MONTHYEARIR 05000458/20240052024-08-22022 August 2024 Updated Inspection Plan for River Bend Station (Report 05000458/2024005) IR 05000458/20230062024-02-28028 February 2024 Annual Assessment Letter for River Bend Station - Report 05000458/2023006 IR 05000458/20230052023-08-21021 August 2023 Updated Inspection Plan for River Bend Station (Report 05000458/2023005) - Mid Cycle Letter IR 05000458/20220062023-03-0101 March 2023 Annual Assessment Letter for River Bend Station Report 05000458/2022006 ML23059A2332023-03-0101 March 2023 Cyber Security Inspection Request for Information ML22235A1082022-08-19019 August 2022 RBS Emergency Preparedness (EP) Exercise Inspection October 2022 RFI ML22186A0762022-07-0505 July 2022 Information Request, Security IR 2022402 ML22175A0652022-06-30030 June 2022 Notification of Inspection (NRC Inspection Report 05000458/2022004) and Request for Information ML22180A0612022-06-29029 June 2022 Notification of an NRC Fire Protection Baseline Inspection (NRC Inspection Report 05000458/2022010) and Request for Information IR 05000458/20210062022-03-0202 March 2022 Annual Assessment Letter (Report 05000458/2021006) ML21253A2442021-09-13013 September 2021 Notification of NRC Triennial Heat Exchanger/Sink Performance Inspection (5000458/2021004) and Request for Information ML21232A2272021-09-0101 September 2021 RBS Mid-Cycle Inspection Plan Transmittal Letter 2021 ML21099A0312021-03-30030 March 2021 Email 3-30-2021 - Request for Information_ RBS EP Exercise Inspection (Week of 5_10_2021) ML21063A2372021-03-0303 March 2021 RBS 2020 Annual Assessment Letter ML20350B8112020-12-11011 December 2020 2021 RBS PIR Request for Information ML20337A4452020-12-0202 December 2020 Riverbend Station Inservice Inspection Request for Information ML20328A1202020-11-23023 November 2020 Notification of Evaluations of Changes, Tests, and Experiments Inspection (Inspection Report 05000458/2021001) and Request for Information ML20255A1892020-09-0909 September 2020 Email 09Sept2020 - RFI for RBS EP Exercise Inspection IR 05000458/20200052020-09-0101 September 2020 Updated Inspection Plan for River Bend Station (Report 05000458/2020005) ML20162A1122020-06-10010 June 2020 Notification of Inspection (NRC Inspection Report 05000458/2020003) and Request for Information ML20105A3712020-04-14014 April 2020 Notification of NRC Design Bases - Assurance Inspection (Teams) (05000458/2020011) and Initial Request for Information ML20055E1572020-03-0303 March 2020 RBS2019006 Annual Assessment Letter IR 05000458/20190052019-08-30030 August 2019 Updated Inspection Plan for River Bend Station, Report 05000458/2019005 ML19128A1012019-05-0808 May 2019 Notification of NRC Design Bases Assurance Inspection (Programs) (05000458/2019012) and Initial Request for Information IR 05000458/20180062019-03-0404 March 2019 Annual Assessment Letter for River Bend Station (Report 05000458/2018006) IR 05000458/20180052018-08-31031 August 2018 Updated Inspection Plan for River Bend Station (Report 05000458/2018005) ML18166A2362018-06-15015 June 2018 Notification Inspection Report 05000458/2018003, and Request for Information IR 05000458/20170062018-03-0101 March 2018 Annual Assessment Letter for River Bend Station (Report 05000458/2017006) IR 05000458/20170052017-08-28028 August 2017 Updated Inspection Plan for River Bend Station(Report 05000458/2017005) IR 05000458/20160062017-03-0101 March 2017 Annual Assessment Letter for River Bend Station (Report (05000458/2016006) ML17053C0312017-02-22022 February 2017 Notification of NRC Inspection of the Implementation of Mitigation Strategies and Spent Fuel Pool Instrumentation Orders and Emergency Preparedness Communication/Staffing/Multi-Unit Dose Assessment Plans(05000458/2017008) and RFI IR 05000458/20160052016-09-12012 September 2016 Errata for Mid-Cycle Assessment Letter for River Bend Station (Report 05000458/2016005) IR 05000458/20164012016-08-31031 August 2016 Non-Public Security Inspection Plan for River Bend Station (NRC Physical Security Inspection Report Number 05000458/2016401) ML16242A3262016-08-31031 August 2016 Mid-Cycle Assessment Letter for River Bend Station (Report 05000458/2016005) IR 05000458/20150062016-03-0202 March 2016 Annual Assessment Letter for River Bend Station (Report 05000458/2015006) IR 05000458/20154012015-09-0101 September 2015 Non-Public Security Inspection Plan for River Bend Station (NRC Physical Security Inspection Report Number 05000458/2015401) IR 05000458/20150052015-09-0101 September 2015 Mid-Cycle Assessment Letter for River Bend Station (05000458/2015005) ML15170A2332015-06-19019 June 2015 Notification of Evaluations of Changes, Tests, and Experiments, and Permanent Plant Modifications Inspection (05000458/2015007) and Request for Information IR 05000458/20144022014-09-0202 September 2014 Non-Public Security Inspection Plan for River Bend Station (NRC Physical Security Inspection Report Number 05000458/2014402) IR 05000458/20140062014-09-0202 September 2014 Mid-Cycle Assessment Letter for River Bend Station (Report 05000458/2014006) IR 05000416/20130062013-09-0303 September 2013 Mid-Cycle Assessment Letter for Grand Gulf Nuclear Station (Report 05000416/2013006) IR 05000458/20130062013-09-0303 September 2013 Mid-Cycle Assessment Letter for River Bend Station (Report 05000458/2013006) IR 05000458/20128012013-03-0404 March 2013 Annual Assessment Letter for River Bend Station (Report 05000458-12-801) IR 05000458/20120062012-09-0404 September 2012 IR 05000458-12-006, on 08/15/2012, Mid-Cycle Assessment Letter for River Bend Station, Inspection Plan ML12229A5112012-08-16016 August 2012 IR 05000458-12-010, River Bend, Augmented Inspection Team Follow-Up Inspection Planning Letter ML12180A5012012-06-28028 June 2012 IR 05000458-12-004, on 08/06/2012 - 08/10/2012, River Bend Station - Notification of Inspection (NRC Inspection and Request for Information) IR 05000458/20120012012-03-0505 March 2012 Annual Assessment Letter for River Bend Station (Report 05000458/2012001) ML11250A0632011-09-0707 September 2011 IR 05000458-11-005, on 11/14/2011, River Bend Station - Notification of Inspection and Request for Information ML1124305932011-09-0101 September 2011 Mid-Cycle Performance Review and Inspection Plan - River Bend Station IR 05000458/20110012011-03-0404 March 2011 IR 05000458-11-001, 03/01/2011 - 06/30/2012, Annual Assessment Letter for River Bend Station 2024-08-22
[Table view] Category:Letter
MONTHYEARIR 05000458/20213012024-11-14014 November 2024 NRC Initial Operator Licensing Examination Approval 05000458/2021301 ML24289A0312024-11-0808 November 2024 – Issuance of Amendments Related to the Removal of License Condition 2.F as Part of the Consolidated Line-Item Improvement Process (CLIIP) IR 05000458/20240102024-10-31031 October 2024 Design Basis Assurance Inspection (Programs) Inspection Report 05000458/2024010 IR 05000458/20240032024-10-31031 October 2024 Integrated Inspection Report 05000458/2024003 RBG-48315, Reply to a Notice of Violation, NRC Inspection Report 05000458/2023003 Supplement2024-09-24024 September 2024 Reply to a Notice of Violation, NRC Inspection Report 05000458/2023003 Supplement RBG-48306, Report of Changes and Errors to 10CFR50.462024-09-24024 September 2024 Report of Changes and Errors to 10CFR50.46 ML24263A2712024-09-19019 September 2024 Application to Revise Technical Specifications to Adopt TSTF-592, Revise Automatic Depressurization System (ADS) Instrumentation Requirements ML24255A1192024-09-16016 September 2024 Notification of NRC Follow Up Inspection for One Severity Level (SL) III and Two SL IV or Three or More SL IV Violations and Request for Additional Information RBG-48311, Reply to a Notice of Violation, NRC Inspection Report 05000458/20240022024-08-28028 August 2024 Reply to a Notice of Violation, NRC Inspection Report 05000458/2024002 IR 05000458/20240052024-08-22022 August 2024 Updated Inspection Plan for River Bend Station (Report 05000458/2024005) ML24220A2642024-08-20020 August 2024 Entergy Operations, Inc. - Entergy Fleet Project Manager Assignment ML24185A1522024-08-13013 August 2024 Issuance of Amendment Nos. 334, 235, and 215, Respectively, to Revise TSs to Adopt TSTF-205 ML24214A2752024-08-0202 August 2024 Acknowledgement of Readiness for Supplemental Inspection RBG-48308, Notification of Readiness for Supplemental Inspection2024-07-31031 July 2024 Notification of Readiness for Supplemental Inspection IR 05000458/20240022024-07-30030 July 2024 Integrated Inspection Report 05000458/2024002 and Notice of Violation ML24164A0862024-06-12012 June 2024 Notification of Commercial Grade Dedication Inspection (05000458/2024010) and Request for Information 05000458/LER-2023-005-01, Manual Reactor Scram Due to Lowering Feedwater Temperature Following an Automatic Isolation of Feedwater Heater String2024-06-0404 June 2024 Manual Reactor Scram Due to Lowering Feedwater Temperature Following an Automatic Isolation of Feedwater Heater String ML24060A2192024-05-30030 May 2024 Authorization of Alternative to Use EN-RR-01 Concerning Proposed Alternative to Adopt Code Case N-752 ML24093A0892024-05-16016 May 2024 Issuance of Amendment No. 214 Adoption of 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems, and Components for Nuclear Power Reactors ML24081A0072024-05-16016 May 2024 Issuance of Amendment No. 213 Revision to Technical Specifications to Adopt TSTF 505, Revision 2, Provide Risk-Informed Extended Completion Times – RITSTF Initiative 4b IR 05000458/20240012024-05-14014 May 2024 Integrated Inspection Report 05000458/2024001 ML24102A2842024-05-0707 May 2024 Summary of Regulatory Audit in Support of LARs to Revise Technical Specifications to Adopt Risk-Informed Completion Times and Implement the Provisions of 10 CFR 50.69 ML24128A0422024-05-0707 May 2024 License Amendment Request to Remove Obsolete License Conditions RBG-48276, 2023 Annual Radioactive Effluent Release Report2024-04-23023 April 2024 2023 Annual Radioactive Effluent Release Report IR 05000458/20244022024-04-15015 April 2024 Security Baseline Inspection Report 05000458/2024402 (Full Report) RBG-48288, Louisiana Pollutant Discharge Elimination System Permit Renewal2024-04-15015 April 2024 Louisiana Pollutant Discharge Elimination System Permit Renewal ML24106A0432024-04-11011 April 2024 June 2024 Emergency Preparedness Exercise Inspection Request for Information ML24101A3882024-04-10010 April 2024 Response to Request for Confirmation of Information by the Office of Nuclear Reactor Regulation Proposed Alternative Request EN-RR-22-001 Risk-Informed Categorization and Treatment for Repair RBG-48277, 2023 Annual Radiological Environmental Operating Report2024-04-10010 April 2024 2023 Annual Radiological Environmental Operating Report IR 05000458/20243012024-04-0202 April 2024 Notification of NRC Initial Operator Licensing Examination 05000458/2024301 ML24089A2262024-03-29029 March 2024 Entergy Response to Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Exams IR 05000458/20240402024-03-15015 March 2024 – 95001 Supplemental Inspection Report 05000458/2024040 and Follow-Up Assessment ML24075A1712024-03-15015 March 2024 Nuclear Onsite Property Damage Insurance (10 CFR 50.54(w)(3)) ML24074A2892024-03-14014 March 2024 Proof of Financial Protection (10 CFR 140.15) ML24066A1802024-03-0707 March 2024 Notification of NRC Follow-Up Inspection for Any Severity Level I or II Traditional Enforcement Violation IR 05000458/20230062024-02-28028 February 2024 Annual Assessment Letter for River Bend Station - Report 05000458/2023006 RBG-48286, Revision to Owners Activity Report Form (OAR) for Cycle 222024-02-27027 February 2024 Revision to Owners Activity Report Form (OAR) for Cycle 22 RBG-48278, 2023 Spent Fuel Storage Radioactive Effluent Release Report2024-02-27027 February 2024 2023 Spent Fuel Storage Radioactive Effluent Release Report ML24031A0042024-02-21021 February 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0052 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) 05000458/LER-2023-006, Automatic Reactor Scram Due to a Turbine Trip Following a Disconnect Failure at Switchyard2024-02-0808 February 2024 Automatic Reactor Scram Due to a Turbine Trip Following a Disconnect Failure at Switchyard RBG-48274, Notification of Readiness for Supplemental Inspection2024-02-0505 February 2024 Notification of Readiness for Supplemental Inspection IR 05000458/20230042024-01-30030 January 2024 Integrated Inspection Report 05000458/2023004 IR 05000458/20230402024-01-18018 January 2024 – 95001 Supplemental Inspection Supplemental Report 05000458/2023040 and Follow-Up Assessment Letter 05000458/LER-2023-005, Manual Reactor Scram Due to Lowering Feedwater Temperature Following an Automatic Isolation of Feedwater Heater String2024-01-16016 January 2024 Manual Reactor Scram Due to Lowering Feedwater Temperature Following an Automatic Isolation of Feedwater Heater String ML24012A1962024-01-12012 January 2024 Response to 2nd Round Request for Additional Information Concerning Relief Request Number EN-RR-22-001 – Proposed Alternative to Use ASME Code Case N-752, Risk-Informed Categorization and RBG-48271, Supplement to License Amendment Request to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times – RITSTF Initiative 4b and Application to Adopt 10 CFR 50.69, Risk2024-01-12012 January 2024 Supplement to License Amendment Request to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times – RITSTF Initiative 4b and Application to Adopt 10 CFR 50.69, Risk ML24011A1742024-01-11011 January 2024 Security Baseline Inspection Report (Cover Letter) 05000458/LER-2023-004, Drywall Post Accident Radiation Monitor Inoperable Due to Unrecognized Surveillance Failure2023-12-28028 December 2023 Drywall Post Accident Radiation Monitor Inoperable Due to Unrecognized Surveillance Failure ML23349A1672023-12-21021 December 2023 Request for Withholding Information from Public Disclosure ML23348A3572023-12-14014 December 2023 Application to Revise Technical Specifications to Use Online Monitoring Methodology – Slides and Affidavit for Pre-Submittal Meeting 2024-09-24
[Table view] |
Text
March 2, 2022
SUBJECT:
ANNUAL ASSESSMENT LETTER FOR RIVER BEND STATION (REPORT 05000458/2021006)
Dear Mr. Scott:
The U.S. Nuclear Regulatory Commission (NRC) has completed its end-of-cycle performance assessment of River Bend Station, reviewing performance indicators (PIs), inspection results, and enforcement actions from January 1, 2021 through December 31, 2021. This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility. The NRC concluded that overall performance at your facility preserved public health and safety. The baseline inspection program was completed at your facility as defined in Inspection Manual Chapter 2515, Light-Water Reactor Inspection Program
- Operations Phase.
The NRC determined the performance at River Bend Station during the most recent quarter was within the Licensee Response Column, the highest performance category of the NRCs Reactor Oversight Process (ROP) Action Matrix, because all inspection findings had very low safety significance (i.e., Green), and all PIs were within the expected range (i.e., Green). Therefore, the NRC plans to conduct ROP baseline inspections at your facility.
The enclosed inspection plan lists the inspections scheduled through December 31, 2023.
The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last twelve months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes.
In response to the COVID-19 public health emergency (PHE), the NRC adjusted inspection plans and schedules in order to safeguard the health and safety of both NRC and licensee staff while still effectively implementing the ROP. While the PHE continues, overall conditions throughout the country support performance of our inspection and oversight activities to return to normal onsite presence by our resident and region-based inspectors and completion of nominal baseline inspection samples. We continue to monitor site-specific conditions and as discussed in our November 2, 2021 memo, Implementation of Inspection Programs Following Re-Entry from the Public Health Emergency for the Reactor Safety Program (ML21295A302),
it may be necessary to alter how and when we perform our inspection and oversight activities as we balance the importance of protecting the health and safety of our staff with the need to conduct effective oversight that supports the NRCs critical safety mission. For inspections requiring extensive coordination with offsite organizations, such as evaluated emergency preparedness exercises, NRC guidance and frequently asked questions for security and emergency preparedness can be found here: https://www.nrc.gov/about-nrc/covid-19/security-ep/. Similarly, the NRC has developed guidance if force-on-force inspections cannot be completed as scheduled due to an emergency, such as the COVID-19 PHE. These changes help ensure the health and safety of both NRC and licensee staff while maintaining the NRCs important safety and security mission during the COVID-19 PHE. The attached inspection plan is accurate on the date of issuance but remains subject to change based on approval of potential exemption requests or other changes needed due to changing conditions in the COVID-19 PHE. NRC staff will contact your appropriate regulatory affairs staff in order to coordinate inspection planning and scheduling.
On March 12, 2018, the NRC issued a Confirmatory Order (ADAMS Accession No.
ML18072A191) (EA-17-132 and EA-17-153) to the Entergy fleet. On January 14, 2022, the NRC issued Inspection Report 05000416/2021010, which documented the completion of a follow-up inspection of Entergys implementation of actions required by the Confirmatory Order (ML22011A099). The inspection documented in that report represents the final completion of the NRCs planned follow-up inspection activities for the Confirmatory Order, and no additional inspections are included in the enclosed inspection plan.
Between October 1, 2020, and September 30, 2021, the NRC issued three Severity Level III traditional enforcement violations associated with willfulness. The Regional Administrator has previously authorized follow-up inspection to be performed using Inspection Procedure 92722, Follow Up Inspection for Any Severity Level I or II Traditional Enforcement Violation or for Two or More Severity Level III Traditional Enforcement Violations in a 12-Month Period, to follow-up on these violations. This inspection will be scheduled when you notify the NRC of your readiness.
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Please contact me at 817-200-1148 with any questions you have regarding this letter.
Sincerely, Jeffrey E. Josey, Chief Project Branch C Division of Operating Reactor Safety Docket No. 05000458 License No. NPF-47 Enclosure:
Inspection Plan
/RA/
ML22053A348 SUNSI Review ADAMS:
Non-Publicly Available Non-Sensitive Keyword:
By: PJV Yes No Publicly Available Sensitive NRC-002 OFFICE SPE:DORS/C C:DORS/C NAME PVossmar JJosey SIGNATURE
/RA/
/RA/
DATE 2/23/22 02/23/2022
07200049 - River Bend (ISFSI)
01/01/2022 - 12/31/2023 Unit Start End Activity CAC Title Staff Count River Bend ISFSI Triennial Loading Inspection (1 week in July)(Part 72)
1 7/1/2022 7/29/2022 IP 60855 001001 Operation Of An ISFSI Prepared on 2/22/2022 1:44:08 PM 1 of 3 Site Inspection Activity Plan
River Bend 01/01/2022 - 12/31/2023 Unit Start End Activity CAC Title Staff Count FORCE-ON-FORCE PLANNING AND EXERCISE WEEKS - RB
1 2/28/2022 3/4/2022 IP 71130.03 000735 Contingency Response - Force-On-Force Testing
3/21/2022 3/25/2022 IP 71130.03 000735 Contingency Response - Force-On-Force Testing Power-Operated Valves Inspection - 21N - River Bend Station
1 4/4/2022 4/22/2022 IP 71111.21N.02 001645 Design-Basis Capability of Power-Operated Valves Under 10 CFR 50.55a Requirements River Bend Target Set Review
1 4/18/2022 4/29/2022 IP 71130.14 000743 Review of Power Reactor Target Sets Security Access Control.02
1 5/9/2022 5/13/2022 IP 71130.02 000734 Access Control
5/9/2022 5/13/2022 IP 71130.09 001656 Security Plan Changes
5/9/2022 5/13/2022 IP 71151 001338 Performance Indicator Verification River Bend ISFSI Triennial Loading Inspection (Part 50) Feeder for Residents
1 7/1/2022 7/2/2022 IP 60855 001001 Operation Of An ISFSI RBS 2022 BRQ
1 8/28/2022 9/3/2022 IP 71111.11B 000704 Licensed Operator Requalification Program and Licensed Operator Performance Security Training/Equip Maint.07 and.04
1 8/29/2022 9/2/2022 IP 71130.04 000736 Equipment Performance, Testing, and Maintenance
8/29/2022 9/2/2022 IP 71130.07 000739 Security Training Fire Protection Inspection - RBS
1 10/17/2022 10/21/2022 IP 71111.21N.05 001646 Fire Protection Team Inspection (FPTI)
10/31/2022 11/4/2022 IP 71111.21N.05 001646 Fire Protection Team Inspection (FPTI)
EP 2022 Biennial Exercise & PI Inspection - RBS
1 10/17/2022 10/21/2022 IP 71114.01 000716 Exercise Evaluation
10/17/2022 10/21/2022 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes
10/17/2022 10/21/2022 IP 71151 001397 Performance Indicator Verification RP 1,4,PI - RBS
1 11/14/2022 11/18/2022 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls
11/14/2022 11/18/2022 IP 71124.04 000728 Occupational Dose Assessment RBS 2022 INITIAL EXAM
1 10/30/2022 11/5/2022 OV 000956 FB-OR-ONSITE VALIDATION OF INITIAL LICENSE EXAMINATION (OV)
12/4/2022 12/10/2022 EXAD 000500 FB-OR-INITIAL LICENSE EXAM ADMINISTRATION (EXAD)
Design Bases Assurance Inspection (Team) - 21M - River Bend Station
Prepared on 2/22/2022 1:44:08 PM 2 of 3 Site Inspection Activity Plan
1/1/2023 6/30/2023 IP 71111.21M 000713 Design Bases Assurance Inspection (Teams)
Inservice Inspection RFO 22 - RBS
1 2/20/2023 3/3/2023 IP 71111.08G 000701 Inservice Inspection Activities (BWR)
RP 1,3,PI -
1 2/27/2023 3/3/2023 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls
2/27/2023 3/3/2023 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation Security Protective Strategy.05 (Place Holder)
1 5/8/2023 5/12/2023 IP 71130.05 000737 Protective Strategy Evaluation Security Access Authorization.01 and Access Control.02 + PIV + Plan Change.09
1 6/19/2023 6/23/2023 IP 71130.01 000733 Access Authorization
6/19/2023 6/23/2023 IP 71130.02 000734 Access Control
6/19/2023 6/23/2023 IP 71130.09 001656 Security Plan Changes
6/19/2023 6/23/2023 IP 71151 001338 Performance Indicator Verification RP 5,8 -
1 7/24/2023 7/28/2023 IP 71124.05 000729 Radiation Monitoring Instrumentation
7/24/2023 7/28/2023 IP 71124.08 000732 Radioactive Solid Waste Processing & Radioactive Material Handling, Storage, & Transportation Security FFD.08
1 8/7/2023 8/11/2023 IP 71130.08 000740 Fitness For Duty Program EP 2023 Program & PI Inspection - RBS
1 8/14/2023 8/18/2023 IP 71114.02 000717 Alert and Notification System Testing
8/14/2023 8/18/2023 IP 71114.03 000718 Emergency Response Organization Staffing and Augmentation System
8/14/2023 8/18/2023 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes
8/14/2023 8/18/2023 IP 71114.05 000720 Maintenance of Emergency Preparedness
8/14/2023 8/18/2023 IP 71151 001397 Performance Indicator Verification River Bend Station Biennial PI&R
1 10/16/2023 10/20/2023 IP 71152B 000747 Problem Identification and Resolution
10/30/2023 11/3/2023 IP 71152B 000747 Problem Identification and Resolution Prepared on 2/22/2022 1:44:08 PM 3 of 3 Site Inspection Activity Plan