ML20303A140
| ML20303A140 | |
| Person / Time | |
|---|---|
| Site: | River Bend |
| Issue date: | 10/30/2020 |
| From: | Jason Kozal NRC/RGN-IV/DRP/RPB-C |
| To: | Vercelli S Entergy Operations |
| References | |
| IR 2020003 | |
| Download: ML20303A140 (17) | |
See also: IR 05000458/2020003
Text
October 30, 2020
Mr. Steven Vercelli, Site Vice President
Entergy Operations, Inc.
River Bend Station
5485 U.S. Highway 61N
St. Francisville, LA 70775
SUBJECT:
RIVER BEND STATION - INTEGRATED INSPECTION
REPORT 05000458/2020003
Dear Mr. Vercelli:
On September 30, 2020, the U.S. Nuclear Regulatory Commission (NRC) completed an
inspection at River Bend Station. On October 13, 2020, the NRC inspectors discussed the
results of this inspection with you and other members of your staff. The results of this
inspection are documented in the enclosed report.
No NRC-identified or self-revealing findings were identified during this inspection.
A licensee-identified violation which was determined to be of very low safety significance is
documented in this report. We are treating this violation as a non-cited violation (NCV)
consistent with Section 2.3.2 of the Enforcement Policy.
If you contest the violation or the significance or severity of the violation documented in this
inspection report, you should provide a response within 30 days of the date of this inspection
report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN:
Document Control Desk, Washington, DC 20555-0001; with copies to the Regional
Administrator, Region IV; the Director, Office of Enforcement; and the NRC Resident Inspector
at River Bend Station.
S. Vercelli
2
This letter, its enclosure, and your response (if any) will be made available for public inspection
and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document
Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public
Inspections, Exemptions, Requests for Withholding.
Sincerely,
Jason W. Kozal, Chief
Reactor Projects Branch C
Division of Reactor Projects
Docket No. 05000458
License No. NPF-47
Enclosure:
As stated
cc w/ encl: Distribution via LISTSERV
Jason W.
Kozal
Digitally signed by
Jason W. Kozal
Date: 2020.10.30
08:14:56 -05'00'
SUNSI Review
Non-Sensitive
Sensitive
Publicly Available
Non-Publicly Available
OFFICE
SRI:DRP/C
RI:DRP/C
C:DRS/EB1
C:DRS/EB2
C:DRS/OB
NAME
RKumana rjk
BParks bdp
VGaddy VGG
NTaylor NHT
GWerner / GEW
DATE
10/27/2020
10/26/2020
10/26/2020
10/26/2020
10/26/2020
OFFICE
C:DRS/RCB
TL:DRS/IPAT
C:DNMS/RIB
SPE:DRP/C
BC:DRP/C
NAME
MHaire MSH
AAgrawal ANA
GWarnick GGW
CYoung chy
JKozal JWK
DATE
10/26/2020
10/26/20
10/27/2020
10/26/2020
10/30/2020
Enclosure
U.S. NUCLEAR REGULATORY COMMISSION
Inspection Report
Docket Number:
05000458
License Number:
Report Number:
Enterprise Identifier: I-2020-003-0005
Licensee:
Entergy Operations, Inc.
Facility:
River Bend Station
Location:
St. Francisville, Louisiana
Inspection Dates:
July 1, 2020 to September 30, 2020
Inspectors:
R. Alexander, Senior Emergency Preparedness Inspector
B. Bergeon, Operations Engineer
R. Fanner, Operations Engineer
S. Hedger, Emergency Preparedness Inspector
R. Kumana, Senior Resident Inspector
B. Parks, Resident Inspector
Approved By:
Jason W. Kozal, Chief
Reactor Projects Branch C
Division of Reactor Projects
2
SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees
performance by conducting an integrated inspection at River Bend Station, in accordance with
the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for
overseeing the safe operation of commercial nuclear power reactors. Refer to
https://www.nrc.gov/reactors/operating/oversight.html for more information. A
licensee-identified non-cited violation is documented in report Section 71111.05.
List of Findings and Violations
No findings or violations of more than minor significance were identified.
Additional Tracking Items
None.
3
PLANT STATUS
River Bend Station began the inspection period at rated thermal power. On July 24, 2020, the
station conducted a downpower to approximately 8 percent power to conduct maintenance on
reactor recirculation pump A. The unit was returned to rated thermal power on
August 1, 2020. On August 21, 2020, the station manually inserted a reactor scram in response
to power oscillations associated with a loss of reactor recirculation pump B. The unit was
returned to approximately 95 percent power on August 30, 2020, and remained flow-limited at
that power level due to grid demand considerations that prevented the station from performing a
control rod pattern adjustment. On September 12, 2020, the station conducted a downpower to
approximately 61 percent to perform a control rod pattern adjustment. The unit was returned to
rated thermal power on September 13, 2020. On September 25, 2020, the station conducted a
downpower to approximately 61 percent power to perform a control rod pattern adjustment. The
unit was returned to rated thermal power on September 29, 2020. The unit remained at rated
thermal power for the remainder of the inspection period.
INSPECTION SCOPES
Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in
effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with
their attached revision histories are located on the public website at http://www.nrc.gov/reading-
rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared
complete when the IP requirements most appropriate to the inspection activity were met
consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection
Program - Operations Phase. The inspectors reviewed selected procedures and records,
observed activities, and interviewed personnel to assess licensee performance and compliance
with Commission rules and regulations, license conditions, site procedures, and standards.
Starting on March 20, 2020, in response to the National Emergency declared by the President
of the United States on the public health risks of the coronavirus (COVID-19), resident and
regional inspectors were directed to begin teleworking and to remotely access licensee
information using available technology. During this time the resident inspectors performed
periodic site visits each week, increasing the amount of time on site as local COVID-19
conditions permitted. As part of their onsite activities, resident inspectors conducted plant
status activities as described in IMC 2515, Appendix D; observed risk significant activities; and
completed on site portions of IPs. In addition, resident and regional baseline inspections were
evaluated to determine if all or portion of the objectives and requirements stated in the IP could
be performed remotely. If the inspections could be performed remotely, they were conducted
per the applicable IP. In some cases, portions of an IP were completed remotely and on site.
The inspections documented below met the objectives and requirements for completion of the
IP.
REACTOR SAFETY
71111.01 - Adverse Weather Protection
Seasonal Extreme Weather Sample (IP Section 03.01) (1 Sample)
(1)
The inspectors evaluated summer readiness of offsite and alternate alternating
current (AC) power systems on August 19, 2020.
4
71111.04 - Equipment Alignment
Partial Walkdown Sample (IP Section 03.01) (3 Samples)
The inspectors evaluated system configurations during partial walkdowns of the following
systems/trains:
(1)
Control building heating, ventilation, and air conditioning chilled water system on
July 30, 2020
(2)
Division II emergency diesel generator on August 12, 2020
(3)
Containment unit cooler 1B on September 10, 2020
Complete Walkdown Sample (IP Section 03.02) (1 Sample)
(1)
The inspectors evaluated system configurations during a complete walkdown of the
low pressure core spray system on September 11, 2020.
71111.05 - Fire Protection
Fire Area Walkdown and Inspection Sample (IP Section 03.01) (6 Samples)
The inspectors evaluated the implementation of the fire protection program by conducting a
walkdown and performing a review to verify program compliance, equipment functionality,
material condition, and operational readiness of the following fire areas:
(1)
Low pressure core spray pump room, fire area AB-6/Z-1, on July 20, 2020
(2)
Heating, ventilation, and air conditioning 1B room, fire area C-4, on July 23, 2020
(3)
Diesel generator B room, fire area DG-4/Z-1, on August 12, 2020
(4)
Standby cooling tower pump A transformer room, fire area PH-1/Z-2, on
September 2, 2020
(5)
125 VDC switchgear room, fire area C-24, on September 10, 2020
(6)
Cable chase IV, fire area C-10, on September 11, 2020
Fire Brigade Drill Performance Sample (IP Section 03.02) (1 Sample)
(1)
The inspectors evaluated the onsite fire brigade training and performance during an
unannounced fire drill on September 11, 2020. During this drill, the inspectors
evaluated the capability of the fire brigade members, the leadership ability of the
brigade leader, the brigades use of turnout gear and fire-fighting equipment, and the
effectiveness of the fire brigades team operation. The inspectors also reviewed
whether the licensees fire brigade met NRC requirements for training, dedicated size
and membership, and equipment.
71111.06 - Flood Protection Measures
Inspection Activities - Internal Flooding (IP Section 03.01) (1 Sample)
The inspectors evaluated internal flooding mitigation protections in the:
(1)
Division I and Division II control building chilled water system chiller rooms on
September 29, 2020
5
71111.11A - Licensed Operator Requalification Program and Licensed Operator Performance
Requalification Examination Results (IP Section 03.03) (1 Sample)
(1)
The inspectors reviewed and evaluated the licensed operator examination failure
rates for the requalification annual operating exam administered from
August 10, 2020, through October 2, 2020.
71111.11B - Licensed Operator Requalification Program and Licensed Operator Performance
Licensed Operator Requalification Program (IP Section 03.04) (1 Sample)
(1)
Biennial Requalification Written Examinations
The inspectors evaluated the quality of the licensed operator biennial requalification
written examination administered between August 10, 2020, and October 2, 2020.
Annual Requalification Operating Tests
The inspectors evaluated the adequacy of the facility licensees annual requalification
operating test.
Administration of an Annual Requalification Operating Test
The inspectors evaluated the effectiveness of the facility licensee in administering
requalification operating tests required by 10 CFR 55.59(a)(2) and that the facility
licensee is effectively evaluating their licensed operators for mastery of training
objectives.
Requalification Examination Security
The inspectors evaluated the ability of the facility licensee to safeguard examination
material, such that the examination is not compromised.
Remedial Training and Re-examinations
The inspectors evaluated the effectiveness of remedial training conducted by the
licensee and reviewed the adequacy of re-examinations for licensed operators who
did not pass a required requalification examination.
Operator License Conditions
The inspectors evaluated the licensees program for ensuring that licensed operators
meet the conditions of their licenses.
Control Room Simulator
The inspectors evaluated the adequacy of the facility licensees control room
simulator in modeling the actual plant and for meeting the requirements contained in
6
Problem Identification and Resolution
The inspectors evaluated the licensees ability to identify and resolve problems
associated with licensed operator performance.
71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance
Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01)
(2 Samples)
(1)
The inspectors observed and evaluated licensed operator performance in the Control
Room during power operation limited by 100 percent core flow on July 27, 2020.
(2)
The inspectors observed and evaluated licensed operator performance in the Control
Room during a control rod pattern adjustment on August 28, 2020.
Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)
(1)
The inspectors observed and evaluated licensed operator requalification training on
July 7, 2020.
71111.12 - Maintenance Effectiveness
Maintenance Effectiveness (IP Section 03.01) (1 Sample)
The inspectors evaluated the effectiveness of maintenance to ensure the following
structures, systems, and components remain capable of performing their intended function:
(1)
Functional failure review of Division III diesel generator system on
September 28, 2020
Quality Control (IP Section 03.02) (1 Sample)
The inspectors evaluated the effectiveness of maintenance and quality control activities to
ensure the following structures, systems, and components remains capable of performing its
intended function:
(1)
Review of commercial grade parts installed in reactor core isolation cooling turbine
lube oil pressure relief valve ICS-RV159 on September 18, 2020
71111.13 - Maintenance Risk Assessments and Emergent Work Control
Risk Assessment and Management Sample (IP Section 03.01) (4 Samples)
The inspectors evaluated the accuracy and completeness of risk assessments for the
following planned and emergent work activities to ensure configuration changes and
appropriate work controls were addressed:
(1)
Yellow risk during surveillance testing on Division II emergency diesel generator and
planned maintenance on Division II containment unit cooler on August 18, 2020
(2)
Yellow risk during planned maintenance on reactor core isolation cooling system on
September 1, 2020
7
(3)
Yellow risk during planned maintenance on Division I containment unit cooler on
September 2, 2020
(4)
Yellow risk during emergency core cooling system reactor vessel pressure low safety
relief valve actuation instrumentation channel calibration on September 22, 2020
71111.15 - Operability Determinations and Functionality Assessments
Operability Determination or Functionality Assessment (IP Section 03.01) (3 Samples)
The inspectors evaluated the licensee's justifications and actions associated with the
following operability determinations and functionality assessments:
(1)
Reactor core isolation cooling after discovery that a commercial grade part
designated as non-safety-related was installed in a safety-related application on
September 18, 2020 (CR-RBS-2020-03056)
(2)
Control building air conditioning system after delayed trip of chiller 1D during chiller
shutdown on September 23, 2020 (CR-RBS-2020-03915)
(3)
Standby service water system after inadvertent operation of all three normal service
water pumps on September 28, 2020 (CR-RBS-2020-03942)
71111.18 - Plant Modifications
Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02)
(2 Samples)
The inspectors evaluated the following temporary or permanent modifications:
(1)
Control building chiller A replacement of controls instrumentation, guide vane
actuator, and hot gas bypass actuator permanent modification on July 21, 2020
(2)
Plugging of weep holes in the G tunnel ventilation duct permanent modification on
September 23, 2020
71111.19 - Post-Maintenance Testing
Post-Maintenance Test Sample (IP Section 03.01) (6 Samples)
The inspectors evaluated the following post-maintenance test activities to verify system
operability and functionality:
(1)
Work Order (WO) 00517472 after disassembly of C41-VF033B, standby liquid control
pump B discharge header check valve, on July 31, 2020
(2)
WO 00546349 testing following maintenance on containment unit cooler 1B on
August 3, 2020
(3)
WO 00548350 after replacement of Division III emergency diesel generator speed
sensing circuit power supply on August 5, 2020
(4)
WO 00549582 repair of jacket water inlet piping on Division II emergency diesel
generator on August 25, 2020
(5)
WO 52849959 after replacement of Division I containment unit cooler relays on
September24, 2020
(6)
WO 00550588 testing following replacement of high pressure core spray instrument
power supply on September 29, 2020
8
71111.22 - Surveillance Testing
The inspectors evaluated the following surveillance tests:
Surveillance Tests (other) (IP Section 03.01) (3 Samples)
(1)
STP-309-0201, Division I Diesel Generator Operability Test, Revision 63, on
July 10, 2020
(2)
STP-309-0603, Division III ECCS Test, Revision 48, on August 4, 2020
(3)
STP-204-4503, LPCI Pump A Discharge Flow - Low, Channel Functional Test
(E12-N652A), Revision 302, on September 3, 2020
Inservice Testing (IP Section 03.01) (1 Sample)
(1)
STP-256-6321, Div I Service Water Recirculation Pump and Valve Operability Test,
Revision 27, on September 15, 2020
71114.04 - Emergency Action Level and Emergency Plan Changes
Inspection Review (IP Section 02.01-02.03) (1 Sample)
(1)
The inspectors evaluated the following Emergency Action Level procedure and
Emergency Plan changes, which were submitted to the NRC on June 9, 2020, in
accordance with 10 CFR 50.54(q)(5):
River Bend Emergency Plan, Revisions 46 and 47
EIP-2-001, Classification of Emergencies, Revisions 29 and 30
ElP-2-007, Protective Action Recommendation Guidelines, Revision 28
This evaluation does not constitute NRC approval.
71114.06 - Drill Evaluation
Select Emergency Preparedness Drills and/or Training for Observation (IP Section 03.01)
(1 Sample)
(1)
The inspectors observed simulator-based licensed operator requalification training
that contributed to the Drill and Exercise Performance (DEP) performance indicator
on July 7, 2020.
OTHER ACTIVITIES - BASELINE
71151 - Performance Indicator Verification
The inspectors verified licensee performance indicators submittals listed below:
MS05: Safety System Functional Failures (SSFFs) Sample (IP Section 02.04) (1 Sample)
(1)
July 2019 through June 2020
9
MS09: Residual Heat Removal Systems (IP Section 02.08) (1 Sample)
(1)
July 2019 through June 2020
MS10: Cooling Water Support Systems (IP Section 02.09) (1 Sample)
(1)
July 2019 through June 2020
71152 - Problem Identification and Resolution
Annual Follow-up of Selected Issues (IP Section 02.03) (1 Sample)
The inspectors reviewed the licensees implementation of its corrective action program
related to the following issue:
(1)
Fuel failure under Condition Report CR-RBS-2020-01548 on August 12, 2020
71153 - Follow-up of Events and Notices of Enforcement Discretion
Personnel Performance (IP Section 03.03) (1 Sample)
(1)
The inspectors evaluated personnel performance during an inadvertent high pressure
core spray initiation on September 4, 2020.
INSPECTION RESULTS
Licensee-Identified Non-Cited Violation
This violation of very low safety significance was identified by the licensee and entered in the
licensees corrective action program and is being treated as a non-cited violation, consistent
with Section 3.2 of the Enforcement Policy.
Violation: The River Bend Station, Unit 1, Renewed Facility Operating License, Section C(10)
and Attachment 4, requires that the licensee implement and maintain in effect all provisions of
the approved fire protection program. The licensees fire protection program requires the
licensee to implement fire watches for an inoperable fire rated assembly. Contrary to the
above, from July 15, 2020, to August 7, 2020, the licensee failed to implement required fire
watches as compensatory measures for four inoperable fire rated assemblies. Specifically,
the licensee failed to establish an hourly fire watch for inoperable fire seals in penetrations
1C3W99, 1C3W109, 1N1W35, and 1N1W40.
Significance/Severity: Green. The inspectors assessed the significance of the finding using
Inspection Manual Chapter 0609, Appendix F, Fire Protection Significance Determination
Process. The inspectors determined the finding affected fire confinement and should be
assigned a high degradation rating in accordance with Attachment 2. The inspectors
determined the finding was of very low safety significance (Green) because the degraded fire
confinement element continued to provide adequate fire endurance to prevent fire
propagation through the fire confinement element, given the combustible loading and location
of equipment important to safe shutdown in the fire area of concern.
Corrective Action References: CR-RBS-2020-03309 and CR-RBS-2020-03929
10
EXIT MEETINGS AND DEBRIEFS
The inspectors verified no proprietary information was retained or documented in this report.
On September 2, 2020, the inspectors presented the emergency plan/emergency action
level changes in-office inspection results to Mr. T. Gates, Manager, Emergency
Planning, and other members of the licensee staff.
On September 3, 2020, the inspectors presented the licensed operator requalification
program biennial inspection results to Mr. S. Vercelli, Site Vice President, and other
members of the licensee staff.
On October 2, 2020, the inspectors presented the 2020 licensed operator requalification
inspection results to Mr. M. McCue, Superintendent, Training, and other members of the
licensee staff.
On October 13, 2020, the inspectors presented the integrated inspection results to
Mr. S. Vercelli, Site Vice President, and other members of the licensee staff.
11
DOCUMENTS REVIEWED
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Corrective Action
Documents
CR-RBS-
2020-03301, 2020-03307, 2020-03309
Procedures
CB-116-129
125 VDC Switchgear Room Fire Area C-24
4
ET-067-403
B Tunnel East Fire Area ET-1
3
NS-98
Normal Switchgear Building, Elevation 98'
2
Work Orders
71111.11B Corrective Action
Documents
CR-RBS-2019-
06924
RBS SRC Station Performance Deficiency 19-02
10/29/2019
CR-RBS-2019-
3891
Unplanned SCRAM
05/31/2019
DR 17-0034
Simulator Discrepancy Report, LOR Load, IC 101
06/09/2017
DR 18-0017
Simulator Discrepancy Report, Questions raised during PO-
18-01
01/03/2018
DR 18-0039
Simulator Discrepancy Report, Unexpected results during
Malfunction ED001, Loss of Offsite Power and then removing
Malfunction ED001
06/12/2018
Corrective Action
Documents
Resulting from
Inspection
CR-RBS-2020-
03696
NRC Identified Simulator Transient Test #8 Documentation
09/02/2020
DR 20-0041
Simulator Discrepancy Report, MOV Failed to Work During
LOR Scenario
09/02/2020
Miscellaneous
2020 RO Exam
- 1
RO Biennial Written Requalification Examination
08/17/2020
2020 RO Exam
- 2
RO Biennial Written Requalification Examination
08/24/2020
2020 SRO Exam
- 1
SRO Biennial Written Requalification Examination
08/17/2020
2020 SRO Exam
- 2
SRO Biennial Written Requalification Examination
08/24/2020
PEST-19-01
Post Event Simulator Test 19-03, Scram
05/31/2019
PEST-20-01
Post Event Simulator Test 20-01, CV #3 Testing
06/29/2020
RBS-TT-03
Simultaneous Closure of all Main Steam Isolation Valves
05/08/2019
RBS-TT-04
Simultaneous Trip of All Recirculation Pumps
05/08/2019
12
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
RBS-TT-08
Recirculation Loop Rupture with Loos of Offsite Power and
Div 1 DG Failure
05/08/2019
RJPM-OPS-053-
06
2020 Biennial Job Performance Measure
0
RJPM-OPS-200-
14
2020 Biennial Job Performance Measure
0
RJPM-OPS-203-
10
2020 Biennial Job Performance Measure
0
RJPM-OPS-305-
08
2020 Biennial Job Performance Measure
0
RJPM-OPS-309-
06
2020 Biennial Job Performance Measure
0
RJPM-OPS-403-
02
2020 Biennial Job Performance Measure
0
RJPM-OPS-AR2-
1
2020 Biennial Job Performance Measure
0
RJPM-OPS-AR2-
2
2020 Biennial Job Performance Measure
0
RJPM-OPS-AS2-
1
2020 Biennial Job Performance Measure
0
RJPM-OPS-AS2-
2
2020 Biennial Job Performance Measure
0
RO Exam #1
RO Biennial Written Requalification Exam
08/17/2020
RSES-OPS-814-
07
2020 Biennial Operating Scenario
08/12/2020
RSES-OPS-831-
05
2020 Biennial Operating Scenario
08/12/2020
RSES-OPS-843-
00
2020 Biennial Operating Scenario
08/12/2020
RSES-OPS-845-
00
2020 Biennial Operating Scenario
08/12/2020
Scenario Based
Testing
2020 LOR Scenario RSES-OPS-845-00
05/08/2019
Scenario Based
2019 Initial License Examination Scenario #1
07/09/2019
13
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Testing
Simulator
Operability Test
Simulator Real Time Test
04/17/2017
Simulator
Operability Test
Steady State Test #1 40% Power
03/21/2017
Simulator
Operability Test
Simulator Steady State Test #2 80% Power
03/21/2017
Simulator
Operability Test
Steady State Test #3 100% Power
03/21/2017
Simulator Work
Instruction 1.13
Simulator Core Performance Testing
05/08/2019
TQF-210-DD03-
Grade
LOR Crew Performance Evaluation Grading Criteria
5
TQF-210-DD04-
Grade
RO/SRO Performance Evaluation Grading Criteria
2
TQF-210-DD05-
Grade
STA/SE Performance Evaluation Grading Criteria
2
Procedures
Medical Program
21
Shift Turnover and Relief
2
Time Critical Action/Time Sensitive Action Program Standard
3
Licensed Operator Requalification Training Program
Description
13
Simulator Configuration Control
11
Conduct of Simulator Training
16
Examination Security
10
TQF-114-
AOESIM
Annual Operating Exam Simulator Scenario Set Quality
Checklist
8
Self-Assessments LO-RLO-2017-
00097
2020 Operations Accredited Training Comprehensive Self-
Assessment
07/10/2020
Miscellaneous
50.54(q) Screen for EIP-2-001 Revision 29
04/28/2020
50.54(q) Screen for EIP-2-001 Revision 30
05/01/2020
50.54(q) Evaluation for EIP-2-001 Revision 30
01/20/2020
50.54(q) Screen for EIP-2-007 Revision 28
04/23/2020
EN-LI-100 Review for RBS Emergency Plan Revision 46
04/23/2020
14
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
50.54(q) Screen for RBS Emergency Plan Revision 46
04/23/2020
EN-LI-100 Review for RBS Emergency Plan Revision 47
04/27/2020
50.54(q) Screen for RBS Emergency Plan Revision 47
04/28/2020
Letter from NRC to Entergy/River Bend - RIVER BEND
STATION, UNIT 1 - ISSUANCE OF AMENDMENT TO
REVISE EMERGENCY ACTION LEVELS TO A SCHEME
BASED ON NEI 99-01, REVISION 6, "DEVELOPMENT OF
EMERGENCY ACTION LEVELS FOR NON-PASSIVE
REACTORS" (EPID L-2018-LLA-0130)
05/14/2019
Procedures
Emergency Planning 10CFR50.54(q) Review Program
8
Process Applicability Determination
29