Security Baseline Inspection Report 05000458/2020410
ML20247J467
Person / Time
Site: River Bend 
Issue date: 09/03/2020
From: Ray Kellar
Plant Support Branch-1
To: Vercelli S
Entergy Operations
References
IR 2020410
Download: ML20247J467 (8)


Text

September 3, 2020

SUBJECT:

RIVER BEND STATION - SECURITY BASELINE INSPECTION REPORT 05000458/2020410

Dear Mr. Vercelli:

On July 24, 2020, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at River Bend Station and discussed the results of this inspection with Mr. J. Reynolds, Regulatory Assurance and Performance Improvement Director, and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Ray L. Kellar, P.E., Chief Plant Support Branch 1 Division of Reactor Safety

Docket No. 05000458 License No. NPF-47

Enclosure:

As stated

Inspection Report

Docket Number:

05000458

License Number:

NPF-47

Report Number:

05000458/2020410

Enterprise Identifier: I-2020-410-0009

Licensee:

Entergy Operations, Inc.

Facility:

River Bend Station

Location:

St. Francisville, LA

Inspection Dates:

July 20, 2020 to July 24, 2020

Inspectors:

D. Holman, Sr Physical Security Inspector

Approved By:

Ray L. Kellar, P.E., Chief

Plant Support Branch 1

Division of Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a security baseline inspection at River Bend Station, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

INSPECTION SCOPES

Unless otherwise noted, baseline security inspections were conducted in accordance with the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter 2201, Security Inspection Program for Commercial Nuclear Power Reactors. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards. Publicly available IPs are located at:

http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html.

SAFEGUARDS

71130.02 - Access Control

The inspectors evaluated the access control program through completion of the following

===inspection elements:

Access Control===

(1)

  • Tier I: All Requirements
  • Tier II: 7 Requirements (02.06 a - d, 02.08 a,b,e)
  • Tier III: 1 Requirement (02.09)

71130.09 - Security Plan Changes

The inspectors evaluated the security plan changes through completion of the following procedure elements:

Review Security Plan Changes (IP Section 02.01) (1 Sample)

(1) The opportunity to apply this procedure was not available in accordance with Inspection Manual Chapter 0306. This sample was not available because the licensee did not conduct the activity covered by this IP. Specifically, the licensee has not initiated a physical security plan change in accordance with 10 CFR 50.54(p)(2)since the implementation of this IP.

OTHER ACTIVITIES - BASELINE

71151 - Performance Indicator Verification

The inspectors verified licensee performance indicators submittals listed below:

PP01: Protected Area Security Equipment Performance Index Sample (IP Section 02.17) (1 Sample)

The inspector verified licensee performance indicators submittals listed below:

(1) The inspector reviewed a sample of PI data from October 2019 through June 2020 with no discrepancies noted.

INSPECTION RESULTS

No findings were identified.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On July 24, 2020, the inspectors presented the security baseline inspection results to Mr. J. Reynolds, Regulatory Assurance and Performance Improvement Director, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71130.02

Corrective Action

Documents

2019-04179

Pepper spray detected in PAP search process

4/7/20

2019-05957

DG 108-G1 came open without key

9/11/19

2019-07800

Visitor denied access (on barred list)

2/10/19

20-00077

Key broke off inside lock

1/7/20

Corrective Action

Documents

Resulting from

Inspection

20-03022

Minor violation security procedure doesn't implement the

code.

7/21/20

20-03024

Observations on RLP-SEC-PERPAC

7/21/2020

20-03025

Observations on site security procedure SPI-04

7/21/20

20-03042

Minor violation, vegetation on PA barrier

7/21/20

20-03043

SGI container seals observation

7/21/20

20-03069

Minor violation mechanical key design marking

7/22/20

HQN-2020-01416

Fleet procedure EN-NS-231 observations

7/21/20

HQN-2020-01433

Minor violation procedure does not implement the code.

7/23/20

Miscellaneous

EN-NS-232 RI,

Visitor Escort Responsibilities Sheet (Typical)

Unknown

Lock/Key

Inventory

Core Issued to Active

6/24/20

MA 100022

Revision 0D

SAFRAN, Morpho, Itemiser 4DX-COMM, User's Guide

2015-2016

PA Visitor

Responsibilities

River Bend Security, PA Escorted Visitor Guidance 1 - 10.

October

2012

Procedures

EN-LI-102

Corrective Action Program

Revision 40

EN-NS-101

Unescorted Access Authorization Program

Revision 27

EN-NS-101-06

Terminating, Denial and Appeal of Unescorted Access

Authorization/Unescorted Access

Revision 5

EN-NS-204

Protection of Unclassified Safeguards Information

Revision 16

EN-NS-231

Protected Area Search

Revision 2

EN-NS-232

General Employee Security Responsibilities

Revision 2

SDI-012

Security Lock and Key Control

Revision 11

SDI-016

Protected Area and Vital Area Access Control

Revision 11

SPI-02

Patrol Officer

Revision 35

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

SPI-04

Access Control Officer(s)

Revision 67

SPI-06

Alarm Station Supervisor

Revision 67

SPI-09

Vehicle/Material Search

Revision 41