the River Bend Station.
If you disagree with a cross-cutting aspect assignment or a finding not associated with a
regulatory requirement in this report, you should provide a response within 30 days of the date
of this inspection report, with the basis for your disagreement, to the Regional Administrator,
Region IV, and the NRC Resident Inspector at the River Bend Station.
In accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding,
of the NRCs Rules of Practice, a copy of this letter, its enclosure, and your response (if any)
will be available electronically for public inspection in the NRCs Public Document Room or from
the Publicly Available Records (PARS) component of the NRC's Agencywide Documents
Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at
http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA/
Geoffrey B. Miller, Chief
Engineering Branch 2
Division of Reactor Safety
Docket No.: 50-458
License No.: NPF-47
Enclosures: 1 - Notice of Violation
2 - Inspection Report 05000458/2013007
w/Attachment: Supplemental Information
cc w/Enclosure: Electronic Distribution for River Bend Station
E. Olson -3-
Electronic distribution by RIV:
Regional Administrator (Marc.Dapas@nrc.gov)
Deputy Regional Administrator (Steven.Reynolds@nrc.gov)
DRP Director (Kriss.Kennedy@nrc.gov)
DRP Deputy Director (Troy.Pruett@nrc.gov)
DRS Director (Tom.Blount@nrc.gov)
DRS Deputy Director (Jeff.Clark@nrc.gov)
Senior Resident Inspector (Grant.Larkin@nrc.gov)
Resident Inspector (Andy.Barrett@nrc.gov)
RBS Administrative Assistant (Lisa.Day@nrc.gov)
Branch Chief, DRP/C (Don.Allen@nrc.gov)
Senior Project Engineer (Ray.Azua@nrc.gov)
Public Affairs Officer (Victor.Dricks@nrc.gov)
Public Affairs Officer (Lara.Uselding@nrc.gov)
Project Manager (Alan.Wang@nrc.gov)
Branch Chief, DRS/TSB (Ray.Kellar@nrc.gov)
RITS Coordinator (Marisa.Herrera@nrc.gov)
ACES (R4Enforcement.Resource@nrc.gov)
Regional Counsel (Karla.Fuller@nrc.gov)
Technical Support Assistant (Loretta.Williams@nrc.gov)
BC RES/DRA/FRB (MarkHenry.Salley@nrc.gov)
Congressional Affairs Officer (Jenny.Weil@nrc.gov)
RIV/ETA: OEDO (Brett.Rini@nrc.gov)
Accession Number: ML14002A437
SUNSI Rev Compl. xYes No ADAMS xYes No Reviewer Initials GBM
Publicly Avail xYes No Sensitive Yes x No Sens. Type Initials GBM
DRS\EB2:RI SRI: DRP: RI SRA ACES EB2 BC
S. Alferink J. Mateychick A. Barrett D. Loveless H. Gepford G. Miller
/RA/ /RA/ /RA/E /RA/ /RA/ /RA/
12/03/2013 12/04/2013 12/03/2013 12/04/2013 12/05/2013 01/02/2014
OFFICIAL RECORD COPY
NOTICE OF VIOLATION
Entergy Operations, Inc. Docket No. 50-458
River Bend Station License No. NFP-47
During an NRC inspection completed on December 30, 2013, a violation of NRC requirements
was identified. In accordance with the NRC Enforcement Policy, the violation is listed below:
Title 10 of the Code of Federal Regulations (10 CFR) Part 50, Appendix B, Criterion XVI,
states that measures shall be established to assure that conditions adverse to quality,
such as failures, malfunctions, deficiencies, deviations, defective material and
equipment, and nonconformances are promptly identified and corrected.
Contrary to the above, from November 2, 2012, to December 30, 2013, the licensee
failed to promptly identify and correct conditions adverse to quality. Specifically, the
licensee failed to implement all of the required corrective actions for multiple spurious
operations concerns prior to November 2, 2012, which marked the expiration of
enforcement discretion for multiple spurious operations contained in Enforcement
Guidance Memorandum 09-002.
This violation is associated with a Green significance determination process finding.
Pursuant to the provisions of 10 CFR 2.201, Entergy Operations, Inc. is hereby required to
submit a written statement or explanation to the U.S. Nuclear Regulatory Commission,
ATTN: Document Control Desk, Washington, DC 20555-0001 with a copy to the Regional
Administrator, Region IV, and a copy to the NRC Resident Inspector at River Bend Station
within 30 days of the date of the letter transmitting this Notice of Violation (Notice). This reply
should be clearly marked as a Reply to a Notice of Violation: EA-13-110 and should include:
(1) the reason for the violation, or, if contested, the basis for disputing the violation or severity
level; (2) the corrective steps that have been taken and the results achieved; (3) the corrective
steps that will be taken; and (4) the date when full compliance will be achieved. Your response
may reference or include previous docketed correspondence, if the correspondence adequately
addresses the required response. If an adequate reply is not received within the time specified
in this Notice, an order or a Demand for Information may be issued as to why the license should
not be modified, suspended, or revoked, or why such other action as may be proper should not
be taken. Where good cause is shown, consideration will be given to extending the response
time.
If you contest this enforcement action, you should also provide a copy of your response, with
the basis for your denial, to the Director, Office of Enforcement, United States Nuclear
Regulatory Commission, Washington, DC 20555-0001.
Because your response will be made available electronically for public inspection in the NRC
Public Document Room or from the NRCs document system (ADAMS), accessible from the
NRC Web site at http://www.nrc.gov/reading-rm/adams.html, to the extent possible, it should not
include any personal privacy, proprietary, or safeguards information so that it can be made
available to the public without redaction. If personal privacy or proprietary information is
necessary to provide an acceptable response, then please provide a bracketed copy of your
response that identifies the information that should be protected and a redacted copy of your
response that deletes such information. If you request withholding of such material, you must
-1- Enclosure 1
specifically identify the portions of your response that you seek to have withheld and provide in
detail the bases for your claim of withholding (e.g., explain why the disclosure of information will
create an unwarranted invasion of personal privacy or provide the information required by
10 CFR 2.390(b) to support a request for withholding confidential commercial or financial
information). If safeguards information is necessary to provide an acceptable response, please
provide the level of protection described in 10 CFR 73.21.
Dated this 2nd day of January 2014.
-2- Enclosure 1
U.S. NUCLEAR REGULATORY COMMISSION
REGION IV
Docket: 50-458
License: NPF-47
Report No.: 05000458/2013007
Licensee: Entergy Operations, Inc.
Facility: River Bend Station
Location: 5485 U.S. Highway 61
St. Francisville, LA
Dates: April 15 through December 30, 2013
Team Leader: S. Alferink, Reactor Inspector, Engineering Branch 2
Inspectors: J. Mateychick, Senior Reactor Inspector, Engineering Branch 2
S. Achen, Reactor Inspector, Engineering Branch 2
A. Barrett, Resident Inspector, Project Branch C
Approved By: Geoffrey B. Miller, Branch Chief
Engineering Branch 2
Division of Reactor Safety
-1- Enclosure 2
SUMMARY OF FINDINGS
IR 05000458/2013007; 04/15/2013 - 12/30/2013; River Bend Station; Triennial Fire Protection
Team Inspection.
The report covered a two-week triennial fire protection team inspection by three specialist
inspectors and one resident inspector from Region IV. The inspectors documented five findings
of very low safety significance (Green) in this report. Four of these findings involved violations
of NRC requirements.
The significance of inspection findings was indicated by their color (i.e., greater than Green,
Green, White, Yellow, or Red) and determined using Inspection Manual Chapter 0609,
Significance Determination Process, dated June 2, 2011. Cross-cutting aspects were
determined using Inspection Manual Chapter 0310, Components Within the Cross Cutting
Areas, dated October 28, 2011. All violations of NRC requirements were dispositioned in
accordance with the NRCs Enforcement Policy dated January 28, 2013. The NRCs program
for overseeing the safe operation of commercial nuclear power reactors is described in
NUREG-1649, Reactor Oversight Process, Revision 4.
A. NRC-Identified and Self-Revealing Findings
Cornerstone: Mitigating Systems
- Green. The team identified a Green violation of 10 CFR Part 50, Appendix B,
Criterion XVI for the failure to complete corrective actions associated with multiple
spurious operations concerns in a timely manner. Specifically, the licensee failed to
implement all of the required corrective actions for multiple spurious operations concerns
prior to November 2, 2012, which marked the expiration of enforcement discretion for
multiple spurious operations contained in Enforcement Guidance Memorandum 09-002.
The licensee entered this issue into their corrective action program as Condition Report
The failure to implement all of the required corrective actions for multiple spurious
operations concerns in a timely manner was a performance deficiency. The
performance deficiency was more than minor because it was associated with the
protection against external events (fire) attribute of the Mitigating Systems Cornerstone
and it adversely affected the cornerstone objective of ensuring the availability, reliability,
and capability of systems that respond to initiating events to prevent undesirable
consequences. The team evaluated this finding using Inspection Manual Chapter 0609,
Appendix F, Fire Protection Significance Determination Process, dated
September 20, 2013, because it affected the ability to reach and maintain safe shutdown
conditions in case of a fire. A senior reactor analyst performed a Phase 3 evaluation to
determine the risk significance of this finding since it involved multiple fire areas. The
senior reactor analyst determined this finding was of very low safety significance
(Green).
The finding had a cross-cutting aspect in the Work Practices component of the Human
Performance area because the licensee failed to ensure supervisory and management
oversight of work activities, including contractors, such that nuclear safety was
supported. H.4(c) (Section 1R05.01.b)
-2- Enclosure 2
- Green. The team identified a Green non-cited violation of Technical
Specification 5.4.1.d for the failure to implement and maintain adequate written
procedures covering fire protection program implementation. Specifically, the licensee
failed to maintain an alternative shutdown procedure that ensured operators could safely
shutdown the plant under all postulated control room fire scenarios. The licensee
entered this issue into their corrective action program as Condition Report
The failure to maintain adequate written procedures covering fire protection program
implementation was a performance deficiency. The performance deficiency was more
than minor because it was associated with the procedure quality attribute of the
Mitigating Systems Cornerstone and it adversely affected the cornerstone objective of
ensuring the availability, reliability, and capability of systems that respond to initiating
events to prevent undesirable consequences. The team evaluated this finding using
Inspection Manual Chapter 0609, Appendix F, Fire Protection Significance
Determination Process, dated September 20, 2013, because it affected the ability to
reach and maintain safe shutdown conditions in case of a fire. A senior reactor analyst
performed a Phase 3 evaluation to determine the risk significance of this finding since it
involved a postulated control room fire that led to control room evacuation. The senior
reactor analyst determined this finding was of very low safety significance (Green).
The finding did not have a cross-cutting aspect since it was not indicative of present
performance in that the performance deficiency occurred more than three years ago.
(Section 1R05.05.b.1)
- Green. The team identified a Green non-cited violation of License Condition 2.C.(10) for
the failure to implement and maintain in effect all provisions of the approved fire
protection program. Specifically, the licensee failed to properly calculate the amount of
time available for operators to perform time critical actions for all control room fire
scenarios. The licensee entered this issue into their corrective action program as
Condition Report CR-RBS-2013-03472.
The failure to properly calculate the amount of time available for operators to perform
time critical actions for all control room fire scenarios was a performance deficiency.
The performance deficiency was more than minor because it was associated with the
protection against external events (fire) attribute of the Mitigating Systems Cornerstone
and it adversely affected the cornerstone objective of ensuring the availability, reliability,
and capability of systems that respond to initiating events to prevent undesirable
consequences. The team evaluated this finding using Inspection Manual Chapter 0609,
Appendix F, Fire Protection Significance Determination Process, dated
September 20, 2013, because it affected the ability to reach and maintain safe shutdown
conditions in case of a fire. A senior reactor analyst performed a Phase 3 evaluation to
determine the risk significance of this finding since it involved a postulated control room
fire that led to control room evacuation. The senior reactor analyst determined this
finding was of very low safety significance (Green).
The finding had a cross-cutting aspect in the Decision Making component of the Human
Performance area because the licensee failed to use conservative assumptions in
decision making when applying the guidance for control room fires contained in the safe
shutdown analysis. H.1(b) (Section 1R05.05.b.2)
-3- Enclosure 2
- Green. The team identified a Green non-cited violation of License Condition 2.C.(10) for
the failure to implement and maintain in effect all provisions of the approved fire
protection program. Specifically, the licensee failed to ensure that the communications
systems would work under all postulated control room fire scenarios. The licensee
entered this issue into their corrective action program as Condition Reports
CR-RBS-2013-03243 and CR-RBS-2013-03397.
The failure to ensure that the communications systems would work under all postulated
control room fire scenarios was a performance deficiency. The performance deficiency
was more than minor because it was associated with the protection against external
events (fire) attribute of the Mitigating Systems Cornerstone and it adversely affected the
cornerstone objective of ensuring the availability, reliability, and capability of systems
that respond to initiating events to prevent undesirable consequences. The team
evaluated this finding using Inspection Manual Chapter 0609, Appendix F, Fire
Protection Significance Determination Process, dated September 20, 2013, because it
affected the ability to reach and maintain safe shutdown conditions in case of a fire. A
senior reactor analyst performed a Phase 3 evaluation to determine the risk significance
of this finding since it involved a postulated control room fire that led to control room
evacuation. The senior reactor analyst determined this finding was of very low safety
significance (Green).
The finding had a cross-cutting aspect in the Work Practices component of the Human
Performance area because the licensee failed to ensure supervisory and management
oversight of work activities, including contractors, such that nuclear safety was
supported. H.4(c) (Section 1R05.07.b)
- Green. The team identified a Green finding for the failure to properly implement the
engineering change process. Specifically, the licensee failed to update the Maintenance
Rule program and perform the required preventive maintenance tasks after the addition
of three 8-hour Appendix R emergency lights. During subsequent discharge testing, two
of the three lights failed. The licensee entered this issue into their corrective action
program as Condition Reports CR-RBS-2013-03118 and CR-RBS-2013-03273.
The failure to properly implement the engineering change process was a performance
deficiency. The performance deficiency was more than minor because it was associated
with the protection against external events (fire) attribute of the Mitigating Systems
Cornerstone and it adversely affected the cornerstone objective of ensuring the
availability, reliability, and capability of systems that respond to initiating events to
prevent undesirable consequences. The team evaluated this finding using Inspection
Manual Chapter 0609, Appendix F, Fire Protection Significance Determination
Process, dated September 20, 2013, because it affected the ability to reach and
maintain safe shutdown conditions in case of a fire. The team assigned the finding a low
degradation rating since the ability to reach and maintain safe shutdown conditions in
the event of a control room fire would be minimally impacted by the failure of the three
emergency lights to function for 8-hours. Specifically, the team determined that the
alternative shutdown procedure provided operators with an alternate method of verifying
that the emergency diesel generator breaker was closed. Because this finding had a low
degradation rating, it screened as having very low safety significance (Green).
The finding did not have a cross-cutting aspect since it was not indicative of present
-4- Enclosure 2
performance in that the performance deficiency occurred more than three years ago.
(Section 1R05.08.b)
B. Licensee-Identified Violations
None
-5- Enclosure 2
REPORT DETAILS
1. REACTOR SAFETY
Cornerstones: Initiating Events, Mitigating Systems, and Barrier Integrity
1R05 Fire Protection (71111.05T)
This report presents the results of a triennial fire protection inspection conducted in
accordance with NRC Inspection Procedure 71111.05T, Fire Protection (Triennial), at
the River Bend Station. The inspection team evaluated the implementation of the
approved fire protection program in selected risk-significant areas with an emphasis on
the procedures, equipment, fire barriers, and systems that ensure the post-fire capability
to safely shutdown the plant.
Inspection Procedure 71111.05T requires the selection of three to five fire areas for
review. The inspection team used the fire hazards analysis section of the River Bend
Station Individual Plant Examination of External Events to select the following four risk-
significant fire areas (inspection samples) for review:
- Fire Area AB-7 D-Tunnel
- Fire Area C-4 ACU West Room
- Fire Area C-16 Remote Shutdown Room
- Fire Area C-24 Control Building General Area
The inspection team evaluated the licensees fire protection program using the
applicable requirements, which included plant Technical Specifications, Operating
License Condition 2.C.(10), NRC safety evaluations, 10 CFR 50.48, and Branch
Technical Position 9.5-1. The team also reviewed related documents that included the
Final Safety Analysis Report, Section 9.5; the fire hazards analysis; and the post-fire
safe shutdown analysis.
Specific documents reviewed by the team are listed in the attachment. Four inspection
samples were completed.
.01 Protection of Safe Shutdown Capabilities
a. Inspection Scope
The team reviewed the piping and instrumentation diagrams, safe shutdown equipment
list, safe shutdown design basis documents, and the post-fire safe shutdown analysis to
verify that the licensee properly identified the components and systems necessary to
achieve and maintain safe shutdown conditions for fires in the selected fire areas. The
team observed walkdowns of the procedures used for achieving and maintaining safe
shutdown in the event of a fire to verify that the procedures properly implemented the
safe shutdown analysis provisions.
For each of the selected fire areas, the team reviewed the separation of redundant safe
shutdown cables, equipment, and components located within the same fire area. The
team also reviewed the licensees method for meeting the requirements
-6- Enclosure 2
of 10 CFR 50.48; Branch Technical Position 9.5-1, Appendix A; and 10 CFR Part 50,
Appendix R,Section III.G. Specifically, the team evaluated whether at least one
post-fire safe shutdown success path remained free of fire damage in the event of a fire.
In addition, the team verified that the licensee met all applicable license commitments.
b. Findings
Introduction. The team identified a Green violation of 10 CFR Part 50, Appendix B,
Criterion XVI for the failure to complete corrective actions associated with multiple
spurious operations concerns in a timely manner. Specifically, the licensee failed to
implement all of the required corrective actions for multiple spurious operations concerns
prior to November 2, 2012, which marked the expiration of enforcement discretion for
multiple spurious operations contained in Enforcement Guidance Memorandum 09-002.
Description. The NRC issued Enforcement Guidance Memorandum 09-002,
Enforcement Discretion for Fire Induced Circuit Faults, on May 14, 2009. The purpose
of this enforcement guidance memorandum was to describe the conditions limiting
enforcement discretion during the resolution of fire protection concerns involving multiple
spurious operations. The enforcement guidance memorandum provided enforcement
discretion for three years from the date of issuance of Regulatory Guide 1.189, Fire
Protection for Nuclear Power Plants, Revision 2, for licensees to complete the
corrective actions for noncompliances associated with multiple spurious operations
concerns. Regulatory Guide 1.189, Revision 2, was issued on November 2, 2009.
Regulatory Guide 1.189, Revision 2, endorsed specific portions of NEI 00-01, Guidance
for Post-Fire Safe-Shutdown Circuit Analysis, Revision 2. Specifically, Regulatory
Guide 1.189, Revision 2, Section 5.3.1.1, Protection for the Safe-Shutdown Success
Path, stated:
The approach outlined in Chapter 4 of NEI 00-01, which relies on the Expert
Panel Process and the Generic List of Multiple Spurious Operations contained in
Appendix G to that document, provides an acceptable methodology for the
identification of multiple spurious actuations that may affect safe shutdown
success path SSCs, when applied in conjunction with this regulatory guide.
Spurious actuations, either single or multiple, with the potential to affect safe-
shutdown success path components should be mitigated in accordance with the
features described in this section; tools such as fire modeling and manual actions
should not be used.
Regulatory Guide 1.189, Revision 2, Section 5.3.1.2, Protection for Components
Important to Safe Shutdown, contained a similar statement:
The approach outlined in Chapter 4 of NEI 00-01, which relies on the Expert
Panel Process and the Generic List of Multiple Spurious Operations contained in
Appendix G, provides an acceptable methodology for the analysis of multiple
spurious operations for protection of components important to safe shutdown,
when applied in conjunction with this regulatory guide.
The licensee began their evaluation of multiple spurious operations in accordance with
NEI 00-01, Revision 2. The licensee formed a multiple spurious operations expert panel,
which met on March 23, 2010, to review the generic list of multiple spurious operations
-7- Enclosure 2
contained in NEI 00-01, Revision 2. The multiple spurious operations expert panel
meeting results were documented in Engineering Planning Management, Inc. (EPM)
Report P2083-02-002, MSO Expert Panel Results, Revision 0, dated May 2010. This
report identified several scenarios that required detailed circuit analyses to resolve.
The licensee had a contractor perform the detailed circuit analyses. The contractor
documented the results of the analyses and recommended additional actions for
scenarios that could not be resolved by circuit analysis in EPM Report P2083-07-001,
Regulatory Guide 1.189 Support Project Final Report, Revision 0, dated August 2010.
The licensee had another contractor perform additional detailed circuit analyses. This
contractor documented the results of the additional analyses and recommended
additional actions for scenarios that still could not be resolved by circuit analysis in
ENERCON Report ENTGRB083-PR-01, Multiple Spurious Operations Circuit Analysis
and Scenario Disposition, Revision 0, dated July 14, 2011.
The licensee formed a supplemental multiple spurious operations expert panel, which
met on August 30-31, 2011, to review the generic list of multiple spurious operations
contained in a draft version of NEI 00-01, Revision 3. The supplemental expert panel
revisited several scenarios that were fundamentally unchanged from NEI 00-01,
Revision 2. The licensee identified additional actions for some of these scenarios, but
failed to complete all of these additional actions by the end of the enforcement discretion
period for multiple spurious operations. The supplemental expert panel results were
documented in Engineering Report RBS-FP-11-0000, Expert Panel for Addressing
Multiple Spurious Operations, Revision 0, dated December 13, 2011.
Prior to the inspection, the licensee addressed all multiple spurious operations scenarios
through analysis only. The licensee determined no plant modifications were needed to
resolve the multiple spurious operations scenarios.
For this inspection, the team focused on the multiple spurious operations scenarios that
were identified during the licensees review of NEI 00-01, Revision 2. The team
identified the following three examples of multiple spurious operations concerns where
the licensee did not complete the corrective actions prior to the end of the enforcement
discretion period, November 2, 2012.
Example 1: Plant-Specific Scenario Diverting the Suppression Pool Inventory to the
Upper Fuel Pool
This scenario involved the spurious opening of the return valve from the residual heat
removal system to the upper pool (1E12*MOVF037A or 1E12*MOVF037B) in the non-
credited train in combination with the spurious operation of the residual heat removal
pump in the non-credited train. The concern was that the residual heat removal pump
would transfer inventory from the suppression pool to the upper pool and negatively
impact the safe shutdown pumps that take suction from the suppression pool.
This scenario was evaluated in ENERCON Report ENTGRB083-PR-01. The team
determined that the licensee took no actions to address the potential loss of suppression
pool inventory. The team reviewed the safe shutdown analysis, which evaluated these
valves as a single spurious operation concern and concluded that the valve in the
credited residual heat removal train would be controlled and would not be susceptible to
-8- Enclosure 2
spurious operation. The safe shutdown analysis did not evaluate the potential impact of
the valve in the non-credited train spuriously opening in combination with the residual
heat removal pump in the non-credited train also spuriously operating.
The team determined that the corrective actions for this scenario were inadequate since
the multiple spurious operations expert panel failed to identify the flow diversion path of
a spuriously operating residual heat removal pump combined with a spuriously opening
valve resulting in the transfer of suppression pool inventory to the upper fuel pool. This
resulted in the licensee failing to evaluate this relevant plant-specific scenario.
Example 2: NEI 00-01, Revision 2, Scenario 2ab - Spurious Opening of Both Reactor
Core Isolation Cooling Test Return to Condensate Storage Tank Valves with Suction
from the Suppression Pool Transferring Inventory to the Condensate Storage Tank
This scenario involved the spurious operation of the reactor core isolation cooling pump
in combination with the spurious operation of multiple valves (1E51*MOVF031,
1E51*MOVF022, and 1E51*MOVF059) required to transfer inventory to the condensate
storage tank. The concern was that the reactor core isolation cooling pump would
transfer inventory from the suppression pool to the condensate storage tank and
negatively impact the safe shutdown pumps that take suction from the suppression pool.
This scenario was evaluated in ENERCON Report ENTGRB083-PR-01, which
concluded that this scenario was not a concern at the River Bend Station. For six fire
areas, the report credited operators terminating the flow from the control room by closing
the reactor core isolation cooling system steam isolation valve 1E51*MOVF063. The
team noted that the evaluation did not establish the maximum time available to respond
to the flow diversion before post-fire safe shutdown would be impacted.
For one fire area (Fire Area C-16), operators may not be able to control
valve 1E51*MOVF063 from the control room. For this fire area, the report credited a
rapid depressurization of the reactor pressure vessel to allow low pressure coolant
injection as a means of reducing the steam pressure available to the reactor core
isolation cooling system turbine and terminating the loss of suppression pool inventory.
Prior to the inspection, the post-fire safe shutdown procedure was not updated to
provide procedural guidance to the control room operators for this scenario. The team
identified that the post-fire safe shutdown procedure contained a note which stated, in
part, It is expected that normal, abnormal, and emergency procedures will be followed
for shutdown. This AOP [Abnormal Operating Procedure] should not be misinterpreted to
be the required method of shutdown. The team identified that, absent guidance in the
post-fire safe shutdown procedure, the rapid depressurization of the reactor pressure
vessel might not occur before the loss of suppression pool inventory impacted the post-
fire safe shutdown.
The team concluded that the evaluation for this scenario contained in ENERCON Report
ENTGRB083-PR-01 was inadequate since it failed to identify the amount of time
available for operators to close the steam isolation valve or initiate a rapid
depressurization of the reactor pressure vessel in order to terminate the loss of
suppression pool inventory. The team concluded that the corrective actions were
untimely since they were not completed by the end of the enforcement discretion period.
These actions were still not completed prior to the beginning of the inspection.
-9- Enclosure 2
Example 3: NEI 00-01, Revision 2, Scenario 2l - Spurious Residual Heat Removal
Minimum Flow Valve Failure to Open with Failure to Establish a Discharge Path
This scenario involved the spurious operation of a residual heat removal pump in the
non-credited train in combination with the spurious closure of the associated minimum
flow valve (1E12*MOVF064A, 1E12*MOVF064B, or 1E12*MOVF064C). The concern
was that the failure to establish a discharge path would lead to pump damage and
possible seal failure for the residual heat removal pump. The loss of suppression pool
inventory through the failed seal could negatively impact the safe shutdown pumps that
take suction from the suppression pool.
This scenario was originally evaluated in EPM Report P2083-07-001. This report
recommended the following additional actions:
- Perform a more detailed circuit analysis or evaluate fire modeling to eliminate the
concern,
- Perform an evaluation to determine whether pump overheating or cavitation
could result in pump/pipe damage, and
- Perform a calculation for water inventory control versus loss rate in case of
system piping failure to determine acceptable plant response times.
These scenarios were also evaluated in ENERCON Report ENTGRB083-PR-01. This
report stated:
As a property protection measure, consider tripping a non-credited residual heat
removal pump locally (at the respective switchgear) should it spuriously start with
a fire in the areas in the areas identified above.
The licensee did not complete the recommended actions by the end of the enforcement
discretion period. The licensee identified that the actions were not completed and
issued Condition Report CR-RBS-2013-0515 on January 29, 2013.
Although the actions were not complete, the licensee did have a contractor calculation
(P2265-0001-1.12) that estimated the time to pump damage after deadheading. This
calculation estimated that a residual heat removal pump would reach its maximum
design temperature of 360 °F within 21.7 minutes after deadheading. The post-fire safe
shutdown procedure was not updated with this information prior to the inspection.
The team concluded that the evaluation contained in ENERCON Report ENTGRB083-
PR-01 was inadequate since it focused on the property protection aspect of the scenario
and failed to consider the safe shutdown aspect of the scenario. Specifically, the team
noted that this scenario could result in pump damage within a relatively short amount of
time which could result in a seal failure and subsequent loss of suppression pool
inventory. The team concluded that the corrective actions were untimely since they
were not completed by the end of the enforcement discretion period. These actions
were still not completed prior to the beginning of the inspection.
- 10 - Enclosure 2
The licensee entered this issue into their corrective action program for further evaluation
and implemented enhanced operator rounds as a compensatory measure for this issue.
Analysis. The failure to implement all of the required corrective actions for multiple
spurious operations concerns in a timely manner was a performance deficiency. The
performance deficiency was more than minor because it was associated with the
protection against external events (fire) attribute of the Mitigating Systems Cornerstone
and it adversely affected the cornerstone objective of ensuring the availability, reliability,
and capability of systems that respond to initiating events to prevent undesirable
consequences.
The team evaluated this finding using Inspection Manual Chapter 0609, Appendix F,
Fire Protection Significance Determination Process, dated September 20, 2013,
because it affected the ability to reach and maintain safe shutdown conditions in case of
a fire. A senior reactor analyst performed a Phase 3 evaluation to determine the risk
significance of this finding since it involved multiple fire areas.
Example 1: Plant-Specific Scenario Diverting the Suppression Pool Inventory to the
Upper Fuel Pool
This scenario involved the spurious opening of the return valve from the residual heat
removal system to the upper pool (1E12*MOVF037A or 1E12*MOVF037B) in the non-
credited train in combination with the spurious operation of the residual heat removal
pump in the non-credited train. The concern was that the residual heat removal pump
would transfer inventory from the suppression pool to the upper pool and negatively
impact the safe shutdown pumps that take suction from the suppression pool.
The senior reactor analyst noted that the upper pool could receive a limited amount of
suppression pool inventory before overfilling. Once the upper pool was full, then any
additional suppression pool inventory would spill back down into the suppression pool.
In response to the senior reactor analysts questions, the licensee performed a
calculation to determine the amount of inventory that was required to fill the upper pool
and the resulting change in net positive suction head for the safe shutdown pumps that
took suction from the suppression pool. The licensee determined that the residual heat
removal pumps could transfer approximately 28,165 gallons of suppression pool
inventory before the upper pool overfilled. This corresponded to a change in net positive
suction head of approximately 6 inches.
The senior reactor analyst reviewed the available and required net positive suction head
for the safe shutdown pumps that took suction from the suppression pool. The senior
reactor analyst noted that the smallest margin between the available and required net
positive suction head was approximately 18 inches. Since the reduction of 6 inches of
net positive suction head would not prevent the safe shutdown pumps from operating,
the senior reactor analyst concluded that this example would lead to a negligible change
in core damage frequency. Therefore, the senior reactor analyst concluded that this
example was of very low safety significance (Green).
- 11 - Enclosure 2
Example 2: NEI 00-01, Revision 2, Scenario 2ab - Spurious Opening of Both Reactor
Core Isolation Cooling Test Return to Condensate Storage Tank Valves with Suction
from the Suppression Pool Transferring Inventory to the Condensate Storage Tank
This scenario involved the spurious operation of the reactor core isolation cooling pump
in combination with the spurious operation of multiple valves (1E51*MOVF031,
1E51*MOVF022, and 1E51*MOVF059) required to transfer inventory to the condensate
storage tank. The concern was that the reactor core isolation cooling pump would
transfer inventory from the suppression pool to the condensate storage tank and
negatively impact the safe shutdown pumps that take suction from the suppression pool.
The senior reactor analyst noted that the condensate storage tank was located at a
higher elevation than the suppression pool. Since the reactor core isolation cooling
pump was normally lined up to take a suction from the condensate storage tank, the
senior reactor analyst noted that the reactor core isolation cooling pump would
preferentially take a suction from the condensate storage tank rather than the
suppression pool.
In response to the senior reactor analysts questions, the licensee performed a
calculation to determine the fraction of suction flow from the condensate storage tank
versus the suppression pool for this scenario. The licensee determined that all of the
flow would come from the condensate storage tank. Since this would result in a
recirculation loop for the reactor core isolation cooling pump that did not reduce any
suppression pool inventory, the senior reactor analyst concluded that this example would
lead to a negligible change in core damage frequency. Therefore, the senior reactor
analyst concluded that this example was of very low safety significance (Green).
Example 3: NEI 00-01, Revision 2, Scenario2) - Spurious Residual Heat Removal
Minimum Flow Valve Failure to Open with Failure to Establish a Discharge Path
This scenario involved the spurious operation of a residual heat removal pump in the
non-credited train in combination with the spurious closure of the associated minimum
flow valve (1E12*MOVF064A, 1E12*MOVF064B, or 1E12*MOVF064C). The concern
was that the failure to establish a discharge path would lead to pump damage and
possible seal failure for the residual heat removal pump. The loss of suppression pool
inventory through the failed seal could negatively impact the safe shutdown pumps that
take suction from the suppression pool.
Since this issue could not be screened out using a qualitative evaluation, the team
performed a plant walkdown to identify fire source/target combinations that could lead to
these fire scenarios. Using the spreadsheets from NUREG-1805, Fire Dynamics Tools
(FDTs) Quantitative Fire Hazard Analysis Methods for the U.S. Nuclear Regulatory
Commission Fire Protection Inspection Program, the team identified six different
source/target combinations (for a total of nine fire scenarios) that could lead to these
For each scenario, the senior reactor analyst calculated a bounding change in core
damage frequency using the following equation:
CDF = FIF x SF x PNS x PMSO x HEP
- 12 - Enclosure 2
where: FIF denotes the fire ignition frequency adjusted for the number of vertical
sections (for electrical panels) or the critical area (for transients),
SF denotes the severity factor,
PNS denotes the manual non-suppression probability,
PMSO denotes the probability of circuit failures leading to the multiple spurious
operations, and
HEP denotes the human error probability for operators failing to mitigate the
scenario.
The senior reactor analyst used Manual Chapter 0609, Appendix F, Fire Protection
Significance Determination Process, dated September 20, 2013, to obtain values for the
fire ignition frequency, severity factor, and non-suppression probability. The senior
reactor analyst used the best available information contained in the Interim Guidance
Pending Publication of Expert Elicitation Results (ML13165A214) to obtain a value for
the probability of circuit failures leading to the multiple spurious operations.
The senior reactor analyst used the SPAR-H methodology to obtain a human error
probability for these scenarios. In response to the senior reactor analysts questions, the
licensee determined a maximum leak rate of approximately 120 gpm due to a seal
failure. Using the information provided in the first example, the senior reactor analyst
estimated that operators had more than 11 hours1.273148e-4 days <br />0.00306 hours <br />1.818783e-5 weeks <br />4.1855e-6 months <br /> to diagnose the scenario and send an
operator to close the upstream suction valve. The analyst assigned a nominal time of 75
minutes for diagnosis and 20 minutes for action and an available time of 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> for
diagnosis and 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> for action. The senior reactor analyst used the SPAR-H
methodology and calculated a human error probability of 3.02E-3.
The following table summarizes the Phase 3 evaluation results.
- 13 - Enclosure 2
Heat
Ignition Fire
Release FIF SF PNS PMSO HEP CDF
Source Target
Rate
1RSS* 1RSS*
200 kW 6.00E-05 0.9 1.00 0.81 3.02E-3 1.32E-07
PNL102 PNL102
1RSS* 1RSS*
650 kW 6.00E-05 0.1 1.00 0.81 3.02E-3 1.46E-08
PNL102 PNL102
1ENB-
1TC085R 200 kW 1.20E-04 0.1 1.00 0.56 3.02E-3 2.03E-08
SWG01A
1ENB-
1TC087R 200 kW 2.40E-04 0.1 0.35 0.56 3.02E-3 1.42E-08
INV01A1
1EHS-
200 kW
MCC8A/ 1TC087R 5.17E-05 1 1.00 0.56 3.02E-3 8.74E-08
(HEAF)
14A
Transients 1TC088R 200 kW 3.02E-07 0.1 0.58 0.56 3.02E-3 2.97E-11
Transients 1TC089R 200 kW 3.02E-07 0.1 1.00 0.56 3.02E-3 5.11E-11
1C61* 1C61*
200 kW 1.20E-04 0.9 1.00 0.56 3.02E-3 1.83E-07
PNLP001 PNLP001
1C61* 1C61*
650 kW 1.20E-04 0.1 1.00 0.56 3.02E-3 2.03E-08
PNLP001 PNLP001
Total 4.71E-07
In accordance with the guidance in Manual Chapter 0609, Appendix H, Containment
Integrity Significance Determination Process, the senior reactor analyst screened the
finding for its potential risk contribution to large early release frequency since the
bounding change in core damage frequency provided a risk significance estimate
greater than 1E-7.
The issue represented a Type A finding, based on the guidance in Appendix H, because
the finding influenced the likelihood of accidents leading to core damage. As
documented in Appendix H, Table 5.1, accident sequences that lead to large early
release frequency for boiling water reactors with Mark III containment include high
pressure transient events.
The analyst utilized the plant-specific standardized plant analysis risk model and
determined that most of the sequences involving control room evacuation with a lack of
communications devices to assist operators in stabilizing the plant resulted in the reactor
coolant system being at high pressure at the time of vessel breach. Using Table 5.2,
Phase 2 Assessment Factors - Type A Findings at Full Power, the analyst selected a
large early release frequency factor of 0.2 for these sequences.
The sum of the large early release frequency score as stated in Step 3.2, LERF
Significance Evaluation, was then quantified. The change in large early release
frequency was estimated to be 9.42E-08. This value agrees with the result of the
change in core damage frequency evaluation that this example was of very low safety
significance (Green).
The finding had a cross-cutting aspect in the Work Practices component of the Human
Performance area because the licensee failed to ensure supervisory and management
- 14 - Enclosure 2
oversight of work activities, including contractors, such that nuclear safety was
supported. H.4(c)
Enforcement. Title 10 of the Code of Federal Regulations (10 CFR) Part 50,
Appendix B, Criterion XVI states that measures shall be established to assure that
conditions adverse to quality, such as failures, malfunctions, deficiencies, deviations,
defective material and equipment, and nonconformances are promptly identified and
corrected. Contrary to the above, from November 2, 2012, to November 21, 2013, the
licensee failed to promptly identify and correct conditions adverse to quality.
Specifically, the licensee failed to implement all of the required corrective actions for
multiple spurious operations concerns prior to November 2, 2012, which marked the
expiration of enforcement discretion contained in Enforcement Guidance
Memorandum 09-002.
The licensee entered this issue into their corrective action program as Condition Report
CR-RBS-2013-03465. Because the licensee failed to restore compliance within a
reasonable period of time after this violation was initially identified, this violation is being
treated as a cited violation, consistent with Section 2.3.2.a of the NRC Enforcement
Policy. This is a violation of 10 CFR Part 50, Appendix B, Criterion XVI. A Notice of
Violation is included with this report: VIO 05000458/2013007-01, Failure to Resolve
Noncompliances Associated with Multiple Spurious Operations in a Timely Manner.
.02 Passive Fire Protection
a. Inspection Scope
The team walked down accessible portions of the selected fire areas to observe the
material condition and configuration of the installed fire area boundaries (including walls,
fire doors, and fire dampers) and verify that the electrical raceway fire barriers were
appropriate for the fire hazards in the area. The team compared the installed
configurations to the approved construction details, supporting fire tests, and applicable
license commitments.
The team reviewed installation and qualification records for a sample of rated fire wraps
protecting circuits required for post-fire safe shutdown to ensure the material possessed
an appropriate fire rating and that the installation met the engineering design to achieve
the required 1-hour fire rating.
b. Findings
No findings were identified.
.03 Active Fire Protection
a. Inspection Scope
The team reviewed the design, maintenance, testing, and operation of the fire detection
and suppression systems in the selected fire areas. The team verified the automatic
detection systems and the manual and automatic suppression systems were installed,
tested, and maintained in accordance with the National Fire Protection Association code
- 15 - Enclosure 2
of record or approved deviations and that each suppression system was appropriate for
the hazards in the selected fire areas.
The team performed a walkdown of accessible portions of the detection and suppression
systems in the selected fire areas. The team also performed a walkdown of major
system support equipment in other areas (e.g., fire pumps and Halon supply systems) to
assess the material condition of these systems and components.
The team reviewed the electric and diesel fire pumps flow and pressure tests to verify
that the pumps met their design requirements.
The team assessed the fire brigade capabilities by reviewing training, qualification, and
drill critique records. The team also reviewed pre-fire plans and smoke removal plans
for the selected fire areas to determine if appropriate information was provided to fire
brigade members and plant operators to identify safe shutdown equipment and
instrumentation and to facilitate suppression of a fire that could impact post-fire safe
shutdown capability. In addition, the team inspected fire brigade equipment to determine
operational readiness for firefighting.
The team observed an unannounced fire drill and subsequent drill critique on
April 30, 2013, using the guidance contained in Inspection Procedure 71111.05AQ, Fire
Protection Annual/Quarterly. The team observed fire brigade members fight a
simulated pump motor fire in a control building equipment room. The team verified that
the licensee identified problems, openly discussed them in a self-critical manner at the
drill debrief, and identified appropriate corrective actions. Specific attributes evaluated
were:
- Proper wearing of turnout gear and self-contained breathing apparatus;
- Proper use and layout of fire hoses;
- Employment of appropriate firefighting techniques;
- Sufficient firefighting equipment was brought to the scene;
- Effectiveness of fire brigade leader communications, command, and control;
- Search for victims and propagation of the fire into other areas;
- Smoke removal operations;
- Utilization of pre-planned strategies;
- Adherence to the pre-planned drill scenario; and
- Drill objectives.
b. Findings
No findings were identified.
.04 Protection From Damage From Fire Suppression Activities
a. Inspection Scope
The team performed plant walkdowns and document reviews to verify that redundant
trains of systems required for hot shutdown, which are located in the same fire area,
would not be subject to damage from fire suppression activities or from the rupture or
inadvertent operation of fire suppression systems. Specifically, the team verified:
- 16 - Enclosure 2
- A fire in one of the selected fire areas would not directly, through production of
smoke, heat, or hot gases, cause activation of suppression systems that could
potentially damage all redundant safe shutdown trains,
- A fire in one of the selected fire areas or the inadvertent actuation or rupture of a
fire suppression system would not directly cause damage to all redundant trains
(e.g., sprinkler-caused flooding of other than the locally affected train), and
- Adequate drainage is provided in areas protected by water suppression systems.
b. Findings
No findings were identified.
.05 Alternative Shutdown Capability
a. Inspection Scope
Review of Methodology
The team reviewed the safe shutdown analysis, operating procedures, piping and
instrumentation drawings, electrical drawings, the Final Safety Analysis Report, and
other supporting documents to verify that hot and cold shutdown could be achieved and
maintained from outside the control room for fires that require evacuation of the control
room, with or without offsite power available.
The team conducted plant walkdowns to verify that the plant configuration was
consistent with the description contained in the safe shutdown and fire hazards
analyses. The team focused on ensuring the adequacy of systems selected for
reactivity control, reactor coolant makeup, reactor decay heat removal, process
monitoring instrumentation, and support systems functions.
The team also verified that the systems and components credited for shutdown would
remain free from fire damage. Finally, the team verified that the transfer of control from
the control room to the alternative shutdown location would not be affected by
fire-induced circuit faults (e.g., by the provision of separate fuses and power supplies for
alternative shutdown control circuits).
Review of Operational Implementation
The team verified that licensed and non-licensed operators received training on
alternative shutdown procedures. The team also verified that sufficient personnel to
perform a safe shutdown were trained and available onsite at all times, exclusive of
those assigned as fire brigade members.
The team performed a walkdown of the post-fire safe shutdown procedure with licensed
and non-licensed operators to determine the adequacy of the procedure. The team
verified that the operators could be reasonably expected to perform specific actions
within the time required to maintain plant parameters within specified limits. Time critical
actions that were verified included restoring electrical power, establishing control at the
- 17 - Enclosure 2
remote shutdown and local shutdown panels, establishing reactor coolant makeup, and
establishing decay heat removal.
The team also reviewed the periodic testing of the alternative shutdown transfer
capability and instrumentation and control functions to verify that the tests were
adequate to demonstrate the functionality of the alternative shutdown capability.
b. Findings
.1 Inadequate Alternative Shutdown Procedure
Introduction. The team identified a Green non-cited violation of Technical
Specification 5.4.1.d for the failure to implement and maintain adequate written
procedures covering fire protection program implementation. Specifically, the licensee
failed to maintain an alternative shutdown procedure that ensured operators could safely
shutdown the plant under all postulated control room fire scenarios.
Description. The licensee developed Procedure AOP-0031, Shutdown from Outside the
Main Control Room, Revision 320, to shutdown the reactor in the event a fire required
evacuation of the control room. The team performed a walkdown of this procedure and
identified a control room fire scenario where the procedure did not provide adequate
steps for operators to mitigate the scenario. Specifically, this procedure did not provide
steps for operators to mitigate a spurious injection from the high pressure core spray
system. This scenario could be caused by a control room fire that directly caused the
injection through a spurious high pressure core spray system actuation or indirectly
caused the injection through a spurious emergency core cooling system actuation signal.
The alternative shutdown procedure provided a caution for the operators which noted
that some injection systems could not be controlled from the remote shutdown panel and
could result in overfilling or overpressuring the reactor pressure vessel. The caution,
first added to the procedure in 2003, provided the high pressure and low pressure core
spray systems as examples.
Although the procedure provided a caution for the operators, the procedure failed to
provide steps for operators to mitigate the spurious injection of the high pressure core
spray system. In response to the teams concerns, the licensee indicated that operators
would be able to mitigate the scenario by opening the breakers associated with the high
pressure core spray pump. This action was documented and promulgated to operators
in Standing Order 270 during the inspection.
The licensee did not have a calculation to determine the amount of time available for
operators to isolate the high pressure core spray system prior to overfilling the reactor
pressure vessel. In order to obtain an estimate of the amount of time available, the
licensee performed a preliminary evaluation on the simulator. The licensee ran a
simulator scenario with the high reactor level (level 8) trip disabled due to fire damage
with the spurious injection of the high pressure core spray system. In this scenario, the
licensee observed that it took approximately 9 minutes for the reactor water level to
reach the bottom of the main steam lines. The team determined that this was an
insufficient amount of time to ensure operators would identify the spurious operation,
determine the appropriate mitigating action, determine the appropriate operator to
- 18 - Enclosure 2
perform the mitigating action, and complete the action prior to overfilling the reactor
pressure vessel.
The licensee entered this issue into their corrective action program. The licensee
implemented a corrective action for this issue by revising the alternative shutdown
procedure on June 18, 2013.
Analysis. The failure to maintain adequate written procedures covering fire protection
program implementation was a performance deficiency. The performance deficiency
was more than minor because it was associated with the procedure quality attribute of
the Mitigating Systems Cornerstone and it adversely affected the cornerstone objective
of ensuring the availability, reliability, and capability of systems that respond to initiating
events to prevent undesirable consequences.
The team evaluated this finding using Inspection Manual Chapter 0609, Appendix F,
Fire Protection Significance Determination Process, dated September 20, 2013,
because it affected the ability to reach and maintain safe shutdown conditions in case of
a fire. A senior reactor analyst performed a Phase 3 evaluation to determine the risk
significance of this finding since it involved a postulated control room fire that led to
control room evacuation.
Because the River Bend Station control room included the plant instrumentation and
relay cabinets for Divisions I and II, the senior reactor analyst added a generic fire
ignition frequency for the relay room (FIFIR) to the control room fire ignition frequency
(FIFCR) listed in the Individual Plant Examination for External Events. The analyst
multiplied the combined fire ignition frequency by a severity factor (SF) and a non-
suppression probability indicating that operators failed to extinguish the fire within 20
minutes, assuming a 2 minute detection that required a control room evacuation (NPCRE).
The resulting control room evacuation frequency (FCR-EVAC) was:
FCR-EVAC = (FIFCR + FIFIR) * SF * NPCRE
= (9.50E-3/yr + 1.42E-3/yr) * 0.2 * 1.30E-2
= 2.84E-5/yr
The control room had a total of 109 electrical and control cabinets. The analyst
determined that a fire in one of these cabinets could lead to the spurious operation and
loss of control function for the high pressure core spray system which could result in
overfilling the reactor vessel to the main steam lines or above. The analyst calculated a
bounding change in core damage frequency for the finding (CDFFIRE-HPCS) by multiplying
the control room evacuation frequency by the fraction of panels containing the affected
circuits.
CDFFIRE-HPCS = FCR-EVAC * 1 / 109
= 2.84E-5/yr * 0.0092
= 2.61E-7/yr
This frequency was considered to be bounding since it assumed:
- 19 - Enclosure 2
- Fire damage in the applicable cabinet would create circuit faults such that the
high pressure core spray system spuriously injected and the level 8 trip was
disabled, resulting in overfilling the reactor vessel above the main steam lines;
- The conditional core damage probability given a control room fire with evacuation
and the spurious injection of the high pressure core spray system was equal to
one; and
- The performance deficiency accounted for the entire change in core damage
frequency (i.e., the baseline core damage frequency for this event was zero)
In accordance with the guidance in Manual Chapter 0609, Appendix H, Containment
Integrity Significance Determination Process, the senior reactor analyst screened the
finding for its potential risk contribution to large early release frequency since the
bounding change in core damage frequency provided a risk significance estimate
greater than 1E-7.
The issue represented a Type A finding, based on the guidance in Appendix H, because
the finding influenced the likelihood of accidents leading to core damage. As
documented in Appendix H, Table 5.1, accident sequences that lead to large early
release frequency for boiling water reactors with Mark III containment include high
pressure transient events.
The analyst determined that most of the sequences involving control room evacuation
with spurious operation of the high pressure core spray system resulted in the reactor
coolant system being at high pressure at the time of vessel breach. Using Table 5.2,
Phase 2 Assessment Factors - Type A Findings at Full Power, the analyst selected a
large early release frequency factor of 0.2 for these sequences.
The sum of the large early release frequency score as stated in Step 3.2, LERF
Significance Evaluation, was then quantified. The change in large early release
frequency was estimated to be 5.22E-08. This value agrees with the result of the
change in core damage frequency evaluation that the finding was of very low safety
significance (Green).
The finding did not have a cross-cutting aspect since it was not indicative of present
performance in that the performance deficiency occurred more than three years ago.
Enforcement. Technical Specification 5.4.1.d states that written procedures shall be
established, implemented, and maintained covering fire protection program
implementation. Contrary to the above, from 2003 to November 21, 2013, the licensee
failed to establish, implement, and maintain adequate written procedures covering fire
protection program implementation. Specifically, the licensee failed to maintain an
alternative shutdown procedure that provided steps for operators to mitigate a spurious
injection from the high pressure core spray system.
Because this violation was of very low safety significance and has been entered into the
corrective action program (Condition Report CR-RBS-2013-03150), this violation is
being treated as a non-cited violation, consistent with Section 2.3.2.a of the NRC
Enforcement Policy: NCV 05000458/2013007-02, Inadequate Alternative Shutdown
Procedure.
- 20 - Enclosure 2
.2 Failure to Properly Calculate the Time Available for Operator Actions
Introduction. The team identified a Green non-cited violation of License
Condition 2.C.(10) for the failure to implement and maintain in effect all provisions of the
approved fire protection program. Specifically, the licensee failed to properly calculate
the amount of time available for operators to perform time critical actions for all control
room fire scenarios.
Description. Following the 2010 triennial fire protection inspection, the licensee
reviewed the design basis for determining the amount of time available for operators to
perform select time critical actions in the alternative shutdown procedure. The licensee
determined that several different calculations formed the design basis for determining
the amount of time available.
These calculations were performed in accordance with the safe shutdown analysis and
determined the amount of time available for operators to perform specific actions under
various alternative shutdown scenarios. The safe shutdown analysis incorporated NRC
staff guidance related to control room fire scenarios. Specifically, the safe shutdown
analysis made the following two assumptions: (1) offsite power was lost as well as the
automatic starting of the emergency diesel generators and (2) the automatic function of
valves and pumps whose control circuits could be affected by a control room fire was
lost. The safe shutdown analysis also noted that the only manual action in the control
room prior to evacuation given credit was the reactor trip. Finally, the safe shutdown
analysis noted that the safe shutdown capability should not be adversely affected by any
one spurious action or signal resulting from a fire.
The team reviewed the assumptions, methods, and results of these calculations. The
team identified one alternative shutdown scenario where the licensee failed to properly
calculate the amount of time available for operators to perform time critical actions. This
scenario involved the amount of time available to terminate feedwater injection prior to
overfilling the reactor vessel.
For this scenario, the team noted that overfilling the reactor vessel could disable the
reactor core isolation cooling system and damage the steam lines. The reactor core
isolation cooling system was relied upon in this scenario to restore and maintain reactor
vessel level and control pressure. Overfilling the reactor vessel could also damage the
safety relief valves since they were not analyzed to pass high pressure water.
This issue was first identified during the 2010 triennial fire protection inspection as non-
cited violation 05000458/2010006-03. In response to this violation, the licensee revised
the alternative shutdown procedure to direct the auxiliary control room operators to
immediately terminate feedwater injection by closing the condensate demineralizer
service inlet and outlet isolation valves. The nominal stroke time for these motor-
operated valves was 48 seconds.
In addition, the licensee performed Calculation G13.18.12.2-139, Estimated Time to
Overfill the RPV Due to Continued Feedwater Operation During a Fire in the Main
Control Room, Revision 0, to determine the amount of time available for operators to
terminate feedwater injection prior to overfilling the reactor pressure vessel. This
calculation concluded that operators would have less than 45 seconds available to
terminate feedwater injection if all three of the normally running feedwater pumps
- 21 - Enclosure 2
continued to inject. Based on this calculation, the licensee concluded that the overfill
condition happens so quickly that manual action outside of the control room to mitigate
the concern has a low probability of success. Further, the licensee concluded that
directing the Auxiliary Control Room to close the condensate demin filter valves and the
actual closing of the valves would require more than one minute.
The licensee then generated a corrective action item to perform an evaluation that could
be used as a basis for a deviation request to justify the manual actions to be taken in the
auxiliary control room of closing the condensate demineralizer filter valves for preventing
reactor vessel overfill during a control room fire scenario with the continued injection of
The licensee subsequently revised Calculation G13.18.12.2-139 to examine scenarios
where one or two feedwater pumps continued to inject and the remaining feedwater
pumps stopped. The revised calculation concluded that operators would have
approximately 2 minutes available to terminate feedwater injection if only one of the
normally running feedwater pumps continued to inject. The licensee performed a timed
walkdown of these steps and concluded that operators could perform the required
actions within a range of 1 minute 53 seconds to 2 minutes 15 seconds. The licensee
concluded that no deviation request was necessary since operators could reasonably
perform the actions within the required time and the actions could not be undone by a
control room fire. Further, the licensee noted that this control room fire scenario involved
multiple spurious actuations.
The team reviewed the licensees evaluation and concluded that the licensee incorrectly
implemented the guidance for control room fires contained in the safe shutdown
analysis. Specifically, the team noted that the continued injection of the feedwater
pumps and the loss of automatic actuation/trip signals were part of the design
assumptions for a control room fire and were not considered to be spurious actuations.
The team concluded that the bounding control room fire scenario involved the continued
injection of all three normally running feedwater pumps and operators had less than 45
seconds to terminate feedwater injection.
Based on the timed walkdown of the alternative shutdown procedure, the team
determined that the auxiliary control room operators would complete the immediate
action of terminating feedwater injection in approximately 2 minutes 5 seconds.
The licensee entered this issue into their corrective action program for further evaluation
and implemented enhanced operator rounds as a compensatory measure for this issue.
Analysis. The failure to properly calculate the amount of time available for operators to
perform time critical actions for all control room fire scenarios was a performance
deficiency. The performance deficiency was more than minor because it was associated
with the protection against external events (fire) attribute of the Mitigating Systems
Cornerstone and it adversely affected the cornerstone objective of ensuring the
availability, reliability, and capability of systems that respond to initiating events to
prevent undesirable consequences.
The team evaluated this finding using Inspection Manual Chapter 0609, Appendix F,
Fire Protection Significance Determination Process, dated September 20, 2013,
because it affected the ability to reach and maintain safe shutdown conditions in case of
- 22 - Enclosure 2
a fire. A senior reactor analyst performed a Phase 3 evaluation to determine the risk
significance of this finding since it involved a postulated control room fire that led to
control room evacuation.
Because the River Bend Station control room included the plant instrumentation and
relay cabinets for Divisions I and II, the senior reactor analyst added a generic fire
ignition frequency for the relay room (FIFIR) to the control room fire ignition frequency
(FIFCR) listed in the Individual Plant Examination for External Events. The analyst
multiplied the combined fire ignition frequency by a severity factor (SF) and a non-
suppression probability indicating that operators failed to extinguish the fire within 20
minutes, assuming a 2 minute detection that required a control room evacuation (NPCRE).
The resulting control room evacuation frequency (FCR-EVAC) was:
FCR-EVAC = (FIFCR + FIFIR) * SF * NPCRE
= (9.50E-3/yr + 1.42E-3/yr) * 0.2 * 1.30E-2
= 2.84E-5/yr
The control room had a total of 109 electrical and control cabinets. The analyst
determined that a fire in one of these cabinets could lead to the spurious operation and
loss of control function for the feedwater system which could result in overfilling the
reactor vessel to the main steam lines or above. The analyst calculated a bounding
change in core damage frequency for this example (CDFCR-FW) by multiplying the
control room evacuation frequency by the fraction of panels containing the affected
circuits.
CDFCR-FW = FCR-EVAC * 1 / 109
= 2.84E-5/yr * 0.0092
= 2.61E-7/yr
This frequency was considered to be bounding since it assumed:
- Fire damage in the applicable cabinet would create circuit faults such that the
feedwater pumps continued to operate and the level 8 trip was disabled, resulting
in overfilling the reactor vessel above the main steam lines;
- The conditional core damage probability given a control room fire with evacuation
and the spurious injection of the feedwater system was equal to one; and
- The performance deficiency accounted for the entire change in core damage
frequency (i.e., the baseline core damage frequency for this event was zero).
In accordance with the guidance in Manual Chapter 0609, Appendix H, Containment
Integrity Significance Determination Process, the senior reactor analyst screened the
finding for its potential risk contribution to large early release frequency since the
bounding change in core damage frequency provided a risk significance estimate
greater than 1E-7.
- 23 - Enclosure 2
The issue represented a Type A finding, based on the guidance in Appendix H, because
the finding influenced the likelihood of accidents leading to core damage. As
documented in Appendix H, Table 5.1, accident sequences that lead to large early
release frequency for boiling water reactors with Mark III containment include high
pressure transient events.
The analyst determined that most of the sequences involving control room evacuation
with spurious operation of the feedwater system resulted in the reactor coolant system
being at high pressure at the time of vessel breach. Using Table 5.2, Phase 2
Assessment Factors - Type A Findings at Full Power, the analyst selected a large early
release frequency factor of 0.2 for these sequences.
The sum of the large early release frequency score as stated in Step 3.2, LERF
Significance Evaluation, was then quantified. The change in large early release
frequency was estimated to be 5.22E-08. This value agrees with the result of the
change in core damage frequency evaluation that this example was of very low safety
significance (Green).
The finding had a cross-cutting aspect in the Decision Making component of the Human
Performance area because the licensee failed to use conservative assumptions in
decision making when applying the guidance for control room fires contained in the safe
shutdown analysis. H.1(b)
Enforcement. License Condition 2.C.(10) requires that the licensee comply with the
requirements of their fire protection program as specified in Attachment 4. Attachment 4
states, in part, that the licensee shall implement and maintain in effect all provisions of
the approved fire protection program as described in the Final Safety Analysis Report for
the facility through Amendment 22 and as approved in the Safety Evaluation Report
dated May 1984 and Supplement 3 dated August 1985.
The fire protection program requirements are described in the Final Safety Analysis
Report, Section 9.5.1 and Appendices 9A and 9B. Appendix 9A references Design
Criterion 240.201A. Design Criterion 240.201A, Post-Fire Safe Shutdown Analysis,
Revision 4, contains the assumptions that need to be made for control room fire
scenarios. These assumptions include the statement that the safe shutdown capability
should not be adversely affected by any one spurious actuation or signal resulting from a
fire in any plant area.
Contrary to the above, prior to November 21, 2013, the licensee failed to implement and
maintain in effect all provisions of the approved fire protection program. Specifically, the
licensee failed to properly calculate the amount of time available for operators to perform
time critical actions. This resulted in the failure to ensure that the safe shutdown
capability would not be adversely affected by any one spurious actuation or signal
resulting from a fire in the control room.
Because this violation was of very low safety significance and has been entered into the
corrective action program (Condition Report CR-RBS-2013-03472), this violation is
being treated as a non-cited violation, consistent with Section 2.3.2.a of the NRC
Enforcement Policy: NCV 05000458/2013007-03, Failure to Properly Calculate the Time
Available for Operator Actions.
- 24 - Enclosure 2
.06 Circuit Analysis
a. Inspection Scope
The team reviewed the post-fire safe shutdown analysis to verify the licensee identified
the circuits that may impact the ability to achieve and maintain safe shutdown. The team
verified, on a sample basis, that the licensee properly identified the cables for equipment
required to achieve and maintain hot shutdown conditions in the event of a fire in the
selected fire areas. The team verified that these cables were either adequately
protected from the potentially adverse effects of fire damage or were analyzed to show
that fire-induced circuit faults (e.g., hot shorts, open circuits, and shorts to ground) would
not prevent safe shutdown. The team reviewed the circuits associated with the following
components:
- Main Steam Isolation Valves (1B21*AOVF028A and 1B21*AOVF022A)
- Shutdown Cooling Isolation High-Low Pressure Interface Valves
(E12-MOVF008 and E12-MOVF009)
- Residual Heat Removal Valves (RHR-6-B, 16-B, 49, 74-B, and 115-B)
- Flow Transmitter Contact Control Switch Modification (1KVK*CHL1B and
1HVK*CHL1D)
- Demineralization Valves associated with Post Fire Safe Shutdown to Isolate
Feedwater (CND-MOV10A-K and CND-MOV11A-K)
- Normal Service Water System
- Control Power for Over Current Trip Protection Capability of 4kV Breakers
For this sample, the team reviewed electrical elementary and block diagrams and
identified power, control, and instrument cables necessary to support their operation. In
addition, the team reviewed cable routing information to verify that fire protection
features were in place as needed to satisfy the separation requirements specified in the
fire protection license basis.
b. Findings
Introduction. The team identified an unresolved item associated with the isolation of
post-fire safe shutdown circuitry for control room fire scenarios. Specifically, the team
identified that the licensee may not adequately isolate circuitry for the safety relief valves
and the main steam isolation valves from the effects of a control room fire.
- 25 - Enclosure 2
Description. In the event of a fire in the control room, the licensee must ensure control
circuitry for equipment credited for post-fire safe shutdown is electrically isolated from
the control room so that fire damage could not prevent the ability to achieve and
maintain safe shutdown conditions. For valves that are required to close or remain
closed for post-fire safe shutdown, the licensee must ensure that control room fires do
not prevent the closure of the valves and do not spuriously open the valves once the
control room has been isolated and control transferred from the control room to the
remote shutdown panel.
Example 1: Spurious Opening of the Safety Relief Valves
The alternative shutdown procedure provided steps for operators to mitigate the effects
of any single spurious actuation or signal resulting from a control room fire that occurred
prior to transferring control from the control room to the remote shutdown panel. For the
safety relief valves, the procedure directed operators to de-energize two 125 Vdc panels
(ENB-PNL02A and ENB-PNL02B) in order to ensure that the 13 non-credited safety
relief valves were closed. The three credited safety relief valves were isolated from the
control room via the use of transfer switches.
The team identified a concern that hot shorts in the control room could cause a spurious
actuation that threatened the ability to achieve and maintain safe shutdown conditions.
The team noted that the control room cabinets containing the safety relief valves also
contained other 125 Vdc circuits that remained energized during an alternative
shutdown. The team was concerned that hot shorts from one of these circuits could
prevent the closure of a safety relief valve (if spuriously open) or could spuriously open
the safety relief valve once the control room was isolated and control transferred from
the control room to the remote shutdown panel. The team was also concerned that the
safe shutdown analysis did not analyze for one or more safety relief valves remaining
open during the plant shutdown. This concern applied to the 13 safety relief valves that
did not have control transferred to the remote shutdown panel.
In addition, the team noted that circuit failures could spuriously open multiple safety relief
valves through the spurious actuation of the automatic depressurization system. The
team was concerned that the spurious actuation of the automatic depressurization
system could be considered a single spurious actuation or signal that fell within the
bounds of the safe shutdown analysis. A similar concern was first identified during the
1997 fire protection functional inspection and documented in Inspection Reports97-201
and 98-16.
Example 2: Spurious Opening of the Main Steam Isolation Valves
As noted in the previous example, the alternative shutdown procedure provided steps for
operators to mitigate the effects of any single spurious actuation or signal resulting from
a control room fire that occurred prior to transferring control from the control room to the
remote shutdown panel. For the main steam isolation valves, the procedure directed
operators to attempt to close the main steam isolation valves inside the control room and
then de-energize the reactor protection system motor generator sets outside the control
room. The reactor protection system provides power to the circuitry for the main steam
isolation valve solenoids. When the solenoids are de-energized, the main steam
isolation valves fail closed.
- 26 - Enclosure 2
The team identified a concern that hot shorts in the control room could cause spurious
actuations that threatened the ability to achieve and maintain safe shutdown conditions.
Specifically, the team identified that a portion of the trip logic circuitry was connected in
the control room to the portion of the circuitry that energizes the solenoid valve for each
main steam isolation valve. The trip logic circuitry was located downstream of where the
reactor protection system bus was de-energized, and it did not contain a protective
circuit device such as fusing or open contacts that would isolate the trip logic portion of
the circuitry from the solenoid valve. The control room cabinet containing the trip logic
circuitry also contained other 125 Vdc circuits that remained energized during an
alternative shutdown.
The team was concerned that hot shorts from these circuits could prevent the closure of
the main steam isolation valves or could spuriously open the main steam isolation valves
after the reactor protection system motor generator sets were de-energized. The team
noted that one main steam isolation valve, either inboard or outboard, must close and
remain closed in order to maintain inventory.
The licensee entered these issues into the corrective action program as Condition
Report CR-RBS-2013-03473. The team determined that additional inspection is
required to determine if a performance deficiency exists. This issue of concern is being
treated as an Unresolved Item URI 05000458/2013007-04, Unresolved Item Associated
with the Isolation of the Alternative Shutdown System.
.07 Communications
a. Inspection Scope
The team inspected the contents of designated emergency storage lockers and
reviewed the alternative shutdown procedure to verify that portable radio
communications and fixed emergency communications systems were available,
operable, and adequate for the performance of designated activities. The team verified
the capability of the communication systems to support the operators in the conduct and
coordination of their required actions. The team also verified that the design and
location of communications equipment such as repeaters and transmitters would not
cause a loss of communications during a fire. The team discussed system design,
testing, and maintenance with the system engineer.
b. Findings
Introduction. The team identified a Green non-cited violation of License
Condition 2.C.(10) for the failure to implement and maintain in effect all provisions of the
approved fire protection program. Specifically, the licensee failed to ensure that the
communications systems would work under all postulated control room fire scenarios.
Description. The safe shutdown analysis described the four permanent communications
systems installed in the plant that operators could use when responding to a fire in the
plant. These systems included the plant paging system, radios, telephones, and a
portable intercom jack system.
For a fire in the control room, the safe shutdown analysis assumed the plant paging
system would be lost because system power originated from the control room. The
- 27 - Enclosure 2
analysis credited the remote shutdown panel room telephone as the primary
communication method and the portable intercom jack system as the backup
communication method. The analysis stated that the intercom jack system required the
use of switching equipment located in the auxiliary control room. The analysis also
stated that the distributed antenna system was not routed through the main control room
and would be unaffected by a control room fire. In particular, the analysis stated that
portable radios could still be used for communication between the remote shutdown
panel room and any plant location (except the control room or inside containment) in this
event.
During a control room walkdown, the team identified that a breaker for the radio system
shared the same cabinet as the breaker for the plant paging system. Based on
discussions with site communications personnel, the team concluded that a fire in this
cabinet could result in a loss of both the plant paging system and the radio system in the
control building. The team also noted that the portable intercom jack system required
additional equipment to use that was not staged at the remote shutdown panel, and
operators did not obtain the equipment required for the intercom system during the timed
alternative shutdown walkdowns.
The team questioned whether a control room fire could affect the licensees telephone
system. In response to the teams question, the licensee discovered that the telephones
in the remote shutdown panel rooms did not work. The licensee returned the telephones
to service on April 24, 2013.
The licensee subsequently determined that the phones were disconnected by Entergy
Telecom on May 10, 2012, prior to an upgrade of the site telephone system. The team
determined that the licensee failed to verify that emergency phone lines (including the
phones in the remote shutdown panel rooms) were not included on the list of phones to
be disabled. Further, the licensee did not have an onsite oversight process for Entergy
Telecom.
The licensee entered this issue into their corrective action program. The licensee
implemented a corrective action for this issue by returning the telephones to service on
April 24, 2013.
Analysis. The failure to ensure that the communications systems would work under all
postulated control room fire scenarios was a performance deficiency. The performance
deficiency was more than minor because it was associated with the protection against
external events (fire) attribute of the Mitigating Systems Cornerstone and it adversely
affected the cornerstone objective of ensuring the availability, reliability, and capability of
systems that respond to initiating events to prevent undesirable consequences.
The team evaluated this finding using Inspection Manual Chapter 0609, Appendix F,
Fire Protection Significance Determination Process, dated September 20, 2013,
because it affected the ability to reach and maintain safe shutdown conditions in case of
a fire. A senior reactor analyst performed a Phase 3 evaluation to determine the risk
significance of this finding since it involved a postulated control room fire that led to
control room evacuation.
Because the River Bend Station control room included the plant instrumentation and
relay cabinets for Divisions I and II, the senior reactor analyst added a generic fire
- 28 - Enclosure 2
ignition frequency for the relay room (FIFIR) to the control room fire ignition frequency
(FIFCR) listed in the Individual Plant Examination for External Events. The analyst
multiplied the combined fire ignition frequency by a severity factor (SF) and a non-
suppression probability indicating that operators failed to extinguish the fire within 20
minutes, assuming a 2 minute detection that required a control room evacuation (NPCRE).
The resulting control room evacuation frequency (FCR-EVAC) was:
FCR-EVAC = (FIFCR + FIFIR) * SF * NPCRE
= (9.50E-3/yr + 1.42E-3/yr) * 0.2 * 1.30E-2
= 2.84E-5/yr
The control room had a total of 109 electrical and control cabinets. The analyst
determined that a fire in one of these cabinets could disable the plant paging system and
the radio system in the control building. The analyst calculated a bounding change in
core damage frequency for the finding (CDFFIRE-COM) by multiplying the control room
evacuation frequency by the fraction of panels containing the affected circuits.
CDFFIRE-COM = FCR-EVAC * 1 / 109
= 2.84E-5/yr * 0.0092
= 2.61E-7/yr
This frequency was considered to be bounding since it assumed:
- Fire damage in the applicable cabinet would create circuit faults such that the
plant paging system and the radio system in the control building were disabled,
- The conditional core damage probability given a control room fire with evacuation
and the loss of the plant paging system and radio system in the control building
was equal to one, and
- The performance deficiency accounted for the entire change in core damage
frequency (i.e., the baseline core damage frequency for this event was zero).
In accordance with the guidance in Manual Chapter 0609, Appendix H, Containment
Integrity Significance Determination Process, dated May 6, 2004, the senior reactor
analyst screened the finding for its potential risk contribution to large early release
frequency since the bounding change in core damage frequency provided a risk
significance estimate greater than 1E-7.
Based on the guidance in Appendix H, the issue represented a Type A finding because
the finding influenced the likelihood of accidents leading to core damage. As
documented in Appendix H, Table 5.1, accident sequences that lead to large early
release frequency for boiling water reactors with Mark III containment include high
pressure transient events.
The analyst utilized the plant-specific standardized plant analysis risk model and
determined that most of the sequences involving control room evacuation with a lack of
- 29 - Enclosure 2
communications devices to assist operators in stabilizing the plant resulted in the reactor
coolant system being at high pressure at the time of vessel breach. Using Table 5.2,
Phase 2 Assessment Factors - Type A Findings at Full Power, the analyst selected a
large early release frequency factor of 0.2 for these sequences.
The sum of the large early release frequency score as stated in Step 3.2, LERF
Significance Evaluation, was then quantified. The change in large early release
frequency was estimated to be 5.22E-08. This value agrees with the result of the
change in core damage frequency evaluation that the finding was of very low safety
significance (Green).
The finding had a cross-cutting aspect in the Work Practices component of the Human
Performance area because the licensee failed to ensure supervisory and management
oversight of work activities, including contractors, such that nuclear safety was
supported. H.4(c)
Enforcement. License Condition 2.C.(10) requires that the licensee comply with the
requirements of their fire protection program as specified in Attachment 4. Attachment 4
states, in part, that the licensee shall implement and maintain in effect all provisions of
the approved fire protection program as described in the Final Safety Analysis Report for
the facility through Amendment 22 and as approved in the Safety Evaluation Report
dated May 1984 and Supplement 3 dated August 1985.
The fire protection program requirements are described in the Final Safety Analysis
Report, Section 9.5.1 and Appendices 9A and 9B. Appendix 9A references Design
Criterion 240.201A. Design Criterion 240.201A, Post-Fire Safe Shutdown Analysis,
Revision 4, describes the permanent communications systems installed in the plant.
These systems include the plant paging system, radios, telephones, and a portable
intercom jack system.
The safe shutdown analysis credits the remote shutdown panel room telephone as the
primary communication method and the portable intercom jack system as the backup
communication method. Contrary to the above, from May 10, 2012, to April 24, 2013,
the licensee failed to implement and maintain in effect all provisions of the approved fire
protection program. Specifically, the licensee failed to ensure that the communications
systems would work under all postulated control room fire scenarios.
Because this violation was of very low safety significance and has been entered into the
corrective action program (Condition Reports CR-RBS-2013-03243 and
CR-RBS-2013-03397), this violation is being treated as a non-cited violation, consistent
with Section 2.3.2.a of the NRC Enforcement Policy: NCV 05000458/2013007-05,
Failure to Maintain Communication Systems Required for Alternative Shutdown
Scenarios.
a. Inspection Scope
The team reviewed the portion of the emergency lighting system required for alternative
shutdown to verify that it was adequate to support the performance of manual actions
required to achieve and maintain hot shutdown conditions and to illuminate access and
egress routes to the areas where manual actions would be required. The team
- 30 - Enclosure 2
evaluated the locations and positioning of the emergency lights during a walkdown of the
alternative shutdown procedure.
The team verified that the licensee installed emergency lights with an 8-hour capacity,
maintained the emergency light batteries in accordance with manufacturer
recommendations, and tested and performed maintenance in accordance with plant
procedures and industry practices.
b. Findings
Introduction. The team identified a Green finding for the failure to properly implement
the engineering change process. Specifically, the licensee failed to update the
Maintenance Rule program and perform the required preventive maintenance tasks after
the addition of three 8-hour Appendix R emergency lights. During subsequent discharge
testing, two of the three lights failed.
Description. On June 30, 2008, the licensee approved Engineering Change 4026, which
was developed to add three emergency lights to the population of 8-hour Appendix R
emergency lights. On July 2, 2008, the three emergency lights were added to the list of
Appendix R emergency lights in the safe shutdown analysis and the emergency light
drawings. Procedure EN-DC-115, Engineering Change Process, Revision 5,
Attachment 9.4, Detailed Impact Screening Criteria, required the responsible engineer
to review the engineering change for impacts to the Maintenance Rule and preventative
maintenance programs.
The team identified that the licensee failed to include the three emergency lights in the
Maintenance Rule program, even though the Appendix R emergency lighting system
was within the scope of the licensees Maintenance Rule program. The team reviewed
Engineering Change 4026 and noted that the responsible engineer considered the
Maintenance Rule aspects of the change, but concluded that the Maintenance Rule
program was not impacted. A reviewer commented on this issue to ensure the
Maintenance Rule program included the three emergency lights. This comment was
resolved with a similar statement that the Maintenance Rule program was not impacted.
The team concluded that the Maintenance Rule program was impacted, and the licensee
should have included the three additional lights into the program.
The team also identified that the licensee failed to implement the required preventive
maintenance tasks for the three emergency lights. The team noted that the licensee
identified an impact to the preventive maintenance program during the screening for
Engineering Change 4026. The licensee issued Action Request 34967 to add the three
emergency lights to the Appendix R lighting preventive maintenance tasks for monthly
functional testing, annual inspection, and battery replacement. This action request was
approved and marked as completed on November 23, 2009.
On August 2, 2011, an engineering contractor, who had previously been a program
engineer at the station, discovered that the emergency lights were added to the
preventive maintenance task for battery replacement, but not to the monthly functional
testing or annual inspection tasks. The action request had been in the engineers task
inbox when he retired and had not been transferred to another owner following his
departure. The contractor corrected the condition by issuing a second action request,
- 31 - Enclosure 2
Action Request 126683, but failed to write a condition report for the deficiency. Action
Request 126683 was not completed prior to the inspection.
The three emergency lights were added to the battery replacement preventive
maintenance task, but their batteries were not replaced as the preventive maintenance
task change occurred after the last performance of the task. The licensee last tested the
three lights on January 4, 2012, via the non-Appendix R emergency light preventive
maintenance task. This functional test ensured that the lights worked for a short
duration, but did not ensure the lights worked for the required 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />. In response to
the teams concerns, the licensee tested the three emergency lights and discovered that
one light did not work, one light worked for approximately 5 minutes, and one light met
the 8-hour lighting requirement.
The licensee entered this issue into their corrective action program. The licensee
implemented corrective actions for this issue by including the emergency lights in the
monthly functional testing and annual inspection tasks and including the emergency
lights in the Maintenance Rule program.
Analysis. The failure to properly implement the engineering change process was a
performance deficiency. The performance deficiency was more than minor because it
was associated with the protection against external events (fire) attribute of the
Mitigating Systems Cornerstone and it adversely affected the cornerstone objective of
ensuring the availability, reliability, and capability of systems that respond to initiating
events to prevent undesirable consequences.
The team evaluated this finding using Inspection Manual Chapter 0609, Appendix F,
Fire Protection Significance Determination Process, dated September 20, 2013,
because it affected the ability to reach and maintain safe shutdown conditions in case of
a fire. The team assigned the finding to the post-fire safe shutdown category since it
impacted the remote shutdown and control room abandonment element.
The team assigned the finding a low degradation rating since the ability to reach and
maintain safe shutdown conditions in the event of a control room fire would be minimally
impacted by the failure of the three emergency lights to function for 8-hours.
Specifically, the team determined that the alternative shutdown procedure provided
operators with an alternate method of verifying that the emergency diesel generator
breaker was closed. Because this finding had a low degradation rating, it screened as
having very low safety significance (Green).
The finding did not have a cross-cutting aspect since it was not indicative of present
performance in that the performance deficiency occurred more than three years ago.
Enforcement. This finding does not involve enforcement action because no violation of a
regulatory requirement was identified. The licensee entered this finding into the
corrective action program as Condition Reports CR-RBS-2013-03118 and
CR-RBS-2013-03273. Because this finding did not involve a violation and was of very
low safety significance, it is identified as FIN 05000458/2013007-06, Failure to
Implement the Engineering Change Process for Appendix R Lighting.
- 32 - Enclosure 2
.09 Cold Shutdown Repairs
a. Inspection Scope
The team verified that the licensee identified repairs needed to reach and maintain cold
shutdown and had dedicated repair procedures, equipment, and materials to accomplish
these repairs. Using these procedures, the team evaluated whether these components
could be repaired in time to bring the plant to cold shutdown within the time frames
specified in their design and licensing bases. The team verified that the repair
equipment, components, tools, and materials needed for the repairs were available and
accessible on site.
b. Findings
No findings were identified.
.10 Compensatory Measures
a. Inspection Scope
The team verified that compensatory measures were implemented for out-of-service,
degraded, or inoperable fire protection and post-fire safe shutdown equipment, systems,
or features (e.g., detection and suppression systems and equipment; passive fire
barriers; or pumps, valves, and electrical devices providing safe shutdown functions).
The team also verified that the short-term compensatory measures compensated for the
degraded function or feature until appropriate corrective action could be taken and that
the licensee was effective in returning the equipment to service in a reasonable period of
time.
The team reviewed operator manual actions credited for achieving hot shutdown for fires
that do not require an alternative shutdown. The team verified that operators could
reasonably be expected to perform the actions within the applicable shutdown time
requirements. The team reviewed these operator manual actions using the guidance
contained in NUREG-1852, Demonstrating the Feasibility and Reliability of Operator
Manual Actions in Response to Fire, dated October 2007.
b. Findings
No findings were identified.
.11 Review and Documentation of Fire Protection Program Changes
a. Inspection Scope
The team reviewed changes to the approved fire protection program. The team verified
that the changes did not constitute an adverse effect on the ability to safely shutdown.
The team also reviewed a modification the licensee made to the reactor recirculation
pumps oil system for impact on the approved fire protection program.
- 33 - Enclosure 2
b. Findings
No findings were identified.
.12 B.5.b Inspection Activities
a. Inspection Scope
The team reviewed the licensees implementation of guidance and strategies intended to
maintain or restore core, containment, and spent fuel pool cooling capabilities under the
circumstances associated with the potential loss of large areas of the plant due to
explosions or fire as required by Section B.5.b of the Interim Compensatory Measures
Order, EA-02-026, dated February 25, 2002, and 10 CFR 50.54(hh)(2).
The team verified that the licensee maintained and implemented adequate procedures,
maintained and tested the equipment necessary to properly implement the strategies,
and ensured station personnel were knowledgeable and capable of implementing the
procedures. The team performed a visual inspection of portable equipment used to
implement the strategy to ensure the availability and material readiness of the
equipment, including the adequacy of portable pump trailer hitch attachments, and verify
the availability of on-site vehicles capable of towing the portable pump. The team
assessed the off-site ability to obtain fuel for the portable pump and foam used for
firefighting efforts. The strategies and procedures selected for this inspection sample
included:
- OSP-0066, Extensive Damage Mitigation Procedure, Revision 21,
Attachment 12, Electrical Power Restoration Methods to Support Mitigation
Strategies
- OSP-0066, Extensive Damage Mitigation Procedure, Revision 21,
Attachment 19, Miscellaneous Strategies, Step 1.4, Emergency Makeup Water
Addition to Emergency Diesel Generator Jacket Water
Two B.5.b mitigating strategy samples were completed.
b. Findings
No findings were identified.
4. OTHER ACTIVITIES [OA]
4OA2 Identification and Resolution of Problems
Corrective Actions for Fire Protection Deficiencies
a. Inspection Scope
The team selected a sample of condition reports associated with the licensee's fire
protection program to verify that the licensee had an appropriate threshold for identifying
deficiencies. The team reviewed the corrective actions proposed and implemented to
verify that they were effective in correcting identified deficiencies. The team evaluated
- 34 - Enclosure 2
the quality of recent engineering evaluations through a review of condition reports,
calculations, and other documents during the inspection.
b. Findings
No findings were identified.
4OA6 Meetings, Including Exit
Exit Meeting Summary
The team presented the preliminary inspection results to Mr. E. Olson and other
members of the licensee staff at a debrief meeting on May 3, 2013. The team presented
updated inspection results to Mr. T. Evans and other members of the licensee staff
during a telephonic meeting on November 21, 2013. The team presented the final
inspection results to Mr. T. Evans and other members of the licensee staff during a
telephonic exit meeting on December 30, 2013. The licensee acknowledged the findings
presented.
The inspectors verified that no proprietary information was retained by the
inspectors or documented in this report.
4OA7 Licensee-Identified Violations
None
ATTACHMENT: SUPPLEMENTAL INFORMATION
- 35 - Enclosure 2
SUPPLEMENTAL INFORMATION
KEY POINTS OF CONTACT
Licensee Personnel
C. Blackledge, Senior Engineer
G. Bush, Manager, Materials, Purchasing, and Contracts
M. Chase, Manager, Training
J. Clark, Manager, Regulatory Assurance
F. Corley, Manager, Design and Program Engineering
R. Doerr, Supervisor, Engineering
T. Evans, Director, Regulatory and Performance Improvement
R. Gadbois, General Manager, Plant Operations
K. Huffstatler, Senior Licensing Specialist
A. Johnson, Fire Marshal
P. Lucky, Manager, Performance Improvement
W. Mashburn, Director, Engineering
C. Miller, Senior Project Manager, Engineering
E. Olson, Vice President, Operations
E. Roan, Senior Engineer
L. Woods, Manager, Nuclear Oversight
NRC Personnel
D. Frumkin, Fire Protection Team Leader
G. Larkin, Senior Resident Inspector
D. Loveless, Senior Reactor Analyst
G. Taylor, Fire Protection Engineer
LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED
Opened
Unresolved Item Associated with the Isolation of the
Alternative Shutdown System
Opened and Closed
Failure to Resolve Noncompliances Associated with
Multiple Spurious Operations in a Timely Manner
05000458/2013007-02 NCV Inadequate Alternative Shutdown Procedure
Failure to Properly Calculate the Time Available for
Operator Actions.
Failure to Maintain Communication Systems Required for
Alternative Shutdown Scenarios
Failure to Implement the Engineering Change Process for
Appendix R Lighting
-1- Attachment
LIST OF DOCUMENTS REVIEWED
CABLE ROUTING DATA COMPONENTS
1B21*AOVF022A 1SWP*AOV599 1SWP*MOV40D 1SWP*MOV81A
1B21*AOVF028A 1SWP*MOV171 1SWP*MOV507A 1SWP*MOV81B
1CND*MOV10A-K 1SWP*MOV172 1SWP*MOV507B 1SWP*MOV96A
1CND*MOV11A-K 1SWP*MOV173 1SWP*MOV55A 1SWP*MOV96B
1E12*MOVF008 1SWP*MOV174 1SWP*MOV55B 1SWP*P2B
1E12*MOVF009
CALCULATIONS
Number Title Revision
12210-E-200-239C Load Center Feeders 1NJS-4A & 4B 2
12210-E-221 Time-Current Characteristic Curves for TRANS-1STX- 1
XS2A & 2B
12210-E-222 Time-Current Characteristic Curves for 1MWS-P4A, 1
4B14C
12210-E-223 Time-Current Characteristic Curves for TRANS-1RTX- 1
XSR1C & 1D
12210-E-224 Time-Current Characteristic Curves for Chiller Motors 1
1HVN-CHL2A, B, & C
12210-E-231 Time-Current Characteristic Curves for 480V Load 1
Center 1EJS*SWG1A,2A,1B, 2B Incoming Feeds
12210-E-239A Time-Current Characteristic Curves for Pumps 1SWC- 1
P1A, 1B, & 1C
7214.400.273.062 Hydraulic Calculations WS-8D D
7214.400.273.076 Calculation System AS-1B B
ENTGRB083 Multiple Spurious Operation Circuit Analysis and 0
Scenario Disposition
G13.18.12.2-139 Estimated Time to Overfill the RPV Due to Continued 0
Feedwater Operation During a Fire in the Main Control
-2- Attachment
Room
G13.18.12.2-27 10 CFR 50 Appendix R Manual Action Time Frame 1
G13.18.13.2*84 Condenser Pressure During Loss of Circulating Water 0
G13.18.14.0*29 Reactor Level Response to a Fire in the Control Room 1
G13.18.14.4*42 Safe Shutdown Scenario Evaluation Regarding the 1
Emergency Operating Procedures and Emergency
Depressurization
G13.18.2.6*34 Determine No. of SRV Actuations from LSV Air 2
Receiver
G13.18.3.6*012 10 CFR 50 Appendix R Analysis of Fire Area PT-1 0
G13.18.3.6*012 10 CFR 50 Appendix R Analysis of Fire Area PT-1 A
CONDITION REPORTS
CR-HQN-2012-00684 CR-RBS-2011-08112 CR-RBS-2012-06622
CR-RBS-1997-00991 CR-RBS-2012-00344 CR-RBS-2012-06623
CR-RBS-2007-02159 CR-RBS-2012-00578 CR-RBS-2012-07320
CR-RBS-2008-01869 CR-RBS-2012-00604 CR-RBS-2012-07847
CR-RBS-2008-04481 CR-RBS-2012-00813 CR-RBS-2013-00165
CR-RBS-2008-05348 CR-RBS-2012-00985 CR-RBS-2013-00167
CR-RBS-2008-05538 CR-RBS-2012-01013 CR-RBS-2013-00169
CR-RBS-2008-05552 CR-RBS-2012-01260 CR-RBS-2013-00190
CR-RBS-2009-01602 CR-RBS-2012-01263 CR-RBS-2013-00192
CR-RBS-2009-06539 CR-RBS-2012-01349 CR-RBS-2013-00193
CR-RBS-2010-00017 CR-RBS-2012-01456 CR-RBS-2013-00198
CR-RBS-2010-01775 CR-RBS-2012-01554 CR-RBS-2013-00292
CR-RBS-2010-01783 CR-RBS-2012-01581 CR-RBS-2013-00323
CR-RBS-2010-01808 CR-RBS-2012-02146 CR-RBS-2013-00407
CR-RBS-2010-01849 CR-RBS-2012-02277 CR-RBS-2013-00436
-3- Attachment
CR-RBS-2010-01850 CR-RBS-2012-02374 CR-RBS-2013-00515
CR-RBS-2010-01971 CR-RBS-2012-02515 CR-RBS-2013-00541
CR-RBS-2011-01671 CR-RBS-2012-02522 CR-RBS-2013-00545
CR-RBS-2011-02171 CR-RBS-2012-03149 CR-RBS-2013-00819
CR-RBS-2011-02177 CR-RBS-2012-03438 CR-RBS-2013-01046
CR-RBS-2011-02209 CR-RBS-2012-03440 CR-RBS-2013-01046
CR-RBS-2011-02272 CR-RBS-2012-03473 CR-RBS-2013-01274
CR-RBS-2011-03511 CR-RBS-2012-03474 CR-RBS-2013-01473
CR-RBS-2011-03821 CR-RBS-2012-03524 CR-RBS-2013-01872
CR-RBS-2011-03822 CR-RBS-2012-03533 CR-RBS-2013-02218
CR-RBS-2011-04041 CR-RBS-2012-03817 CR-RBS-2013-02408
CR-RBS-2011-04105 CR-RBS-2012-03960 CR-RBS-2013-02678*
CR-RBS-2011-04131 CR-RBS-2012-04118 CR-RBS-2013-02702*
CR-RBS-2011-04582 CR-RBS-2012-04515 CR-RBS-2013-02970
CR-RBS-2011-04607 CR-RBS-2012-04686 CR-RBS-2013-02987*
CR-RBS-2011-04714 CR-RBS-2012-05007 CR-RBS-2013-03020*
CR-RBS-2011-04895 CR-RBS-2012-05011 CR-RBS-2013-03118*
CR-RBS-2011-05518 CR-RBS-2012-05018 CR-RBS-2013-03150*
CR-RBS-2011-05784 CR-RBS-2012-05029 CR-RBS-2013-03177*
CR-RBS-2011-05788 CR-RBS-2012-05032 CR-RBS-2013-03243*
CR-RBS-2011-05882 CR-RBS-2012-05062 CR-RBS-2013-03273*
CR-RBS-2011-06100 CR-RBS-2012-05187 CR-RBS-2013-03350*
CR-RBS-2011-06428 CR-RBS-2012-05217 CR-RBS-2013-03352*
CR-RBS-2011-06453 CR-RBS-2012-05259 CR-RBS-2013-03397*
CR-RBS-2011-07359 CR-RBS-2012-05289 CR-RBS-2013-03440*
-4- Attachment
CR-RBS-2011-07421 CR-RBS-2012-05467 CR-RBS-2013-03464*
CR-RBS-2011-07540 CR-RBS-2012-05716 CR-RBS-2013-03471*
CR-RBS-2011-07644 CR-RBS-2012-05845 CR-RBS-2013-03473*
CR-RBS-2011-07955 CR-RBS-2012-06009 CR-RBS-2013-03556*
CR-RBS-2011-07983 CR-RBS-2012-06619 LO-NOE-2009-00516
- Issued as a result of inspection activities.
DESIGN CRITERIA
Number Title Revision
240.201A Post-Fire Safe Shutdown Analysis 4
DRAWINGS
Number Title Revision
0214.400-273-007, Water Spray & Sprinkler Fire Protection 6
Sheet 1
0214.400-273-007, Water Spray & Sprinkler Fire Protection 6
Sheet 2
0214.400-273-083, Water Spray & Sprinkler Fire Protection 0
Sheet 1
0214.400-273-196 Sprinkler System Partial Plan Elevation 98-0 Control 0
Building
0214.400-273-198 Sprinkler System Isometric Elevation 98-0 Control B
Building
0227.300-090-244 Schematic Wiring Diagram Valve Position Indicating F
Lights for Demin 1G
0244.700-041-083 Control Panel Schematic for EGS-PNL3A Standby 302
Diesel Generator EGS-EG1A
12210-EE-18G-4 Wiring Diagram Fire and Smoke Detection Control 4
Building - Elevation 115-0 & 116-0
12210-EE-34CC-4 Cable Tray Identification Control Building 4
-5- Attachment
12210-EE-34CH-3 Sections & Details Sleeves, Inserts & Openings 3
Auxiliary Building
12210-EE-34CJ-4 Sections & Details Sleeves, Inserts & Openings 4
Auxiliary Building
12210-EE-34CK-6 Sections & Details Sleeves, Inserts & Openings 6
Auxiliary Building
12210-EE-8OW-8 Communications Plan Standby Switchgear Area
Control Building
74109-445 Schematic Wiring Diagram Motor & Solenoid Actuated D
Valves for Demin 1G
828E445AA Elementary Diagram Nuclear Steam Supply Shut Off 28
System
851E225AA, Elementary Diagram Automatic Depressurization 23
Sheet 5 System
851E225AA, Automatic Depressurization System 14
Sheet 11
CDB-ISM108 Nuclear Steam Supply Shutoff System-Partial A
CDB-ISM110 Nuclear Steam Supply Shutoff System-Partial A
CE-001A Appendix R Safe-Shutdown Analysis Emergency 5
Lighting Control Building EL. 98-0
CE-001B Appendix R Safe-Shutdown Analysis Emergency 7
Lighting Control Building EL. 116-0
CE-001C Appendix R Safe-Shutdown Analysis Emergency 5
Lighting Control Building EL. 136-0
CE-001F Appendix R Safe-Shutdown Analysis Emergency 7
Lighting Diesel Generator Building EL. 98-0
CE-001H Appendix R Safe-Shutdown Analysis Emergency 2
Lighting Auxiliary Building EL. 95-0
CE-001J Appendix R Safe-Shutdown Analysis Emergency 6
Lighting Auxiliary Building EL. 114-0
CE-001K Appendix R Safe-Shutdown Analysis Emergency 6
Lighting Auxiliary Building EL. 141-0
-6- Attachment
CE-001Q Appendix R Safe-Shutdown Analysis Emergency 4
Lighting Standby Cooling Tower EL. 118-0
CE-001U Appendix R Safe-Shutdown Analysis Emergency 3
Lighting Turbine Building EL. 67-6
CE-001V Appendix R Safe-Shutdown Analysis Emergency 3
Lighting T-Tunnel EL. 123-6
CE-001W Appendix R Safe-Shutdown Analysis Emergency 5
Lighting Switchgear Building EL. 98-0
EB-003AB Fire Area Boundaries Plant Plan View - Elevations 65- 5
0 to 90-0
EB-003AC Fire Area Boundaries Plant Plan View - Elevations 83- 6
0 to 106-0
EB-003AE Fire Area Boundaries Plant Plan View - Elevations 4
113-0 to 186-3
EB-003BB Fire Protection Features Plant Plan View - Elevations 4
65-0 to 90-0
EB-003BC Fire Protection Features Plant Plan View - Elevations 5
83-0 to 106-0
EB-003BE Fire Protection Features Plant Plan View - Elevations 5
113-0 to 186-3
EE-001AC Start Up Electrical Distribution Chart 45
EE-001M 4160V One Line Diagram Standby Bus E22-S004 9
EE-003GD Wiring Diagram 1CND-PNL212 Auxiliary Control 8
Building
EE-003GE Wiring Diagram CND-PNL212 Auxiliary Control 4
Building
EE-003GF Wiring Diagram 1CND-PNL212 Auxiliary Control 2
Building
EE-007DD External Connection Diagram PGCC Termination 9
Cabinet 1H13*P710 Bay A
EE-007DE External Connection Diagram PGCC Termination 13
Cabinet H13-P710 Bay B
EE-007EM Wiring Diagram Misc. Details 1B21*AOVF22 & 28 8
-7- Attachment
EE-007EX Wiring Diagram Miscellaneous Details of 1
1B21*AOVF22 & 28
EE-009GL 480V Wiring Diagram 1NHS-MCC4A, CNDS 3
DMNRLZR & Off Gas BLDG
EE-009GN 480V Wiring Diagram 1NHS-MCC4B CNDS DMNRLZR 3
& Off Gas Area
EE-009GQ 480V Wiring Diagram 1NHS-MCC4A & 1NHS-MCC4B 9
COND DMNRLZR & Off Gas Area
EE-009NL 480V MISC Wiring Diagram EHS-MCC2E Auxiliary 10
Building
EE-009PE 480V Wiring Diagram 1EHS*MCC2K Auxiliary Building 7
EE-009SY 480V Wiring Diagram 1EHS*MCC2L Auxiliary Building 11
EE-009SZ 480V MISC Wiring Diagram EHS-MCC2L Auxiliary 17
Building
EE-018AE Wiring Diagram Fire & Smoke Detection System 8
Auxiliary Biulding
EE-018E Wiring Diagram Fire & Smoke Detection Control 5
Building Elevation 70-0
EE-018F Wiring Diagram Fire & Smoke Detection Control 5
Building Elevation 98-0
EE-01J 4160V One Line Diagram Bus NNS-SWG3A, 3B &1C 12
EE-034YC Appendix R Raceway Fire Protection Details 6
EE-034YL Appendix R Raceway Fire Protection Details 0
EE-034YN Appendix R Raceway Fire Protection Details 0
EE-037B Arrangement Inserts, Sleeves & Openings Control 14
Building
EE-037C-8 Arrangement Inserts, Sleeves & Openings Control 8
Building
EE-037S Arrangement Inserts, Sleeves & Openings Auxiliary 13
Building Elevation 70-0 & 95-0
EE-080AX Distribution Antenna System Control Building EL. 70-0 1
-8- Attachment
EE-080BL Distribution Antenna system Normal Switchgear 1
Building EL. 123-6
EE-080U Communications Plan Main Control Room 7
EE-37AF-5 Sections Inserts, Sleeves & Openings Control Building 5
Elevation 98-0
ESK-03Z Control Switch Contact Diagram 16
ESK-05SWP01 Elementary Diagram 4.16kV SWGR Service Water 17
Pump P7A
ESK-05SWP02 Elementary Diagram 4.16kV Switchgear Service Water 16
Pump P7B
ESK-05SWP03 Elementary Diagram 4.16kV Switchgear Service Water 17
Pump P7C
ESK-05SWP05 Elem. Diag. 4.16kV SWGR Standby Service Water 19
Pump P2E
ESK-05SWP07 Elem. Diag. - 4.16kV SWGR Standby Service Water 17
Pump P2D
ESK-06CND04 Elementary Diagram 480V Control Circuit Condensate 4
Demineralizer System
ESK-06CND05 Elementary Diagram 480V Control Circuit Condensate 7
Demineralizer System
ESK-06CND06 Elementary Diagram 480V Control Circuit Condensate 5
Demineralizer System
ESK-06CND07 Elementary Diagram 480V Control Circuit Condensate 7
Demineralizer System
ESK-06CND08 Elementary Diagram 480V Control Circuit Condensate 4
Demineralizer System
ESK-06CND09 Elementary Diagram 480V Control Circuit Condensate 4
Demineralizer System
ESK-06CND10 Elementary Diagram 480V Control Circuit Condensate 4
Demineralizer System
ESK-06CND11 Elementary Diagram 480V Control Circuit Condensate 4
Demineralizer System
-9- Attachment
ESK-06CND12 Elementary Diagram 480V Control Circuit Condensate 4
Demineralizer System
ESK-06CND13 Elementary Diagram 480V Control Circuit Condensate 4
Demineralizer System
ESK-06RHS22 Elementary Diagram 480V Control Circuit Residual 12
Heat Removal System
ESK-06SWP05 Elementary Diagram 480V Control Circuit Service 12
Water Pumps Discharge Valves
ESK-06SWP09 Elementary Diagram 480V Control Circuit Service 13
Water System MOVs
ESK-06SWP10 Elementary Diagram 480V Control Circuit Service 20
Water System MOVs
ESK-07EGA03 Elementary Diagram 120VAC Control Circuit Remote 9
Shutdown Transfer Relays
ESK-07SVV03 Elementary Diagram 125VDC Control CKTS Main 7
Steam SRV
ESK-07SWP01 Elementary Diagram 120V Control Circuit Service 5
Water Pumps Aux Cont Circuit
ESK-08EGS16 DC Elementary Diagram STBY Bus UNDV PROT and 7
Load Sequence
ESK-08NNS03 Elem. Diag. 4.16kV SWGR Bus 2A & 2B Potential 7
Circuits River Bend Power Station - Unit 1
ESK-11EGA01 Elem Diag 125VDC Control Stby DSL 1A Rear Start 23
Ckt
ESK-11NNS04 Elementary Diagram 4.16kV SWGR Bus 2A 11
Undervoltage Trip Circuit
ESK-11NNS05 Elementary Diagram 4.16kV SWGR Bus 2B 9
Undervoltage Trip Circuit
ESK-11NNS08 Elementary Diagram 4.16kV SWGR Bus 2A-2B XFMR 10
Protection
ESK-11SWP04 Elementary Diagram 125VDC Control Circuit Standby 15
Service Water Aux. Control
ESK-8NNS03 Elementary Diagram 4.16kV SWGR Bus 2A & 2B 7
Potential Circuits
- 10 - Attachment
KA-0228.212-047- Wiring Diagram (SMB) Limitorque (VELAN) 0
009
PID-15-01A Fire Protection-Water and Engine Pumps 18
PID-15-01B Fire Protection-Water and Engine Pumps 15
PID-15-01C Fire Protection-Water and Engine Pumps 13
PID-15-01D Fire Protection-Water and Engine Pumps 7
PID-15-01E Fire Protection-Water and Engine Pumps 11
RBS-SSD-FA-001 Appendix R Safe Shutdown Analysis Fire Area Map 4
RBS-SSD-FA-002 Appendix R Safe Shutdown Analysis Fire Area Map 3
RBS-SSD-FA-003 Appendix R Safe Shutdown Analysis Fire Area Map 3
RBS-SSD-FA-004 Appendix R Safe Shutdown Analysis Fire Area Map 4
RBS-SSD-FA-005 Appendix R Safe Shutdown Analysis Fire Area Map 4
TLD-MSS-033 Test Loop Diagram Main Steam Inboard Isolation B21- 0
AOVF022A
TLD-MSS-037 Test Loop Diagram Main Steam Outboard Isolation 1
B21-AOVF028A
ENGINEERING CHANGES
Number Title Revision
1933 Provide Alternate Power Source for E51-MOVF063 0
During a Main Control Room Fire
4026 Add Emergency Lights LAD-1G1-7-0-B2, LAD-1G1-7- 0
0-B4, and LAD-1G1-8-0-B-1 to the List of Appendix R
Emergency Lights in the Post-Fire Safe Shutdown
Analysis and Drawing CE-001F
8684 Modify Div 1-2 DG Controls, Not Bypass Trips, LOP- 0
Only Start; Ref. CR-RBS-2007-2102 LT-ACE,
Reportable Regulatory Issue
10403 Install (2) 1-Gallon Auxiliary Oil Reservoirs Above The 1
Lower Oilfill Line Of The Reactor Recirculation Pump
B33-PC00001A. This Revision Corrects Support
Dimensions Based On Field Measurements.
- 11 - Attachment
14988 Supplemental Oil Reservoir For B33-PC001A/B Motor 0
18178 Revise G13.18.2.6*034 and Post-Fire Safe Shutdown 0
Analysis
21841 SRV Operation During Control Room Fire 0
22335 Documentation of Risk Evaluation for Control Room 0
Fire with Fire Induced Loss of Manual and Automatic Trip Function of the Feedwater Pump and Control
System
22852 Post-Fire Safe Shutdown Analysis Basis for AOP-0031 0
22973 Markup Calculation G13.18.14.0*29, Rev. 1 to Capture 0
Time to Top of Active Fuel
23359 Estimated Time to Overfill the RPV Due to Continued 0
Feedwater Operation During a Fire in the Main Control
Room
32205 Markup Calculation G13.18.12.2-139 Rev. 0 to Address 0
1 and 2 Reactor Feedwater Pump Operation
43742 Safe Shutdown Scenario Evaluation Regarding the 1
Emergency Operating Procedures and Emergency
Depressurization
ENGINEERING REPORTS
Number Title Revision
ENTGRB083-PR-01 Multiple Spurious Operations Circuit Analysis and 0
Scenario Disposition
EPM Report MSO Expert Panel Results May 2010
P2083-02-001
EPM Report Regulatory Guide 1.189 Support Project Final Report September
P2083-07-001 2010
ER-RB-1998-0430- Safety Relief Valve, SRV Control Circuit Modification 0
000 Associated With Pressure Transmitters, B21-
PTN068A,B,E, and F.
ER-RB-2001-0136- Document the Basis for the Scope and Frequency of 0
000 Fire Protection Testing
ER-RB-2001-0843- Clarification For the Use of the Normal Service Water 0
- 12 - Attachment
000 system for Post-fire Safe Shutdown in Fire Area PT-1
ER-RB-2003-0534- Replacement Required for Emergency Lighting 0
000 Batteries, Eagle Picher CF6V50
ER-RB-2003-0711- Revising Post-Fire Safe Shutdown Operator Manual 0
001 Action Evaluations Following Release of RIS 2006-10
ER-RB-2004-0275- Summarize All RBS NFPA Code Deviations 0
000
ER-RB-2005-0258- Spent Fuel Pool Configuration (Open Area) 0
000
RBS-FP-11-00001 Expert Panel for Addressing Multiple Spurious 0
Operations
SEA-95-001 Individual Plant Examination for External Events 0
LESSON PLANS
Number Title Revision
RLP-OPS-AOP0031 AOP-0031 Shutdown from Outside the Main Control 2
Room
MODIFICATIONS
Number Title Revision
MR 91-0075 Upgrade Appendix R Thermo-Lag Enclosures 0
MR 91-0075, FCN2 1-Hour Fire Rated enclosure For E12-MOVF068B 0
MR 96-0023 Re-route Control Cable Associated with 0
1SWP*AOV599
MR 96-0023 D01 Installation of New Cable, Conduit and Junction Box 0
and Rework Conduit Cable
MR 96-0024 Re-route Control Cable Associated with 0
1SWP*AOV55A/B
MR 96-0027 Control Building Chiller Control Circuit 0
MR 96-0052 FCN1 Install Double Fuses on Cable 1 SWP in Main Control 0
Room Panel
- 13 - Attachment
MR 96-0052 FCN2 Correct Referenced Drawing to Reflect the Correct 0
Circuit Fuses
MR 96-0052 FCN3 Relocate Fuse Locations 0
PREVENTIVE MAINTENANCE TASKS
0P011 T2102
PROCEDURES
Number Title Revision
AB-070-408 Pre-Fire Strategies *D-Tunnel Fire Area AB-7 1
AOP-0031 Shutdown From Outside the Main Control Room 320
AOP-0052 Fire Outside the Main Control Room In Areas 22
containing Safety Related Equipment
CB-070-110 Pre-fire Strategies * HVAC 1A Room Fire Area C-4 4
CB-070-111 Pre-fire Strategies * HVAC 1B Room Fire Area C-4 3
CB-098-120 Pre-fire Strategies *Cable Tray Area an Stairway #3 3
Fire Area C-16 and C-29
CB-098-122 Water Chiller Equipment 1A Room Fire Area C-13W 3
CB-116-129 Pre-fire Strategies *125 VDC Switchgear Room Fire 4
Area C-24
EN-DC-115 Engineering Change Development 6
EN-DC-127 Control of Hot Work and Ignition Sources 12
EN-DC-128 Fire Protection Impact Reviews 3
EN-DC-128 Fire Protection Impact Reviews 5
EN-DC-161 Control of Combustibles 7
EN-DC-179 Preparation of Fire Protection Engineering Evaluations 3
EN-DC-330 Fire Protection Program 1
EN-EV-112 Chemical control Program 12
- 14 - Attachment
EN-IS-109 Compressed Gas Cylinder Handling and Storage 7
EN-LI-100 Process Applicability Determination 8
EN-LI-100 Process Applicability Determination 13
EN-OP-115 Conduct of Operations 13
EN-TQ-125 Fire Brigade Drills 1
EOP-0001 Emergency Operating Procedure - RPV Control 25
OSP-0009 Authors Guide/Control and Use of Emergency 36
Operating and Severe Accident Procedures
OSP-0028 Log Report - Normal Switchgear, Control, and Diesel 73
Generator Buildings
OSP-0029 Log Report - Auxiliary, Reactor, and Fuel Buildings 53
OSP-0066 Extensive Damage Mitigation Procedure 19
OSP-0066 Extensive Damage Mitigation Procedure 20
OSP-0066 Extensive Damage Mitigation Procedure 21
OSP-0601 Remote Shutdown System Control Circuit Operability 5
Test (Switches 43-1EGAN05, 43-1EJSA01, 43-
1ENSC04, 43A-1ENSA01, 43B-1ENSA03, 43C-
1ENSA09, 43D-1ENSC04, 43E-1ENSC01, 43F-
1ENSA01, And 43G-1ENSA03)
OSP-0602 Remote Shutdown System Control Circuit Operability 4
Test (Switches 43-1HVCN30, 43-1HVCN31, 43-
1HVCN32 And 43=1HVKA01)
SEP-FPP-RBS-001 River Bend Station Fire Protection Program 0
SEP-FPP-RBS-002 River Bend Station Fire Fighting Procedure 1
SEP-FPP-RBS-003 River Bend Station Post Fire Ventilation/Smoke 1
Management
SEP-FPP-RBS-004 River Bend Station Guidelines for Preparation of Pre- 1
Fire Strategies and Pre-Fire Plans
SEP-FPP-RBS-005 River Bend Station Duties of Fire Watch 1
SEP-FPP-RBS-006 River Bend Station Fire Protection System Impairment 1
- 15 - Attachment
SEP-FPP-RBS-007 River Bend Station Visual Inspection of Non-TRM Fire 1
Barriers
SOP-0027 Remote Shutdown System (#200) 303
STP-200-0603 Division III Remote Shutdown System Control Circuit 1
Operability Test
STP-250-4535 FPM-PNL11 fire Detection Channel Functional and 1
Operational Tests For Zone SD28, SD29, SD30,
SD83(A&B), SD97, SD98, and SC99
STP-251-3602 Fire Pump Functional Test 15
STP-251-3700 Fire System Yard Water Suppression Loop Flow Test 9
STP-251-3700 Fire System Yard Water Suppression Loop Flow Test 10
TPP-7-021 Fire Protection Training and Qualifications 13
SYSTEM TRAINING MANUALS
Number Title Revision
R-STM-0053 Reactor Recirculation System 12
R-STM-0107 Reactor Feedwater and Level Control Systems 23
R-STM-0109 Main Steam System 12
R-STM-0118 Service Water Systems 24
R-STM-0203 High Pressure Core Spray System (HPCS) 8
R-STM-0204 Residual Heat Removal System (RHR) 10
R-STM-0205 Low Pressure Core Spray (LPCS) 5
R-STM-0209 Reactor Core Isolation Cooling (RCIC) System 10
R-STM-0250 System Training Manual Fire Protection and Detection 6
R-STM-0601 Reactor Water Cleanup (RWCU) System 8
- 16 - Attachment
WORK ORDERS
112483 234891 50991592 52197768
164892 342422 51561607 52241530
166039 23489101 51658086 52306270
174983 50342942
MISCELLANEOUS DOCUMENTS
Number Title Revision
Final Safety Analysis Report, Appendix 9A
Final Safety Analysis Report, Appendix 9B
Final Safety Analysis Report, Section 9.5.1
Letter of Agreement Between Entergy Operations, Inc. July 22, 2005
River Bend Station and the St. Francisville Volunteer
Fire Department of West Feliciana Parish, Louisiana
Letter of Agreement Between Entergy Operations, Inc. May 23, 2012
River Bend Station and the Fire Protection District #1
of West Feliciana Parish, Louisiana
Letter of Agreement dated July 22, 2005 - Review December 18,
Certification 2012
Operations Standards and Expectations 45
Safety Evaluation Report
Safety Evaluation Report, Supplement 3
6240.201-795-042A Regulatory Guide 1.189 Support Project Final Report 0
Criterion 240.201A Post-Fire Safe Shutdown Analysis 4
RCBT-EP-B5b Extensive Damage Mitigation Training 1
SCRB-24686 File No. G9.5, G9.20.6.10 Additional B.5.B Information January 11,
River Bend Station 2007
SCRB-24813 File No. G9.5, G9.20.6.10 Additional B.5.B Information August 11,
River Bend Station 2008
- 17 - Attachment
Standing Order 270 AOP-0031 Shutdown From Outside the Main Control 0
Room
TR 3.3.7.4 Fire Detection Instrumentation 79
TR 3.7.9.1 Fire Suppression Systems 128
TR 3.7.9.2 Spray and/or Sprinkler Systems 128
TR 3.7.9.3 Halon Systems 79
TR 3.7.9.4 Fire Hose Stations 128
TR 3.7.9.5 Yard Fire Hydrants and Hydrant Hose Houses 58
TR 3.7.9.6 Fire-Rated Assemblies 128
- 18 - Attachment