IR 05000458/2023012

From kanterella
Jump to navigation Jump to search
– Comprehensive Engineering Team Inspection Report 05000458/2023012
ML23236A496
Person / Time
Site: River Bend 
Issue date: 09/01/2023
From: Vincent Gaddy
NRC/RGN-IV/DORS/EB1
To: Hansett P
Entergy Operations
References
IR 2023012
Download: ML23236A496 (24)


Text

September 01, 2023

SUBJECT:

RIVER BEND STATION - COMPREHENSIVE ENGINEERING TEAM INSPECTION REPORT 05000458/2023012

Dear Phil Hansett:

On August 3, 2023, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at River Bend Station and discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report.

Three findings of very low safety significance (Green) are documented in this report. Two of these findings involved violations of NRC requirements. We are treating these violations as non-cited violations (NCVs) consistent with Section 2.3.2 of the Enforcement Policy.

If you contest the violations or the significance or severity of the violations documented in this inspection report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN:

Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region IV; the Director, Office of Enforcement; and the NRC Resident Inspector at River Bend Station.

If you disagree with a cross-cutting aspect assignment or a finding not associated with a regulatory requirement in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region IV; and the NRC Resident Inspector at River Bend Station. This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Vincent G. Gaddy, Chief Engineering Branch 1 Division of Operating Reactor Safety Docket No. 05000458 License No. NPF-47

Enclosure:

As stated

Inspection Report

Docket Number:

05000458

License Number:

NPF-47

Report Number:

05000458/2023012

Enterprise Identifier:

I-2023-012-0002

Licensee:

Entergy Operations, Inc.

Facility:

River Bend Station

Location:

St. Francisville, LA

Inspection Dates:

July 17, 2023 to August 3, 2023

Inspectors:

J. Braisted, Senior Reactor Inspector

D. Bryen, Reactor Inspector

W. Cullum, Senior Reactor Inspector

C. Franklin, Reactor Inspector

R. Kumana, Senior Reactor Inspector

D. Reinert, Senior Reactor Inspector

F. Thomas, Reactor Inspector

Approved By:

Vincent G. Gaddy, Chief

Engineering Branch 1

Division of Operating Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a comprehensive engineering team inspection at River Bend Station, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors.

Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

Failure to Follow Procedure for Work Performed on Safety-Related 480 VAC Electrical Equipment Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green FIN 05000458/2023012-01 Open/Closed

[H.12] - Avoid Complacency 71111.21M The inspectors identified a Green finding involving the licensee's failure to initiate condition reports for observed elevated temperatures on safety-related switchgear in accordance with station procedure EN-DC-310.

Failure to Follow Instructions for Standby Service Water Flow Balance Testing Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000458/2023012-02 Open/Closed

[H.5] - Work Management 71111.21M The inspectors identified a Green finding and associated non-cited violation (NCV) of 10 CFR Part 50, Appendix B, Criterion V, "Instructions, Procedures, and Drawings," with five examples, of the licensees failure to work order test instructions.

Failure to Maintain Test Records Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000458/2023012-03 Open/Closed None (NPP)71111.21M The inspectors identified a Green finding and associated non-cited violation (NCV) of 10 CFR Part 50, Appendix B, Criterion XVII, "Quality Assurance Records," for two examples of the licensees failure to maintain test records for the standby service water flow balance.

Additional Tracking Items

None.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

===71111.21M - Comprehensive Engineering Team Inspection The inspectors evaluated the following components and listed applicable attributes, permanent modifications, and operating experience:

Structures, Systems, and Components (SSCs) (IP section 03.01)===

(1) Containment Unit Cooler A Return Header Inboard Containment Isolation Valve, SWP-MOV503A

Updated final safety analysis report, technical specifications, and technical specifications bases document

Motor-operated valve program document, environmental qualification reports, inservice testing plan, and standby service water system design criteria

Calculations for maximum expected differential and line pressure, torque and thrust setpoints, and the seismic/weak-link analysis

Standby service water system piping and instrumentation diagram and the motor-operated valve electrical schematic diagram

Valve and actuator vendor manuals for installation, operation, and maintenance

Inservice testing records including procedures and results for position indication, leakage, opening, and closing

Diagnostic testing records including procedures and results

Maintenance work order history records of visual inspections, packing adjustments, lubrications, and overhaul

Corrective action program documents

Visual inspection of the as-built configuration and material condition

(2) Containment Unit Cooler A, HVR-UC1A

Updated safety analysis report, technical specifications, and technical specifications bases document

Environmental qualification reports and reactor plant ventilation system design criteria

Calculations for accident environmental conditions in containment, air intake free area of the unit cooler, and the maximum temperature of containment after a loss of offsite power Standby service water system piping and instrumentation diagram

Vendor manuals for installation, operation, and maintenance of the cooling coils and fan

Surveillance test records of air flow and standby service water system flow balancing

Maintenance work order history records of visual inspections

Corrective action program documents

Visual inspection of the as-built configuration and material condition

(3) Division 1 Diesel Generator Room Standby Exhaust Fan, HVP-FN02A

Updated safety analysis report, technical specifications, and technical specifications bases document

Diesel generator building ventilation system design criteria

Calculations for electrical power supply for motor and controls, heat removal and ventilation attributes, damper design for normal and extreme conditions

Vendor manuals for installation, operation, and maintenance of the fan and dampers

Maintenance work order history records of visual inspections and cleaning/lubrication

Corrective action program documents

Visual inspection of the as-built configuration and material condition

(4) Reactor Core Isolation Cooling Pump Injection Isolation Valve, E51-MOVF013

Updated final safety analysis report, technical specifications, and technical specifications bases document

Motor-operated valve program document, environmental qualification reports, inservice testing plan, and reactor core isolation cooling system design criteria

Calculations for maximum expected differential and line pressure, torque and thrust setpoints, and the seismic/weak-link analysis

RCIC system piping and instrumentation diagram and the motor-operated valve electrical schematic diagram

Valve and actuator vendor manuals for installation, operation, and maintenance

Inservice testing records including procedures and results for position indication, leakage, opening, and closing

Diagnostic testing records including procedures and results

Maintenance work order history records of visual inspections, packing adjustments, lubrications, and overhaul

Corrective action program document

(5) Division 1 Diesel Generator, EGS-EG1A

Updated final safety analysis report, technical specifications, and technical specifications bases document.

Diesel generator lube oil and jacket water system design criteria.

Calculations for electrical loading and environmental conditions.

Vendor manuals for installation, operation, and maintenance of the diesel engine and generator.

Diesel generator operating logs

Diesel generator reliability program procedures and records.

Maintenance work order history records.

Corrective action program documents.

Visual inspection of the as-built configuration and material condition.

(6) Division 1 Diesel Fuel Oil Transfer Pump, EGF-P1A

Updated final safety analysis report, technical specifications, and technical specifications bases document

Design basis documents

System operating procedures

Corrective action program documents.

Visual inspection of component during walkdown

Surveillance testing records including procedures and results

(7) Diesel Generator Loading & Sequencing

Updated final safety analysis report, technical specifications, and technical specifications bases document

Design calculations and associated engineering changes

Surveillance testing records including procedures and results

(8) Standby Service Water Pump 2B, SWP-P2B

Updated final safety analysis report, technical specifications, and technical specifications bases document

Vendor pump curves

Design basis calculations for standby service water system flow

Net positive suction head requirements

Pump runout condition calculations

Preventative maintenance tasks

Vendor manuals and recommendations

Corrective action program documents

Standby service water system piping and instrumentation diagrams

Visual inspection of the as-built configuration and material condition

(9) Reactor Core Isolation Cooling Turbine Steam Supply Isolation Valve, E51-MOVF045

Updated final safety analysis report, technical specifications, and technical specifications bases documents

Motor-operated valve design calculations and program guidance

Motor-operated valve weak link analysis including seismic

Visual inspection of the as-built configuration and material condition

RCIC system piping and instrumentation diagram

Preventative maintenance tasks

Corrective action program documents

(10) Division 1 Standby 480V Switchgear 2A, EJS-SWG2A

Updated final safety analysis report, technical specifications, and technical specifications bases document.

Visual inspection of switchgear for as-built configuration and material condition

Environmental conditions for equipment

Voltage analysis and short circuit calculations

Protection settings and coordination study

Vendor manual for conformance with manufacturer instructions for installation and maintenance

Preventive maintenance and periodic verification testing

Component maintenance history

Schematic and wiring drawings

System health report

Corrective action program documents

(11) Division 2 Standby 480V Transformer 2B, EJS-X2B

Updated final safety analysis report, technical specifications, and technical specifications bases document.

Electrical drawings

Component maintenance history and corrective action program documents

Procedures for transformer inspection, maintenance, and testing

Thermography procedure and results

Voltage analysis and short circuit calculations

Visual inspection of switchgear for as-built configuration and material condition

Environmental conditions for equipment

System health report

Vendor manual and plant design drawings

Modifications (IP section 03.02) (4 Samples)

(1) EC 80652, Permanent Shielding AB-07/10-93 & RB-9B
(2) EC 93930, Raise the Level of the Main Turbine Level 8 Trip to Ensure no Overlap with RPS
(3) EC 92964, Standby Diesel Generator Fuel Line Replacement
(4) EC 94914, Gear Ratio Change for G33-MOVF053 10 CFR 50.59 Evaluations/Screening (IP section 03.03) (19 Samples)
(1) EC 84684, Replace Minimum Flow Feedwater Regulating Valve C (FWR-FV2C) Steel Piston Ring with Graphite Piston Ring to Prevent Valve Sticking
(2) EC 88823, Evaluation of Temperature Difference in HPCS Room while HPCS Is Running and HVR-UC5 Is Running per CR-RBS-2020-03649 CA 0004
(3) EC 88938, Evaluation of River Bend Spent Fuel Cooling Heat Exchangers (SFC-E1A and SFC-E1B) Degraded Performance Documented in CR-RBS-2020-2064 (SFC-E1A) And CR-RBS-2020-3877 (SFC-E1B)
(4) EC 93439, Evaluation Due to Flooding in Annulus Area
(5) EC 90805, Document Updates for Hydrogen Igniter Replacement
(6) EC 85966, Equivalent Replacement Valve for EG1-V137
(7) EC 92964, Standby Diesel Generator Fuel Line Replacement
(8) EC 86722, Tornado Missile Risk Evaluator (TRME)
(9) EC 89710, Removal of Ovation Point TCS Push Button Trip from Scan
(10) EC 92194, Evaluate MSIV Test Box When Performing 1/2 Isolation Surveillances
(11) EC 88513, Installation of Kiene Valves on HPCS Diesel Generator
(12) LBDCR 08.03-163, Update Values for the Emergency Diesel Loading for USAR
(13) EC 94914, Gear Ratio Change for G33-MOVF053
(14) EC 0000093476, RBS Appendix J Program Scope Reduction
(15) EC 0000089499, E12-MOVF021 Equivalency
(16) EC 0000084643, Replace SWP-MOV40C With Tricentric Butterfly
(17) EC 75637, Replace 2 J11 Gould Relays with 3 Allen Bradley Relays
(18) EC 75802, Replace 5 Obsolete Gould J11 Relays in EJS-SWG1A
(19) EC 94412, Nuclear Instrumentation Cable Splice Evaluation

Operating Experience Samples (IP section 03.04) (3 Samples)

(1) NOE-2021-0083, IRIS 498875 - Reactor Feedwater Pump Turbine Trip and Eight Percent Power Reduction
(2) NOE-2022-00185, Part 21 60-Day Final Report Notification: GNF3 Raised Water Rod
(3) NOE-2019-00168, NRC Information Notice 2019-02 Emergency Diesel Generator Excitation System Diode Failures

INSPECTION RESULTS

Failure to Follow Procedure for Work Performed on Safety-Related 480 VAC Electrical Equipment Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green FIN 05000458/2023012-01 Open/Closed

[H.12] - Avoid Complacency 71111.21M The inspectors identified a Green finding involving the licensee's failure to initiate condition reports for observed elevated temperatures on safety-related switchgear in accordance with station procedure EN-DC-310.

Description:

The purpose of the licensees predictive maintenance program is to improve plant safety, equipment availability, and reliability through early detection and analysis of equipment problems and degradation prior to equipment failure. The inspectors reviewed thermography data in work order (WO) 52952270 that was recorded as part of the Predictive Maintenance Program and noted that there were several instances where temperature rises for certain components met the action level criteria identified in the work orders and in procedure EN-DC-310, "Predictive Maintenance Program." Specifically, the inspectors reviewed the last several performances of the Division 2 thermography work orders and noted a progressively increasing trend in the temperature rise above ambient for EJS-SWG2B, standby 480 VAC Switchgear 2B, and EHS-MCC15B, standby 480 VAC motor control center 15B.

"Attachment 3, Data Evaluation," of EN-DC-310 defines the action levels to be used to classify anomalous temperature rises for 480 VAC equipment. Attachment 3, sections 2.7 through 2.9, state that a condition report and work request should be initiated for all conditions identified as level 1 or above.1 It also states, in part, that emphasis should be placed on observed trends and that severity of temperature indication must be determined by evaluation. Furthermore, when degraded conditions are indicated, the predictive maintenance team will take appropriate actions to ascertain the validity of the data and notify the system engineer and other appropriate personnel of the condition.

The thermography data from the reviewed work orders indicate that action levels up to level 3 have been reached. Level 3, denoted as Action, is defined as a temperature rise in excess of 50 degrees Fahrenheit (F) above an established reference temperature.

Section 6.7 of procedure EN-DC-310, "Predictive Maintenance Program," titled "Equipment Health Classification" indicates that the equipment health classification of Action suggests that accelerated degradation is expected, and that the following actions be taken:

1. Contact Operations, System Engineer and/or Component Engineer.

2. Compare the inspection results with other predictive maintenance trending information.

3. Ensure a Condition Report and Work Request/ECR or EC has been initiated to resolve

issue.

4. Recommend scheduling an emergent Work Request into the normal scheduling process.

According to the licensee, none of the above actions were taken. Thus, inspectors expressed concern that there could be a progressing degraded condition on safety-related components that has not been identified or evaluated.

Standby 480V Switchgear 2B contains several Square D MasterPact circuit breakers. Vendor Manual S345-148, page 9 of 479, indicates an operating temperature range of -22 degrees F and +140 degrees F for the Square D MasterPact circuit breakers. With maximum switchgear surface temperatures exceeding 140 degrees F, the inspectors expressed concern that these circuit breakers could be exposed to temperatures more than their established operating range for longs periods of time.

Based on interviews with engineering program personnel, there were no condition reports that could be found associated with the action level 1 or above temperature conditions, and there was no available documentation to indicate that any evaluation of observed trends or any corrective actions taken to address degraded conditions.

Corrective Actions: The licensee initiated condition reports to enter this concern into their corrective action program and to further review thermography data and other predictive maintenance trending information Division 2 Class 1E 480 VAC equipment for indications of accelerated degradation.

Corrective Action References: CR-RBS-2023-05997 and CR-RBS-2023-06233

Performance Assessment:

Performance Deficiency: The licensee failed to follow station procedures for work performed on safety-related equipment. Specifically, the licensee failed to write a condition report for observed temperature rise conditions that met procedure action levels on safety-related switchgear EJS-SWG2B and motor control center EHS-MCC15B in accordance with procedure EN-DC 310, "Predictive Maintenance Program."

Screening: The inspectors determined the performance deficiency was more than minor because if left uncorrected, it would have the potential to lead to a more significant safety concern. Specifically, the licensee failed to identify a deficient and deviating condition of significant temperature rise on EJS-SWG2B, standby 480 VAC Switchgear 2B, and EHS-MCC15B, standby 480 VAC motor control center 15B. If not addressed, this temperature rise could potentially lead to the degradation and failure of other internal components (i.e., relays and circuit breakers). Section 6.7 of the procedure EN-DC-310, titled Equipment Health Classification (Pages 19 and 20) indicates that the equipment health classification of Action means that accelerated degradation is expected.

Significance: The inspectors assessed the significance of the finding using IMC 0609 Appendix A, The Significance Determination Process (SDP) for Findings At-Power. Exhibit 2

- Mitigating Systems Screening Questions, Item A. Mitigating SSCs and PRA Functionality (except Reactivity Control Systems), specified that if the finding affected the design or qualification of a mitigating SSC, but it maintained its operability or PRA functionality then it screens to Green. The progressive increase in temperature rise on standby 480V switchgear 2B standby 480V motor control center 15B had not resulted in any known equipment failures.

Cross-Cutting Aspect: H.12 - Avoid Complacency: Individuals recognize and plan for the possibility of mistakes, latent issues, and inherent risk, even while expecting successful outcomes. Individuals implement appropriate error reduction tools. Specifically, licensee personnel failed to question the anomalous measured data or compare the measurements with historical trends.

Enforcement:

Inspectors did not identify a violation of regulatory requirements associated with this finding.

Failure to Follow Instructions for Standby Service Water Flow Balance Testing Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000458/2023012-02 Open/Closed

[H.5] - Work Management 71111.21M The inspectors identified a Green finding and associated non-cited violation (NCV) of 10 CFR Part 50, Appendix B, Criterion V, "Instructions, Procedures, and Drawings," with five examples, of the licensees failure to work order test instructions.

Description:

While reviewing documentation for the standby service water system flow balance tests, the inspectors identified five examples of the licensees failure to follow the test instructions.

Specifically:

The inspectors reviewed work order (WO) 323927 from the Division 2 standby service water system flow balance test conducted in December 2017. Step 4.3.4 stated Compare the collected data with acceptance criteria specified in Attachment 1, Flow Acceptance Criteria. Contrary to this step, the inspectors noted the following three issues:

The range of flow transmitter SWP-FT69B used to measure flow for HVK Chiller 1B and 1D is 0 to 670 gallons per minute (gpm). The maximum acceptable flow rate for HVK-CHL1B/D is 756 gpm. Therefore, the flow transmitters range is not suitable for the test. The acceptance criteria was not verified.

An alarm was used to demonstrate flow rate to ES001, the high-pressure core spray diesel generator cooler, was not below 700 gpm. However, no definitive value was taken for the ES001 flow rate. The minimum flow rate for ES001 is 800 gpm. The flow rate exceeding 700 gpm is not confirmation that it met the acceptance criteria.

The acceptance criteria for radiation monitors RMS-RE11A/B and RMS-RE15A/B is to verify flow exists. No flow measurement was taken for these components and a licensee technician annotated the work order package to indicate that these components were omitted from testing. Therefore, the acceptance criteria was not met.

Similarly, in the Division 1 standby service water system flow balance test WO 512093 conducted in March 2019, step 4.3.4 stated Compare the collected data with acceptance criteria specified in Attachment 1, Flow Acceptance Criteria. Contrary to this step four component flow rates were recorded with readings outside the acceptance criteria. However, all of the readings were marked acceptable in the work order.

In another instance, the Division 1 standby service water system flow balance test WO 323938 in November 2020, step 4.1.1.4 again stated Compare the collected data with acceptance criteria specified in Attachment 1, Flow Acceptance Criteria. The licensee recorded low flow for LSV-C3A, the penetration valve leakage control compressor. The licensee had previously determined the minimum acceptable flow rate to be 40 gpm and the flow rate recorded was 39.9 gpm. Licensee engineers approved of the deviation citing expected measurement and test equipment error, but no formal past operability determination was performed as required by the licensee procedure EN-LI-108, Event Notification and Reporting.

The inspectors also noted that WO 323938 for performance of the standby service water flow balance test in October 2019 contained a component / plant impact assessment statement which described many issues the licensee has encountered during historic performances of the standby service water flow balance tests. The challenges described include ownership of the work activity, resources, work schedule conflicts, radiological concerns, emergent work, procedural adequacy, and control of test instructions. It is unclear if any of these issues have been previously addressed in the corrective action program.

Corrective Actions: The licensee entered each procedural compliance issue into the corrective action program and performed operability evaluations to verify that the deficient flows had not rendered the affected components incapable of performing their required safety functions.

Corrective Action References: CR-RBS-2023-05991, CR-RBS-2023-05992, CR-RBS-2023-05994, CR-RBS-2023-05982, and CR-RBS-2023-06196

Performance Assessment:

Performance Deficiency: The licensee failed to follow a quality-related procedure in accordance with 10 CFR Part 50, Appendix B, Criterion V, "Instructions, Procedures, and Drawings." Specifically, the inspectors identified five examples of the failure to compare collected test data with established acceptance criteria.

Screening: The inspectors determined the performance deficiency was more than minor because it was associated with the Human Performance attribute of the Mitigating Systems cornerstone and adversely affected the cornerstone objective to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences. Specifically, the failure to perform a past operability evaluation on LSV-C3A created a doubt as to the past operability of the component. As a result, the component could have insufficient heat removal during a design basis accident.

Significance: The inspectors assessed the significance of the finding using IMC 0609 Appendix A, The Significance Determination Process (SDP) for Findings At-Power. Exhibit 2

- Mitigating Systems Screening Questions, Item A. Mitigating SSCs and PRA Functionality (except Reactivity Control Systems), specified that if the finding affected the design or qualification of a mitigating SSC, but it maintained its operability or PRA functionality then it screens to Green. The licensee was able to demonstrate that, through an updated methodology for calculating uncertainty, the component would have maintained positive margin and, therefore, remained operable. Specifically, the standby service water train would have maintained its function although one component may not have the required flow.

Cross-Cutting Aspect: H.5 - Work Management: The organization implements a process of planning, controlling, and executing work activities such that nuclear safety is the overriding priority. The work process includes the identification and management of risk commensurate to the work and the need for coordination with different groups or job activities. This cross-cutting aspect was chosen because it reflects the station's difficulty in assigning priority and resources to complete this work activity.

Enforcement:

Violation: 10 CFR 50, Appendix B, Criterion V, "Instructions, Procedures, and Drawings,"

requires, in part, "Activities affecting quality shall be prescribed by documented instructions, procedures, or drawings, of a type appropriate to the circumstances and shall be accomplished in accordance with these instructions, procedures, or drawings."

Contrary to the above, from December 2017 until November 2020, the licensee did not accomplish activities affecting quality in accordance with prescribed procedures. Specifically, the licensee did not compare collected test data with established acceptance criteria in accordance with work instructions for conducting standby service water system flow balance test work instructions.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

Failure to Maintain Test Records Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000458/2023012-03 None (NPP)71111.21M Open/Closed The inspectors identified a Green finding and associated non-cited violation (NCV) of 10 CFR Part 50, Appendix B, Criterion XVII, "Quality Assurance Records," for two examples of the licensees failure to maintain test records for the standby service water flow balance.

Description:

While reviewing documentation for the standby service water pumps, inspectors requested the work orders for recently completed standby service water flow balance tests. The flow balance test is conducted to verify that all components cooled by the safety-related standby service water flow loops receive appropriate flows. Upon retrieval of the work order packages, it was discovered that two of the work orders did not contain the completed paperwork and the flow data was missing.

Specifically:

Work order 51695027 for the performance of Division 1 standby service water flow balance testing in 2014 did not contain the completed test data. In the work order package 51008285 for Division 2 standby service water flow balance testing in 2008 the completed work order could not be located.

Although the completed data was not retained, the work orders contained statements that indicated the work was performed and no preventative maintenance tasks were missed.

However, it is unknown if all the results were acceptable since the data is missing.

Corrective Actions: The licensee wrote condition reports to document the missing records.

Corrective Action References: CR-RBS-2023-05938 and CR-RBS-2023-05911

Performance Assessment:

Performance Deficiency: The licensee's failure to maintain quality records for standby service water flow balance tests in accordance with 10 CFR Part 50, Appendix B, Criterion XVII, "Quality Assurance Records," was a performance deficiency.

Screening: The inspectors determined the performance deficiency was more than minor because it was associated with the Human Performance attribute of the Mitigating Systems cornerstone and adversely affected the cornerstone objective to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences. Specifically, subsequent standby service water flow balance testing found that several components were outside of the acceptance criteria, which called into question whether the 2008 and 2014 testing had satisfactory results. This is consistent with IMC 0612 Appendix E Minor Examples 1.a and 1.b.

Significance: The inspectors assessed the significance of the finding using IMC 0609 Appendix A, The Significance Determination Process (SDP) for Findings At-Power. Exhibit 2

- Mitigating Systems Screening Questions, Item A. Mitigating SSCs and PRA Functionality (except Reactivity Control Systems), specified that if the finding affected the design or qualification of a mitigating SSC, but it maintained its operability or PRA functionality then it screens to Green. Even though subsequent testing reveal that several components were outside the acceptance criteria, the licensee was able to demonstrate through analysis that operability was maintained.

Cross-Cutting Aspect: Not Present Performance. No cross-cutting aspect was assigned to this finding because the inspectors determined the finding did not reflect present licensee performance. The missing data in the work orders are from 2008 and 2014. The subject work activities have been performed more recently and those records were retained.

Enforcement:

Violation: 10 CFR Part 50, Appendix B, Criterion XVII, " Quality Assurance Records,"

requires, in part, " Sufficient records shall be maintained to furnish evidence of activities affecting quality. The records shall include at least the following: Operating logs and the results of reviews, inspections, tests, audits, monitoring or work performance, and materials analysis. Inspection and test records shall, as a minimum identify the inspector or data recorder, the type of observation, the results, the acceptability, and the action taken in connection with any deficiencies noted. Records shall be identifiable and retrievable.

Contrary to the above, in 2008 and 2014, the licensee did not ensure that sufficient records were maintained to furnish evidence of activities affecting quality. Specifically, standby service water flow balance work orders 51695027 and 51008285 did not contain completed test data.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

On August 3, 2023, the inspectors presented the comprehensive engineering team inspection results to Phil Hansett and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.21M

Calculations

28.212-047-

008D

Seismic Analysis 6" Forged Bolted Bonnet Gate Valve

ASME Class 150-600 lb. Carbon Steel Nuclear Class 1, 2 &

71111.21M

Calculations

28.212-047-

016C

Design Report 6" - 900LB PS Gates Valve

71111.21M

Calculations

28.212-047-

053A

Weak Link Calculation for 6" Class 150 Forged Carbon Steel

Bolted Bonnet Motor Operated Butt Welded End Gate Valve

71111.21M

Calculations

28.212-

047.040C

Weak Link Analysis - Seismic Qual of M.O. Valves

B

71111.21M

Calculations

28.201-007-

001A

Selection Procedures & Switch Setting Charts

300

71111.21M

Calculations

E-176

Standby Load Center, MCC, and 120 Volt Panel Short

Circuit Calculation

71111.21M

Calculations

E-178

Voltage Drop Calculation for Standby 480 & 120/240 Volt

Distribution System

07/27/1987

71111.21M

Calculations

E-192

Standby Diesel Generator Loading Calculation

71111.21M

Calculations

E-200

Overcurrent Device Setpoints

71111.21M

Calculations

E-219

480 VAC Normal & Standby Motor Control Centers, Load

Tabulation

71111.21M

Calculations

E-222

Load Tabulation for 480VAC Normal and Standby Load

Centers

71111.21M

Calculations

E-222-E22-S002

E-222-E22-S002, 480VAC Standby Motor Control Center

Load Tabulation Including Cable Verification

71111.21M

Calculations

G13.18.10.2*025

Temporary Lead Shielding on Line on RHR System

71111.21M

Calculations

G13.18.12.2-022

River Bend Station - Combustible Loading

71111.21M

Calculations

G13.18.13.2*086

Effects of Maximum Safeguards Operation on the Ultimate

Heat Sink (Standby Cooling Tower)

71111.21M

Calculations

G13.18.14.0*042

Standby Service Water Performance With Only One Pump

71111.21M

Calculations

G13.18.14.0*112

Hydraulic Analysis of Flow-Balanced Service Water System

71111.21M

Calculations

G13.18.14.0*116-

Volume of Water in the Service Water System

71111.21M

Calculations

G13.18.14.0-30

Service Water Pump Trip Pressure Transient

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.21M

Calculations

G13.18.2.1*083

Diesel Generator Building Design Basis Calculation -

Summer Condition

71111.21M

Calculations

G13.18.2.1*086

Diesel Generator Building Design Basis Calculation - Winter

Condition

71111.21M

Calculations

G13.18.2.1*089

Determine Air Intake Free Area for Containment Unit

Coolers HVR-UC1A/B/C

71111.21M

Calculations

G13.18.2.1-084

Diesel Generator Building Calculation for Fan Total

Pressure

71111.21M

Calculations

G13.18.2.3*286

GL 89-10 Design Basis Review for SWP-MOV503A/B

71111.21M

Calculations

G13.18.2.3*304

Computer Model Pressures and Flowrates Generated for

the Service Water System in Support of GL 89-10

71111.21M

Calculations

G13.18.2.3*325

River Bend Station NRC Generic Letter 96-05 AC MOV

Actuator Output Capability Calculation

71111.21M

Calculations

G13.18.2.3-198

G.L. 89-10 Design Basis Review for E51-MOVF013

71111.21M

Calculations

G13.18.2.4*047

Standby Service Water Division 1 and 2 Small Bore Cross

Tie Sizing - Flow rate and Orifice Sizing

71111.21M

Calculations

G13.18.3.6*016

Degraded Voltage Calculation for Class IE Buses and 480V

Motor Operated Valves

71111.21M

Calculations

G13.18.4.6-002

Normal Service Water System Heat Loads

71111.21M

Calculations

G13.18.4.6-005

Size New Service Water Pumps

71111.21M

Calculations

PB-268

Maximum Temperature of Containment Outside of the

Drywell During Loss of Offsite Power

0A

71111.21M

Calculations

PM-078

Standby Service Water Pump Capacity Verification

71111.21M

Calculations

Z-78-2011A

Pipe Support

71111.21M

Corrective Action

Documents

Condition Report

(CR-RBS-)

20-02064, 2020-03877, 2020-03649, 2017-05785, 2021-

2445, 2023-03268, 2017-01527, 2022-05725, 2022-03801,

22-03133, 2022-04193, 2023-01877, 2023-05943, 1997-

01784, 2014-00752, 2022-03172, 2023-06037, 2021-02926,

21-01712, 2022-06400, 2019-06442, 2015-03407, 2018-

05468, 2018-05478, 2018-05479, 2021-00626, 2022-01853,

23-03237, 2023-03409, 2022-01845, 2020-05179, 2022-

04193, 2023-02005

71111.21M

Corrective Action

Condition Report

23-05104, 2023-05863, 2023-05868, 2023-05869, 2023-

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Documents

Resulting from

Inspection

(CR-RBS-)

05875, 2323-05902, 2023-05905, 2023-05908, 2023-05909,

23-05911, 2023-05927, 2023-05934, 2023-05936, 2023-

05938, 2023-05943, 2023-05944, 2023-05945, 2023-05946,

23-05948, 2023-05949, 2023-05950, 2023-05973, 2023-

05976, 2023-05979, 2023-05982, 2023-05985, 2023-05986,

23-05991, 2023-05992, 2023-05994, 2023-05997, 2023-

06037, 2023-06059, 2023-06101, 2023-06105, 2023-06172,

23-06196, 2023-06204, 2023-06214, 2023-06231, 2023-

233

71111.21M

Drawings

EE-001A

Main One Line Diagram, Key Drawing, Power Distribution

71111.21M

Drawings

EE-001AB

480V One Line Diagram, Standby Bus, EJS-LDC1B & EJS-

LDC2B

71111.21M

Drawings

EE-001AC

Start Up Electrical Distribution Chart

71111.21M

Drawings

ESK-06HVR09

Elementary Diagram, 480V Switchgear, Containment Unit

Cooler, HVR-UC1A

71111.21M

Drawings

ESK-07HVC25,

Sheet 1

Elementary Diagram, 120VAC Control Circuit, Remote

Shutdown, Transfer Relays

71111.21M

Drawings

ESK-07HVK03,

Sheet 1

Elementary Diagram, 120VAC Control CKT [Circuit],

Remote Shutdown Transfer Relays

71111.21M

Drawings

ESK-07HVR20,

Sheet 1

Elementary Diagram, 120VAC Control Circuit, Remote

Shutdown Transfer Relays

71111.21M

Drawings

PID-09-10A

Engineering P & I Diagram System 118 Service Water -

Normal

71111.21M

Drawings

PID-09-10C

Engineering P & I Diagram System 118 Service Water

Normal

71111.21M

Drawings

PID-09-10D

Engineering P & I Diagram System 118 Service Water -

Normal

71111.21M

Drawings

PID-09-10F

Engineering P & I Diagram System 118 Service Water

Normal

71111.21M

Drawings

PID-09-10G

Engineering P * I Diagram SWP Corrosion Coupon and

Monitoring Rack System118 "C" Tunnel EL. 67'-6"

71111.21M

Drawings

PID-09-10H

Engineering P & I Diagram System 118 Service Water -

Normal

71111.21M

Drawings

PID-22-07A

Engineering P & I Diagram System 405 HVAC - Diesel

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Generators

71111.21M

Drawings

PID-22-14D

Engineering P&I Diagram, System 410, HVAC-Chilled Water

71111.21M

Drawings

PID-27-06A

Engineering P & I Diagram System 209 Reactor Core

Isolation Cooling

71111.21M

Drawings

PID-27-07A

Engineering P & I Diagram System 204 Residual Heat

Removal - LPCI

71111.21M

Engineering

Changes

EC 30846

Prepare Markup of Calculation E-192 and G13.18.3.6*019 to

Generator Frequency Analytical Limits

71111.21M

Engineering

Changes

EC 38515

Diesel Generator Margin Recovery Governor Setpoint

Change

71111.21M

Engineering

Changes

EC 40572

Div 2 Diesel Generator Margin Recovery Governor Setpoint

Change

71111.21M

Engineering

Changes

EC 40578

Diesel Generator Margin Recovery Calculation Updates

71111.21M

Engineering

Changes

EC 40751

Div 1 Diesel Generator Margin Recovery Governor Setpoint

Change

71111.21M

Engineering

Changes

EC 75637

Replace 2 J11 Gould Relays with 3 Allen Bradley 700-

P400A1 W/ 700-PLL11A1 Relays in EJS-SWG2A

000

71111.21M

Engineering

Changes

EC 75802

Replace 5 Obsolete Gould J11 Relays in EJS-SWG1A

000

71111.21M

Engineering

Changes

EC 79763

Update to Hydrogen Igniter Vendor Equivalency Evaluation

000

71111.21M

Engineering

Changes

EC 80652

Permanent Shields AB-07/10-93 & RB-9B

71111.21M

Engineering

Changes

EC 82198

RBS Appendix J Program Scope Reduction EC Evaluation

000

71111.21M

Engineering

Changes

EC 85966

Equivalent Replacement Valve for EGA-V137 Check Valve

for Diesel Generator Air Start System

000

71111.21M

Engineering

Changes

EC 88823

Evaluate Temperature Differ in HPCS Room While HPCS Is

Running and HVR-UC5 Is Running per CR-RBS-2020-

03649 CA 0004

71111.21M

Engineering

Changes

EC 90805

Document Updates for Hydrogen Igniter Replacement

001

71111.21M

Engineering

EC 93439

Evaluation Due to External Flood In-Leakage to Annulus

000

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Changes

Area Under PMF Event

71111.21M

Engineering

Changes

EC 93930

Raise the Level of the Main Turbine Level 8 Trip to Ensure

No Overlap with RPS

000

71111.21M

Engineering

Changes

EC 94412

NI [Nuclear Instrument] Cable Splice Evaluation

000

71111.21M

Engineering

Changes

EC 94678

Level 8 Turbine Trip Setpoint Change

000

71111.21M

Engineering

Changes

EC-84643

Replace SWP-MOV40C With Tricentric Butterfly

71111.21M

Engineering

Changes

EC-89499

E12-MOVF021 Equivalency

71111.21M

Engineering

Changes

EC-93476

RBS Appendix J Program Scope Reduction Evaluation

71111.21M

Engineering

Changes

EC-94914

Gear Ratio Change for G33-MOVF053

71111.21M

Engineering

Evaluations

RBS-CS-15-

00009

RBS Fukushima Flooding Hazard Re-Evaluation - Local

Intense Precipitation

000

71111.21M

Miscellaneous

1.ILEGT.008

Diesel Generator Jacket Circ Pump and Heater

71111.21M

Miscellaneous

200.010

Structural Design Criteria for River Bend Station - Unit 1

71111.21M

Miscellaneous

215.252

Containment Unit Coolers and Auxiliary Building Unit

Coolers With ASME III, Class 3 Coils

71111.21M

Miscellaneous

244.700

Standby Diesel Generator Systems

71111.21M

Miscellaneous

242.526-082

ITE Motor Control Center Instruction Manual

06/26/1985

71111.21M

Miscellaneous

242.533-265-

003

Installation and Operating Instruction Manual, 480V Standby

Load Centers

06/01/1983

71111.21M

Miscellaneous

242.533-265-

003B

Installation and Operating Instruction Manual, 480V Standby

Load Centers

06/01/1983

71111.21M

Miscellaneous

242.562-082-

001A

Instruction Manual, Installation, Operation and Maintenance

of Motor Control Centers

301

71111.21M

Miscellaneous

A160-0159

Heavy Duty Industrial Relays, 700-P-Series, Allen Bradley

000

71111.21M

Miscellaneous

B515-0102

Buffalo Forge Axial Fan Service Manual

71111.21M

Miscellaneous

B515-0121

Buffalo Forge Installation and Operation Instructions for Air

Handling Cabinets

71111.21M

Miscellaneous

B515-0136

Installation and Maintenance of Axial Flow Fans

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.21M

Miscellaneous

EA-RA-92-0001-

M

Conformance of River Bend Station Blackout Rule (10 CFR 50.63) and NUMARC 87-00

71111.21M

Miscellaneous

EDS-ME-017

Lead Shielding

71111.21M

Miscellaneous

EQAR-007

Raychem Heat Shrink & Tubing Kits

71111.21M

Miscellaneous

EQAR-024

Westinghouse Medium Duty Motors

71111.21M

Miscellaneous

EQAR-027

Limitorque Motorized Valve Actuators with Class RH

Insulated AC Motors

71111.21M

Miscellaneous

SDC-203

Safety Related 4.16KV Electrical Distribution System Design

Criteria

71111.21M

Miscellaneous

SDC-209

Reactor Core Isolation Cooling System Design Criteria;

System Number 209

71111.21M

Miscellaneous

SDC-303

Safety Related 480 V Electrical Distribution System Design

Criteria, System Number 303

71111.21M

Miscellaneous

SDC-309

Standby Diesel Generator Division I & II Diesel Generator

Building Ventilation System, System Design Criteria

71111.21M

Miscellaneous

SEP-RBS-IST-1

RBS Inservice Testing Bases Document

71111.21M

Miscellaneous

SWP-MOV503A-

ST-005

MOV TEST REPORT

08/27/2018

71111.21M

Miscellaneous

V085-0138

Velan IOM for Manual Operated Bolted Bonnet Gate, Globe,

Stop Check and Check Valves

71111.21M

Miscellaneous

VTD-C634-0112

Transamerica Delaval Instruction Manual for Model DSR-48

Diesel Engine/Generator

71111.21M

Miscellaneous

VTD-G080-0105

General Electric Instructions Type AKD-6 Low Voltage

Switchgear

71111.21M

Miscellaneous

VTD-S322-0100

Southern Transformer Guide for Installation and

Maintenance of Dry-Type Transformers

71111.21M

Procedures

AOP-0004

Loss of Offsite Power

71111.21M

Procedures

AOP-0013

Primary Containment Control

71111.21M

Procedures

AOP-0050

Station Blackout

71111.21M

Procedures

CMP-EM-000-

1009

Masterpact Circuit Breaker Clean and Inspect

013

71111.21M

Procedures

CMP-EM-000-

1013

480 Volt Switchgear Clean and Inspect

003

71111.21M

Procedures

EN-DC-115-01

Industry Standard Design Process (IP-ENG-001)

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.21M

Procedures

EN-DC-117

Post Modification Testing and Special Instructions

71111.21M

Procedures

EN-DC-198

Emergency Diesel Generator Reliability Program

71111.21M

Procedures

EN-DC-310

Predictive Maintenance Program

71111.21M

Procedures

EN-DC-312

Motor Operated Valve (MOV) Test Data Review

71111.21M

Procedures

EN-LI-100

Process Applicability Determination

71111.21M

Procedures

EN-LI-101

CFR 50.59 Evaluations

71111.21M

Procedures

EN-LI-102

Corrective Action Program

049

71111.21M

Procedures

EOP-0002

Primary Containment Control

71111.21M

Procedures

OSP-0019

Electrical Bus Outages

313

71111.21M

Procedures

OSP-0053

Emergency and Transient Response Support Procedure

71111.21M

Procedures

PEP-0026

Diesel Generator Operating Logs

71111.21M

Procedures

RBNP-001

Development, Control and Maintenance of RBS Procedures

71111.21M

Procedures

SOP-0047

480 VAC System

71111.21M

Procedures

SOP-0053

Standby Diesel Generator and Auxiliaries

347

71111.21M

Procedures

SOP-0059

Containment HVAC System (Sys #403)

71111.21M

Procedures

SOP-0061

Diesel Generator Building Ventilation

016

71111.21M

Procedures

STP 309-601

Div I ECCS Test

71111.21M

Procedures

STP 309-6301

STP 309-6301

71111.21M

Procedures

STP-107-3806

Feedwater Penetration KJB-Z3A Valve Leak Rate Test

71111.21M

Procedures

STP-203-6305

HPCS Quarterly Pump and Valve Operability Test

71111.21M

Procedures

STP-209-6800

RCIC Cold Shutdown Valve Operability Test

304

71111.21M

Procedures

STP-256-3828

Service Water Return Train A Penetration KJB-Z53A Valve

Leak Rate Test

71111.21M

Procedures

STP-256-6301

Div I Standby Service Water Quarterly Valve Operability

Test

71111.21M

Procedures

STP-256-6803

Div I Service Water Cold Shutdown Valve Operability Test

305

71111.21M

Procedures

STP-309-0201

Division I Diesel Generator Operability Test

71111.21M

Procedures

STP-403-0301

Containment Unit Cooler HVR-UC1A Flow Rate Verification

71111.21M

Procedures

STP-501-4202

FWS/Main Turbine Trip System - Reactor Vessel Water

Level - High Level 8, Channel Calibration and LSFT (C33-

N004B, C33-K624B, C33-R606B, C33-K650-3)

71111.21M

Work Orders

Work Order (WO-

)

23000570, 00512093, 52898848, 53023404, 52977233,

2974530, 52921774, 52703603, 00309004, 00391911,

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

2957179, 52920239, 52952387, 53007316, 51023678,

53036390, 52864225, 52907504, 52864224, 53016063,

53023928, 52446190, 52337985, 52580647, 52952270,

2903062, 52690220, 00323927, 00323938, 00512093,

51695027, 52847647, 52857807, 52907862, 52791882,

00593803, 00593992, 52795062, 52717386, 00449735,

2888418, 52684098, 00518175, 52634167, 00449812,

2684215, 52684213, 52684214, 00449786, 00421255,

00449682, 00449729, 00570792, 52684178, 52724430,

2839770, 52618184, 52684178, 52890204, 52980190,

53016051