ML101180295

From kanterella
Jump to navigation Jump to search
IR 05000341-10-006; on 01/25 - 04/05/2010; Fermi Power Plant, Unit 2; Component Design Bases Inspection (CDBI)
ML101180295
Person / Time
Site: Fermi DTE Energy icon.png
Issue date: 04/27/2010
From: Lougheed V
NRC/RGN-III/DRS/EB2
To: Jennifer Davis
Detroit Edison
References
IR-10-006
Download: ML101180295 (46)


See also: IR 05000341/2010006

Text

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION III

2443 WARRENVILLE ROAD, SUITE 210

LISLE, IL 60532-4352

April 27, 2010

Mr. Jack M. Davis

Senior Vice President and

Chief Nuclear Officer

Detroit Edison Company

Fermi 2 - 210 NOC

6400 North Dixie Highway

Newport, MI 48166

SUBJECT: FERMI POWER PLANT, UNIT 2 NRC COMPONENT DESIGN BASES

INSPECTION (CDBI) INSPECTION REPORT 05000341/2010-006(DRS)

Dear Mr. Davis:

On April 5, 2010, the U.S. Nuclear Regulatory Commission (NRC) completed a component

design bases inspection at your Fermi Power Plant, Unit 2. The enclosed report documents the

inspection findings, which were discussed on February 26, 2010, with Mr. J. Plona and other

members of your staff, and on April 26, 2010 with Mr. J. Plona, Mr. M. Caragher, and other

members of your staff.

The inspection examined activities conducted under your license as they relate to safety and to

compliance with the Commissions rules and regulations and with the conditions of your license.

The inspectors reviewed selected procedures and records, observed activities, and interviewed

personnel.

Based on the results of this inspection, six NRC-identified findings of very low safety

significance were identified, six of which involved violations of NRC requirements. However,

because of their very low safety significance, and because the issues were entered into your

corrective action program, the NRC is treating the issues as Non-Cited Violations in accordance

with Section VI.A.1 of the NRC Enforcement Policy.

If you contest the subject or severity of any NCV, you should provide a response within

30 days of the date of this inspection report, with the basis for your denial, to the U.S.

Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-

0001, with a copy to the Regional Administrator, U.S. Nuclear Regulatory Commission -

Region III, 2443 Warrenville Road, Suite 210, Lisle, IL 60532-4352; the Director, Office of

Enforcement, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001; and the

Resident Inspector Office at the Fermi Power Plant. In addition, if you disagree with the

characterization of any finding in this report, you should provide a response within 30 days of

the date of this inspection report, with the basis for your disagreement, to the Regional

Administrator, Region III, and the NRC Resident Inspector at the Fermi Power Plant. The

information that you provide will be considered in accordance with Inspection Manual

Chapter 0305.

J. Davis -2-

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter,

its enclosure, and your response (if any), will be available electronically for public inspection in

the NRC Public Document Room or from the Publicly Available Records System (PARS)

component of NRC's Agencywide Documents Access and Management System (ADAMS),

accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public

Electronic Reading Room).

Sincerely,

/RA/

V. Patricia Lougheed, Acting Chief

Engineering Branch 2

Division of Reactor Safety

Docket No. 50-341

License No. NPF-43

Enclosure: Inspection Report 05000341/2010-006

w/Attachment: Supplemental Information

cc w/encl: Distribution via ListServ

U. S. NUCLEAR REGULATORY COMMISSION

REGION III

Docket No: 50-341

License No: NPF-43

Report No: 05000341/2010-006(DRS)

Licensee: Detroit Edison Company

Facility: Fermi Power Plant, Unit 2

Location: Newport, MI

Dates: January 25 through April 5, 2010

Inspectors: Z. Falevits, Senior Reactor Inspector, Lead

C. Brown, Reactor Inspector, Electrical

B. Jose, Senior Reactor Inspector, Electrical

M. Jones, Reactor Inspector, Mechanical

C. Moore, Reactor Inspector, Operations

G. Skinner, Electrical Contractor

C. Baron, Mechanical Contractor

L. Kozak, Senior Reactor Analyst

Approved by: V. Patricia Lougheed, Acting Chief

Engineering Branch 2

Division of Reactor Safety

Enclosure

SUMMARY OF FINDINGS

IR 05000341/2010-006; 01/25/2010 - 04/05/2010; Fermi Power Plant, Unit 2; Component

Design Bases Inspection (CDBI).

The inspection was a 3-week onsite baseline inspection that focused on the design of

components that are risk-significant and have low design margin. The inspection was

conducted by regional engineering inspectors and two consultants. Six findings of very low

safety significance were identified with six associated Non-Cited Violations (NCVs) of NRC

regulations. The significance of most findings is indicated by their color (Green, White, Yellow,

Red) using Inspection Manual Chapter (IMC) 0609, Significance Determination Process

(SDP). Findings for which the SDP does not apply may be Green or be assigned a severity

level after NRC management review. The NRCs program for overseeing the safe operation of

commercial nuclear power reactors is described in NUREG-1649, Reactor Oversight Process,

Revision 4, dated December 2006.

A. NRC-Identified and Self-Revealed Findings

Cornerstone: Initiating Events

  • Green. The inspectors identified a finding having very low safety significance with an

Non-Cited Violation (NCV) of 10 CFR 50.65(b)(2)(iii), for the licensees failure to include

turbine building heating ventilation and air conditioning (TBHVAC) fans in the scope of

their maintenance rule program. Specifically, the licensee failed to effectively control

TBHVAC system components condition through the implementation of appropriate

preventive maintenance as directed by the requirements of the maintenance rule. The

TBHVAC system is used to maintain the turbine building at a negative pressure for

radiological considerations and room and area temperature below design limits to

prevent a Group 1 Isolation resulting in main steam isolation valves (MSIV) closure and

a reactor trip. The licensee entered the issue into their corrective action program for

further evaluation.

This finding was more than minor because it was associated with the Initiating Events

cornerstone attribute of equipment performance, and affected the cornerstone objective

to limit the likelihood of those event that upset plant stability and challenge critical

safety functions during shutdown, as well as power operations. This finding is of very

low safety significance (Green), because it does not contribute to the likelihood that

mitigation equipment or functions will not be available. The inspectors determined there

was no cross-cutting aspect associated with this finding because the system was initially

scoped out during the initial baseline evaluation for maintenance rule in June 1995 and

was not reflective of current performance. (Section 1R21.3.b.(4))

Cornerstone: Mitigating Systems

  • Green. The inspectors identified a finding having very low safety significance with an

associated NCV of 10 CFR Part 50, Appendix B, Criterion III, Design Control, for the

licensees failure to perform adequate calculations to ensure the availability of offsite

power. Specifically, on two occasions the licensee failed to perform adequate

calculations to demonstrate the availability of 120kV system offsite power. The first

occasion was related to the analysis in calculation DC-0919 for conditions when the

System Service (SS) Transformer No. 64 load tap changer (LTC) was in service. The

1 Enclosure

second occasion was related to TSR-35286, which analyzed conditions for placing the

SS Transformer No. 64 LTC in manual. This finding was entered into the licensees

corrective action program to revise the calculations and perform an Engineering

Functional Analysis (EFA) to demonstrate operability.

The finding was more than minor because it was associated with the Mitigating Systems

cornerstone attribute of design control and affected the cornerstone objective of ensuring

the availability, reliability, and capability of safety-related equipment to respond to

initiating events to prevent undesirable consequences. Specifically, there was

reasonable doubt as to whether the offsite power supply would remain operable during a

design basis event pending re-analysis. This finding is of very low safety significance

(Green) because the design deficiency was confirmed not to result in loss of operability

or functionality. This finding has a cross-cutting aspect in the area of Human

Performance, Resources, because the licensee did not provide a complete, accurate,

and up-to-date design documentation, to assure nuclear safety. (IMC 0310, Section

06.01.b.(3) H.2(c)) (Section 1R21.3.b.(1))

  • Green. The inspectors identified a finding having very low safety significance (Green)

with an associated NCV of Technical Specifications 5.4.1.a, Procedures for the

licensees failure to translate the design requirements for the availability of the 120kV

offsite power into station operating procedures, which are used to control voltages on the

offsite power system within acceptable ranges. Specifically, the licensee failed to

translate the 2.1 percent switchyard voltage drop criteria assumed in calculation DC-

0919 into station operating procedures. This finding was entered into the licensees

corrective action program to revise the calculations and perform an EFA to demonstrate

operability.

The finding was more than minor because it was associated with the Mitigating Systems

cornerstone attribute of design control and affected the cornerstone objective of ensuring

the availability, reliability, and capability of safety-related equipment to respond to

initiating events to prevent undesirable consequences. Specifically, the licensee did not

ensure the availability of the 120kV power source to 4160V safety buses by

implementing procedural controls to ensure that the step voltage decrease on the trip on

the Fermi generating unit did not exceed the 2.1 percent value analyzed in calculation

DC-0919. This finding is of very low safety significance (Green), because the design

deficiency was confirmed not to result in loss of operability or functionality. The

inspectors concluded that the cause of the finding was related to the cross-cutting

aspect of Human Performance, Resources, because the licensee did not provide

complete, accurate, and up-to-date design documentation to assure nuclear safety.

(IMC 0310, Section 06.01.b.(3) H.2(c)) (Section 1R21.3.b.(3))

  • Green. The inspectors identified a finding having very low safety significance with an

associated NCV of 10 CFR Part 50, Appendix B, Criterion III, Design Control, for the

licensees failure to accurately account for the cable resistance for the reactor core

isolation cooling (RCIC) and high pressure core injection (HPCI) dc Motor Operated

Valves (MOVs) in the DC short circuit calculation. The issue, along with other related

electrical calculational errors, was entered into the licensees corrective action program.

2 Enclosure

The finding was more than minor because it was associated with the Mitigating Systems

cornerstone attribute of design control and affected the cornerstone objective of ensuring

the availability, reliability, and capability of safety-related equipment to respond to

initiating events to prevent undesirable consequences. This finding is of very low safety

significance (Green) because the design deficiency was confirmed not to result in loss of

operability or functionality. The inspectors concluded that the cause of the finding was

related to the cross-cutting aspect of Human Performance, Resources, because the

licensee did not provide complete, accurate, and up-to-date design documentation to

assure nuclear safety. (IMC 0310, Section 06.01.b.(3) H.2(c)) (Section 1R21.3.b.(6))

  • Green. The inspectors identified a finding of very low safety significance (Green) for the

licensees failure to adhere to operating experience program procedural requirements.

Specifically, the inspectors identified three instances where the licensee failed to

adequately evaluate and take appropriate corrective actions on industry operating

experience contrary to the requirements in licensees operating experience Procedure

MLS04, Revision 22. Also, based on the inspectors finding, the licensee performed an

extent of condition and identified approximately 30 more operating experience reviews

performed within the last two years as less than adequate. No violation of NRC

requirements occurred.

The finding was more than minor because it was associated with the Mitigating Systems

cornerstone attribute of equipment performance and affected the cornerstone objective

of ensuring equipment availability and reliability. Specifically, multiple examples were

identified where the licensee failed to ensure that problems identified in industry

operating experience were evaluated for applicability to Fermi and corrective actions

implemented. This finding is of very low safety significance (Green) because the design

deficiency was confirmed not to result in loss of operability or functionality. The

inspectors concluded that the cause of the finding was related to the cross-cutting

element of Problem Identification and Resolution, Operating Experience, because the

licensee failed to systematically collect, evaluate, and communicate to affected internal

stakeholders in a timely manner relevant internal and external operating experience to

support plat safety. (IMC 0310, Section 06.02.b.(1) P.2(a)) (Section 1R21.4.b)

  • Green. The inspectors identified a finding of very low safety significance (Green) with an

associated NCV of 10 CFR Part 50, Appendix B, Criterion III, Design Control, having

very low safety significance with two examples, for failing to perform adequate electrical

design calculations to support modifications to the degraded voltage protection scheme.

The first example involved the failure to analyze motor starting capability based on

voltages afforded by the degraded voltage relay scheme. The second example involved

the failure to perform conservative calculations to show that spurious grid separation

would not occur during accidents due to action of the degraded voltage relays. This

finding was entered into the licensees corrective action program to revise the

calculations and perform an EFA to demonstrate operability.

The finding was more than minor because it was associated with the Mitigating Systems

cornerstone attribute of design control and affected the cornerstone objective of ensuring

the availability, reliability, and capability of safety-related equipment to respond to

initiating events to prevent undesirable consequences. Specifically, the licensee failed

to confirm the adequacy of new degraded voltage relay set-points by ensuring motors

had adequate voltage to start if safety buses remained connected to offsite power during

a LOCA with degraded voltage. In addition, the licensee failed to ensure that spurious

3 Enclosure

grid separation would not occur during accidents due to action of the degraded voltage

relays. This finding is of very low safety significance (Green) because the design

deficiency was confirmed not to result in loss of operability or functionality. The

inspectors concluded that the cause of the finding was related to the cross-cutting

aspect of Human Performance, Resources, because the licensee did not provide

complete, accurate, and up-to-date design documentation to assure nuclear safety.

(IMC 0310, Section 06.01.b.(3) H.2(c)) (Section 1R21.5.b)

Cornerstone: Barrier Integrity

  • Green. The inspectors identified a finding of very low safety significance (Green) with an

associated NCV of 10 CFR Part 50, Appendix B, Criterion III, Design Control, for failing

to perform proper motor starting studies to demonstrate that motors would successfully

start when connected to the offsite power supply. This finding was entered into the

licensees corrective action program to revise the calculations and perform an EFA to

demonstrate operability.

The finding was more than minor because it was associated with the Barrier Integrity

cornerstone attribute of design control and affected the cornerstone objective to provide

reasonable assurance that physical design barriers protect the public from radionuclide

releases caused by accidents or events. Specifically, failing to demonstrate that the

approved design was adequate to ensure safety-related motors have sufficient voltage

to start created a reasonable doubt as to the operability of the control complex hearing

ventilation and air-conditioning system needed to provide a radiological barrier for

control room personnel during an accident. The inspectors determined that this finding

is of very low safety significance (Green) because the radiological function of the control

complex was not affected. The inspectors concluded that the cause of the finding was

related to the cross-cutting aspect of Human Performance, Resources, because the

licensee did not provide complete, accurate, and up-to-date design documentation to

assure nuclear safety. (IMC 0310, Section 06.01.b.(3) H.2(c)) (Section 1R21.3.b.(2))

B. Licensee-Identified Violations

No violations of significance were identified.

4 Enclosure

REPORT DETAILS

1. REACTOR SAFETY

Cornerstone: Initiating Events, Mitigating Systems, and Barrier Integrity

1R21 Component Design Bases Inspection (71111.21)

.1 Introduction

The objective of the component design bases inspection is to verify that design bases

have been correctly implemented for the selected risk-significant components and

that operating procedures and operator actions are consistent with design and

licensing bases. As plants age, their design bases may be difficult to determine and an

important design feature may be altered or disabled during a modification. The

probabilistic risk-assessment (PRA) model assumes the capability of safety systems and

components to perform their intended safety function successfully. This inspectable

area verifies aspects of the Initiating Events, Mitigating Systems, and Barrier Integrity

cornerstones for which there are no indicators to measure performance.

Specific documents reviewed during the inspection are listed in the Attachment to this

report.

.2 Inspection Sample Selection Process

The inspectors selected risk-significant components and operator actions for review

using information contained in the licensees PRA and the Fermi Standardized Plant

Analysis Risk (SPAR) Model, Revision 3.5. In general, the selection was based upon

the components and operator actions having a risk achievement worth of greater than

1.3 and/or a risk-reduction worth greater than 1.005. The operator actions selected for

review included actions taken by operators both inside and outside of the control room

during postulated accident scenarios. In addition, the inspectors selected operating

experience issues associated with the selected components.

The inspectors performed a margin assessment and detailed review of the selected risk-

significant components to verify that the design bases have been correctly implemented

and maintained. This design margin assessment considered original design reductions

caused by design modification, power uprates, or reductions due to degraded material

condition. Equipment reliability issues were also considered in the selection of

components for detailed review. These included items such as performance test results,

significant corrective action, repeated maintenance activities, Maintenance Rule (a)(1)

status, components requiring an operability evaluation, NRC resident inspector input of

problem areas/equipment, and system health reports. Consideration was also given to

the uniqueness and complexity of the design, operating experience, and the available

defense in depth margins. A summary of the reviews performed and the specific

inspection findings identified are included in the following sections of this report.

This inspection constituted 26 samples as defined in Inspection Procedure 71111.21-05.

5 Enclosure

.3 Component Design

a. Inspection Scope

The inspectors reviewed the updated final safety analysis report (UFSAR), Technical

Specifications (TS), design basis documents, drawings, calculations and other available

design basis information, to determine the performance requirements of the selected

components. The inspectors used applicable industry standards, such as the American

Society of Mechanical Engineers (ASME) Code, Institute of Electrical and Electronics

Engineers (IEEE) Standards and the National Electric Code, to evaluate acceptability of

the systems design. The NRC also evaluated licensee actions, if any, taken in

response to NRC issued operating experience, such as Bulletins, Generic Letters (GLs),

Regulatory Issue Summaries (RISs), and Information Notices (INs). The review was to

verify that the selected components would function as designed when required and

support proper operation of the associated systems. The attributes that were needed for

a component to perform its required function included process medium, energy sources,

control systems, operator actions, and heat removal. The attributes to verify that the

component condition and tested capability was consistent with the design bases and

was appropriate may include installed configuration, system operation, detailed design,

system testing, equipment and environmental qualification, equipment protection,

component inputs and outputs, operating experience, and component degradation.

For each of the components selected, the inspectors reviewed the maintenance history,

system health reports, operating experience-related information and licensee corrective

action program documents. Field walkdowns were conducted for all accessible

components to assess material condition and to verify that the as-built condition was

consistent with the design. Other attributes reviewed are included as part of the scope

for each individual component.

The following 15 components were reviewed:

reviewed RCIC pump and turbine data to ensure compatibility so that the

intended safety function of the system can be met. Hydraulic calculations were

reviewed to assure that the flow requirements were met and that sufficient net

positive suction head (NPSH) was available from both the RCIC tank and the

suppression pool. The water supply was further examined to assure that a

reliable water supply was available and that transfer from the RCIC tank to the

suppression pool could be accomplished without pump damage and within

acceptable transfer times. An interview was conducted with systems engineers

to discuss testing, reservoir capacity and maintenance history. The requirements

from both the UFSAR and TS were reviewed to assure that the design

conformed to the licensing commitments.

  • Core Spray (CS) Pump (E2101C001C): The inspectors reviewed the system

hydraulic calculations including NPSH, system flow, and potential vortexing to

ensure the pump was capable of providing sufficient flow under accident

conditions. The inspectors reviewed surveillance test procedures and the bases

for the acceptance criteria to verify that the tests would ensure the pumps were

capable of their required performance. The inspectors also reviewed aligning the

pump to an alternate water source and the minimum flow protection for the pump

6 Enclosure

to verify performance under all conditions. The inspectors performed a

walkdown of the pump and associated equipment to verify the material condition

and verify that no hazards existed in the area. The inspectors reviewed a sample

of past corrective action documents, the system health report, training

documents, the TS, and the design basis document. In addition, the inspectors

reviewed electrical load flow and voltage drop calculations to determine whether

the CS Pump 1C motor would have adequate voltage to start and run during

design basis accident conditions. In addition, the inspectors reviewed electrical

schematic and logic diagrams to determine whether automatic and manual

control functions for the motors were as described in the design bases. The

inspectors also reviewed the 130Vdc control voltage drop calculation and verified

that the pump breaker control components would have sufficient voltage to close

the breaker when the source (associated 130Vdc battery) was at its minimum

voltage.

  • Core Spray Division 1 Outboard Isolation Motor Operated Valve (MOV)

(E2150F004A): The inspectors reviewed the calculations including required

thrust, structural weak link analysis, and maximum differential pressure, to

ensure the valve was capable of functioning under design conditions. The

system engineer was interviewed, primarily to discuss overall health and issues

associated with the identified voiding and potential binding concerns. Periodic

verification diagnostic and in-service testing (IST) results were reviewed to verify

acceptance criteria were met and performance degradation would be identified.

the mechanical aspects of the EDG, including the fuel system, the cooling

system, and the building ventilation system. The inspectors reviewed the

capacity of the fuel-oil storage system and the design of the fuel-oil transfer

system to verify that they meet their design basis requirements. This review

included the fuel consumption rate of the EDG and the minimum allowable tank

levels to preclude vortexing. The inspectors reviewed the design of the EDG

cooling system to verify that adequate cooling water would be provided. The

inspectors reviewed the design of the EDG area ventilation system to verify that

the system was capable of maintaining an acceptable environment for the

operating equipment. In addition, the inspectors reviewed the capability of the

EDG to perform its design function in the event of a postulated tornado event.

This review included the capability of interior building walls to withstand pressure

differentials and the required response of the operators to damaged ventilation

equipment. The inspectors also performed a walkdown of the EDG and

associated equipment to verify the material condition and to verify that no

hazards existed in the area. The inspectors reviewed a sample of past corrective

action documents, to determine whether there had been any adverse operating

trends; the system health report; training documents; the TS, and the design

basis documents. In addition, the inspectors reviewed the EDG output breaker

control logic; verified the minimum voltage requirements of the control

components and compared the minimum voltage requirement to the minimum

available voltage when the associated 130Vdc battery was at its lowest voltage

to ensure that the EDG output breaker will close when required.

7 Enclosure

  • Fire Protection Diesel Fire Pump, (P8000C001): The inspectors reviewed the

pump start schematic diagrams, the 48Vdc start up battery requirements, and the

battery condition and verified that sufficient power and control source was available

to start the pump and maintain the engine auxiliary components that require dc

control power. In addition, the inspectors reviewed the motor nameplate data to

determine compatibility with the pump and power supply requirements. The

schematic diagram was reviewed to verify manual and automatic operation of the

pump. The inspectors reviewed the vendor manual and the pump curve to verify

pumping capability. The interaction between the fuel-oil day tank level indicator

and the fuel oil transfer pump was reviewed to verify continual compliance with the

system design requirements. Fuel-oil storage tank design was reviewed to ensure

usable volume was consistent with design calculations and surveillance results.

The inspectors reviewed the maintenance rule scoping documents used for re-

classifying the system to (a)(1) status and the associated corrective actions and

pending revisions to the Get Well Plan. Due to pending actions associated with

the maintenance rule status change, only a limited review of the licensees most

recent root cause report could be performed. A walkdown was conducted with the

systems engineer to assess the material condition of the pump and diesel.

  • System Service (SS) Transformer No. 64 (R1200S002): The inspectors reviewed

the calculations and operating procedures to determine whether bus voltages

maintained by the automatic load-tap changer were adequate to assure the

availability of offsite power during low voltage conditions. The inspectors reviewed

sources of power for automatic control equipment to determine whether the

transformer would operate properly during low voltage conditions. The inspectors

reviewed maintenance schedules, procedures, vendor manuals, and completed

work records to determine whether the transformer was being properly maintained.

The inspectors reviewed corrective action histories to determine whether there had

been any adverse operating trends. In addition, the inspectors performed a visual

inspection of SS Transformer No. 64 to assess material condition and the presence

of hazards.

  • Division 1 Essential Safety Feature (ESF) Bus 64C 4.16 kV (R1400S001C): The

inspectors reviewed bus loading calculations to determine whether the 4160Vac

system had sufficient capacity to support its required loads under worst case

accident loading and grid voltage conditions. The inspectors reviewed the design

of the 4160Vac bus degraded voltage protection scheme to determine whether it

afforded adequate voltage to safety-related devices at all voltage distribution

levels. This included review of degraded voltage relay setpoint calculations, motor

starting and running voltage calculations, and motor control center (MCC) control-

circuit voltage drop calculations. The inspectors reviewed procedures and

completed surveillances for calibration of the degraded voltage relays to determine

whether acceptance criteria was consistent with design calculations, and to

determine whether relays were performing satisfactorily. The inspectors reviewed

operating procedures to determine whether the limits and protocols for maintaining

offsite voltage were consistent with design calculations. The inspectors reviewed

the Fermi response to NRC Generic Letter 2006-02 to determine whether current

procedures for maintaining the availability of offsite power were consistent with

licensee responses. The inspectors reviewed protective relaying schemes and

calculations to determine whether equipment such as motors and cables were

adequately protected, and to determine whether protective devices featured proper

8 Enclosure

selective tripping coordination. The inspectors reviewed system health reports,

corrective action documents and maintenance records to determine whether there

were any adverse operating trends. The inspectors reviewed approved

modification packages to address deficiencies in the degraded voltage protection

scheme subject to NRC backfit requirements issued in June 2008. In addition, the

inspectors performed a visual inspection of the 4160Vac safety buses to assess

material condition and the presence of hazards. In addition, the inspectors

reviewed the 130Vdc control voltage drop calculation and verified that sufficient

control voltage would be available for the breaker trip and close components for

both the incoming lines and the associated EDG breaker.

  • ESF Bus 72C 480Vac Switchgear and 72C-2A MCC: The inspectors reviewed the

degraded voltage protection scheme to determine whether the voltage setpoints

were selected based on the voltage requirements for safety-related loads at the

480Vac level. The inspectors reviewed 480Vac short circuit calculations to

determine whether protective devices were applied within their ratings and whether

appropriate fault values were used in protective relaying calculations. The

inspectors reviewed maintenance procedures, and schedules for the 480Vac load

centers and MCC to determine whether equipment was being properly maintained.

The inspectors reviewed system health and corrective action documents to

determine whether there were any adverse operating trends. In addition, the

inspectors performed a visual inspection of the 480Vac safety buses to assess

material condition and the presence of hazards.

Minimum Flow Air Operated Valve (E11F400B): The inspectors reviewed the

system description for the control air system to determine the valves ability to

maintain line pressure on the interruptible control air system. The inspectors

reviewed valve and actuator design data to verify compatibility. The inspectors

reviewed corrective action documents to ensure condition reports were

appropriately addressed and resolved or closed. The inspectors reviewed piping

and instrumentation diagrams for the control air system, where the valve was

located, and performed a system walkdown with licensee staff to verify the valves

position in the system lineup.

  • Division 1 RHRSW Pump A (E1151C001A): The inspectors reviewed the 130Vdc

control voltage drop calculation and verified that sufficient control voltage would be

available for the pump start breaker control components when the associated

130Vdc battery was at its minimum voltage. In addition, the inspectors reviewed

the system hydraulic calculations including NPSH, system flow, and submergence

to ensure the pump was capable of providing sufficient flow under normal and

accident conditions. The inspectors reviewed the design of the pump area

ventilation system to verify that the system was capable of maintaining an

acceptable environment for the operating equipment. The inspectors reviewed

surveillance test procedures and the bases for the acceptance criteria to verify that

the tests would ensure the pumps were capable of their required performance.

The inspectors also reviewed the minimum flow protection for the pump to verify

adequate performance under all conditions. The inspectors reviewed a design

change associated with replacing the pump. The inspectors performed a

walkdown of the pump and associated equipment to verify the material condition

and verify that no hazards existed in the area. The inspectors also reviewed a

9 Enclosure

sample of past corrective action documents, the system health report, training

documents, the TS, and the design basis document.

(E1150F068A): The inspectors reviewed the thrust and differential pressure

calculations associated with this motor operated valve to verify its capability to

perform its function during normal and accident conditions. The inspectors

reviewed the applicable surveillance test procedure and completed surveillances to

ensure actual performance was acceptable. Post-accident operating procedures

related to the valves operation were also reviewed. The inspectors reviewed the

voltage used in the MOV calculations to verify consistency with the associated

electrical distribution calculations. The inspectors performed a walkdown of the

pump and associated equipment to verify the material condition and verify that no

hazards existed in the area. The inspectors also reviewed a sample of past

corrective action documents, the system health report, training documents, the TS,

and the design basis document.

  • Battery 2PA 130/260Vdc (R3200S003): The inspectors reviewed calculations and

analyses relating to battery sizing and capacity, hydrogen generation, and station

blackout (SBO) coping. The review was performed to ascertain the adequacy and

appropriateness of design assumptions, and to verify that the battery was

adequately sized to support the design basis required voltage requirements of the

130/260Vdc safety-related loads under both design basis accident and SBO

conditions. The inspectors also reviewed a sample of completed surveillance

tests, service tests, performance discharge tests, and modified performance tests.

The review of various discharge tests was to verify that the battery capacity was

adequate to support the design basis duty cycle requirements and to verify that the

battery capacity meets TS requirements.

  • Division 1 dc Bus 2PA-2 (R3200S026): The inspectors reviewed 130Vdc short

circuit calculations and verified that the interrupting ratings of the fuses were well

above the calculated short circuit currents. The 130Vdc voltage drop calculations

were reviewed to determine if adequate voltage would be available for the 4.16kV

breaker open and close coils and spring charging motors. The inspectors reviewed

the 4.16kV motor control logic diagrams and the 130Vdc voltage-drop calculation

to ensure adequate voltage would be available for the control circuit components

under all design basis conditions. The inspectors also reviewed the dc equipment

operability calculation and the dc MOV mechanical thrust calculation to ensure that

the RCIC and high pressure coolant injection (HPCI) MOVs would develop

sufficient thrust under worst case voltage conditions.

  • Division 1 Battery Charger 2A-1 (R3200S020): The inspectors reviewed

calculations relating to sizing and current limit setting to ascertain the adequacy

and appropriateness of design assumptions, and to verify that the charger was

adequately sized to support the design basis duty cycle requirements of the

130Vdc safety-related loads and the associated battery under both normal and

design basis accident conditions. In addition, the test procedures were reviewed to

determine whether maintenance and testing activities for the battery charger were

in accordance with vendors recommendations. The inspectors also reviewed

preventive maintenance activities to verify that the electrolytic capacitors installed

in the battery charger were replaced with appropriate frequency.

10 Enclosure

  • Turbine Building HVAC Exhaust Fan (U4100C006): The inspectors reviewed

system health reports and corrective actions program documents for the turbine

building HVAC (TBHVAC) system. The inspectors reviewed maintenance rule

scoping documents and the basis for the systems exclusion. The inspectors

reviewed vendor manuals and performance curves to verify the system was

capable of meeting its intended function when in operation. The TBHVAC system

engineer was interviewed and the overall health of the TBHVAC system, with an

emphasis on exhaust fan failures, was discussed. The inspectors performed a

walkdown with the system engineer and maintenance personnel of the plenum

area and of the failed TBHVAC fans.

b. Findings

(1) Inadequate Calculations for Availability of 120kV System Offsite Power

Introduction: The inspectors identified a finding of very low safety significance and an

associated Non-Cited Violation (NCV) of 10 CFR Part 50, Appendix B, Criterion III,

Design Control, for the licensees failure to perform adequate calculations to ensure the

availability of offsite power. Specifically, on two occasions the licensee failed to perform

adequate calculations to demonstrate the availability of 120kV system offsite power. The

first occasion was related to the analysis in calculation DC-0919, for conditions when the

service system (SS) transformer No. 64 LTC was in service. The second occasion was

related to TSR-35286, which analyzed conditions for placing the SS transformer No. 64

LTC in manual operation.

Description: The inspector reviewed calculation DC-0919, Undervoltage Relay

Setpoints. This calculation relied, in part, upon computer databases ETAP and

LOFSTAB, which were not maintained as independent calculations such that the

assumptions and inputs could not be independently verified. This increased the difficulty

in reviewing the many permutations presented in the DC-0919 calculation. The inspector

identified numerous errors with this calculation including unverified assumptions and

unsupported conclusions. The inspector specifically identified a concern with the analysis

of SS transformer No. 64 LTC performance in Section 9.13 of DC 0919, Undervoltage

Relay Setpoints, which resulted in the analysis being non-conservative. Major errors

included failure to properly account for the 2.1 percent step voltage decrease on the trip of

the unit, and failure to account for the two percent LTC deadband.

The calculation determined the degraded voltage relay time delay necessary to permit the

SS transformer No. 64 LTC to compensate for voltage drops on the 4160V safety-related

buses at the onset of an accident, with the associated trip of the main generator. Although

the calculation described the need to consider a 2.1 percent step voltage decrease on the

trip of the unit, it was not clear in the calculation how this was actually accomplished. The

calculation included a two-tap margin above the eight taps shown to be needed by voltage

results from ETAP runs in Attachment I. The ETAP runs did not account for the 2.1

percent step voltage decrease, and also considered an initial bus voltage slightly above

the center of the LTC deadband, instead of conservatively at the low-end of the band. In

addition, because the low-end of the LTC deadband was 99 percent, the LTC might not

act to improve voltage any further once the 4kv bus reached this level. The acceptance

criteria in calculation DC-0919 required voltage to recover to 99.8 percent; therefore,

voltage might not recover, regardless of the time afforded for LTC action, the inspector

noted that this error adversely affected the licensees response to Generic Letter (GL)

11 Enclosure

2006-002 Item 2c. Had the error been known at the time the licensee responded to the

GL, the response to Item 2c should probably have been answered negatively. The

licensee addressed this condition in EFA-R14-10-004, Revisions 0 and A, and took credit

for degraded voltage relay tolerances from surveillance results that were more favorable

than the values used in the calculation. The EFA-R14-10-004, Revision 0, was

superseded by EFA-R14-10-004, Revision A after the end of the inspection period so a

detailed assessment of this revision was not made.

Additionally, Technical Service Request (TSR)-35286 analyzed conditions for placing the

SS transformer No. 64 LTC in manual. This condition could occur while the offsite voltage

is within its expected voltage range as defined in the UFSAR. The technical approach in

the TSR was to select a manually adjusted target voltage for the Division-1 4160V buses

that was approximately 2.64 percent higher than normal (4270V minimum versus 4160V

+/-1 percent with the LTC in automatic). This was done in order to compensate for the

increased post LOCA loading on the buses, thus enabling the degraded voltage relays to

reset. The TSR included a steady state ETAP run that showed bus voltage with LOCA

loads would recover to 4188V, which was considered to be sufficient to reset the relays,

because they reset at approximately 4160V. However, the analysis failed to consider the

step voltage decrease that could occur on the trip of the unit, which was assumed to be

2.1 percent in calculation DC-0919. Consequently, the analysis was non-conservative.

Preliminary calculations by the inspectors showed that compensation of approximately

2.64 percent above the normal bus voltage range would not be sufficient to offset the

approximately 4.3 percent drop that would occur due the combined effects of LOCA bus

loading and the 2.1 percent step voltage decrease on the trip of the unit. In response to

the inspectors concerns, the licensee initiated a CARD and implemented restrictions on

placing the LTC in manual, pending reanalysis.

Analysis: The inspectors determined that the failure to perform adequate analyses for

availability of the120kV offsite power supply was contrary to 10 CFR Part 50, Appendix B,

Criterion III, Design Control, and was a performance deficiency. The performance

deficiency was determined to be more than minor because the finding was associated with

the Mitigating Systems cornerstone attribute of design control, and affected the

cornerstone objective of ensuring the availability, reliability, and capability of systems that

respond to initiating events to prevent undesirable consequences. Specifically, there was

reasonable doubt as to whether the offsite power supply would remain operable during a

design basis event pending reanalysis. The finding was also similar to Example 3.j. of

IMC 0612, Appendix E,

Based on additional information provided by the licensee after the exit, the inspectors

determined the finding could be evaluated using the SDP in accordance with IMC 0609,

Significance Determination Process, Attachment 0609.04, Phase 1 - Initial Screening

and Characterization of findings, Table 4a for the Mitigating Systems Cornerstone. The

inspectors answered No to each of the questions in Column 2. Therefore, the finding

screened as having very low safety significance (Green).

The inspectors determined the primary cause of this issue was related to Human

Performance, Resources, which requires complete, accurate, and up-to-date design

documentation, including calculations and procedures, to assure nuclear safety.

(IMC 0310, Section 06.01.b.(3) H.2(c))

12 Enclosure

Enforcement: Title 10 CFR Part 50, Appendix B, Criterion III, Design Control, requires, in

part, that measures be established to assure that applicable regulatory requirements and

the design basis are correctly translated into specifications, drawings, procedures, and

instructions.

Contrary to the above, as of January 25, 2010, the licensee failed to ensure that the

design basis for the degraded voltage relay setpoint was correctly translated into

procedures. Specifically, on two occasions the licensee failed to perform conservative

calculations to show that the Division 1 degraded voltage relays would reset when

required to maintain the availability of offsite power. Because this violation was of very low

safety significance and was entered into the licensees corrective action program as CARD

10-21733, this violation is being treated as an Non-Cited Violation (NCV), consistent

with Section VI.A.1 of the NRC Enforcement Policy. (NCV 05000341/2010006-01,

Inadequate Calculations for Availability of 120kV System Offsite Power).

(2) Inadequate Motor Starting Voltage Calculations

Introduction: The inspectors identified a finding having very low safety significance and

associated NCV of 10 CFR Part 50, Appendix B, Criterion III, Design Control, for the

licensees failure to perform proper calculations to demonstrate that motors would

successfully start when connected to the offsite power supply.

Description: The NRC previously determined that the design of the Fermi degraded

voltage protection scheme had failed to consider a simultaneous LOCA with a degraded

voltage, in that, the time delay for actuation of the degraded voltage protection exceeded

the time delay assumed in the UFSAR accident analysis (see Inspection Report 05000341/2008-008). The NRC required that the licensee rectify this design oversight.

The modifications are scheduled for implementation in the fall of 2010, during Refueling

Outage 14.

The electrical system design in place prior to the modifications being implemented was

based on offsite power system voltages no lower than the administrative limits listed in

UFSAR Section 8.2.2.5.1 as follows: 120kV system - 112kV minimum and 345kV system

- 339.5kV minimum. Calculation DC-0919 determined the onsite electrical system bus

voltages available with these voltages on the offsite power system based on the starting

voltage requirements for motors, and compared to available bus voltages. The inspectors

determined that these calculations were non-conservative because motor starting voltage

requirements were based on 70 percent of motor rated voltage at the terminals, rather

than on the voltages stipulated in the motor specifications. These voltages were as

follows:

  • RHR Motors 80 percent (Specification 3037-A);
  • Core Spray Motors 90 percent (Specification 3037-A); and
  • 460V Motors (except MOVs) 85 percent (Specification 3067).

The inspectors determined that this error stemmed, in part, from the licensee canceling

calculation DC-5264, which analyzed 460Vac motor starting capability during accident

load sequencing.

13 Enclosure

Motor starting voltage less than the specified minimum could result in inadequate load

torque, slow starting, overheating, or tripping of overcurrent protective devices. These

factors were not evaluated in the calculation. The inspectors noted that DC-0919,

Attachment I, Revision F, which contained the static motor starting results, and DC-0919,

Attachment O (from ECR 35621-1), which was a dynamic study, showed considerably

different results. For example, the minimum voltage at the terminals of RHR Pump A

during starting in Attachment O was 85.48 percent, whereas the voltage shown in

Attachment I was 82.54 percent. The licensee confirmed that the dynamic analysis in

Attachment O was non-conservative due to incorrect modeling of the SS Transformer

No. 64 transformer automatic LTC. In addition, Attachment I was determined to be non-

conservative because it did not take the 2.1 percent step voltage decrease at the start of

an accident described in calculation DC-0919, Assumption 5.1, and did not take into

account the effect of the two percent deadband on the SS Transformer No. 64 LTC. The

licensee performed an operability evaluation, EFA-R14-10-004, which the inspectors

determined to be incomplete because it did not address the case where 480V motors were

started simultaneously with the large ESF motors during accident load sequencing, did not

address the step voltage decrease occurring on the trip of the unit, and did not address the

transient response time of voltage regulators on the Division 2 480V buses. The licensee

revised the operability analysis and was able to demonstrate operability; however a

detailed review of the operability analysis was not completed. The inspectors determined

that the components with the lowest margin were the control complex HVAC chiller supply

and return motors.

Analysis: The inspectors determined that the failure to perform adequate calculations to

demonstrate that motors had sufficient voltage to start during accidents was contrary to 10 CFR Part 50, Appendix B, Criterion III, Design Control, and was a performance

deficiency. The performance deficiency was determined to be more than minor because

the finding was associated with the Barrier Integrity cornerstone attribute of design control

and affected the cornerstone objective of provide reasonable assurance that physical

design barriers (fuel cladding, reactor coolant system, and containment) protect the public

from radionuclide releases caused by accidents or events. Specifically, the licensee failed

to demonstrate that the approved design was adequate to ensure safety-related motors

had sufficient voltage to start if safety buses remained connected to offsite power during a

LOCA with normal offsite power system voltages.

The inspectors determined the finding could be evaluated using the SDP in accordance

with IMC 0609, Attachment 04, and Table 4a for the Barrier Integrity Cornerstone. The

inspectors determined that there was only a degradation of the radiological barrier function

provided for the control room. As such, the finding was determined to be of very low

safety significance (Green).

The inspectors determined the primary cause of this issue was related to Human

Performance, Resources, which requires complete, accurate, and up-to-date design

documentation, including calculations and procedures, to assure nuclear safety.

(IMC 0310, Section 06.01.b.(3) [H.2.(c)])

Enforcement: Title 10 CFR Part 50, Appendix B, Criterion III, Design Control, requires, in

part, that design control measures provide for verifying or checking the adequacy of

design, such as by the performance of design reviews, by the use of alternate or simplified

calculational methods, or by the performance of a suitable testing program.

14 Enclosure

Contrary to the above, as of January 25, 2010, the licensees design control measures

failed to verify the adequacy of design of the onsite electrical distribution system.

Specifically, the inspectors identified that the licensee failed to properly analyze motor

starting voltage requirements while the safety buses were connected to offsite power.

Because this violation was of very low safety significance and was entered into the

licensees corrective action program as CARDs 10-20748, and 10-21733, this violation is

being treated as an NCV, consistent with Section VI.A.1 of the NRC Enforcement Policy.

(NCV 05000341/2010006-02, Inadequate Motor Starting Voltage Calculations)

(3) Inadequate Procedures for Controlling Availability of 120kV System Voltage

Introduction: The inspector identified a finding of very low safety significance with an

associated NCV of TS 5.4.1.a, Procedures for the licensees failure to translate design

requirements for the availability of offsite power into procedures. Specifically, the licensee

failed to translate the 2.1 percent switchyard voltage drop criteria assumed in calculation

DC-0919 into station operating Procedures ODE-12, Operations Department

Expectations, Revision 18; MOP05, Control of Equipment, Revision 30, and

20.300.Grid, Grid Disturbance, Revision 2.

Description: Calculation DC-0919, Assumption 5.1, identified that a 2.1 percent step

voltage decrease could occur on the 120kV offsite power system on the trip of the unit.

This assumption was necessary because SS Transformer No. 64, which supplies power to

the Division 1 buses from the 120kV switchyard, was equipped with an automatic LTC.

During normal operation, the LTC normalizes voltage on the 4160V bus. When a sudden

switchyard voltage decrease occurs, such as may occur on the trip of the unit, the voltage

decrease is reflected onto the 4160V buses. The degraded voltage relays on the Division

1 4160V safety buses featured a nominal 44 second time delay to afford time for the LTC

to compensate for this voltage decrease and raise the bus voltage above the reset

setpoint (99.8 percent of bus rated voltage) of the relays. If the voltage decrease

exceeded the value assumed in the calculation, the LTC might not have sufficient time to

adjust voltage to the required value before the degraded voltage relay scheme times out,

and grid separation occurs.

The inspectors noted that station and system operations procedures intended to

control voltages on the offsite power system within acceptable ranges only addressed the

minimum and maximum discrete voltages for the 120 kV systems, and did not address the

magnitude of the sudden voltage decrease that could be tolerated. Specifically, Procedure

ODE-12, Section 7, Table 1 provided values from which the licensed limits for operability

were derived. Table 1 identified the minimum and maximum discrete values (112kV and

126kV, respectively) for 120kV system voltage and did not address the sudden decrease

in voltage that could be tolerated, as discussed in calculation DC-0919. Similarly,

Procedure 20.300.GRID provided criteria for assessing operability of the offsite power

supplies based on minimum voltages only, instead of including voltage drop criteria for the

120kV system. Procedure MOP5, Section 6.13 discussed conditions where the offsite

power supplies would be considered inoperable, but these did not include exceeding the

voltage drop criteria analyzed in Calculation DC-0919. In response the inspectors

concerns, the licensee issued a CARD and initiated monitoring of voltage drop criteria.

The CARD stated that as of March 3, 2010, ITC Transmission added the 2.1 percent

voltage drop limits on Buses 101 and 102 for real time contingency analysis.

15 Enclosure

Analysis: The inspectors determined that the failure to translate design criteria for the

operability of 120kV offsite power supply into procedures was contrary to TS 5.4.1a,

Procedures, and was a performance deficiency.

The performance deficiency was determined to be more than minor because the finding

was associated with the Mitigating Systems cornerstone attribute of Design Control, and

affected the cornerstone objective of ensuring the availability, reliability, and capability of

systems that respond to initiating events to prevent undesirable consequences.

Specifically, the licensee did not ensure the availability of the 120kV power source to

4160V safety buses by implementing procedural controls to ensure that the step voltage

decrease on the trip on the Fermi generating unit did not exceed the 2.1 percent value

analyzed in calculation DC-0919. The finding was also similar to Example 3.j. of IMC 0612, Appendix E. The inspectors determined the finding could be evaluated using the

SDP in accordance with IMC 0609, Attachment 04, and Table 4a for the Mitigating

Systems Cornerstone. The inspectors answered No to each of the questions in

Column 2. Therefore, the finding screened as having very low safety significance (Green).

The inspectors determined the primary cause of this issue was related to Human

Performance, Resources, which requires complete, accurate and up-to-date design

documentation, including calculations and procedures, to assure nuclear safety.

(IMC 0310, Section 06.01.b.(3) H.2(c))

Enforcement: Technical Specification 5.4.1.a, requires, in part, that written procedures

be established, implemented, and maintained covering the applicable procedures

recommended in Regulatory Guide 1.33, Revision 2, Appendix A, February 1978.

Regulatory Guide 1.33, Appendix A, Paragraph 6, Procedures for Combating

Emergencies and Other Significant Events, Item c addresses loss of electrical power and

degraded power sources.

Licensee Procedures ODE-12, Operations Department Expectations, Revision 18,

MOP05, Control of Equipment, Revision 30, and 20.300.Grid, Grid Disturbance,

Revision 2, address loss of electrical power and degraded power sources.

Contrary to the above, as of January 25, 2010, the licensee failed to establish a

procedure to address degraded power sources. Specifically, the licensee failed to

translate switchyard voltage drop criteria determined in calculation DC-0919 into

Procedures ODE-12, MOP05, and 20.300.Grid. Because this violation was of very low

safety significance, and was entered into the licensees corrective action program as

CARD 10-21791, this violation is being treated as an NCV, consistent with Section VI.A.1

of the NRC Enforcement Policy. (NCV 05000341/2010006-03, Inadequate Procedures for

Controlling Availability of 120kV System Voltage)

16 Enclosure

(4) Failure to include Turbine Building Heating, Ventilation and Air Conditioning Fans in the

Scope of the Maintenance Rule Program

Introduction: The inspectors identified a finding of very low safety significance (Green)

with and associated NCV of 10 CFR 50.65, Requirements for Monitoring the

Effectiveness of Maintenance at Nuclear Power Plants, for the failure to include the

TBHVAC fans within the scope of the Maintenance Rule program. Failure of all three

fans could cause an increase in steam tunnel temperatures that would lead to a forced

shutdown, i.e., manual scram, in anticipation of a Group 1 isolation (MSIV closure)

resulting in a reactor trip.

Description: As a part of the inspection sample and discussions with the resident

inspectors, the inspectors selected the TBHVAC system for review based on the

historical events and evaluations of recent failures of the systems exhaust fans. The

inspectors reviewed corrective action program documents, root cause evaluations,

maintenance rule procedures and scoping documents, preventive maintenance

procedures, system operating procedures, and system design documents.

The TBHVAC system exhaust fans have experienced approximately 10 catastrophic

failures since 1990, with an increase in the frequency of failure or periodicity of operation

with degraded fans, over the past ten years from 1999-2010. The TBHVAC system

recently degraded to a point where no exhaust fans were operable and the licensee was

forced to take compensatory action to limit and monitor the temperature in the turbine

building steam tunnel for any increase, which might have challenged trigger points

established in the operational decision making issue (ODMI) plan, which could have

spurred the licensee into a forced shutdown in anticipation of a reactor trip.

The inspectors reviewed Maintenance Rule (MR) Evaluation 95-010, which provides the

basis for not including the TBHVAC system in scope of the program. The licensee

stated that the TBHVAC system did not meet any of the requirements in 10 CFR 50.65

to be a MR system. The licensee considered that for non-safety-related systems,

structures, or components (SSCs) to be considered important, they must add significant

value to the mitigation function of an emergency operating procedure by providing the

total or a significant fraction of the total functional ability required to mitigate core

damage or radioactive release where the significance determination was made based on

utility specific technical judgment.

The licensee provided additional justification for excluding the TBHVAC system from the

MR program in MR Program position papers97-006 and 98-023. The inspectors

identified that the licensee referenced a modification plan that was never implemented,

that would have been credited for alleviating high steam tunnel temperatures. The

licensee entered this issue into their corrective actions program for evaluation. The

inspectors also identified in the licensees consideration of the criteria in (b)(2) of

10 CFR 50.65, instead of asking if failure of the SSC would cause a scram or actuation

of a safety-related system, the licensee asked, would failure of the SSC cause a

safety-related SSC to fail to perform its function? The inspectors identified that

10 CFR 50.65(b)(2)(iii), Requirements for Monitoring Maintenance at Nuclear Power

Plants, states that non-safety-related SSCs whose failure could cause a reactor scram

or actuation of safety-related systems shall be included in the MR program. The

licensee stated in its basis document, and in more recent ODMIs, that if all three

fans in the TBHVAC system fail, plant shutdown would commence at 193 degrees

17 Enclosure

Fahrenheit (°F) and at 195°F the reactor mode switch would be placed in shutdown. At

temperatures greater than 200°F, group one isolation could occur, causing a reactor

scram.

Analysis: The inspectors determined that the licensees failure to scope the TBHVAC

system into its maintenance rule program is a performance deficiency. The

performance deficiency was determined to be more than minor because it was

associated with the Initiating Events cornerstone attribute of Equipment Performance,

and affected the cornerstone objective to limit the likelihood of those events that upset

plant stability and challenge critical safety functions during shutdown as well as power

operations. Specifically, because the TBHVAC fans were initially not scoped into the

Maintenance Rule program, the licensee could not provide reasonable assurance that

the preventive maintenance being performed ensured the system remained capable of

performing its intended function. The finding was also similar to Example 7.d. of

IMC 0612, Appendix E.

The inspectors determined the finding could be evaluated using the SDP in accordance

with IMC 0609, Attachment 04, and Table 4a for the Transient Initiators Cornerstone.

The inspectors determined that the finding did not contribute to the likelihood that

mitigation equipment or functions would not be available. Therefore, the finding

screened as having very low safety significance (Green).

The inspectors determined there was no cross-cutting aspect associated with this finding

because the system was originally scoped out during the initial baseline evaluation for

Maintenance Rule in June 1995; therefore, was not reflective of current performance.

Enforcement: Title 10 CFR 50.65(b)(2)(iii) Requirements for Monitoring the

Effectiveness of Maintenance at Nuclear Power Plants, states that non-safety-related

SSCs whose failure could cause a reactor scram or actuation of a safety-related system

shall be scoped in the monitoring program as specified in 10 CFR 50.65(a)(1).

Contrary to the above, from June 1995 through January 25, 2010, the licensee failed to

adequately scope into the Maintenance Rule program the TBHVAC fans, whose

intended function is to control temperature and building pressure below design limits to

preclude reaching temperatures that could lead to the initiation of manual or automatic reactor trips. Because this violation was of very low safety significance and was

entered into the licensees corrective actions program as CARDs 10-21757, 10-21761,

and 10-21777, this violation is being treated as a NCV with Section VI.A.1 of the

Enforcement Policy. (NCV 05000341/201006-04, Failure to include Turbine Building

Heating Ventilation and Air Conditioning Fans in the Scope of the Maintenance Rule

Program).

(5) Inadequate Calculation for DC Short Circuit Analysis

Introduction: The inspectors identified a finding of very low safety significance with an

associated NCV of 10 CFR Part 50, Appendix B, Criterion III, Design Control for the

licensees failure to correctly translate cable resistances into dc calculations. The

inspectors noted that the licensee failed to use conservative assumptions, verify the

accuracy of design inputs and parameters, and avoid conceptual errors, which led to a

decrease in margin in the short circuit calculation.

18 Enclosure

Description: During review of calculation, DC-0214, Short Circuit Calculation for dc

System, the inspectors identified several errors which reduced the overall margin of

the dc system. Specifically, the inspectors determined that the licensee did not

recognize the actual cable wiring configuration and instead incorrectly calculated the

cable resistance for HPCI and RCIC MOVs by taking the individual length of a feed

cable conductor and multiplying it by four. The inspectors determined that this resulted

in overestimating the cable resistance by a factor of 2.285 which resulted in reduction in

the short-circuit current available to the breakers. The inspectors determined that the

incorrect and non-conservative methodology affected the breaker short-circuit rating not

only for the individual MOV breakers, but also the main feed breakers for both divisions.

In addition to this error, the inspectors also identified that the short circuit calculation

used non-conservatively high values for battery inter-cell connection resistance and

omitted the battery terminal connection resistance, which again decreased the available

short-circuit current to the breakers. The inspectors identified a third error - using only

half of the MOV circuit resistance values -- that was conservative. The inspectors

determined that the current configuration was still acceptable; however, future load

additions could result in exceeding the short circuit rating of the main feed breakers

resulting in the potential for a loss of either dc division.

In addition to the errors in the short circuit calculation, the inspectors identified that

the incorrect methodology for calculating cable resistance was also used in calculations

DC-4943, DC Equipment Operability, DC-5351, DC Voltage Drop, DC-0213, Battery

and Charger Sizing, and mechanical calculation 021-014-AWI for computing dc MOV

thrust margins. The inspector determined that the methodology, while still incorrect,

resulted in conservative results for these calculations. Similarly, the licensee also

failed to include the battery inter-cell and terminal connection resistance in calculation

DC-0213. The inspectors identified additional errors in the above calculations, which

either had minor effects or did not result in a significant loss of margin. These errors

ranged from simple arithmetic issues to failing to select the worst case first minute

battery terminal voltage to listing timing sequences and corresponding voltages that did

not agree with the UFSAR accident sequences. Based on the extent of the issues, and

when combined with the errors discovered in the ac electrical calculation DC-0919, as

described above, the inspectors determined that there was a concern with the licensees

design control process in the electrical area. The inspectors noted that all the

calculations were revised within the last two years, with calculation DC-4943 having

been revised several times without identifying and correcting the incorrect timing

sequences.

Analysis: The inspectors determined that the licensees failure to incorporate

conservative cable resistance values into the dc short circuit calculation was contrary to

10 CFR Part 50, Appendix B, Criterion III, Design Control, and was a performance

deficiency. The performance deficiency was determined to be more than minor because

the issue was associated with the Mitigating Systems cornerstone attribute of design

control, and affected the cornerstone objective of ensuring the availability, reliability, and

capability of systems that respond to initiating events to prevent undesirable

consequences. Specifically, if the errors were not corrected, they could lead to one or

both dc divisions being lost if additional loads were added to the main feed breakers.

The finding was also similar to Example 3.j of IMC 0612, Appendix E.

19 Enclosure

The inspectors determined the finding could be evaluated using the SDP in accordance

with IMC 0609, Attachment 04, Table 4a for the Mitigating Systems Cornerstone. The

inspectors answered No to each of the questions in Column 2. Therefore, the finding

screened as having very low safety-significance (Green).

The inspectors concluded that the primary cause of the finding was related to the cross-

cutting element of Human Performance, Resources, which requires complete, accurate

and up-to-date design documentation, including calculations and procedures, to assure

nuclear safety. (IMC 0310, Section 06.01.b.(3) H.2(c))

Enforcement: Title 10 CFR Part 50, Appendix B, Criterion III, Design Control requires,

in part, that design control measures provide for verifying or checking the adequacy of

design, such as by the performance of design reviews, by the use of alternate or

simplified calculational methods, or by the performance of suitable testing program.

Contrary to this requirement, as of January 25, 2010, the licensees design control

measures failed to ensure the adequacy of the design for the RCIC and HPCI MOVs.

Specifically, the licensee failed to ensure that the cable resistances used in the short

circuit analysis were conservative to ensure adequate current to the main feed breakers.

Because this violation was of very low safety-significance and because the issues were

entered into the licensees corrective action program, as CARDS 10-20981, 10-20982,

10-20992, 10-21209, 10-21265, 10-21285, 10-21311, 10-21564, 10-21567, and

10-21591, this violation is being treated as an NCV consistent with Section VI.A.1 of the

NRC Enforcement Policy (NCV 05000341/2010006-05, Inadequate Calculation for DC

Short Circuit Analysis)

.4 Operating Experience

a. Inspection Scope

The inspectors reviewed five operating experience issues to ensure that NRC generic

concerns had been adequately evaluated and addressed by the licensee. The operating

experience issues listed below were reviewed as part of this inspection:

  • IN 2009-02, Biodiesel in Fuel Oil Could Adversely Impact Diesel Engine

Performance;

  • OE 28932, Higher than Expected Failure Rate on Initial License Training Exam

(Catawba);

  • IN 2009-09, Improper Flow Controller Settings Renders Injection Systems

Inoperable and Surveillance Did Not Identify;

  • IN 2008-02, Findings Identified During Component Design Bases Inspections;

and

  • GL 2007-001, Inaccessible or Underground Power Cable Failures that Disable

Accident Mitigation Systems or Cause Plant Trip.

20 Enclosure

b. Findings

(1) Failure to Adequately Evaluate Industry Operating Experience for Applicability to Fermi 2

Introduction: The inspectors identified a finding of very low safety significance for the

failure to follow procedures when evaluating industry operating experience for

applicability to Fermi 2 Power Plant. Specifically, the inspectors identified three

instances where the licensee did not evaluate and take corrective actions on industry

operating experience that was applicable to the Fermi 2 site. This did not meet the

requirements in licensees operating experience Procedure MLS04, Fermi 2

Licensing/Safety Engineering Conduct Manual for Operating Experience Program,

Revision 22.

Description: The inspectors identified three examples where the licensee did not follow

its internal procedure for review and disposition of industry operating experience.

1. On February 4, 2008, the licensee initiated CARD 08-20775 in response to

industry operating experience regarding digital feed water control system power

supply failures causing automatic reactor scram with complications including

RCIC trip while injecting into the reactor vessel. On July 28, 2008, this CARD

was closed out without addressing RCIC trip while injecting into the reactor

vessel due to changes made to the RCIC flow controller tuning parameters.

Specifically, no attempt was made to address the applicability of RCIC flow

controller tuning parameters to Fermi 2.

2. On February 21, 2008, the licensee initiated CARD 08-21245 after learning about

changes to flow controller tuning parameters contributed to RCIC pump trip at

Perry. This CARD was closed out on April 17, 2008, without clearly reviewing

and determining its applicability to Fermi 2 despite the fact that a note was added

to the CARD that stated CARD 07-24478 was written to address concerns

regarding HPCI/RCIC system tuning based on OE 25305 and OE 15574 and that

CARD was closed without action. The licensee issued CARD 09-24985 on

June 25, 2009, in response to NRC Information Notice (IN) 2009-09 Improper

Flow Controller Settings Renders Injection Systems Inoperable and Surveillance

Did Not Identify to review for impact to Fermi. This appeared to be the fourth

CARD in a series that the licensee initiated on the same issue dealing with the

HPCI and RCIC controller tuning parameters. The action plans described in this

CARD appeared to be reasonable in resolving the issue. However, as of

February 26, 2010, this CARD was still open and the issue unresolved.

3. On April 22, 2008, the licensee initiated CARD 08-22662 in response to NRC

IN-2008-02 Findings identified during component design bases inspections.

This CARD was closed out on June 17, 2009, without addressing all the issues

identified in the NRC IN. Specifically, the IN had described a finding at Quad

Cities related to the Quad Cities safety-related Division 1 and 2 batteries having

non-conservative inter-cell and terminal connection resistance values ( 150

micro-ohms (µ) per connection) prescribed in the Quad Cities TS. Fermi had

the same resistance values in its TS and failed to evaluate this finding for

applicability to Fermi. During the inspection, the inspectors brought the issue to

the attention of the licensee and the licensee indicated that they had initiated

CARD 09-27471 on September 25, 2009, in preparation for the CDBI but had not

21 Enclosure

resolved the issue. The inspectors performed a quick calculation and determined

that the Fermi Division 2 safety-related 130/260 VDC battery would become

inoperable due to negative voltage margin if every inter-cell and terminal

connection resistances was allowed to reach 150 µ as allowed by the Fermi

Technical Specifications.

Based on the inspectors findings, the licensee performed a formal evaluation and took

appropriate corrective actions. The licensee also performed an extent of condition

review and identified approximately 30 additional operating experience reviews

performed within the last 2-year period, which did not meet licensee expectations.

Analysis: The inspectors determined that the licensees failure to follow operating

experience Procedure MLS04 in evaluating industry operating experience for

applicability to Fermi on several occasions in the recent past was a performance

deficiency warranting a significance evaluation. The finding was more than minor

because it was associated with the Mitigating Systems cornerstone attribute of

equipment performance and affected the cornerstone objective of ensuring equipment

availability and reliability. Specifically, multiple examples were identified where the

licensee failed to ensure that problems identified in industry operating experience were

evaluated for applicability to Fermi and corrective actions implemented.

The inspectors determined the finding could be evaluated using the SDP in accordance

with IMC 0609, Attachment 04, and Table 4a for the Mitigating Systems Cornerstone.

The inspectors answered No to each of the questions in Column 2. Therefore, the

finding screened as having very low safety significance (Green).

The inspectors concluded that the cause of the finding was related to the cross-cutting

element of Problem Identification and Resolution, Operating Experience, because the

licensee failed to systematically collect, evaluate and communicate to affected internal

stakeholders in a timely manner relevant internal and external operating experience to

support plat safety (IMC-0310, Section 06.02.b.(1) P.2(a))

Enforcement: The inspectors determined that no violation of regulatory requirements

had occurred. The licensee entered these issues in their corrective action program as

CARDs 10-20898, 10-20912, and 10-21122. (FIN 0500341/2010006-06, Failure to

Adequately Evaluate Industry Operating Experience for Applicability to Fermi 2).

.5 Modifications

a. Inspection Scope

The inspectors reviewed 11 permanent plant modifications related to selected

risk-significant components to verify that the design bases, licensing bases, and

performance capability of the components had not been degraded through modifications.

The modifications listed in the List of Documents Reviewed of this report, were

reviewed as part of this inspection effort.

22 Enclosure

b. Findings

(1) Inadequate Calculations for Backfit Modifications

Introduction: The inspectors identified a finding very low safety significance with an

associated NCV of 10 CFR Part 50, Appendix B, Criterion III, Design Control, for failing

to perform adequate calculations to support modifications to the Fermi 2 degraded

voltage protection scheme. The first example involved the failure to analyze motor

starting capability based on voltages afforded by the degraded voltage relay scheme.

The second example involved the failure to perform conservative calculations to show

that spurious grid separation would not occur during accidents due to action of the

degraded voltage relays.

Description: The NRC previously determined that the design of the Fermi degraded

voltage protection scheme had failed to consider a simultaneous LOCA with a degraded

voltage, in that the time delay for actuation of the degraded voltage protection exceeded

the time delay assumed in the UFSAR accident analysis (see Inspection Report 05000341/2008-008). The NRC required that the licensee rectify this design oversight.

Modification EDP-35621, Revision 0 (dated March 02, 2009), changed the time delay of

the degraded voltage relay scheme from a maximum of 46.2 seconds to a maximum of

8.4 seconds, to ensure that if a degraded grid condition occurred concurrent with a

LOCA, the safety-related buses would be disconnected from the degraded offsite power

source and ESF loads would have power available from the diesel generators within the

time assumed in the accident analysis. However, EDP-35621 also concluded that grid

separation and load shedding might occur for large motor starting with initial bus voltage

at the lower end of the range above the secondary voltage relay settings. The lower

end of the range referred to was the allowable range of switchyard voltage defined in

UFSAR Section 8.2.2.5.1. Since a design that would allow separation of the offsite

power supply if an accident occurred with switchyard voltage within its expected range

was not acceptable, EDP-36014, dated September 22, 2009, was issued to replace the

existing ITE 27-D degraded voltage relays with Model ABB 27-N relays. The new relays

would feature a smaller deadband, thereby providing a lower voltage for relay reset, and

more margin for spurious grid separation avoidance. The revised setpoints of the new

relays were evaluated in ECR-35621-1, Revision A, dated September 11, 2009, by

performing dynamic motor starting studies using ETAP. The inspectors determined that

these motor starting studies were not adequate because they did not address whether

motors had adequate voltage to start based on voltage afforded by the new degraded

voltage relays. In addition, the studies were non-conservative for purposes of showing

that the relays would be able to reset and avoid spurious grid separation if offsite voltage

remained within its expected range during accidents.

Motor Starting Voltage

None of the approved modification packages described above evaluated whether

safety-related motors would have adequate voltage to start, considering the worst case

voltages that could exist on the safety-related buses during an accident. During

transient conditions at the onset of an accident, starting the large ESF motors would

cause the degraded voltage relays to drop out, initiating the delay timers. If voltage

recovered above the relay reset setpoint before the time delay expired, then the

safety buses would remain connected to offsite power. Engineering Change Request

23 Enclosure

(ECR)-35621-1 revised the nominal reset setpoint for the Division 1 degraded voltage

relays from 95 percent X 103 percent = 97.85 percent to 95 percent X 101 percent =

95.95 percent. Calculation DC-0919, Appendix C, established a two percent tolerance

for the degraded voltage relays that was also adopted in ECR-35621-1. Applying the

tolerance in the negative direction, the Division 1 relays could reset as low as 95.95

percent X 98 percent = 94.03 percent. This is lower than the minimum voltage that

would occur with the existing design, 97.85 percent X 98 percent = 95.89 percent.

Because the degraded voltage modifications have not yet been installed in the field, this

issue did not affect current operability.

Spurious Grid Separation

ECR-35621-1 evaluated the time delay and reset setpoints of the new ABB-27N relays

scheduled to be installed by EDP-036014 as part of the modifications to comply with

NRC backfit orders relating to degraded voltage concerns. The ECR added

Attachment O to Calculation DC-0919. This attachment was a dynamic ETAP motor

starting study intended to demonstrate the adequacy of the revised relay reset setpoint

and time delays. Because Attachment O was a dynamic model, it showed both the

magnitude and duration of the voltage dips and was used in lieu of the separate static

and dynamic models used in the previous version of the calculation.

As stated above, ECR-35621-1 revised the nominal reset setpoint for the degraded

voltage relays and adopted a two percent tolerance for the degraded voltage relays.

Applying the tolerance in the positive direction, a maximum reset voltage was

determined as 95.95 percent X 102 percent = 97.87 percent. The Attachment O

showed that the voltage on Buses 64B and 64C recovered to 97.89 percent within 3.5

seconds following the start of the Core Spray Pumps during an accident, providing

voltage margin of 0.02 percent.

The inspectors compared the static motor starting results from calculation DC-0919,

Revision F, Attachment I to the dynamic study contained in Attachment O from

ECR-35621-1. The inspectors noted that the Attachment I and Attachment O showed

considerably different results. For example, the minimum voltage at the terminals of

RHR Pump A during starting in Attachment O was 85.48 percent, whereas the

voltage shown in Attachment I was 82.54 percent. The inspectors determined that the

dynamic analysis in Attachment O was non-conservative due to incorrect modeling of

the SS Transformer No. 64 transformer automatic LTC. Consequently, considering the

approximately 3 percent error in the Attachment O results versus the calculated reset

margin of 0.02 percent, the inspectors determined that the conclusion in ECR-35621-1

that the new design would prevent spurious grid separation were not justified. Because

the degraded voltage modifications have not yet been installed in the field, this issue did

not affect current operability.

Analysis: The inspectors determined that the failure to perform adequate calculations to

support modifications to the Fermi 2 degraded voltage protection scheme was contrary

to 10 CFR Part 50, Appendix B, Criterion III, Design Control, and was a performance

deficiency.

24 Enclosure

The performance deficiency was determined to be more than minor because the finding

was associated with the Mitigating Systems cornerstone attribute of Design Control, and

affected the cornerstone objective of ensuring the availability, reliability, and capability of

systems that respond to initiating events to prevent undesirable consequences.

Specifically, the licensee failed to confirm the adequacy of new degraded voltage relay

setpoints by ensuring motors had adequate voltage to start if safety buses remained

connected to offsite power during a LOCA with degraded voltage. In addition, the

licensee failed to ensure that spurious grid separation would not occur during

accidents due to action of the degraded voltage relays. The finding was also similar to

Example 3.j. of IMC 0612, Appendix E.

The inspectors determined the finding could be evaluated using the SDP in accordance

with IMC 0609, Attachment 04, and Table 4a for the Mitigating Systems Cornerstone.

The inspectors answered Question 1 positively. Therefore, the finding screened as

having very low safety significance (Green).

The inspectors determined the primary cause of this issue was related to Human

Performance, Resources, which requires complete, accurate, and up-to-date design

documentation, including calculations and procedures, to assure nuclear safety.

(IMC 0310, Section 06.01.b.(3) H.2(c))

Enforcement: Title 10 CFR Part 50, Appendix B, Criterion III, Design Control, requires,

in part, that design control measures shall provide for verifying or checking the adequacy

of design, such as by the performance of design reviews, by the use of alternate or

simplified calculational methods, or by the performance of a suitable testing program.

Contrary to the above, as of January 25, 2010, the licensees design control measures

failed to verify the adequacy of design of the safety-related degraded voltage protection

scheme scheduled to be installed during RFO14, in October 2010. Specifically, the

inspectors identified that the licensee failed to analyze motor starting voltage

requirements, and to ensure that spurious grid separation would not occur in calculations

to support modifications for the degraded voltage protection scheme. Because this

violation was of very low safety significance, and was entered into the licensees

corrective action program as CARDs 10-21733 and 10-21792, this violation is being

treated as an NCV, consistent with Section VI.A.1 of the NRC Enforcement Policy.

(NCV 05000341/2010006-07, Inadequate Calculations for Backfit Modifications)

.6 Risk-Significant Operator Actions

a. Inspection Scope

The inspectors performed a margin assessment and detailed review of six risk-

significant, time critical operator actions (six samples). These actions were

selected from the licensees PRA rankings of human action importance based on risk

achievement worth values. Where possible, margins were determined by the review of

the design basis and USAR response times and performance times documented by job

performance measures results. For the selected operator actions, the inspectors

performed a detailed review and walk through of associated procedures, including

observing the performance of some actions in the stations simulator and in the plant for

other actions, with an appropriate plant operator to assess operator knowledge level,

adequacy of procedures, and availability of special equipment where required.

25 Enclosure

The following operator actions were reviewed:

  • Action to Locally Operate an RHR Motor Operated Valve;
  • Action to Locally Tie in an Alternate Battery Charger;
  • Action to Locally Cross-Tie Division 1 to Division 2 NIAS Control Air;
  • Action to Align 4160V Maintenance Cross-Tie Breakers 64T/65T to Cross-Tie

Division 1 to Division 2 Following a Loss Of Offsite Power and the Failure of Diesel

Generators on One Division of ESF Power;

  • Action to Keep MSIVs Open Following a Reactor Scram; and
  • Action to Start the Standby Feedwater Pump to Maintain RPV Water Level.

b. Findings

No findings of significance were identified.

4. OTHER ACTIVITIES

4OA2 Identification and Resolution of Problems

.1 Review of Items Entered Into the Corrective Action Program

a. Inspection Scope

The inspectors reviewed a sample of the selected component problems that were

identified by the licensee and entered into the corrective action program. The inspectors

reviewed these issues to verify an appropriate threshold for identifying issues and to

evaluate the effectiveness of corrective actions related to design issues. In addition,

corrective action documents written on issues identified during the inspection were

reviewed to verify adequate problem identification and incorporation of the problem into

the corrective action program. The specific corrective action documents that were

sampled and reviewed by the inspectors are listed in the Attachment to this report.

b. Findings

No findings of significance were identified.

4OA6 Meeting(s)

.1 Exit Meeting Summary

On February 26, 2010, the inspectors presented the inspection results to Mr. J. Plona

and other members of the licensee staff. On April 26, 2010, the inspectors conducted a

re-exit of the inspection results with Mr. J. Plona, Mr. M. Caragher, and other members

of the licensee staff. The licensee acknowledged the issues presented. The inspectors

asked the licensee whether any materials examined during the inspection should be

considered proprietary. Several documents reviewed by the inspectors were considered

proprietary information and were either returned to the licensee or handled in

accordance with NRC policy on proprietary information.

ATTACHMENT: SUPPLEMENTAL INFORMATION

26 Enclosure

SUPPLEMENTAL INFORMATION

KEY POINTS OF CONTACT

Licensee

J. Plona, Site Vice President

M. Caragher, Nuclear Engineering Director

T. Conner, Plant Manager

K. Howard, Manager, Plant System Engineering

J. Davis, Manager, Nuclear Training

R. Johnson, Manager, Licensing

S. Hassoun, Supervisor, Licensing and Compliance

R. Salmon, Principal Engineer, Licensing

J. Tigai, Engineering Supervisor, NQA

J. Moyers, Manager, NQA

J. Ellis, Work Management, Manager

G. Strobel, Operations Manager

W. Meath, Operations Department

J. Dudlets, Supervisor, PSE, Electrical/I and C

K. Lawson, Principal Engineer, PSE

B. Sanders, PSE Mechanical Engineering

B. Waybright, PSE Electrical/I and C

P. Temple, PSE Mechanical Civil

J. Korte, Manager, Nuclear Strategy

Nuclear Regulatory Commission

M. Morris, Senior Resident Inspector

J. Benjamin, EB2 Acting Branch Chief, RIII

F. Tran, Projects Inspector, RIII

LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED

Opened and Closed

05000341/2010006-01 NCV Inadequate Calculations for Availability of 120kV System

Offsite Power

05000341/2010006-02 NCV Inadequate Motor Starting Voltage Calculations05000341/2010006-03 NCV Inadequate Procedures for Controlling Availability of 120kV

System Voltage

05000341/2010006-04 NCV Failure to include Turbine Building Heating Ventilation and Air

Conditioning Fans in the Scope of the Maintenance Rule

Program.05000341/2010006-05 NCV Adequate Calculation for DC Short Circuit Analysis05000341/2010006-06 FIN Failure to Adequately Evaluate Industry Operating

Experience for Applicability to Fermi 2

05000341/2010006-07 NCV Inadequate Calculations for Backfit Modifications

1 Attachment

LIST OF DOCUMENTS REVIEWED

The following is a list of documents reviewed during the inspection. Inclusion on this list does

not imply that the NRC inspectors reviewed the documents in their entirety, but rather, that

selected sections of portions of the documents were evaluated as part of the overall inspection

effort. Inclusion of a document on this list does not imply NRC acceptance of the document or

any part of it, unless this is stated in the body of the inspection report.

CALCULATIONS

Number Description or Title Revision

DC-0106 Vol. 1 Control Valve Sizing and Selection RHR, RHRSW, EESW, & D

DGSW Systems

DC-0213 Sizing of 130/260 V Batteries U

DC-0214 Short Circuit Calculation For DC System H

DC-0230 Vol. 1 Core Spray System Design Calculations G

DC-0559 Vol. 1 Volume of Reservoir - RHR Complex C

DC-0835 System Voltage Study (superseded) E

DC-0919 Undervoltage Relay Setpoints F

DC-2712 Vol. 1 Specifications of Motor Operated Valve Stroke Times X

DC-3141 Vol.1A Piping Stress Report 04/14/86

DC-4388 Protective Relay Settings for 13.2KV 4.16KV and 480V G

Auxiliary Equipment

DC-4943 DC Equipment Operability O

DC-5036 Vol. 1 Maximum Differential Pressure for MOVs E1150-F068A & 0

E1150-F068B

DC-5041 Maximum Expected Differential Pressure for Valves A

E2150F004A and E2150F004B

DC-5079 Vol. 1 LPCI and CS Pump Acceptance Criteria and LOCA Input D

Verification

DC-5084 Vol. 1 Seismic Review of Hoist Chains in Safety Related Buildings A

DC-5111 RHR and CS Pump Motor Overcurrent Relay Time Current A

Curve

DC-5264 Operability Evaluation of Electrical Equipment During System A

Transient due to LPCI & LPCS Initiation Following DBA-LOCA

with Degraded Grid (canceled)

DC-5351 DC Control Voltage Calculation for Division 1 G

DC-5405 Vol. 1 Third Party Review of Thrust Capacities of Wm. Powell Co. G

MOVs (Report No. 455597)

DC-5424 Vol. 1 Ventilation Air Quantity Required for RHR Complex Rooms C

DC-5489 Vol. 1 Ventilation Air Quality for Diesel Generator Room 11 A

DC-5719 Vol. 1 Minimum Required Target Thrust (MRTT) for Generic Letter 89- P

10 Gate, Globe, and Quarter-Turn Valves (torque)

DC-5894 Vol. 1 RHR Reservoir Replenishment Requirements A

DC-5945 Vol. 1 Design Basis System Parameters for AOVs E11F400A, A

E11F400B, E11F400C and E11F400D

2 Attachment

DC-5986 AOV Stem Force Requirement and Actuator Capability A

Calculation for E11F400A, E11400B, E11400C, E11400D

DC-6186 Electrical Loading Short Circuit Current and Running Voltages C

for 4.15kV 480 Volt and 120 Volt System using ETAP Power

Station (superseded)

DC-6249 Vol. 1 Service Water Systems Calibrated Hydraulic Model 0

DC-6258 Division I and Division II Switchgear Rooms Components ---

Operability Evaluation at 122°F (50°C)

DC-6309 Vol. 1 Design Basis of EDG Fuel Oil and Day Tank Level 0

Requirements and Setpoints

DC-6348 QL1 MOV Thermal Overload Heater Sizing O

DC-6397 Vol. 1 Calculation of Safety Related GL 89-10/96-05 and non-GL 89- 0

10/ 96-05 ACMOV Motor Terminal Voltages

DE-FR-041 Seismic and Weak Link Analysis of 3 Fisher Air Operated 1

Valves

DSN 455597 Reevaluation of Thrust Capacities for Powell Valves 09/21/94

DSN 729190 Survivable Thrust Capacities for Powell Valves 08/24/94

021-014-AWI DC MOV Thrust Margins 1

CORRECTIVE ACTION PROGRAM DOCUMENTS GENERATED AS A RESULT OF THE

INSPECTION

Number Description or Title Date

1020695 Potential Safety Concern: Loose Cabinet Screws Unable to be 01/27/10

Tightened

10-20700 NRC Concern: DFP Tach Generator Wiring 01/27/10

10-20716 4160V Breaker Not Properly Staged After Being Racked Out. 01/27/10

10-20720 NRC CDBI Inspection Identified Corrosion on RHRSW Pump 'A' 01/27/10

Pedestal

10-20723 2010 CDBI Item: Evaluate the Effect of P43R403C Reading Below 0 01/27/10

psid

10-20746 4160V Breaker Not Properly Staged After Being Racked Out 01/27/10

10-20747 2010 CDBI Div I/II Switchgear Room Cabinets Have Loose Knob 01/28/10

Screws

10-20748 CDBI Identified Canceled DC-5264 May Have To Be Reinstated 01/28/10

10-20764 2010 CDBI issue - Catch Hose Not Tracked In Accordance With 01/28/10

RWWI-02

10-20771 DC-4943 Vol I Issued with TSR-Config Instead of TSR-ABN 01/29/10

10-20776 2010 CDBI, Enhancements for 23.309, 260/130V DC ELECTRICAL 01/29/10

SYSTEM

10-20784 2010 CDBI - Missing Continuation Arrow on Dwg. M-2135-1 01/29/10

10-20787 2010 CDBI - Water under Diesel Fire Pump Battery Box 01/29/10

10-20793 2010 CDBI - Revise Hoist And Rigging Procedures 01/29/10

10-20819 CDBI Question on Fuel Clad Temp 01/29/10

3 Attachment

CORRECTIVE ACTION PROGRAM DOCUMENTS GENERATED AS A RESULT OF THE

INSPECTION

Number Description or Title Date

10-20823 CDBI 2010 Concern Revise DC-0919 to Include Correct LTC volts per 01/29/10

Tap

10-20861 2010 CDBI - Minor Changes Required to Operator Action 02/01/10

HERFACHRPLNT

10-20888 2010 CDBI Revise DC-6397 to Include Voltage Bounding Condition 02/02/10

Discussion

10-20894 2010 CDBI DC-0919 Requires Revision To Properly Verify Design 02/02/10

Inputs

10-20898 2010 CDBI, Operating Experience Review 02/02/10

10-20912 Reevaluate INPO SEN 271, Digital Feedwater Control System Power 02/02/10

Supply Failures Cause Automatic Reactor Scram with Complications,

for Impact to Fermi

10-20928 Evaluate Improved Trending Method for Key Calculation 02/02/10

Reviews/Design Calc Project

10-20981 2010 CDBI - Design Calculation Improvements for DC-4943 "DC 02/04/10

Equipment Operability

10-20982 2010 CDBI DC-0213 Improvement 02/04/10

10-20992 2010 CDBI RFI No -G027-4 (CDBI -0127) NRC Inspection Question 02/04/10

Regarding Temperature Requirement for DC-4943

10-21038 2010 CDBI Procedure Changes associated with 64 Xfmr Load Tap 02/05/10

Changer Manual Ops

10-21101 2010 CDBI ETAP Calculation Process Question 02/08/10

10-21122 2010 CDBI Inspection Item - Missed Opportunity during 2009 CDBI 02/08/10

Self-Assessment

10-21209 2010 CDBI - Discrepancy Found in Design Calculation DC-4943 "DC 02/11/10

Equipment Operability

10-21212 2010 CDBI - Review Manipulation Timing Analysis of Operator Action 02/10/10

HERFRMOVPLNT

10-21256 2010 CDBI Inspection Item - Error Found in RID-78612 02/11/10

10-21265 2010 CDBI DC-4943 Needs Revision 02/11/10

10-21283 2010 CDBI Questions On The Voltage Boundaries in DC-0919 Volume 02/11/10

1 Revision F

10-21285 2010 CDBI - Discrepancy Found During Document Review 02/11/10

10-21287 2010 CDBI - Installation of Washers on 2PA Found Reversed 02/11/10

10-21311 2010 CDBI DC-0214 Validation of Battery Resistance 02/12/10

10-21317 CDBI 2010 - Data Recorded in ICSS is Inconsistent with Loop 02/12/10

Instructions

10-21320 2010 CDBI - Design Calc Discrepancy 02/12/10

10-21332 Enhancement to Various IST-Related Surveillance Procedures 02/12/10

10-21564 Improper Output Torque Capability Used for MOV E4150F012 Margin 02/19/10

Determination

4 Attachment

CORRECTIVE ACTION PROGRAM DOCUMENTS GENERATED AS A RESULT OF THE

INSPECTION

Number Description or Title Date

10-21567 2010 CDBI Inspection - Design Specification 3071-128-EP 02/19/10

Discrepancy

10-21591 2010 CDBI - Found Minor Inconsistencies in DC-0214 02/22/10

10-21733 2010 CDBI DC-0919 LTC and Motor Starting 02/25/10

10-21749 2010 CDBI, Tornado Action Enhancement Associated with RHR 02/25/10

Complex HVAC

10-21757 CDBI 2010: Evaluate Previous Maintenance Rule Scoping of U4100 02/25/10

System

10-21761 Re-Evaluate the TBHVAC System Exclusion From the Maintenance 02/25/10

Rule scope

10-21777 2010 CDBI - Re-evaluate PM Classification and PM Work for TBHVAC 02/25/10

Fans

10-21791 2010 CDBI Voltage Drop Limits Not Used at Fermi to Assess 120 Kv 02/26/10

Offsite Power

10-21792 2010 CDBI - EDP 35621 Backfit Mod Issue 02/26/10

10-21920 2010 CDBI NRC Questioned Completeness of EFA-R14-10-004 03/03/10

10-21332 Enhancement to Various IST Related Procedures 02/12/10

10-22135 NRC CDBI Item -- Completeness and Accuracy of Information 03/12/10

Provided to the NRC

CORRECTIVE ACTION PROGRAM DOCUMENTS REVIEWED

Number Description or Title Date

98-13970 Ground Detected on 2PC3-14 05/15/98

99-11707 RHRSW Pump Discharge Pressure Gauges No Longer Used in 02/08/99

Surveillances

04-01842 Ground Detected on BOP Battery System 11/14/04

04-23862 CTG 11-2 through CTG 11-4 Auto-Started with NO Operator Action 08/25/04

05-10283 Procedure Enhancement for 23.412 01/13/05

05-26492 Design Calculation for RHR Complex Depressurization Is Not 11/17/05

Available

06-20446 AFCC 3 Relay OTH Failed During Testing; Event R295060100 01/30/06

06-20534 EDG 12 Trip On Overvoltage When Exciter Reset During Pmt Test 02/02/06

Sequence

06-20574 EDG 12 Output Breaker Fails to Open 02/03/06

06-20584 After AVR Replacement, Generator Voltage Could Not be Adjusted 02/05/06

Above ~3000V From Local Control Panel

07-10001 NQA Surveillance 06-0125, Fermi Vulnerability to Underground 01/05/07

Cable Failures

07-10001-01 Complete Effectiveness Review 10/13/08

5 Attachment

CORRECTIVE ACTION PROGRAM DOCUMENTS REVIEWED

Number Description or Title Date

07-20860 Information Notice 2007-05 Vertical Deep Draft Pump Shaft and 02/13/07

Coupling Failures

07-22460 Minimum CST Level for Pump Starting Does Not Protect Minimum 05/04/07

Submergence Requirements for CS and SBFW Pumps

07-22838 WANO/IMPO AFI CM.3-1 Calculation Errors 05/22/07

07-23630 UFSAR Anti-Vortex Methodology Non-Conservative 06/11/09

07-23998 CDBI RAI on Two RHR Safety Evaluations 09/23/09

07-27685 Inadequate EDP 11/29/07

08-20544 Test 4.16KV Unshielded RHR Div. 1 Anaconda Cables in RF13 01/29/08

08-22662 NRC Information Notice, IN-2008-02 Findings Identified During 04/22/08

Component Design Bases Inspections

08-25007 DC-5003 Enhancements Identified by PSE Independent Challenge 08/04/08

Board

08-27182 Declining Trend in RHRSW Pump A Hydraulic Performance 10/29/08

08-27295 RCIC Hydraulic Calculation Quality Review 11/03/08

08-28060 DC-0230 Vol. 1, Core Spray System Key Calculation Review 12/03/08

Results

08-28393 WGI Review of Calculation DC-2913, Vol. 1, Rev. N 12/15/08

09-20006 WGI Review Of Design Calculation DC-4943, Vol. I, Revision N 01/02/09

09-21353 Investigate Two NRC Issues Related to PI&R Cross Cutting Aspect 03/04/09

of Corrective Action

09-21669 Evaluate NRC IN 2009-02 03/18/09

09-22161 MOV Actuator Very Difficult To Get Into Manual Operation 04/02/09

09-24210 Trip of N. TBHVAC Exhaust Fan Root Cause Team Report 07/10/09

09-24325 Operations Training Review of OE28932 - Initial License Exam 06/04/09

High Failure Rate

09-24985 Improper Flow Controller Settings Renders Injection Systems 06/29/09

Inoperable and Surveillance Did Not Identify

09-26366 Key Calc Review of DC-5489 Vol. 1, Ventilation Air Quality for 08/19/09

EDGs

09-27471 Cell To Cell and Terminal Connection Resistance May Need To Be 09/25/09

Addressed In DC-0213

09-28748 Underground Cable Manholes Sump Pump Monitoring 11/11/09

09-28894 EDG 12 Output Breaker Fuse Clips, RM, Loose 11/16/09

09-29829 While Performing 24.307.15 for EDG 12 Observed Lowering Load 12/23/09

With No Operator Action

09-29830 EDG 12 Load Not Stable (Decreased Without Demand) During 12/24/09

Surveillance Test

09-29843 Failed PMT - EDG 12 Load Not Stable After Replacement of Digital 12/25/09

Reference Unit

09-29856 Catastrophic Failure of the North Turbine HVAC Exhaust Fan. 12/27/09

Repeat Occurrence

6 Attachment

CORRECTIVE ACTION PROGRAM DOCUMENTS REVIEWED

Number Description or Title Date

10-20147 Battery Operated Emergency Light Fails Discharge Test 01/07/10

10-20432 High Viscosity in EDG 13 Starting Air Compressor 01/19/10

10-20519 Cracked Battery Fill Caps 01/21/10

10-20539 Green Trickle Charge Light is Burned out 01/22/10

10-21657 Center TBHVAC Exhaust Fan Nose Cone Failure 02/23/10

DRAWINGS

Number Description or Title Revision

E21-3144-G33 Support Drawing B

6C721N-2273 RHR Complex Framing Plan EL 590-0 - Center South Area AC

6C721N-2274 RHR Complex Framing Plan EL 590-0 - Center North Area AF

6C721N-2277 RHR Complex Framing Plan EL 617-0 - Center South Area AA

6C721N-2296 RHR Complex Framing Area South Area 0

6I721-2231-01 S/D RCIC Turbine Gland Seal Condenser and Vacuum Pumps U

6I721-2231-03 S/D RCIC Steam Line Inboard Isolation Valve and Trip and Y

Throttle Valve

6I721-2231-04 S/D RCIC Steam Line Outboard Isolation Valve and W

Condenser Tank Pump Suction Valve

6I721-2231-05 S/D RCIC Pump Discharge Valves to Feed water Header X

6I721-2231-06 S/D RCIC suppression Pool Isolation Valves S

6I721-2231-07 S/D RCIC Valves E51F045 and F046 AA

6I721-2231-08 S/D RCIC Minimum Flow Bypass and Test Valves AA

6I721-2231-09 S/D RCIC Vacuum Breaker Isolation Valves F062 and F084 T

6I721-2231-10 S/D RCIC Turbine Exhaust and Vacuum Pump Discharge J

Valves F001 and F002

6I721-2231-11 S/D RCIC Steam Inlet Bypass Valve F095 C

6I721-2421-01 Schematic Diagram Reactor Building Closed Cooling Water L

Pump North P4200C001

6I721-2441-01 Schematic Diagram Emergency Equipment Cooling Water R

System Pump A P4400C001A

6I721-2571-01 One Line Synchronizing Diagram 4160V System Service and E

EDG Breakers

6I721-2571-2B One Line Diagram 4160V Bus and Line Potential Connecting E

Division 1

6I721-2572-13 Schematic Diagram 4160V ESS Bus 64C Pos C8 P

6I721-2572-14 Schematic Diagram 4160V ESS Bus 64C Pos C9 P

6I721-2572-15 Schematic Diagram 4160V ESS Bus 64C -Pos C6 S

6I721-2572-16 Schematic Diagram 4160V ESS Bus 64C Pos C11 H

6I721-2572-28 Schematic Diagram 4160V ESS Buses 64B & 64C - Load R

Shedding Strings

7 Attachment

DRAWINGS

Number Description or Title Revision

6I721-2572-29 Schematic Diagram 4160V ESS Buses 64E and 64F - Load M

Shedding Strings

6I721-2573-07 Schematic Diagram 480V ESS Bus 72C Pos 1B and 1C K

6I721-2573-08 Schematic Diagram 480V ESS Bus 72C Pos 2A and 2B J

6I721-2578-07 Relay and Metering Diagram 4160V ESS Bus 64C N

6I721-2578-19 Relay and Metering Diagram 480V ESS Bus 72EA EB B, C, L

and S

6I721-2581-02 Schematic Diagram - Cooling Circuit 4160V SS Transformer B

No. 64

6I721-2581-03 Schematic Diagram - Cooling Circuit 4160V SS Transformer D

No. 64

6I721-2581-04 Schematic Diagram - Cooling Circuit 4160V SS Transformer B

No. 64

6I721-2581-05 Schematic Diagram - Annunciator Circuit 4160V SS F

Transformer No. 64

6I721-2611-35 Schematic Diagram Main Control Room A/C Chiller Z

Compressor T4100B009 Div. 1

6I721-2641-01 Schematic Diagram Standby Gas Treatment Cont Panel 1 and J

2 480V Bus 72C Pos 4D and ESS Bus 72F Pos 3A

6I721N-2572-11 Schematic Diagram 4160V ESS Diesel Bus 12EB Pos EB3 X

6I721N-2572-12 Schematic Diagram 4160V ESS Diesel Bus 12EB Pos EB5 P

6I721N-2578-08 Relay and Metering Diagram Diesel Generator No. 12 Y

6M721-2015 Station and Control Air CB

6M721-2034 Core Spray System - CSS Reactor Building AN

6M721-2045 Reactor Core Isolation Cooling (RCIC) System Barometric AQ

Condenser

6M721-2083 Residual Heat Removal System Division 2 BL

6M721-2084 Residual Heat Removal System Division 1 BF

6M721-2135-01 Diagram Fire Protection System AY

6M721-2135-02 Diagram Fire Protection System AY

6M721-2656 Ventilation - Duct Layout 3rd FL N

6M721-3144-1 North Core Spray Pump Discharge to RPV Penetration V

6M721-3144-2 Hanger Piping Isometric North Core Spray Pump Discharge to L

RPV Penetration Reactor Building

6M721-5357 Emergency Equipment Cooling Water System Division II BJ

6M721-5728-1 TBCCW System 2nd and 3rd AH

6M721-5734 Emergency Diesel Generator System Functional Operating BB

Sketch

6M721N-2052 RHR Service Water System Division 1 RHR Complex AD

6M721N-2053 RHR Service Water System Division 2 RHR Complex AG

6SD721-2500-01 One Line Diagram Plant 4160V and 480V System Service Unit AK

2

6SD721-2500-02 One Line Diagram 13.8kV AB

8 Attachment

DRAWINGS

Number Description or Title Revision

6SD721-2500-03 One Line Diagram 4160V System Service Buses 64B 64C O

6SD721-2500-04 One Line Diagram 4160V System Service Buses No. 64E 65F P

65G - Reactor Bldg. Unit No. 2

6SD721-2500-05 One Line Diagram 4160V System Service Buses 64A 64D 64L U

6SD721-2500-08 One Line Diagram 4160V Diesel Gen. Buses No. 11EA 12EB O

13EC and 14ED Diesel Generator Building

6SD721-2500-09 Phasing Diagram Main Power System N

6SD721-2510-01 One Line Diagram 480v E.S.S. Bus No. 72B 72C 72E and 72F AF

6SD721-2510-05 One Line Diagram Diesel Gen Buses No. 72EA 72EB T2EC M

72ED

6SD721-2530-10 One Line Diagram 260/130V ESS Dual Battery 2PA AK

Distribution Division 1

MISCELLANEOUS

Number Description or Title Date or

Revision

Fermi Grid Adequacy Study 12/08 &

11/09

Black & Veatch Fermi 2 TBHVAC Fan Test Study 06/16/95

Project 27022

CI-7281 RF-13 Cable Monitoring Program Summary 10/23/09

DBD E11-XX Residual Heat Removal Service Water System B

DBD E21-00 Core Spray System C

DBD R30-00 Emergency Diesel Generator F

EMD 5285 CS 06 Piping Stress Analysis Report 06/14/78

E11-XX Residual Heat Removal Service Water System B

E21-00 Core Spray System C

GEK-5651A Load-Tap-Changing Equipment A

GEK-6143C Automatic Static Control for Load-Tap-Changer C

Equipment, Revision

HEOFMSOVOM1 Operator Fails To Keep MSIVs Open Following Scram 12/06/09

HEOFSBFWHESF1 Operator Fails To Start SBFW System 12/06/09

HERFACHRPLNT Operator Fails To Tie In Alternate Charger 12/06/09

HERFCACSHEOLB Failure To Manually Crosstie Div. 1 And 2 Control Air 12/06/09

HERFRMOVPLNT Failure To Manually Operate An RHR MOV Locally 12/06/09

HERFXMXTPLNT4H Operator Fails To Align 4160V Maint X-Tie 65T/64T 12/06/09

Within 4 Hours

MES60 Electrical Cable Monitoring Program 1

NQA Report 09-11 NQA Quarterly Report October - December 2009 01/27/10

NRC-07-0017 Detroit Edisons 90-Day Response to Generic Letter 05/04/07

2007-01

9 Attachment

MISCELLANEOUS

Number Description or Title Date or

Revision

ODE-15 Compensatory Monitoring Plan - TBHVAC Exhaust Fan 02/03/10

Differential Pressure

P.O. 1E87829 VertiLine Fire Pump Performance and Construction Data 09/21/10

Sheet

R1200S002 Maintenance Strategy 01/26/10

SE 95-0017 LCR 95-049-UFS 0

Spec. 3037-A Horizontal and Vertical A.C. Electric Motors 2300 Volts Addendum

and Above for Power Plant Duty Standard Specification C

Spec. 3067 460 Volt AC Motors Power Plant Service 03/68

TDDATA Nuclear Plant Operating Agreement 4

TE-E11-08-078 Removal of RHR Complex Pump Room Plugs under A

LCO 3.0.9

TE-U41-09-049 Evaluate Operation on the Center TBHVAC Exhaust Fan 0

with a Missing Hub Nose Cone

TM-09-0030 Nuclear Engineering Plant Indicators - November 2009 12/17/09

TMPE-09-0227 2009 Component Design Bases Inspection (CDBI) Self- 11/24/09

Assessment Final Report

VME8-11 General Electric Inductrol Type AIRT Voltage Regulators F

95-010 Maintenance Rule Program Position Paper 0

97-006 Maintenance Rule Program Position Paper 0

MODIFICATIONS

Number Description or Title Date or

Revision

ECR-35621-1 Revision of Calculation DC-0919 Vol I to Reflect Minimum And A

Maximum Error Evaluation and Motor Starting Transient Study

EDP 4921 Removal of Clutch Trippers from Fifteen Limitorque Valve A

Motor Operators

EDP 30405 Replacement of Division 1, 130/260 VDC batteries 12/10/99

ERE 32781 Replacement Pump Column Assemblies and Stuffing Boxes for B

Three RHR Complex Pumps

EDP-35621 DC-0919 Vol. 1 Under-Voltage Relay Setpoints 0

EDP-36014 DC-0919 Vol. 1 Under-Voltage Relay Setpoints 0

EDP-35607 Replace EDG Feeder Cables to 4.16kV Buses B

RID-78612 Replace Relay E21A-K16C in panel H11P626 0

TSR-35286 Incorporate Revisions into DC-4388, Vol. I and DC-0919 Vol I 0

TSR-35664 Clarify HPCI and RCIC Pump Suction and Discharge Design A

Temperature

TSR-35792 Revise HPCI/RCIC DBDs A

10 Attachment

MODIFICATIONS

Number Description or Title Date or

Revision

TSR-36184 Suggested Improvement for DC-0106 Vol. 1 RHRSWS 0

Minimum Flow Analysis

TSR-36383 Update of DC-5424 for CARD 09-22041 0

OPERABILITY EVALUATIONS

Number Description or Title Date

EFA-R14-10-002 Analysis to determine Electrical Equipment Functionality During A

a Transient due to LPCI and LPCS Initiation for a DBA-LOCA

with Degraded Grid (canceled)

EFA-R14-10-004 Analysis to Determine Electrical Equipment Functionality of A

4160 Volt 480 Volt Motors and SS64 LTC

EFA-R16-07-003 Analysis of the Fermi 5kV 3/C 500 MCM Copper Non-Shielded A

Cables to Perform Their Safety-Related Functions While

Operating In Continuously Wetted Environment.

EFA-R32-10-003 Engineering Functional Analysis To Determine Battery 0

Functionality Due To Incomplete Accounting Of Inter-Cell

Resistance In The DC-0213 Vol. 1 Calculation For Terminal

Voltage

PROCEDURES

Number Description or Title Revision

ARP 3D18 IPCS Monitored Inputs Abnormal 25

ARP 7D3 Div I RHR Reservoir Level Abnormal 15

ARP 7D4 Div II RHR Reservoir Level Abnormal 16

ARP 9D22 Div I Bus Voltage Low 15

ARP 10D43 Div II Bus Voltage Low 14

FIP-OP1-04 Equipment Labeling and Signs 5

MES02 Design Configuration Management 19

MES06 Preparation and Control of Design Basis Documents 6

MES15 Design Calculations 26

MGA03 Procedure Use and Adherence 20

MLS04 Fermi 2 Licensing/Safety Engineering Conduct Manual for 22

Operating Experience Program

MOP App B Plant Labeling Guidelines 1

MOP03 Operations Conduct Manual Chapter 3 - Policies and Practices 26

MOP05 Control of Equipment 30

MOP17 Plant Labeling 4

MMA08 Scaffolding 13

MMR03 Maintenance Rule Conduct Manual 1

11 Attachment

PROCEDURES

Number Description or Title Revision

MMR10 Maintenance Rule Conduct Manual Monitoring 7

MMR App C Maintenance Rule Scoping Summary Report 2

MQA11 Fermi 2 Quality Assurance Conduct Manual for Condition 29

Assessment Resolution Document

ODE-2 Operations Department Expectation Operations Conduct 22

ODE-12 Operations Department Expectations 18

ODMI-09-006A South TBHVAC Exhaust Fan 08/28/09

ODMI-10-001 TBHVAC System Reliability 02/11/10

PEP 47.306.01 Signature Analysis of Motor-Operated Valves 28

20.300.GRID Grid Disturbance 2

20.300.65E Att. 1, Bus 65E De-Energized Loads - MCR 4

23.106 Control Rod Drive Hydraulic System 95

23.127 Reactor Building Closed Cooling Water / Emergency Equipment 118

Cooling Water System

23.129 Station and Control Air System 92

23.138.01 Reactor Recirculation System 101

23.138.02 Operation of Recirculation System Motor Generator Set Fan Coil 17

Units

23.203 Core Spray System 42

23.208 RHR Complex Service Water Systems 97

23.307 Emergency Diesel Generator System 108

23.308 120V AC Instrument and Control Power System 61

23.309 260/130V DC Electrical System 56

23.310 48/24V DC Electrical System 25

23.316 RPS 120V AC and RPS MG Sets 51

23.320 Balance of Plant Auxiliary Electrical Distribution System 46

23.321 Engineered Safety Features Auxiliary Electrical Distribution 46 - 48

System

23.412 Turbine Building Heating, Ventilation, and Air Conditioning 50

System

23.413 Control Center HVAC 83

23.414 Steam Tunnel Cooling 17

23.420 RHR Complex Heating and Ventilation 33

23.426 Reactor Building Heating Ventilation Air Conditioning 54

23.707 Reactor Water Cleanup 126

23.708 Fuel Pool Cooling and Cleanup System 68

24.206.01 RCIC System Pump and Valve Operability Test 69

35.LIM.003 Limitorque SMB-0 Through SMB-4 and 4T Operator - 35

Maintenance

35.301.001 4160V Switchgear 34

35.304.006 ITE Circuit Breaker Types 5HK250 and 5HK350 General 22

Maintenance and Inspections

12 Attachment

PROCEDURES

Number Description or Title Revision

35.304.010 Refurbishing 5HK Air Circuit Breakers 13

35.306.001 480 Volt Switchgear Breaker and Relay Control Testing 37

35.306.005 MCC Bus and Compartment General Inspection and 30

Maintenance

35.306.006 Motor Operated Valve Setup Verification 35

35.306.012 Stroke Trace Recording of Motor Operated Valves 8

35.306.020 Motor Operated Valve Mini Periodic Inspection 4

35.318.014 Medium Voltage Switchgear Breaker and Relay Control 35

42.302.07 Cal and Functional Test of Div 1 4160 V Bus 64B Undervoltage 33

Relays

42.302.08 Cal and Functional Test of Div 1 4160 V Bus 64C Undervoltage 34

Relays

42.302.09 Cal and Functional Test of Div 2 4160 V Bus 65E Undervoltage 32

Relays

42.302.10 Cal and Functional Test of Div 2 4160 V Bus 65F Undervoltage 32

Relays

42.309.02 Division 1/2 Quarterly 130/260 VDC Battery Check 36

47.000.20 Diagnostic Testing of Medium Voltage Cables 2

SURVEILLANCES (COMPLETED)

Number Description or Title Date or

Revision

42.309.02 Division 1/2 Quarterly 130/260 VDC Battery Check 12/28/09

42.309.05 Division 1 (5 year) 130/260 VDC Battery Check 04/06/06

42.309.03 Division 1 18 month 130/260 VDC Battery Check 04/07/09

24.203.02 Division 1 CSS Pump and Valve Operability, and Automatic 48

Actuation

24.203.03 Division 2 CSS Pump and Valve Operability, and Automatic 50

Actuation

24.205.05 Division 1 RHRSW Pump and Valve Operability Test 47

24.205.06 Division 2 RHRSW Pump and Valve Operability Test 46

WORK ORDERS/WORK REQUESTS

Number Description or Title Date or

Revision

Double Test Report 04/04/06

A839050100 Perform Mini Periodic MOV Inspection and MPM Stroke Test 03/13/05

E581961116 Inspect Lube and Test Motor Op Valve, Test, Associated 02/02/00

Feeder Position

13 Attachment

WORK ORDERS/WORK REQUESTS

Number Description or Title Date or

Revision

WO R05070100 Inspect, Clean, Megger Bus 64C and Calibrate Current Indicator 04/06/09

WO 26926949 Perform Mini Periodic MOV Inspection And VPM Stroke Test 02/12/08

WO 27035002 Perform 24.203.02 Sec-5.1 CSS Pump and Valve Operability 12/23/08

Test

WO 27067666 Perform 24.203.02 Sec-5.1 CSS Pump and Valve Operability 04/11/09

Test

WO 27303748 Perform 24.203.02 Sec-5.1 Division 1 CSS Pump and Valve 06/23/09

Operability Test

WR E200070100 Perform MOV Thrust (Viper) Testing Per GL 96-05 Program 09/09/07

WRR371940708 Inspect 72C-2A for Cleanliness Damage and Megger Bus 11/24/04

WRR517070100 Inspect and Test 480V Unit Substation 11/19/04

WRZ325100100 PM Inspect, Clean, Test and Functionally Check SS Xfmr No. 04/12/06

64 and its Components

14 Attachment

LIST OF ACRONYMS USED

AC Alternating Current

ACE Apparent Cause Evaluation

ADAMS Agencywide Document Access Management System

CAP Corrective Action Program

CARD Condition Assessment and Resolution Document

CDBI Component Design Bases Inspection

CFR Code of Federal Regulations

DC Direct Current

ECR Engineering Change Request

EDG Emergency Diesel Generator

EECW Emergency Equipment Cooling Water

EFA Engineering Functional Analysis

HPCI High Pressure Cooling Injection

IN Information Notice

IP Inspection Procedure

IST Inservice Testing

kV Kilovolt

LCO Limiting Conditions of Operations

LOCA Loss of Coolant Accident

LOOP Loss of Off-site Power

LTC Load Tap Changer

NCV Non-Cited Violation

NPP Nuclear Power Plant NRC

ODE Operations Department Expectation

ODMI Operational Decision Making Issue

PM Preventative Maintenance

PMT Post Maintenance Test

RHR Residual Heat Removal

RCIC Reactor Core Isolation Cooling

SBO Station Blackout

SDP Significance Determination Process

SS System Service

SSC Systems, Structures, and Components

TBHVAC Turbine Building Heating Ventilation and Air Conditioning

TS Technical Specification

TSR Technical Service Request

TSO Transmission System Operator

UFSAR Updated Final Safety Analysis Report

URI Unresolved Item

Vac Volts Alternating Current

Vdc Volts Direct Current

WO Work Order

WR Work Request 15 Attachment

Bob,

Following the referenced evaluation of EFA-R14-10-004 Revision A by the CDBI team, I am

forwarding a question and a comment. Please advise CDBI Lead, Zelig Falevits, and the

Residents of your reply.

Thx.

Bob Jones

Resident Inspector

APPENDIX

Ref: Evaluation of EFA-R14-10-004 Revision A, George Skinner

QUESTION

Section 4.1 of Revision 0 of the EFA addressed the implementation of administrative controls to

ensure that the relays remain within the values evaluated in the EFA, in lieu of the criteria in the

current surveillance procedures. Inexplicitly, this provision has been removed from Revision A

of the EFA. Similarly, neither Revision 0 nor Revision A lists the requirement to implement

alternate criteria as a compensatory action in Section 5.0 of the EFA. In order to establish

reasonable assurance of continued operability of the offsite power sources, the EFA needs to

address what measures are being implemented to assure that the relays will not drift above their

new limits. This affects the conclusion of the finding on Offsite Power Calculations.

COMMENT

Attachment 7 compared 460V motor protective device trip times with motor start times. The

attachment referred to the ETAP static motor starting analysis for motor start durations but

these values were artificial since they were manually entered based on assumed values

described in Section 3.1.1, not calculated based on a dynamic analysis. The dynamic ETAP

case in Attachment 17 could not be used to determine start durations because it only modeled

the 4kV RHR and Core Spray pumps starting and did not model 460V motors starting. Start

durations for 460V motors were affected by the starting durations of the RHR and CS motors,

but these may also be non-conservative, as described in the next item. The margins for

spurious trip avoidance listed in Attachment 8 were small for some motors. (Motor T4100C041

showed negative margin but this was determined to be a typographical error.) Consequently, it

was not clear that 460V motor would accelerate without activating their protective devices. This

item affects the conclusion of the finding on Motor Starting Voltage Calculations. Affected

motors are listed in Attachment 8 of the EFA.

16 Attachment

J. Davis -2-

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter, its enclosure, and

your response (if any), will be available electronically for public inspection in the NRC Public Document

Room or from the Publicly Available Records System (PARS) component of NRC's Agencywide

Documents Access and Management System (ADAMS), accessible from the NRC Web site at

http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

V. Patricia Lougheed, Acting Chief

Engineering Branch 2

Division of Reactor Safety

Docket No. 50-341

License No. NPF-43

Enclosure: Inspection Report 05000341/2010006

w/Attachment: Supplemental Information

cc w/encl: Distribution via ListServ

DISTRIBUTION:

Susan Bagley

RidsNrrDorlLpl3-1 Resource

RidsNrrPMFermi2 Resource

RidsNrrDirsIrib Resource

Cynthia Pederson

Steven Orth

Jared Heck

Allan Barker

Carole Ariano

Linda Linn

DRPIII

DRSIII

Patricia Buckley

Tammy Tomczak

ROPreports Resource

DOCUMENT NAME: G:\DRS\Work in Progress\FERMI 2010-006 CDBI ZXF.doc

Publicly Available Non-Publicly Available Sensitive Non-Sensitive

To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy

OFFICE RIII RIII RIII

NAME ZFalevits (via VPLougheed

phone)

DATE 04/27/10 04/27/10

OFFICIAL RECORD COPY