IR 05000458/2021004

From kanterella
Jump to navigation Jump to search
Integrated Inspection Report 05000458/2021004
ML22019A301
Person / Time
Site: River Bend Entergy icon.png
Issue date: 01/25/2022
From: Jeffrey Josey
NRC/RGN-IV/DRP/RPB-C
To: Karenina Scott
Entergy Operations
References
IR 2021004
Download: ML22019A301 (26)


Text

January 25, 2022

SUBJECT:

RIVER BEND STATION - INTEGRATED INSPECTION REPORT 05000458/2021004

Dear Mr. Scott:

On December 31, 2021, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at River Bend Station. On January 10, 2022, the NRC inspectors discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report.

Two findings of very low safety significance (Green) are documented in this report. Both of these findings involved violations of NRC requirements. We are treating these violations as non-cited violations (NCVs) consistent with Section 2.3.2 of the Enforcement Policy.

If you contest the violations or the significance or severity of the violations documented in this inspection report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN:

Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region IV; the Director, Office of Enforcement; and the NRC Resident Inspector at River Bend Station.

If you disagree with a cross-cutting aspect assignment in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region IV; and the NRC Resident Inspector at River Bend Station. This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Jeffrey E. Josey, Chief Reactor Projects Branch C Division of Reactor Projects Docket No. 05000458 License No. NPF-47

Enclosure:

As stated

Inspection Report

Docket Number:

05000458

License Number:

NPF-47

Report Number:

05000458/2021004

Enterprise Identifier:

I-2021-004-0141

Licensee:

Entergy Operations, Inc.

Facility:

River Bend Station

Location:

St. Francisville, Louisiana

Inspection Dates:

October 1, 2021 to December 31, 2021

Inspectors:

R. Kopriva, Senior Reactor Inspector

R. Kumana, Senior Resident Inspector

J. ODonnell, Senior Health Physicist

C. Osterholtz, Senior Operations Engineer

W. Sifre, Senior Reactor Inspector

C. Wynar, Resident Inspector

Approved By:

Jeffrey E. Josey, Chief

Reactor Projects Branch C

Division of Reactor Projects

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at River Bend Station, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

Failure to Maintain the Ability of a Fire Door to Close Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000458/2021004-01 Open/Closed None (NPP)71111.05 The inspectors identified a Green finding and associated non-cited violation of River Bend Station, Unit 1, Renewed Facility Operating License, Section 2.C(10), for failure to implement the fire protection program by not verifying that automatic closing mechanisms for normally open fire doors were operable.

Failure to Demonstrate Effective Control of Performance for a Maintenance Rule (a)(2)

System Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000458/2021004-02 Open/Closed

[H.8] -

Procedure Adherence 71111.06 The inspectors identified a Green finding and associated non-cited violation of 10 CFR 50.65(a)(2) with 13 examples of failures to demonstrate effective control of performance of a maintenance rule scoped system through appropriate preventive maintenance.

Additional Tracking Items

Type Issue Number Title Report Section Status NOV 05000458/2021010-03 Failure to Restore Compliance Associated with Technical Specification Required Procedures 71152 Closed

PLANT STATUS

River Bend Station began the inspection period at rated thermal power. On November 14, 2021, River Bend Station lowered power to approximately 62 percent for a rod pattern adjustment. River Bend Station returned to rated thermal power on November 22, 2021 and remained at or near rated thermal power for the remainder of the inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed activities described in IMC 2515, Appendix D, Plant Status, conducted routine reviews using IP 71152, Problem Identification and Resolution, observed risk significant activities, and completed onsite portions of IPs. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

Starting on March 20, 2020, in response to the National Emergency declared by the President of the United States on the public health risks of the coronavirus (COVID-19), resident and regional inspectors were directed to begin telework and to remotely access licensee information using available technology. During this time, the resident inspectors performed periodic site visits each week, increasing the amount of time on site as local COVID-19 conditions permitted.

As part of their onsite activities, resident inspectors conducted plant status activities as described in IMC 2515, Appendix D; observed risk significant activities; and completed onsite portions of IPs. In addition, resident and regional baseline inspections were evaluated to determine if all or a portion of the objectives and requirements stated in the IP could be performed remotely. If the inspections could be performed remotely, they were conducted per the applicable IP. In some cases, portions of an IP were completed remotely and on site. The inspections documented below met the objectives and requirements for completion of the IP.

REACTOR SAFETY

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (4 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1) Containment unit coolers A, B, and C on November 15, 2021
(2) Division I 4160 volt AC control system on November 29, 2021
(3) Residual heat removal B on November 29, 2021
(4) Drywell floor and equipment drain instrumentation on December 15, 2021

Complete Walkdown Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated system configurations during a complete walkdown of the remote shutdown system on December 1, 2021.

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (5 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1) Heating, ventilation, and air conditioning 1B room, fire area C-4, on November 2, 2021
(2) Diesel driven fire pump 1B room, fire area FP-3, on November 9, 2021
(3) Containment unit cooler area, fire area RC-4/Z-5, on November 12, 2021
(4) Control rod drive system pump and filter room, fire area FB-1/Z-1, on December 2, 2021
(5) Standby switchgear 1A room, fire area C-15, on December 13, 2021

71111.06 - Flood Protection Measures

Inspection Activities - Internal Flooding (IP Section 03.01) (2 Samples)

The inspectors evaluated internal flooding mitigation protections in the:

(1) Low pressure core spray system room
(2) High pressure core spray system room

71111.07A - Heat Sink Performance

Annual Review (IP Section 03.01) (1 Sample)

The inspectors evaluated readiness and performance of:

(1) Heat exchanger SFC-E1B

71111.07T - Heat Sink Performance Heat Exchanger (Service Water Cooled) (IP Section 03.02)

The inspectors evaluated heat exchanger/sink performance on the following:

(1) Emergency diesel generator B jacket water cooler - EGT-E1B (cooled by service water)
(2) Steam tunnel room cooler - HVR-UC8 (room cooler cooled by service water)
(3) Containment unit cooler B - HVR-UC1B (cooled by service water)
(4) Reactor core isolation cooling / low pressure core spray / residual heat removal A room cooler - HVR-UC6 (cooled by service water)

71111.11A - Licensed Operator Requalification Program and Licensed Operator Performance

Requalification Examination Results (IP Section 03.03) (1 Sample)

(1) The inspectors reviewed and evaluated the licensed operator examination failure rates for the requalification annual operating exam administered on November 9, 2021.

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1) The inspectors observed an evaluated simulator training session on October 22, 2021.

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (2 Samples)

The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components remain capable of performing their intended function:

(1) Review of control building ventilation system performance on November 29, 2021
(2) Performance monitoring of pressure tight doors on December 15, 2021

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (4 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:

(1) Elevated risk with reactor core isolation cooling out of service on November 10, 2021
(2) Elevated risk due to unit cooler HVR-UC6 coil inspection on November 15, 2021
(3) Elevated risk due to reactor core isolation cooling drain pot level instrument out of service on November 22, 2021
(4) Elevated risk with auxiliary building internal flooding door AB070-03 out of service on December 15, 2021

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (5 Samples)

The inspectors evaluated the licensees justifications and actions associated with the following operability determinations and functionality assessments:

(1) Division I penetration valve leakage control system air compressor on November 3, 2021 (CR-RBS-2021-05930)
(2) Diesel air compressor functionality with dryer pressure drop on November 4, 2021 (CR-RBS-2021-01240)
(3) Division I and Division III emergency diesel generator operability for STP-200-0603, Revision 19, Division III Remote Shutdown System Control Circuit Operability Test, while in Mode 1 on November 15, 2021
(4) Reactor core isolation cooling on December 2, 2021 (CR-RBS-2021-06973)
(5) Suppression pool cooling spurious valve opening and suppression pool level drop on December 15, 2021 (CR-RBS-2021-07351)

71111.18 - Plant Modifications

Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02) (1 Sample)

The inspectors evaluated the following temporary or permanent modifications:

(1) Unit coolers HVR-UC11A and HVR-UC11B motor replacement (EC 88863)

71111.19 - Post-Maintenance Testing

Post-Maintenance Test Sample (IP Section 03.01) (9 Samples)

The inspectors evaluated the following post-maintenance test activities to verify system operability and functionality:

(1) Work Order (WO) 00497132, high pressure core spray minimum flow restriction orifice, on October 5, 2021
(2) WO 00490016, Division III remote shutdown relay replacement, on October 12, 2021
(3) WO 00558034, Division I diesel generator overspeed pilot 3-way valve replacement, on October 19, 2021
(4) WO 52863766, Division III diesel generator 18-year inspection, on October 21, 2021
(5) WO 00567590, reactor core isolation cooling solenoid, on November 17, 2021
(6) WO 00489142, replacement of remote shutdown system J11 relays, on December 6, 2021
(7) WO 52852289, replacement of B21C-K13B relay, on December 21, 2021
(8) WO 52942091, adjustment of AB070-03 door seal, on December 22, 2021
(9) WO 00566861, troubleshooting of control rod 24-25 rod block, on December 27, 2021

71111.22 - Surveillance Testing

The inspectors evaluated the following surveillance tests:

Surveillance Tests (other) (IP Section 03.01)

(1) STP-309-0611, Revision 055, Division I Diesel Generator 24 Hour Run, on November 15, 2021
(2) COP-0032, Revision 11, Startup and Operation of the Reactor Sample Panel G33-Z020 and EN-CY-110, Revision 04, Chemistry Gamma Spectroscopy System Operation, on December 6, 2021
(3) STP-410-3601, Revision 12, Control Building Chiller 1A Performance Test, on December 13, 2021

Inservice Testing (IP Section 03.01) (1 Sample)

(1) STP-205-6301, Revision 28, LPCS Pump and Valve Operability Test, on November 16, 2021

RCS Leakage Detection Testing (IP Section 03.01) (1 Sample)

(1) STP-000-0001, Revision 92, Reactor Coolant System Leakage, on December 16, 2021

71114.06 - Drill Evaluation

Select Emergency Preparedness Drills and/or Training for Observation (IP Section 03.01) (1 Sample)

(1) Emergency response organization drill on October 13, 2021

Drill/Training Evolution Observation (IP Section 03.02) (1 Sample)

The inspectors evaluated:

(1) Emergency response organization drill on November 10,

RADIATION SAFETY

71124.05 - Radiation Monitoring Instrumentation

Walkdowns and Observations (IP Section 03.01) (9 Samples)

The inspectors evaluated the following radiation detection instrumentation during plant walkdowns:

(1) Area radiation monitors in various buildings - reactor building general area [RE-144]

and sample station [RE-151], radwaste solidification area [RE-188] and offgas building, and valve area [RE-167]

(2) Effluent monitors for the fuel building ventilation exhaust [RE-5A/B], radwaste building ventilation exhaust [RE-6A/B], main plant exhaust duct [RE-125/RE-126]
(3) Portable frisker (Ludlum Model 177) stationed in the services building 123-foot hallway [CHP-CR-074] and portable frisker (ASP-1) stored and ready for use in the services building 109-foot count room [CHP-MF-030]
(4) Portable ion chamber (Ludlum Model 9-3) stored and ready for use in the services building 109-foot count room [CHP-DR-487]
(5) High dose rate G-M instrument (TelePole) stored and ready for use in the services building 109-foot count room [CHP-TEL097]
(6) Laboratory instruments for smear counting (BC-4 [HP-CS-008]; SAC-4 [HP-DS-070];

iSOLO [CHP-C-011]) located in the service building 109-foot count room

(7) Personnel contamination monitors (Argos) used at the exit to the radiologically controlled area [1410-184, 1410-185, 1410-186]
(8) Portal monitors (PM-7) used at the exit to the radiologically controlled area [PM7-394, PM7-395]
(9) Tool and equipment monitor (Cronos) used at the exit to the Unit 2 radiologically controlled area [1011-061]

71124.06 - Radioactive Gaseous and Liquid Effluent Treatment

Walkdowns and Observations (IP Section 03.01) (4 Samples)

The inspectors evaluated the following radioactive effluent systems during walkdowns:

(1) Standby gas treatment ventilation system discharge to main plant vent stack
(2) Radwaste building ventilation system discharge to atmosphere
(3) Fuel building ventilation system discharge to atmosphere
(4) Auxiliary building ventilation system discharge to main plant vent stack

Sampling and Analysis (IP Section 03.02) (1 Sample)

The inspectors evaluated the following effluent samples, sampling processes, and compensatory samples:

(1) Weekly iodine and particulate sampling for the plant vent [RE-126], the fuel building vent [RE-05A], and the radwaste building vent [RE-06A]

71124.07 - Radiological Environmental Monitoring Program

Environmental Monitoring Equipment and Sampling (IP Section 03.01) (1 Sample)

(1) The inspector evaluated environmental monitoring equipment. No environmental sample collection was available for observation.

71124.08 - Radioactive Solid Waste Processing & Radioactive Material Handling, Storage, &

Transportation

Radioactive Material Storage (IP Section 03.01)

The inspectors evaluated the licensees performance in controlling, labeling, and securing the following radioactive materials:

(1) Radwaste 106-foot storage room with drums, bags, and boxes of radioactive waste

Radioactive Waste System Walkdown (IP Section 03.02) (1 Sample)

The inspectors walked down the following accessible portions of the solid radioactive waste systems and evaluated system configuration and functionality:

(1) Waste and floor drain collector subsystem of the liquid waste system

Shipment Preparation (IP Section 03.04) (1 Sample)

(1) The inspectors observed the preparation of condensate bead resin liner #200L-21003 for shipment as an LSA-II shipment (RBS-2021-083) on November 17,

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:

BI01: Reactor Coolant System (RCS) Specific Activity Sample (IP Section 02.10)===

(1) October 1, 2020 through September 30, 2021

BI02: RCS Leak Rate Sample (IP Section 02.11) (1 Sample)

(1) October 1, 2020 through September 30, 2021

71152 - Problem Identification and Resolution (PI&R)

Semiannual Trend Review (IP Section 02.02) (1 Sample)

(1) The inspectors reviewed the licensees corrective action program for potential adverse trends in condition report classification that might be indicative of a more significant safety issue.

Annual Follow-up of Selected Issues (IP Section 02.03) (2 Samples)

The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:

(1) Entry into EOP-0002 on June 2, 2021 (CR-RBS-2021-04016)
(2) Response to cited violation of Technical Specification 5.4.1 (CR-RBS-2021-00644)

The inspectors reviewed the licensees response to NOV 05000458/2021010-03 and determined that the reason, corrective actions taken and planned to address recurrence, and the date when full compliance was achieved for this violation is adequately addressed and captured on the docket.

INSPECTION RESULTS

Failure to Maintain the Ability of a Fire Door to Close Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000458/2021004-01 Open/Closed None (NPP)71111.05 The inspectors identified a Green finding and associated non-cited violation of River Bend Station, Unit 1, Renewed Facility Operating License, Section 2.C(10), for failure to implement the fire protection program by not verifying that automatic closing mechanisms for normally open fire doors were operable.

Description:

During a walkdown of fire protection requirements in the fire pump house, the inspectors noted that the fire suppression pumps were separated by normally open rated fire doors. The inspectors reviewed the testing program for fire doors to determine if these doors complied with the approved fire protection program.

River Bend Station incorporated their fire protection program requirements and fire hazard analysis into Chapter 9A of their updated safety analysis report (USAR). The USAR states that each fire suppression pump is separated by a 3-hour rated fire barrier. The arrangement of fire suppression pumps at River Bend Station is such that the two diesel driven pumps are on either side of the motor driven pump. The doors separating the pumps are large, horizontally sliding, rated metal fire doors, with a mechanical pulley closing mechanism.

Each door is held fully open by a rope with two fusible links. The USAR states that all fire doors shall be provided with closing mechanism and inspected semiannually to verify the closing mechanisms are operable.

The inspectors found that River Bend Station did not verify semiannually that the two fire doors that comprise the 3-hour rated fire barrier between the electrically driven fire pump and the two diesel driven fire pumps were operable. While the doors had originally been inspected periodically, the inspectors found that the doors had not been inspected to verify the closing mechanisms were operable since October 2003.

The fire suppression pumps are required to be separated such that a failure of one supply does not result in a failure of the other supply. The pumps are 50 percent capacity pumps such that at least two must function to supply 100 percent fire water demand. If either of the fire doors fail to close, a failure of any pump due to fire will fail at least one other pump. The inspectors determined that the failure to verify the door closing mechanisms were operable was a failure to meet the licensees approved fire protection program.

The inspectors also determined that the doors were removed from the licensees inspection program without making a change to the approved fire protection program in accordance with their license condition. The inspectors determined that the decision to change the inspections occurred in 2003 and was not indicative of current performance.

Corrective Actions: The licensee added the two doors to their testing program.

Corrective Action References: CR-RBS-2021-06648

Performance Assessment:

Performance Deficiency: The failure to verify operability of a required fire door in accordance with the approved fire protection plan was a performance deficiency.

Screening: The inspectors determined the performance deficiency was more than minor because it was associated with the Protection Against External Factors attribute of the Mitigating Systems cornerstone and adversely affected the cornerstone objective to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences. Specifically, the finding represented a loss of control of fire barriers required to ensure the availability of fire suppression equipment.

Significance: The inspectors assessed the significance of the finding using Appendix F, Fire Protection and Post - Fire Safe Shutdown SDP. Using Inspection Manual Chapter 0609, 04, Initial Characterization of Findings, the inspectors determined the finding was associated with the Mitigating Systems cornerstone. Using Inspection Manual Chapter 0609, Appendix F, Fire Protection Significance Determination Process, the inspectors determined the finding was associated with fire confinement and was assigned a High degradation rating. The inspectors used Step 1.4.4 to determine that the finding was of very low safety significance (Green) because there was an adequate automatic suppression system on one side of each fire confinement element.

Cross-Cutting Aspect: Not Present Performance. No cross-cutting aspect was assigned to this finding because the inspectors determined the finding did not reflect present licensee performance. The inspectors determined that the performance deficiency was not reflective of present performance because the performance deficiency occurred in 2003.

Enforcement:

Violation: The River Bend Station, Unit 1, Renewed Facility Operating License, Section 2.C(10) and Attachment 4, requires that the licensee implement and maintain in effect all provisions of the approved fire protection program. The approved fire protection plan requires that self-closing fire doors shall be inspected semiannually to verify that automatic hold-open, release, and closing mechanisms and latches are operable. Contrary to the above, from October 2003 to December 2021, the licensee failed to verify that the affected automatic hold-open, release, and closing mechanisms were operable.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

Failure to Demonstrate Effective Control of Performance for a Maintenance Rule (a)(2)

System Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000458/2021004-02 Open/Closed

[H.8] -

Procedure Adherence 71111.06 The inspectors identified a Green finding and associated non-cited violation of 10 CFR 50.65(a)(2) with 13 examples of failures to demonstrate effective control of performance of a maintenance rule scoped system through appropriate preventive maintenance.

Description:

The inspectors identified multiple examples where the performance of structures, systems, and components (SSCs) that were subject to the maintenance rule were neither monitored against goals and corrective actions nor demonstrated to be effectively controlled through appropriate preventive maintenance.

All of the examples are related to Systems 888 and 889, Pressure and Watertight Doors, however the one discussed in detail for this finding is AB070-03.

Watertight door AB070-03 is an internal flood mitigation door between two safety-related systems, low pressure core spray (LPCS) and residual heat removal train A (RHR A). The licensees maintenance rule program classifies this door as a high-risk safety-related door, and the door is currently included in their systems to be monitored under (a)(2) of the maintenance rule. Procedure EN-DC-150, Condition Monitoring of Maintenance Rule Structures, Section 7.1.5 states: follow-up inspections will be performed at 5-year intervals for high-risk and 10-year intervals for low-risk systems, if the walkdown is not conducted in interval plus grace period it should be classified as A1. River Bend Station Specification No. 210.461, Pressure tight Doors, Watertight Doors, and Special Doors, Revision 2, specifically states that AB070-03 shall be designed to sustain a pressure of 2.1 psi multiplied by a dynamic load factor of 1.85 and that the door shall withstand 28 feet of head from both sides. Additionally, the vendor manual, 3210.461-3040002C, Revision A, requires removing the boltwork cover to check and lubricate the linkages every 6 months. It gives a specification for door seal adjustment to 3/32-inch utilizing set screws in order to ensure 100 percent seal engagement with the door frame. However, it does not specify a periodicity to perform this action.

To ensure the door could meet its design function as specified, the performance monitoring requirement utilized by the licensee was work order (WO) 00196451. This work order was last completed January 12, 2010. This has exceeded the 5-year performance monitoring criteria of EN-DC-150 and the door should have had goals and corrective actions established per 10 CFR 50.65(a)(1). The licensee failed to do this.

After the inspectors brought this issue to the licensees attention, they went to the field with licensee engineers to assess the status of the door seal and to ascertain its ability to accomplish its design function. During the field inspection, the inspectors discovered that air could be felt leaking past the door seal in various locations and questioned the doors ability to maintain pressure tight and watertight integrity. The licensee agreed that the door failed to meet its inspection acceptance criteria, declared the door non-functional, and took action to correct the deficiency.

Additional watertight and pressure tight doors scoped into (a)(2) as high risk that have work orders to validate the doors safety function but have not been monitored every 5 years are:

AB095-02, AB095-06, AB141-04, DG098-01, DG098-02, DG098-03, DG098-10, FB070-04, SS118-05, SS118-06, SS154-01, and SS154-02.

Corrective Actions: The licensee entered this issue into their corrective action program, performed an engineering inspection on door AB070-03, and adjusted the door to restore its function.

Corrective Action References: CR-RBS-2021-07349, CR-RBS-2021-07493, and CR-RBS-2022-00061

Performance Assessment:

Performance Deficiency: The failure to monitor the performance or demonstrate effective control of performance of systems covered by the maintenance rule is a performance deficiency.

Screening: The inspectors determined the performance deficiency was more than minor because it was associated with the SSC Performance attribute of the Mitigating Systems cornerstone and adversely affected the cornerstone objective to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences.

Significance: The inspectors assessed the significance of the finding using Appendix A, The Significance Determination Process (SDP) for Findings At-Power. Using Inspection Manual Chapter 0609, Attachment 04, Initial Characterization of Findings, dated October 7, 2016, the inspectors determined the finding was associated with the Mitigating Systems cornerstone. Using Inspection Manual Chapter 0609, Appendix A, The Significance Determination Process (SDP) For Findings At-Power, Exhibit 2, Mitigating Systems Screening Questions, led the inspectors to Exhibit 4, External Events Screening Questions.

The inspectors determined the finding was of very low safety significance (Green) because the finding did not represent a degradation in two or more trains of a multi-train system or function and did not involve a loss of any Probabilistic Risk Assessment function.

Cross-Cutting Aspect: H.8 - Procedure Adherence: Individuals follow processes, procedures, and work instructions. The licensee had the opportunity to identify and correct this gap in System 889 performance monitoring during their last SSC inspection to meet the objectives of EN-DC-150 in 2019.

Enforcement:

Violation: Title 10 CFR 50.65(a)(1), requires, in part, that the holders of an operating license shall monitor the performance or condition of SSCs within the scope of the rule as defined by 10 CFR 50.65(b), against licensee-established goals, in a manner sufficient to provide reasonable assurance that such SSCs are capable of fulfilling their intended functions.

Title 10 CFR 50.65(a)(2) states, in part, that monitoring as specified in 10 CFR 50.65(a)(1) is not required where it has been demonstrated that the performance or condition of an SSC is being effectively controlled through the performance of appropriate preventive maintenance, such that the SSC remains capable of performing its intended function.

Contrary to the above, from January 12, 2010 to December 15, 2021, the licensee failed to demonstrate that the performance or condition of watertight door AB070-03 had been effectively controlled through the performance of appropriate preventive maintenance and did not monitor against licensee-established goals. Specifically, the licensee failed to monitor the performance of watertight door AB070-03 for over 10 years, exceeding the established 5-year monitoring period. The performance or condition of this SSC was not being effectively controlled through the performance of appropriate preventive maintenance and, as a result, goal setting and monitoring was required. The licensee then failed to evaluate the door for (a)(1) status. There were 12 additional examples of this violation associated with watertight and pressure tight doors AB095-02, AB095-06, AB141-04, DG098-01, DG098-02, DG098-03, DG098-10, FB070-04, SS118-05, SS118-06, SS154-01, and SS154-02.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

Observation: Semiannual Trend Review 71152 The inspectors reviewed a selection of several condition reports for appropriate screening and classification in accordance with the licensees corrective action procedure. Title 10 CFR 50, Appendix B, Criterion XVI, states Measures shall be established to assure that conditions adverse to quality, such as failures, malfunctions, deficiencies, deviations, defective material and equipment, and nonconformances are promptly identified and corrected. The inspectors noticed a trend of condition reports that identified failures, malfunctions, deficiencies, deviations, defective material and equipment, and nonconformances, but were not classified as conditions adverse to quality.

The licensee uses Procedure EN-LI-102, Corrective Action Program, as guidance for meeting the regulatory requirements of Criterion XVI. Under the definitions section, the procedure defines condition adverse to quality (CAQ) as a failure, malfunction, deficiency, deviation, defective material or equipment, or nonconformance affecting the safety-related function of a structure, system or component. It further breaks down the definitions of all the terms used to define a CAQ. If an equipment condition is found to not be a CAQ, their procedure allows it to be classified as non-adverse, which does not require corrective action to be taken.

The inspectors determined that the licensee has in some cases used a determination that a component is operable in accordance with the approved Technical Specification as a basis for determining a condition is not a condition adverse to quality. The inspectors noted that a determination of operability is not used in the language of Criterion XVI or the licensees procedure as a basis to determine whether a condition is a CAQ and whether it is required to be corrected. Some examples are defined below:

Condition Report CR-RBS-2021-03195 describes a safety-related residual heat removal sample isolation valve that failed to open. The licensee initially classified this condition report as non-adverse, but after the inspectors questioned the classification, the licensee reclassified it as a CAQ.

Condition Report CR-RBS-2021-03617 describes a steam leak on the reactor core isolation cooling turbine flange. The licensee classified this condition report as non-adverse despite it being a deficiency of a safety-related component.

Condition Report CR-RBS-2021-03618 describes a steam leak on the reactor core isolation cooling governor valve. The licensee classified this condition report as non-adverse despite it being a deficiency of a safety-related valve.

Condition Report CR-RBS-2021-05750 describes a ground on the safety-related 125 VDC bus. The licensee classified this condition report as non-adverse despite it being a deficiency of a safety-related bus.

Condition Report CR-RBS-2021-07000 describes significant corrosion on the diesel fire pump 1A exhaust pipe, which is a quality-related component. The licensee classified this condition report as non-adverse despite it being a deficiency of a quality-related pipe.

The inspectors noted that these condition reports were closed to the work management system and had open work orders associated with them. Procedure EN-LI-102 allows use of the work management system but has administrative controls to ensure that these CAQs are corrected. Because the conditions were classified as non-adverse, the licensee would be allowed by procedure to close the work orders without correcting the condition.

The inspectors identified one example of a minor violation of 10 CFR 50, Appendix B, Criterion XVI.

Condition Report CR-RBS-2017-02678 describes a failed remote shutdown panel light socket, which is a safety-related component, that was identified on March 19, 2017. The lack of indication prevents normal operation of the system because operators would have to take additional actions to operate the system. Specifically, the circuit automatically repositioned valves required for shutdown outside the control room, and the light provided indication that the associated switches were in the correct position. With the light socket failed, operators would have to verify proper alignment of components in the field. The licensee classified the condition report as non-adverse and closed the associated work order without correcting the deficiency. The deficiency was identified again in 2019 and a new condition report (CR-RBS-2019-03671) was generated. This condition report was also classified as non-adverse and closed to a work order that remains open. The inspectors determined that the licensee had not promptly corrected this CAQ because the condition has existed for nearly four years with multiple opportunities to correct the condition. The inspectors determined the violation was minor because it would not lead to a more significant safety concern and did not adversely impact any reactor oversight process cornerstone. The inspectors determined that, while the condition requires additional operator actions to verify proper operation of the circuit, the licensee had demonstrated through unrelated test and maintenance activities that the circuit would still automatically operate the affected components as designed. The licensee has an open work order in place to repair the light socket. This failure to comply with 10 CFR 50, Appendix B, Criterion XVI, constitutes a minor violation that is not subject to enforcement action in accordance with the NRCs Enforcement Policy. The licensee entered this violation into their corrective action program under Condition Report CR-RBS-2021-07529.

The inspectors did not identify a finding associated with this review.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

On January 10, 2022, the inspectors presented the integrated inspection results to Mr. K. Scott, Site Vice President, and other members of the licensee staff.

On November 8, 2021, the inspectors presented the heat sink performance inspection results to Mr. B. Chenard, Director, Engineering, and other members of the licensee staff.

On November 19, 2021, the inspectors presented the public radiation safety inspection results to Mr. B. Chenard, Director, Engineering, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.05

Corrective Action

Documents

CR-RBS-

1991-00123

71111.05

Miscellaneous

ER-RB-2001-

0136-000

Document the Basis for the Scope and Frequency of Fire

Protection Testing

71111.05

Miscellaneous

ER-RB-2004-

275-000

Summarize All RBS NFPA Code Deviations

71111.05

Procedures

FPP-0108

Fire Door Monthly Inspection - Non Cat I

71111.05

Work Orders

WO 2986268

71111.06

Miscellaneous

RBS-CS-15-

00005

Maintenance Rule Structures Basis/Scoping Document

71111.06

Miscellaneous

River Bend

Station

Specification No.

210.461

Pressuretight Doors, Watertight Doors, and Special Doors

71111.06

Miscellaneous

Vendor Manual

210.461-

3040002C

Installation Operating and Maintenance Instructions for

Pressure Tight and Water Tight Doors

A

71111.06

Procedures

EN-DC-150

Condition Monitoring of Maintenance Rule Structures

71111.07T

Calculations

Calculation No.

28.850-DB-1505

Steam Tunnel Heat Gain Due to Jet Impingement Wall

71111.07T

Calculations

Calculation No:

IA-SWP*9

Setpoint Calculation for Bistables SWP*ESX064,

SWP*ESY164, SWP*ESX167, and SWP*ESY167 Standby

Cooling Tower Hi-Low Level Alarm & Min Wtr

71111.07T

Calculations

ES-164

Drywell and Containment Response to Small and

intermediate Break Accidents

71111.07T

Calculations

G13.18.2.1*061

Auxiliary Building Design Basis Heat Loads and Unit Cooler

Sizing Verification

71111.07T

Calculations

G13.18.2.7*51

WATHAM Analysis with Trapped Air in SSW System Drywell

Unit Coolers Piping

0A

71111.07T

Calculations

G13.18.3.0*3-1

Auxiliary Building Normal/Accident Electrical Heat Loads

08/26/1996

71111.07T

Calculations

PX-562

Waterhammer Analysis with Trapped Air in SSW System A

Header and LONSW 1/LORPCCW and LOOP Events

2A

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.07T

Calculations

PX-567

Segment Force Factor for the Component Piping of the SSW

System

2A

71111.07T

Corrective Action

Documents

CR-RBS-

CR-RBS-2019-04371, CR-RBS-2017-4302, CR-RBS-1999-

00137, CR-RBS-2021-04161, CR-RBS-2021-04373, CR-

RBS-2018-03888, CR-RBS-2019-02728

71111.07T

Corrective Action

Documents

Resulting from

Inspection

CR-RBS-

CR-RBS-2021-06720, CR-RBS-2021-06756

71111.07T

Drawings

215.253-809-

2

Auxiliary Building Unit Cooler Replacement Cooling Coil

C

71111.07T

Drawings

E-1027

  1. 1818 Type NSP - 2 Pass Jacket Water Cooler

01/07/1981

71111.07T

Drawings

EP-19H

River Send Station Unit 1 - Service Water Piping Standby

Cooling Tower (Plan).

71111.07T

Drawings

PID-08-09C

River Bend Unit 1 Engineering P&ID Diagram System 309

Diesel Generator

71111.07T

Engineering

Changes

ER-RB-1999-

0766-000

Raise Area Temperatures to 122 Degrees Fahrenheit for

EDC Zones AB-114-1, AB-114-3, AB-141-1, AB-141-2, AB-

141-3, AB-141-4, and AB170-2

71111.07T

Engineering

Evaluations

ER#: ER-RB-

1999-0690-000

Design Margin Recovery for Aux Building Unit Coolers Using

degrees Fahrenheit Max Service Water Temperature vs

degrees Fahrenheit Used in Original HVAC Design

71111.07T

Miscellaneous

Accessible System Walkdown Plan - Standby Service Water

(SSW/256)

10/04/2021

71111.07T

Miscellaneous

  • R-STM-0403

System Training Manual - *Reactor Building HVAC System

71111.07T

Miscellaneous

Cycle 22 -

August 6, 2021

River Bend Station Closed Cooling Water Systems Strategic

Plan

71111.07T

Miscellaneous

ER99-0766 -

NESE908

Heat Transfer Performance of Replacement Coils for

Auxiliary Building Unit Coolers at 95°F Service Water

Temperature

05/30/2001

71111.07T

Miscellaneous

File Nos.:

G1.49.5, G9.5,

G9.33.4

Updated Response to Generic Letter 89-13, Service Water

System Problems Affecting Safety-Related Equipment

10/21/1998

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.07T

Miscellaneous

LCR No:

1.ILMOS.042

Loop Calibration Report

71111.07T

Miscellaneous

LCR No:

1.ILMOS.009

Loop Calibration Report

71111.07T

Miscellaneous

Loop No:

1.ILSWP.174

Standby Cooling Tower 1 Level Loop

10/04/2017

71111.07T

Miscellaneous

Operability

Evaluation CR-

RBS-2021-4161

Evaluate Steam Tunnel Temperatures with Active Steam

Leak in Progress

06/16/2021

71111.07T

Miscellaneous

Operating and

Maintenance

Manual NU9-M62

Air Handling Cabinets

06/14/1982

71111.07T

Miscellaneous

Q3-2021 RBS

256-Service

Water Standby

Third Quarter 2021 System Health Report for Service Water

Cooling System

10/07/2021

71111.07T

Miscellaneous

RBC-39428

NRC Generic Letter NO, 89-13, Letter of NRCs Receipt of

GSUs First of Two Responses to Service Water System

Problems Affecting Safety-Related Equipment

03/14/1990

71111.07T

Miscellaneous

SDC-118, 130, &

256

System Design Criteria, Normal Service Water - System

Number 118. Standby Service Water - System Number 256.

Service Water Cooling - System Number 130

71111.07T

Miscellaneous

Set Point Data

Sheet No. 12210-

IA-MOS-CP100A-

MUX39-1

Plant Computer & 1Swp-MUX39 - Standby Service Water

Cooling Tower 1 (Wide Range Temperature Detection

(Temp. High))

07/27/1994

71111.07T

Miscellaneous

Specification No.

215.252

Specification for Containment Unit Coolers and Auxiliary

Building Unit Coolers with ASME III, Class 3 Coils

07/30/1981

71111.07T

Miscellaneous

Specification No.

244.700

Specification for Standby diesel Generator Systems, ASME

Code,Section III, Class 3

04/12/1985

71111.07T

Miscellaneous

Suppliers

Document Data

Form File No.

21.482-601-

001A

Heat Exchanger Performance at Design Conditions

11/03/1999

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.07T

Miscellaneous

System Training

Manual - RTM -0

118

Service Water Systems

71111.07T

Miscellaneous

Vendor Manual

No. NU9-M62

Buffalo Forge Company, Installation and Operation

Instructions for Air Handling Cabinets for Gulf States Utilities,

River Bend Station, Unit 1

01/14/1986

71111.07T

Miscellaneous

Vendor Manual:

Site Manual No:

B515-0136

Howden Buffalo Service Manual, Installation and

Maintenance of Axial Flow Fans

71111.07T

NDE Reports

BOP-UT-09-017

Carbon Steel 8 inch Line - B Tunnel 79 foot. (Procedure

CED-NDE-0505)

10/21/2019

71111.07T

NDE Reports

BOP-UT-19-012

Carbon Steel 8 inch Line (Procedure CEP-NDE-0505)

10/16/2019

71111.07T

NDE Reports

BOP-UT-19-013

Carbon Steel 12 inch Line (Procedure CEP-NDE-0505)

10/21/2019

71111.07T

NDE Reports

BOP-UT-19-014

Carbon Steel 8 inch Line (Procedure CED-NDE-0505)

10/16/2019

71111.07T

NDE Reports

BOP-UT-19-015

Carbon Steel 8 inch Line - B Tunnel 81 foot. (Procedure

CED-NED-0505)

10/16/2019

71111.07T

NDE Reports

BOP-UT-19-016

Carbon Steel 8 inch Line - B Tunnel 79 foot. (Procedure

CED-NDE-0505)

10/21/2019

71111.07T

NDE Reports

BOP-UT-21-019

UT Thickness on HVR UC8 Accessible Coils

03/05/2021

71111.07T

Procedures

  • STP-602-6311
    • DIV 1 FUEL POOL COOLING PUMP AND VALVE

OPERABILITY

TEST

307

71111.07T

Procedures

AOP-0009

River Bend Station Operating Manual Abnormal Operating

Procedure - Loss of Normal Service Water.

71111.07T

Procedures

AOP-0016

River Bend Station Operating Manual Abnormal Operating

Procedure - Loss of Standby Service Water

71111.07T

Procedures

AOP-0053

River Bend Station Operating Manual Abnormal Operating

Procedure - Initiation of Standby Service Water with Normal

Service Water Running.

71111.07T

Procedures

COP-0123

River Bend Station Operating Manual Chemistry Operation

Procedure - Chemical Treatment of the Standby Cooling

Tower

71111.07T

Procedures

CSP-0006

River Vend Station Operating Manual Chemistry Section

Procedure - Chemistry Surveillance and Scheduling System.

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.07T

Procedures

EN-DC-126

Engineering Calculation Process

71111.07T

Procedures

EN-DC-150

Condition Monitoring of Maintenance Rule Structures

71111.07T

Procedures

EN-DC-178

System Walkdowns

71111.07T

Procedures

EN-DC-184

NRC Generic Letter 89-13 Service Water Program

71111.07T

Procedures

EN-DC-316

Heat Exchanger Performance and Condition Monitoring

71111.07T

Procedures

EN-DC-343

Underground Piping and Tanks Inspection and Monitoring

Program

71111.07T

Procedures

EN-WM-100

Work Request Generation, Screening and Classification

71111.07T

Procedures

EN-WM-102

Work Implementation and Closeout

71111.07T

Procedures

EN-WM-110

Surveillance Program

71111.07T

Procedures

SDC-118, 130, &

256

River Bend Station System Design Criteria, Service Water

System Design Criteria System Numbers 118, 130, & 256

71111.07T

Procedures

SEP-HX-RBS-00

Service Water Heat Exchanger Inspection

71111.07T

Procedures

SEP-HX-RBS-002

Performance Monitoring Program for the Residual Heat

Removal Heat Exchangers E12-EB001B and E12-EB001D

(DIV II)

71111.07T

Procedures

SEP-HX-RBS-003

Performance Monitoring Program for Residual Heat Removal

Heat Exchangers E12-EB001 A and E12-EB001C (DIV I)

71111.07T

Procedures

SEP-SW-RBS-

001

RBS GL89-13 Service Water Heat Exchanger Program

71111.07T

Procedures

STP-256-6301

Div I Standby Service Water Quarterly Valve Operability Test

71111.07T

Procedures

STP-256-6302

Div II Standby Service Water Quarterly Valve Operability

Test

71111.07T

Procedures

STP-256-6303

Standby Service Water A Loop Quarterly Pump and Valve

Operability Test

71111.07T

Procedures

STP-256-6304

Standby Service Water B Loop Quarterly Pump and Valve

Operability Test

307

71111.07T

Procedures

STP-256-6305

Div I Standby Service Water Quarterly Valve Operability Test

71111.07T

Procedures

STP-256-6306

Div II Standby Service Water Quarterly Valve Operability

Test

71111.07T

Procedures

STP-256-6801

Div I Standby Service Water Cold Shutdown Pump and

Valve Operability Test

71111.07T

Procedures

STP-256-6802

Div II Standby Service Water Cold Shutdown Pump and

Valve Operability Test

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.07T

Procedures

STP-403-0303

Containment Unit Cooler HVR-UC1B Flow Rate Verification

307

71111.07T

Procedures

TP-256-0202

Division II Standby Cooling Tower Fans Operability Test

71111.07T

Self-Assessments

Engineering

Report No. RBS-

CS-19-00004

2019 Maintenance Rule Structures Periodic Assessment

09/25/2019

71111.07T

Self-Assessments LO Tracking No.

RLO-2020-00021

Pre-NRC Self-Assessment - Heat Sink Performance. River

Bend Station

07/21/2021

71111.07T

Self-Assessments LO Tracking No.

LO-RLO-2019-

00144 CA2

Heat Exchanger Self-Assessment

71111.07T

Work Orders

Work Orders -

RBS

00323927, 00512093, 52969070, 53971325, 52971330,

2972347, 52972352, 52972852, 52980530, 52981898,

2898379, 00361644, 00546349, 52770525, 51087021,

2763985, 52896855, 52763985, 52491009, 52767256,

2782059, 52799020, 52975603, 00512093, 00361644,

00523466, 52887229-01,

71124.05

Miscellaneous

Radiation Protection Instrument List

11/16/2021

71124.05

Miscellaneous

USAR Table 12.3-

Area Direct Radiation Monitor Locations

71124.05

Miscellaneous

USAR Table 12.3-

Airborne Process and Effluent Radiation Monitors

71124.06

Miscellaneous

USAR Table 12.3-

Airborne Process and Effluent Radiation Monitors

71124.06

Miscellaneous

USAR, Chapter

Radioactive Waste Management

71124.07

Miscellaneous

Metrology Data for 11/15/2021

11/16/2021

71124.07

Miscellaneous

Daily Operating Logs

Data Sheet 1, Page 8 of 19

11/16/2021

71124.08

Miscellaneous

USAR, Chapter

Radioactive Waste Management

71124.08

Procedures

RWS-0336

Setup and Operation of the RDS-1000 Dewatering Unit

71124.08

Radiation

Surveys

RBS-2106-00097

4114 Special Nuclear Material Storage Room, RadWaste

106'

06/08/2021

71124.08

Radiation

RBS-2106-00138

Liner 200L-21003 Characterization in the RadWaste 106'

06/15/2021

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Surveys

Processing Area

71124.08

Radiation

Surveys

RBS-2110-00255

4100 RadWaste 106' (Monthly Survey)

10/30/2021

71124.08

Radiation

Surveys

RBS-2111-00139

28 RadWaste 90' Vendor Transfer Header

11/11/2021

71124.08

Radiation Work

Permits (RWPs)

211234

RadWaste Liner Processing and Support Activities

71124.08

Shipping Records

RBS-2021-083

LWS Bead Resin / 200L-21003

UN 3321 Radioactive Material, Low Specific Activity (LSA-II),

11/17/2021

71152

Corrective Action

Documents

CR-RBS-

21-00644

71152

Corrective Action

Documents

CR-RBS-

2017-02678, 2019-03671

71152

Procedures

EN-LI-102

Corrective Action Program

71152

Procedures

OSP-0053

Emergency and Transient Response Support Procedure

71152

Procedures

OSP-0602

Remote Shutdown System Control Circuit Operability Test

71152

Procedures

SOP-0009

Reactor Feedwater System (SYS#107)

JJ

JE

FR

HG

PV

VG

RK

CW

AS

MH

DATE

RIVER BEND STATION - INTEGRATED INSPECTION REPORT 05000458/2021004

January 25,

22